Sarro & Associates, Inc. v. United States ( 2021 )


Menu:
  •           In the United States Court of Federal Claims
    No. 19-691C
    (Filed: January 15, 2021)
    )
    SARRO & ASSOCIATES, INC.,                        )
    )
    Plaintiff,                  )
    )
    v.                                     )
    )
    THE UNITED STATES,                               )
    )
    Defendant.                 )
    )
    Patrick R. Quigley, Bradley Arant Boult Cummings LLP, Washington, D.C., for Plaintiff.
    Igor Helman, United States Department of Justice, Civil Division, Washington, DC, for
    Defendant. With him on the briefs were Joseph H. Hunt, Assistant Attorney General,
    Civil Division, Robert E. Kirschman, Jr., Director, and Claudia Burke, Assistant Director,
    Commercial Litigation Branch, Civil Division, United States Department of Justice,
    Washington, DC.
    OPINION AND ORDER
    SOLOMSON, Judge.
    This case arises under a contract between Plaintiff, Sarro & Associates, Inc.
    (“Sarro”), and Defendant, the United States, acting by and through the United States
    Geological Survey (“USGS” or the “Agency”), for the installation of a generator at the
    USGS facility in Flagstaff, Arizona (the “City”). During the performance of that
    contract, Sarro incurred unanticipated, increased costs complying with the City’s
    permitting requirements, which necessitated Sarro having to reperform substantial
    parts of the contract. Sarro submitted a claim to the USGS contracting officer (“CO”) for
    an equitable adjustment pursuant to the Contract Disputes Act (“CDA”), 
    41 U.S.C. § 7103
    , which the CO denied. Sarro now brings claims in this Court against the United
    States for damages arising from an alleged breach of the implied duty to disclose
    superior knowledge, breach of contract, cardinal change, and breach of the implied
    duty of good faith and fair dealing. The government moved to dismiss Sarro’s
    amended complaint pursuant to Rules 12(b)(1) and 12(b)(6) of the Rules of the Court of
    Federal Claims (“RCFC”) for, respectively, lack of jurisdiction and failure to state a
    claim upon which relief may be granted. For the reasons explained below, the Court
    grants the government’s motion to dismiss Plaintiff’s amended complaint – the first
    count for lack of jurisdiction and the three remaining counts for failure to state a claim –
    in its entirety.
    I.     Factual And Legal Background1
    A.     The Contract
    On September 12, 2016, USGS2 awarded a firm-fixed-price contract, No.
    G16PX01471, to Sarro, a Colorado-based small business that specializes in installing
    electrical and mechanical systems. ECF No. 16 (“Am. Compl.”) ¶¶ 1–3, 13; see ECF No.
    23-1 (“Def. App.”) at 24–25. The contract required Sarro to install a permanent 130Kw
    diesel generator at USGS’s astrogeology facility in Flagstaff, Arizona and provide all
    essential electrical connections. Am. Compl. ¶¶ 6, 14; Def. App. at 2. The statement of
    work (“SOW”) delineated technical specifications for the generator, installation and
    construction requirements, and various work instructions. Def. App. at 13–16. The
    SOW expressly provided that the City “as owner of land and building requires review
    and approval of all drawings/specs” and that “[u]pon completion of the work, the
    Contractor shall deliver an original marked set of As-Built Drawings.” 
    Id.
     at 15–16.
    The contract also contained numerous standard clauses and provisions, 
    id.
     at 3–
    13, including Federal Acquisition Regulation (“FAR”) 52.236-7, Permits and
    Responsibilities (“P&R clause”), which provides, in relevant part:
    The Contractor shall, without additional expense to the
    Government, be responsible for obtaining any necessary
    1For the purpose of resolving the pending motion to dismiss, the facts alleged in Plaintiff’s
    amended complaint are assumed to be true, and do not constitute factual findings by the Court.
    See, infra, Section II. The Court also relies upon exhibits appended to Defendant’s motion to
    dismiss and Plaintiff’s response brief, which contain documents that are referenced to in the
    amended complaint. See Dimare Fresh, Inc. v. United States, 
    808 F.3d 1301
    , 1306 (Fed. Cir. 2015)
    (holding that courts may consider “matters incorporated by reference or integral to the claim”).
    RCFC 9(k) requires that, in contract dispute cases, a party must either describe the relevant
    contract provisions or annex a copy of the contract to the pleading. See Terry v. United States,
    
    103 Fed. Cl. 645
    , 647 n.1 (2012) (relying on “an exhibit appended to defendant’s motion
    containing plaintiff’s concession contract”).
    2 USGS is a federal agency within the Department of the Interior whose mission is to “develop
    new methods and tools to supply timely, relevant, and useful information about the Earth and
    its processes.” https://www.usgs.gov/ (last visited Dec. 31, 2020); see 
    43 U.S.C. §§ 31
     et seq.
    -2-
    licenses and permits, and for complying with any Federal,
    State, and municipal laws, codes, and regulations applicable
    to the performance of the work. . . . The Contractor shall also
    be responsible for all materials delivered and work performed
    until completion and acceptance of the entire work . . . .
    Def. App. at 5. The contract also incorporated by reference FAR 52.236-11, Use and
    Possession Prior to Completion, which provides, in relevant part, that “the Contracting
    Officer shall furnish the Contractor a list of items of work remaining to be performed or
    corrected on those portions of the work that the Government intends to take possession
    of or use [, but t]he Government’s possession or use shall not be deemed an acceptance
    of any work under the contract.” Def. App. at 5. Additionally, the contract
    incorporated by reference FAR 52.243-5, Changes and Changed Conditions (“Changes
    clause”), which requires the contracting officer to make an equitable adjustment to the
    contract when the contracting officer “in writing, orders changes in the drawings and
    specifications within the general scope of the contract.” Def. App. at 5.
    B.     Sarro’s Performance Of The Contract
    In December 2016, the CO directed Sarro to obtain a permit from the City before
    installing the generator. Am. Compl. ¶ 21. On December 2, 2016, Sarro, through its
    local subcontractor, Kirby Electric, LLC, applied for an “over the counter” permit. 
