  •       In the United States Court of Federal Claims
    No. 19-1390C
    (Filed: October 16, 2020)
    ************************************ *
    *
    JKB SOLUTIONS AND SERVICES, LLC, *
    *
    Motion for Summary Judgment;
    Plaintiff,       *
    Tucker Act; Breach of Contract; Task
    *
    Order; Termination for Convenience;
    v.                                   *
    Partial Termination for Convenience;
    *
    Constructive      Termination    for
    THE UNITED STATES,                   *
    Convenience;      Termination    for
    *
    Convenience Damages.
    Defendant.       *
    *
    ************************************ *
    William A. Lascara, with whom was Bryan S. Peeples, Pender & Coward, P.C., Virginia
    Beach, Virginia, for Plaintiff JKB Solutions and Services, LLC.
    Amanda L. Tantum, with whom were Robert E. Kirschman, Jr., Director, Steven J.
    Gillingham, Assistant Director, Commercial Litigation Branch, Ethan P. Davis, Acting
    Assistant Attorney General, U.S. Department of Justice, Washington, D.C., and Major
    Nicole Kim, Judge Advocate, U.S. Army Legal Services Agency, for Defendant.
    OPINION AND ORDER
    WHEELER, Judge.
    Plaintiff JKB Solutions and Services, LLC and the U.S. Army Contracting
    Command-New Jersey entered into a three-year Indefinite Quantity/Indefinite Delivery
    contract for instructor services for the Operational Contract Support course, a class
    developed and managed by the United States Army Logistics University. Under the
    contract, the Army could request up to fourteen classes per ordering period; the contract
    covered three ordering periods.
    The Army ordered and paid for nine courses the first ordering period, thirteen the
    second period, and eight the third period. JKB alleges that the Army was required to pay
    for fourteen courses per ordering period, regardless of how many it actually needed. The
    Government, however, argues that it could order up to fourteen courses but was only
    required to pay for the courses JKB actually performed. Even if the Army was required to
    order fourteen courses, the Government argues that the contract includes a termination for
    convenience clause, FAR 52.212-4, which limits JKB’s recovery to termination for
    convenience costs.
    Now before the Court is the Government’s motion for summary judgment. For the
    reasons discussed below, the Court GRANTS the Government’s motion.
    Background
    The Court previously provided a detailed history of the solicitation at issue in this
    case in its reported order denying the Government’s motion to dismiss. See JKB Sols. &
    Servs., LLC v. United States, 
    148 Fed. Cl. 93
    , 95–96 (2020). Briefly, the solicitation was
    for JKB to provide the Army with instructors for its Operation Contract Support course.
    Id. at 95.
    The Army was to issue task orders for each one-year ordering period under the
    contract; the Army could order up to fourteen classes per ordering period.
    Id. JKB’s contract with
    the Army incorporated various standard provisions of the Federal Acquisition
    Regulations (“FAR”). Dkt 1-2 at 1. One such provision incorporated in the IDIQ contract
    relates to “Termination for the Government’s convenience” and states that “[t]he
    Government reserves the right to terminate the contract, or any part hereof, for its sole
    convenience.” FAR 52.212-4(l). Ultimately, the Government did not order the full
    fourteen classes in any of the ordering periods: in period one it ordered nine courses, in
    period two it ordered thirteen, and in period three it ordered eight. Dkt. 31 at 9. However,
    although the Army did not order the full fourteen courses during any of the ordering
    periods, it never explicitly terminated the task orders or the contract for convenience.
    JKB filed its complaint in this Court on September 11, 2019. Dkt. 1. In its
    complaint, JKB alleged that the Army breached its contractual duty when it refused to pay
    for fourteen classes for each ordering period.
    Id. at ¶¶ 5–15.
    On January 16, 2020, the
    Government moved to dismiss the complaint for failure to state a claim upon which relief
    may be granted, arguing that the contract’s language made clear JKB would only be paid
    for services that were actually provided or, in the alternative, for summary judgment. Dkt.
