Treadwell Corporation v. United States ( 2019 )


Menu:
  •             In the United States Court of Federal Claims
    BID PROTEST
    No. 17-287C
    Filed Under Seal: March 14, 2019
    Reissued For Publication: April 12, 2019*
    )
    TREADWELL CORPORATION,                         )
    )
    Plaintiff,                                )
    )       Post-Award Bid Protest; Permanent
    v.                                             )       Injunction; RCFC 52.1; RCFC 65;
    )       Supplementing The Administrative
    THE UNITED STATES,                             )       Record; Delivery Schedule; Motion To
    )       Strike.
    Defendant,                                )
    )
    v.                                             )
    )
    HAMILTON SUNDSTRAND                            )
    CORPORATION,                                   )
    )
    Defendant-Intervenor.                     )
    )
    Anthony J. Marchese, Counsel of Record, Pamela J. Bethel, Of Counsel, Carol L.
    O’Riordan, Of Counsel, Taimur Rabbani, Of Counsel, O’Riordan Bethel Law Firm LLP,
    Washington, DC, for plaintiff.
    Sean L. King, Trial Attorney, Douglas K. Mickle, Assistant Director, Robert E.
    Kirschman, Jr., Director, Joseph H. Hunt, Assistant Attorney General, Commercial Litigation
    Branch, Civil Division, United States Department of Justice, Washington, DC; Gary M.
    Saladino, Of Counsel, Jonathan D. Pavlovcak, Of Counsel, United States Department of the
    Navy, Naval Surface Warfare Center, Philadelphia, PA, for defendant.
    John W. Chierichella, Attorney of Record, Keith R. Szeliga, Of Counsel, Adam A.
    Bartolanzo, Of Counsel, Sheppard Mullin Richter & Hampton LLP, Washington, DC, for
    defendant-intervenor.
    *
    This Memorandum Opinion and Order was originally filed under seal on March 14, 2019 (docket entry
    no. 65). The parties were given an opportunity to advise the Court of their views with respect to what
    information, if any, should be redacted from the Memorandum Opinion and Order. The parties filed a
    joint status report on April 11, 2019 (docket entry no. 67) proposing certain agreed-upon redactions and
    requesting that, in lieu of additional redactions, the Court rephrase certain information. And so, the Court
    is reissuing its Memorandum Opinion and Order dated March 14, 2019, with the adopted redactions
    indicated by three consecutive asterisks within brackets ([***]).
    MEMORANDUM OPINION AND ORDER
    GRIGGSBY, Judge
    I.     INTRODUCTION
    Plaintiff, Treadwell Corporation (“Treadwell”), brought this post-award bid protest
    matter challenging the United States Navy’s (“Navy”) decision to award a contract for low
    pressure electrolyzer (“LPE”) oxygen-generating systems (the “LPE Contract”) to Hamilton
    Sundstrand Corporation (“Hamilton”). The parties have filed cross-motions for judgment upon
    the administrative record on the issue of whether the Navy’s decision to award the LPE Contract
    to Hamilton was arbitrary, capricious, or contrary to law, pursuant to Rule 52.1 of the Rules of
    the United States Court of Federal Claims (“RCFC”). Hamilton has also moved to strike certain
    portions of a declaration filed in support of Treadwell’s motion for judgment upon the
    administrative record and portions of Treadwell’s motion.
    For the reasons discussed below, the Court: (1) DENIES Treadwell’s motion for
    judgment upon the administrative record; (2) GRANTS the government’s and Hamilton’s
    respective cross-motions for judgment upon the administrative record; (3) GRANTS Hamilton’s
    motion to strike; and (4) DISMISSES the complaint.
    II.    FACTUAL AND PROCEDURAL BACKGROUND1
    A.      Factual Background
    Treadwell is an unsuccessful offeror in connection with the solicitation for the LPE
    Contract. Compl. at ¶ 7; Pl. Mot. at 3-5. In this post-award bid protest matter, Treadwell
    challenges the Navy’s decision to award the LPE Contract to Hamilton in connection with the
    Navy’s Solicitation No. N64498-16-R-5003 (the “RFP”). See Compl.; see also AR Tab 23 at
    159.
    1
    The facts recited in this Memorandum Opinion and Order are taken from the complaint (“Compl.”); the
    second corrected administrative record (“AR”); Treadwell’s motion for judgment upon the administrative
    record (“Pl. Mot.”); the government’s cross-motion for judgment upon the administrative record and
    response and opposition to Treadwell’s motion for judgment upon the administrative record (“Def.
    Mot.”); and Hamilton’s cross-motion for judgment upon the administrative record and response and
    opposition to Treadwell’s motion for judgment upon the administrative record (“Def.-Int. Mot.”). Except
    where otherwise noted, the facts cited herein are undisputed.
    2
    Treadwell alleges in this action that the Navy’s decision to award the LPE Contract to
    Hamilton was unreasonable and contrary to law because: (1) the RFP requires delivery of
    certain LPE production units within 15 months of contract award; (2) Hamilton’s proposal was
    non-responsive; (3) Hamilton’s proposal was technically unacceptable; (4) the Navy engaged in
    unequal treatment of offerors; and (5) the Navy’s post-award modification of the LPE Contract
    was a material and cardinal change. See Pl. Mot. at 16-30. Treadwell further alleges that the
    Court should enjoin Hamilton from further performance under the LPE Contract because, among
    other things, Treadwell will be irreparably harmed by Hamilton’s continued performance under
    that contract. 
    Id. at 30-35.
    And so, Treadwell requests that the Court set aside the Navy’s
    decision to award the LPE Contract to Hamilton. 
    Id. at 35.
    1.      The Request For Proposals
    As background, the Navy issued a request for proposals to design, manufacture, test and
    deliver low pressure electrolyzer oxygen-generating systems which involve a self-contained
    oxygen generator to be used in submarines on December 28, 2015. AR Tab 23 at 159-245;
    Compl. ¶ 10. The RFP contemplates the award of an indefinite-delivery, indefinite-quantity
    contract, based upon a lowest-priced, technically acceptable basis. AR Tab 23 at 208-09, 243;
    Compl. ¶ 12.
    The RFP provides that proposals will be evaluated in accordance with an established
    evaluation plan, which would rate offerors’ proposals based upon “Technical Capability,
    Corporate Experience, and Past Performance, and on an overall basis.” AR Tab 23 at 242. With
    respect to the Technical Capability factor, the RFP provides that “offerors shall furnish
    information on [their] capability to furnish a Low Pressure Electrolyzer that will meet or exceed
    all the requirements set forth in the Specification.” 
    Id. at 234.
    2.      The First Article Test And Delivery Schedule
    The RFP also contains several requirements regarding the delivery schedule for the first
    article testing unit and the first article test for the low pressure electrolyzer oxygen-generating
    systems. In this regard, the RFP requires that the awardee of the LPE Contract provide the Navy
    with a first article testing unit, LPE simulators, and LPE production units. 
    Id. at 160-64.
    The
    statement of work for the RFP also describes the tests and procedures that the awardee must
    complete in order for the Navy to approve the first article testing unit. 
    Id. at 181-89.
    3
    Specifically, the RFP provides for the quality conformance and visual inspections, as well
    as the various testing requirements associated with first article testing—such as an endurance
    test, a vibration test and a shock test. 
    Id. In addition,
    the RFP incorporates Federal Acquisition
    Regulation (“FAR”) 52.209-3, which provides, in relevant part, that:
    Before first article approval, the acquisition of materials or components for, or the
    commencement of production of, the balance of the contract quantity is at the sole
    risk of the Contractor. Before first article approval, the costs thereof shall not be
    allocable to this contract for (1) progress payments, or (2) termination settlements
    if the contract is terminated for the convenience of the Government.
    
