Willow Creek Assoc. v. HY Barr Inc. , 2021 UT App 116 ( 2021 )


Menu:
  •                          
    2021 UT App 116
    THE UTAH COURT OF APPEALS
    WILLOW CREEK ASSOCIATES OF GRANTSVILLE LLC,
    Appellant,
    v.
    HY BARR INCORPORATED AND HYRUM BARLOW,
    Appellees.
    Opinion
    No. 20200260-CA
    Filed November 4, 2021
    Third District Court, Tooele Department
    The Honorable Matthew Bates
    No. 190300674
    Rick N. Haderlie and Christopher W. Eckels,
    Attorneys for Appellant
    Adam C. Dunn and Michael C. Dunn, Attorneys
    for Appellees
    JUDGE RYAN D. TENNEY authored this Opinion, in which
    JUDGES GREGORY K. ORME and RYAN M. HARRIS concurred.
    TENNEY, Judge:
    ¶1      Willow Creek Associates hired Hy Barr Incorporated to
    remodel some apartments. The parties’ contract included a
    mandatory arbitration agreement that required them to arbitrate
    all claims “arising out of or related to” the contract.
    ¶2    After Willow Creek and Hy Barr had a falling out over
    some payments to subcontractors, Willow Creek made a claim
    against Hy Barr and Hyrum Barlow (Hy Barr’s president) and
    submitted that claim to arbitration. But when Willow Creek later
    made other claims against Hy Barr and Barlow, it did so through
    a lawsuit. The district court dismissed those claims for failure to
    Willow Creek Assoc. v. Hy Barr Inc.
    first submit them to arbitration as required by the contract.
    Willow Creek now appeals that dismissal. We affirm.
    BACKGROUND1
    The Contract
    ¶3    Willow Creek owns an apartment complex. Hy Barr is a
    corporation that specializes in apartment renovations, and
    Hyrum Barlow is the president and owner of Hy Barr.
    ¶4     In 2017, Willow Creek and Hy Barr entered into a contract
    under which Hy Barr would remodel Willow Creek’s apartment
    complex (the Project). Willow Creek and Hy Barr agreed that
    this contract “represent[ed] the entire and integrated agreement
    between the parties.”
    ¶5    The contract identified Willow Creek as the “Owner” and
    Hy Barr as the “Contractor.” It defined “Contractor” to include
    “the Contractor’s authorized representative.” And Hyrum
    Barlow was identified in the contract as the “Contractor’s
    representative.”
    ¶6     The contract also set forth the process by which the
    parties were required to resolve their “claims and disputes.” It
    defined “claim” as “a demand or assertion by one of the parties
    seeking, as a matter of right, payment of money, or other relief
    1. “On appeal from a motion to dismiss, we review the facts only
    as they are alleged in the complaint. We accept the factual
    allegations as true and draw all reasonable inferences from those
    facts in a light most favorable to the plaintiff.” Haynes v.
    Department of Public Safety, 
    2020 UT App 19
    , n.2, 
    460 P.3d 565
    (quotation simplified).
    20200260-CA                    2               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    with respect to the terms of the Contract.” “Claim” “also
    include[d] other disputes and matters in question between the
    Owner and the Contractor arising out of or relating to the
    Contract.” (Emphasis added.) 2
    ¶7     Under the contract, a claim by Willow Creek or Hy Barr
    had to “be initiated by written notice to the other party and to
    the Initial Decision Maker.” The contract identified the Initial
    Decision Maker as the “Architect,” an architectural firm
    associated with the Project. Within ten days of receiving a claim,
    the Initial Decision Maker was required to approve or reject the
    claim. The Initial Decision Maker was also empowered to inform
    the parties that it was “unable to resolve the Claim” if the Initial
    Decision Maker thought it would be “inappropriate” to do so.
    ¶8     A decision by the Initial Decision Maker was “final and
    binding on the parties but [could be] subject to mediation.”
    Claims that were “subject to, but not resolved by, mediation
    [were] subject to arbitration.” Within thirty days of an initial
    decision, the contract allowed a party to demand that the other
    party request mediation. If that demand was made and the party
    who received the demand did not then request mediation, “both
    parties waive[d] their right to mediate or pursue binding dispute
    resolution proceedings with respect to the initial decision.”3
    2. As noted, this provision required the parties to arbitrate claims
    that were “arising out of or relating to” the contract. For stylistic
    clarity, this opinion will sometimes refer to claims that “arose
    out of or related to” the contract without noting the alteration in
    tense.
    3. As evidenced by our discussion below, this dispute-resolution
    process later proved critical in the ensuing litigation. Although
    this process called for three steps—submission to the Initial
    (continued…)
    20200260-CA                      3               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    The Initial Decision
    ¶9     In the contract, the parties agreed that Willow Creek
    would transfer money to Hy Barr, which Hy Barr would then
    use to pay subcontractors.
