Yahya Technologies, LLC v. United States ( 2022 )


Menu:
  •              In the United States Court of Federal Claims
    No. 22-585C
    (E-Filed UNDER SEAL: May 31, 2022)
    (Reissued: June 27, 2022) 1
    )
    YAHYA TECHNOLOGIES, LLC                     )
    d/b/a Y-TECH, LLC,                          )
    )
    Plaintiff,                    )
    )      Competition in Contracting Act;
    v.                                 )      
    31 U.S.C. § 3553
    ; Stay of
    )      Performance; Temporary Restraining
    THE UNITED STATES,                          )      Order; Mootness; Bid Protest.
    )
    Defendant.                    )
    )
    Liza Craig, Washington, DC, for plaintiff. Joshuah Turner, of counsel.
    Daniel A. Hoffman, Trial Attorney, with whom were Brian M. Boynton, Principal
    Deputy Assistant Attorney General, Patricia M. McCarthy, Director, and Douglas K.
    Mickle, Assistant Director, Commercial Litigation Branch, Civil Division, United States
    Department of Justice, Washington, DC, for defendant. Stephani L. Abramson, National
    Archives and Records Administration, of counsel.
    OPINION
    CAMPBELL-SMITH, Judge.
    This bid protest involves a challenge to the decision by the National Archives and
    Records Administration (NARA or the agency) to override an automatic stay pursuant to
    1
    This opinion was filed under seal on May 31, 2022. See ECF No. 14. The parties were
    invited to identify source selection, propriety, or confidential material subject to deletion on the
    basis that the matter is protective or privileged. As of June 27, 2022, no proposed redactions
    were received from the parties. Thus, the sealed and the public versions of this opinion are
    identical, except for the publication date and this footnote.
    the Competition in Contracting Act (CICA), 
    31 U.S.C. § 3553
    (d)(3)(C)(i). See ECF No.
    1 at 1 (complaint).
    Presently before the court are plaintiff’s motions for a temporary restraining order
    (TRO) or preliminary injunction, which plaintiff filed on May 27, 2022. See ECF No. 4
    (motions); ECF No. 5 (memorandum in support). The parties argued the motions during
    the initial status conference in this matter, and defendant filed a response to the motions
    reducing its argument to writing on May 31, 2022, see ECF No. 10, and plaintiff filed a
    reply in support of the motions on the same day, see ECF No. 13.
    The motions are now fully briefed and ripe for decision. The court has considered
    all of the parties’ arguments and addresses the issues that are pertinent to the court’s
    ruling in this opinion. For the following reasons, the motions for a temporary restraining
    order or preliminary injunction are DENIED and plaintiff’s complaint is DISMISSED as
    moot.
    I.     Background
    Plaintiff is a small, minority-owned business that “provides Enterprise Information
    Technology (“IT”) Solutions, which consists of Software Development, Information
    Assurance, Cybersecurity, Cloud Services, Supply Chain Management, Program
    Management, and Helpdesk/Service Desk Support.” ECF No. 1 at 1. Plaintiff has
    provided these services to the agency since 2019, when it was awarded the NARA
    Information Technology and Telecommunications Support Services contract. See 
    id. at 2
    . Plaintiff is currently performing under a six-month option to extend services, which
    ends May 31, 2022. See 
    id.
    In July 2021, the agency informed plaintiff that it would not exercise another
    option period and would instead recompete the contract. See 
    id.
     In December 2021, the
    agency issued a request for quotations under full and open competition that contained,
    according to plaintiff, “restrictive terms.” 
    Id. at 2-3
    . Plaintiff protested that solicitation
    at the Government Accountability Office (GAO) and, on March 22, 2022, the agency
    informed the GAO that it intended to take corrective action by cancelling the solicitation
    and issuing a new one. See 
    id. at 3
    . The GAO, therefore, dismissed plaintiff’s protest.
    See 
    id.
    The agency, however, did not immediately reissue a solicitation, instead awarding,
    pursuant to its 8(a) authority, a sole source bridge contract to an Alaska Native
    Corporation on May 13, 2022. See 
    id. at 3-4
    . Performance on the bridge contract began
    on May 16, 2022. See 
    id.
