Caddell Construction Co., LLC v. United States , 120 Fed. Cl. 724 ( 2015 )


Menu:
  •                      United States Court of Federal Claims
    Nos. 15-135 C
    15-136 C
    (Filed Under Seal April 10, 2015)
    Reissued April 14, 2015 1
    CADDELL CONSTRUCTION                          )
    CO., LLC,                                     )   Pre-Award    Protest; Jurisdiction;
    Plaintiff,                    )   Competition in Contracting Act;
    v.                                  )   Override of Stay in Effect During
    )   Pending GAO Protest.
    THE UNITED STATES,                            )
    Defendant.      )
    Dirk Haire, Fox Rothschild LLP, Washington, DC, for plaintiff. Alexa
    Santora and Sonia Tabriz, of counsel.
    Albert S. Iarossi, Commercial Litigation Branch, Civil Division, United States
    Department of Justice, Washington, D.C., with whom appeared Benjamin C. Mizer,
    Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director and Allison
    Kidd-Miller, Assistant Director.
    ORDER
    Merow, Senior Judge
    Plaintiff filed two bid protests on February 10, 2015. The cases have been
    consolidated for consideration of preliminary matters, including the government’s
    challenge to this court’s jurisdiction. See Doc. 11. 2 On April 1, 2015, the parties
    argued their positions on the plaintiff’s motions for judgment on the administrative
    record, see Doc. 16, and the government’s motions to dismiss for lack of jurisdiction,
    see Doc. 19.
    1
    Reissued without redactions pursuant to defendant’s notice, doc. 25, filed April 14, 2015.
    2
    The relevant filings in this case are virtually identical. For ease of reference, the court will cite
    to the documents filed in Case No. 1:15-cv-135.
    I.    BACKGROUND
    Plaintiff is one of several bidders for a contract to construct embassy facilities
    in Maputo, Mozambique. See Doc. 1, ¶ 10. Prior to filing the protest action in this
    court, plaintiff filed two protests before the GAO, challenging the pre-qualification
    of two of its competitors for the contract award. See Doc. 16-1 at 5. The GAO’s
    decisions are expected on or about April 20, 2015, see Doc. 16-1 at 7, and the merits
    of the GAO protests are not before this court. The plaintiff filed these actions
    alleging that the government violated its duty to stay the contracting process
    pursuant to the Competition in Contracting Act (“CICA”) while the GAO protests
    are pending, and that its failure to stay the contracting process amounted to an
    unlawful override. See 31 U.S.C. 3553(c)(1)-(2) (prohibiting agencies from
    awarding contracts during the pendency of a GAO protest unless certain
    requirements are met).
    The complaint states:
    29.    The Agency Report admits that the Protest “triggers the stay on
    contract award provided by 31 U.S.C. 3553(c)(1)” but further
    provides that the solicitation “will continue as scheduled without
    regard to the protest.”
    30.    Although unclear, it appears that this constitutes OBO’s
    [Overseas Buildings Operations’] decision to override the
    mandatory CICA stay.
    See Doc. 1.
    The government admits that it has continued to evaluate proposals despite the
    GAO protests, but denies that it has taken any action that violates CICA or that its
    conduct constitutes an override. See Doc. 19 at 11.
    II.   ANALYSIS
    As a threshold issue, this court must determine whether it has jurisdiction to
    adjudicate plaintiff’s claims. Plaintiff bears the burden to establish subject matter
    jurisdiction by a preponderance of the evidence. See Reynolds v. Army & Air Force
    Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988). Here, the government challenges
    the factual basis for the court’s jurisdiction, as opposed to the facial sufficiency of
    the plaintiff’s jurisdictional allegations. See Doc. 19 at 13, 16. As such, the court
    2
    will take as true only the uncontroverted factual allegations, and it is not restricted
    to the face of the complaint in making its determination. See Reynolds, 846 at 747;
    see also Cedars-Sinai Med. Ctr. v. Watkins, 
    11 F.3d 1573
    , 1583-84 (Fed. Cir. 1993).
    If the court does not have jurisdiction, it must dismiss the complaint. See RCFC
    12(h)(3).
