Smargon v. Grand Lodge Partners , 288 P.3d 1063 ( 2012 )


Menu:
  •                         IN THE UTAH COURT OF APPEALS
    ‐‐‐‐ooOoo‐‐‐‐
    Daniel M. Smargon and Audrey M.            )               OPINION
    Viterbi,                                   )
    )          Case No. 20110059‐CA
    Plaintiffs and Appellees,            )
    )
    v.                                         )                FILED
    )            (October 25, 2012)
    Grand Lodge Partners, LLC; and Jack        )
    Koson,                                     )            
    2012 UT App 305
    )
    Defendant and Appellant.             )
    ‐‐‐‐‐
    Third District, Silver Summit Department, 070500572
    The Honorable Keith A. Kelly
    The Honorable Bruce C. Lubeck
    Attorneys:     Joseph E. Wrona, Draper, and Todd D. Wakefield, Park City, for
    Appellant
    James S. Lowrie and Nathan D. Thomas, Salt Lake City, for Appellees
    ‐‐‐‐‐
    Before Judges Davis, Thorne, and Roth.
    ROTH, Judge:
    ¶1     Defendant Grand Lodge Partners, LLC (GLP) appeals from the district court’s
    grant of summary judgment and subsequent award of damages to Plaintiffs Daniel M.
    Smargon and Audrey M. Viterbi (the Smargons). We affirm.
    BACKGROUND
    ¶2     In February 2005, the Smargons entered into a contract (the Contract) with GLP
    for the purchase of a resort condominium unit (the Unit) near Park City, Utah. At the
    time of contracting, construction had not yet begun on the condominium development.
    Pursuant to the Contract, the Smargons paid GLP an option payment of $154,900 to
    reserve the Unit.
    ¶3      In March 2005, the Smargons reviewed the plans for the project and became
    aware that a mechanical room would be located across the hall from the Unit. The
    mechanical room would house a large chiller that would provide climate control for the
    development. The Smargons voiced concerns to GLP about the location of the
    mechanical room and the disturbance it could create in the Unit. GLP responded by
    letter on March 9, 2005, writing that “[it] w[ould] make every effort to mitigate the noise
    through insulation and extra construction methods to ensure that the noise is reduced
    to an acceptable level.” The Smargons then let pass a time‐limited option to rescind the
    Contract and paid GLP an additional $154,900 as an earnest money deposit. In the
    months that followed, the Smargons spent $92,717.17 to make several upgrades to the
    Unit, including, among other things, the installation of an exterior door and custom
    flooring and countertops. Eventually, a closing date was set for August 10, 2007, and
    the Smargons wired the balance of the $1,549,000 purchase price into escrow in
    anticipation.
    ¶4     On August 9, the day before the scheduled closing, the Smargons conducted a
    walk‐through inspection of the Unit. The walk‐through inspection was an option
    provided to the buyer under the Contract, which, as GLP put it, would permit the
    Smargons to create a “punch list” of needed repair work. Specifically, the Contract
    stated that the Smargons “may conduct a ‘walk‐through inspection’ of the . . . Unit . . . .
    for the purpose of identifying any corrective or repair work . . . that needs to be
    completed to achieve substantial completion of the . . . Unit.” The Smargons began the
    inspection by noting a problem with the custom flooring, which they marked with blue
    tape. The walk‐through was soon disrupted, however, by noise and vibration
    emanating from the equipment in the mechanical room. As a result, the Smargons cut
    short the inspection and did not complete a punch list of needed repair work.
    20110059‐CA                                  2
    ¶5      Because of the mechanical room problem, the Smargons did not attend the
    scheduled closing the next day. GLP contacted the Smargons later in the day,
    acknowledged the noise and vibration in the Unit, and apparently conceded that, under
    the circumstances, it did not expect the Smargons to close on the Unit at that time.
    Nevertheless, GLP requested that they complete a punch list to address needed repair
    work, including the noise and vibration problem. The Smargons declined to do so
    because they did not believe that the mechanical room problem was appropriately
    addressed as a punch list item.
    ¶6      Over the next month, the parties contacted each other to discuss the noise and
    vibration in the Unit and the Smargons’ obligation to close on the Contract under the
    circumstances. In the course of these discussions, the Smargons took the position that if
    they decided not to purchase the Unit, GLP should refund both their option payment
    and earnest money deposit, as well as the amount they had spent to upgrade the Unit.
    They also requested that GLP pay them the substantial appreciation in the value of the
    Unit from the date the Contract was executed to the date scheduled for closing,
    reasoning that they had missed the opportunity to purchase a comparable unit in this or
    another condominium development when such units were similarly priced. During
    this time period, GLP sent an email and two letters to the Smargons on August 20, 2007,
    August 29, 2007, and September 6, 2007 (collectively, the letters). The legal effect of
    these letters has become one of the main focuses of the dispute.
    ¶7     In the August 20 email, GLP acknowledged the noise and vibration in the Unit
    caused by the equipment in the mechanical room. GLP explained that the problem was
    caused by “unusual circumstances present when [the Smargons] were [in the Unit for
    the walk‐through inspection] but” asserted that “the sound levels are, under normal
    conditions, much lower than you heard.” GLP described some specific actions it “might
    do to further reduce the noise levels,” such as to “put in spring isolators and dampers
    under the chiller,” “put a sound blanket on the chiller,” and “put isolators at pipe wall
    penetrations.” GLP asserted that these actions “should greatly reduce the noise,” and it
    “expect[ed] better than industry standards verifiable by acoustical instruments.” GLP
    also asserted, “[W]e feel we have an enforceable contract. I am sorry about how you felt
    about the condition of your condominium but even with the . . . things needing
    punchlist attention, the unit was as the contract specified.” According to GLP, “[a]ll the
    issues . . . raised would be taken care of in a usual punchlist process.” Nevertheless,
    20110059‐CA                                 3
    GLP offered the Smargons the option to either proceed with closing or be “refund[ed]
    [their] deposit” and reimbursed what they had paid for modifications to the Unit.