    Id. ¶ 33
    ; see ECF No. 27-1 (“Pl. Resp. App.”) at 6. The permit application included a
    disclaimer that “[t]he granting of a permit does not presume to give authority to violate
    or cancel the provisions of any other state or local law regulating construction or the
    performance of construction.” Pl. Resp. Br. at 6.
    Three days later, on December 5, 2016, the City issued Permit No. BP-16-02063
    (the “2016 Permit”). Am. Compl. ¶ 34. The 2016 Permit provided that it was “over the
    counter” and included an acknowledgment that the contractor “agree[s] to comply with
    all applicable codes of the City of Flagstaff and the State of Arizona . . . [and allows] all
    pertinent City personnel access [to the] property at any time deemed necessary to
    inspect work being done relating to this permit.” Pl. Resp. App. at 9 (capitalization
    removed). The City never requested “any engineering drawings or specifications
    relating to the generator installation” during the permitting process; nor did the Agency
    make any such demands. Am. Compl. ¶ 34.
    For the type of electrical work that Sarro needed to perform, however, it should
    have applied for a different permit. Def. App. at 25–27. The City requires a
    “commercial” permit for significant electrical projects, including, as relevant here, the
    permanent installation of a generator. 
    Id.
     As part of the application process for a
    -3-
    commercial permit, the City mandates the submission of certain electrical drawings. 
    Id. at 27
    . However, this error went unnoticed by Sarro and the City and, unfortunately,
    was discovered only much later, as described below. 
    Id. at 25
    ; see Pl. Resp. App. at 35–
    36. There is no allegation that the Agency had any control over the City’s permitting
    process.
    On December 19, 2016, Sarro began performing the contract. Am. Compl. ¶ 39.
    On January 20, 2017, Sarro completed installing the generator and all necessary
    electrical connections. Am. Compl. ¶ 42. Throughout this time, the City inspected
    Sarro’s work on five separate occasions but did not identify any problems with Sarro’s
    permit or installation. 
    Id.
     ¶¶ 43–44. On January 25, 2017, a representative from the
    generator manufacturer commissioned the generator and, six days later, on January 31,
    the City approved Sarro’s work and closed the 2016 Permit. 
    Id.
     ¶¶ 47–48; Pl. Resp. App.
    at 10.
    Following the commissioning of the generator, USGS paid Sarro nearly the entire
    contract price but withheld $2,000 until Sarro completed certain “punch list” items.
    Am. Compl. ¶ 50. On March 17 and 27, 2017, the CO sent Sarro various punch list items
    for completion. 
    Id.
     ¶¶ 51–52; Pl. Resp. App. at 20–22. On March 30, 2017, the CO sent
    Sarro a third punch list that included, among other things, a requirement that Sarro
    “provide AutoCAD As-built Construction Drawings showing details of layout, trench
    depth and path, location of Generator, wire and conduit specifications.” Am. Compl.
    ¶¶ 54, 56; Pl. Resp. App. at 24–25. That same day, the CO forwarded to Sarro an email
    from the City, which provided the following notice:
    The city will be on site Tuesday, April 3rd at lpm with the
    inspection team to determine the extent of the incomplete
    work performed. Per IBC and NEC, the work must be
    completed and we are going to revoke the building permit if
    necessary based on the findings. The requirements in code
    require a fire barrier that is breached to [sic] re-established by
    the contractor. Other issues may include the supporting of
    conduit, cable installation, labeling of electrical components
    and panelboards schedule updates.
    
    Id. at 23
    . On April 3, 2017, Sarro, the USGS Technical Liaison, and a City inspector
    visited the USGS facility and viewed the work that Sarro had performed. Am. Compl.
    -4-
    ¶¶ 58–59. Following the inspection, the City inspector informed Sarro “that a
    significant portion of the work would have to be done all over again.” 
    Id. ¶ 58
    .
    On April 27, 2017, Sarro, the CO, the USGS Technical Liaison, and certain
    unnamed City officials met to discuss Sarro’s work. 
    Id. ¶ 60
    . During the meeting, Sarro
    noticed that the “City officials had electrical engineering drawings in their possession,
    which they refused to share with [Sarro].” 
    Id. ¶ 61
    . The CO told Sarro that the
    government should have included the drawings in the Solicitation, but they had “not
    made it in.” 
    Id. ¶ 62
    . That same day, the City revoked the 2016 Permit. 
    Id. ¶ 63
    . On
    May 3, 2017, the City informed the CO, through a correction notice, that the generator
    installation was in violation of numerous state and local ordinances and instructed that
    “no more work shall be done upon these premises until the above corrections have been
    made.” 
    Id.
     ¶¶ 65–66; Pl. Resp. App. at 28–29. The correction notice further required
    Sarro to hire an electrical engineer “to design and check all requirements, calculations,
    and installations” and that plans would need to be submitted to the City “prior to any
    work commencing related to fixes, repairs of modifications” to the project. 
    Id.
     The CO
    emailed the correction notice to Sarro. 
    Id. at 31
    . This required Sarro:
    (a) paying a much higher permit fee than Kirby had already
    paid; (b) complying with 2011 [National Electrical Code
    (“NEC”)] wiring standards instead of the 2017 NEC standards
    that Sarro had followed and, as a result swapping the already
    installed 4/0 gauge wiring for thinner 3/0 gauge wiring; (c)
    obtaining expensive engineering drawings; and (d) paying
    similar, related additional expenses for work that had already
    been completed and accepted by the City months earlier.
    Am. Compl. ¶ 68. On December 13, 2017, the City issued Sarro, through its new local
    subcontractor, Nitro Electric, a commercial permit, Permit No. BP-17-02039. Def. App.
    at 25. On January 19, 2018, Sarro completed the project. 
    Id.
    C.     Sarro’s CDA Claim
    On April 13, 2018, Sarro submitted a certified claim to the CO, seeking an
    equitable adjustment in accordance with the contract’s Changes clause, FAR 552.243-71,
    and the CDA, 
    41 U.S.C. § 7103
    , in the amount of $33,557.08.3 Am. Compl. ¶ 74; Def.
    3The parties refer to Sarro’s CDA claim as “certified.” Am. Compl. ¶ 74; Def. Mot at 2. Indeed,
    Sarro noted in its CDA claim that the “FAR states that we must certify this claim.” Def. App. at
    19 (emphasis added). The CDA and implementing FAR provision, however, only require
    certification for claims over $100,000. 
