Aclr, LLC v. United States ( 2021 )


Menu:
  •           In the United States Court of Federal Claims
    No. 15-767C
    (consolidated with No. 16-309C)
    (E-Filed: December 15, 2021)1
    )
    ACLR, LLC,                               )
    )       Summary Judgment; RCFC 56;
    Plaintiff,                     )       Constructive Termination for
    )       Convenience; Damages.
    v.                                       )
    )
    THE UNITED STATES,                       )
    )
    Defendant.                     )
    )
    Thomas K. David, Reston, VA, for plaintiff. John A. Bonello, of counsel.
    Joseph A. Pixley, Trial Attorney, with whom were Brian M. Boynton, Acting Assistant
    Attorney General, Martin F. Hockey, Jr., Acting Director, Commercial Litigation Branch,
    Civil Division, United States Department of Justice, Washington, DC, for defendant.
    Robyn Littman, United States Department of Health and Human Services, Baltimore,
    MD, of counsel.
    OPINION AND ORDER
    CAMPBELL-SMITH, Judge.
    Plaintiff’s motion for summary judgment as to its damages made pursuant to Rule
    56 of the Rules of the United States Court of Federal Claims (RCFC), is currently before
    the court. See ECF No. 107. Defendant responded to the motion, see ECF No. 115, and
    plaintiff replied, see ECF No. 119. The motion is now fully briefed, and ripe for
    1
    This opinion and order issued under seal on November 19, 2021. See ECF No. 120. The
    parties were invited to identify proprietary or confidential material subject to deletion on the
    basis that the material is protected/privileged. No redactions were proposed by the parties. See
    ECF No. 124. Thus, the sealed and this public version of this opinion and order are identical,
    except for the publication date and this footnote.
    decision. The parties did not request oral argument, and the court deems such argument
    unnecessary.
    The court has considered all of the parties’ arguments and addresses the issues that
    are pertinent to the court’s ruling in this opinion. For the following reasons, plaintiff’s
    motion for summary judgment is DENIED.
    I.     Background
    A.      Contract Background 2
    To identify and recover improper Medicare Part D payments, the Centers for
    Medicare & Medicaid Services (CMS), a component of the United States Department of
    Health and Human Services (HHS), entered into a task order with plaintiff pursuant to a
    General Services Administration (GSA) federal supply schedule contract for “recovery
    audit” services. See ECF No. 107-2 at 5 (plaintiff’s memorandum in support of its
    motion for summary judgment); see also ECF No. 51-3 at 154 (task order). Pursuant to
    the task order, the attached performance work statement, and later the statement of work,
    plaintiff was to conduct recovery audits for particular calendar years. See ECF No. 51-3
    at 152-54. Plaintiff conducted seven audits for which it was paid contingency fees. See
    ECF No. 115 at 12; ECF No. 119 at 7-8. The audits at issue here, which the court
    determined were constructively terminated, are the 2007 and 2010 duplicate payment
    audits. See ECF No. 76 at 11-12 (March 23, 2020 opinion, reported at ACLR, LLC v.
    United States, 
    147 Fed. Cl. 548
     (2020)).
    The task order stated that plaintiff was to be paid a firm, fixed-price contingency
    fee for audit work detailed in a performance work statement. See ECF No. 51-3 at 152-
    54. Any payments to plaintiff were contingent upon the recovery of improper payments
    from plan sponsors and were to be fixed as a percentage of such recoveries. See id. at
    155. Federal Acquisition Regulation (FAR) provision 52.212-4(l), addressing
    termination for the government’s convenience, was included in the task order pursuant to
    the federal supply schedule contract. See id. at 154 (incorporating the terms of the GSA
    federal supply schedule contract); ECF No. 70-1 at 21 (GSA federal supply schedule
    contract incorporating the language of FAR § 52.212-4(l)). Under the contract’s
    termination for convenience clause, should the agency elect to terminate the contract for
    2
    The court detailed the extensive procedural and factual background of this case in its
    opinion on the parties’ cross-motions for summary judgment, and will, therefore, only reiterate
    the facts necessary to this opinion. See ECF No. 76 (March 23, 2020 opinion, reported at ACLR,
    LLC v. United States, 
    147 Fed. Cl. 548
     (2020)). The court notes that the contract documents
    associated with this case were not attached to the motion currently before the court; therefore, the
    court cites to the documents filed with the parties’ prior cross-motions for partial summary
    judgment.
    2
    convenience, plaintiff would be owed “a percentage of the contract price reflecting the
    percentage of the work performed prior to the notice of termination, plus reasonable
    charges the Contractor [could] demonstrate to the satisfaction of the ordering [agency]
    using its standard record keeping system, [to] have resulted from the termination.” 3 
    Id.
    B.      Procedural History
    Plaintiff filed this Contract Disputes Act (CDA), 
    41 U.S.C. §§ 7101-7109
    , suit on
    July 22, 2015, contesting the denial of its certified claim for $28,506,591, see ECF No. 1
    (complaint), associated with two duplicate payment audits—the 2007 and 2010 audits at
    issue here—and filed a second suit on March 9, 2016, contesting the denial of its second
    certified claim for $79,314,795, see Case No. 16-309, ECF No. 1 (complaint), associated
    with a separate audit. Following discovery, the two cases were consolidated. See ECF
    No. 48 (order). The parties filed cross-motions for partial summary judgment in 2018.
    See ECF No. 51 (plaintiff’s motion), ECF No. 52 (defendant’s cross-motion).
    On March 23, 2020, this court issued its opinion on the motions and found that
    defendant “effected constructive terminations for convenience” of plaintiff’s 2007 and
    2010 audits. 4 ECF No. 76 at 16. Consequently, the court held that plaintiff is entitled to
    damages amounting to “‘a percentage of the contract price reflecting the percentage of
    the work performed prior to the notice of termination, plus reasonable charges the
    Contractor can demonstrate to the satisfaction of the ordering activity using its standard
    record keeping system, [that] resulted from the termination.’” 
    Id.
     (alteration in original)
    (citing ECF No. 70-1 at 21 (GSA contract)).
    Because the parties had not presented “sufficient evidence and argument regarding
    the percentage of work performed by plaintiff, or its reasonable charges resulting from a
    termination for convenience,” the court required the parties to confer and make additional
    submissions on the issue. 
    Id.