    Id. at 207
    (quoting 48 C.F.R. § 52.209-3(g)); see also AR Tab 28 at 353.
    The prescriptive language for the aforementioned FAR clause provides that:
    Before first article approval, the acquisition of materials or components, or
    commencement of production, is normally at the sole risk of the contractor. To
    minimize this risk, the contracting officer shall provide sufficient time in the
    delivery schedule for acquisition of materials and components, and for production
    after receipt of first article approval. When Government requirements preclude this
    action, the contracting officer may, before approval of the first article, authorize the
    contractor to acquire specific materials or components or commence production to
    the extent essential to meet the delivery schedule (see Alternate II of the clause at
    52.209–3, First Article Approval—Contractor Testing, and Alternate II of the
    clause at 52.209–4, First Article Approval—Government Testing. Costs incurred
    based on this authorization are allocable to the contract for (1) progress payments
    and (2) termination settlements if the contract is terminated for the convenience of
    the Government.
    48 C.F.R. § 9.305. Lastly, the RFP requires that the awardee deliver the first article testing unit
    “15 months after award of delivery order.” AR Tab 25 at 252.
    The RFP also contains several provisions relevant to the delivery schedule for the LPE
    simulators and LPE production units. AR Tab 23 at 197-98. In this regard, the RFP provides
    that:
    Any supplies and services to be furnished under this contract shall be ordered by
    issuance of delivery orders or task orders by the individuals or activities designated
    in the Schedule. Such orders may be issued from date of contract award through
    60 months thereafter.
    
    Id. at 208.
    4
    The delivery schedule in the RFP also provides that:
    52.211-8.       TIME OF DELIVERY (JUN 1997)
    (a) The Government requires delivery to be made according to the
    following schedule:
    REQUIRED DELIVERY SCHEDULE
    DELIVERY INFORMATION
    Delivery shall be specified in individual delivery orders. Delivery
    of LPE units is to be made at a rate of one (1) LPE per month
    beginning fifteen (15) months after receipt of each individual order.
    Delivery of LPE Simulator is the [sic] made at a rate of one (1) LPE
    Simulator per month beginning fifteen (15) months after receipt of
    each individual order. . . .
    Offers that propose delivery that will not clearly fall within the
    applicable required delivery period specified above, will be
    considered nonresponsive and rejected.
    
    Id. at 197;
    see also AR Tab 25 at 252.
    Lastly, the RFP provides that “the technical proposal shall be so specific, detailed and
    complete as to clearly and fully demonstrate that the prospective contractor has a thorough
    understanding of the technical requirements . . . of this solicitation.” AR Tab 26 at 313. In this
    regard, the RFP also provides that the “LPE delivery schedule shall be included in the technical
    proposal” and that:
    The Government will evaluate equally, as regards time of delivery, offers that
    propose delivery of each quantity within the applicable delivery period specified
    above. Offers that propose delivery that will not clearly fall within the applicable
    required delivery period specified above, will be considered nonresponsive and
    rejected.
    Id.; AR Tab 23 at 197. In addition, the RFP provides that “[i]f the offeror proposes no other
    delivery schedule, the required delivery schedule above will apply.” AR Tab 23 at 197. And so,
    the RFP provides that the completion and submission of the award documents “will constitute an
    offer (proposal) and will be considered the offeror’s unconditional assent to the terms and
    conditions of this solicitation and any attachments and/or exhibits hereto.” 
    Id. at 233.
    3.      Evaluation Of Proposals
    Prior to the submission of its initial proposal, Treadwell requested that the Navy change
    the due date for the delivery of the first article testing unit under the RFP to six months after
    5
    receipt of contract award. AR Tab 25 at 252. Treadwell also requested that the Navy change the
    due date for the delivery of the LPE production units and LPE simulators to one unit per month,
    beginning fifteen months after receipt of the LPE Contract and first article testing unit approval.
    
    Id. On January
    28, 2016, the Navy rejected Treadwell’s request and responded that:
    The delivery schedule for the production units remains unchanged. The delivery
    schedule for the [first article testing] unit is 15 months after award of delivery order.
    Simulators are also to be delivered 1 per month beginning 15 months after award
    of delivery order.
    