    41 U.S.C. § 7103
    (b)(1); FAR 52.233-1(c), (d)(2). Because
    Sarro only seeks $33,557.08, it was not required to certify its claim.
    -5-
    App. at 19–23. Sarro sought “[r]eimbursement for costs associated with unilateral
    errors made by the City of Flagstaff and omissions, errors, discrepancies, and
    ambiguous drawing and specs which were not contemplated in the original contract
    price/bid.” 
    Id. at 19
    . On May 10, 2018, the CO issued his final decision, denying Sarro’s
    certified claim. Am. Compl. ¶ 75; Def. App. at 24–28.
    D.     Procedural History
    On May 6, 2019, Sarro, acting pro se, filed a complaint in this Court. ECF No. 1.4
    On July 18, 2019, the case was stayed so Sarro could seek counsel. ECF No. 9. After
    obtaining counsel, on October 14, 2019, Sarro filed an amended complaint. Am. Compl.
    at 1, 12. Sarro’s amended complaint contains four claims. 
    Id.
     at 12–16. Sarro alleges
    that USGS: (1) failed to disclose its superior knowledge regarding “the difficulties with
    obtaining permits from the City or the difficulties experienced by prior Agency
    contractors in obtaining permits from the City”; (2) breached the contract’s Changes
    clause by requiring compliance with the City’s “unreasonable” permitting
    requirements, which increased the costs, without making an equitable adjustment; (3)
    breached the contract by requiring compliance with the City’s permitting requirements,
    which “drastically alter[ed] the quality, character, nature or type of work contemplated
    by the original Purchase Order,” thus resulting in a cardinal change; and (4) breached
    the implied duty of good faith and fair dealing by not providing Sarro with “drawings
    and specifications [that] were required” to complete the project and not “disclos[ing]
    the prior difficulties encountered by other USGS contractors in obtaining permits from
    the City.” 
    Id.
     Accordingly, Sarro seeks $33,557.08 for additional costs incurred while
    completing the project. 
    Id. at 17
    .
    On January 3, 2020, the government moved to dismiss the amended complaint
    pursuant to RCFC 12(b)(1) and 12(b)(6) for, respectively, lack of jurisdiction and failure
    to state a claim. ECF No. 23 (“Def. Mot.”). On February 7, 2020, Sarro filed its response
    to the government’s motion to dismiss. ECF No. 27 (“Pl. Resp.”). On March 6, 2020, the
    government filed its reply in support of its motion to dismiss. ECF No. 29 (“Def.
    Reply”). On June 9, 2020, the Court heard oral argument. ECF No. 31.
    II.    Jurisdiction And Standard Of Review
    The Tucker Act, as amended by the CDA, Pub. L. No. 95-563, 
    92 Stat. 2383
     (1978),
    provides this Court “jurisdiction to render judgment upon any claim by or against, or
    dispute with, a contractor arising under section 7104(b)(1) of title 41 . . . on which a
    4 This case originally was assigned to Judge Bruggink, ECF No. 2, but, on February 5, 2020, was
    transferred to the undersigned Judge. ECF No. 25.
    -6-
    decision of the contracting officer has been issued under section 6 of that Act.” 
    28 U.S.C. § 1491
    (a)(2). “[J]urisdiction thus requires both a valid claim and a contracting
    officer’s final decision on that claim.” M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010); see England v. Swanson Grp. v. United States, 
    353 F.3d 1375
    , 1379 (Fed. Cir. 2004). The plaintiff “has the burden of establishing jurisdiction by
    a preponderance of the evidence.” Fid. & Guar. Ins. Underwriters, Inc. v. United States,
    
    805 F.3d 1082
    , 1087 (Fed. Cir. 2015). Furthermore, as with any claim before the Court of
    Federal Claims, only the federal government is a proper defendant and “if the relief
    sought is against others than the United States the suit as to them must be ignored as
    beyond the jurisdiction of the court.” Double Lion Uchet Express Trust v. United States,
    
    149 Fed. Cl. 415
    , 420 (2020) (alteration omitted) (quoting United States v. Sherwood, 
    312 U.S. 584
    , 588 (1941)). In the absence of subject-matter jurisdiction, the Court must
    dismiss the claim. Lindsay v. United States, 
    295 F.3d 1252
    , 1257 (Fed. Cir. 2002); RCFC
    12(h)(3).
    To survive a motion to dismiss for failure to state a claim, the Court views the
    facts in the light most favorable to the plaintiff and accepts as true all factual allegations
    — but not conclusory legal assertions — contained in the complaint. Bell Atl. Corp. v.
    Twombly, 
    550 U.S. 544
    , 555 (2007); see Am. Bankers Ass’n v. United States, 
    932 F.3d 1375
    ,
    1380 (Fed. Cir. 2019). Those facts must yield a “reasonable inference that the defendant
    is liable for the misconduct alleged.” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009).
    III.   The Court Lacks Jurisdiction Over Sarro’s Implied Duty To Disclose Superior
    Knowledge Claim But Possesses Jurisdiction Over The Remaining Claims
    The government, in its motion to dismiss, argues that, pursuant to RCFC 12(b)(1),
    this Court lacks jurisdiction to resolve the following claims because Sarro failed to
    present them as part of its certified claim to the CO: (1) the government’s alleged
    breach of an implied duty to disclose superior knowledge; (2) the government’s alleged
    breach of contract via a unilateral cardinal change; and (3) the government’s alleged
    breach of the implied duty of good faith and fair dealing. Def. Mot. at 8–14. The Court
    notes that, to the extent Sarro seeks to hold the City responsible for the increased costs
    of the project, this Court has no jurisdiction to adjudicate such claims. See, e.g., Anderson
    v. United States, 
    117 Fed. Cl. 330
    , 331 (2014) (“This court does not have jurisdiction over
    any claims alleged against states, localities, [or] state and local government
    entities . . . .”).5 Although the Court has jurisdiction over the cardinal change and good
    5Nor, for that matter, does Sarro cite any legal authority that would require the government to
    pay for the City’s wrongful acts. Accordingly, to the extent Sarro’s pending amended
    complaint seeks to hold the City liable – or the government liable for the City’s acts – Sarro’s
    -7-
    faith and fair dealing claims, the Court agrees with the government that Sarro’s CDA
    claim did not assert a breach of the government’s implied duty to disclose superior
    knowledge.
