Northrop Grumman Computing Systems, Inc. v. United States , 120 Fed. Cl. 460 ( 2015 )


Menu:
  •            In the United States Court of Federal Claims
    No. 07-613C
    (Filed Under Seal: March 18, 2015)
    Reissued: April 6, 2015 1
    __________
    NORTHROP GRUMMAN                              *
    COMPUTING SYSTEMS, INC.,                      *
    * Contract; Motion for summary judgment;
    Plaintiff,                 * Software; Expectation damages; No harm
    * incurred under delivery order; No damages;
    Maintenance expenses not recoverable; Motion
    v.                                      *
    for summary judgment granted.
    *
    UNITED STATES,                                *
    *
    Defendant.
    *
    *
    __________
    OPINION
    __________
    David C. Aisenberg, Looney, Cohen, et al., Boston, MA, for plaintiff.
    Martin Mason Tomlinson, Civil Division, United States Department of Justice,
    Washington, D.C., with whom was Acting Assistant Attorney General Stuart F. Delery, for
    defendant.
    ALLEGRA, Judge:
    Plaintiff, Northrop Grumman Computing Systems, Inc. (Northrop), brings this action
    seeking damages for the alleged breach of an agreement with the Department of Homeland
    Security (DHS), Bureau of Immigration and Customs Enforcement (ICE). Under that agreement,
    Northrop leased surveillance software to ICE to be used in intercepting the internet
    communications of the targets of criminal investigations arising under Title III of the Omnibus
    Crime Control and Safe Streets Act of 1968, 18 U.S.C. § 2510, et seq. This case is pending before
    the court on defendant’s motion for summary judgment on damages. In its motion, defendant
    asseverates that Northrop has received all the compensation to which it is entitled under the
    1
    An unredacted version of this opinion was issued, under seal, on March 18, 2015. The
    opinion issued today incorporates the parties’ redactions (plaintiff did not propose any). This
    redacted material is represented by brackets [ ].
    contract at issue. Having carefully reviewed the parties’ briefs on this motion, the court holds that
    defendant is correct and it hereby GRANTS defendant’s motion.
    I.     BACKGROUND
    A brief recitation of the basic facts (many of which are stipulated) sets the context for this
    opinion.
    Sometime in 2003, ICE’s Technical Operations’ National Program Manager for Internet
    Intercept identified the agency’s need for Internet intercept software. Tech Ops’ mission is to
    provide field agents with the most innovative cutting edge electronic surveillance equipment and
    support in furtherance of ICE investigations and national security operations. Prior to entering
    into the lease agreement below, DHS/ICE used other software to gather evidence, during a
    criminal investigation, of a subject’s internet usage. This software, however, could capture data
    only from [ ] 2 and thus could not [ ]. In 2004, DHS/ICE decided that it needed software that could
    overcome this [ ] limitation. After conducting market research, it chose Northrop’s Internet
    Observer software, also known as the Oakley software (the Oakley software). That software, [ ].
    On September 24, 2004, ICE awarded Delivery Order COW-4-D-1025 (Delivery Order) to
    Northrop pursuant to a preexisting contract between ICE and plaintiff – Contract No. NAS5–
    01143. 3 According to the Delivery Order, plaintiff was to lease the Oakley software to ICE and
    perform specific support services for a one-year base period in return for payment of $900,000,
    with three one-year options at $899,186 per option year – for a total contract price of $3,597,558 if
    all three options were exercised. 4 On September 28, 2004, ICE provided plaintiff with an
    “essential use statement” that described the intended use of the Oakley software and was designed
    to facilitate third-party funding for the Oakley software. From September 30, 2004, to October 18,
    2004, ICE executed three modifications to the Delivery Order, adding, inter alia, a first priority
    clause, a best efforts clause, and a nonsubstitution clause. On October 13, 2004, plaintiff delivered
    the Oakley software to defendant and was paid $900,000.
    2
    See Daniel Garrie & Francis Allegra, “Plugged In: Guidebook on Software and the
    Law,” § 3.3 (2013).