    Id. Treadwell and
    Hamilton timely submitted initial proposals in response to the RFP in
    February 2016. See generally AR Tab 32; AR Tab 34. Treadwell’s initial proposal was the only
    proposal that the Navy deemed to be technically acceptable. Compl. ¶¶ 36, 85; AR Tab 38 at
    907-16.2
    Following the receipt of these initial proposals, the Navy conducted an evaluation under
    the RFP’s Technical Capability, Corporate Experience and Past Performance Factors. AR Tab
    38 at 907-09, 915-16. On April 11, 2016, the Navy sent letters to Hamilton and Treadwell
    notifying the offerors of any issues with respect to the initial proposals and providing an
    opportunity for the offerors to submit revised proposals. AR Tab 39 at 917-18, 923-24.
    On May 16, 2016, Treadwell submitted a revised proposal which set forth the following
    delivery schedule for the first article testing unit, LPE simulators, and LPE production units:
    •   The delivery schedule for all CLINs will be in full compliance with
    Amendment 0002 of [the RFP].
    •   LPE Production units (CLINs 0003 – 0007) will be delivered at a rate of one
    (1) per month beginning fifteen (15) months after receipt of each individual
    order.
    •   LPE Simulators (CLINs 0008 & 0009) will be delivered at a rate of one (1) per
    month beginning fifteen (15) months after receipt of each individual order.
    2
    In the cover letter to its initial proposal, Treadwell states that:
    The solicitation requires that the contractor be able to complete First Article Test, one
    production unit and one simulator within fifteen MARC [months after receipt of contract].
    These three simultaneous requirements can only be accomplished within fifteen months by
    a contractor that has already completed LPE design, First Article testing and simulator
    design.
    AR Tab 34 at 659.
    6
    •   The LPE First Article Test (CLIN 0001) and Test Report (CLIN 0002) will be
    completed and delivered no later than fifteen (15) months after award of
    delivery order.
    AR Tab 43 at 1126.
    Hamilton submitted its revised proposal on May 17, 2016. See generally AR Tab 42.
    Hamilton’s revised proposal proposes a schedule for qualification of fifteen months, meaning
    that Hamilton planned to complete first article testing unit approval within fifteen months of
    contract award. 
    Id. at 1009.
    Hamilton does not otherwise address the delivery schedule in its
    revised proposal. See generally 
    id. at 941-1013.
    Following the evaluation of revised proposals, the Navy deemed the revised proposals
    submitted by Treadwell and Hamilton to be technically acceptable. AR Tab 44 at 1140-41. And
    so, on May 27, 2016, the Navy sent Treadwell and Hamilton letters affording both offerors the
    opportunity to submit final proposal revisions. AR Tab 45 at 1142; AR Tab 46 at 1152-53.
    Treadwell submitted its final proposal revision on June 2, 2016. See generally AR Tab
    49. In its final proposal revision, Treadwell states that “[t]he solicitation requires that the
    contractor be able to complete First Article Test, one production unit and one simulator within
    fifteen [months after receipt of contract].” 
    Id. at 1341.
    In addition, Treadwell’s final proposal
    revision proposes a price of [***]. 
    Id. at 1345.
    Hamilton submitted its final proposal revision on June 3, 2016. See generally AR Tab
    48. In its final proposal revision, Hamilton states that its “proposed schedule for Qualification is
    fifteen (15) months . . . .” AR Tab 48 at 1321. In the technical proposal volume of its final
    proposal revision, Hamilton also provides a delivery schedule for the first article testing unit. 
    Id. (providing a
    timeline for design, procurement, assembly, grooming, qualification testing, and
    shock testing). Hamilton does not otherwise address the delivery schedule in its final proposal
    revision. See generally 
    id. at 1165-1338.
    But, Hamilton’s final proposal revision incorporates
    the RFP’s delivery schedule and states that Hamilton “is agreeable to the terms, conditions, and
    provisions included in the solicitation . . . .” 
    Id. at 1166,
    1215. In addition, Hamilton’s final
    proposal revision proposes a price of $42,782,640.00—approximately [***] less than
    Treadwell’s final proposed price. AR Tab 51 at 1373.
    7
    4.      Award To Hamilton
    The Navy deemed the final proposal revisions from Treadwell and Hamilton to be
    technically acceptable. 
    Id. at 1369-71.
    And so, on July 13, 2016, the Navy awarded the LPE
    Contract to Hamilton, based upon the agency’s determination that Hamilton submitted the
    lowest-priced, technically acceptable proposal. See generally AR Tab 54.
    5.      Post-Award Contract Modifications
    On July 13, 2016, the Navy issued Delivery Order 0001 to Hamilton requesting the
    delivery of the first article testing unit and two LPE production units. See generally AR Tab 55.
    The delivery order states in a note that “[p]roduction units shall not be delivered until after
    Approval of First Article.” 
    Id. at 1465.
    On September 13, 2016, Hamilton responded to the Navy’s delivery order by stating that:
    [W]e were not aware or had planned financially to be supporting a parallel
    production procurement during the design & development effort. We are happy to
    support this additional opportunity but if qualification issues arise that require
    system/hardware changes UTAS would have to support. This additional risk was
    not anticipated.
    AR Tab 64 at 1669.
    On November 2, 2016, the Navy issued a modification to the LPE Contract which
    extended the original delivery deadline for the two requested LPE production units from October
    13, 2017, to November 30, 2018, and clarified that the deadline for delivery of the LPE
    production units would be 12 months after first article testing unit approval. AR Tab 61 at 1541,
    1545.27.
    6.      The Court’s July 19, 2017, Decision
    After Treadwell commenced this post-award bid protest action, the Court issued a
    memorandum opinion and order denying Treadwell’s motion for a preliminary injunction on July
    19, 2017 (the “July 19, 2017, Decision”). See generally Treadwell Corp. v. United States, 
    133 Fed. Cl. 371
    (2017). In the July 19, 2017, Decision, the Court held that Treadwell did not meet
    its heavy burden to show that it is entitled to emergency injunctive relief in this matter, because,
    among other reasons, the administrative record shows that the Navy’s decision to award the LPE
    8
    Contract to Hamilton was reasonable and in accordance with the terms of the RFP and applicable
    law. 
    Id. at 389.
    Specifically relevant to the parties’ cross-motion for judgment upon the administrative
    record, the Court held in the July 19, 2017, Decision that Treadwell’s claims that Hamilton’s
    proposal was unresponsive and technically unacceptable are unsubstantiated by the record
    evidence, because the RFP contemplates the approval of the first article testing unit before the
    LPE production units or the LPE simulators are to be delivered to the Navy. 
    Id. at 383-86;
    see
    generally AR Tabs 23-30. In this regard, the Court observed that the RFP incorporates FAR
    52.209-3, which warns potential contractors that starting production of deliverables under a
    government contract prior to first article testing unit approval would be at the sole risk of the
    contractor. Treadwell 
    Corp., 133 Fed. Cl. at 384
    ; see also AR Tab 23 at 207; AR Tab 28 at 352-
    53. And so, the Court concluded that the RFP for the LPE Contract requires that the Navy
    approve the first article testing unit prior to the delivery of the LPE production units and LPE
    simulators to the Navy. Treadwell 
    Corp., 133 Fed. Cl. at 385
    .
    The Court also rejected Treadwell’s argument that Hamilton’s proposal was not
    technically acceptable, because Hamilton did not demonstrate that it could meet the RFP’s
    delivery schedule. 
    Id. at 386.
    Specifically, the Court found that the administrative record shows
    that the Navy reasonably determined that Hamilton was technically capable of meeting the
    delivery schedule called for under the RFP and that Hamilton expressly committed to the RFP’s
    delivery schedule in its final proposal revision. Id.; see also AR Tab 23 at 197; AR Tab 48 at
    1166.
    In addition, the Court held that Treadwell’s unequal treatment claim was not
    substantiated by the administrative record, because the RFP did not require that Hamilton meet
    the aggressive delivery schedule that Treadwell proposed in its own proposal. Treadwell 
    Corp., 133 Fed. Cl. at 386
    . In this regard, the Court determined that the administrative record shows
    that the Navy equally evaluated the proposals submitted by Treadwell and Hamilton, based upon
    the evaluation factors set forth in the RFP. Id.; see also AR Tab 23 at 242; AR Tab 38 at 907-16;
    AR Tab 44 at 1140-41; AR Tab 51 at 1369-71. The Court also determined that the record
    evidence shows that the Navy’s November 2, 2016, modification of the LPE Contract
    was not a cardinal or material change, because this modification fell within the scope of the
    9
    original procurement for the LPE Contract. 
    Id. at 387-88,
    n.8. And so, the Court concluded that
    Treadwell failed to demonstrate a likelihood of success upon the merits of any of its claims, and,
    as a result, Treadwell was not entitled to preliminary injunctive relief. 
    Id. at 389.
    3
    After the Court issued the July 19, 2017, Decision, Treadwell filed an interlocutory
    appeal of the decision to the United States Court of Appeals for the Federal Circuit. Notice of
    Appeal, dated Sept. 8, 2017. On June 13, 2018, the Federal Circuit issued a per curiam opinion
    affirming the Court’s July 19, 2017, Decision. See generally Treadwell Corp. v. United States,
    726 F. App’x 826 (Fed. Cir. 2018) (per curiam).
    B.      Procedural Background
    Treadwell commenced this post-award bid protest action on March 1, 2017. See
    generally Compl. On March 1, 2017, Treadwell filed a motion for a preliminary injunction and a
    memorandum in support thereof. See generally Pl. Mot. for Prelim. Inj.; Pl. Mem.
    On March 23, 2017, the government filed the administrative record. See generally Initial
    AR. On March 31, 2017, the government filed a corrected administrative record. See Notice,
    Mar. 31, 2017. On April 5, 2017, the government filed a second corrected administrative record.
    See generally AR.
    After the parties fully briefed Treadwell’s motion for a preliminary injunction, the Court
    issued a memorandum opinion and order denying Treadwell’s motion on July 19, 2017. See
    generally Treadwell 
    Corp., 133 Fed. Cl. at 371-89
    . Following Treadwell’s interlocutory appeal
    of the July 19, 2017, Decision, the Federal Circuit issued a per curiam opinion affirming the
    Court’s July 19, 2017, Decision on June 13, 2018. See generally Treadwell Corp., 726 F. App’x
    at 826-27.
    On September 19, 2018, Treadwell filed a motion for judgment upon the administrative
    record. See generally Pl. Mot. On October 31, 2018, the government and Hamilton filed their
    respective responses and oppositions to Treadwell’s motion for judgment upon the
    administrative record and cross-motions for judgment upon the administrative record. See
    3
    The Court also held that Treadwell’s claims that the Navy awarded the LPE Contract with the intent to
    modify and that the Navy failed to engage in meaningful discussions were unsubstantiated by the record
    evidence. Treadwell Corp. v. United States, 
    133 Fed. Cl. 371
    , 388-89 (2017).
    10
    generally Def. Mot.; Def.-Int. Mot. On October 31, 2018, Hamilton filed a motion to strike
    paragraphs 2, 4, 5, 6, and 7 of the Declaration of Robert Johnson and certain portions of
    Treadwell’s motion for judgment upon the administrative record. See generally Def.-Int. Mot. at
    37-41.
    On November 30, 2018, Treadwell filed a response and opposition to the government’s
    and Hamilton’s respective cross-motions for judgment upon the administrative record, a response
    to Hamilton’s motion to strike, and a reply in support of its motion for judgment upon the
    administrative record. See generally Pl. Resp. On December 14, 2018, the government and
    Hamilton filed their respective reply briefs. See generally Def. Reply; Def.-Int. Reply.
    These matters having been fully briefed, the Court resolves the pending motions.
    III.     LEGAL STANDARDS
    A.     Jurisdiction And Bid Protests
    The Tucker Act grants the United States Court of Federal Claims jurisdiction over bid
    protests brought by “an interested party objecting to a solicitation by a Federal agency for bids or
    proposals for a proposed contract or to a proposed award or the award of a contract or any
    alleged violation of statute or regulation in connection with a procurement or a proposed
    procurement.” 28 U.S.C. § 1491(b)(1). In bid protest cases, this Court reviews agency actions
    under the Administrative Procedure Act’s (“APA”) “arbitrary and capricious” standard. See 28
    U.S.C. § 1491(b)(4) (adopting the standard of review set forth in the Administrative Procedure
    Act). And so, under the APA’s standard, an award may be set aside if, “(1) the procurement
    official’s decision lacked a rational basis; or (2) the procurement procedure involved a violation
    of regulation or procedure.” Banknote Corp. of Am., Inc. v. United States, 
    365 F.3d 1345
    , 1351
    (Fed. Cir. 2004) (quoting Impresa Construzioni Geom. Domenico Garufi v. United States, 
    238 F.3d 1324
    , 1332 (Fed. Cir. 2001)). The United States Court of Appeals for the Federal Circuit
    has also recognized that:
    When a challenge is brought on the first ground, the test is whether the contracting
    agency provided a coherent and reasonable explanation of its exercise of discretion,
    and the disappointed bidder bears a “heavy burden” of showing that the award
    decision had no rational basis. When a challenge is brought on the second ground,
    the disappointed bidder must show a clear and prejudicial violation of applicable
    statutes or regulations.
    11
    