     The parties agreed that the plaintiff should submit a
    termination for convenience settlement proposal to the agency for approval and requested
    3
    The court notes the language of the termination for convenience provision incorporated in
    plaintiff’s contract differs slightly from that in 
    48 C.F.R. § 52.212-4
    (l), but the differences are de
    minimus and do not change the meaning of the provision. The court will therefore refer to FAR
    § 52.212-4(l) throughout the opinion interchangeably with the provision in the contract.
    4
    The court also found that defendant had not breached the contract or its duty of good faith
    and fair dealing regarding the audit about which plaintiff filed the second suit. See ECF No. 76
    at 13-16. The court therefore denied plaintiff’s motion for summary judgment as to the claim in
    case number 16-309 and granted defendant’s cross-motion on the same. See id. at 14, 16.
    Although the cases remain consolidated, because the court granted defendant’s motion for
    summary judgment, no claims are still pending in plaintiff’s second suit, case number 16-309.
    The court will therefore deconsolidate this matter, and will issue judgment in favor of defendant
    in case no. 16-309 in due course, pursuant to the court’s March 23, 2020 opinion.
    3
    that the court remand the case to CMS, which the court did on April 21, 2020. See ECF
    No. 82 (remand order).
    Plaintiff submitted a termination for convenience settlement proposal to the
    agency requesting $10,418,948. See ECF No. 101-2 at 4 (revised settlement proposal).
    The agency denied plaintiff’s claim related to the 2007 audit in its entirety and denied all
    but $157,318 for the 2010 audit. See ECF No. 98 at 9, 12 (CMS decision on remand).
    The court then lifted the stay in this matter, see ECF No. 100 (order), and plaintiff filed
    an amended complaint, see ECF No. 101. Therein, plaintiff seeks termination for
    convenience damages of “at least $5,923,754 plus interest and additional legal fees
    incurred in this proceeding,” which was, according to plaintiff, an amount “based upon
    actual costs incurred.” Id. at 4.
    C.      Plaintiff’s Damages Claim
    Plaintiff has now filed a motion for summary judgment arguing that it is entitled to
    a total of $6,095,118.35 in termination for convenience damages “through December 31,
    2020.” ECF No. 107-2 at 22. According to plaintiff, because the agency did not call its
    termination of the audits a termination for convenience at the time, plaintiff “continued to
    incur costs under the PWS and rightly did so to comply with its contractual obligations
    with the belief that it had a continuing contractual obligation with CMS” until March 23,
    2020, when the court found that the termination was “‘constructively effected.’” Id. at 11-
    12. Plaintiff alleges that “100% of its costs during the period of January 13, 2011
    [through] January 31, 2012” are “reasonable charges resulting from the termination for
    convenience” of the 2007 audit because “this was the only audit conducted during that
    time period.” Id. at 12. Likewise, plaintiff argues that the time period for its “work
    efforts” on the 2010 audit was January 2012 to April 24, 2015. Id. at 18. Plaintiff
    acknowledges, however, that it “was also conducting additional audits for CMS” during
    that time period. Id.
    For the 2007 audit, plaintiff argues that it is entitled to six types of damages:
    “personnel costs, managing principal costs, general administrative costs, rental space
    costs, loan interest, and reasonable profit.” Id. at 13. For the 2010 audit, plaintiff seeks
    $923,558.62 of personnel costs. Id. at 18. Plaintiff also seeks settlement fees, including
    its legal fees and “its principal[’]s time and effort in this lawsuit,” id., and interest on its
    claim pursuant to the CDA, id. at 21. In support of its claims, plaintiff attached an
    affidavit from Christopher Mucke, plaintiff’s managing principal, and twenty-two
    exhibits containing plaintiff’s bank statements, payroll documentation, lease
    documentation, loan documentation, various cost summaries and calculations, and legal
    expense documentation. See ECF No. 107-3 through 107-13 (exhibits); 107-3 at 1
    (appendix table of contents).
    4
    II.    Legal Standards
    According to RCFC 56(a), summary judgment is appropriate “if the movant shows
    that there is no genuine dispute as to any material fact and the movant is entitled to
    judgment as a matter of law.” “[A]ll evidence must be viewed in the light most favorable
    to the nonmoving party, and all reasonable factual inferences should be drawn in favor of
    the nonmoving party.” Dairyland Power Coop. v. United States, 
    16 F.3d 1197
    , 1202
    (Fed. Cir. 1994) (citations omitted).
    A genuine dispute of material fact is one that could “affect the outcome” of the
    litigation. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986). “The moving
    party . . . need not produce evidence showing the absence of a genuine issue of material
    fact but rather may discharge its burden by showing the court that there is an absence of
    evidence to support the nonmoving party’s case.” Dairyland Power, 
    16 F.3d at
    1202
    (citing Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 325 (1986)). A summary judgment
    motion is properly granted against a party who fails to make a showing sufficient to
    establish the existence of an essential element to that party’s case and for which that party
    bears the burden of proof at trial. Celotex, 
    477 U.S. at 324
    .
    The Supreme Court of the United States has instructed that “the mere existence of
    some alleged factual dispute between the parties will not defeat an otherwise properly
    supported motion for summary judgment; the requirement is that there be no genuine
    issue of material fact.” Anderson, 
    477 U.S. at 247-48
    . A nonmovant will not defeat a
    motion for summary judgment “unless there is sufficient evidence favoring the
    nonmoving party for [the fact-finder] to return a verdict for that party.” 
    Id. at 249
    (citation omitted). “A nonmoving party’s failure of proof concerning the existence of an
    element essential to its case on which the nonmoving party will bear the burden of proof
    at trial necessarily renders all other facts immaterial and entitles the moving party to
    summary judgment as a matter of law.” Dairyland Power, 
    16 F.3d at
    1202 (citing
    Celotex, 
    477 U.S. at 323
    ).
    III.   Analysis
    A.     FAR § 52.212-4(l) Governs Plaintiff’s Damages Claim
    As an initial matter, defendant argues that plaintiff’s argument is “fatally flawed”
    and its motion should be denied because plaintiff based its request for damages on the
    wrong FAR provision. ECF No. 115 at 19. Throughout its motion, plaintiff cites to 
    48 C.F.R. § 52.249-2
    (g)—the FAR termination for convenience provision for fixed-price,
    non-commercial item contracts. See, e.g., ECF No. 107-2 at 13-17. Plaintiff’s contract,
    however, contains FAR § 52.212-4(l)—the termination for convenience provision for
    commercial item contracts. See ECF No. 76 at 4 (citing ECF No. 70-1 at 21 (GSA
    federal supply schedule contract)). Plaintiff explains that, because of the “lack of
    precedent on termination for convenience damages for contingency fee contracts,” it
    5
    “utilized the methodology of FAR § 52.249-2 to determine the costs associated with the
    terminations.” ECF No. 119 at 12.
