Federal Contracting, Inc. v. United States , 128 Fed. Cl. 788 ( 2016 )


Menu:
  •        In the United States Court of Federal Claims
    No. 16-215C
    Filed: September 28, 2016
    )    Keywords: Contract Disputes Act;
    FEDERAL CONTRACTING, INC.,                  )    Breach of Contract; Performance
    d/b/a BRYAN CONSTRUCTION, INC.,             )    Bond; Sum Certain; Performance
    )    Evaluation; Termination for Cause;
    Plaintiff,            )    Termination for Convenience.
    )
    v.                                          )
    )
    THE UNITED STATES OF AMERICA,               )
    )
    Defendant.            )
    )
    )
    J. Taylor Benson, Benson Law Office, Colorado Springs, CO, for Plaintiff.
    Robert C. Bigler, Trial Attorney, Commercial Litigation Branch, Civil Division, with
    whom were Claudia Burke, Assistant Director, Robert E. Kirschman, Jr., Director, and
    Benjamin C. Mizer, Principal Deputy Assistant Attorney General, U.S. Department of
    Justice, Washington, DC, for Defendant. Pietro Mistretta, Attorney, Office of Counsel,
    U.S. Army Corps of Engineers, Winchester, VA, Of Counsel.
    OPINION AND ORDER
    KAPLAN, Judge.
    Currently before the Court in this contract case are the government’s motion to
    partially dismiss the complaint of Plaintiff Federal Contracting, Inc. d/b/a Bryan
    Construction, Inc. (FCI) and FCI’s cross-motion for a default judgment as to Count III of
    its complaint. The government’s motion seeks dismissal of Counts I, II, and IV of the
    complaint pursuant to Rule 12(b)(1) of the Rules of the Court of Federal Claims (RCFC).
    FCI seeks a default judgment against the government as to Count III of its complaint.
    As discussed below, the Court agrees with the government that it lacks
    jurisdiction over Counts I and II of FCI’s complaint seeking monetary damages for
    breach of contract, because FCI failed to submit valid claims alleging to the contracting
    officer (CO) under the Contract Disputes Act (CDA), 
    41 U.S.C. §§ 7101
    –09. However,
    the Court rejects the government’s jurisdictional objections to Count IV of FCI’s
    complaint. In that Count, FCI challenges and seeks an order directing the government to
    withdraw an unsatisfactory evaluation of FCI’s performance on the contract. Contrary to
    the government’s argument, the Court concludes that FCI did submit that claim to the CO
    as required by the CDA and received a final decision from the CO as to that claim.
    Accordingly, the government’s motion to dismiss is GRANTED-IN-PART and
    DENIED-IN-PART. In addition, for the reasons discussed below, FCI’s cross-motion
    for default judgment is DENIED.
    BACKGROUND1
    I.      The Contract
    On January 23, 2015, the United States Army Corps of Engineers (USACE)
    awarded FCI a contract for the construction of a medical warehouse on the premises of
    Al Udeid Air Base, Qatar (Al Udeid). Compl. ¶ 5, ECF No. 1. The contract was a firm
    fixed-price contract in the amount of $4,899,425. 
    Id.
     FCI was to complete the building by
    January 28, 2016. See 
    id. ¶ 6
    .
    On March 19, 2015, USACE sent FCI a Letter of Concern regarding the
    timeliness of several mandatory pre-construction submissions.2 Compl. ¶ 13; Def.’s Mot.
    to Dismiss (Def.’s Mot) App. at A1, ECF No. 10-1. The agency expressed its concern
    that FCI’s “fail[ure] to provide [the] required submittals . . . put[] the project at risk.” 
    Id.
    On May 5, 2015, USACE sent FCI a Notice of Intent to Issue [an] Interim Unsatisfactory
    Performance Appraisal, stating that “the contract continues to fall behind schedule” and
    that there were “no indication[s] that [FCI] is making sufficient progress in recovering
    lost time.” 
    Id.
     at A5; see also Compl. ¶ 16.
    On April 28, 2015, FCI invoiced USACE for a progress payment in the amount of
    $33,997.00. See Compl. ¶ 53. The progress payment was to reimburse FCI for the cost of
    performance and payment bonds it obtained in February 2015. 