    Id. (citations omitted).
    In reviewing an agency’s procurement decision, the Court should recognize that the
    agency’s decision is entitled to a “presumption of regularity.” Citizens to Pres. Overton Park,
    Inc. v. Volpe, 
    401 U.S. 402
    , 415 (1971) (citations omitted), overruled on other grounds by
    Califano v. Sanders, 
    430 U.S. 99
    (1977). And so, the Court should not substitute its judgment
    for that of the agency. Cincom Sys., Inc. v. United States, 
    37 Fed. Cl. 663
    , 672 (1997). In
    addition, “[t]he protestor must show, by a preponderance of the evidence, that the agency’s
    actions were either without a reasonable basis or in violation of applicable procurement law” or
    procedure. Info. Tech. & Applications Corp. v. United States, 
    51 Fed. Cl. 340
    , 346 (2001), aff’d,
    
    316 F.3d 1312
    (Fed. Cir. 2003); see also Bannum, Inc. v. United States, 
    60 Fed. Cl. 718
    , 723
    (2004); Gentex Corp. v. United States, 
    58 Fed. Cl. 634
    , 648 (2003). This standard “is highly
    deferential” and “requires a reviewing court to sustain an agency action evincing rational
    reasoning and consideration of relevant factors.” Advanced Data Concepts, Inc. v. United States,
    