    3
    The Homeland Security Act of 2002, Pub. L. No. 107-296, 116 Stat. 2135 (Nov. 25,
    2002), created DHS. The Act also consolidated the United States Immigration and Naturalization
    Service and the United States Customs Service into a newly-formed Bureau of Immigration and
    Customs Enforcement, which is now known as ICE. ICE possesses its own Head of Contracting
    Activity (“HCA”), who, in turn, appoints contracting officers pursuant to agency regulations and
    the Federal Acquisition Regulation (Title 48, Code of Federal Regulations).
    4
    The $899,186 for the first option year comprised $434,451 for the software license,
    $434,451 for annual software maintenance, and $30,284 for annual server maintenance. If ICE
    had exercised the second option year, it would have paid $615,251 for the software license,
    $253,651 for annual software maintenance, and $30,284 for annual server maintenance. If ICE
    had exercised the third option year, it would have paid $502,488 for the software license and
    $396,698 for annual software maintenance.
    -2-
    To finance the agreement, Northrop relied on ESCgov, with whom Northrop had a
    preexisting Purchase and Assignment Agreement. The Purchase and Assignment Agreement
    stated that if Northrop assigned its interest in a government contract to ESCgov and that contract
    was “discontinued because of non-appropriation of funds, failure of the Government to exercise a
    renewal option under the Government Contract or termination for convenience” Northrop would
    “not be liable to ESCgov for any costs, expenses or lost profits, whatsoever,” as long as Northrop
    complied with Provision 19(a) of the agreement. Provision 19(a) provided, in relevant part: “[i]f
    ESCgov has substantial grounds for concluding that the actions taken by the U.S. Government
    constitute a sound basis for filing a claim with the Government, [Northrop] will use its best efforts
    to obtain the maximum recovery from the Government.” Northrop agreed to “diligently pursue
    such recovery” in cooperation with ESCgov. If a claim or any subsequent litigation were
    successful, Provision 19(a) provided that ESCgov would have the first right to any damages
    awarded to Northrop. But, if no money was recovered, Northrop would not have to repay ESCgov
    any amount. 5
    Consistent with the Purchase and Assignment Agreement, on October 22, 2004, ESCgov
    entered into Equipment Schedule No. 1, in which it agreed to pay Northrop $3,296,093 in
    exchange for Northrop’s assignment to ESCgov of any payments it received under the Delivery
    Order. Of this amount, ESCgov paid $2,899,710 directly to Oakley Networks for, inter alia, the
    purchase of the Oakley software licenses, “operational support hours,” and “annual maintenance.”
    Also included in the total payment under Equipment Schedule No. 1 was a payment of $191,571
    from ESCgov to Northrop, which represented Northrop’s anticipated profit for its performance
    under the Delivery Order.
    On October 22, 2004, Northrop also executed and delivered to Citizens Leasing
    Corporation, n/k/a RBS Citizens, N.A. (Citizens) a Consent to Assignment agreeing to ESCgov’s
    plan to assign its rights under Equipment Schedule No. 1 to Citizens. On October 25, 2004,
    Northrop executed an Instrument of Assignment assigning its rights and interests to any payments
    from the United States under the Delivery Order to Citizens. On November 19, 2004, ESCgov
    executed an Assignment Agreement assigning its rights under Equipment Schedule No. 1 to
    Citizens in exchange for $3,325,252.16.
    On September 30, 2005, ICE informed plaintiff that it would not exercise the first one-year
    option due to a lack of funds. On September 21, 2006, Northrop filed a claim with the contracting
    officer pursuant to the Contract Disputes Act of 1978 (the CDA), 41 U.S.C. § 601, et seq. (current
    version at 41 U.S.C. § 7101, et seq.):
    5
    Equipment Schedule No. 1 further specified that if the contracting officer denied a claim
    and Northrop elected not to pursue an appeal, Northrop would have to pay ESCgov the discounted
    balance of the contract. However, if Northrop did pursue an appeal, “such suit . . . would be
    sponsored by and brought in the name of [Northrop], with [ESCgov] responsible for costs of such
    appeal.”