    Id.
     at 52–53. FCI then
    responded to USACE’s Letter of Concern on May 8, 2015, arguing that USACE had not
    “accurately represent[ed] [its] performance on the project” because it “identifie[d] old
    issues that have since been overcome.” Def.’s Mot. App. at A11. FCI also contended that
    the notice “appeare[d] to be written in a vindictive manner.” 
    Id.
    On May 14, 2015, USACE issued an Interim Unsatisfactory Performance
    Appraisal identifying six major unresolved performance issues. 
    Id.
     at A12–13; see also
    Compl. ¶¶ 16–17. Two weeks later, on May 28, 2015, the agency followed up with a
    Cure Notice, which stated that USACE considered FCI’s “failure to progress
    1
    The facts in this section are based on the documents attached to the parties’ briefs as
    well as the allegations in Plaintiff’s complaint, which the Court assumes to be true for
    purposes of deciding the motion to dismiss.
    2
    USACE considered Al Udeid a “special work environment” presenting certain logistical
    difficulties, including issues related to obtaining base access badges for the contractor’s
    personnel and construction permits from the Qatari government. See Def.’s Mot. App. at
    A9.
    2
    satisfactorily as a refusal to prosecute the work with the diligence that will ensure its
    completion within the time specified in the contract.” Def.’s Mot. App. at A16; see also
    Compl. ¶ 20. The agency noted that FCI had not “sufficiently demonstrated its plan to
    perform 20% of the construction, as required by the contract” or “completed any
    mobilization or any physical work at the site.” Def.’s Mot. App. at A17. As a result,
    USACE warned FCI that it “m[ight] terminate this contract for default” if FCI failed to
    cure the deficiencies within ten days. 
    Id.
     at A16.
    FCI responded to the Interim Unsatisfactory Performance Appraisal and the Cure
    Notice on June 8, 2015. 
    Id.
     at A19–38; see also Compl. ¶ 23. It claimed that “the basis for
    the Cure Notice [was] factually incorrect,” and argued that it was attempting in good faith
    to perform and that the performance delays were justified by circumstances beyond its
    control. See Def.’s Mot. App. at A20–22. It also contended that it still had adequate time
    to meet the contract’s completion date. 
    Id.
     at A30, A33, A38. FCI also noted that it
    “strongly disagree[d]” with the interim performance evaluation and “formally
    request[ed]” its withdrawal. 
    Id.
     at A35, A38. On June 29, 2015, FCI again requested that
    the interim unsatisfactory evaluation be withdrawn, arguing that it contained inaccuracies
    and inconsistencies and that USACE did not adhere to the proper evaluation methodology
    or best practices guidelines. 
    Id.
     at A49–50.
    On July 6, 2015, USACE issued a Show Cause Notice stating that it was
    considering terminating FCI’s contract for default. 
    Id.
     at A51; see also Compl. ¶ 29. The
    agency gave FCI ten days to present mitigating circumstances demonstrating that its
    failure to perform arose out of causes beyond its control and without FCI’s fault or
    negligence. Def’s Mot. App. at A51.
    The show cause notice also stated that FCI’s request for withdrawal of the interim
    unsatisfactory CPARS evaluation was denied. 
    Id. at 55
    . On July 13, 2015, the agency
    finalized FCI’s unsatisfactory performance evaluation. See Pl.’s Opp’n to Def.’s Mot. to
    Partially Dismiss Compl. (Pl.’s Opp’n) App. at A248–52, ECF No. 11-2. The final
    performance evaluation included comments from FCI, in which it expressed its
    disagreement with the evaluation and “request[ed] that it be reevaluated.” 
    Id.
     at A250–52.
    FCI responded to the Show Cause Notice on July 23, stating its belief that
    USACE “ha[d] no intention of cooperating with [FCI],” and that USACE had breached
    the contract by failing in its “duty not to hinder, delay, or increase the cost of
    performance via its unreasonable exercise of discretion.” Def.’s Mot. App. at A58–59.
    FCI also requested that the contract be terminated for convenience. 
    Id.
     at A59.
