Cardiosom, L.L.C. v. United States , 117 Fed. Cl. 526 ( 2014 )


Menu:
  •        In the United States Court of Federal Claims
    No. 08-533C
    (E-Filed: June 30, 2014)
    (Reissued: August 19, 2014)1
    )
    CARDIOSOM, L.L.C.,                                     )
    )   Cross-Motions for Summary
    Plaintiff,                        )   Judgment; RCFC 56(a); Breach of
    )   Contract; Contract Interpretation;
    v.                                                     )   Risk-Shifting Contract Language
    )
    THE UNITED STATES,                                     )
    )
    Defendant.                        )
    )
    Jerry Stouck, Washington, D.C., for plaintiff.
    Gregg M. Schwind, Senior Trial Counsel, with whom were Stuart F. Delery, Assistant
    Attorney General; Robert E. Kirschman, Jr., Director; and Steven J. Gillingham,
    Assistant Director, Commercial Litigation Branch, Civil Division, United States
    Department of Justice, Washington, D.C., for defendant.
    OPINION and ORDER
    CAMPBELL-SMITH, Chief Judge
    This is a claim for breach of contract that arises out of the government’s
    termination of plaintiff’s contract to supply durable medical equipment to Medicare
    recipients.2 See Corrected Compl. ¶¶ 22-23, ECF No. 10.
    1
    This Opinion is reissued solely to reflect the names of defendant’s current counsel.
    No other changes to the originally issued opinion have been made.
    2
    Plaintiff also has asserted a takings claim. Corrected Compl. ¶¶ 24-26, ECF No.
    10. As provided in the court’s March 26, 2012 Order, the court has deferred
    consideration of the takings claim until after it has decided the breach of contract claim.
    Order, ECF No. 63. Therefore, plaintiff’s takings claim is not addressed in this Opinion.
    Cardiosom, L.L.C. (plaintiff or Cardiosom) is a Medicare contractor. Centers for
    Medicare & Medicaid Services (CMS) of the Department of Health & Human Services
    (defendant or HHS) administers the Medicare program. Effective July 1, 2008, CMS
    contracted with Cardiosom to provide specified equipment to Medicare beneficiaries.
    On July 15, 2008, Congress passed legislation directing HHS to cancel certain
    contracts, including the subject contract in this action. It is undisputed that defendant
    terminated plaintiff’s contract. What is disputed is whether defendant’s termination of
    plaintiff’s contract amounts to a breach.
    Defendant argues that certain language in the contract shifted the risk of regulatory
    change to Cardiosom. Defendant adds that because Cardiosom accepted the risk that its
    contract could be terminated by a change in the governing statute, it cannot maintain the
    instant action for breach of contract.
    Plaintiff counters that the contract language on which defendant relies states only
    that plaintiff was required to comply with relevant statutes and regulations. Plaintiff
    insists that nothing in the referenced contractual language precludes it from maintaining a
    breach of contract claim. Plaintiff adds that accepting defendant’s characterization of the
    contract language would render the contract illusory because defendant could terminate
    the contract at will, with no further obligation to plaintiff. Such a reading, plaintiff
    asserts, must be rejected.
    Pending before the court is plaintiff’s motion for summary judgment on contract
    liability, and defendant’s cross-motion for summary judgment on contract liability. Both
    motions are ripe for consideration. Oral argument was neither requested by the parties
    nor deemed necessary by the court. For the reasons explained below, plaintiff’s motion
    for summary judgment is GRANTED, and defendant’s cross-motion for summary
    judgment is DENIED.
    I.     Background
    Plaintiff filed this claim on July 22, 2008. Compl., ECF No. 1. On July 24, 2009,
    plaintiff moved for summary judgment on contract liability. Pl.’s Mot., ECF No. 36.
    Defendant filed a cross-motion on summary judgment on September 15, 2009. Def.’s
    Mot., ECF No. 41. Plaintiff and defendant each filed reply briefs. Pl.’s Reply, ECF No.
    44. Def.’s Reply, ECF No. 45. In addition, the parties filed a Consolidated Statement of
    Uncontroverted Facts on November 16, 2009. ECF No. 46 (Fact Stmt.). Plaintiff also
    filed the declaration of Kevin P. Greisl, President of Cardiosom, which is incorporated by
    reference in the Consolidated Statement of Uncontroverted Facts. ECF No. 37-1 (Greisl
    2
    Decl.). The contract at issue is included as Exhibit A to the Greisl declaration, and the
    contract termination letter CMS sent to Cardiosom is included as Exhibit B to the Greisl
    declaration. Greisl Decl. Exs. A, B.
    The facts of this case regarding contract termination are not in dispute. A detailed
    recitation of these facts has been set forth in previous decisions of both the Federal
    Circuit and this court. See Cardiosom, L.L.C. v. United States, 
    656 F.3d 1322
     (Fed. Cir.
    2011) (finding that the immunity provision in MIPPA did not manifest an unambiguous
    intent to withdraw the Tucker Act’s waiver of sovereign immunity), rev’g 
    91 Fed. Cl. 659
     (2010); Cardiosom, L.L.C. v. United States, 
    115 Fed. Cl. 761
     (2014) (finding that
    neither MIPPA nor the interpreting regulations precluded plaintiff from proceeding with
    its Tucker Act breach of contract claim). These decisions, however, did not address
    contract liability. For ease of reference, a brief review of the pertinent facts follows.