    ¶8      On August 29, GLP again wrote to the Smargons, stating that it “would like to
    resolve the issue of your condominium as soon as possible” but also expressing the
    view that GLP was “on firm ground and that you are now technically in default.” With
    regard to the mechanical room problem, GLP explained that “[s]ome aspects of the
    noise . . . have been mitigated and further steps are being taken.” GLP then reiterated
    its prior offer “to release you from [the] contract and refund both [the] deposit and the
    monies . . . spent to modify” the Unit. However, GLP stated that it would not pay the
    Smargons the appreciation in value of the Unit. The letter gave the Smargons until
    September 7, 2007, to accept one of the options GLP had offered or it would “consider
    [them] in default with all the consequences that such condition warrants.” GLP
    expressed regret for the letter’s “litigious tone,” but explained that it had “spoken to our
    attorney and he feels we are on extremely firm ground in our position” and “he feels
    that we do not need to make our generous offer of releasing you from your obligations
    and returning your money.” GLP also pointed out that, under the Contract, “the loser
    in any litigation will pay for the legal cost of the prevailing party so we feel totally
    confident in what we have proposed herein.”
    ¶9      About a week later, on September 6, GLP sent a final letter to the Smargons,
    written by its attorney, asserting that GLP “ha[d] performed its obligations under” the
    Contract, but “[t]he Smargons failed to close on the purchase of the unit [on August 10]
    pursuant to the terms of the purchase contract and have thereby defaulted on their
    obligations under that contract.” GLP also asserted that, “[r]ather than closing on the
    unit as required by the contract,” the Smargons had “attempted to impose upon [GLP]
    other demands and requirements not provided for in the contract, such as returning . . .
    option money, paying interest and paying additional sums . . . , all based on [their]
    apparent dislike of the unit because of sound that originates in a nearby mechanical
    room, which [they] believe[] will be bothersome.” GLP then explained that the
    Smargons’ “concerns would have been addressed through the punch list procedure
    provided for in the contract.” According to GLP, it was “confident that [it] delivered a
    unit that meets or exceeds any applicable industry standards,” had “taken additional
    measures to reduce any possible sound from the mechanical room,” and had “made
    significant efforts to resolve the Smargon[s’] concerns.” GLP then reiterated its offer to
    either refund the Smargons their “option money” and the monies paid to upgrade the
    20110059‐CA                                  4
    Unit or allow the Smargons to close on the Contract, though specifying that the option
    to close must be accepted by performance. GLP also required that “acceptance of either
    . . . offer[] must also be accompanied by a signed full release of any potential claims by
    the Smargons.” GLP explained that it did “not believe that [it] has the legal obligation
    to do any of these things for the Smargons” because they had “defaulted by not closing
    and that [GLP] has the right, as one of their various remedies under the contract, to
    unilaterally terminate the contract, keep all option money or other money paid by the
    Smargons and resell the unit with no further obligation to the Smargons.” The letter
    gave the Smargons until the next day, September 7, 2007 at 5:00 p.m. to accept one of
    the options, warning that if they did not do so, GLP would “consider the contract
    terminated, with no further obligations to the Smargons” and would “retain all money
    paid by the Smargons pursuant to the terms of the contract and . . . remarket and resell
    the unit.”1
    ¶10 The Smargons responded in writing that same day, indicating their interest in
    “resolving th[e] problem in a fair and equitable way” but explaining that the impending
    twenty‐four‐hour deadline imposed by GLP was “not conducive to that exercise.” The
    Smargons did not accept either of GLP’s alternative offers, apparently because they had
    determined by this time that they no longer wanted to purchase the Unit due to
    concerns about the noise and vibration and could not reach an agreement with GLP on
    the amount GLP should pay them to terminate the Contract. See infra ¶ 24 n.5.
    ¶11 The Smargons filed a complaint against GLP alleging breach of contract, and
    GLP counterclaimed for breach of contract, as well. Both parties moved for summary
    judgment. The district court granted the Smargons’ motion for summary judgment and
    denied GLP’s cross‐motion, concluding that GLP had repudiated the Contract and was
    therefore in breach. The district court reasoned that GLP had “modified the Contract by
    promising to make every effort to ensure the noise levels in the Unit would be at an
    1. After the walk‐through inspection, GLP consulted with its architects and sound
    engineers about how to address the noise and vibration in the Unit caused by the
    equipment in the mechanical room. During the ensuing litigation, GLP also explained
    that in a newly‐constructed condominium development, chillers such as the one in the
    mechanical room would take time to “balance” and in the interim could cause some
    noise. It appears from the record that by December 2007, the noise and vibration issues
    had not been remedied, but by July 2008, noise levels met industry standards.
    20110059‐CA                                 5
    acceptable level” and that on the day before closing, GLP “had not kept its end of the
    bargain.” The district court concluded that GLP then failed to provide adequate
    assurances to the Smargons that it would perform as required under the Contract.
    ¶12 A bench trial was later held to determine damages for GLP’s breach. The
    Contract provided that in the event of GLP’s default, the Smargons were entitled to “a
    refund of the Earnest Money Deposit plus interest” and “an amount equal to the
    amount of the Option Payment.” Pursuant to this liquidated damages provision, the
    court awarded the Smargons their option payment and earnest money deposit with
    applicable interest. The Smargons also requested expectancy damages for the
    appreciation in value of the Unit from the date of the Contract to the date of the
    scheduled closing. The court concluded, however, that such an award was barred by
    the Contract’s liquidated damages provision because such damages were “incapable or
    very difficult of accurate estimation at the time of execution of the contract.”
    Nevertheless, despite the liquidated damages provision, the court awarded the
    Smargons reliance damages to compensate them for the amount they had paid for
    upgrades to the Unit. The court reasoned that “at the time of contract formation” GLP
    knew “that it would allow buyers of condominium units to make change order
    upgrades,” and the liquidated damages provision did not provide “just compensation”
    for those upgrades in the event of GLP’s default despite the amount being “capable of
    accurate estimation.”
    ¶13    GLP appeals.
    ISSUES AND STANDARDS OF REVIEW
    ¶14 GLP challenges the district court’s grant of summary judgment. Summary
    judgment is appropriate only if “there is no genuine issue as to any material fact and [if]
    the moving party is entitled to a judgment as a matter of law.” Utah R. Civ. P. 56(c).
    “A district court’s decision to grant summary judgment is reviewed for correctness,
    with no deference afforded to the district court.” Oman v. Davis Sch. Dist., 
    2008 UT 70
    ,
    ¶ 14, 
    194 P.3d 956
     (internal quotation marks omitted).
    ¶15 GLP also contests the district court’s award of damages, specifically challenging
    the court’s decision to award reliance damages to the Smargons. We construe GLP’s
    20110059‐CA                                  6
    argument as presenting a question as to whether the court applied the correct legal
    standard, a matter that we review for correctness. See Chen v. Stewart, 
    2004 UT 82
    , ¶ 19,
    
    100 P.3d 1177
     (“[W]hether the trial court applied the proper legal standards is a
    question of law that is reviewed for correctness.”).