    On July 30, 2015, USACE notified FCI that it had not processed FCI’s invoices
    requesting reimbursement for its payment of bond premiums because of certain
    irregularities in FCI’s submission. Compl. ¶ 54. According to FCI, by letter of July 31,
    2015, it advised USACE that it had remedied the irregularities; nonetheless, USACE did
    not pay the invoices. 
    Id. at ¶ 56
    .
    3
    II.    USACE’s Termination of the Contract and FCI’s Communication with the
    CO Following the Termination
    On August 3, 2015, USACE issued a Notice of Termination for Default, stating
    that FCI’s “response to [the] Show Cause Notice did not provide any information which
    demonstrated that [it] could meet the required completion date of the contract,” and that it
    “did not show that the default otherwise was beyond [FCI’s] control and without [its]
    fault or negligence.” Def.’s Mot. App. at A76; see also Compl. ¶ 32. The Notice of
    Termination also outlined twenty-six acts or omissions constituting the default, and stated
    that the notice “constitute[d] [USACE’s] final decision that [FCI] is in default.” Def.’s
    Mot. App. at A92.
    On August 12, 2015, FCI responded to the Notice of Termination. 
    Id.
     at A94. It
    contended that the Notice of Termination was “void and defective” because (among other
    things) USACE had “committed a material Anticipatory Breach by neglecting to
    reimburse [FCI] for its Bond Premiums for Bonds furnished on the Contract.” 
    Id.
     Further,
    it argued that USACE was “wrongfully holding Bonds for which the required
    consideration has not been paid” and requested “that the Government return the bonds.”
    
    Id.
     at A96.
    On September 28, 2015, FCI sent the CO another letter, in which it purportedly
    “identif[ied] the grounds for [the] improper Default Termination” and “formally
    request[ed] concurrent Inspector General (IG) and Criminal Investigation Division (CID)
    investigations into USACE’s contract management of [the] contract.” 
    Id.
     at A98. FCI
    claimed that USACE had breached its duty of good faith and fair dealing by intentionally
    withholding an approved dig permit for the project. 
    Id.
     at A98–100. FCI also stated that
    default termination is a “drastic sanction” which should only be imposed for “good
    grounds and on solid evidence,” and alleged that USACE failed to cooperate with FCI
    and did not attempt to engage in routine contract administration activities to resolve
    factual disputes. 
    Id.
     at A102.
    USACE responded to this letter on October 2, 2015, stating that the government
    would “look into the allegations [raised] regarding the dig permit” but that it
    “unequivocally disagree[d] with [the] allegation that it acted in bad faith.” Pl.’s Opp’n
    App. at A221. The agency reiterated that its decision to terminate the contract for default
    remained in effect. 
    Id.
     On October 15, 2015, USACE sent a follow-up letter stating that it
    had investigated the dig permit allegation and determined that FCI’s allegations were
    “unsubstantiated.” 
    Id.
     at A222.
    FCI replied by letter on December 7, 2015, stating that it was dissatisfied with
    USACE’s “lack of transparency . . . and cooperation” with regards to the internal
    investigation into the dig permit. Def.’s Mot. App. at A104. FCI also claimed that the
    agency’s failure to provide it with the dig permit before August 20, 2015 led to a
    “Government-caused delay,” and that the Termination for Default was improper in light
    of that delay. 
    Id.
     at A104–05. FCI then “formally request[ed] that USACE immediately
    convert this Termination for Default into a Termination for the Convenience of the
    Government” and indicated that it was ready “to pursue a full and appropriate resolution
    4
    of this matter via any administrative and/or legal recourse that may be necessary.” 
    Id.
     at
    A109.
    III.   This Action
    FCI filed a four-count complaint in this Court on February 12, 2016. In it, FCI
    alleged: (1) that USACE breached the contract by violating the duty of good faith and fair
    dealing; (2) that USACE breached the contract by failing to reimburse FCI for the bond
    premium payments; (3) that USACE wrongfully terminated FCI for default; and (4) that
    the interim unsatisfactory performance evaluation was “unfair, inaccurate, erroneous,
    biased, and an abuse of discretion.” Compl. ¶¶ 57–60. As relief, FCI requested that the
    Court: (1) enter judgment in its favor as to its breach of contract claims; (2) grant
    damages in the amount of $4,899,425; (3) declare the unsatisfactory performance
    evaluation null and void; (4) direct USACE to “take proper and just actions to remedy the
    unlawful Unsatisfactory Performance Evaluation”; (5) declare that the Government’s
    termination of the Contract for default was wrongful and convert it to a termination for
    convenience; and (6) award reasonable attorney’s fees, costs, and expenses. 