    In April 2007, CMS issued a final rule establishing a Competitive Acquisition
    Program (CAP) for the supply of Durable Medical Equipment, Orthotics and Supplies
    (DMEPOS) to Medicare beneficiaries in specified areas. Fact Stmt. ¶ 2. In July 2007,
    Cardiosom submitted a bid to CMS for what was known as Round 1 of the CAP. Id. at
    ¶ 3. On March 21, 2008, CMS notified Cardiosom that it was a successful bidder. Id. at
    ¶ 4.
    Under the terms of the contract, which became effective on July 1, 2008,
    Cardiosom agreed to provide, on CMS’s behalf, oxygen and/or respiratory equipment and
    supplies in nine different metropolitan areas for a period of three years. Id. at ¶¶ 1, 4.
    Two weeks later, on July 15, 2008, Congress passed legislation terminating all contracts,
    that had been issued under the Round 1 contracting process. Medicare Improvements for
    Patients and Providers Act of 2008 (MIPPA) § 154, 42 U.S.C. § 1395w-3(a)(1) (2012).
    Plaintiff’s contract with CMS was among those terminated. Fact Stmt. ¶ 6.
    After filing its complaint in this court in 2008, plaintiff sought damages through an
    administrative process established by CMS for contractors, like Cardiosom, whose
    contracts were terminated after the passage of MIPPA. See Pl.’s Second Supp. Br.3 Ex.
    A, ECF No. 69, at 40-43. Cardiosom received partial payment on its administrative
    claim. Pl.’s Second Supp. Br. Ex. B, ECF No. 69, at 47.
    3
    In May 2012, Cardiosom filed additional briefing at the request of the court. See
    Pl.’s Second Supp. Br., ECF No. 69.
    3
    II.    Legal Standards
    A.     Jurisdiction
    The Tucker Act confers upon the Court of Federal Claims jurisdiction to “render
    judgment upon any claim against the United States founded . . . upon any express or
    implied contract with the United States.” 
    28 U.S.C. § 1491
    (a)(1)(2012). It does not,
    however, “create any substantive right enforceable against the United States for money
    damages.” United States v. Testan, 
    424 U.S. 392
    , 398 (1976). Instead, the right to
    money damages must be found in a separate source of law. See Loveladies Harbor, Inc.
    v. United States, 
    27 F.3d 1545
    , 1554 (Fed. Cir. 1994) (en banc). “[I]n a contract case, the
    money-mandating requirement for Tucker Act jurisdiction normally is satisfied by the
    presumption that money damages are available for breach of contract, with no further
    inquiry being necessary.” Holmes v. United States, 
    657 F.3d 1303
    , 1314 (Fed. Cir.
    2011).
    B.     Summary Judgment
    Summary judgment is appropriate “if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    RCFC 56(a); see Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-48 (1986); Celotex
    Corp. v. Catrett, 
    477 U.S. 317
    , 322-23 (1986). A genuine dispute is one that “may
    reasonably be resolved in favor of either party.” Liberty Lobby, 
    477 U.S. at 250
    . A fact
    is “material” if it “might affect the outcome of the suit.” 
    Id. at 248
    . The moving party
    carries the burden of establishing its entitlement to summary judgment. Celotex Corp. v.
    Catrett, 
    477 U.S. 317
    , 322-23 (1986). Once that burden is met, the onus shifts to the non-
    movant to identify evidence demonstrating a dispute over a material fact that would allow
    a reasonable finder of fact to rule in its favor. Liberty Lobby, 
    477 U.S. at 256
    .
    In considering a motion for summary judgment, the court does not weigh each
    side’s evidence but, rather, must draw all inferences in the light most favorable to the
    nonmoving party. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587-
    88 (1986). Where, as here, the parties have filed cross-motions for summary judgment,
    the court evaluates each motion on its own merits and makes all reasonable inferences
    against the party whose motion is under consideration. Marriot Int’l Resorts, L.P. v.
    United States, 
    586 F.3d 962
    , 968-69 (Fed. Cir. 2009). To the extent there exists a
    genuine issue of material fact, both motions must be denied. Id. at 969.
    4
    C.     Breach of Contract
    The “[f]ailure to perform a contractual duty when it is due is a breach of the
    contract.” Winstar Corp. v United States, 
    64 F.3d 1531
    , 1545 (Fed. Cir. 1995) (citing
    Restatement (Second) of Contracts § 235(2) (1981)).
    “To recover for breach of contract, a party must allege and establish: (1) a valid
    contract between the parties, (2) an obligation or duty arising out of the contract, (3) a
    breach of that duty, and (4) damages caused by the breach.” San Carlos Irrigation &
    Drainage Dist. v. United States, 
    877 F.2d 957
    , 959 (Fed. Cir. 1989).
    D.     Contract Interpretation
    Determining the obligation or duty that arises out of a contract “is a legal question
    of contract interpretation,” 
    id.,
     and contract interpretation is “generally amenable to
    summary judgment,” Varilease Tech. Grp., Inc. v. United States, 
    289 F.3d 795
    , 798 (Fed.
    Cir. 2002). The general rules of contract interpretation apply to contracts into which the
    government has entered as a party. Lockheed Martin IR Imaging Sys. v. West, 
    108 F.3d 319
    , 322 (Fed. Cir. 1997).
    It is “a fundamental precept of common law that the intention of the parties to a
    contract controls its interpretation.” Tri-Star Elecs. Int’l, Inc. v. Preci-Dip Durtal SA,
    