    ANALYSIS
    I. Summary Judgment
    ¶16 On appeal, GLP asserts that the district court erred in two respects when it
    granted summary judgment to the Smargons. First, GLP argues that the court
    inappropriately concluded as a matter of law that GLP had repudiated the Contract.
    Second, GLP argues that the Smargons themselves breached the Contract before any
    repudiation by GLP.
    A. Repudiation
    ¶17 The district court granted summary judgment to the Smargons, concluding that
    GLP had breached the Contract by repudiation. GLP argues that in granting summary
    judgment, the district court inappropriately resolved a factual issue as a matter of law:
    whether GLP provided adequate assurances to the Smargons that it would perform as
    required under the amended Contract to mitigate the noise in the Unit caused by the
    equipment in the mechanical room.
    ¶18 Repudiation of a contract “‘gives rise to a claim for . . . total breach.’” Bitzes v.
    Sunset Oaks, Inc., 
    649 P.2d 66
    , 70 (Utah 1982) (quoting Restatement (Second) of Contracts
    § 253(1) (1979)). If a party to a contract has “reasonable grounds . . . to believe that the
    [other party] will commit a breach by non‐performance that would of itself give [rise to]
    . . . a claim for . . . total breach,” he or she “may demand adequate assurance of due
    performance.” Restatement (Second) of Contracts § 251(1). Under such circumstances,
    the demanding party “may treat as a repudiation the [other party’]s failure to provide
    within a reasonable time such assurance of due performance as is adequate in the
    circumstances of [a] particular case.” Id. § 251(2); see also Bitzes, 649 P.2d at 70.
    “Whether an assurance of due performance is ‘adequate’ depends on what . . . is
    reasonable to require in a particular case taking account of the circumstances of that
    20110059‐CA                                  7
    case.” Restatement (Second) of Contracts § 251 cmt. e; see also id. (explaining that
    “relevant factors” to be considered in assessing the adequacy of assurances include
    “[t]he relationship between the parties, any prior dealings that they have had, the
    reputation of the party whose performance has been called into question, the nature of
    the grounds for insecurity, and the time within which the assurance must be
    furnished”).2
    ¶19 The issue presented for review under the repudiation analysis is a narrow one.
    GLP concedes that the March 9, 2005 letter modified the Contract; therefore, GLP was
    required by the Contract to “make every effort to mitigate the noise [coming from the
    equipment in the mechanical room] . . . to [e]nsure that the noise [in the Unit] is reduced
    to an acceptable level.” Further, the noise and vibration in the Unit caused by the
    equipment in the mechanical room was not at “an acceptable level” on the day before
    the scheduled closing, and GLP does not dispute that the Smargons had reasonable
    grounds to doubt whether GLP would perform as required under the Contract. Thus,
    the pertinent question is whether GLP provided the Smargons with adequate
    assurances of its performance.3 Specifically, the Smargons were entitled to treat GLP’s
    2. Section 251 of the Restatement (Second) of Contracts is modeled after section 2‐609 of
    the Uniform Commercial Code (the UCC). Both rules rest on similar principles, but the
    relevant portion of the UCC only “applies to contracts for the sale of goods” while the
    rule as stated in the Restatement “is a generalization, applicable without regard to the
    subject matter of the contract.” Restatement (Second) of Contracts § 251 cmt. a (1979).
    Despite the Restatement being modeled after the UCC, the two differ in some ways: for
    example, under the Restatement, “[w]hether an assurance of due performance is
    ‘adequate’ depends on what . . . is reasonable to require in a particular case taking
    account of the circumstances of that case,” id. § 251(2) & cmt. e; whereas the UCC
    provides that assurances must be “adequate under the circumstances of the particular
    case” but specifies that “the adequacy of any assurance offered shall be determined
    according to commercial standards,” U.C.C. § 2‐609(4), (2) (1999). Despite this
    variation, cases decided under the UCC are helpful to our analysis due to the
    substantive similarities of the rules.
    3. Under the repudiation analysis, GLP argues on appeal that the Smargons failed to
    demand assurances and that a valid demand must be in writing. GLP asserts that the
    (continued...)
    20110059‐CA                                 8
    failure to mitigate the noise and vibration in the Unit as a repudiation of the Contract if
    GLP “fail[ed] to provide [adequate] assurances of such performance, within a
    reasonable time under the circumstances.” See Restatement (Second) of Contracts
    § 251(2). In granting summary judgment, the district court concluded that GLP’s
    assurances to the Smargons were inadequate as a matter of law.
    ¶20 “[N]ormally . . . the adequacy of any assurance offered [is a] factual question[,
    but] . . . to preclude summary judgment on this issue, the evidence relied upon . . .
    would have to be such that a rational trier of fact might conclude that . . . [a party] gave
    adequate assurance.” Kaiser‐Francis Oil Co. v. Producer’s Gas Co., 
    870 F.2d 563
    , 568 (10th
    Cir. 1989) (citation omitted). If “[a] rational trier of fact could not make such a
    conclusion,” then summary judgment is appropriate. Id.; see also Brisbin v. Superior Valve
    Co., 
    398 F.3d 279
    , 285 (3d. Cir. 2005) (explaining that the adequacy of assurances is
    “generally [a] question[] of fact, but may sometimes be decided as a matter of law”);
    Spring Creek Holding Co. v. Shinnihon U.S.A. Co., 
    943 A.2d 881
    , 894‐95 (N.J. 2008)
    (explaining that whether assurances are adequate is “ordinarily [a] question[] of fact for
    the jury” but “occasions do arise where the undisputed facts establish that” assurances
    are inadequate “as a matter of law,” thus summary judgment may be appropriate if “no
    3. (...continued)
    district court “was apparently unaware of the requirement that the Smargons must
    make a demand for adequate assurances.” However, the court’s failure to take up the
    question seems to have resulted from GLP’s failure to bring the issue to the court’s
    attention. As a result, the issue is not preserved and we do not address it further. See
    generally 438 Main St. v. Easy Heat, Inc., 
    2004 UT 72
    , ¶ 51, 
    99 P.3d 801
     (“[I]n order to
    preserve an issue for appeal[,] the issue must be presented to the trial court in such a
    way that the trial court has an opportunity to rule on that issue” by “put[ting] the trial
    judge on notice of the asserted error and allow[ing] for correction at that time in the
    course of the proceeding. For a trial court to be afforded an opportunity to correct the
    error (1) the issue must be raised in a timely fashion[,] (2) the issue must be specifically
    raised[,] and (3) the challenging party must introduce supporting evidence or relevant
    legal authority.” (alterations in original) (citation and internal quotation marks
    omitted)).