    Although neither party cites to—and the court could not locate—binding
    precedent involving termination for convenience damages on a contingency fee contract,
    there is precedent for applying FAR § 52.212-4(l) when plaintiff is not due any payment
    under the contract. 5 See, e.g., SWR, Inc., ABSCA No. 56708, 
    15-1 BCA ¶ 35,832
    ; First
    Division Design, LLC, 
    ASBCA No. 60049
    , 
    18-1 BCA ¶ 37,201
    . In SWR, the plaintiff
    had a requirements contract in which services were to be ordered by delivery orders. See
    SWR, 
    15-1 BCA ¶ 35,832
     at 175,225. The Board noted that the agency never issued any
    delivery orders, so the plaintiff never performed any services for which the plaintiff could
    recover under the contract price prong of FAR § 52.212-4(l). See id. The Board went
    on, however, to award the plaintiff damages under the second prong of the provision, for
    “reasonable charges” resulting from the termination. Id. The court finds persuasive the
    reasoning and analysis of the Board in SWR that FAR § 52.212-4(l)—the provision
    contained in plaintiff’s contract—may be applied when plaintiff is ultimately due no
    payment under the contract.
    The court does not agree, however, with defendant that plaintiff’s citation to FAR
    § 52.249-2(g) is fatal to its argument. Although the court will not apply that provision in
    its analysis of plaintiff’s damages claims, the court does not perceive plaintiff’s argument
    to be premised on application of FAR § 52.249-2(g) such that it must fail if the provision
    does not apply. Thus, the court will examine plaintiff’s damages claim using the
    framework of FAR § 52.212-4(l).
    FAR § 52.212-4(l) provides that, upon termination for convenience, “the
    Contractor shall be paid a percentage of the contract price reflecting the percentage of the
    work performed prior to the notice of termination, plus reasonable charges the Contractor
    can demonstrate to the satisfaction of the Government using its standard record keeping
    system, have resulted from the termination.” 
    48 C.F.R. § 52.212-4
    (l). The purpose of
    this payment is to “fairly compensate the contractor and to make the contractor whole for
    the costs incurred in connection with the terminated work.” Nicon, Inc. v. United States,
    
    331 F.3d 878
    , 885 (Fed. Cir. 2003) (citation omitted); see also Jacobs Eng’g Grp. v.
    United States, 
    434 F.3d 1378
    , 1381 (Fed. Cir. 2006) (quoting Kasler Elec. Co., DOTCAB
    1425, 
    84-2 BCA ¶ 17,374
    ) (“A contractor is not supposed to suffer as the result of a
    termination for convenience of the Government, nor to underwrite the Government’s
    decision to terminate.”).
    5
    While it is not binding precedent, the court finds the reasoning of the Armed Services
    Board of Contract Appeals persuasive here, and “carefully considers the Board’s expertise in
    interpreting government contracts.” Grumman Aerospace Corp. v. Wynne, 
    497 F.3d 1350
    , 1356
    (Fed. Cir. 2007).
    6
    The termination for convenience provision clearly provides for the contractor to be
    paid for the “percentage of the work performed prior to the notice of termination.” FAR
    § 52.212-4(l). It also provides for payment of “reasonable charges” resulting from the
    termination. Id. The contract appeals boards have construed “reasonable charges” to be
    costs separate from those charges associated directly with the completed work, and to
    refer to such things as “start-up costs; unrecovered running expense; preventive
    maintenance; settlement charges; and other charges that are normally paid pursuant to a
    long form termination for convenience provision to fairly compensate a contractor.”
    SWR, 
    15-1 BCA ¶ 35,832
     at 175,223 (citing cases construing the word “charges”). Thus,
    the boards have found “three general categories of recovery,” including: “(1) [t]he price
    of work performed under the contract prior to a notice of termination . . . ; (2) settlement
    expenses . . . ; and (3) . . . costs resulting from the termination.” Dellew Corp., 
    ASBCA No. 58538
    , 
    15-1 BCA ¶ 35,975
     at 175,783; accord Red River Holdings, LLC v. United
    States, 
    802 F. Supp. 2d 648
    , 662 (D. Md. 2011) (holding that FAR § 52.212-4(l) entitles a
    contractor to “(1) payment of ‘a percentage of the contract price reflecting the percentage
    of the work performed prior to the notice of termination’; and (2) a payment as
    compensation for settlement costs or costs reasonably incurred in anticipation of contract
    performance, provided such costs are not adequately reflected as a percentage of the work
    performed, and provided such costs could not have been reasonably avoided”) (emphasis
    in original). The court finds the reasoning and conclusions of the boards to be persuasive
    and will apply this framework in analyzing plaintiff’s claim.
    B.     Plaintiff Is Not Entitled to Compensation for a Percentage of the Contract
    Price, but May Be Able to Recover Its Reasonable Charges
    The first category of recovery—the work performed prior to termination—is
    “‘calculated based on contract price, i.e., as a percentage of contract price reflecting
    percentage of work performed prior to termination.’” Dellew, 
    15-1 BCA ¶ 35,975
     at
    175,783 (quoting SWR, 
    15-1 BCA ¶ 35,832
     at 175,224). Where there is no payment due
    pursuant to the contract, as in the case of a requirements contract where no orders were
    made or where work was not authorized under the contract, the contractor cannot recover
    under the first category. See id.; SWR, 
    15-1 BCA ¶ 35,832
     at 175,225.
    Defendant argues that plaintiff has failed to present evidence of its contract price,
    the total work to be performed, the percentage of work actually performed, and the date
    of termination of the 2007 and 2010 audits. See ECF No. 115 at 26. Thus, according to
    defendant, plaintiff is entitled to no recovery under the first category of compensation.
    See id. at 27. Citing Red River Holdings, defendant further argues that because the first
    category is “controlling,” and the “bulk” of plaintiff’s claimed costs “would necessarily
    be captured in the first prong” of the termination provision, plaintiff cannot recover under
    the reasonable charges prong. Id. at 27 (citing Red River Holdings, 802 F. Supp. 2d at
    662).