    619 F.3d 1364
    , 1367 (Fed. Cir. 2010) (internal quotation marks omitted); see also Padilla
    v. United States, 
    58 Fed. Cl. 585
    , 591 (2003) (“When interpreting disputed contractual
    provisions, the primary objective for the court is to determine the intent of the parties to
    the contract at the time they contracted.”). The intention of the parties is gathered from
    the four corners of the contract. See Mktg. & Mgmt. Info., Inc. v. United States, 
    57 Fed. Cl. 665
    , 674 (2003) (“The parties’ respective rights and responsibilities would normally
    be found only within the four corners of the contract.”).
    In interpreting a contract, we begin with the plain language of the contract. C.
    Sanchez & Son, Inc. v. United States, 
    6 F.3d 1539
    , 1543 (Fed. Cir. 1993) (“A contract is
    read in accordance with its express terms and the plain meaning thereof.”). “We give the
    words of the agreement their ordinary meaning unless the parties mutually intended and
    agreed to an alternative meaning.” Harris v. Dep’t of Veterans Affairs, 
    142 F.3d 1463
    ,
    1467 (Fed. Cir. 1998). The plain language of the contract “must be given that meaning
    that would be derived from the contract by a reasonably intelligent person acquainted
    with the contemporaneous circumstances.” TEG-Paradigm Envtl., Inc. v. United States,
    