    No. 9. The Government disagreed about how many courses it was contractually required
    to order per period. The Court held that the task orders contained both patent and latent
    ambiguities as to whether the Army was required to pay for 14 courses per ordering period
    and denied the Government’s motion. JKB Sols. & 
    Servs., 148 Fed. Cl. at 98
    –99.
    After the Court addressed the Government’s motion to dismiss, the parties filed a
    joint preliminary status report on June 29, 2020. Dkt. 20. In the joint status report, the
    Government argued that the Court should find a constructive termination for convenience
    and limit JKB’s recovery to termination for convenience costs. Dkt. 20 at 3 (relying on
    G.L. Christian & Assoc. v. United States, 
    312 F.2d 418
    (Ct. Cl. 1963). The Court then
    2
    held a telephonic conference on August 11, 2020, where the parties agreed to an expedited
    briefing on the Government’s motion for summary judgment. Dkt. 30.
    The Government filed its motion for summary judgment on August 25, 2020. Dkt.
    31. JKB then filed its response and a cross-motion for summary judgment on September
    8, 2020. Dkt. 34. In response, the Government requested that the Court stay the deadline
    for its response to JKB’s cross-motion for summary judgment until the Court ruled upon
    the Government’s pending motion for summary judgment. Dkt. 35. The Court granted the
    Government’s request. Dkt. 36. On September 23, 2020, the Government filed its reply
    in support of its motion for summary judgment. Dkt. 39. The Government’s motion for
    summary judgment is now fully briefed and ripe for decision.
    Standard of Review
    Summary judgment is appropriate where the evidence demonstrates that there is “no
    genuine issue as to any material fact and that the moving party is entitled to judgment as a
    matter of law.” Rules of the United States Court of Federal Claims (“RCFC”) 56(a); see
    also Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247–49 (1986); Casitas Mun. Water
    Dist. v. United States, 
    543 F.3d 1276
    , 1283 (Fed. Cir. 2008). The moving party bears the
    initial burden of showing that there exists no genuine dispute as to any material fact.
    Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323 (1986). Once that burden is met, the onus
    shifts to the non-movant to identify evidence demonstrating a dispute over a material fact
    that would allow a reasonable finder of fact to rule in its favor. See 
    Anderson, 477 U.S. at 256
    .
    Summary judgment will not be granted if the “evidence is such that a reasonable
    [trier of fact] could return a verdict for the nonmoving party.” 
    Anderson, 477 U.S. at 248
    .
    However, when “the record taken as a whole could not lead a rational trier of fact to find
    for the nonmoving party, there is no ‘genuine issue for trial.’” Scott v. Harris, 
    550 U.S. 372
    , 380 (2007) (quoting Matsushita Elec. Industrial Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587 (1986)).
    Discussion
    The contract between JKB and the Army incorporated a termination for convenience
    clause. The Army constructively terminated each task order for convenience. Therefore,
    JKB may only recover its termination for convenience costs, but it neither alleged these
    costs in its complaint nor subsequently provided any evidence that it suffered them.
    Accordingly, the Government is entitled to summary judgment.
    3
    I.      The Army Exercised the Termination for Convenience Clause Contained in its
    Contract with JKB
    When a party to a contract fails to perform or improperly repudiates its obligations,
    the nonbreaching party is entitled to damages. See Best Foam Fabricators, Inc. v. United
    States, 
    38 Fed. Cl. 627
    , 637 (1997). However, the Government has more rights, and
    government contractors have correspondingly fewer rights, than do parties to an ordinary
    contract. One of the Government’s heightened rights is the power to terminate a contract
    for convenience. This power is codified in FAR 52.212-4(l), which provides in relevant
    part:
    The Government reserves the right to terminate this contract, or any part
    hereof, for its sole convenience. . . . Subject to the terms of this contract, the
    Contractor shall be paid a percentage of the contract price reflecting the
    percentage of the work performed prior to the notice of termination, plus
    reasonable charges the Contractor can demonstrate to the satisfaction of the
    Government using its standard record keeping system, have resulted from the
    termination. The Contractor shall not be required to comply with the cost
    accounting standards or contract cost principles for this purpose. . . . The
    Contractor shall not be paid for any work performed or costs incurred which
    reasonably could have been avoided.