    Pursuant to 
    28 U.S.C. § 1491
    (b)(1), the Court of Federal Claims has
    jurisdiction:
    to render judgment on an action by an interested party objecting to a
    solicitation by a Federal agency for bids or proposals for a proposed
    contract or to a proposed award or the award of a contract or any alleged
    violation of statute or regulation in connection with a procurement or a
    proposed procurement.
    The Federal Circuit has held, as both parties acknowledge, that this grant of
    jurisdiction covers claims that the government violated the CICA override provision,
    
    31 U.S.C. § 3553
    (c)(2). See RAMCOR Servs. Group, Inc. v. United States, 
    185 F.3d 1286
    , 1289-90 (Fed. Cir. 1999). See also Doc. 1, ¶ 4; Doc. 19 at 9-10. The court,
    therefore, must decide whether the plaintiff has sufficiently alleged a CICA violation
    such that it has jurisdiction in this case.
    The sections of CICA relevant to this analysis are as follows:
    (c)(1) Except as provided in paragraph (2) of this subsection, a contract
    may not be awarded in any procurement after the Federal agency has
    received notice of a protest with respect to such procurement from the
    Comptroller General and while the protest is pending.
    (2) The head of the procuring activity responsible for award of a
    contract may authorize the award of the contract (notwithstanding a
    protest of which the Federal agency has notice under this section)--
    (A) upon a written finding that urgent and compelling
    circumstances which significantly affect interests of the United
    States will not permit waiting for the decision of the Comptroller
    General under this subchapter; and
    (B) after the Comptroller General is advised of that finding.
    3
    
    31 U.S.C.A. § 3553
    (c)(1) and (2).3
    Plaintiff alleges that the court has jurisdiction based on its claim that the
    government violated 
    31 U.S.C. § 3553
    (c)(2). See Doc. 1, ¶ 4. Specifically, plaintiff
    claims that the government acknowledged that a stay was in place, but announced
    its intention to continue with solicitation activities. Plaintiff cites to a report that the
    government issued on February 9, 2015, admitting that the GAO protest “triggers
    the stay on the contract award provided by 31 U.S.C. 3553(c)(1),” and stating that
    the solicitation “will continue as scheduled without regard to the protest.” Doc. 1, ¶
    29; see also Doc. 16-1 at 7 (citing AR at 118, 129). According to the plaintiff, the
    government’s statement “constitutes . . . [a] decision to override the mandatory
    CICA stay,” Doc. 1, ¶ 30, but without the proper documentation and justification,
    see 
    id. ¶¶ 35-44
    .
    In response, the government argues that this court does not have jurisdiction
    because the agency has not violated CICA’s stay or override provisions. The
    government insists that no contract has been awarded, the agency has incurred no
    obligations, no override has been instituted, and the agency has notified the GAO
    that the stay remains in place. See Doc. 19 at 11. As a basis for these assertions, the
    government submitted the Declaration of Department of State contracting officer
    Jimmy Lai. See 
    id.
     at Ex. A. Plaintiff has offered no additional evidence to counter
    Mr. Lai’s declaration.
    Plaintiff’s argument conflates the concepts of violating the CICA stay and
    instituting an override. Its position is predicated on its contention that the
    government violated the stay by continuing with the solicitation process after
    plaintiff filed its GAO protests. Plaintiff claims that violating the stay essentially
    amounts to a de facto override. See Doc. 16-1 at 9. The court is not entirely
    convinced of this logic, but because plaintiff has failed to allege sufficient facts to
    support its claim that the government violated the stay, the court need not decide
    whether a violation of the stay necessarily amounts to an override.
    CICA states that “a contract may not be awarded” while a GAO protest is
    pending. 
    31 U.S.C. § 3553
    (c)(1). Therefore, to support this court’s jurisdiction,
    even under its own theory, plaintiff must allege that a contract has been awarded. In
    3
    The court notes that although this case is pre-award, the plaintiff repeatedly cites to 
    31 U.S.C. § 3553
    (d) in the complaint, a subsection of the statute that applies to post-award contract
    performance. Because both parties have made their arguments under § 3553(c), and because
    plaintiff alleged this court’s jurisdiction under § 3553(c), the court will treat its references to §
    3553(d) as a typographical error, and address the merits of the argument.