    20110059‐CA                                   9
    rational trier of fact could conclude that . . . adequate assurance” was given).4 GLP
    argues that because the adequacy of assurances is a fact‐intensive inquiry, the district
    court inappropriately decided that issue on summary judgment. According to GLP,
    there are genuine issues of material fact as to whether the assurances provided were
    adequate, and those factual issues should have been resolved by a jury. In response, the
    Smargons assert that summary judgment was appropriate because, based on the
    undisputed facts, no reasonable trier of fact could conclude that GLP had given them
    adequate assurances.
    ¶21 In addressing the adequacy of the assurances, GLP and the Smargons rely upon
    the letters. Because these writings are the only evidence GLP and the Smargons rely
    upon, our analysis is similarly limited. There is no dispute that GLP sent the letters in
    response to the Smargons’ concerns about noise and vibration in the Unit, and their
    content is likewise undisputed. The parties’ contentions focus, rather, on the legal
    import of the letters, that is, whether as a matter of law the letters communicate
    assurances of GLP’s performance that were adequate under the circumstances. Based
    on the content of the letters, we conclude that a rational trier of fact could not conclude
    that GLP adequately assured the Smargons that it would resolve the noise and vibration
    problem; summary judgment was, therefore, appropriate.
    ¶22 In the August 20 letter, GLP listed some specific actions that it “might do to
    further reduce the noise levels,” such as putting “spring isolators and dampers under
    the chiller,” “a sound blanket on the chiller,” and “isolators at pipe wall penetrations.”
    4. While Utah courts have not addressed the propriety of determining on summary
    judgment the adequacy of assurances in a repudiation context, the underlying principle
    is nevertheless established under our own case law. See Oman v. Davis Sch. Dist., 
    2008 UT 70
    , ¶¶ 48‐49, 
    194 P.3d 956
     (“Summary judgment is appropriate only when
    reasonable minds could not differ” in resolving a fact‐intensive issue. If “no reasonable
    person could conclude” that the facts support a particular position, then summary
    judgment is appropriate.); Sanderson v. First Sec. Leasing Co., 
    844 P.2d 303
    , 306 (Utah
    1992) (explaining that although factual questions are better decided by a jury than on
    summary judgment, “the court retains the power to decide whether, as a matter of law,
    a reasonable jury could” reach a legal conclusion based on the facts, and “[i]f a
    reasonable jury cannot” reach the required legal conclusion based on the facts, then
    “summary judgment is appropriate”).
    20110059‐CA                                 10
    GLP also assured the Smargons that these actions “should greatly reduce the noise.”
    But GLP also wrote,
    [W]e feel we have an enforceable contract. I am sorry about
    how you felt about the condition of your condominium but
    even with the . . . things needing punchlist attention, the unit
    was as the contract specified. . . . All the issues you raised
    would be taken care of in a usual punchlist process . . . . As
    to the noise, there were some unusual circumstances present
    when you were here but the sound levels are, under normal
    conditions, much lower than you heard.
    GLP then stated that it would “consent to refund [the] deposit” as well as the amount
    the Smargons had paid for upgrades to the Unit.
    ¶23   A little over a week later, in the August 29 letter, GLP wrote,
    [GLP] feels that we are on firm ground and that you are now
    technically in default. Some aspects of the noise you heard
    when here have been mitigated and further steps are being
    taken. With this being said, GLP is willing to release you
    from your contract and refund both your deposit and the
    monies you have spent to modify your unit.
    GLP then gave the Smargons two options:
    First is to close on the property . . . . [S]econd . . . we will
    agree to let you out of the contract with full refund of your
    deposit and [the monies spent to modify the unit]. This offer
    . . . is open until close of business . . . on the 7th of
    September, 2007. After that date, if you have not either
    elected to be released from your contract or closed on the
    condominium, we will consider you in default with all the
    consequences that such condition warrants.
    20110059‐CA                                 11
    GLP rejected the Smargons’ request to be compensated for the appreciation in value of
    the Unit. GLP apologized for the letter’s “litigious tone” but explained that it had
    “spoken to our attorney and he feels we are on extremely firm ground in our position”
    and “feels that we do not need to make our generous offer of releasing you from your
    obligations and returning your money.” GLP also pointed out that, under the Contract,
    “the loser in any litigation will pay for the legal cost of the prevailing party so we feel
    totally confident in what we have proposed.”
    ¶24 The final letter, dated September 6, was written by GLP’s attorney. In it, GLP
    asserted that “[t]he Smargons failed to close on the purchase of the unit [on August 10]
    pursuant to the terms of the purchase contract and have thereby defaulted on their
    obligations under that contract,” but GLP had “performed its obligations under that
    contract.” GLP wrote that
    [r]ather than closing on the unit as required by the contract[,
    the Smargons had] attempted to impose upon [GLP] other
    demands and requirements not provided for in the contract,
    such as returning [the] option money, paying interest and
    paying additional sums . . . , all based on [their] apparent
    dislike of the unit because of sound that originates in a
    nearby mechanical room, which [they] believe[d] will be
    bothersome.
    GLP asserted that any such concerns “would not have been grounds to refuse to close
    or delay closing” and “such concerns would have been addressed through the punch
    list procedure provided for in the contract.” According to GLP, it was “confident that
    [it] delivered a unit that meets or exceeds any applicable industry standards” and that it
    had “taken additional measures to reduce any possible sound from the mechanical
    room” and had “made significant efforts to resolve the Smargon[s’] concerns.” GLP
    then restated its previous offer that, “notwithstanding the fact that the Smargon[s] have
    defaulted on their obligations under the purchase contract,” GLP would either “allow
    the Smargons to close on the purchase of the unit under the terms of the contract” or
    “return the option money paid by the Smargons to them together with the amounts
    previously paid by the Smargons [to modify the Unit] and allow the Smargons to be
    released from their obligations under the contract.” GLP required, however, that “[t]he
    acceptance of either of the above offers must also be accompanied by a signed full
    20110059‐CA                                 12
    release of any potential claims by the Smargons.” GLP then restated the “deadine of
    tomorrow, September 7, 2007, 5:00 p.m. . . . to accept either of these offers or the offers
    will automatically lapse.” If neither offer were accepted, GLP would “consider the
    contract terminated, with no further obligations to the Smargons,” and it would
    retain all money paid by the Smargons pursuant to the terms
    of the contract and . . . remarket and resell the unit. If the
    Smargons choose to pursue this matter, [GLP] will seek
    reimbursement of all enforcement, litigation or other similar
    costs incurred in response to the Smargons’ actions, as
    provided for in the contract.