    Id. at 8
    .
    On May 27, 2016, the government moved to dismiss the first, second, and fourth
    counts of FCI’s complaint, arguing that those counts are subject to the CDA and that FCI
    failed to submit any valid claims or obtain final decisions from the CO before filing its
    complaint. Def.’s Mot. at 13–14. The government also asked the Court to stay the third
    cause of action (regarding the allegedly wrongful termination for default) until FCI files
    an amended complaint following a CO’s determination as to the breach of contract and
    improper evaluation claims. 
    Id. at 14
    .
    FCI responded on June 13, 2016. ECF No. 11. Along with its response, FCI
    moved for a default judgment as to the third count of its complaint. 
    Id.
     at 25–27. The
    government filed its reply on June 30, 2016, ECF No. 12, and oral argument was held on
    September 27, 2016. The motions are now ripe for decision.
    DISCUSSION
    I.     Standards for Motions to Dismiss Under RCFC 12(b)(1)
    Whether this Court has subject-matter jurisdiction is a threshold matter, and, if no
    jurisdiction exists, the Court must order dismissal without proceeding further. See PODS,
    Inc. v. Porta Stor, Inc., 
    484 F.3d 1359
    , 1365 (Fed. Cir. 2007) (citing Steel Co. v. Citizens
    for a Better Env’t, 
    523 U.S. 83
    , 94–95 (1998)). In deciding a motion to dismiss for lack
    of subject matter jurisdiction, the court accepts as true all undisputed facts in the
    plaintiff’s complaint and draws all reasonable inferences in favor of the plaintiff. Trusted
    Integration, Inc. v. United States, 
    659 F.3d 1159
    , 1163 (Fed. Cir. 2011). If subject matter
    jurisdiction is challenged, however, the plaintiff cannot rely merely on allegations in the
    complaint, but must instead bring forth relevant, competent proof to establish jurisdiction.
    Reynolds v. Army & Air Force Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988). The
    party invoking a court’s jurisdiction bears the burden of establishing it, and must
    5
    ultimately do so by a preponderance of the evidence. Id.; see also Rocovich v. United
    States, 
    933 F.2d 991
    , 993 (Fed. Cir. 1991).
    II.    The Court’s Jurisdiction Over CDA Claims
    A.      Tucker Act
    Pursuant to the Tucker Act, the United States Court of Federal Claims may
    “render judgment upon any claim against the United States founded either upon the
    Constitution, or any Act of Congress or any regulation of an executive department, or
    upon any express or implied contract with the United States, or for liquidated or
    unliquidated damages in cases not sounding in tort.” 
    28 U.S.C. § 1491
    (a) (2012).
    Subsection (a)(2) of section 1491 further grants the Court of Federal Claims “jurisdiction
    to render judgment upon any claim by or against, or dispute with, a contractor arising
    under section 7104(b)(1) of title 41”—that is, the CDA—“including a dispute concerning
    termination of a contract, rights in tangible or intangible property, compliance with cost
    accounting standards, and other nonmonetary disputes on which a decision of the
    contracting officer has been issued under section 6 of that Act.” 
    Id.
     § 1491(a)(2).
    B.      The Contract Disputes Act
    The CDA covers all claims based upon “any express or implied contract . . . made
    by an executive agency for—(1) the procurement of property, other than real property in
    being; (2) the procurement of services; (3) the procurement of construction, alteration,
    repair, or maintenance of real property; or (4) the disposal of personal property.” 
    41 U.S.C. § 7102
    (a) (2012). Under the CDA, “procurement” means “the acquisition by
    purchase, lease or barter, of property or services for the direct benefit or use of the
    Federal Government.” New Era Constr. v. United States, 
    890 F.2d 1152
    , 1157 (Fed. Cir.
    1989) (quotation and emphasis omitted).
    The CDA sets forth its own jurisdictional requirements. See M. Maropakis
    Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1327–28 (Fed. Cir. 2010). In particular,
    it states that a contractor may bring an action de novo in federal court “within 12 months
    from the date of receipt of a contracting officer’s decision.” 