    Pursuant to the CDA, “[e]ach claim by a contractor against the Federal
    Government relating to a contract shall be submitted to the contracting officer for a
    decision.” 
    41 U.S.C. § 7103
    (a)(1). “A claim need not be submitted in any particular
    form or use any particular wording . . . , but it must provide a clear and unequivocal
    statement that gives the contracting officer adequate notice of the basis and amount of
    the claim.” K-Con Bldg. Sys., Inc. v. United States, 
    778 F.3d 1000
    , 1005 (Fed. Cir. 2015)
    (internal brackets and quotation marks omitted). “This approach, which has been
    applied in a practical way, serves the objective of giving the contracting officer an
    ample pre-suit opportunity to rule on a request, knowing at least the relief sought and
    what substantive issues are raised by the request.” 
    Id. at 1006
    .
    In turn, as a prerequisite for this Court’s jurisdiction, a plaintiff in this Court
    must assert in its operative complaint “the same claim previously presented to and
    denied by the contracting officer.” Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365
    (Fed. Cir. 2003) (quotation marks omitted). “This standard, however, does not require
    ridged adherence to the exact language or structure of the original administrative CDA
    claim.” 
    Id.
     All that is required is that the complaint arises from the “same operative
    facts” and seeks “essentially the same relief” as the claim presented to the contracting
    officer. 
    Id.
     When the complaint, however, presents “a materially different factual or
    legal theory,” then the complaint is different from the CDA claim. Lee’s Ford Dock, Inc.
    v. Sec’y of the Army, 
    865 F.3d 1361
    , 1369 (Fed. Cir. 2017) (emphasis added) (quotation
    marks omitted); see also K-Con, 778 F.3d at 1005 (“Our longstanding demand that a claim
    adequately specify both the amount sought and the basis for the request implies that, at
    least for present purposes, we should treat requests as involving separate claims if they
    either request different remedies (whether monetary or non-monetary) or assert grounds
    that are materially different from each other factually or legally.” (emphasis in
    original)). In sum, “the claim before the court [in the complaint] cannot be said to arise
    from the same operative facts [in the CDA claim] unless it is clear that the claim
    presented to the contracting officer was specific enough to give the officer notice of the
    basis of the claim and allow him to make an informed judgment about it.” Affiliated
    Constr. Grp., Inc. v. United States, 
    115 Fed. Cl. 607
    , 612 (2014).
    In its certified claim, Sarro asserted, among other things, that “[n]one of the specs
    identified an NEC version . . . [,but t]he City of Flagstaff then required us to pay a
    amended complaint is dismissed under RCFC 12(b)(1) and 12(b)(6), respectively, for lack of
    jurisdiction or failure to state a claim upon which relief may be granted.
    -8-
    much higher permitting fee well after the project had been completed and required
    [Sarro] to change out the gauge of wire to meet the 2011 NEC standards instead of the
    2017 NEC standards.” Def. App. at 20. Sarro further claimed that “[t]here were no
    specific references in the original SOWs identifying which version of the NEC applied
    to this work or any other Code requirement, again leading to confusion and the added
    costs.” 
    Id. at 21
    . Sarro sought $33,557.08 for its uncompensated costs arising from the
    unforeseen changes to the project that Sarro alleges were caused by the government. 
    Id. at 23
    . Sarro also claimed that “[c]lear and precise drawing and specs were not disclosed
    in the specifications or general conditions provided in bid documents.” 
    Id. at 20
    . These
    claims are almost identical to factual allegations contained in Sarro’s amended
    complaint filed in this Court, seeking damages for a cardinal change and for the breach
    of the implied duty of good faith and fair dealing. See Am. Compl. ¶¶ 101–10.
    The CO, in his final decision, acknowledged that Sarro sought reimbursement
    because “the scope of work did not identify the version of NEC or any other Code
    requirements that applied to the work” and for costs associated with “draw[ing] the
    necessary engineered drawings.” Def. App. at 26. The CO also clearly understood
    Sarro’s claim as holding the federal government – and not just the City – responsible for
    Sarro’s additional costs. This is evident from the CO’s conclusion that “USGS disagrees
    the Federal Government should be responsible for any costs the Contractor may have
    incurred for complying with the City’s building permit or of complying with any code
    applicable to the work required under the Contract.” 
    Id.
     (emphasis added).
    The government urges dismissal because Sarro’s certified claim sought an
    equitable adjustment as the remedy for unforeseen additional costs caused by the
    government but now proceeds under various breach-of-contract theories. See Def. Mot.
    at 11–13. But such a legal distinction, standing alone, is not dispositive. While Sarro
    “augments the legal theories underlying its claim[s] . . . it does not change the essence of
    [those] claim[s].” Cerebonics, Inc. v. United States, 
    13 Cl. Ct. 415
    , 419 (1987); see M.A.
    DeAtley Const., Inc. v. United States, 
    75 Fed. Cl. 575
    , 578–80 (2007) (holding that plaintiff
    could assert breach of contract and breach of good faith claims in complaint based on
    same operative facts presented in claim to contracting officer although the latter did not
    identify specific legal arguments). In essence, the Court holds here – in the language of
    the United States Court of Appeals for the Federal Circuit’s K-Con decision – that the
    legal theory distinction the government highlights is not material in light of the
    operative facts. The operative factual bases that give rise to Sarro’s claims in the
    amended complaint are – with one notable exception discussed below – the same as
    those contained in the CDA claim. Sarro’s requested monetary award of $33,557.08,
    representing its alleged additional costs, is also identical to what Sarro sought in its
    CDA claim submitted to, and denied by, the CO.
    -9-
    Because the breach of contract and implied duty of good faith and fair dealing
    claims in Sarro’s amended complaint arise from the same facts and request the same
    relief contained in Sarro’s certified claim to the CO, they are properly before this Court.