    GLP’s attorney then stated,
    I do not believe that [GLP] has the legal obligation to do any
    of these things for the Smargons. I believe that the Smargons
    have defaulted by not closing and that [GLP] has the right,
    as one of their various remedies under the contract, to
    unilaterally terminate the contract, keep all option money or
    other money paid by the Smargons and resell the unit with
    no further obligation to the Smargons. [GLP] has been very
    generous and accommodating in trying to amicably resolve
    the Smargons’ concerns, especially in light of the fact that the
    Smargons have defaulted on their contractual obligations.
    The Smargons accepted neither offer.5
    5. As previously mentioned, see supra ¶ 10, it appears that the main reason that the
    Smargons did not simply accept GLP’s offer to be released from the Contract was due to
    a dispute over the amount of damages to which the Smargons were entitled. The
    Smargons requested that GLP pay them the appreciation in value of the Unit between
    the time of contracting and the time scheduled for closing. GLP refused to do so, and
    the Smargons consequently declined GLP’s offer for reimbursement. In addition, the
    Smargons assert that in offering to reimburse them the monies already paid for the
    Unit, GLP offered less than they would be entitled to under the Contract. Specifically,
    (continued...)
    20110059‐CA                                  13
    ¶25 In arguing that the district court inappropriately concluded as a matter of law
    that it failed to provide the Smargons with adequate assurances, GLP relies on portions
    of the August 20 email and August 29 letter, which GLP asserts contain assurances that
    a trier of fact could reasonably conclude were adequate under the circumstances. GLP
    relies primarily on the August 20 email where it listed some specific actions it might
    undertake to address the noise in the Unit caused by the equipment in the mechanical
    room that “should greatly reduce the noise.” Similarly, GLP also relies on the August
    29 letter, where it stated that “[s]ome aspects of the noise . . . have been mitigated and
    further steps are being taken.” However, the adequacy of the assurances given must be
    determined by the August 20, August 29, and September 6 letters as a whole. See Spring
    Creek Holding Co. v. Shinnihon U.S.A. Co., 
    943 A.2d 881
    , 896 (N.J. 2008) (explaining that
    the adequacy of assurances must be assessed in the context of which they were given);
    see also Brisbin v. Superior Valve Co., 
    398 F.3d 279
    , 289 (3d. Cir. 2005) (explaining that the
    “analysis must be based on the facts and circumstances known at the time,” so “[i]f a
    party had no knowledge of certain facts, it follows that” the party’s conduct “was not
    based on those facts”). When all three of the letters are considered together, we agree
    with the district court that the assurances GLP gave the Smargons are inadequate as a
    matter of law.
    ¶26 The assurances that GLP provided in the August 20 and August 29 writings were
    accompanied by attempts to minimize the extent of the noise problem. In the August 20
    email, GLP attributed the noise to “some unusual circumstances” that were present at
    the time of the walk‐through inspection and explained that “the sound levels are, under
    normal conditions, much lower”‐‐though GLP did not describe those unusual
    circumstances or provide any information from which the likelihood of their recurrence
    could be assessed. In the same letter, GLP also asserted that “the unit was as the
    contract specified” and “the issues . . . raised would be taken care of in a usual punchlist
    5. (...continued)
    under the Contract, the Smargons would be entitled to be reimbursed the option money
    and the earnest money deposit, as well as applicable interest. However, in these letters
    it is arguable that GLP only offered to reimburse the option money or the earnest
    money deposit but not both. Indeed, the Smargons have asserted this as an alternative
    basis for their argument that GLP repudiated the Contract, but because we conclude
    that GLP repudiated the Contract by failing to provide adequate assurances of its
    performance with respect to the noise problem, we do not reach that issue.
    20110059‐CA                                  14
    process.” A little over a week later, in the August 29 letter, GLP stated that “[s]ome
    aspects of the noise . . . have been mitigated and further steps are being taken,” though
    it did not explain the nature or extent of the mitigation in any way or describe the
    “further steps” and their potential impact. In the broader context of the August 20
    email and the August 29 letter, GLP’s more tangible assurances seem equivocal and
    noncommittal, thereby significantly undermining their adequacy. See, e.g., Spring Creek
    Holding Co., 
    943 A.2d at
    897‐98 (reasoning that assurances were inadequate where they
    only “constituted predictions of success in [pending] litigation or straight denials of any
    problem” without “provid[ing] other tangible assurance”).
    ¶27 The adequacy of the assurances is further undermined by GLP’s accompanying
    assertions that the Smargons themselves had breached the Contract and its concomitant
    demand that the Smargons close on the Contract. GLP first offered in the August 20
    email to refund the Smargons’ monies already paid for the Unit or proceed to closing,
    also stating that it “fe[lt it] had an enforceable contract.” But the August 29 letter had
    what GLP itself described as a more “litigious tone.” In that letter, GLP offered that the
    Smargons could either close on the Contract or be reimbursed monies already paid for
    the Unit, but GLP also asserted that the Smargons were “technically in default” and
    demanded that the Smargons accept one of its offers by September 7 or be “in default
    with all the consequences that such condition warrants.” In that letter, GLP further
    stated that it was on “extremely firm ground” and explained that it was not obligated to
    return any of the Smargons’ money. GLP also pointed out that, under the Contract,
    “the loser in any litigation will pay for the legal cost of the prevailing party.”
    ¶28 To the extent the first two letters gave any assurances at all, the September 6
    letter effectively abandoned them. Drafted by GLP’s attorney, that letter was clearly
    prepared in anticipation of litigation. GLP repeated its general representation that it
    had “taken additional measures to reduce any possible sound from the mechanical
    room” and had “made significant efforts to resolve the Smargon[s’] concerns,” but GLP
    again failed to give any further reassuring details about its efforts. Rather, GLP simply
    asserted that it had “performed its obligations under th[e] [C]ontract” and demanded
    that the Smargons either close on the Contract the next day, with the Unit remaining
    essentially “as is” with regard to the mechanical room problem, or accept a
    reimbursement of monies paid for the Unit. GLP gave the Smargons only one day to
    choose between the two options or be considered in default of the Contract and lose all
    monies already paid, nearly $400,000. In addition, GLP demanded that the Smargons’
    20110059‐CA                                 15
    acceptance of either offer “must be accompanied by a signed full release of any
    potential claims by the Smargons.” Finally, GLP threatened that if the Smargons
    themselves pursued the matter, GLP would “seek reimbursement of all enforcement,
    litigation or other similar costs incurred in response to the Smargon[s’] actions.”