    41 U.S.C. § 7104
    (b)(3), (4).
    Thus, the Federal Circuit has held that for the Court of Federal Claims to possess
    jurisdiction, the contractor must have first submitted a valid claim to the contracting
    officer and received the contracting officer’s final decision on that claim. M. Maropakis
    Carpentry, 
    609 F.3d at
    1327–28; see also Dalton v. Sherwood Van Lines, Inc., 
    50 F.3d 1014
    , 1017 (Fed. Cir. 1995) (“When the [CDA] applies, it provides the exclusive
    mechanism for dispute resolution; [it] was not designed to serve as an alternative
    administrative remedy, available at the contractor’s option.”).
    The definition of “claim” for purposes of the CDA derives from the FAR, which
    implements the CDA. See M. Maropakis Carpentry, 
    609 F.3d at
    1327–28. FAR 2.101
    provides, in pertinent part, that “claim” means “a written demand or written assertion by
    one of the contracting parties seeking, as a matter of right, the payment of money in a
    sum certain, the adjustment or interpretation of contract terms, or other relief arising
    6
    under or relating to the contract.” Id.; see also FAR 52.233-1 (setting forth, in a standard
    contract clause, the same definition of “claim”).
    In interpreting the CDA, the Federal Circuit has held that a valid claim for
    payment consists of three components: “(1) a written demand, (2) seeking, as a matter of
    right, (3) the payment of money in a sum certain.” Northrop Grumman Computing Sys.,
    Inc. v. United States, 
    709 F.3d 1107
    , 1112 (Fed. Cir. 2013) (citing Reflectone, Inc. v.
    Dalton, 
    60 F.3d 1572
    , 1575–76 (Fed. Cir. 1995)). The Federal Circuit has further
    explained that “a valid claim under the CDA must contain ‘a clear and unequivocal
    statement that gives the contracting officer adequate notice of the basis and amount of the
    claim,’” but that it “need not take any particular form or use any particular wording.” 
    Id.
    (quoting Contract Cleaning Maint., Inc. v. United States, 
    811 F.2d 586
    , 592 (Fed. Cir.
    1987)). Instead, “[a]ll that is required is that the contractor submit in writing to the
    contracting officer a clear and unequivocal statement that gives the contracting officer
    adequate notice of the basis and amount of the claim.” 
    Id.
     (quoting Contract Cleaning
    Maint., Inc., 
    811 F.2d at 592
    ).
    For claims seeking more than $100,000, FAR 2.101 additionally incorporates
    within the definition of “claim” the CDA’s certification requirement. 
    41 U.S.C. § 7103
    (b)(1). That requirement provides as follows:
    For claims of more than $100,000 made by a contractor, the contractor shall
    certify that--
    (A) the claim is made in good faith;
    (B) the supporting data are accurate and complete to the best of the
    contractor’s knowledge and belief;
    (C) the amount requested accurately reflects the contract adjustment for
    which the contractor believes the Federal Government is liable; and
    (D) the certifier is authorized to certify the claim on behalf of the
    contractor.
    Id.; see also FAR 33.207(c) (providing specific certification language, which includes the
    language of § 7103(b)(1) nearly verbatim).
    In addition, “[b]esides meeting the FAR definition of a claim, the CDA also
    requires that all claims be submitted to the contracting officer for a decision.” James M.
    Ellett Constr. Co. v. United States, 
    93 F.3d 1537
    , 1543 (Fed. Cir. 1996); see also M.
    Maropakis Carpentry, 
    609 F.3d at
    1327–38. The contractor is not required to make a
    single, “explicit request for a final decision.” James M. Ellett Constr., 
    93 F.3d at 1543
    .
    Rather, “as long as what the contractor desires by its submissions is a final decision, that
    prong of the CDA claim test is met.” 
    Id.
     (quoting Transamerica Ins. Corp., Inc. ex rel.
    Stroup Sheet Metal Works v. United States, 
    973 F.2d 1572
    , 1576 (Fed. Cir. 1992),
    overruled on other grounds by Reflectone, Inc., 
    60 F.3d at
    1582–83.