    Thus, FAR 52.212-4(l) allows the Government to terminate a contract without having to
    pay ordinary expectation damages; instead a government contractor is only entitled to
    payment for work already completed and any costs that it incurred as a direct result of the
    termination. “[T]he government is entitled to considerable latitude in making such a
    decision to terminate.” Custom Printing Co. v. United States, 
    51 Fed. Cl. 729
    , 733–34
    (2002).
    JKB argues that FAR 52.212-4(l) is inapplicable in this case because that section of
    the FAR deals with commercial item contracts, and this contract between JKB and the
    Government is a service contract. Dkt. 34 at 20. JKB is mistaken. It is true that FAR
    52.212-4 does have the heading “Contract Terms and Conditions—Commercial Items.”
    However, as the Government correctly notes, nothing in the FAR limits the applicability
    of Section 52.212-4(l) to commercial item contracts. Dkt. 31 at 13. To allow JKB to
    escape the application of the termination for convenience clause, which was incorporated
    by explicit reference into its contract with the Army, simply because the clause was initially
    envisioned as a provision in a different sort of contract would be to deny the Government
    the benefit of its bargain. The Court will not do this.
    The termination for convenience clause contained in FAR 52.212-4(l) does not
    leave government contractors totally helpless in the face of a termination for convenience.
    First, the contract at issue must actually contain a termination for convenience clause in
    4
    order for the Government to be able to invoke it. See Praecomm, Inc. v. United States, 
    78 Fed. Cl. 5
    , 11 (2007). Even if the contract at issue contains a termination for convenience
    clause, the Government’s decision to terminate could still potentially qualify as a breach
    of the contract. However, a termination for convenience constitutes a breach of contract
    only in two “very limited circumstances”: “when ‘the agency (1) terminates the contract in
    bad faith or (2) abuses its discretion in its decision to terminate the contract.’” TigerSwan,
    Inc. v. United States, 
    118 Fed. Cl. 447
    , 451 (2014) (quoting Tigerswan, Inc. v. United
    States, 
    110 Fed. Cl. 336
    , 345 (2013)). Moreover, if a “contract contains a termination for
    convenience clause and the contracting officer could have invoked the clause instead of
    terminating, rescinding or repudiating the contract on some other invalid basis,” this Court
    “will constructively invoke the clause to retroactively justify the government’s actions,
    avoid breach, and limit liability.” 
    Praecomm, 78 Fed. Cl. at 11
    (quoting Best Foam
    Fabricators, 
    Inc., 38 Fed. Cl. at 638
    ).
    Therefore, if (1) the contract between JKB and the Army contained a termination
    for convenience clause, (2) the Army did not terminate the contract in bad faith or abuse
    its discretion in doing so, and (3) the contracting officer could have elected to terminate
    the contract—or, as relevant here, the task orders issued pursuant to the contract—for
    convenience, then the Government is not in breach. Each of these conditions is met in this
    case.
    First, the contract between JKB and the Army did contain a termination for
    convenience clause. The contract explicitly states that it “Incorporates By Reference FAR
    52.212-4.” Dkt. 1-2 at 1. As the Government notes, the relevant question in this case is
    whether each task order issued pursuant to the contract between JKB and the Army also
    included a termination for convenience clause. See Dkt. 39 at 14. They did. The contract
    said that “[a]ll . . . task orders are subject to the terms of this contract.”
    Id. at 33.
    Therefore,
    not only the contract, but also all of the task orders issued pursuant to it, included the
    termination for convenience clause from FAR 52.212-4(l).
    Second, there is no indication that the Army terminated the task orders in bad faith,
    and its decision to do so was not an abuse of discretion. As a starting point, the questions
    of whether the Army terminated the contract in bad faith or its decision to do so was an
    abuse of discretion presuppose that there was actually a decision to terminate the contract
    for convenience. However, here the Court is constructively invoking the termination for
    convenience clause; the Army never explicitly invoked it, so it cannot have done so in bad
    faith or abused its discretion in having done so. Even assuming the contracting officer did
    decide to terminate the contract for convenience, though, there was no bad faith or abuse
    of discretion. In evaluating these questions, this Court uses four factors established by the
    Federal Circuit: “(1) subjective bad faith on the part of the CO, (2) the reasonableness of
    the decision, (3) the amount of discretion delegated to the CO, and (4) any violations of an
    applicable statute or regulation.” 