    ¶29 Thus, in the course of only two weeks, GLP’s letters to the Smargons progressed
    from vague yet conciliatory descriptions of some specific steps it might take in order to
    remedy a serious problem to assertions that the Smargons themselves were in default
    while GLP had fully performed, without presenting any information on the nature of
    that performance or its effects, much less details that could provide tangible reassurance
    about its efficaciousness. These assertions were further accompanied by demands that
    the Smargons immediately close on the Contract to avoid losing everything they had
    already paid toward the Unit. Indeed, in making these demands, GLP required the
    Smargons to close before it demonstrated that it had “mitigate[d] the noise . . . to an
    acceptable level,” as required under the modification to the Contract. In addition, GLP
    demanded that, in accepting either offer, the Smargons release any potential claims
    against GLP. This would essentially deprive the Smargons of their ability to address
    (1) whether GLP had performed as required under the Contract by reducing the noise
    in the Unit to “an acceptable level” or (2) whether the monetary damages GLP offered
    to the Smargons were consistent with those provided by the Contract, regardless of
    whether GLP or the Smargons had breached the Contract, see supra ¶ 24, n.5. See, e.g.,
    Bitzes v. Sunset Oaks, Inc., 
    649 P.2d 66
    , 70 (Utah 1982) (“The respondent’s answer
    through its attorney inviting a lawsuit is certainly a failure to provide any assurance of
    due performance.”); see also Spring Creek Holding Co., Inc., 
    943 A.2d at
    897‐98 (reasoning
    that one party’s characterization of the other party’s “expression of insecurity [of
    performance] as an anticipatory breach” and threatening litigation were not “adequate
    assurance of performance”); Brisbin, 
    398 F.3d at 288
     (reasoning that assurances were
    inadequate where one party’s correspondence indicates a “willingness to entertain
    alternative forms of assurances in lieu of immediate payment” and “demonstrate[d] a
    continued interest in reaching an amicable solution,” but the other party “neither
    presented a single counterproposal nor gave any indication that it was willing and able
    to perform its obligations under the contract” and instead “decided to cease all
    communications and referred the matter to its legal department”).
    ¶30 Accordingly, we conclude that the district court appropriately granted summary
    judgment because, based on the undisputed facts, GLP failed to provide adequate
    20110059‐CA                                16
    assurances to the Smargons as a matter of law. See Kaiser‐Francis Oil Co. v. Producer’s
    Gas Co., 
    870 F.2d 563
    , 568 (10th Cir. 1989) (“[N]ormally [under a repudiation analysis]
    . . . the adequacy of any assurance offered [is a] factual question[, but] . . . to preclude
    summary judgment on this issue, the evidence relied upon . . . would have to be such
    that a rational trier of fact might conclude that . . . [a party] gave adequate assurance.”
    If “[a] rational trier of fact could not make such a conclusion,” then summary judgment
    is appropriate. (citation omitted)).
    B. Breach of Contract
    ¶31 GLP contends that regardless of whether it breached the Contract by
    repudiation, the Smargons breached the Contract first, thereby relieving GLP of any
    further obligation. Specifically, GLP argues that under the Contract, the Smargons were
    required to close on the purchase despite any repair work needed to complete the Unit,
    including any repair work required to mitigate the noise and vibration in the Unit
    caused by the mechanical room equipment.
    ¶32 In support of its argument, GLP relies on a plain language interpretation of the
    Contract. “The goal of contract interpretation is to give effect to the contracting parties’
    intentions at the time the contract was made.” Merrick Young Inc. v. Wal‐Mart Real Estate
    Bus. Trust, 
    2011 UT App 164
    , ¶ 17, 
    257 P.3d 1031
    . “[U]nder well‐accepted rules of
    contract interpretation, we [begin our analysis by] look[ing] to the language of the
    contract to determine its meaning and the intent of the contracting parties. We also
    consider each contract provision . . . in relation to all of the others, with a view toward
    giving effect to all and ignoring none.” 
    Id.
     (second and third alterations and omission in
    original) (internal quotation marks omitted). “If the language within the four corners of
    the contract is unambiguous, the parties’ intentions are determined from the plain
    meaning of the contractual language, and the contract may be interpreted as a matter of
    law.” 
    Id.
     (internal quotation marks omitted).
    ¶33 In support of this position, GLP relies on section 3.1 of the Contract, which
    provides the Smargons with a procedure to identify repair work needed to complete
    construction of the Unit by conducting a walk‐through inspection and creating a
    “punch list” of the needed repair work. Specifically, section 3.1 of the Contract
    provides,
    20110059‐CA                                  17
    Buyer may conduct a “walk‐through” inspection of the
    Condominium Unit . . . [, which] shall be for the purpose of
    identifying any corrective or repair work . . . that needs to be
    completed to achieve substantial completion of the
    Condominium Unit pursuant to the Plans and Specifications
    . . . . If . . . Repair Work remains to be completed, this shall
    not alter Buyer’s obligation to close . . . . Buyer may,
    pending completion of such Repair Work withhold in
    escrow . . . , a reasonable amount set by Seller in the exercise
    of the good faith reasonable judgment of the Seller, sufficient
    to pay for completion of such Repair Work. If such Repair
    Work is not completed within thirty (30) days after
    Settlement, the amount so escrowed may, at Buyer’s option,
    be released to Buyer as liquidated and agreed damages for
    failure to complete the Repair Work. The exercise by the
    Buyer of the option to take the escrowed funds shall be
    deemed to be full and final settlement of any damages to the
    Buyer by reason of the failure to timely complete and no
    other or further claim may be made by Buyer in connection
    therewith. As portions of the Repair Work are completed,
    the Buyer shall authorize interim releases to the Seller of
    some of the escrowed funds so long as the remaining funds
    remain sufficient to reasonably cover the remaining
    incomplete Repair Work.