    7
    II.    Whether the Court has Jurisdiction Over Counts I, II, and IV of FCI’s
    Complaint
    A.      Counts I and II
    In Count I of its complaint, FCI alleges that USACE breached the contract by
    violating the duty of good faith and fair dealing. Compl. ¶ 57. According to the
    allegations in Count I, “no meeting of the minds occurred as USACE held no
    preconstruction meeting, [s]ubmittals were not approved, and no cooperation took place.”
    
    Id.
     In Count II, FCI claims that USACE breached the contract by “fail[ing] to reimburse
    [it] for surety bond payments in the amount of $33,997.00, as required by FAR
    52.232-5.” Compl. ¶ 58. FCI further alleges in Count II that the government’s failure to
    provide reimbursement and its termination of the contract for default “while continuing to
    assert payment and/or performance on the contract from the bonding company. . . has
    unfairly impacted [FCI’s] bonding capacity.” 
    Id.
     As a remedy for each of these two
    breaches, FCI requested “costs to be determined at a later date, pursuant to the contract
    amount of $4,899,425.00.” Id. at ¶¶ 57, 58.
    FCI does not contest that the CDA applies to these claims. See Pl.’s Opp’n at 9.
    And it also does not allege in its complaint that it submitted certified claims to the CO
    concerning the allegations of breach of contract set forth in Counts I and II. Nonetheless,
    it argues in its response to the government’s motion to dismiss that it effectively
    submitted its breach of contract claims to the CO in its responses to USACE’s May 28,
    2015 Cure Notice and its July 6, 2015 Show Cause Notice. See id. at 10. FCI further
    argues that USACE’s Notice of Termination for Default constituted the CO’s final
    decision as to those claims. See id.
    FCI’s arguments lack merit. FCI’s responses to the Cure Notice and Show Cause
    Notice did not constitute valid claims for payment under the CDA for alleged breaches of
    contract because, among other reasons, FCI never requested payment for such claims in a
    sum certain, which is a requirement for a valid claim seeking monetary damages. See
    Northrop Grumman Computing Sys., 709 F.3d at 1112; Alliant Techsystems, Inc. v.
    United States, 
    178 F.3d 1260
    , 1266–67 (Fed. Cir. 1999). Indeed, FCI concedes that it did
    not request payment in a sum certain with respect to either Count I or Count II of its
    complaint, opining that it would be “premature to certify a sum certain at this point in
    time” because the Termination for Default might be converted to a Termination for
    Convenience. See Pl.’s Opp’n at 18. And because FCI never requested a sum certain, it
    also necessarily failed to comply with the CDA’s certification requirement for claims
    over $100,000, which requires contractors to certify that “the amount requested
    accurately reflects the contract adjustment for which the contractor believes the Federal
    Government is liable.” See 
    41 U.S.C. § 7103
    (b)(1).
    Nor did FCI present a valid claim to the contracting officer in its August 12, 2015
    letter responding to the Notice of Termination. In that letter it stated, among other things,
    that USACE had committed a “material Anticipatory Breach by neglecting to reimburse
    FCI for its Bond Premiums for Bonds furnished on the Contract.” Def.’s Mot. App. at
    A94. It also observed that “USACE is wrongfully holding Bonds for which consideration
    8
    has not been paid” and requested “that the Government return the Bonds.” 
    Id.
     at A96.
    The letter, however, does not request payment of a sum certain as damages for any
    alleged breach of contract. Indeed, the letter had another independent purpose: to seek
    relief from the default termination order. See 
    id.
     (stating that the purpose of FCI’s August
    12, 2015 letter was to “notify[] the Government that its Anticipatory Breach and failure
    to notify the Surety Bonding Companies are asserted as strong defenses to the
    Termination for Default action”). This correspondence, accordingly, does not constitute a
    valid claim for damages under the CDA. See Armour of Am. v. United States, 
    69 Fed. Cl. 587
    , 592 (2006) (no valid claim for convenience damages under CDA where “letter from
    Plaintiff to the [CO] merely requests reconsideration of the default termination,” where
    “[t]here is no evidence of record before the Court to show that Plaintiff requested
    monetary damages of a sum certain,” and where “there was no final decision by the [CO]
    on a claim for convenience termination monetary damages”).