    216 F.3d 1054
    , 1058 (Fed. Cir. 2000) (citing Bowman Transp., Inc. v. Ark.–Best Freight Sys.,
    Inc., 
    419 U.S. 281
    , 285 (1974)).
    In this regard, the Federal Circuit has held that, as long as there is “a reasonable basis for
    the agency’s action, the court should stay its hand even though it might, as an original
    proposition, have reached a different conclusion . . . .” Honeywell, Inc. v. United States, 
    870 F.2d 644
    , 648 (Fed. Cir. 1989) (citations omitted). But, the Federal Circuit has also recognized
    that, if “the agency ‘entirely fail[s] to consider an important aspect of the problem [or] offer[s] an
    explanation for its decision that runs counter to the evidence before the agency,’” then the
    resulting action lacks a rational basis and is, therefore, defined as arbitrary and capricious. Ala.
    Aircraft Indus., Inc.–Birmingham v. United States, 
    586 F.3d 1372
    , 1375 (Fed. Cir. 2009)
    (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)).
    B.      Injunctive Relief And RCFC 65
    Under its bid protest jurisdiction, the Court “may award any relief that [it] considers
    proper, including declaratory and injunctive relief.” 28 U.S.C. 1491(b)(2); see also Centech
    Grp., Inc. v. United States, 
    554 F.3d 1029
    , 1037 (Fed. Cir. 2009). In deciding whether to issue a
    permanent injunction, the Court “considers: (1) whether . . . the plaintiff has succeeded on the
    merits of the case; (2) whether the plaintiff will suffer irreparable harm if the court withholds
    12
    injunctive relief; (3) whether the balance of hardships to the respective parties favors the grant of
    injunctive relief; and (4) whether it is in the public interest to grant injunctive relief.” PGBA,
    LLC v. United States, 
    389 F.3d 1219
    , 1228-29 (Fed. Cir. 2004) (citing Amoco Prod. Co. v. Vill.
    of Gambell, Alaska, 
    480 U.S. 531
    , 546 n.12 (1987) (“The standard for a preliminary injunction is
    essentially the same as for a permanent injunction with the exception that the plaintiff must show
    a likelihood of success on the merits rather than actual success.”); see also Centech Grp., 
    Inc., 554 F.3d at 1037
    . In this regard the Federal Circuit has held that:
    No one factor, taken individually, is necessarily dispositive. If a preliminary
    injunction is granted by the trial court, the weakness of the showing regarding one
    factor may be overborne by the strength of the others. If the injunction is denied,
    the absence of an adequate showing with regard to any one factor may be sufficient,
    given the weight or lack of it assigned the other factors, to justify the denial.
    FMC Corp. v. United States, 
    3 F.3d 424
    , 427 (Fed. Cir. 1993) (citations omitted).
    A plaintiff who cannot demonstrate actual success upon the merits cannot prevail upon a
    motion for injunctive relief. Cf. Nat’l Steel Car, Ltd. v. Canadian Pacific Ry., Ltd., 
    357 F.3d 1319
    , 1325 (Fed. Cir. 2004) (finding that a plaintiff who cannot demonstrate likely success upon
    the merits cannot prevail upon its motion for preliminary injunctive relief). This Court has also
    found success upon the merits to be “the most important factor for a court to consider when
    deciding whether to issue injunctive relief.” Dellew Corp. v. United States, 
    108 Fed. Cl. 357
    ,
    369 (2012) (citing Blue & Gold Fleet, L.P. v. United States, 
    492 F.3d 1308
    , 1312 (Fed. Cir.
    2007)). But, while success upon the merits is necessary, it is not sufficient alone for a plaintiff to
    establish that it is entitled to injunctive relief. See Contracting, Consulting, Eng’g LLC v. United
    States, 
    104 Fed. Cl. 334
    , 353 (2012) ((“Although plaintiff’s entitlement to injunctive relief
    depends on its succeeding on the merits, it is not determinative because the three equitable
    factors must be considered, as well.”) (citations omitted)).
    C.      Supplementing The Administrative Record
    Lastly, the Federal Circuit held in Axiom Resource Management, that the “parties’ ability
    to supplement the administrative record is limited” and that the administrative record should only
    be supplemented “if the existing record is insufficient to permit meaningful review consistent
    with the APA.” Axiom Res. Mgmt., Inc. v. United States, 
    564 F.3d 1374
    , 1379-81 (Fed. Cir.
    2009); see also Caddell Constr. Co., Inc. v. United States, 
    111 Fed. Cl. 49
    , 93 (2013). The
    13
    Federal Circuit also recognized that, in Camp v. Pitts, the Supreme Court held that “the focal
    point for judicial review should be the administrative record already in existence, not some new
    record made initially in the reviewing court.” 
    Axiom, 564 F.3d at 1379
    (quoting Camp v. Pitts,
    
    411 U.S. 138
    , 142 (1973)).
    This Court has interpreted the Federal Circuit’s directive in Axiom to mean that
    supplementation of the administrative record is permitted to correct mistakes and fill gaps, but
    supplementation is not permitted when the documents proffered are unnecessary for an effective
    review of the government’s procurement decision. L-3 Commc’ns EOTech, Inc. v. United States,
    
    87 Fed. Cl. 656
    , 672 (2009). And so, this Court has precluded supplementation of the
    administrative record with declarations that contain “post-hoc contentions of fact and argument.”
    