    7
    The court agrees with defendant that plaintiff cannot recover under the first
    category of compensation. The court previously held that the agency terminated
    plaintiff’s 2007 and 2010 audits for convenience after plaintiff had reviewed the data for
    each and presented defendant with its findings. See ECF No. 76 at 11. Thus, plaintiff
    had performed some portion of the work under the contract. However, plaintiff’s
    contract price was to be paid based on a contingency fee—a portion of plaintiff’s
    recovery of any improper payments. See id. at 4-5. Because plaintiff’s work had not yet
    reached the stage of recovering improper payments, but was terminated at the data
    analysis stage, it did not collect any fees. See id. at 5-7. Therefore, although plaintiff had
    performed some of the work under the contract, the amount to which plaintiff was
    technically entitled under the terms of the contract remained at zero. The court cannot,
    then, pursuant to the plain language of the FAR provision, award plaintiff compensation
    under the first category of recovery—any percentage of zero is zero. See Dellew, 
    15-1 BCA ¶ 35,975
     at 175,783; SWR, 
    15-1 BCA ¶ 35,832
     at 175,225.
    Plaintiff is not precluded, however, from recovering its reasonable charges and
    settlement costs. The reasonable charges category is designed to capture those costs that
    “are not adequately reflected as a percentage of the work performed.” Red River
    Holdings, 802 F. Supp. 2d at 662 (emphasis in original); see also SWR, 
    15-1 BCA ¶ 35,832
     at 175,223. This is in keeping with the well-established principle that the
    purpose of compensation for a termination for convenience is to “fairly compensate the
    contractor and to make the contractor whole for the costs incurred in connection with the
    terminated work.” Nicon, 
    331 F.3d at 885
    .
    C.     Genuine Disputes of Material Fact Remain Regarding Plaintiff’s Claims for
    Its Reasonable Charges
    To recover its reasonable charges, plaintiff bears the burden of “proving the
    amount of loss with sufficient certainty so that the determination of the amount of
    damages will be more than mere speculation.” Lisbon Contractors, Inc. v. United States,
    
    828 F.2d 759
    , 767 (Fed. Cir. 1987) (quoting Willems Indus., Inc. v. United States, 
    295 F.2d 811
    , 831 (Ct. Cl. 1961)). The plain language of the FAR provision also requires that
    plaintiff prove its reasonable charges “using its standard record keeping system.” FAR
    § 52.212-4(l).
    Defendant argues generally that plaintiff failed to carry its burden. See ECF No.
    115 at 28-40. According to defendant, plaintiff’s claimed charges are unreasonable. See
    id. at 28. This is so, defendant contends, because plaintiff claims more than five million
    dollars in termination for convenience damages for two audits, while it received just over
    three million dollars total in contingency fees under the contract for seven completed
    audits. See id. Specifically, defendant argues for each of plaintiff’s claimed costs that
    plaintiff requests far more than is reasonable given the time frame of the contracts, and
    that plaintiff fails to prove its charges using its standard record keeping system as
    8
    required by FAR § 52.212-4(l). See id. at 28-40. The court will address each of
    plaintiff’s requests in turn.
    1.         Personnel Costs
    i.         2007 Audit
    Plaintiff first claims that it is entitled to its payroll costs of $408,462.83 for the full
    year of 2011. See ECF No. 107-2 at 13. In support of the claimed amount, plaintiff cites
    to the affidavit of its managing principal, Mr. Mucke, and a payroll summary attached to
    Mr. Mucke’s affidavit as Exhibit B. See id. (citing ECF No. 107-3 at 5, 60-66).
    Plaintiff also argues that it is entitled to its “managing principal costs” for Mr.
    Mucke’s time working as the project director, as defined by the contract. See id. at 13-
    14. Plaintiff argues without citation that “[u]nder a fixed-fee or cost plus contract, Mr.
    Mucke’s work would be a recoverable cost,” and “[i]f Mr. Mucke had not devoted his
    time and attention to the [2007 audit], he would have devoted his time and attention to
    other business efforts that would have generated revenue for [plaintiff].” Id. at 14.
    Noting that, because he is an owner and not an employee, Mr. Mucke does not receive a
    salary, and that he did not specifically track his hours worked on the contract, plaintiff
    states that “[t]o determine costs associated with his efforts, Mr. Mucke estimated the
    number of hours he worked during the relevant time period and then multiplied those
    hours by his contracted GSA schedule rate” to arrive at a total of $645,730. 6 Id. (citing
    ECF No. 107-3 at 5-6; ECF No. 107-5).
    Defendant responds by arguing that the period of performance for the 2007 audit
    began on August 25, 2011, “when CMS asked [plaintiff] to draft a proposed audit plan,”
    and ran to November 30, 2011, “when CMS ‘killed the review.’” ECF No. 115 at 29
    (citations omitted). According to defendant, plaintiff’s personnel costs include the full
    year of 2011 for eight employees and Mr. Mucke as managing principal. See id. at 29-
    33. Further, defendant contends, plaintiff’s calculation of personnel costs is not based on
    data from its standard record keeping system, but is “ginned up ‘summaries’” and “over
    500 pages of year-end W-2s and payroll reports” that are not specific to the 2007 audit.
    Id. at 30. Likewise, plaintiff’s managing principal costs, according to defendant, are not
    supported by “any contemporaneous documentation from [plaintiff’s] ‘standard record
    keeping system,’” and rely instead on “the self-serving testimony of Mr. Mucke of the
    ‘estimated’ hour[s] he worked.” Id. at 32 (citations omitted) (emphasis in original).
    Plaintiff replies that the time period for its personnel costs is reasonable because
    the 2007 audit was the only audit it performed in 2011, and it was “developing secure
    6
    Plaintiff also, contradictorily, stated that its managing principal costs totaled $654,064.
    See ECF No. 107-2 at 13.
    9
    systems, developing audit and payment calculation processes, communication
    documents, and training materials for Part D contractors that [were] all related to the
    [2007 audit].” ECF No. 119 at 16. Further, plaintiff argues, it was contractually required
    to retain its “key personnel” until January 31, 2012, when the key personnel requirement
    in its contract was eliminated. See id. Plaintiff also contends that the estimates and
    summaries it provided were appropriate because it had no “other mechanism by which
    [plaintiff] could prove its managing principal’s work efforts.” Id. at 15. Plaintiff
    provided the summaries rather than “the over 1,958 email communications and 161,877
    documents analyzed to make these estimates.” Id.