    See Scott Timber Co., 
    333 F.3d at 1365
    ; see also Kansas City Power & Light Co. v. United
    States, 
    124 Fed. Cl. 620
    , 630 (2016) (holding that “it is clear that irrespective of the way in
    which the counts are captioned . . . both plaintiff’s certified claim and . . . the complaint
    are based on the same underlying theory”).6
    In contrast, Sarro’s claim that the government failed to disclose superior
    knowledge falls outside this Court’s jurisdiction. As the Federal Circuit has explained,
    “[t]he superior knowledge doctrine imposes upon a contracting agency an implied duty
    to disclose to a contractor otherwise unavailable information regarding some novel
    matter affecting the contract that is vital to performance.” Giesler v. United States, 
    232 F.3d 864
    , 876 (Fed. Cir. 2000). The nature of a superior knowledge claim naturally
    focuses on “what the government [knew] . . . and when they knew it.” Laidlaw Envtl.
    Servs. (GS), Inc. v. United States, 
    43 Fed. Cl. 44
    , 50 (1999) (emphasis in original). In that
    regard, Sarro’s amended complaint does just that, alleging as follows:
    •   Sarro was not aware of the difficulties in obtaining permits
    from the City[;]
    •   USGS knew that Sarro was not aware of the difficulties it
    could face in obtaining a permit from the City[;]
    •   [N]either the [CO] nor anyone else working for the
    Agency provided information regarding the permit
    difficulties to Sarro at any time before the generator was
    installed[;]
    •   Sarro was misled to its detriment by the nondisclosure.
    Am. Compl. ¶¶ 83–88. The fatal jurisdictional flaw inherent in Sarro’s superior
    knowledge claim before this Court, however, is that such allegations are entirely absent
    from the CDA claim submitted to the CO. See Laidlaw, 43 Fed. Cl. at 50; see also Manuel
    Bros., Inc, v. United States, 
    55 Fed. Cl. 8
    , 33–34 (2002) (finding jurisdiction over superior
    knowledge claim where plaintiff in the certified claim “did discuss the defendant’s
    knowledge of the conditions of the soil and wrote about how the defendant allegedly
    withheld that knowledge”).
    6This represents only a determination that these counts do not suffer from a jurisdictional
    defect, but that does not mean that the claims survive the government’s motion to dismiss
    pursuant to RCFC 12(b)(6) for failure to state a claim, which is discussed infra, Section IV.
    - 10 -
    In Sarro’s claim submitted to the CO, Sarro focuses almost entirely upon the
    behavior of the City, arguing at length that “[t]he City of Flagstaff failed to properly
    handle its own permit process.” Def. App. at 19–20. Sarro repeatedly alleged that the
    City failed to inform Sarro about the wiring requirements during construction and only
    raised the permitting issue after Sarro’s completion of the project. 
    Id.
     Only in the last
    line of the four-paragraph claim does Sarro make a bare mention of the government’s
    knowledge, alleging that, as “[the CO] well know[s] . . . . you have encountered many
    problems with the City of Flagstaff on most of your contracts. This case is not an
    exception.” 
    Id. at 20
     (ellipses in original). Sarro agrees that this lone reference served as
    the basis for its superior knowledge claim in its amended complaint. Pl. Resp. at 10.
    The Court, however, cannot discern how any “reasonable person could have inferred”
    that Sarro was alleging that USGS violated its duty to disclose superior knowledge
    about its alleged history of permitting issues with the City based on that lone reference.
    See Laidlaw, 43 Fed. Cl. at 51; Affiliated Constr. Grp., 115 Fed. Cl. at 613–14 (noting that
    “the claim as presented failed to provide a clear and unequivocal statement that
    disclosed the basis . . . of the claim” (alteration in original and internal quotation marks
    omitted)).
    Nowhere in the certified CDA claim did Sarro allege that USGS knew, prior to
    Sarro bidding on the contract, that the City had a history of being uncooperative in
    permitting matters; nor did Sarro even allude to USGS’s alleged failure to disclose such
    information or how such a failure damaged Sarro. See Canpro Inv. Ltd. v. United States,
    
    130 Fed. Cl. 320
    , 336 (2017) (“Nowhere in its certified claim did [plaintiff] contend that
    the [government] knew, during lease negotiations, [the information], nor did [plaintiff]
    allude to any failure of the [government] to disclose that information during lease
    negotiations.”). Likewise, the CO’s final decision denying Sarro’s claim does not make
    any reference to USGS’s alleged “many problems with the City of Flagstaff on most of
    [its] contracts.” Def. App. at 20. This is further evidence that Sarro did not “clearly”
    place the CO on notice as to the relevant operative facts upon which Sarro, for the first
    time before this Court, frames a superior knowledge claim against the government.
    Sarro further asserts that the CO was on notice as to the superior knowledge
    claim because Sarro’s transmittal email to the CO provided as follows: “I believe you
    have had other problems dealing with the City of Flagstaff and can possibly understand
    how the City’s mishandling of the process increased the costs.” Pl. Resp. App. at 1
    (emphasis added). This excerpt is not from the claim itself, however, and Sarro has not
    referred to any caselaw in which a court or board of contract appeals has assumed
    jurisdiction over a complaint based on materials presented to a contracting officer
    outside of the certified claim. Moreover, this statement also fails to put the CO on
    notice of the critical point that USGS allegedly withheld such knowledge from Sarro
    - 11 -
    prior to its bidding on the contract. Sarro’s assertion that a government official might
    understand how or why the City (allegedly) mishandled its permitting process is not
    the same thing as claiming that the government is responsible for the City’s action due
    to a failure to disclose specific information. In sum, Sarro’s superior knowledge claim
    currently before this Court in the amended complaint was not presented to the CO for
    decision in Sarro’s certified claim and, thus, dismissal of the superior knowledge count,
    for lack of jurisdiction, is warranted.
    For these same reasons, the Court also must dismiss Sarro’s similarly worded
    allegation contained in its amended complaint that the government breached its duty of
    good faith and failing dealing by failing “to disclose the prior difficulties encountered
    by other USGS contractors in obtaining permits from the City.” Am. Compl. ¶ 111.