    465 F.3d 1329
    , 1338 (Fed. Cir. 2006) (internal quotation marks omitted).
    5
    When interpreting the plain language of a contract, the “contract must be
    interpreted when possible as a whole in a manner which gives reasonable meaning to all
    its parts and avoids conflict or surplusage of its provisions.” Granite Constr. Co. v.
    United States, 
    962 F.2d 998
    , 1003 (Fed. Cir. 1992). “A reasonable interpretation must
    ‘assure that no contract provision is made inconsistent, superfluous, or redundant.”’
    Medlin Const. Group, Ltd. v. Harvey, 
    449 F.3d 1195
    , 1200 (Fed. Cir. 2006) (quoting
    Lockheed Martin, 
    108 F.3d at 322
    ).
    III.   Discussion
    The court considers whether plaintiff has satisfied the required showing for a
    breach of contract claim and if so, whether defendant has provided a valid defense.
    A.     Plaintiff’s Breach of Contract Claim
    It is undisputed that a valid contract existed between the parties. See Fact Stmt.
    ¶ 5 (“On June 20, 2008, CMS and CardioSom executed a ‘Medicare Durable Medical
    Equipment, Prosthetics, Ortohotics, and Supplies (DMEPOS) Competitive Bidding
    Program Contract.”’); Greisl Decl. Ex. A (contract).
    It is also undisputed that defendant cancelled Cardiosom’s contract effective June
    30, 2008 and thus, failed to perform its duties. See Fact Stmt. ¶ 7 (“CMS notified
    CardiSom of the termination of its contract by letter dated July 21, 2008 . . . .”). In its
    July 21, 2008 letter, CMS told Cardiosom that in accordance with 42 U.S.C. § 1395w-
    3(a)(1), Cardiosom’s contract was “completely terminated effective June 20, 2008.”
    Greisl Decl. Ex. B.
    Plaintiff asserts that it was harmed by the contract termination. Fact Stmt. ¶¶ 8,
    10. Defendant objects to plaintiff’s asserted damages, “[on] the grounds that it is based
    entirely upon the declaration of plaintiff’s principal, and there is no independent evidence
    in the contemporaneous record to support it. Absent such evidence, defendant [claims it]
    is unable at this time to either confirm or refute the accuracy of [the damages] statement.”
    Id.
    Plaintiff contends, that in fact, it “incurred expenses in reliance on the Agreement
    [with CMS] and suffered damages, as set forth in the accompanying declaration of its
    President,” Kevin P. Greisl. Pl.’s Mot. 28 (citing Greisl Decl. ¶¶ 9,10, 14, 15). Mr.
    Greisl declared that CMS notified Cardiosom on March 21, 2008 that it was a successful
    bidder in nine areas in which it had submitted bids, and “awarded CardioSom the right to
    . . . qualified supplier [status] for a three-year term beginning on July 1, 2008.” Greisl
    Decl. ¶ 6. Based on this received notice, “[b]etween March 21, 2008 and July 1, 2008,
    6
    CardioSom incurred significant out of pocket expenses and liabilities in preparing to
    perform its obligations under the Agreement.” Greisl Decl. ¶ 9; Fact Stmt. ¶ 8. Mr.
    Greisl further declared that Cardiosom’s additional damages include the “lost . . . profits
    it would have earned as a contract supplier during the 3-year term” of the terminated
    contract. Greisl Decl. ¶ 15; see also Fact Stmt. ¶ 10.
    Plaintiff later filed a detailed explanation of the damages request it submitted to
    CMS in March 2010, including, inter alia, its termination wages and expenses, as well as
    rent and utility costs it incurred for its new sites. Pl.’s Supp. Br. Ex. A, at 40-43. CMS
    reimbursed Cardiosom for a portion of these termination expenses in August 2011. Pl.’s
    Supp. Br. Ex. B, at 47.
    The “[f]ailure to perform a contractual duty when it is due [constitutes] a breach of
    the contract.” Winstar Corp. v United States, 
    64 F.3d 1531
    , 1545 (Fed. Cir. 1995). The
    court finds that plaintiff has shown that it had a valid contract with CMS, that CMS had a
    duty under that contract and that in terminating Cardiosom’s contract, CMS breached that
    duty. The court also finds that Cardiosom has provided sufficient evidence that it
    incurred damages attributable to the contract termination to satisfy its breach of contract.
    Plaintiff has established its breach of contract claim and thereby, has proven
    defendant’s contract liability.
    B.     Defendant’s Risk-Shifting Defense
    Urging that the disputed contract language precludes a finding of breach,
    defendant puts forward a defense to plaintiff’s claim. Def.’s Mot. 32 (stating that
    Cardiosom’s attempts to rebut its argument that the contract language is “a valid defense
    against [Cardiosom’s] claim of breach . . . are of no moment.”). The question for the
    court is whether defendant has presented a valid defense. The burden to prove such a
    defense rests with defendant, see Brunswick Bank & Trust Co. v. United States, 
    707 F.2d 1355
    , 1360 (Fed. Cir. 1983); Eden Isle Marina, Inc. v. United States, 
    89 Fed. Cl. 480
    , 523
    (2009), and defendant must prove its defense by a preponderance of the evidence, see
    Thomas v. Nicholson, 
    423 F.3d 1279
    , 1283 (Fed. Cir. 2005).
    Defendant’s particular burden is to show that the disputed contract language,
    Article II.D of the contract, when read in the context of this court’s contract interpretation
    case law, see supra Part II.D, is read correctly as risk-shifting language.
    Risk-shifting language refers to contractual language that shifts the risk of
    regulatory change from the government to the contractor. The risk of regulatory change
    7
    refers to the risk that Congress might pass a new statute, or an agency might promulgate a
    new regulation, that would prevent the agency from meeting its obligations, as promised
    under an existing contract with a private party. See generally United States v. Winstar
    Corp., 
    518 U.S. 839
    , 881 (1996). The risk of regulatory change rests with the agency,
    because it would be the agency that could not perform its promise and would be in breach
    and thus liable for damages. “Winstar stands for the proposition that the government is
    still obligated to honor its contracts even if the governing regulations change,” preventing
    its performance. Admiral Fin. Corp. v. United States, 
    378 F.3d 1336
    , 1342-43 (Fed. Cir.
    2004) (citing Winstar Corp., 
    518 U.S. at 869-70
    ).
    Parties to a contract, however, may address “the risk-shifting issue” during
    bargaining, and may elect to shift the risk from the government to the contractor. 
    Id.
     at
    1343 (citing Winstar, 
    518 U.S. 869
     n.15). In contrast, contract language that simply
    requires the contractor to comply with applicable laws and regulations does not shift the
    risk of regulatory change to the contractor. See Winstar, 
    518 U.S. at 868
    .
    The court considers the plain language of Article II.D, as well as defendant’s
    arguments for the contract interpretation proposed.
    1.      Contract Language
    Article II.D of the contract states in its entirety: “[t]his Contract is subject to any
    changes in the Medicare statute or regulations that affect the Medicare program.” Greisl
    Decl. Ex. A, at 4.
    According to defendant,
    Cardiosom’s contract, at Article II.D, expressly states that it “is subject to
    any changes in the Medicare statute or regulations that affect the Medicare
    program.” . . . CMS’ termination of Cardiosom’s contract was pursuant to
    the express direction of section 154 of the MIPPA – a change to the
    Medicare program. Accordingly, CMS’ termination was not a breach of
    Cardiosom’s Round 1 . . . contract.
    Def.’s Mot. 25. Defendant urges that the plain meaning of the language at Article II.D
    “should be given effect by this Court,” 
    id.,
     and that “nothing in the language of Article
    II.D limits its scope or effect upon the parties,” id. at 27. Defendant reasons that
    Article II.D simply reflects the parties’ understanding that the Medicare
    statute provides the regime under which the DMEPOS CAP operates, and
    8
    that in the event the statute were to change in a matter that affected the
    rights of the parties, such a change would not constitute a breach of
    contract.
    Id. at 31 (emphasis added).
    While defendant bases its argument on a narrow interpretation of Article II.D
    standing alone, the court must consider the contract as a whole. See Granite Constr. Co.,
    