    2
    Plaintiff filed a second GAO protest on May 20, 2022, alleging that the agency
    failed to take corrective action and issued the bridge contract in bad faith. 2 See 
    id.
    Plaintiff’s GAO filing triggered an automatic Competition in Contracting Act (CICA)
    stay of performance under the contract. See 
    id.
     On May 25, 2022, the agency notified
    plaintiff that it intended to override the CICA stay and allow performance to proceed.
    See 
    id.
     The agency determined, in a four-page document, that continued performance of
    the bridge contract “is in the best interests of the United States.” See ECF No. 5-1 at 30
    (Justification for Continued Performance of Awardee). The justification is concise and
    consists, in relevant part, of the following:
    Continued contract performance of Award No. 88310322P00039 is in the
    best interests of the United States in accordance with FAR 33.104(c)(2)(i).
    The decision to override the stay is based on contract performance being in
    the best interests of the United States. Notwithstanding contract performance
    over the past two-years, within the past six-months NARA has endured three
    service outages of varying degrees, and more recently NARA has identified
    significant security vulnerabilities within its information technology systems
    that went unresolved by the incumbent. The outages and unresolved
    vulnerabilities present a risk to NARA's infrastructure and its ability to meet
    the Agency’s core mission.
    The United States has come under increased attack by foreign states. These
    entities exploit common vulnerabilities and exposures (CVE) seeking access
    to vital Government systems and information. The Department of Homeland
    Security (DHS) noted these vulnerabilities are among a specific set of
    vulnerabilities that are actively exploited by Russian Advanced Persistent
    Threat (APT) groups. The Cybersecurity and Infrastructure Security Agency
    (CISA) notified NARA of these vulnerabilities November 2021, with
    subsequent notifications in March 2022. These vulnerabilities went
    unresolved by the incumbent for nearly five months, a condition that
    presented a significant security risk to the Agency.
    Consequently, due to deficiencies in the incumbent’s performance, NARA
    determined it is not in the best interest of the United States to exercise
    additional performance periods beyond May 31, 2022, the end of the current
    option. But because the services are essential to the Agency’s operation,
    NARA must have a contract in place to perform these services. Thus, it is
    necessary to override the statutory stay.
    2
    In its complaint, plaintiff states that it filed its second GAO protest on May 20, 2011. See
    ECF No. 1 at 4. Given the context of the case and the timeline at issue, the court assumes that
    plaintiff intended to provide the date as May 20, 2022.
    3
    
    Id. at 30-31
    .
    On May 27, 2022, plaintiff filed the instant protest challenging the agency’s
    decision to override the CICA stay. See ECF No. 1. Plaintiff alleges that if the agency is
    not enjoined from overriding the stay, it will go out of business and will not be able to
    compete for the contract when it is recompeted. See 
    id. at 7
    . Specifically, plaintiff
    argues that “absent an injunction, [plaintiff] will cease to exist shortly after May 31,
    2022,” ECF No. 5 at 21, and its “ability to maintain its highly skilled staff,” will likely be
    “destroy[ed],” 
    id. at 22
    .
    The court convened an initial status conference with the parties on May 31, 2022.
    See ECF No. 11 (order memorializing the status conference). During the conference,
    both parties set forth their respective arguments regarding plaintiff’s request for a TRO or
    preliminary injunction. See 
    id. at 2
    . The court then set a compressed briefing schedule to
    permit the parties to reduce their arguments to writing. See 
    id. at 3
    .
    II.    Legal Standards
    A.       Bid Protest Jurisdiction
    In its complaint, plaintiff invokes this court’s bid protest jurisdiction. See ECF
    No. 1 at 5. This court’s bid protest jurisdiction is based on the Tucker Act, which gives
    the court authority:
    to render judgment on an action by an interested party objecting to a
    solicitation by a Federal agency for bids or proposals for a proposed contract
    or to a proposed award or the award of a contract or any alleged violation of
    statute or regulation in connection with a procurement or a proposed
    procurement . . . . without regard to whether suit is instituted before or after
    the contract is awarded.
    
    28 U.S.C. § 1491
    (b)(1). The Tucker Act also states that the court may grant “any relief
    that the court considers proper, including . . . injunctive relief.” 