    Id. But, the
    Court has also held that “it is appropriate to add evidence pertaining to prejudice and
    the factors governing injunctive relief to the record in a bid protest—not as a supplement to the
    AR, but as part of this Court’s record.” AshBritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 366-67
    (2009).
    IV.       LEGAL ANALYSIS
    The parties have filed cross-motions for judgment upon the administrative record on the
    issue of whether the Navy’s decision to award the LPE Contract to Hamilton was arbitrary,
    capricious, or contrary to law, pursuant to RCFC 52.1.
    In its motion for judgment upon the administrative record, Treadwell alleges that the
    Navy’s decision to award the LPE Contract to Hamilton was unreasonable and contrary to law
    for five reasons—namely, because: (1) the RFP requires delivery of the LPE production units
    within 15 months of contract award; (2) Hamilton’s proposal was non-responsive; (3) Hamilton’s
    proposal was technically unacceptable; (4) the Navy engaged in unequal treatment of offerors;
    and (5) the Navy’s post-award modification of the LPE Contract was a material and cardinal
    change. See Pl. Mot. at 16-30. Treadwell further alleges that the Court should enjoin Hamilton
    from further performance under the LPE Contract because, among other things, Treadwell will
    be irreparably harmed by Hamilton’s continued performance under that contract. 
    Id. at 30-35.
    The government and Hamilton counter in their respective cross-motions for judgment
    upon the administrative record that the Navy’s decision to award the LPE Contract to Hamilton
    was reasonable and in accordance with the requirements of the RFP and applicable law because:
    14
    (1) the RFP does not require delivery of the LPE production units within 15 months of contract
    award; (2) the Navy evaluated responsive proposals in accordance with the requirements of the
    RFP; and (3) the Navy’s post-award modification of the LPE Contract was not a cardinal or
    material change. See Def. Mot. at 8-20; Def.-Int. Mot. at 16-30. Hamilton has also moved to
    strike certain portions of the Declaration of Robert Johnson, which Treadwell has filed in support
    of its motion for judgment upon the administrative record, and certain portions of Treadwell’s
    motion, upon the ground that Treadwell seeks to improperly supplement the administrative
    record with this information. Def.-Int. Mot. at 37-41.
    For the reasons discussed below, the record evidence in this matter does not substantiate
    any of Treadwell’s challenges to the Navy’s decision to award the LPE Contract to Hamilton.
    In addition, Hamilton correctly argues that certain information contained in the Declaration of
    Robert Johnson is not properly before the Court. And so, the Court: (1) DENIES Treadwell’s
    motion for judgment upon the administrative record; (2) GRANTS the government’s and
    Hamilton’s respective cross-motions for judgment upon the administrative record; (3) GRANTS
    Hamilton’s motion to strike; and (4) DISMISSES the complaint.
    A.      The Court Grants Hamilton’s Motion To Strike
    As an initial matter, the Court must grant Hamilton’s motion to strike certain paragraphs
    contained in the declaration submitted by Treadwell’s chief operating officer, Robert Johnson
    (the “Johnson Declaration”), because this declaration contains information that is not included in
    the administrative record. A careful review of the Johnson Declaration shows that paragraphs 2,
    4, 5, 6, and 7 of the declaration address certain meetings and discussions that Treadwell alleges
    occurred between the company and the Navy during the procurement process for the LPE
    Contract. Johnson Decl. at ¶¶ 2, 4-7. Other paragraphs in this declaration address the harm that
    Treadwell will allegedly suffer if the Court declines to award Treadwell injunctive relief. 
    Id. at ¶¶
    8-18.
    To the extent that Treadwell seeks to supplement the administrative record with
    information regarding meetings and discussions that Treadwell held with the Navy, the Court
    must disregard this information. This Court has held that it may consider information that is not
    contained in the administrative record as part of the Court record in a bid protest dispute, if the
    information pertains to the factors that the Court weighs in deciding whether to grant injunctive
    15
    relief. See, e.g., AshBritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 366-67 (2009) (“In general, it is
    appropriate to add evidence pertaining to prejudice and the factors governing injunctive relief to
    the record in a bid protest—not as a supplement to the AR, but as part of this Court’s record.”).
    But, as Hamilton correctly argues in its motion to strike, paragraphs 2, 4, 5, 6, and 7 of the
    Johnson Declaration address the merits of Treadwell’s claims and contain information that is not
    included in the existing administrative record. Def.-Int. Mot. at 37-41. The government has
    filed a comprehensive administrative record in this matter, and the disputed paragraphs of the
    Johnson Declaration neither correct, nor fill any gaps in the administrative record. See Initial
    AR; Notice, Mar. 31, 2017; see generally AR. Given this, the Court concurs with Hamilton that
    certain portions of the Johnson Declaration are not properly before the Court. And so, the Court
    GRANTS Hamilton’s motion to strike.
    B.      Treadwell’s Claims Are Unsubstantiated By The Record Evidence
    1.      The RFP Does Not Require Delivery
    Within 15 Months Of Contract Award
    With respect to the merits of Treadwell’s claims, the administrative record does not
    support the premise of this bid protest dispute—that the RFP requires delivery of the LPE
    production units to the Navy within 15 months of the award of the LPE Contract. Pl. Mot. at 16-
    21. Rather, a plain reading of the RFP makes clear that the RFP contemplates the approval of the
    first article testing unit before LPE production units (or the LPE simulators) are to be delivered
    to the Navy. See generally AR Tabs 23-30. And so, Treadwell cannot prevail in this bid protest
    dispute.
    As the Court held in the July 19, 2017, Decision, the Court must read the RFP’s delivery
    schedule requirements within the context of federal procurement regulations that are applicable
    to the LPE Contract. Essex Electro Eng’rs, Inc. v. United States, 
    702 F.2d 998
    , 1002 (Fed. Cir.
    1983) (explaining that a contract provision cannot “be interpreted to override the applicable
    regulations”); Treadwell 
    Corp., 133 Fed. Cl. at 383-86
    . These regulations make clear that the
    Navy has discretion regarding when to issue delivery orders under the LPE Contract, provided
    that the Navy allows for sufficient time in the delivery schedule for the acquisition of materials
    and production after the approval of the first article unit. 48 C.F.R. §§ 9.305, 52.209-3.
    16
    Notably, the RFP incorporates FAR 52.209-3, which warns potential contractors that
    starting production of deliverables under a government contract prior to first article testing unit
    approval would be at the sole risk of the contractor. AR Tab 23 at 207; AR Tab 28 at 352-53. In
    this regard, FAR 52.209-3 provides that:
    Before first article approval, the acquisition of materials or components for, or the
    commencement of production of, the balance of the contract quantity is at the sole
    risk of the Contractor. Before first article approval, the costs thereof shall not be
    allocable to this contract for (1) progress payments, or (2) termination settlements
    if the contract is terminated for the convenience of the Government.
    AR Tab 23 at 207; AR Tab 28 at 352-53; see also 48 C.F.R. § 52.209-3(g). And so, this
    regulation makes clear that Hamilton assumes the financial risk of starting the production of the
    LPE production units (or LPE simulators) prior to the approval of the first article testing unit. 48
    C.F.R. § 52.209-3(g).
    The Court’s reading of the RFP to require the approval of the first article testing unit
    prior to the delivery of the LPE production units (or LPE simulators) is also reinforced by the
    requirements of FAR 9.305, which provides, in relevant part, that:
    Before first article approval, the acquisition of materials or components, or
    commencement of production, is normally at the sole risk of the contractor. To
    minimize this risk, the contracting officer shall provide sufficient time in the
    delivery schedule for acquisition of materials and components, and for production
    after receipt of first article approval. When Government requirements preclude this
    action, the contracting officer may, before approval of the first article, authorize the
    contractor to acquire specific materials or components or commence production to
    the extent essential to meet the delivery schedule (see Alternate II of the clause at
    52.209–3, First Article Approval—Contractor Testing, and Alternate II of the
    clause at 52.209–4, First Article Approval—Government Testing. Costs incurred
    based on this authorization are allocable to the contract for (1) progress payments
    and (2) termination settlements if the contract is terminated for the convenience of
    the Government.
    48 C.F.R. § 9.305.4 And so, when read in light of FAR 9.305 and 52.209-3, the RFP requires
    that the Navy provide sufficient time in the delivery schedule for, among other things, production
    4
    In addition, FAR 52.101(c) provides that:
    (c) Prescriptions. Each provision or clause in subpart 52.2 is prescribed at that place in the
    FAR text where the subject matter of the provision or clause receives its primary treatment.
    The prescription includes all conditions, requirements, and instructions for using the
    17
    of the LPE production units (or LPE simulators) following the first article approval. AR Tab 23
    at 207.
    Treadwell’s reliance upon the delivery schedule in the RFP to argue that Hamilton must
    deliver the LPE production units within 15 months of the award of the LPE Contract is also
    misplaced. Section F of the RFP provides that:
    Delivery of LPE units is to be made at a rate of one (1) LPE per month beginning
    fifteen (15) months after receipt of each individual order. Delivery of LPE
    Simulator is the [sic] made at a rate of one (1) LPE Simulator per month beginning
    fifteen (15) months after receipt of each individual order.
    AR Tab 23 at 197. As Treadwell correctly observes, this delivery schedule requires that
    Hamilton deliver the LPE production units (or LPE simulators) beginning 15 months after
    receipt of a delivery order. See Pl. Mot. at 16. But, this schedule does not require that the LPE
    production units be delivered within 15 months of contract award as Treadwell suggests. See 
    id. To the
    contrary, when read in light of FAR 52.209.3 and 9.305, the RFP’s delivery
    schedule clearly requires that “the contracting officer shall provide sufficient time in the delivery
    schedule for acquisition of materials and components, and for production after receipt of first
    article approval.” 48 C.F.R. § 9.305. And so, as discussed above, the RFP’s delivery schedule
    simply does not mandate that Hamilton deliver the LPE production units (or LPE simulators)
    before receipt of first article approval.
    Treadwell’s reliance upon the RFP’s order of precedence clause to show that the LPE
    production units must be delivered to the Navy within 15 months of contract award is equally
    misplaced. Treadwell argues in its motion for judgment upon the administrative record that the
    FAR 52.215-8 Order of Precedence—Uniform Contract Formation Clause, which is incorporated
    by reference into the RFP, requires that the Navy give precedence to the delivery schedule set
    forth in the RFP over any inconsistent requirements set forth in FAR 52.209-3 and 9.305. Pl.
    Mot. at 17; see AR Tab 23 at 204. But, to the extent that there is any conflict or inconsistency
    provision or clause and its alternates, if any. The provision or clause may be referred to in
    other FAR locations.
    48 C.F.R. § 52.101(c).
    18
    between the FAR and the RFP’s delivery schedule, the RFP’s order of precedence clause is not
    intended to resolve that conflict.
    Notably, the order of precedence clause provides that:
    Any inconsistency in this solicitation . . . shall be resolved by giving precedence in
    the following order:
    (a) The Schedule (excluding the specifications).
    (b) Representations and other instructions.
    (c) Contract clauses.
    (d) Other documents, exhibits, and attachments.
    (e) The specifications.
    48 C.F.R. § 52.215-8 (emphasis supplied); see also AR Tab 23 at 204. The purpose of this
    clause is to harmonize internal conflicts within the provisions of the RFP, rather than to resolve
    any conflicts between the terms of the RFP and federal procurement regulations. 48 C.F.R. §
    52.215-8; Apollo Sheet Metal, Inc. v. United States, 
    44 Fed. Cl. 210
    , 214 (1999) (“One thus looks
    to the order of precedence clause to resolve inconsistencies between specific terms in competing
    clauses of like provision . . . .”); see also Sperry Corp. v. United States, 
    845 F.2d 965
    , 968 (Fed.
    Cir. 1988). And so, the RFP’s order of precedence clause does not support Treadwell’s claim.
    2.      Treadwell Has Not Shown That Hamilton’s
    Proposal Was Unresponsive Or Technically Unacceptable
    Because the Court does not read the RFP to require the delivery of the LPE production
    units within 15 months of the award of the LPE Contract, Treadwell’s claims that Hamilton’s
    proposal was unresponsive and technically unacceptable are also belied by the record evidence.
    Pl. Mot. at 21-24. Treadwell argues in its motion for judgment upon the administrative record,
    that Hamilton’s proposal was not responsive to the RFP because Hamilton did not include a
    delivery schedule for the LPE production units in its technical proposal. 
    Id. at 21.
    But, the
    record evidence in this matter makes clear that the Navy reasonably determined that Hamilton
    could meet the RFP’s delivery schedule requirements for several reasons.
    First, a careful review of the administrative record shows that Hamilton committed to
    meeting the RFP’s delivery schedule in the final proposal revision submitted to the Navy on June
    19
    3, 2016. AR Tab 48 at 1215; see also AR Tab 23 at 197. Specifically, the administrative record
    shows that Hamilton included the RFP’s delivery schedule in volume one of its final proposal
    revision. AR Tab 48 at 1215. Hamilton also states in the cover letter to its final proposal
    revision that it “is agreeable to the terms, conditions, and provisions included in the solicitation.”
    