    962 F.2d at 1003
    . The contract is not long, just under seven pages, exclusive of
    signatures and attachments. Greisl Decl. Ex. A, at 3-9. Review of the whole contract
    shows that Articles II and III are particularly relevant to the matter at issue. In its entirety
    Article II states,
    Article II
    Compliance with Laws and Regulations
    A. The Contract Supplier, and its affiliated companies and subcontractors,
    shall comply with all applicable Federal laws and regulations including,
    without limitation, the final rule on Competitive Acquisition for Certain
    Durable Medical Equipment, Prosthetics, Orthotics, and Supplies
    (DMEPOS) and Other Issues that appeared in the Federal Register on April
    10, 2007 (
    72 Fed. Reg. 17992
    ) and 42 CFR, Part 414, Subpart F.
    B. This Contract does not supersede or modify 42 CFR, Part 414, Subpart F.
    Failure to reference a statutory or regulatory requirement in this Contract
    does not affect the applicability of such requirement to the Contract
    Supplier. In the event of conflict or ambiguity between this Contract and
    any applicable Federal law or regulation, the conflict or ambiguity shall be
    resolved consistent with the applicable Federal law or regulatory
    requirements.
    C. The Contract Supplier shall comply with all applicable State laws,
    including any applicable State licensing requirements, pertaining to
    functions under this Contract.
    D. This Contract is subject to any changes in the Medicare statute or
    regulations that affect the Medicare program.
    Id. at 4.
    9
    The plain text of Article II indicates that the entire Article, including the subpart
    denoted as Article II.D, relates to “Compliance with Laws and Regulations.” Articles
    II.A, II.B, and II.C each address the contract supplier’s obligation to comply with
    relevant statutory or regulatory provisions. Defendant urges the court to give effect to the
    language of Article II.D as risk-shifting language. But defendant offers no explanation as
    to why it urges a reading of Article II.D that is inconsistent with the text in that Article as
    well as the language in the balance of the contract.
    The other relevant contract provision, Article III, is excerpted in relevant part
    below.
    Article III
    Contract Period, Breach and Remedies, and Severability
    A. Contract Period
    The Contract period shall commence on 07/01/2008 and end on
    06/30/2011, unless terminated earlier by CMS as provided in III.B of this
    Contract.
    B. Contract Breach and Remedies
    1. Breach of Contract
    Pursuant to 42 CFR 414.422(f)(1), any violation of the terms of this
    Contract by the Contract Supplier, including failure to comply with
    licensing and accreditation requirements, constitutes a breach of contract.
    Id.
    This Article defines the contract period. As addressed in Article III.A, the parties
    contemplated that a breach by Cardiosom would be the sole ground for CMS to terminate
    Cardiosom’s contract prior to June 2011. Id.
    Defendant argues that “[g]iven that the Medicare statute created the DMEPOS
    CAP, it was not unreasonable to think that the statute could be modified to terminate the
    program, or the contracts entered into as part of that program.” Def.’s Mot. 30.
    Defendant offers no explanation, however, as to why Article III.A—the provision in
    which the contract period is defined—is silent about such a circumstance.
    10
    2.     Case Law
    Defendant argues that the language of Article II.D is “risk-shifting language,” like
    that considered by the Federal Circuit in Admiral Financial. Def.’s Mot. 28-32 (citing
    Admiral Fin. Corp. v. United States, 
    378 F.3d 1336
     (Fed. Cir. 2004)).
    The contract language at issue in Admiral Financial is as follows:
    All references to regulations of the [Federal Home Loan Bank Board
    (Bank Board)] or the [Federal Savings and Loan Insurance Corporation
    (FSLIC)] used in this Agreement shall include any successor regulation
    thereto, it being expressly understood that subsequent amendments to such
    regulations may be made and that such amendments may increase or
    decrease the Acquirors’ obligation under this Agreement.
    Admiral Fin., 
    378 F.3d at 1339
    . This clause, designated as clause VI(D), was included in
    a section of the contract entitled “Miscellaneous Provisions.” 
    Id.
    The Federal Circuit has instructed that the plain language of a contract “must be
    given that meaning that would be derived from the contract by a reasonably intelligent
    person acquainted with the contemporaneous circumstances.” TEG-Paradigm Envtl., 465
    F.3d at 1338 (internal quotation marks omitted). To place the instant contract in proper
    context, the court reviews the relevant background information from Admiral Financial.
    Admiral Financial is a Winstar-related breach of contract case. Admiral Fin., 
    378 F.3d at
    1337 (citing Winstar Corp., 
    518 U.S. 839
    ). Winstar provides a detailed
    description of the circumstances facing the thrift industry in the 1980s that resulted in
    numerous thrifts bringing breach of contract claims against the United States, including
    Winstar and Admiral Financial.
    The late 1970s and early 1980s were difficult times for the savings and loan, or
    thrift, industry, bringing both high interest rates and inflation. Winstar Corp., 
    518 U.S. at 845
    . Thrifts held long-term mortgages for which they earned low interest rates, but were
    increasingly obligated to pay higher interest rates to depositors to attract funds. 
    Id.
    “When the costs of short-term deposits overtook the revenues from long-term mortgages,
    some 435 thrifts failed between 1981 and 1983.” 
    Id.
     As the Winstar Court explained,
    the multitude of already-failed savings and loans confronted FSLIC with
    deposit insurance liabilities that threatened to exhaust its insurance fund
    11
    . . . . in 1985, when the Bank Board estimated that it would take $15.8
    billion to close all institutions deemed insolvent under [Generally Accepted
    Accounting Principles]. By 1988, the year of the last transaction involved
    in this case, FSLIC was itself insolvent by over $50 billion. . . .
    Realizing that FSLIC lacked the funds to liquidate all of the failing
    thrifts, the Bank Board chose to avoid the insurance liability by
    encouraging healthy thrifts and outside investors to take over ailing
    institutions in a series of “supervisory mergers.” . . . [T]he principal
    inducement for these supervisory mergers was an understanding that the
    acquisitions would be subject to a particular accounting treatment that
    would help the acquiring institutions meet their reserve capital
    requirements imposed by federal regulations.
    