    28 U.S.C. § 1491
    (b)(2).
    To establish jurisdiction, a plaintiff must demonstrate that it is an “interested
    party.” 
    28 U.S.C. § 1491
    (b)(1). The United States Court of Appeals for the Federal
    Circuit has held that the “interested party” requirement “imposes more stringent standing
    requirements than Article III.” Weeks Marine, Inc. v. United States, 
    575 F.3d 1352
    , 1359
    (Fed. Cir. 2009). Though the term “interested party” is not defined by the statute, courts
    have construed it to require that a protestor “establish that it ‘(1) is an actual or
    prospective bidder and (2) possess[es] the requisite direct economic interest.’” See 
    id.
    (quoting Rex Serv. Corp. v. United States, 
    448 F.3d 1305
    , 1308 (Fed. Cir. 2006))
    4
    (alteration in original). Although “standing is not often discussed at length in CICA stay
    override cases,” the court makes the same inquiry into actual or prospective bidder status
    and direct economic interest in such circumstances. PMTech, Inc. v. United States, 
    95 Fed. Cl. 330
    , 348 (2010).
    B.     Temporary Restraining Order Relief
    A temporary restraining order is an “‘extraordinary and drastic remedy, one that
    should not be granted unless the movant, by a clear showing, carries the burden of
    persuasion.’” Jones Automation, Inc. v. United States, 
    92 Fed. Cl. 368
    , 370 (2010)
    (quoting Mazurek v. Armstrong, 
    520 U.S. 968
    , 972 (1997)). In evaluating whether a
    temporary restraining order or a preliminary injunction is appropriate, the court considers
    whether the moving party has demonstrated that: (1) it is likely to succeed on the merits;
    (2) it will be irreparably harmed without injunctive relief; (3) the balance of hardships
    tips in its favor and (4) the public interest favors the grant of injunctive relief. Safeguard
    Base Operations, LLC v. United States, 
    140 Fed. Cl. 670
    , 686 (2018) (citing Trebro Mfg.,
    Inc. v. Firefly Equip., LLC, 
    748 F.3d 1159
    , 116 (Fed. Cir. 2014)). “No single factor is
    determinative, and ‘the weakness of the showing regarding one factor may be overborne
    by the strength of the others.’” Contracting Consulting Eng’g LLC v. United States, 
    103 Fed. Cl. 706
    , 709 (2012) (quoting FMC Corp. v. United States, 
    3 F.3d 424
    , 427 (Fed. Cir.
    1993)). It is also true, however, that “the absence of an adequate showing with regard to
    any one factor may be sufficient, given the weight or lack of it assigned the other factors”
    to justify denial of a preliminary injunction or temporary restraining order. Safeguard,
    140 Fed. Cl. at 687 (quoting FMC Corp., 
    3 F.3d at 427
    ).
    III.   Analysis
    A.     Defining the Status Quo
    In this case, plaintiff challenges the agency’s decision to override a CICA stay,
    and has standing to do so as the incumbent contractor performing the work at issue in the
    bridge contract that was stayed by plaintiff’s GAO protest. See ECF No. 1 at 2;
    PMTech,, 95 Fed. Cl. at 348. The CICA states, in relevant part, as follows:
    (A)    If the Federal agency awarding the contract receives notice of a protest
    in accordance with this section during the period described in
    paragraph (4)—
    (i)   the contracting officer may not authorize performance of the
    contract to begin while the protest is pending; or
    5
    (ii) if authorization for contract performance to proceed was not
    withheld . . . before receipt of the notice, the contracting officer
    shall immediately direct the contractor to cease performance
    under the contract and to suspend any related activities that may
    result in additional obligations being incurred by the United
    States under that contract.
    (B)    Performance and related activities suspended pursuant to
    subparagraph (A)(ii) by reason of a protest may not be resumed while
    the protest is pending.
    (C)    The head of the procuring activity may authorize the performance of
    the contract (notwithstanding a protest of which the Federal agency
    has notice under this section)—
    (i)    upon a written finding that—
    (I) performance of the contract is in the best interests of the
    United States; or
    (II) urgent and compelling circumstances that significantly
    affect interests of the United States will not permit waiting
    for the decision of the Comptroller General concerning the
    protest; and
    (ii)   after the Comptroller General is notified of that finding.