    -3-
    to recover damages resulting from the Government’s breach of the provisions of
    the [Delivery Order] by failing to use best efforts to seek and utilize available
    funding from all sources, by failing to reserve funds from the annual budget on a
    first priority designation, and by replacing the software with another system
    performing similar or comparable functions.
    The claim requested damages of $2,697,558, because defendant’s breach of contract entitled “a
    contractor to be placed in as good a position as it would have had the breach not been committed
    by the Government.” Alternatively, Northrop asserted that “if the Government’s breaches of the
    Contract are found to constitute a Termination for Convenience, the amount of . . . damages owed
    by the Government would be $2,674,032.80.” A Northrop official certified that the claim was
    “made in good faith,” “accurate and complete” and stated an accurate damages amount for which
    defendant was liable. The claim did not mention ESCgov, Citizens or any of the aforementioned
    assignments. On December 29, 2006, the contracting officer denied this claim.
    On August 20, 2007, Northrop filed a complaint in this court, asserting that defendant
    breached the Delivery Order by failing to seek funding and exercise the options. The complaint
    averred that, as a result of this breach, “Northrop Grumman is entitled to recover its damages as
    described in the contract, including the payments not made under the Contract in the amount of
    $2,697,558.00, plus interest.” On May 20, 2010, the parties’ cross-motions for summary
    judgment were denied, and after supplemental discovery, trial was scheduled to begin on June 13,
    2011. On May 13, 2011, defendant filed a motion to dismiss for lack of jurisdiction pursuant to
    RCFC 12(b)(1), asserting that Northrop had submitted a claim to the contracting officer that failed
    to provide adequate notice of the nature of the claim and to reveal that the claim was for the losses
    of a third party. On May 27, 2011, plaintiff filed its response, and on June 2, 2011, defendant filed
    its reply. On June 3, 2011, the court cancelled the aforementioned trial.
    On June 15, 2011, the court granted defendant’s motion to dismiss, finding that although
    Northrop was the proper party to bring the claim, its letter to the contracting officer did not
    provide adequate notice of the basis of its claim. Northrop Grumman Computing Sys., Inc. v.
    United States, 
    99 Fed. Cl. 651
    (2011). On July 20, 2011, plaintiff submitted a new claim to the
    contracting officer that did include information on the assignments. On August 23, 2011,
    Northrop appealed this court’s dismissal order. On September 16, 2011, the contracting officer
    purported to deny plaintiff’s second claim. On September 21, 2011, plaintiff filed a new
    complaint (Case No. 11-608) challenging the second denied claim. On November 16, 2011, this
    court granted defendant’s motion to dismiss the second complaint. Northrop Grumman
    Computing Sys., Inc. v. United States, 
    101 Fed. Cl. 362
    (2011). On January 10, 2012, Northrop
    appealed that dismissal order.
    On February 19, 2013, the Court of Appeals for the Federal Circuit issued an opinion
    addressing both of plaintiff’s appeals. Northrop Grumman Computing Sys., Inc. v. United States,
    
    709 F.3d 1107
    (Fed. Cir. 2013) (Northrop Grumman II). The Federal Circuit agreed with this
    court’s determination that the assignment from Northrop to ESCgov was not valid under the Anti-
    Assignment Act, 31 U.S.C. § 3727, 41 U.S.C. § 15, and therefore Northrop was the proper party to
    bring this claim. 
    Id. at 1113.
    However, it reversed this court’s dismissal of this case, finding that
    -4-
    the plaintiff did properly file a claim with the contracting officer. 
    Id. The Federal
    Circuit also
    held that the appeal on Northrop’s second claim was moot, since the court had jurisdiction over
    the original claim. 
    Id. After the
    case was remanded, the parties filed a joint status report in this court, in which
    defendant expressed its intention to file a motion for summary judgment on damages. On October
    1, 2013, defendant filed a motion for summary judgment. Subsequent briefing on this motion has
    been completed. Oral argument was held on May 7, 2014.