    This assertion is simply a restatement of Sarro’s superior knowledge claim under a
    different heading. See Planate Mgmt. Grp., LLC v. United States, 
    139 Fed. Cl. 61
    , 73 (2018)
    (“Two or more counts in a complaint may be merged when they contain the same
    factual allegations and request the same relief.”); Aptus Co. v. United States, 
    61 Fed. Cl. 638
    , 646 (2004) (holding that asserting “duplicative and redundant statement[s]” under
    different legal claims “does not alter [their] nature”).
    IV.    The Court Dismisses Sarro’s Three Remaining Claims For Failure State A
    Claim
    The government, in its motion to dismiss, further contends that all of Sarro’s
    claims fail to state a claim as a matter of law and, thus, should be dismissed pursuant to
    RCFC 12(b)(6). Def. Mot. at 17–27. Because this Court already has concluded that
    Sarro’s superior knowledge claim must be dismissed for lack of subject-matter
    jurisdiction, this Court will not consider the government’s arguments as to that claim.
    See Laidlaw, 43 Fed. Cl. at 51. Regarding the remaining claims, each of which is
    addressed below, the Court agrees with the government that pursuant to RCFC
    12(b)(6), Sarro has failed to allege claims as a matter of law.
    A.     Sarro’s Breach Of Contract And Cardinal Change Claims
    At the motion to dismiss stage of a proceeding, a complaint’s claim for breach of
    contract “requires two components: (1) an obligation or duty arising out of the contract
    and (2) factual allegations sufficient to support the conclusion that there has been a
    breach of the identified contractual duty.” Call Henry, Inc. v. United States, 
    855 F.3d 1348
    , 1354 (Fed. Cir. 2017) (quotation omitted). “In making this assessment, the court
    must interpret the contract’s provisions to ascertain whether the facts plaintiff alleges
    would, if true, establish a breach of contract.” Bell/Heery v. United States, 
    739 F.3d 1324
    ,
    1330 (Fed. Cir. 2014). “Contract interpretation begins with the language of the written
    - 12 -
    agreement,” Coast Fed. Bank, FSB v. United States, 
    323 F.3d 1035
    , 1038 (Fed. Cir. 2003),
    which, when unambiguous, “must be given [its] plain and ordinary meaning.” McAbee
    Const., Inc. v. United States, 
    97 F.3d 1431
    , 1435 (Fed. Cir. 1996) (quotation omitted); see
    ACLR, LLC v. United States, 
    147 Fed. Cl. 548
    , 557 (2020).
    “A cardinal change is a breach that occurs when the Government effects a change
    in the work so drastic that it effectively requires the contractor to perform duties
    materially different from those in the original bargain.” Int’l Data Prods. Corp. v. United
    States, 
    492 F.3d 1317
    , 1325 (Fed. Cir. 2007). Because each “contractual relationship is
    unique, . . . the contractor must [allege and] prove specific facts in support of its
    allegation of a cardinal change.” Keeter Trading Co., Inc. v. United States, 
    79 Fed. Cl. 243
    ,
    260 (2007); see Becho, Inc. v. United States, 
    47 Fed. Cl. 595
    , 601 (2000) (identifying relevant
    factors).
    Sarro’s amended complaint alleges that USGS breached the contract’s Changes
    clause by ordering compliance with the City’s permitting and subsequent new
    installation requirements without providing an equitable adjustment. Am. Compl.
    ¶¶ 89–100. Sarro also claims that USGS breached its contract with Sarro by ordering
    compliance with the City’s permitting and subsequent new installation requirements,
    which, in Sarro’s view, constituted a drastic alteration from the originally contemplated
    work in the purchase order, resulting in a cardinal change. 
    Id.
     ¶¶ 101–06. Under either
    claim, Sarro is seeking the same $33,557.08 for the additional project costs; no more. 
    Id. at 17
    . Accordingly, although styled as two separate claims, both raise the identical
    question – did the Agency order a change from the originally contemplated, contractual
    SOW for which Sarro must be compensated?7
    Generally, a firm-fixed-price contract “places upon the contractor maximum risk
    and full responsibility for all costs and resulting profit or loss.” FAR 16.202-1; RCF Info.
    Sys., Inc. v. United States, 
    139 Fed. Cl. 729
    , 735 (2018). The language of the contract, on
    its face, appears all but dispositive: pursuant to the P&R clause, Sarro clearly assumed
    “responsibl[ity] for obtaining any necessary licenses and permits, and for complying
    with any Federal, State, and municipal laws, codes, and regulations applicable to the
    performance of the work” all “without additional expense to the Government.” FAR
    52.236-7; Def. App. at 5. The Federal Circuit, the decisions of which are binding on this
    Court, confronted a similar issue in Bell/Heery v. United States, 
    739 F.3d 1324
     (Fed. Cir.
    2014). In Bell/Heery, the contractor alleged that the government had violated the
    contract’s Changes clause by not authorizing an equitable adjustment for the increased
    costs related to “the onerous, unreasonable and overzealous [state permitting] official.”
    7During oral argument, the Court raised this issue and counsel for Sarro essentially conceded
    that these two counts merge into one claim. ECF No. 33 at 5–6, 63.
    - 13 -
    
    Id. at 1334
    . The Federal Circuit affirmed the dismissal of the breach of contract claim for
    failure to state a claim on the grounds that the P&R Clause “unequivocally assigns all of
    the risk for complying with the permitting requirements to [the contractor] ‘without
    additional expense to the Government.’” 
    Id.
     (quoting FAR 52.236-7) (emphasis in
    original); see also L.W. Matteson, Inc. v. United States, 
    61 Fed. Cl. 296
    , 308–14, (2004)
    (broadly interpreting a contractor’s liability under a contract’s P&R clause).
    While the Federal Circuit acknowledged that the literal terms of the P&R clause
    are not always dispositive of a contractor’s responsibility, that clause’s effect may be
    mitigated only where there are “other contractual provisions that specifically limit the
    scope of the contractor’s obligations for permitting requirements.” Bell/Heery, 739 F.3d
    at 1331 (emphasis added); see, e.g., Hometown Fin., Inc. v. United States, 
    409 F.3d 1360
    ,
    1369 (Fed. Cir. 2005) (“Our precedent establishes as a principle of contract interpretation
    that a specific contract provision will control over a general contract provision.”). For
    example, a different clause may shift financial responsibility to the government for
    federal regulations promulgated after the award of the contract, see Hills Materials Co. v.