    Id. at 846-48
     (internal citations omitted).
    In considering whether the contract language in Admiral Financial’s contract was
    risk-shifting language, the Federal Circuit looked to an Eleventh Circuit case in which
    that court had found that a contract clause identical to the one at issue, clause VI(D), was
    risk-shifting. Admiral Fin., 
    378 F.3d at
    1339-40 (citing Guaranty Fin. Servs., Inc. v.
    Ryan, 
    928 F.2d 994
    , 999 (11th Cir. 1991)).
    The [Eleventh Circuit] explained that the clause “unmistakably warn[ed]
    Guaranty that its obligations under the contract may be increased by
    subsequent regulation.” [Guaranty, 
    928 F.2d at 999
    .] The court held that
    “the agencies, at the same time they made that promise [of regulatory
    forbearances], also unambiguously warned Guaranty that the rules might
    later change to Guaranty’s detriment,” and that “[b]y signing the contract,
    Guaranty took that chance, in effect wagering the chance that the rules
    would be changed against the potential return if they were not.” 
    Id.
    Id. (emphasis added). The Federal Circuit expressly followed the reasoning of the
    Eleventh Circuit in reaching its decision that clause VI(D) in Admiral Financial’s
    contract was risk-shifting language. Id. at 1343 (“[F]ollowing the lead of the Eleventh
    Circuit in Guaranty . . . , we hold that Admiral assumed the risk of a regulatory change
    such as that brought about by FIRREA.4” (footnote added)).
    4
    Financial Institutions Reform, Recovery, and Enforcement Act of 1989, Pub. L.
    101-73, 
    103 Stat. 183
    .
    12
    Defendant attempts to make a similar comparison here, notwithstanding the
    dissimilarity between the plain text of Article II.D in Cardiosom’s contract and the
    language of clause VI(D) in Admiral Financial’s contract. Article II.D states simply that
    “[t]his Contract is subject to any changes in the Medicare statute or regulations that affect
    the Medicare program,” Greisl Decl. Ex. A, at 4; unlike the subject clause in the Admiral
    Financial contract, it includes no ‘“unmistakable warn[ing]”’ to Cardiosom. See Admiral
    Fin., 
    378 F.3d at 1339-40
     (quoting Guaranty, 
    928 F.2d at 999
    ).
    Moreover, Article II.D was included in a section of Cardiosom’s contract entitled
    “Compliance with Laws and Regulations.” Greisl Decl. Ex. A, at 4. In contrast, Clause
    VI(D) was included in a section of Admiral Financial’s contract entitled “Miscellaneous
    Provisions.” Id. at 1339.
    Also distinguishable from the facts in this case are the circumstances in Admiral
    Financial surrounding contract formation. In February 1987, the individual who formed
    Admiral Financial contacted the Bank Board to discuss his interest in acquiring a failing
    thrift. Admiral Fin., 
    378 F.3d at 1337
    . Sixteen months later, in June 1988, the newly
    formed concern, Admiral Financial, signed an agreement with the Bank Board to acquire
    a failing thrift. 
    Id. at 1338
    .
    The Bank Board provided acquiring institutions, like Admiral Financial, a
    “particular accounting treatment that would help the acquiring institutions meet their
    reserve capital requirements imposed by federal regulations.” Winstar Corp., 
    518 U.S. at 848
    . In the case of Admiral Financial, the Bank Board treated the failing thrift’s
    negative net worth as “goodwill,” an asset, rather than as a liability. [The
    thrift] initially recorded nearly $9 million of goodwill based on its negative
    net worth. In May 1988, . . . the Bank Board[] agree[d] to allow the
    goodwill to be amortized over a period of 25 years using the straight-line
    method of depreciation.
    Admiral Fin., 
    378 F.3d at 1338
    .
    At the time Admiral Financial signed its agreement in June 1988, the thrift
    industry was at least eight years into a national crisis. An individual who spent more than
    one year in the late 1980s working with the Federal Home Loan Bank Board to acquire a
    failing thrift would have been keenly aware of the situation facing the thrift industry. The
    federal government was already attempting to restore stability to the thrift industry
    through agreements like the one the Bank Board entered into with Admiral Financial.
    Further government involvement, including congressional involvement through statutory
    13
    or regulatory change, was not unforeseeable. As the Federal Circuit said, “[o]n its face,
    clause VI(D) contemplated that the government might alter the regulations governing the
    supervision of thrifts such as [the thrift owned by Admiral Financial]; by agreeing to the
    clause, Admiral acknowledged that its obligations might change if the regulatory regime
    changed.” 
    Id. at 1339
    .
    In this case, defendant seeks to analogize to the Admiral Financial case, asserting
    that “it was not unreasonable to think that the [Medicare] statute could be modified to
    terminate the program, or the contracts entered into as part of that program,” Def.’s Mot.
    30; but it points to nothing that supports this position. Ordinarily, a private concern does
    not enter into a contract with the federal government with the expectation that the
    contract will be statutorily terminated. Nor is there anything in the record to suggest that
    when Cardiosom signed the contract in March 2008, it had any idea that Congress might
    act to terminate the Round 1 contracts.
    The record does show, however, that when CMS signed the contract on June 20,
    2008, it knew that Congress was considering terminating the Round 1 contracts.
    On May 6, 2008, the House Subcommittee on Health held a hearing on the
    Medicare DMEPOS Competitive Bidding Program, the program through which CMS
    issued Cardiosom’s contract.5 See Medicare’s DMEPOS Competitive Bidding Program:
    Hearing Before the Subcomm. on Health of the H. Comm. on Ways & Means, 110th
    Cong. (2008) (“Hrg. Rpt.”), available at http://www.gpo.gov/fdsys/search/home.action
    (follow Congressional Hearings hyperlink under “Browse” bar on right). The one
    witness testifying in person was the Acting Administrator of CMS, Mr. Kerry Weems.
    Hrg. Rpt. 6-32. Mr. Weems faced questioning critical of CMS’s mismanagement of the
    Round 1 contracting process, as that process had resulted in the exclusion of numerous
    contractors from final bid consideration for reasons unrelated to bid content. Id. at 18-32.
    Observations made by two Members of Congress, which are representative of the
    questions and concerns expressed that day during the hearing, are set forth below.
    Representative Sam Johnson stated:
    5
    Defendant states that no committee reports accompanied the passage of MIPAA.
    Def.’s Mot. 18 n.10, ECF No. 41. While the May 8, 2008 subcommittee hearing
    preceded the passage of MIPAA, this committee report is part of the MIPAA legislative
    history. See generally Cardiosom, L.L.C. v. United States, 
    115 Fed. Cl. 761
    , 778-79
    (2014).
    14
    Congress can have all the good intentions in the world, but [when] the
    agency in charge [of] putting Congress’ ideas into practice [is] missing
    some mark, it puts us in a difficult position. The number one issue I’ve
    heard about is the same all these other questioners have heard about.
    Id. at 23. He then discussed the approximately 1000 contractors in Dallas, Texas who
    had submitted Round 1 bids, about 600 of which were rejected for a reason other than the
    amount of their bid. Id.
    Representative Dave Camp offered the following:
    Well, I would just have to say that Mr. Weems, this is [a] process where
    some people were not allowed to bid; and, so what’s happened is there’s an
    exclusive group of providers that are now going to be providing this
    equipment . . . . But, what I would like to hear from you is a way to reform
    what you’ve been doing, because I would agree with Mr. Stark that I don’t
    think this process has been one that stands scrutiny.
    ....
    [L]et me suggest something. If you were to provide a 60-day window to re-
    examine the bids that were disqualified due to lack of information, do you
    believe a six-month delay would be necessary? Do you think a rebid would
    still be necessary if you could re-examine those folks that were
    disqualified?
    Id. at 19-20 (emphasis added). The criticism of CMS’s contracting process was pointed
    and oft-repeated.
    About one month later, on June 12, 2008, the Chairman of the House
    Subcommittee on Health, Representative Pete Stark, introduced a bill to “delay and
    reform” the Medicare DMEPOS Competitive Acquisition Program (CAP). Medicare
    DMEPOS Competitive Acquisition Reform Act of 2008, H.R. 6252, 110th Cong. (2008),
    2007 CONG US HR 6252 (Westlaw). H.R. 6252 directed that “the contracts awarded