    II.    DISCUSSION
    We begin with common ground. Summary judgment is appropriate when there is no
    genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of
    law. See RCFC 56; Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-48 (1986); Biery v. United
    States, 
    753 F.3d 1279
    , 1286 (Fed. Cir. 2014). Disputes over facts that are not outcome-
    determinative will not preclude the entry of summary judgment. 
    Anderson, 477 U.S. at 248
    .
    However, summary judgment will not be granted if “the dispute about a material fact is ‘genuine,’
    that is, if the evidence is such that a reasonable [trier of fact] could return a verdict for the
    nonmoving party.” Id.; see also Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587 (1986); 
    Biery, 753 F.3d at 1286
    ; Principal Life Ins. Co. & Subs. v. United States, 
    116 Fed. Cl. 82
    , 88-89 (2014); Becho, Inc. v. United States, 
    47 Fed. Cl. 595
    , 599 (2000).
    When making a summary judgment determination, the court is not to weigh the evidence,
    but to “determine whether there is a genuine issue for trial.” 
    Anderson, 477 U.S. at 249
    ; see also
    Agosto v. INS, 
    436 U.S. 748
    , 756 (1978) (“a [trial] court generally cannot grant summary
    judgment based on its assessment of the credibility of the evidence presented”); Am. Ins. Co. v.
    United States, 
    62 Fed. Cl. 151
    , 154 (2004). The court must determine whether the evidence
    presents a disagreement sufficient to require fact finding, or, conversely, is so one-sided that one
    party must prevail as a matter of law. 
    Anderson, 477 U.S. at 251-52
    ; see also Ricci v. DeStefano,
    
    557 U.S. 557
    , 586 (2009) (“‘Where the record taken as a whole could not lead a rational trier of
    fact to find for the nonmoving party, there is no genuine issue for trial.’” (quoting 
    Matsushita, 475 U.S. at 587
    )). Where there is a genuine dispute, all facts must be construed, and all inferences
    drawn from the evidence must be viewed, in the light most favorable to the party opposing the
    motion. 
    Matsushita, 475 U.S. at 587
    -88 (citing United States v. Diebold, Inc., 
    369 U.S. 654
    , 655
    (1962)); see also Principal Life Ins. Co. v. United States, 
    2015 WL 461558
    , at *7-8 (Fed. Cl.
    Feb. 4, 2015); Stovall v. United States, 
    94 Fed. Cl. 336
    , 344 (2010); L.P. Consulting Grp., Inc. v.
    United States, 
    66 Fed. Cl. 238
    , 240 (2005).
    As a preliminary matter, the court rejects plaintiff’s assertion that defendant’s summary
    judgment motion is untimely. Per contra. Key facts underlying Northrop’s claims were not
    disclosed by the latter during the extended discovery in this case. For example, plaintiff’s initial
    disclosures and 2009 summary judgment motion did not reveal that it had received financing, let
    alone the details of the assignments to ESCgov and Citizens – even though discovery plainly
    should have revealed those details. Instead, the financing documents, and any details regarding
    -5-
    the specific arrangements, were not disclosed by plaintiff until March 7, 2011, several years after
    discovery was completed. That hardly gives plaintiff any basis to complain. 6
    In Northrop Grumman II, the Federal Circuit found it had jurisdiction over Northrop’s
    claim even though plaintiff failed to notify defendant it had assigned its 
    rights. 709 F.3d at 1110
    ,
    1113. Rather than treating that claim as waived, the Federal Circuit held that the contractor’s
    assignment was nullified, leaving plaintiff as if there was no assignment. 
    Id. at 1113.
    But, the
    Federal Circuit certainly did not suggest that Northrop should also be immunized from any
    arguments that defendant could have raised had Northrop met its discovery obligations, as
    required by this court’s orders. Plaintiff thus should not be heard to complain that defendant is
    receiving a second or third bite at the apple, when, in fact, plaintiff sought to deny defendant its
    due in the first instance, as required by the rules. Cf. Eminence Capital, LLC v. Aspeon, Inc., 
    316 F.3d 1048
    , 1053-54 (9th Cir. 2003) (Reinhardt, J., concurring) (citation omitted) (“A cliché like
    ‘three bites at the apple’ provides a formalistic rule that does not account for the particularities of
    an individual case.”).