    Similarly, as described above, FCI’s letters of September 28, 2015, and December
    7, 2015, did not constitute valid claims under the CDA. In the former letter, FCI again
    complained about the termination for default and also requested inspector general and
    criminal investigations of USACE’s management of the contract. See Def.’s Mot. App. at
    A98. The subsequent December letter repeated FCI’s request for investigation and
    provided a series of questions for the CO to answer. See 
    id.
     at A104–09. Nowhere in
    either letter does FCI assert a claim for damages for breach of contract in a sum certain.
    In short, FCI has not complied with the CDA’s exhaustion requirements as to
    Counts I and II of its complaint. Therefore, the government’s motion for partial dismissal
    of the complaint as to those Counts must be granted.
    B.      Count IV
    The government has also moved to dismiss Count IV of the Complaint, in which
    FCI asks the Court to set aside its interim unsatisfactory performance evaluation because
    it was “unfair, inaccurate, erroneous, biased, and an abuse of discretion.” Compl. ¶ 60;
    see also 
    id. at 8
    . It contends that FCI failed to meet the CDA’s exhaustion requirements
    as to this claim as well. See Def.’s Mot. at 12–13. The Court disagrees.
    Courts have regularly held that a contractor’s challenge to an agency’s
    performance evaluation may constitute a claim under the CDA. See Todd Constr. L.P. v.
    United States, 
    85 Fed. Cl. 34
    , 45–46 (2008); BLR Grp. of Am., Inc. v. United States, 
    84 Fed. Cl. 634
    , 647–48 (2008). Because FCI seeks non-monetary relief for this claim, the
    CDA requires only that it have submitted a written demand for a final decision seeking
    relief from the unsatisfactory performance evaluation as a matter of right and received a
    final decision on that claim. See M. Maropakis Carpentry, 
    609 F.3d at
    1327–28; Alliant
    Techsystems, Inc., 
    178 F.3d at
    1266–68.
    The correspondence between FCI and the government reveals that FCI met this
    requirement. In a June 8, 2015 letter, FCI informed the CO that it “strongly disagree[d]”
    with the unsatisfactory performance evaluation and “formally request[ed]” its
    withdrawal. Def.’s Mot. App. at A35, 38. In a second letter on June 29, 2015, FCI again
    9
    “request[ed] that the CPAR evaluation be withdrawn.” 
    Id.
     at A49. The CO responded on
    July 6, 2015, stating that “[y]our request . . . for withdrawal of the Interim Unsatisfactory
    CPARS evaluation is denied.” 
    Id.
     at A55. And on July 13, 2015, the unsatisfactory
    evaluation was finalized. Pl.’s Opp’n App. at A244–52. This correspondence is sufficient
    to meet the CDA’s requirements that FCI submit a written demand for a final decision
    seeking relief from the unsatisfactory performance evaluation as a matter of right and that
    it receive a final decision on that claim from the CO. See BLR Grp. of Am., 84 Fed. Cl.
    at 636–37, 647–48 (written comments to initial performance evaluation which claimed
    entitlement to the relief of a corrected CPAR satisfied plaintiff’s obligation to file claim
    with the CO for purposes of the CDA).
    The Court finds unpersuasive the government’s argument that FCI’s letters do not
    constitute a written demand seeking relief as a matter of right under the CDA because
    FCI “has not demanded anything, but has only requested that the evaluation ‘be
    withdrawn.’” Def.’s Mot. at 12–13. This argument elevates form over substance. In
    common usage, a demand is an authoritative or formal type of request. See Webster’s 3d
    New Int’l Dictionary 598 (1961). Here, as noted, FCI “formally request[ed]” withdrawal
    of the evaluation, which the CO denied. In short, the government’s argument—that FCI
    failed to meet the CDA’s requirements because it couched its action as a “formal request”
    rather than a “demand”—lacks merit.3
    Accordingly, the Court concludes that FCI submitted a claim to the CO within the
    meaning of the CDA, and received the CO’s final decision on that claim. Thus, the Court
    has jurisdiction over Count IV of FCI’s complaint.