    ¶34 According to GLP, the Contract “contemplates that the Unit may still be
    imperfect at the time scheduled for closing, and the Contract [thus] specifies an
    exclusive procedure for addressing and correcting any imperfections.” Specifically,
    GLP looks to the portion of section 3.1 of the Contract, which states that “[t]he ‘walk‐
    through’ inspection shall be for the purpose of identifying any corrective or repair work
    . . . that needs to be completed to achieve substantial completion of the Condominium
    Unit pursuant to the Plans and Specifications.” GLP further relies on section 1.2, which
    provides that the “Unit and related improvements shall be constructed in accordance
    with the architectural and engineering renderings, plans and specifications.” GLP
    explains that under section 1.2, “the subject matter of the ‘Plans and Specifications’ is . . .
    the ‘Unit and related improvements.’” Reading these sections together, GLP asserts
    20110059‐CA                                   18
    that because section 3.1 provides that the Unit must be completed pursuant to the plans
    and specification, the walk‐through inspection established in section 3.1 applies to the
    entire subject matter of the plans and specifications as provided in section 1.2‐‐that is,
    not just the Unit itself but related improvements as well. In other words, according to
    GLP, section 3.1 should be interpreted as providing that the walk‐through inspection is
    for the purpose of identifying any repair work “that needs to be completed to achieve
    substantial completion of the Condominium Unit [and related improvements] pursuant to
    the Plans and Specifications.”
    ¶35 Based on this conflation of sections 3.1 and 1.2, GLP asserts that the noise and
    vibration in the Unit caused by the equipment in the mechanical room is a “related
    improvement[]” and is, therefore, the sort of repair work that must be addressed
    through the punch list process as provided in section 3.1 to achieve substantial
    completion of the Unit. GLP further asserts that since the noise and vibration process
    should have been addressed under section 3.1, the Smargons were required to close on
    the Contract while the necessary repair work was still in process because section 3.1
    further provides that if “Repair Work remains to be completed, this shall not alter the
    Buyer’s obligation to close the purchase transaction.” GLP thus contends that by failing
    to close, the Smargons breached the Contract.
    ¶36 The Smargons counter that the Contract cannot reasonably be read this way, and
    we agree. Section 1.2 provides generally that the Unit and related improvements will
    be constructed according to the plans and specifications. By its own terms, the
    procedure set forth in section 3.1 specifically contemplates identification of “any
    corrective or repair work” that must be “completed to achieve substantial completion of
    the Condominium Unit.” Simply because the plans and specifications, as a general
    matter, encompass the entire condominium project, including the Unit, does not ipso
    facto mean that the entire development is subject to the punch list procedure in section
    3.1. Such an interpretation of the Contract would require the Smargons‐‐and every
    other purchaser‐‐to inspect common areas, such as equipment in mechanical rooms, in
    order to identify a possibly vast array of problems that might have some impact on the
    individual unit subject to the particular purchase contract. Thus, a simple walk‐through
    inspection to identify obvious repair work required to complete work on an individual
    unit‐‐such as cracked tile, problems with paint and drywall, poorly‐laid carpets, non‐
    functioning electrical outlets, and other issues that a typical buyer would detect‐‐could
    become a matter requiring significant investment of time by the buyer and expertise
    20110059‐CA                                 19
    beyond that expected of the great majority of residential purchasers. This is
    substantially more than can be reasonably read into the concept of a “‘walk‐through’
    inspection” by the buyer of a condominium unit. See generally McNeil Eng’g & Land
    Surveying, LLC v. Bennett, 
    2011 UT App 423
    , ¶ 17, 
    268 P.3d 854
     (“‘[A]n interpretation
    which gives a reasonable . . . meaning to all the terms [in a contract] is preferred to an
    interpretation which leaves a part unreasonable . . . .’” (quoting Restatement (Second) of
    Contracts § 203(a) (1979))).
    ¶37 Further, the procedure set forth in section 3.1 for resolving repair work identified
    during a walk‐through inspection is simply not designed to address the kind of
    problem posed by the vibration and noise in the Unit emanating from the mechanical
    room. Under section 3.1, when the need for repair work is identified, the buyer may
    “withhold [from the purchase price] in escrow . . . a reasonable amount set by Seller . . .
    sufficient to pay for completion of” the repair work. If the seller fails to complete that
    repair work within thirty days of closing, the escrowed funds may be released to the
    buyer, at the buyer’s option, “as liquidated and agreed damages for failure to complete”
    the repair work, presumably so that the buyer can then complete the repair work
    herself. Such a process is readily applicable to a defect that occurs within an individual
    unit. For example, during the aborted walk‐through inspection, the Smargons
    identified a problem with the custom flooring in the Unit. Hypothetically, had the
    Smargons closed on the Contract and GLP had not completed that repair work before
    closing, the Smargons could have opted to escrow enough money to cover the repair
    and could later complete the work themselves if GLP did not do so within the
    prescribed thirty days. In contrast, section 3.1 is ill‐adapted to the noise and vibration
    problem that confronted the Smargons. By the time scheduled for closing, and even as
    of late 2007, GLP apparently had been unable to fully remedy the mechanical room
    problem, despite having consulted with its architects and engineers. It is unreasonable
    to expect that the Smargons, no matter how sophisticated they might otherwise be,
    would be independently capable of managing the correction of a problem of that nature
    and scope. In addition, it is not reasonable to assume that GLP would even permit the
    Smargons to independently undertake modifications and repairs to such mechanical
    issues. Thus, the noise and vibration in the Unit caused by the equipment in the
    mechanical room is not reasonably redressable through the punch list process as
    provided in section 3.1 of the Contract.
    20110059‐CA                                 20
    ¶38 Accordingly, we conclude that the noise and vibration in the Unit caused by the
    equipment in the mechanical room does not fall within the scope of the punch list
    process provided for in section 3.1 of the Contract. Therefore, the district court did not
    err when it concluded that the Smargons’ refusal to close on the purchase of the Unit
    while GLP attempted to remedy the problem did not breach the Contract.
    II. Damages
    ¶39 GLP also challenges the district court’s award of damages to the Smargons. The
    Contract contains a liquidated damages provision, which provides that if GLP defaults,
    the Smargons’ “sole and exclusive remedy shall be to receive . . . a refund of the Earnest
    Money Deposit plus interest thereon at an annual rate of seven percent (7%) from the
    date of receipt of the Earnest Money Deposit in escrow until the date of [GLP]’s default
    and . . . an amount equal to the amount of the Option Payment.” After a bench trial, the
    court awarded these liquidated damages to the Smargons, reimbursing them for their
    option payment and earnest money deposits, with interest as provided by the Contract.