    This leads us to defendant’s banner claim – that plaintiff has not proven that any damages
    are owed. Defendant asserts that the undisputed facts show that Northrop has received all the
    compensation to which it is owed pursuant to the Delivery Order – that plaintiff is not entitled to
    any further expectancy damages based on its claim. Defendant is correct.
    Expectation damages give the injured party “the benefits [it] expected to receive had the
    breach not occurred.” Glendale Fed. Bank, FSB v. United States, 
    239 F.3d 1374
    , 1380 (Fed. Cir.
    2001); see also Fifth Third Bank v. United States, 
    518 F.3d 1368
    , 1374 (Fed. Cir. 2008). 7
    Conversely, “[i]t is . . . axiomatic that ‘the non-breaching party should not be placed in a better
    position through the award of expectancy damages than if there had been no breach.” Cuyahoga
    Metro. Hous. Auth. v. United States, 
    65 Fed. Cl. 534
    , 543 (2005) (quoting Bluebonnet Sav. Bank,
    FSB v. United States, 
    339 F.3d 1341
    , 1345 (Fed. Cir. 2003)); see also Repub. Sav. Bank FSB v.
    United States, 
    584 F.3d 1369
    , 1378-79 (Fed. Cir. 2009). The Federal Circuit has further
    elucidated – “[t]he benefits that were expected from the contract, ‘expectancy damages,’ are often
    equated with lost profits, although they can include other damage elements as well.” 
    Glendale, 239 F.3d at 1380
    (citing Restatement (Second) of Contracts, § 347); see also Energy Capital
    Corp. v. United States, 
    302 F.3d 1314
    , 1330 (Fed. Cir. 2002). As such, “[e]xpectation damages
    6
    Indeed, contrary to plaintiff’s claims, a decent case can be made that plaintiff should be
    liable for sanctions under RCFC 37(c)(1) for discovery violations or under RCFC 16 for plaintiff’s
    violation of this court’s discovery and pretrial order. See Pyramid Real Estate Servs., LLC v. United
    States, 
    95 Fed. Cl. 613
    , 622 (2010); Multiservice Jt. Venture, LLC v. United States, 
    85 Fed. Cl. 106
    , 112 (2008); Pac. Gas & Elec. Co. v. United States, 
    82 Fed. Cl. 474
    , 479-80 (2008).
    7
    Similar views are expressed in the Restatement (Second) of Contracts, § 347, cmt. a
    (1981): “Contract damages are ordinarily based on the injured party’s expectation interest and are
    intended to give him the benefit of his bargain by awarding him a sum of money that will, to the
    extent possible, put him in as good a position as he would have been in had the contract been
    performed.” See also Park Props. Assocs. v. United States, 
    82 Fed. Cl. 162
    , 167 n.6 (2008).
    -6-
    are recoverable provided they are ‘actually foreseen or reasonably foreseeable, are caused by the
    breach of the promisor, and are proved with reasonable certainty.’” Nat. Australia Bank v. United
    States, 
    63 Fed. Cl. 352
    , 355 (2004), aff’d in part, rev’d in part on other grounds, 
    452 F.3d 1321
    (Fed. Cir. 2006) (quoting Bluebonnet Sav. Bank, FSB v. United States, 
    266 F.3d 1348
    , 1355 (Fed.
    Cir. 2001)); see also North Star Alaska Housing Corp. v. United States, 
    76 Fed. Cl. 158
    , 213
    (2007); 
    Cuyahoga, 65 Fed. Cl. at 543
    .