    Rice, 
    982 F.2d 514
    , 516–17 (Fed. Cir. 1992) (construing FAR 52.236-13(b)(2)), or may
    impose a duty on the government to intercede with local permitting authorities on
    behalf of the contractor during the construction process. See Bell/Heery, 739 F.3d at
    1331–33. In its amended complaint, however, Sarro fails to identify any specific
    contractual provision that limits the scope of Sarro’s responsibilities and related liability
    under the P&R clause. See Am. Compl. ¶¶ 89–100.
    Indeed, Sarro only asserts that the contract “gave Sarro the discretion on how to
    perform the work.” Id. ¶ 91; see Pl. Resp. at 16. First, Sarro does not direct the Court to
    any language in the contract that purportedly provides this “discretion.” Second, and
    more critically, notwithstanding any generalized discretion that the contract may have
    afforded Sarro in determining how to perform the work, the P&R clause specifically
    placed on Sarro the burden to comply with state and local permitting laws. Sarro
    nowhere explains how generalized discretion to perform work may be invoked to avoid
    its responsibilities under the P&R clause. Moreover, Sarro does not allege that it
    originally obtained the correct permit; nor does Sarro claim that its work complied with
    the state and local regulations. Sarro only argues that “the City [did] not follow[] its
    own commercial permit requirements in issuing [the 2016 Permit].” Am. Compl. ¶ 64.
    But regardless of whether any alleged error in the issuance of the “over the counter”
    permit – instead of the “commercial” permit – was the City’s or Sarro’s, the contract
    clearly and unambiguously allocated the risk of failing to comply with permitting
    requirements to Sarro “without additional expense to the Government.” FAR 52.236-7.
    More significantly still, nothing makes the putative error – if there was one – the
    government’s responsibility.
    - 14 -
    There is one point that gives this Court pause. “When, as here, a contract is silent
    on the time limit of its term, it is established that the term is ordinarily effective for ‘a
    reasonable time.’” Sanchez v. Dep’t of Veterans Affairs, 
    949 F.3d 734
    , 736 (Fed. Cir. 2020)
    (quoting M & G Polymers USA, LLC v. Tackett, 
    574 U.S. 427
    , 441 (2015)). Reasonableness
    “is determined based on the circumstances” surrounding a particular contract. 
    Id.
     A
    reasonable approach to the P&R clause suggests that there must be some endpoint
    following the completion of the contract at which time a contractor is no longer
    responsible for issues that arise with a permit and, at such point, the burden of any
    additional costs shifts to the government. For example, the Court does not believe that
    the government could hold Sarro responsible in a case where the City revokes the
    permit ten years after the completion of the project and after the government’s
    acceptance of the work. Bell/Heery is uninstructive on this point (as applied to the facts
    alleged in Sarro’s amended complaint), as that case concerned additional costs incurred
    by the contractor based on permitting issues in the pre-construction stage and during
    construction, well before the government accepted the work. 739 F.3d at 1328–29.
    In this case, Sarro largely had completed the installation of the generator and the
    government paid Sarro the entire balance minus $2,000. Am. Compl. ¶¶ 47–50. Sarro
    never alleges, however, that the government engaged in final acceptance of the project
    at issue.8 See FAR 52.236-11 (“The Government’s possession or use shall not be deemed
    an acceptance of any work under the contract.”). Moreover, Sarro admittedly was still
    working on the project in the form of the punch list. See Am. Compl. ¶¶ 50–56.
    Accordingly, the Court finds that, given the facts alleged in the amended complaint, the
    P&R clause should be read as allocating the permit (and associated cost) risks here to
    Sarro, according to that clause’s plain meaning.9
    The government makes much of the fact that Sarro “fails to allege that the [CO]
    ordered any changes, let alone ordered them in writing.” Def. Mot. at 20. But that is
    beside the point. Even had the CO ordered in writing that Sarro correct every violation
    in the City’s correction notice, such an order would not have triggered the Changes
    8Plaintiff does allege that the “work . . . had already been completed and accepted by the City
    months earlier,” Am. Compl. ¶ 68 (emphasis added), but never alleges that the Agency engaged
    in final acceptance under FAR 52.236-11.
    9 The Court notes that only in the P&R clause’s last sentence is there an explicit mention of a
    temporal limitation on liability: “The Contractor shall also be responsible for all materials
    delivered and work performed until completion and acceptance of the entire work . . . .” FAR 52.236-
    7 (emphasis added). Whether the term “work performed” covers the P&R clause’s earlier
    reference to permitting requirements, so as to impose a specific durational limitation, is a
    question that the Court need not answer today because, in either event, Sarro does not allege
    that the government engaged in final acceptance of the work at issue.
    - 15 -
    clause. Rather, any such direction would have merely been an order to comply with the
    terms of the P&R Clause, which squarely required Sarro’s compliance with all state and
    local permitting laws. See Agility Def. & Gov’t Servs., Inc. v. United States, 
    115 Fed. Cl. 247
    , 251 (2014) (“[W]hen the Government merely insists on performance in compliance
    with the contract specifications, no adjustment is warranted.”). While the Court
    sympathizes with Sarro’s situation generally, Sarro, simply put, has not stated a claim
    for breach of contract against the government. The contract assigned to Sarro the duty
    and risk of local permitting compliance, and it has not identified any specific
    contractual provision that limited that duty or otherwise shifted the risk of non-
    compliance to the government.
    Having concluded that Sarro has failed to allege sufficient facts which, if true,
    demonstrate that the government ordered a change beyond what Sarro was required to
    perform under the contract, the Court also must dismiss Sarro’s cardinal change claim
    for failure to state a claim. USGS did not order a change or modification to the contract;
    nor did the government otherwise order Sarro to perform work that was not
    contemplated by the parties. Indeed, at most, USGS ordered only that Sarro comply
    with the contract’s P&R Clause. Absent factual allegations that, if true, would
    demonstrate that USGS forced Sarro to incur any costs for work beyond its contractual
    obligations, the Court a fortiori cannot conclude that USGS so drastically altered the
    terms of the contract that a cardinal change resulted. Put differently, in the absence of
    any change, there cannot be a cardinal one. See Bell/Heery, 739 F.3d at 1335.