    4
    order for a contract to be deemed awarded, the contracting officer must have signed
    and mailed the award letter. See Stebel v. United States, 
    108 Ct. Cl. 35
    , 44 (1947).
    And a binding contract does not exist until the letter is delivered. See Rhode Island
    Tool Co. v. United States, 130 Ct Cl. 698, 703 (1955). Plaintiff does not allege either
    that the government has issued an award letter here, or that one has been delivered
    to any of the bidders. Instead, it advocates for a very broad reading of the award
    prohibition, and claims the agency should be required to “declin[e] to take further
    action which will moot GAO’s ability to render recommendations.” See Doc. 16-1
    at 12. Under this reasoning, plaintiff claims, the agency’s continued solicitation
    activities should be considered a violation of the stay.
    In its briefs, though not in the complaint, plaintiff repeatedly expresses its
    belief that the agency intends to award the contract before GAO issues its decision.
    See e.g., Doc. 16-1 at 9 (“OBO’s decision to rank offerors, select an awardee, and
    move to dismiss Caddell’s GAO Protests as academic based on OBO’s intent to
    award constitutes a de facto override decision.”); 
    id.
     at 9 n.5 (“What Caddell objects
    to, and what violates CICA, is OBO’s intention to use its selection of an offeror as
    the intended awardee to convince GAO to dismiss the protests as academic.”); 
    id. at 13
     (“OBO intends to use its selection of an apparently successful offferor [sic] to
    argue that GAO lacks the ability to recommend relief.); 
    id. at 13
     (“OBO does not
    intend to ‘wait[] for the decision of the Comptroller General.’”); 
    id. at 13
     (“OBO
    intends to use its award decision to avoid a decision of the Comptroller General.”)
    (emphasis in original); 
    id. at 13
     (“Because OBO intends to take action to moot the
    GAO Protests and disturb the status quo, OBO effectively overrides the automatic
    CICA stay.”).
    Perhaps an intention to award the contract would be sufficient to establish
    jurisdiction under some set of circumstances, but plaintiff has not alleged any facts
    to support its allegation of the government’s intent beyond the agency’s statement
    that the solicitation would continue. Relying solely on this statement is problematic,
    because plaintiff has not demonstrated that continuing solicitation activities is the
    same as issuing an award letter. The court views these as distinct steps in the
    contracting process, and § 3553(c)(1) is unambiguous in prohibiting only the final
    step of awarding a contract. Furthermore, reliance on this statement is made all the
    more awkward for plaintiff’s position, since plaintiff has conceded that it “does not
    necessarily object to OBO’s continued review of offerors’ qualifications.” Doc. 16-
    1 at 9 n.5. Particularly considering this comment, plaintiff has failed to articulate
    exactly what conduct it believes is a violation of the stay.
    5
    When pressed at oral argument to identify the specific conduct to which
    plaintiff objects, plaintiff’s counsel stated that the contracting officer notified the
    GAO that its source selection process was complete on March 12, 2015, more than
    one month after plaintiff filed the complaints at issue. See Oral Argument Recording
    at 2:01PM, 2:07-2:08PM, 2:42PM, 2:46PM. She admitted, however, that this
    notification is not part of the record. See id. at 2:07PM. The government’s counsel
    denied any knowledge of the notification, see id. at 2:21PM, and notes that nothing
    in the record before the court shows that an awardee has been selected, see id. at
    2:44PM. Because it is neither part of the record nor has it been filed with the court,
    regardless of its content, this alleged notification cannot be considered as evidence
    in this case.
    Plaintiff’s theory that this court has jurisdiction because the government has
    instituted a de facto override is predicated on its allegation that the government
    violated the CICA stay. The court finds that the continued evaluation of proposals,
    the only violative conduct alleged by plaintiff, is not the same as awarding a contract,
    the only conduct that is specifically prohibited by the CICA stay provision. As such,
    plaintiff has failed to establish that this court has subject matter jurisdiction.
    III.   CONCLUSION
    For the foregoing reasons, the government’s motions to dismiss are
    GRANTED, and plaintiff’s motions for judgment on the administrative record are
    DENIED.
    SO ORDERED.
    s/James F. Merow
    James F. Merow
    Senior Judge
    6