    The goal of contract damages thus is “to put the injured party in as good a position as that
    party would have been in if performance had been rendered as promised.” 11 Corbin on Contracts
    § 55.3 (rev. ed. 2009); see also Greenhill v. United States, 
    92 Fed. Cl. 385
    , 399 (2010); Anchor
    Sav. Bank, FSB v. United States, 
    81 Fed. Cl. 1
    , 85-86 (2008). It is not to provide the contracting
    party with a windfall. Plaintiff seeks the latter – it seeks expectation damages that exceed the
    amount that defendant was obliged to pay under the contract. ESCgov expressly agreed to pay
    Northrop $3,296,093 for which Northrop agreed to assign the rights of all payments it received
    from ICE under the Delivery Order. There is no dispute that this amount was, in fact, paid to
    Northrop by ESCgov. The contract between ESCgov and Northrop further makes clear that if
    defendant were to terminate the contract for convenience or declined to exercise a renewal option,
    Northrop was not liable for costs, expenses, lost profits or other damages incurred or suffered by
    ESCgov. Northrop was paid the amount it expected to be paid for its performance under the
    Delivery Order. It is unable to identify any way that it, as opposed to ESCgov or Citizens, was
    harmed by defendant’s actions. 8
    Plaintiff, however, argues that defendant is seeking a windfall – that plaintiff was harmed
    because defendant did not make payments for the three unexercised option years under the
    Delivery Order. But, there is no indication that, under the contract terms, plaintiff was entitled to
    receive those payments. Contrary to plaintiff’s claims, ICE paid in full for the one year it had the
    license for the software in question, and did not use the software thereafter. Had ICE exercised all
    three options, Northrop would not have received any further payments – those payments had been
    assigned to ESCgov. ESCgov’s payment of $191,571 represented Northrop’s anticipated profit
    for its anticipated performance under the Delivery Order. And Northrop, indeed, received that
    payment from its finance company, ESCgov. Northrop reaped the benefit of the bargain it
    negotiated – it is entitled to nothing more from defendant. See Int’l Data Prods. Corp. v. United
    States, 
    492 F.3d 1317
    , 1324 (Fed. Cir. 2007). 9
    8
    Northrop asseverates that the payments it received from its finance company should not
    be treated as payments for Northrop’s performance pursuant to the Delivery Order. It asserts,
    instead, that “[i]t is entitled to proceed to trial to prove its breach of contract and breach of
    warranty claims and seek damages in the principal amount of $2,697,558 for the amounts that the
    Government failed to pay.” The amount cited by plaintiff represents the sum of the three
    payments defendant would have made if it exercised the three option years. The problem is, what
    plaintiff seeks is not a figure to which it is entitled.
    9
    Plaintiff repeatedly asserts that it was harmed solely because defendant did not make
    payments for the three unexercised option years. See, e.g., Plaintiff’s Responding Brief at 14
    (“The Government’s arguments are also misguided because they focus on how much money
    -7-
    Likewise, plaintiff is not entitled to any damages associated with software and server
    maintenance beyond that which the Delivery Order required for the base year. Fundamentally,
    Northrop cannot recover damages for any software and server maintenance work that was not
    performed under the Delivery Order – software and server maintenance that was unnecessary in
    the out-years based on ICE’s decision not to exercise the first option. “The contractor may not
    recover for work not performed.” H.B. Nelson Constr. Co. v. United States, 
    87 Ct. Cl. 375
    , 385
    (1938), cert. denied, 
    306 U.S. 661
    (1939). This court cannot permit otherwise.
    III.   CONCLUSION
    The court will not gild the lily. The court concludes, as a matter of law on essentially
    undisputed facts, that defendant has demonstrated that plaintiff is not entitled to any damages
    under the Delivery Order in question or otherwise. Accordingly, the court GRANTS defendant’s
    motion for summary judgment. The Clerk shall dismiss plaintiff’s complaint.
    IT IS SO ORDERED. 10
    s/Francis M. Allegra
    Francis M. Allegra
    Judge
    Northrop Grumman has received and what obligations it has to parties other than the Government,
    rather than who made the payment and why.”). But, like Ol’ Dobbins, Northrop seemingly dons
    blinders as to whom was entitled to receive such payments – and from the fact that there is no
    indication that it was actually harmed in any way, shape or form by defendant’s decision not to
    exercise its options.
    10
    The court intends to unseal and publish this opinion after April 3, 2015. On or before
    April 3, 2015, each party shall file proposed redactions to this opinion, with specific reasons
    therefor.
    -8-