    B.     Sarro’s Claim For Breach Of The Implied Duty Of Good Faith And Fair
    Dealing
    “Every contract, including one with the federal government, imposes upon each
    party an implied duty of good faith and fair dealing in its performance and
    enforcement.” Dobyns v. United States, 
    915 F.3d 733
    , 739 (Fed. Cir. 2019), cert. denied, 
    140 S. Ct. 1106
     (2020). This includes “the duty not to interfere with the other party’s
    performance and not to act so as to destroy the reasonable expectations of the other
    party regarding the fruits of the contract.” 
    Id.
     (quoting Centex Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005)); see Dotcom Assocs. I, LLC v. United States, 
    112 Fed. Cl. 594
    , 596 (2013) (“[A] party generally must allege some kind of subterfuge or
    evasion . . . or interference with or failure to cooperate in the other party’s
    performance.” (brackets and internal quotation marks omitted)). “[A]n act will not be
    found to violate the duty (which is implicit in the contract) if such a finding would be at
    odds with the terms of the original bargain, whether by altering the contract's
    discernible allocation of risks and benefits or by conflicting with a contract provision.”
    Metcalf Constr. Co., Inc. v. United States, 
    742 F.3d 984
    , 991 (Fed. Cir. 2014).
    - 16 -
    Sarro alleges that “the Agency knew that drawings and specifications were
    required but never provided them to Sarro or any other offeror as part of the
    Solicitation process.” Am. Compl. ¶ 110. 10 This single sentence, however, fails to state
    a claim for breach of the implied duty of good faith and fair dealing.
    First, the single sentence fails to contain sufficient facts to state a plausible claim
    for relief. See Iqbal, 
    556 U.S. at 678
    . Because Sarro has not included any factual
    allegations explaining this conclusory statement, the Court is unable to determine how
    the “drawings and specifications” that Sarro believes the Agency failed to provide
    impacted the eventual performance of the contract. See Scogin v. United States, 
    33 Fed. Cl. 285
    , 293 (1995) (“[T]here is no duty [on the part] of the trial court . . . to create a claim
    which [plaintiff] has not spelled out in his pleading[.]” (quotations omitted)). Sarro
    never explains the connection between the drawings and specifications and the
    damages Sarro allegedly incurred and, thus, entirely omits facts demonstrating either
    breach or a causal link to the alleged increased costs incurred. This is a classic
    Twombly/Iqbal problem. Indeed, in responding to the government’s motion to dismiss,
    Sarro appears to have all but abandoned this particular claim contained in the amended
    complaint. See Pl. Resp. at 23–24 (containing single reference to “drawings and
    specifications”). A party’s failure to raise an argument in an opening or responsive
    brief constitutes waiver. Novosteel SA v. United States, 
    284 F.3d 1261
    , 1273–74 (Fed. Cir.
    2002) (argument raised for first time in reply is waived); see also Cap Exp., LLC v. Zinus,
    Inc., 
    722 F. App'x 1004
    , 1009 (Fed. Cir. 2018) (quoting Stichting Pensioenfonds ABP v.
    Countrywide Fin. Corp., 
    802 F.Supp.2d 1125
    , 1132 (C.D. Cal. 2011), for the proposition
    that “in most circumstances, failure to respond in an opposition brief to an argument
    put forward in an opening brief constitutes waiver or abandonment in regard to the
    uncontested issue”).
    Second, to the extent that Sarro argues that “nothing in the Purchase Order said
    that the review and approval were conditions precedent to the issuance of a permit,” Pl.
    Resp. at 24, the contract demonstrates Sarro is wrong. The contract, in the SOW,
    expressly provided that the City “requires review and approval of all drawings/specs.”
    Def. App. at 15. Moreover, as already explained, the P&R clause required Sarro to
    10Sarro’s amended complaint also alleges that USGS violated this implied duty by “fail[ing] to
    disclose the prior difficulties encountered by other USGS contractors in obtaining permits from
    the City.” Am. Compl. ¶ 111. But this claim fails for the same reason as Sarro’s superior
    knowledge claim, which Sarro did not include in its certified CDA claim to the CO, and, as
    such, is dismissed for lack of jurisdiction. See, supra, Section III. Simply put, Sarro never placed
    the CO on notice that Sarro was seeking damages due the government’s alleged failure to
    disclose certain information.
    - 17 -
    comply with any and all of the City’s permitting requirements “without additional
    expense to the Government.” FAR 52.236-7.11
    In sum, given the facts Sarro alleges in the amended complaint, and in light of
    the contractual requirements, Sarro lacks any viable claim as a matter of law.
    *****
    The Court acknowledges that Sarro may view this result as harsh, given that it
    may have been forced to incur additional costs as a result of the City’s actions that Sarro
    did not and perhaps could not have easily anticipated. The Court further observes that
    the government may come to regret its position here, should contractors get the
    message that they should price into their services the risk of overly onerous or even
    unreasonable local permitting requirements. That said, this Court cannot rewrite the
    P&R clause to reallocate risk to the government merely because it has deeper pockets.
    CONCLUSION
    For all the above reasons, the Court GRANTS the government’s motion to
    dismiss Plaintiff’s amended complaint in its entirety. The first count is dismissed for
    lack of jurisdiction pursuant to RCFC 12(b)(1), while the three remaining counts are
    dismissed pursuant to RCFC 12(b)(6) for failure to state a claim upon which relief may
    be granted. Accordingly, the Clerk shall enter JUDGMENT for Defendant.
    IT IS SO ORDERED.
    s/Matthew H. Solomson
    Matthew H. Solomson
    Judge
    11To the extent that Sarro complains about its difficulties with the City’s review process, that is
    not a claim against the government. As explained, supra, any claim against the City is beyond
    this Court’s jurisdiction and is subject to dismissal pursuant to RCFC 12(b)(1). To the extent
    Sarro claims that the government should be held liable for the City’s actions, Sarro does not cite
    any contractual provision supporting the imposition of such liability, and such a claim is
    dismissed pursuant to RCFC 12(b)(6).
    - 18 -