    Plaintiff’s personnel costs fall under the reasonable charges category of recovery,
    and plaintiff is entitled to recover those personnel costs for the period of performance of
    the 2007 audit that it can prove using its standard record keeping system. See SWR, 
    15-1 BCA ¶ 35,832
     at 175,228. However, the parties dispute what the relevant period of
    performance was: plaintiff argues it was the time from the award of the task order to
    termination of the 2007 audit—January 13, 2011 to November 30, 2011—and defendant
    argues it was from the time the agency asked plaintiff to begin developing a process for
    review to termination—August 2011 to November 30, 2011. See ECF No. 119 at 6, 16;
    ECF No. 115 at 29. The only evidence plaintiff presents in support of its claim that the
    entirety of its work in 2011 was directed at the 2007 audit is Mr. Mucke’s affidavit. See
    ECF No. 119 at 16 (citing ECF No. 107-3 at 4). Defendant disputes plaintiff’s assertion,
    stating that plaintiff did not demonstrate that its “‘infrastructure’ was used solely ‘in
    connection with’ the [2007 audit] as opposed to the 20 total audits that [plaintiff]
    participated in.” ECF No. 115-2 at 2 (quoting ECF No. 107-1 at 1 (plaintiff’s statement
    of uncontroverted facts)). According to defendant, plaintiff did not begin work on the
    2007 audit until the agency requested that plaintiff draft a proposed audit plan. See ECF
    No. 115 at 29 (citing ECF No. 54-2 at 21 (email to plaintiff requesting that it draft an
    audit process)).
    In the court’s view, the agency did not award plaintiff the task order specifically to
    conduct the 2007 audit—it awarded plaintiff the task order to conduct audits for multiple
    years. See ECF No. 51-3 at 182-93 (PWS). Plaintiff’s bare statement that it expended its
    efforts in 2011 solely for the 2007 audit, without more, is insufficient to prove its claim.
    See SWR, 
    15-1 BCA ¶ 35,832
     at 175,230 (“An unsupported claim document that is
    submitted by a party seeking money is not proof of the claim that the party asserts.”)
    (citation omitted). Without evidence from plaintiff’s “standard record keeping system”
    connecting the claimed personnel costs to the 2007 audit, the court cannot find that no
    dispute of material fact exists here. 
    48 C.F.R. § 52.212-4
    (l); see also Anderson, 
    477 U.S. at 248
    .
    Likewise, without support from plaintiff’s standard record keeping system for
    plaintiff’s managing principal costs, the court cannot award plaintiff summary judgment
    on this issue. “[T]estimony of costs incurred without support from the contractor’s
    10
    standard record keeping system, is not sufficient to find recoverable costs.” First
    Division Design, 
    18-1 BCA ¶ 37,201
     at 181,102 (citing SWR, 
    15-1 BCA ¶ 35,832
     at
    175,230). Mr. Mucke’s affidavit, without more, therefore, is insufficient to support
    plaintiff’s claim for managing principal costs. Emails demonstrating that Mr. Mucke
    worked on the contract are also insufficient—they do not reflect hours recorded in a
    standard record keeping system. See id. at 181,103 (denying a claim for personnel
    compensation because the employee did not take a salary and the plaintiff could not
    demonstrate the hours he worked in a standard record keeping system). Because “a party
    seeking summary judgment always bears the initial responsibility of informing the [ ]
    court of the basis for its motion, and identifying those portions of ‘the pleadings,
    depositions, answers to interrogatories, and admissions on file, together with the
    affidavits, if any,’ which it believes demonstrate the absence of a genuine issue of
    material fact,” and because plaintiff has failed to properly support its motion here, the
    court must deny plaintiff’s motion on the issue of personnel costs for the 2007 audit.
    Celotex, 477 U.S. at 323.
    ii.       2010 Audit
    Plaintiff argues that it is entitled to $923,558.62 for the 2010 audit, based on “the
    number of hours that [plaintiff’s] personnel worked” on the audit. ECF No. 107-2 at 18.
    Plaintiff states that its “personnel did not maintain time sheets that attributed work to a
    particular project,” so Mr. Mucke “analyzed over 1,958 email communications and
    161,877 documents that [plaintiff’s] personnel had compiled, analyzed, and reviewed”
    for the 2010 audit to estimate that plaintiff’s personnel had worked 4,376 hours on the
    audit, which he then multiplied by “each person’s corresponding GSA schedule rate.” Id.
    at 18-19 (citing ECF No. 107-3 at 9; ECF No. 107-11 at 1-6).
    Defendant once again argues that plaintiff failed to support its claims with “any
    contemporaneous documentation” from its standard record keeping system. ECF No.
    115 at 39. Defendant notes that plaintiff’s only support for its claim is Mr. Mucke’s
    affidavit in which he “‘estimated’” the hours his employees worked by analyzing
    documents, which plaintiff did not attach to the affidavit. Id. Defendant further argues
    that plaintiff’s use of the GSA schedule rate is inappropriate because it “reflects a ‘price,’
    not a cost, and includes wages, benefits, overhead and profit.” Id. at 40 (citation
    omitted). Plaintiff replies to this point by noting that its contract was a GSA schedule
    contract, so its use of the rate was appropriate. See ECF No. 119 at 20.
    The court agrees with defendant that plaintiff’s claim fails for lack of support.
    “[T]estimony of costs incurred without support from the contractor’s standard record
    keeping system, is not sufficient to find recoverable costs.” First Division Design, 
    18-1 BCA ¶ 37,201
     at 181,102 (citing SWR, 
    15-1 BCA ¶ 35,832
     at 175,230). Mr. Mucke’s
    affidavit, without more, therefore, is insufficient to support plaintiff’s claim for personnel
    costs. Emails and documents demonstrating the employees’ work on the contract are
    likewise insufficient—they do not reflect hours recorded in a standard record keeping
    11
    system. See 
    id.
     (denying a claim for personnel compensation because the plaintiff could
    not demonstrate the hours worked in a standard record keeping system). Because “a
    party seeking summary judgment always bears the initial responsibility of informing the
    [ ] court of the basis for its motion, and identifying those portions of ‘the pleadings,
    depositions, answers to interrogatories, and admissions on file, together with the
    affidavits, if any,’ which it believes demonstrate the absence of a genuine issue of
    material fact,” and because plaintiff has failed to properly support its motion here, the
    court must deny plaintiff’s motion on the issue of personnel costs for the 2010 audit.