    ¶10 In 2019, a subcontractor filed suit against Willow Creek
    and Hy Barr after it did not receive payment for materials that it
    furnished to Hy Barr for the Project.4 In response to the
    subcontractor’s suit, Willow Creek sent a letter to the Initial
    Decision Maker and to Barlow. This letter demanded that
    “Contractor Hy Barr, Inc.” pay $648,734.78 to Willow Creek so
    that Willow Creek could pay the subcontractors.5 The Initial
    Decision Maker later agreed that “the Contractor, Hy Barr, Inc.”
    needed to pay Willow Creek $648,734.78 (hereinafter “the Initial
    Decision”).
    The Cross-claim
    ¶11 After the Initial Decision, Willow Creek timely demanded
    that Barlow and Hy Barr request mediation. When neither did,
    (…continued)
    Decision Maker, followed by mediation, followed by
    arbitration—we will sometimes refer to it globally as an
    “arbitration agreement,” though we will at other times refer to
    the individual steps individually when doing so is more
    appropriate for a particular portion of our analysis.
    4. Various organizations associated with the Project were also
    included as defendants. The district court later dismissed the
    claims against those parties.
    5. This amount included, among others, costs to pay
    subcontractors, liquidated damages, and interest.
    20200260-CA                     4               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    Willow Creek filed a cross-claim in district court against them in
    the action brought by the subcontractor.
    ¶12 In this cross-claim, Willow Creek raised twelve causes of
    action. All twelve were made against Barlow personally and
    against Hy Barr. The first cause of action, titled “Confirmation of
    Initial Decision” (the Initial Decision Claim), was based on the
    claim that Willow Creek had previously submitted to the Initial
    Decision Maker. In that cause of action, Willow Creek alleged
    that it was entitled to a court order “confirming the Initial
    Decision and entering judgment in the amount of $648,734.78
    against Contractor.” Unlike the Initial Decision Claim, however,
    the additional eleven causes of action had not been submitted to
    the Initial Decision Maker.6
    The Motion to Dismiss
    ¶13 Barlow and Hy Barr filed a joint motion to dismiss Willow
    Creek’s cross-claim. With respect to the first cause of action—the
    Initial Decision Claim—Hy Barr agreed that Willow Creek
    “should be awarded a judgment against Hy Barr, Inc. as outlined
    by the” Initial Decision. By contrast, Barlow argued that this
    cause of action did not apply to him personally because “the
    Initial Decision Maker determined that only Hy Barr, Inc. owed
    money to” Willow Creek. (Emphasis in original.)
    6. These additional causes of action were entitled: “Breach of
    Contract,” “Bad Faith Breach of Contract,” “Accounts Stated,”
    “Negligence,” “Intentional Misrepresentation,” “Negligent
    Misrepresentation,” “Unjust Enrichment,” “Violation of U.C.A.
    § 76-10-1603,” “U.C.A. § 25-6-202 to Void Fraudulent
    Conveyance,” “Alter Ego,” and “Declaratory Relief per U.C.A.
    78B-6-401, et seq.”
    20200260-CA                     5               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    ¶14 With respect to the remaining eleven causes of action, Hy
    Barr and Barlow jointly asked the court to dismiss them because
    Willow Creek had not first submitted them to the Initial Decision
    Maker as required by the contract.
    ¶15 In response to this motion to dismiss, Willow Creek
    argued that its cross-claim raised “claims that [were] not within
    and [were] completely outside of the contract.” Willow Creek
    further argued that the Initial Decision Maker “was to only
    approve or reject the initial contract issue. It was not to make
    comprehensive legal determinations under legal causes of
    action.”
    ¶16 The district court held a hearing on the motion to dismiss.
    There, Hy Barr and Barlow argued that all claims other than the
    Initial Decision Claim against Hy Barr should be dismissed
    because Willow Creek had not submitted them to the Initial
    Decision Maker. Echoing this, the court asked Willow Creek
    why it had not taken its claims to the Initial Decision Maker—
    i.e., why it should “allow [Willow Creek] to bring claims in this
    court outside of that process?” Willow Creek responded that its
    letter to the Initial Decision Maker had put Hy Barr and Barlow
    on “notice” that Willow Creek would be pursuing other legal
    claims.
    ¶17 The district court granted the motion to dismiss with
    regard to some of the claims because it was convinced that they
    “should have been submitted to” the Initial Decision Maker.7 But
    the court asked for supplemental briefing on whether the
    7. Specifically, the court dismissed Willow Creek’s claims for
    breach of contract, “Bad Faith Breach of Contract,” “Accounts
    Stated,” negligence, intentional misrepresentation, negligent
    misrepresentation, unjust enrichment, “Violation of U.C.A. § 76-
    10-1603,” and “Declaratory Relief per U.C.A. 78B-6-401.”