    Id. at 1166.
    Hamilton’s representation is notable because the RFP provides that “[i]f the offeror
    proposes no other delivery schedule, the required delivery schedule” will apply. AR Tab 23 at
    197.
    Treadwell also fails to explain why the fact that Hamilton did not include a delivery
    schedule specifically for the LPE production units in the technical volume of its final proposal
    revision renders Hamilton’s proposal technically unacceptable. While the RFP does require that
    Hamilton provide an LPE delivery schedule in its technical proposal, Treadwell points to no
    provision in the RFP that would specifically require Hamilton to include a delivery schedule for
    the LPE production units in the technical portion of the final proposal revision. See Pl. Mot. at
    21-23, 29-30; Pl. Resp. at 11-15; see also AR Tab 26 at 313. Indeed, as the administrative
    record makes clear, Hamilton’s final proposal revision provides a schedule for the delivery of the
    first article testing unit within 15 months of contract award and states that, thereafter, it will
    begin production of the LPE simulators and LPE production units—as required by the RFP. AR
    Tab 48 at 1215, 1321; see also AR Tab 64 at 1669. Hamilton also provides a qualification
    delivery schedule for the first article unit in its technical proposal. AR Tab 48 at 1321. Given
    this, the record evidence in this matter shows that the Navy reasonably determined that
    Hamilton’s final proposal revision was technically acceptable and responsive to the RFP.5
    5
    Treadwell’s reliance upon the United States Government Accountability Office’s (“GAO”) decision in
    Alerting Communicators of America, B-236253, 89-2 CPD ¶ 438 (Comp. Gen. Nov. 7, 1989), is also
    misplaced. Pl. Mot. at 22-23. In that case, the GAO determined that the government properly concluded
    that the protestor’s bid was unresponsive because the bid did not commit to the delivery schedule set forth
    in the invitation for bids. Alerting Communicators of Am., B-236253, 89-2 CPD ¶ 438, at *1 (Comp.
    Gen. Nov. 7, 1989). But, in this case, the administrative record shows Hamilton did agree to meet the
    RFP’s delivery schedule—delivery of the LPE production units and LPE simulators after approval of the
    first article testing unit and beginning 15 months after the receipt of a delivery order. AR Tab 48 at 1166,
    1215. And so, Alerting Communicators does not support Treadwell’s claims.
    20
    3.      Treadwell’s Unequal Treatment Claim Is Unsubstantiated
    Treadwell also fails to show that the Navy treated offerors unequally with respect to the
    RFP’s delivery schedule requirements. In its motion for judgment upon the administrative
    record, Treadwell argues that the Navy’s decision to issue a post-award modification to the LPE
    Contract on November 2, 2016, granted “Hamilton the same schedule relief [that the Navy
    previously] denied Treadwell,” resulting in unequal treatment. Pl. Mot. at 25. Treadwell’s claim
    lacks evidentiary support.
    Contrary to Treadwell’s claims, the administrative record shows that the intent of the
    Navy’s November 2, 2016, contract modification was to clarify the due date for the delivery of
    the first LPE production units under the LPE Contract, and that this modification did not result in
    the unequal treatment of offerors. Specifically, the record evidence shows that the Navy’s post-
    award contract modification extends the delivery deadline for the first two LPE production units
    due under the LPE Contract from October 13, 2017, to November 30, 2018, and that this
    modification also clarifies that the delivery deadline for the LPE production units would be 12
    months after approval of the first article testing unit. AR Tab 55 at 1463-94; AR Tab 61 at 1513-
    45, 1545.27; AR Tab 64 at 1669. As the government explains in its cross-motion, the Navy’s
    contract modification was necessary because the Navy issued a delivery order for the first LPE
    production units “sooner than anticipated,” due to budgetary concerns. Def. Mot. at 16; AR Tab
    61 at 1541.
    The government also acknowledges that the Navy’s delivery order did not ensure that
    Hamilton would have sufficient time to comply with the RFP’s delivery schedule after first
    article testing approval, as required by the RFP and FAR 9.305 and 52.209-3. Def. Mot. at 6, 16;
    see also AR Tab 55 at 1493. Given this acknowledged error on the part of the Navy, the record
    evidence supports the government’s position that the purpose of the Navy’s November 2, 2016,
    contract modification was to correct an error, rather than to grant relief previously denied to
    Treadwell. See AR Tab 23 at 207; AR Tab 25 at 252; AR Tab 27 at 347; AR Tab 28 at 352-53.
    4.      The Navy’s Contract Modification Was Not A Cardinal Change
    Treadwell also fails to show that the Navy’s November 2, 2016, post-award contract
    modification constitutes a material or cardinal change. Treadwell argues that the Navy’s contract
    modification was a cardinal or material change—warranting re-competition of the LPE
    21
    Contract—because Treadwell could not have reasonably anticipated that the Navy would modify
    the LPE Contract to clarify the delivery due date for the LPE production units. Pl. Mot. at 26-28;
    see generally AR Tab 55; AR Tab 61. But, as the Court held in the July 19, 2017, Decision, the
    administrative record shows that the Navy’s contract modification falls well within the scope of
    the original procurement for the LPE Contract. AT&T Communications, Inc. v. Wiltel, Inc., 
    1 F.3d 1201
    , 1204-05 (Fed. Cir. 1993) (holding that “‘a cardinal change . . . occurs when the
    government effects an alteration in the work so drastic that it effectively requires the contractor
    to perform duties materially different from those originally bargained for’”) (quoting Allied
    Materials & Equip. Co. v. United States, 
    569 F.2d 562
    , 563-64 (1978)); Treadwell 
    Corp., 133 Fed. Cl. at 387
    As discussed above, the Navy’s contract modification simply clarifies the delivery due
    date for the LPE production units, thereby making clear that delivery of these units would not
    occur until after the approval of the first article testing unit. See generally AR Tab 55; AR Tab
    61 at 1513-45, 1545.27; AR Tab 64 at 1669. The administrative record also shows that the RFP
    is silent about when the Navy would issue delivery orders to establish the exact delivery dates for
    the LPE production units. AR Tab 23 at 208. Given this silence, the Navy’s contract
    modification appropriately provides this missing information.
    Because the record evidence shows that the Navy’s post-award contract modification did
    not require that Hamilton perform duties materially different than Hamilton originally bargained
    for, Treadwell has not shown that the Navy’s post-award contract modification constitutes a
    cardinal or material change to the LPE Contract.6
    C.        Treadwell Is Not Entitled To Injunctive Relief
    As a final matter, Treadwell has not demonstrated that it is entitled to the injunctive relief
    that it seeks in this matter. In its motion for judgment upon the administrative record, Treadwell
    requests that the Court, among other things, enjoin Hamilton from further performance under the
    LPE Contract. Pl. Mot. at 30-35. But, it is well-established that a plaintiff that has not actually
    succeeded upon the merits of its claims cannot prevail upon a request for injunctive relief.
    6
    Treadwell also fails to explain how it could not have been on notice that the Navy would clarify the
    precise delivery dates for the LPE production units, given that the RFP is silent about when the Navy
    would issue delivery orders for the LPE production units. See AR Tab 23 at 208.
    22
    Argencord Mach. & Equip., Inc. v. United States, 
    68 Fed. Cl. 167
    , 176 (2005). As discussed
    above, Treadwell has not prevailed upon the merits of any of its claims challenging the Navy’s
    decision to award the LPE Contract to Hamilton. And so, the Court must DENY Treadwell’s
    request for permanent injunctive relief.
    V.     CONCLUSION
    In sum, the administrative record in this matter does not support any of Treadwell’s
    challenges to the Navy’s decision to award the LPE Contract to Hamilton. Rather, the record
    evidence shows that the Navy’s award decision was reasonable and in accordance with the terms
    of the RFP and applicable law. The record evidence also does not substantiate Treadwell’s claim
    that the Navy’s post-award modification of the LPE Contract constitutes a cardinal or material
    change.
    In addition, Hamilton has shown that Treadwell improperly seeks to supplement the
    extensive administrative record in this bid protest dispute with certain information that is not
    contained in the administrative record. And so, for the foregoing reasons, the Court:
    (1)     DENIES Treadwell’s motion for judgment upon the administrative record;
    (2)     GRANTS the government’s and Hamilton’s respective cross-motions for
    judgment upon the administrative record;
    (3)     GRANTS Hamilton’s motion to strike; and
    (4)     DISMISSES the complaint.
    The Clerk shall enter judgment accordingly.
    Each party to bear their own costs.
    Some of the information contained in this Memorandum Opinion and Order may be
    considered protected information subject to the Protective Order entered in this matter on March
    2, 2017. This Memorandum Opinion and Order shall be filed UNDER SEAL. The parties shall
    review the Memorandum Opinion and Order to determine whether, in their view, any
    information should be redacted in accordance with the terms of the Protective Order prior to
    publication. After doing so, the parties shall FILE a joint status report identifying the
    information, if any, that they contend should be redacted, together with an explanation of the
    23
    basis for each proposed redaction, on or before April 15, 2019.
    IT IS SO ORDERED.
    s/ Lydia Kay Griggsby
    LYDIA KAY GRIGGSBY
    Judge
    24
    