    
    31 U.S.C. § 3553
    (d)(3).
    The “‘automatic stay is intended to preserve the status quo during the pendency of
    the protest so that an agency would not cavalierly disregard GAO’s recommendations to
    cancel the challenged award,’ thereby ‘preserv[ing] competition in contracting and
    ensur[ing] a fair and effective process at the GAO.’” Reilly’s Wholesale Produce v.
    United States, 
    73 Fed. Cl. 705
    , 710 (2006) (quoting Advanced Sys. Dev., Inc. v. United
    States, 
    72 Fed. Cl. 25
    , 31 (2006)) (alterations in original).
    In its motions, plaintiff argues that the stay is essential to preserve the status quo.
    See ECF No. 5 at 22-23 (arguing that maintenance of the status quo is the purpose of the
    CICA stay and without it, plaintiff will suffer irreparable harm). Plaintiff implies
    throughout its motions, without stating explicitly, that the status quo for this procurement
    is plaintiff’s continued performance under its 2019 contract and a suspension of the
    bridge contract. See generally ECF No. 5. Plaintiff also specifically states in its reply in
    support of its motions that “Congress enacted the CICA Stay to maintain the ‘status quo,’
    6
    pending a thorough review of the acquisition . . . . That is all [plaintiff] wants here, the
    opportunity to continue performing pending the outcome of the GAO protest.” ECF No.
    13 at 4 n.2.
    Defendant argues, however, that plaintiff “seeks to alter the status quo, not
    maintain it.” ECF No. 10 at 3 (capitalization altered). According to defendant, plaintiff
    “has known since July 2021 that NARA intended to recompete the contract in order to
    restructure the contract.” 
    Id.
     Defendant contended during the initial status conference
    that this is, in fact, the status quo—plaintiff’s contract ends on May 31, 2022, and it has
    the opportunity to compete for the new contract. See ECF No. 11 at 2. Defendant thus
    argues that the corrective action the agency intends to take will allow plaintiff to compete
    for the contract and the status quo has not changed because of the override of the stay.
    See ECF No. 10 at 3.
    In the court’s view, the defendant’s definition of the status quo is the correct one.
    Plaintiff has known since July 2021 that the agency would not exercise additional options
    to extend its contract and that it would need to recompete for the new contract should it
    wish to continue working with the agency. See ECF No. 1 at 2; ECF No. 5 at 6. Thus,
    the status quo in this matter is that plaintiff’s contract ends on May 31, 2022. The court
    can see no reason, and plaintiff has not presented a reason, that the agency is under an
    obligation to continue plaintiff’s contract beyond May 31, 2022, simply because it is still
    in the process of recompeting the contract.
    The court further notes that plaintiff’s GAO protest of the bridge contract does not
    redefine the status quo. The outcome of the GAO protest simply does not dictate whether
    plaintiff would continue its performance beyond May 31, 2022. That the agency issued a
    sole source bridge contract pursuant to its 8(a) authority, and whether that contract was
    issued in bad faith, is a separate matter to the continuation of plaintiff’s contract. In other
    words, whether the bridge contract is stayed or the stay is overridden does not necessarily
    bear on the continuation of plaintiff’s performance.
    B.     Plaintiff’s Protest of the CICA Stay Override Is Moot
    To address an issue brought before the court, “an ‘actual controversy’ must exist
    not only ‘at the time the complaint is filed,’ but through ‘all stages’ of the litigation.”
    Already, LLC v. Nike, Inc., 
    568 U.S. 85
    , 90-91 (2013) (quoting Alvarez v. Smith, 
    558 U.S. 87
    , 92 (2009)). “A case becomes moot—and therefore no longer a ‘Case’ or
    ‘Controversy’ for purposes of Article III—‘when the issues presented are no longer ‘live’
    or the parties lack a legally cognizable interest in the outcome.’” 