    Celotex, 477 U.S. at 323.
    2.      General and Administrative Costs 7
    Citing 
    48 C.F.R. § 52.249-2
    (g)—the FAR termination for convenience provision
    for fixed-price, non-commercial item contracts—plaintiff claims that it is entitled to
    $505,569.23 in general and administrative (G&A) costs for the 2007 audit. See ECF No.
    107-2 at 14-15. According to plaintiff, these costs include “travel, information
    technology services, computer equipment, professional services, and other miscellaneous
    office expense from the period January 2011 through January 2012.” 
    Id.
     at 15 (citing
    ECF No. 107-3 at 8; ECF No. 107-8; ECF No. 107-9; ECF No. 107-10).
    Defendant responds that plaintiff’s claimed costs are “not from its standard record
    keeping system” but are again summaries and a “data dump” of check registers and
    invoices that are not linked to the 2007 audit. ECF No. 115 at 33-34. Defendant argues
    that plaintiff bears the burden of proving its damages with “clear records from its
    standard record keeping system,” and it has not met that burden here. Id. at 34. Plaintiff
    does not reply specifically about its G&A costs, but argues generally that it “has provided
    income statements, check registers, and other financial reports generated from its
    standard record keeping system, QuickBooks.” ECF No. 119 at 14.
    G&A charges may be appropriate charges for compensation pursuant to FAR
    § 52.212-4(l). See SWR, 
    15-1 BCA ¶ 35,832
     at 175,231. In SWR, the Board noted that
    in performing a contract, a contractor incurs both direct and indirect costs—costs that can
    be attributed to a specific contract and those, such as “home office overhead,” that
    cannot—and concluded that indirect costs are appropriate for inclusion as reasonable
    charges. 
    Id.
     (citing Nicon, 
    331 F.3d at 878
    ). The charges, however, must be supported
    by documentation and an explanation of how they are allocated to the contract at issue.
    See First Division Design, 
    18-1 BCA ¶ 37,201
     at 181,104.
    7
    Plaintiff’s only claim pertaining to the 2010 audit appears to be its personnel costs related
    to that audit. Thus, the remaining costs addressed in this opinion all relate only to the 2007
    audit.
    12
    Here, in support of its claim, plaintiff provided a spreadsheet listing its claimed
    G&A charges and 464 pages of invoices, but failed to provide any explanation
    connecting the charges to the 2007 audit. ECF No. 107-2 at 15 (citing ECF No. 107-8;
    ECF No. 107-9). The court also notes that plaintiff included charges for “Travel,”
    “Contractor Wages,” “Misc G&A Exp,” and “Legal Fees,” in addition to the more
    standard G&A charges for “IT Services” and “Equipment & Fixtures” in its G&A
    documentation. ECF No. 107-8 at 3-5. Because plaintiff failed to provide any
    “explanation for how these indirect charges are allocated” to the 2007 audit, the court has
    “insufficient information to ascertain how these charges are recoverable as fair
    compensation” for the 2007 audit. First Division Design, 
    18-1 BCA ¶ 37,201
     at 181,104.
    Thus, plaintiff has failed to properly support its motion, and the court cannot grant
    plaintiff’s motion for summary judgment on the issue. See Celotex, 
    477 U.S. at 323
    .
    3.      Office Lease Costs
    Plaintiff argues that it is entitled to its office lease costs of $295,775.80 for the
    2007 audit. See ECF No. 107-2 at 15 (citing 
    48 C.F.R. § 52.249-2
    (g)(2)(i)). According
    to plaintiff, to house the employees needed for the 2007 audit, it “executed a multiyear
    lease for expanded office space” in April 2011, with a monthly lease cost of $9,200 and a
    monthly electricity cost of $1,300. 
    Id.
     In 2013, plaintiff moved to a smaller office and
    executed a sublease of its larger office, and in 2016, the lease expired and plaintiff once
    again moved to a smaller space. See id. at 15-16. Plaintiff calculated its lease costs
    based on its various leases, which it attached to its motion. See ECF No. 107-2 at 15-16
    (citing ECF No. 107-6).
    Defendant responds that plaintiff failed to demonstrate its claimed lease costs were
    directly and singly tied to the 2007 audit. See ECF No. 115 at 35. Defendant argues that
    plaintiff “cannot demonstrate that at the time it signed the five-year lease, it reasonably
    expected the 2007 audit would require five years to perform,” nor can it tie the full
    amount of the lease costs to the term of 2007 audit. Id. According to defendant, the first
    five months of the lease were rent-free and were followed by a reduced lease rate for ten
    additional months, making the cost of the lease for the month of November 2011—the
    month plaintiff worked on the 2011 audit—only $4,957.88. See id. (citing ECF No. 107-
    6 at 323 (lease)).
    Plaintiff replies that before it signed the office lease, defendant “informed
    [plaintiff] that 100% of its time would be dedicated to conducting CMS audits and
    recovering overpayments,” and it signed the lease to “meet the terms of its originally
    proposed PWS that contemplated ‘20-25 audit teams.’” ECF No. 119 at 19 (quoting
    without citation). Plaintiff further states that during the course of the contract, defendant
    “only permitted [plaintiff] to perform three audits covering seven different time periods.”
    Id. Plaintiff therefore argues that its “‘incurrence of an obligation to pay’” is sufficient to
    permit it to recover. Id. (quoting SWR, 
    15-1 BCA ¶ 35,832
     at 175,226).
    13
    While plaintiff’s lease costs may be reasonable charges compensable under FAR
    § 52.212-4(l), in the court’s view, plaintiff has not provided sufficient evidence from its
    standard record keeping system to sustain its claimed costs. As defendant points out, and
    plaintiff confirms, plaintiff signed the lease to “meet the terms” of the PWS, which was
    not specific to the 2007 audit. ECF No. 119 at 19. In addition to the parties’ dispute over
    the term of the 2007 audit—a material fact—plaintiff failed to explain how its lease costs
    are allocated to the 2007 audit. Thus, because there remain material facts in dispute, and
    because plaintiff failed to properly support its motion, the court cannot grant plaintiff’s
    motion for summary judgment on the issue of its office lease costs for the 2007 audit.
    See Celotex, 
    477 U.S. at 323
    .
    4.     Loan Interest Costs
    According to plaintiff, it executed a “business loan agreement” for $600,000 to
    fund its work on the contract and the funds were “used solely to pay for items associated
    with completing all activities necessary to conduct” the 2007 audit. ECF No. 107-2 at 16.