    under this section [Round 1 of Competitive Acquisition Program] before the date of the
    enactment of this subparagraph are terminated.” H.R. 6252 § 2 (a)(1)(A)(iv).
    Eight days later, on June 20, 2008, Representative Charles Rangel introduced the
    bill that was later enacted as MIPPA. Medicare Improvements for Patients and Providers
    Act of 2008, H.R. 6331, 110th Cong. (2008) (enacted), 2007 CONG US HR 6331
    15
    (Westlaw). The bill introduced by Representative Stark, H.R. 6252, was included in its
    entirety in the bill introduced by Representative Rangel, H.R. 6331, as Section 154.
    Compare H.R. 6252 § 2 (Delay in and Reform of Medicare DMEPOS Competitive
    Acquisition Program), with H.R. 6331 § 154 (same).
    CMS signed the contract with Cardiosom on June 20, 2008, less than two months
    after Mr. Weems testified before Congress and after Representative Stark had introduced
    his bill terminating all Round 1 contracts. A review of the circumstances surrounding the
    formation of the subject contract between CMS and Cardiosom reveals that although
    CMS was fully aware that Congress might terminate the Round 1 contracts—even as it
    signed Cardiosom’s contract—Cardiosom was not. This lack of awareness critically
    undercuts defendant’s claim that Cardiosom agreed to bear the risk of any statutory or
    regulatory change.
    Defendant’s further contention that the contract in Cardiosom could be construed
    like the oil leases that were considered by the Supreme Court in Mobil Oil is also
    unavailing. Def.’s Mot. 27-28, 33 (citing Mobil Oil Exploration & Producing Se. v.
    United States, 
    530 U.S. 604
     (2000)). The relevant facts of Mobil Oil, succinctly
    described by defendant, are as follows:
    [P]laintiff oil companies entered into lease agreements with the United
    States to explore and develop oil rights off the coast of North Carolina.
    [Mobil Oil, 530 U.S.] at 609. Those lease agreements, and the oil
    companies’ exploration and development rights, were made “subject” to
    certain requirements set out in the Outer Continental Shelf Lands Act
    (“OCSLA”), the Coastal Zone Management Act (“CZMA”), and
    accompanying existing regulations. 
    Id.
     After the execution of those lease
    agreements and the plaintiffs’ commencement of performance, Congress
    enacted another statute, the Outer Banks Protection Act of 1990 (“OBPA”),
    which set out new requirements that the oil companies had to meet prior to
    exploration, and delayed the Secretary of the Interior’s ability to approve
    the oil companies’ exploration plans and allow them to proceed with the
    time period specified in the lease agreements. 
    Id. at 611-13
    . The oil
    companies sued, alleging that the new requirements set out in the OBPA
    breached their lease agreements, which were subject only to requirements
    and regulations set out in the OCSLA and CZMA. The Court agreed,
    finding that the restrictions in the new statute were inconsistent with the
    promises in the original leases. 
    Id. at 624
    .
    Def.’s Mot. 27-28. The Mobil Oil Court found that defendant violated the contracts.
    16
    Mobil Oil, 
    530 U.S. at 618
    . Defendant argues that Mobil Oil is instructive because the
    Court—which found for plaintiff—“did not suggest that there was anything improper
    about the fact that the leases were expressly made subject to the OCSLA or the CZMA.”
    Def.’s Mot. 28 (emphasis added). Defendant likens the Mobil Oil leases to the
    Cardiosom contract because Article II.D makes the contract “subject to” changes in the
    Medicare statute. See id. at 33. Defendant does not explain how this limited similarity
    between the language in Cardiosom’s contract and in the Mobil Oil leases furnishes
    support for its reading of Article II.D as a risk-shifting provision. As plaintiff observed
    in its briefing, Mobil Oil “teaches little—if anything—about how that case would be
    decided” if the facts of that case were similar to the facts in Cardiosom. Pl.’s Reply 25-
    26. The court finds defendant’s reliance on Mobil Oil to be unpersuasive.
    Defendant also attempts to distinguish the case at bar from the Winstar case.
    Def.’s Mot. 32-33. In Winstar, the Court found the government liable for breach of
    contract even though the government was prevented from performing its contractual
    obligations by a change in the governing regulations. Winstar, 
    518 U.S. at 843, 868
    . In
    an effort to distinguish the contracts, defendant contends that, “unlike the contract clause
    in Winstar, the language [in] Article II.D of Cardiosom’s contract does not simply state
    that Cardiosom must comply with certain laws and regulations. Instead, it states that
    Cardiosom’s contract itself is subject to any changes in the Medicare Act . . . .” 
    Id.
     at 32-
    33.
    The Federal Circuit discussed the Winstar language in its evaluation of the
    Admiral Financial language.
    The Government also cites a provision requiring [the thrift] to “comply in
    all material respects with all applicable statutes, regulations, orders of, and
    restrictions imposed by the United States or . . . by any agency of [the
    United States],” but this simply meant that [the thrift] was required to
    observe FIRREA’s new capital requirements once they were promulgated.
    The clause was hardly necessary to oblige [the thrift] to obey the law, and
    nothing in it barred [the thrift] from asserting that passage of that law
    required the Government to take action itself or be in breach of its contract.
    Admiral Fin., at 1342 (quoting Winstar, 
    518 U.S. at 868-69
    ).
    Defendant asserts that the language in Cardiosom’s contract differs from the
    language in Winstar because the phrase “subject to” appears in Article II.D. Def.’s Mot.
    33. But defendant fails to explain how the “subject to” language supports its
    interpretation of Article II.D as risk-shifting language, notwithstanding the inclusion of
    17
    the clause in the contract section entitled “Compliance with Laws and Regulations.”
    The court does not discern the distinction that defendant attempts to put forward and
    finds defendant’s effort to distinguish the Winstar language unconvincing.
    The court is not persuaded that the language in Article II.D is risk-shifting. Read
    in the context of the contract, it is simply compliance language; it did not shift the risk of
    regulatory change to Cardiosom. Nothing in Article II.D warned RUSH that Congress
    might terminate the contract, or that CMS would attempt to shift the risk of such a
    termination to RUSH. Based on the contract language alone, it is clear that defendant is
    liable for breach of contract to Cardiosom and has no defense for its breach.
    The court also has considered carefully the circumstances surrounding the contract
    formation here and has found nothing in the record suggesting that when Cardiosom
    signed the contract in March 2008, the parties intended Article II.D to be read in any way
    other than is reflected in the title of Article II (“Compliance with Laws and
    Regulations”)—that is, a commitment to follow the applicable law. The court is of the
    view that a reasonably intelligent person acquainted with the contemporaneous
    circumstances would be unlikely to ascribe the risk-shifting meaning to Article II.D
    urged by defendant. See EG-Paradigm Envtl., Inc., 465 F.3d at 1338.
    Plaintiff has argued, in the alternative, that defendant’s interpretation of Article
    II.D would make the contract illusory. Pl.’s Mot. 29-30. The court, however, has found
    that defendant failed to carry its burden on its defense that Article II.D is risk-shifting
    language, and thus, does not address further plaintiff’s alternative argument or
    defendant’s response thereto.
    IV.    Conclusion and Further Action
    For the reasons discussed herein, plaintiff’s motion for summary judgment on
    contract liability is GRANTED. Defendant’s cross-motion for summary judgment on
    contract liability is DENIED.
    Plaintiff now bears the burden of establishing its damages, and showing that it has
    not previously received reimbursement through the CMS administrative process for any
    monies it now seeks through this court. See Cardiosom, 115 Fed. Cl. at 778 (“It merits
    mention that . . . [plaintiff] bears the burden of showing that any damages it seeks from
    this court do not include any of the amounts already recouped through the CMS
    administrative process.” (citing Cardiosom, 
    656 F.3d at 1328-29
    )).
    18
    The parties are directed to file a proposed schedule for briefing on summary
    judgment on damages no later than July 21, 2014.
    IT IS SO ORDERED.
    s/ Patricia E. Campbell-Smith
    PATRICIA E. CAMPBELL-SMITH
    Chief Judge
    19
    