    Id. at 91
     (quoting
    Murphy v. Hunt, 
    455 U.S. 478
    , 481 (1982) (per curiam)). “‘The test for mootness . . . is
    whether the relief sought would, if granted, make a difference to the legal interests of the
    parties.’” Nasatka v. Delta Sci. Corp., 
    58 F.3d 1578
    , 1580-81 (Fed. Cir. 1995) (quoting
    Air Line Pilots Ass’n Int’l v. UAL Corp., 
    897 F.2d 1394
    , 1396 (7th Cir. 1990))
    7
    (alteration in original). Thus, in determining whether a case should be dismissed as
    moot, the court must “examine whether the decision of any disputed issue ‘continues to
    be justified by a sufficient prospect that the decision will have an impact on the parties.’”
    Id. at 1581 (quoting Flagstaff Med. Ctr., Inc. v. Sullivan, 
    962 F.2d 879
    , 884 (9th Cir.
    1992)); see also Church of Scientology of Cal. v. United States, 
    506 U.S. 9
    , 12, (1992)
    (stating that a case is not moot if the “court can fashion some form of meaningful relief”
    (emphasis omitted)); McTech Corp. v. United States, 
    105 Fed. Cl. 726
    , 731 (2012)
    (“[W]here a defendant’s actions have eliminated the possibility of meaningful relief, the
    case ordinarily should be dismissed as moot.”).
    Here, the court cannot fashion any meaningful relief for plaintiff. Plaintiff seeks
    to continue its current performance until its pending GAO protest is decided. See ECF
    No. 13 at 4 n.2. According to plaintiff, if it is not permitted to continue performance it
    may “cease to exist,” irreparably harming it. See ECF No. 5 at 21; see also ECF No. 13
    at 3 (stating that if it is not permitted to continue performing for the agency it “will be
    unable to compete for future work as it will have been put out of business and almost all
    [of plaintiff’s] employees will be consumed by” the bridge contractor). By plaintiff’s
    own complaint, however, the CICA stay applies only to the bridge contract. See ECF
    No. 1 at 4 (stating that the agency “was obligated to suspend performance of the Bridge
    Contract”).
    Even if the court were to order the agency to maintain the CICA stay and the
    status quo, as the court determined above, the status quo in this case is that plaintiff’s
    contract expires on May 31, 2022. The only relief the court can order in this case is that
    the bridge contract be suspended pursuant to the CICA stay pending the GAO’s decision
    in plaintiff’s protest. This relief does not accomplish, as plaintiff assumes, the
    continuation of plaintiff’s performance of the work for more than a matter of hours. The
    court cannot order the agency to exercise another option on plaintiff’s contract or
    otherwise permit plaintiff to continue performing as plaintiff requests—and indeed states
    is necessary for the continuation of its business. See ECF No. 13 at 4 n.2; ECF No. 5 at
    21. This appears to the court, however, to be the only meaningful relief for plaintiff.
    Merely suspending the bridge contract does not afford plaintiff the work it deems
    necessary for the continuation of its business. The court can conceive of no other relief
    that it has the authority to fashion under the circumstances that would meaningfully
    address plaintiff’s complaint.
    Thus, because the court cannot fashion any meaningful relief for plaintiff, its claim
    is moot and its case must be dismissed. See Nasatka, 
    58 F.3d at 1580-81
    ; see also Mail
    Transp., Inc. v. United States, 
    153 Fed. Cl. 205
    , 214-15 (2021) (finding that plaintiffs’
    claims were not moot where the expiration of their contract did not “eliminate the
    possibility of an effective remedy were plaintiffs to prevail in their protest”). As such,
    the court does not reach the merits of plaintiff’s motions for a TRO or preliminary
    injunction, and its motions must be denied.
    8
    IV.   Conclusion
    Accordingly, for the foregoing reasons:
    (1)   Plaintiff’s motions for a temporary restraining order or preliminary
    injunction, ECF No. 4, are DENIED;
    (2)   The clerk’s office is directed to ENTER final judgment in defendant’s
    favor DISMISSING plaintiff’s complaint, without prejudice, as moot; and
    (3)   On or before June 21, 2022, the parties are directed to CONFER and
    FILE a notice attaching the parties’ agreed upon redacted version of this
    opinion, with all competition-sensitive information blacked out.
    IT IS SO ORDERED.
    s/Patricia E. Campbell-Smith
    PATRICIA E. CAMPBELL-SMITH
    Judge
    9