    The Smargons also sought expectancy damages in the amount the Unit had appreciated
    in value from the date of the Contract. The court concluded, however, that such an
    award was barred by the liquidated damages provision because the amount was
    “incapable or very difficult of accurate estimation at the time of execution of the
    contract.” Nevertheless, the court awarded the Smargons reliance damages in the
    amount they had paid for custom modifications and upgrades to the Unit. The court
    reasoned that “at the time of contract formation” GLP knew “that it would allow buyers
    of condominium units to make change order upgrades, opening the door for buyers to
    spend substantial amounts of money on those upgrades,” yet the liquidated damages
    provision did “not reasonably forecast just compensation” for those amounts in the case
    of breach. The court further reasoned that the amount the Smargons had paid to
    modify the unit was “capable of accurate estimation.” In fact, the Smargons and GLP
    stipulated to the amount the Smargons had spent to modify the Unit.
    ¶40 On appeal, GLP argues that the district court erred in awarding reliance damages
    because “the parties agreed that in the event of a breach by either party, the sole and
    exclusive remedy for the non‐breaching party would be liquidated damages in the
    amount of the Earnest Money Deposit, Option Payment, and applicable interest.” There
    are various legal standards that can be applied to determine the enforceability of a
    liquidated damages provision. See generally Commercial Real Estate Inv., LC v. Comcast of
    20110059‐CA                                 21
    Utah II, Inc., 
    2012 UT 49
    , ¶¶ 21‐32 (explaining multiple analytical approaches to
    determining the enforceability of a liquidated damages provision). In challenging the
    court’s decision, GLP’s argument focuses on a particular analytical approach where the
    enforceability of a liquidated damages provision is determined based on whether it
    amounts to a penalty. (Citing Mahoney v. Tingley, 
    529 P.2d 1068
    , 1070 (Wash. 1975);
    Margaret H. Wayne Trust v. Lipsky, 
    846 P.2d 904
    , 910 (Idaho 1993).) However, in
    reaching its decision, the district court did not conduct a penalty analysis but instead
    examined the enforceability of the liquidated damages provision under section 339 of
    the Restatement (First) of Contracts, which provides that an “agreement, made in
    advance of breach fixing the damages therefor, is not enforceable as a contract and does
    not affect the damages recoverable for the breach, unless . . . the amount so fixed is a
    reasonable forecast of just compensation for the harm that is caused by the breach, and
    . . . the harm that is caused by the breach is one that is incapable or very difficult of
    accurate estimation.” Reliance Ins. Co. v. Utah Dep’t of Transp., 
    858 P.2d 1363
    , 1367 (Utah
    1993) (internal quotation marks omitted), abrogated by Commercial Real Estate Inv., 
    2012 UT 49
    . Because GLP does not challenge the actual basis for the district court’s decision
    and failed to analyze the issue under the applicable legal standard, we decline to
    address this issue further.6 See generally Allen v. Friel, 
    2008 UT 56
    , ¶ 7, 
    194 P.3d 903
     (“If
    6. At the time of the district court’s decision, it appeared that Utah followed section 339
    of the Restatement (First) of Contracts in analyzing the validity of contractual liquidated
    damages provisions. See Reliance Ins. Co. v. Utah Dep’t of Transp., 
    858 P.2d 1363
    , 1366
    (Utah 1993) (“In determining the validity of a liquidated damages provision, this court
    has adopted section 399 of the Restatement of Contracts.”), abrogated by Commercial Real
    Estate Inv., LC v. Comcast of Utah II, Inc., 
    2012 UT 49
    , ¶ 27 (explaining that “[t]he three
    most recent Utah Supreme Court cases to consider liquidated damages have all done so
    pursuant to section 339 of the first Restatement of Contracts” but stating that prior case
    law never “officially adopted the Restatement’s test”). Very recently, in Commercial Real
    Estate Investment, LC v. Comcast of Utah II, Inc., 
    2012 UT 49
    , the Utah Supreme Court
    abandoned the Restatement approach in favor of reviewing “liquidated damages
    clauses . . . in the same manner as other contractual provisions,” which are only to be
    invalidated if “enforcement of a liquidated damages clause would be unconscionable.”
    Id. ¶ 38; see also id. ¶¶ 33‐40 (setting forth the new approach to reviewing the
    enforceability of liquidated damages provisions). Notably, on appeal GLP does not
    advocate for application of the approach ultimately adopted by the supreme court in
    (continued...)
    20110059‐CA                                   22
    an appellant fails to allege specific errors of the lower court, the appellate court will not
    seek out errors in the lower court’s decision.”).
    ¶41 GLP also argues that the Smargons were precluded from seeking both
    expectancy damages and reliance damages. The authority GLP relies on, however,
    stands for the proposition that a party cannot recover both expectancy and reliance
    damages; it does not provide that a party may not request both expectancy and reliance
    damages. See White v. Nemastil, 
    503 N.E.2d 189
    , 195 (Ohio Ct. App. 1985) (explaining
    that the buyers “were entitled to recover the highest of one of three possible measures of
    damages: (a) their expectancy damages, (b) their reliance damages, or (c) their
    restitution damages. They were not entitled to recover under more than one of these
    three legal theories.” (emphasis added) (citation omitted)). Though the Smargons may
    have requested both expectancy and reliance damages, the district court awarded only
    reliance damages. Thus, the authority GLP relies upon is inapplicable to the court’s
    decision to award the Smargons only reliance damages rather than expectancy
    damages.
    CONCLUSION
    ¶42 We conclude that the district court appropriately granted summary judgment to
    the Smargons, having determined that GLP breached the Contract by repudiation when
    it failed to provide adequate assurances to the Smargons that it would perform as
    required under the Contract. In addition, the Smargons did not breach before GLP’s
    repudiation when they refused to close as provided under section 3.1 of the Contract.
    We further decline to find error with the district court’s award of damages where GLP
    has failed to challenge the basis for the court’s decision.
    6. (...continued)
    Commercial Real Estate Investment. See generally 
    id.
     ¶¶ 22‐23, 34 (describing the penalty
    approach to assess the enforceability of liquidated damages, but declining to adopt it
    because the purpose of “the penalty inquiry . . . can be adequately protected through
    general contractual remedies”). We decline to consider or apply this recent change in
    our case law here because GLP has failed to appropriately challenge the basis for the
    district court’s decision in the first instance.
    20110059‐CA                                  23
    ¶43   Accordingly, we affirm.
    ____________________________________
    Stephen L. Roth, Judge
    ‐‐‐‐‐
    ¶44   WE CONCUR:
    ____________________________________
    James Z. Davis, Judge
    ____________________________________
    William A. Thorne Jr., Judge
    20110059‐CA                             24