Document Info

Docket Number: 1:08-cv-00533

Citation Numbers: 117 Fed. Cl. 526

Judges: Patricia E. Campbell-Smith

Filed Date: 8/19/2014

Precedential Status: Precedential

Modified Date: 1/13/2023

Authorities (22)

guaranty-financial-services-inc-and-guaranty-federal-savings-bank-v-t , 928 F.2d 994 ( 1991 )

C. Sanchez and Son, Incorporated v. United States , 6 F.3d 1539 ( 1993 )

Holmes v. United States , 657 F.3d 1303 ( 2011 )

Tri-Star Electronics International Inc. v. Preci-Dip Durtal ... , 619 F.3d 1364 ( 2010 )

Medlin Construction Group, Ltd. v. Harvey , 449 F.3d 1195 ( 2006 )

Granite Construction Company v. The United States , 962 F.2d 998 ( 1992 )

Brunswick Bank & Trust Company v. The United States , 707 F.2d 1355 ( 1983 )

San Carlos Irrigation and Drainage District v. The United ... , 877 F.2d 957 ( 1989 )

Dennis R. Thomas, Claimant-Appellant v. R. James Nicholson, ... , 423 F.3d 1279 ( 2005 )

Loveladies Harbor, Inc. And Loveladies Harbor, Unit D, Inc. ... , 27 F.3d 1545 ( 1994 )

Lockheed Martin Ir Imaging Systems, Inc. v. Togo D. West, ... , 108 F.3d 319 ( 1997 )

Cardiosom, LLC v. United States , 656 F.3d 1322 ( 2011 )

Varilease Technology Group, Inc. v. United States , 289 F.3d 795 ( 2002 )

winstar-corporation-united-federal-savings-bank-statesman-savings-holding , 64 F.3d 1531 ( 1995 )

Wayne B. Harris v. Department of Veterans Affairs , 142 F.3d 1463 ( 1998 )

Admiral Financial Corporation v. United States , 378 F.3d 1336 ( 2004 )

United States v. Testan , 96 S. Ct. 948 ( 1976 )

Matsushita Electric Industrial Co., Ltd. v. Zenith Radio ... , 106 S. Ct. 1348 ( 1986 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

View All Authorities »