Document Info

Docket Number: 17-287

Judges: Lydia Kay Griggsby

Filed Date: 4/12/2019

Precedential Status: Precedential

Modified Date: 4/12/2019

Authorities (20)

Information Technology & Applications Corporation v. United ... , 316 F.3d 1312 ( 2003 )

Pgba, LLC v. United States, and Wisconsin Physicians ... , 389 F.3d 1219 ( 2004 )

Honeywell, Inc. v. The United States v. Haz-Tad, Inc. , 870 F.2d 644 ( 1989 )

Blue & Gold Fleet, LP v. United States , 492 F.3d 1308 ( 2007 )

banknote-corporation-of-america-inc-and-guilford-gravure-inc-v-united , 365 F.3d 1345 ( 2004 )

Centech Group, Inc. v. United States , 554 F.3d 1029 ( 2009 )

Fmc Corporation and Monsanto Company v. The United States, ... , 3 F.3d 424 ( 1993 )

Sperry Corporation v. The United States , 845 F.2d 965 ( 1988 )

Essex Electro Engineers, Inc. v. The United States , 702 F.2d 998 ( 1983 )

Advanced Data Concepts, Incorporated v. United States , 216 F.3d 1054 ( 2000 )

Axiom Resource Management, Inc. v. United States , 564 F.3d 1374 ( 2009 )

national-steel-car-ltd-v-canadian-pacific-railway-ltd-canadian , 357 F.3d 1319 ( 2004 )

Alabama Aircraft Industries, Inc.—Birmingham v. United ... , 586 F.3d 1372 ( 2009 )

Impresa Construzioni Geom. Domenico Garufi v. United States , 238 F.3d 1324 ( 2001 )

Amoco Production Co. v. Village of Gambell , 107 S. Ct. 1396 ( 1987 )

at-t-communications-inc-and-richard-g-austin-administrator-general , 1 F.3d 1201 ( 1993 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Camp v. Pitts , 93 S. Ct. 1241 ( 1973 )

Citizens to Preserve Overton Park, Inc. v. Volpe , 91 S. Ct. 814 ( 1971 )

Califano v. Sanders , 97 S. Ct. 980 ( 1977 )

View All Authorities »