    TigerSwan, 118 Fed. Cl. at 451
    (citing Keco Indus., Inc.
    v. United States, 
    492 F.2d 1200
    , 1203–04 (Ct. Cl. 1974), abrogated on other grounds by
    5
    Impresa Construzioni Geom. Domenico Garufi v. United States, 
    238 F.3d 1324
    , 1331-33
    (Fed. Cir. 2001)).
    None of these four factors weigh against the Army’s decision to terminate for
    convenience in this case. JKB does not allege that the contracting officer acted in bad faith;
    nor is there any evidence for this proposition. See Dkt. 34 at 14–15. Nor is there any
    indication that the decision to terminate the contract for convenience was unreasonable.
    For instance, JKB acknowledges that the reason the Army did not order fourteen classes
    per ordering period was that it was able to use its own personnel to teach some of the
    classes. Dkt. 34 at 11–12. The Army’s decision to use its own employees to teach these
    classes, rather than contract them out to an outside vendor, was reasonable. As explained
    above, the contract contained a termination for convenience clause, and the contracting
    officer had the authority to terminate for convenience. JKB insists that there was no
    termination, but this does not mean that the contracting officer did not have the authority
    to terminate. See, e.g., Dkt. 34 at 17. Lastly, JKB does not allege that a termination for
    convenience would have violated any applicable statute or regulation.
    Third, the contracting officer could have chosen to invoke the termination for
    convenience clause when it became clear that, for each task order, the Army required fewer
    classes than it originally anticipated. The Court agrees with the Government that task
    orders, like other agreements between the Government and a contractor, may be partially
    terminated for convenience. See Dkt. 39 at 14; see also Nesbitt v. United States, 
    345 F.2d 583
    , 585–86 (Ct. Cl. 1965); Praecomm, 
    78 F. Cl
    . at 12. This Court has previously found
    that when the Government no longer requires all of the services it has ordered, “the deletion
    of work . . . resulted in a [constructive] termination for convenience.” Praecomm, 
    78 F. Cl
    . at 12. The same principles apply here. The Army could have partially terminated the
    task orders it issued to JKB when it became clear that it did not require JKB to teach
    fourteen classes per order. The Court therefore constructively invokes the termination for
    convenience clause for each of the three task orders.
    For these reasons, JKB’s contract with the Army, and the subsequent task orders
    that arose out of it, contained a termination for convenience clause that the Court
    “constructively invoke[s] . . . to retroactively . . . limit liability.”
    Id. at 11. II.
       JKB May Only Recover Termination for Convenience Costs
    The termination for convenience clause incorporated into the contract between JKB
    and the Government stated that in the event the Army chose to terminate the contract for
    convenience, JKB would “be paid a percentage of the contract price reflecting the
    percentage of the work performed prior to the notice of termination, plus reasonable
    charges [JKB could] demonstrate . . . ha[d] resulted from the termination.” FAR 52.212–
    4(l). The Government notes in its motion for summary judgment that “JKB has provided
    no evidence of costs related to termination of the task orders, let alone presented a claim
    6
    for termination for convenience costs to a contracting officer.” Dkt. 31 at 17. JKB does
    not dispute this characterization. Additionally, JKB did not include a claim for termination
    for convenience costs in its complaint, and did not raise the issue of termination for
    convenience costs in its cross-motion for summary judgment. JKB is not entitled to recover
    any money from the Government, because it is only entitled to termination for convenience
    costs, and has failed to demonstrate, or even allege, that it incurred any of these costs.
    Conclusion
    For these reasons, the Government’s motion for summary judgment is GRANTED.
    Additionally, JKB’s cross-motion for summary judgment is DENIED as moot. The Clerk
    of the Court is directed to enter judgment in favor of the Government. No costs.
    IT IS SO ORDERED.
    s/ Thomas C. Wheeler
    THOMAS C. WHEELER
    Judge
    7