    Plaintiff states that the loan’s maturity date was extended due to its inability to make
    payments “as a result of CMS’s delays in executing” the contract. 
    Id.
     Plaintiff asserts
    that it paid $176,426.46 in interest on the loan to which it claims it is entitled. See 
    id.
    (citing 
    48 C.F.R. § 52.249-2
    (g)(2)(i); ECF No. 107-3 at 8; ECF No. 107-7 (exhibit
    containing loan cost summary, bank statements, and loan agreement)).
    Defendant responds that plaintiff “has no legal basis for this demand.” ECF No.
    115 at 36. Defendant points out that there is no provision for recovery of interest on
    borrowed money, and the FAR establishes that interest on borrowings is not an allowable
    cost. See 
    id.
     (citing FAR § 31.205-20).
    Plaintiff replies that FAR § 31.205-20 only applies to prohibit interest on
    borrowings “‘paid in connection with preparing prospectuses, and costs of preparing and
    issuing stock rights,’” and notes that a contractor may recover interest on funds borrowed
    because of the government’s delay in payment. ECF No. 119 at 18 (quoting FAR §
    31.205-20 and citing Gevyn Constr. Co. v. United States, 
    827 F.2d 752
    , 754 (Fed. Cir.
    1987)).
    The court agrees with defendant that plaintiff has no legal basis to request interest
    on a loan it executed to fund its work on the contract. Plaintiff’s characterization of FAR
    § 31.205-20 is incorrect—that provision states, “[i]nterest on borrowings (however
    represented), bond discounts, costs of financing and refinancing capital (net worth plus
    long-term liabilities), legal and professional fees paid in connection with preparing
    prospectuses, and costs of preparing and issuing stock rights are unallowable.” 
    48 C.F.R. § 31.205-20
    . In context, it is clear that the qualifiers plaintiff asserts exist on the payment
    of interest do not actually apply. The prohibition on the payment of interest on
    borrowings stands alone in this list; it is not qualified in any way. See 
    id.
     Similarly,
    plaintiff has not demonstrated that it borrowed the funds and paid interest because of a
    14
    delay in payment by defendant. Plaintiff states that it “executed a business loan
    agreement . . . to fund [plantiff’s] work under the Part D RAC.” ECF No. 107-2 at 16.
    “The cost of financing performance of a contract is unallowable.” First Division Design,
    
    18-1 BCA ¶ 37,201
     at 181,103 (citing FAR § 31.205-20). Plaintiff’s claim for loan
    interest must fail, and its motion for summary judgment must be denied on this issue.
    5.      Reasonable Profit
    Citing 
    48 C.F.R. § 52.249-2
    (g)(2)(iii), plaintiff argues that it should be awarded
    reasonable profits of $304,885.03 on the contract. See ECF No. 107-2 at 17. Plaintiff
    argues that, “[g]iven the magnitude of potential improper payments that [plaintiff] could
    have collected” if it had performed the audit, a profit rate of fifteen percent is
    “completely reasonable.” 
    Id.
     Plaintiff calculated its profit amount by multiplying its
    costs by fifteen percent, with the exception of the managing principal costs because the
    “GSA rate already contained a profit component.” 
    Id.
     at 17 & n.1.
    Defendant responds that plaintiff is “seeking anticipatory profits, which are not
    recoverable in a termination for convenience action.” ECF No. 115 at 36 (citing
    Praecomm, Inc. v. United States, 
    78 Fed. Cl. 5
    , 11 (2007)). Defendant argues that
    plaintiff bases its costs on “the entirety of its payroll, Livonia office lease, loan interest,
    G&A, and ‘settlement legal fee’ expenses,” “without any connection to ‘work performed’
    on the terminated audits.” Id. at 38. Defendant further asserts that, even if plaintiff is
    entitled to profits, its claim is “based upon pure speculation,” and its profit rate of fifteen
    percent “contravenes the FAR.” Id.
    Plaintiff replies that its use of a fifteen percent profit rate is reasonable because the
    contracting officer “agreed to apply a profit rate of 7.5% to [plaintiff’s] costs.” ECF No.
    119 at 19. Plaintiff further argues that its profits are not anticipatory because they are
    based on its costs, rather than on the “potential recoveries under the” 2007 and 2010
    audits. Id. at 19-20.
    Plaintiff is entitled to receive profits on “charges it recovers as part of its fair
    compensation, except for settlement expense and G&A indirect cost, which do not
    represent costs of preparations made for the terminated work.” SWR, 
    15-1 BCA ¶ 35,832
     at 175,233. Plaintiff, however, in explaining the reasonableness of its profit rate
    only noted that its contingency fees ranged from 7.5% to 20%, and argued that “[g]iven
    the magnitude of potential improper payments that [plaintiff] could have collected,” its
    fifteen percent rate is “completely reasonable.” ECF No. 107-2 at 17. This explanation
    is, in the court’s view, insufficient to justify the reasonableness of plaintiff’s profit rate.
    And, defendant vigorously disputes the reasonableness of that rate. See ECF No. 115 at
    36-39. Thus, a reasonable rate of profit is a material fact that remains in dispute in this
    case, and the court cannot grant plaintiff’s motion for summary judgment on this issue.
    15
    D.     Genuine Disputes of Material Fact Remain Regarding Plaintiff’s Claims for
    Compensation for Its Settlement Costs
    Settlement costs are those “incurred by the contractor for the preparation and
    presentation of settlement claims” to the contracting officer. Dellew, 
    15-1 BCA ¶ 35,975
    at 175,783. This includes reasonable attorneys’ fees for the preparation of a settlement
    proposal and negotiating the amicable resolution of the charges presented in the proposal.
    See SWR, 
    15-1 BCA ¶ 35,832
     at 175,231 (citing Dairy Sales Corp. v. United States, 
    593 F.2d 1002
    , 1005 (Ct. Cl. 1979)). “[N]o claim may be made for fees incurred in the
    preparation of claims which are not compensable.” Dairy Sales, 593 F.2d at 1006.
    Plaintiff argues, citing to 
    48 C.F.R. § 52.249-2
    (g)(3)(i), that it is entitled to its
    settlement costs, including its “legal fees as well as its principal[’]s time and effort in this
    lawsuit that preceded the [c]ourt’s March 23, 2020 Opinion and Order.” ECF No. 107-2
    at 19. Plaintiff contends that its “legal fees and time and effort” were “necessary
    precursors” to the agency taking the position that there was a termination for convenience
    and to plaintiff “obtaining the costs” for the 2007 and 2010 audits. Id. at 20.