    III.   FCI’s Cross-Motion for a Default Judgment as to Count III and Further
    Proceedings in this Case
    The government concedes that the Court has jurisdiction over Count III of FCI’s
    complaint (claiming that the Termination for Default was unlawful and should be
    converted to a Termination for Convenience), at least to the extent that FCI seeks
    declaratory relief. See Def.’s Mot. at 8 n.2. In its motion to dismiss, it asks the Court to
    stay the case pending the receipt of a CO’s decision on FCI’s other claims.
    3
    In its motion to dismiss, the government argues that even if the June 29, 2015 letter
    made a valid claim with respect to the unsatisfactory evaluation, the CDA’s requirements
    have not been met because, it argues, the letter requests different relief than FCI
    requested in Count IV. It notes that “[t]he letter simply requests that the evaluation be
    withdrawn, but in its complaint, FCI demands that the evaluation ‘(1) be declared
    unlawful and should be set aside, and (2) should be removed from’ various reporting
    systems.” Def.’s Mot. at 13 (quoting Compl. ¶ 60). The Court does not perceive a request
    that the Court “set aside” the evaluation and direct the government to remove it from
    official reporting systems to differ in any material respect from a formal request that the
    evaluation be withdrawn.
    10
    Citing Gerlach v. Mich. Bell Tel. Co., 
    448 F. Supp. 1168
    , 1174 (E.D. Mich.
    1978), FCI has moved for a default judgment based on the government’s failure to timely
    respond to Count III. See Pl.’s Opp’n at 25–28. In that case, the district court concluded
    that the filing of a motion under Fed. R. Civ. P. 12(b) does not alter the time within which
    the moving party must respond to claims in the complaint that are not addressed in the
    motion. Gerlach, 
    448 F. Supp. at
    1174–75.
    To the Court’s knowledge, however, “[n]o other court has adopted the Gerlach
    court’s reasoning or ruling; indeed, every court to consider the decision in Gerlach on this
    point has disagreed with and declined to follow it.” Talbot v. Sentinel Ins. Co., No. 11-
    cv-1766, 
    2012 WL 1068763
    , at *4 (D. Nev. 2012) (quoting Ideal Instruments, Inc. v.
    Rivard Instruments, Inc., 
    434 F. Supp. 2d 598
    , 638 (N.D. Iowa 2006)). Instead, courts
    have held that under the language of Fed. R. Civ. P. 12(a) (which is identical to RCFC
    12(a)), a partial 12(b) motion enlarges the time to file an answer. E.g., Circuit City
    Stores, Inc. v. Citgo Petroleum Corp., No. 92-cv-7394, 
    1994 WL 483463
    , at *4 (E.D. Pa.
    Sept. 7, 1994) (citing Brocksopp Eng’g, Inc. v. Bach–Simpson, Ltd., 
    136 F.R.D. 485
    , 486
    (E.D. Wis. 1991)).
    This Court agrees with the reasoning expressed in those cases that “the filing of a
    motion that only addresses part of a complaint suspends the time to respond to the entire
    complaint, not just to the claims that are the subject of the motion.” Charles A. Wright &
    Arthur R. Miller, 5B Fed. Prac. & Proc. Civ. § 1346 (3d ed.); see also id. n.18 (citing
    cases). Further, even the court in Gerlach declined to impose the “harsh remedy” of a
    default judgment on the defendant based on its failure to respond to those counts in the
    complaint that were not the subject of its motion to dismiss. See 
    448 F. Supp. at 1174
    . In
    this case, as in Gerlach, FCI has not been prejudiced by the fact that the government did
    not file a response to Count III when it filed its motion to dismiss Counts I, II, and IV.
    For these reasons, FCI’s motion for a default judgment is DENIED.
    CONCLUSION
    For the reasons discussed above, the government’s motion to dismiss is
    GRANTED-IN-PART and DENIED-IN-PART. Counts I and II of the Complaint are
    DISMISSED without prejudice. FCI’s cross-motion for a default judgment is DENIED.
    The case is STAYED pending the CO’s final decision on the claims set forth in
    Counts I and II of FCI’s complaint. The parties shall file a joint status report with the
    Court no later than November 28, 2016 advising the Court of the status of the claims
    before the CO, and proposing a schedule to govern future proceedings in this case.
    11
    IT IS SO ORDERED.
    s/ Elaine D. Kaplan
    ELAINE D. KAPLAN
    Judge
    12