    Plaintiff separates its costs into two phases—prior to the court’s March 2020
    opinion and after the March 2020 opinion. See id. at 20-21. Prior to the March 2020
    opinion, plaintiff alleges that it paid $617,307.56 to its law firm. See id. at 20 (citing
    ECF No. 107-12 (attorney invoices)). Plaintiff also asserts that its “internal work effort,”
    consisting of 5,481 hours of Mr. Mucke’s review of email and legal communications and
    “other documentation reviewed and revised by [Mr. Mucke] and [plaintiff’s] personnel,”
    cost $1,200,133.39. Id. at 20, 21 (citing ECF No. 107-11 at 62-65 (settlement expenses
    summary)).
    Plaintiff further seeks $183,433.83 for settlement costs between March 23, 2020
    and December 31, 2020, noting that it “also seeks settlement costs for activity after
    December 31, 2020, but does not yet have a final settlement cost amount that it can
    calculate.” Id. at 21 n.2. Similar to the costs identified prior to March 2020, plaintiff
    asserts that it paid its attorneys $29,025 and tracked 678 hours its employees spent that,
    according to plaintiff, cost $154,408.83. Id.
    Defendant responds that plaintiff has no legal basis on which to request its legal
    fees. See ECF No. 115 at 40-41. Defendant notes that “the cost to prosecute claims
    against the United States is not an allowable cost.” Id. at 40 (citing FAR § 31.205-
    47(f)(1)). Defendant argues that “[a]bsent a statute . . . or an express contractual
    provision, the United States is not liable for attorney fees.” Id. at 41.
    Plaintiff replies that defendant conflates the “costs pertaining to [plaintiff’s]
    termination settlement claims with that of [its] request for the reimbursement of
    reasonable charges associated with obtaining a retroactive termination for convenience.”
    ECF No. 119 at 21. Plaintiff argues that its efforts related to obtaining the court’s ruling
    16
    that the agency terminated its audits for convenience were “reasonably necessary” to
    allow it to prepare and present a claim to the contracting officer. Id. at 23 (quoting
    Dellew, 
    15-1 BCA ¶ 35,975
    ). The balance of its costs, according to plaintiff, are
    permissible because they are “associated with finalizing a termination settlement.” 
    Id.
    The court agrees with defendant that the costs associated with prosecuting a claim
    against the United States are not allowable costs, absent a waiver of sovereign immunity
    by statute or contractual provision. Plaintiff’s attempt to overcome the broad prohibition
    on the award of attorneys’ fees by casting the fees as reasonable charges necessary to
    allow it to present its claim to the contracting officer is unavailing. The path to an award
    of attorneys’ fees is narrow—the only compensable fees are those that are incurred in the
    preparation of a termination settlement proposal and its presentation to the contracting
    officer, excluding any fees incurred for the preparation of claims that are not
    compensable. Dairy Sales, 593 F.2d at 1006; SWR, 
    15-1 BCA ¶ 35,832
     at 175,231; see
    also 
    48 C.F.R. § 31.205-42
    (g)(1)(i)(A) (providing for the recovery of settlement
    expenses, including “[t]he preparation and presentation, including supporting data, of
    settlement claims to the contracting officer”).
    Plaintiff, however, has not properly supported its motion for summary judgment
    on this issue. While plaintiff provided a significant number of legal invoices, it failed to
    separate out the costs associated with the preparation of its termination settlement
    proposal and explain how those invoices are connected to that preparation. See ECF No.
    107-2 at 21. Because the court cannot make a determination of either the reasonableness
    of plaintiff’s legal fees or their relation to the preparation of its termination settlement
    proposal, plaintiff’s motion for summary judgment must be denied.
    Plaintiff’s claim for the cost of its “internal work effort” must also fail. ECF No.
    107-2 at 20. As with its legal fees, plaintiff has not parsed out the costs of preparing its
    termination settlement proposal, nor has it made any argument about the reasonableness
    of those costs. See ECF No. 107-2 at 20-21. In the court’s view, plaintiff’s claim that its
    internal work effort cost more than double that of its legal fees requires an explanation of
    the reasonableness of those costs that plaintiff simply has not provided. Therefore, the
    court must deny plaintiff’s motion for summary judgment on this issue.
    E.     Genuine Disputes of Material Fact Remain Regarding Plaintiff’s Claims for
    Interest Pursuant to the Contract Disputes Act
    Finally, plaintiff argues that it is entitled to interest under the CDA. See ECF No.
    107-2 at 21. Plaintiff asserts that the interest on its costs through December 31, 2020,
    amounts to $834,835.74. See 
    id.
     (citing ECF No. 107-13 at 14-32 (exhibit containing
    plaintiff’s CDA interest calculations)). Defendant responds that plaintiff both failed to
    prove its underlying claim and failed to properly calculate the date from which interest
    began to accrue. See ECF No. 115 at 42. Plaintiff responds that “[w]here there is a
    constructive termination for convenience finding years after [plaintiff] incurred
    17
    significant costs, it is only proper for the CDA interest to accrue from the date of the
    constructive termination for convenience as [plaintiff] was not in a position to submit a
    claim any earlier.” ECF No. 119 at 24.
    The court has not yet determined whether plaintiff is entitled to any compensation
    for the termination for convenience of the 2007 or 2010 audit, nor has it determined the
    amount of such compensation. Therefore, whether plaintiff is entitled to CDA interest
    and, if so, how much remains a disputed issue of fact, and the court cannot grant
    plaintiff’s motion for summary judgment on this issue.
    IV.    Conclusion
    Accordingly, for the foregoing reasons:
    (1)     Plaintiff’s motion for summary judgment, ECF No. 107, is DENIED;
    (2)     On or before December 3, 2021, the parties shall CONFER and FILE a
    notice attaching the parties’ proposed redacted version of this opinion,
    with any protectable information blacked out; and
    (3)     On or before December 3, 2021, the parties shall CONFER and FILE a
    joint status report proposing next steps in this litigation, and should the
    parties desire to pursue alternative dispute resolution, the parties shall
    indicate as much in their joint status report.
    IT IS SO ORDERED.
    s/Patricia E. Campbell-Smith
    PATRICIA E. CAMPBELL-SMITH
    Judge
    18