    20200260-CA                    6               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    fraudulent-conveyance and alter-ego claims qualified as “other
    dispute[s] or matter[s] in question between the parties that
    arise[] out of or [are] related to the contract.” The court also
    asked for supplemental briefing “on the extent to which Hyrum
    Barlow [could] be held responsible for his own tortious
    conduct.”
    ¶18 In their supplemental briefing, Hy Barr and Barlow
    argued that the phrase “arising out of or relating to” should be
    interpreted broadly and that the phrase covered the fraudulent-
    conveyance and alter-ego claims. Barlow further argued that
    because he was included in the definition of “Contractor,” claims
    against him personally were required to be submitted to the
    Initial Decision Maker.
    ¶19 Willow Creek responded that because Hy Barr and
    Barlow did not seek mediation or arbitration after the Initial
    Decision, Willow Creek could bring any claims so long as those
    claims were brought within “the time period specified by
    applicable law.” Because Hy Barr had agreed that Willow Creek
    should be awarded a judgment against Hy Barr—but not
    Barlow—based on the Initial Decision, Willow Creek also asked
    for entry of judgment on the Initial Decision Claim against Hy
    Barr.
    ¶20 At a subsequent hearing, the court concluded that the
    claims against Barlow were “subject to the dispute resolution
    terms of the contract.” This was because Barlow—the
    “authorized representative” of Hy Barr—was a “Contractor”
    under the contract. The court also concluded that the phrase
    “arising out of or relating to the contract” was “very broad
    language” that “includes, essentially, all of the claims” brought
    by Willow Creek. The court accordingly dismissed all claims
    against Hy Barr and Barlow that Willow Creek had not
    previously submitted to the Initial Decision Maker. The court
    20200260-CA                    7               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    later entered a final judgment against Hy Barr for $648,734.78
    based on the Initial Decision.8
    Willow Creek’s Rule 60 Motion
    ¶21 After the district court’s decision, Willow Creek sent
    another letter to the Initial Decision Maker asking it to now
    consider all of the claims that had been dismissed by the district
    court. In response, Hy Barr sent a letter to the Initial Decision
    Maker requesting assurances that the Initial Decision did not
    apply against Barlow. Hy Barr also asked the Initial Decision
    Maker to determine that Willow Creek did not timely request a
    decision on the claims it brought in its letter.
    ¶22 Before the Initial Decision Maker responded to these
    letters, Willow Creek filed a notice of appeal challenging the
    district court’s ruling on Hy Barr and Barlow’s motion to
    dismiss.
    ¶23 After Willow Creek filed its notice of appeal, the Initial
    Decision Maker responded to the letters from Willow Creek and
    Hy Barr. The Initial Decision Maker declined to issue any
    decision for two reasons. First, the Initial Decision Maker noted
    that its “contract obligations [had] expired, including any
    obligations to serve as Initial Decision Maker.” Second, the
    Initial Decision Maker expressed its view that it was “not
    qualified to decide the five legal issues” raised in Willow Creek’s
    letter, “and in fairness cannot respond to” Hy Barr and Barlow’s
    “requests either.”
    ¶24 Willow Creek then filed a rule 60 motion in the district
    court asking for relief from the court’s earlier order dismissing
    8. Neither party appealed the district court’s conclusion that the
    Initial Decision applied only against Hy Barr.
    20200260-CA                     8                 
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    its claims. See Utah R. Civ. P. 60 (allowing parties to file for
    “[r]elief from judgment or order”). Willow Creek argued that the
    Initial Decision Maker’s refusal to decide Willow Creek’s claims
    qualified as “newly discovered evidence” that justified relief.
    Willow Creek also argued for the first time that it was entitled to
    relief because arbitration agreements are “unenforceable where a
    plaintiff has been defrauded.”
    ¶25 The district court denied Willow Creek’s motion in
    January 2021. Willow Creek did not file a new or amended
    notice of appeal after the denial of that motion.
    ISSUE AND STANDARD OF REVIEW
    ¶26 On appeal, Willow Creek argues that the district court
    erred in dismissing its claims against Hy Barr and Barlow. A
    district court’s “grant or denial of a motion to dismiss is a
    question of law” that we review for correctness. South Jordan City
    v. Summerhays, 
    2017 UT App 18
    , ¶ 5, 
    392 P.3d 855
     (quotation
    simplified). We do “not defer in any degree” to the district
    court’s “determination of law.” 
    Id.
     (quotation simplified).
    ANALYSIS
    ¶27 In its brief, Willow Creek acknowledges that it “does not
    dispute” that the contract included an arbitration agreement.
    Rather, Willow Creek contends that its claims “against Hy Barr
    and Mr. Barlow are outside the contract and therefore not subject
    to” the arbitration agreement. In the alternative, Willow Creek
    argues that it was “inconsistent with substantial justice” to
    require Willow Creek to take its claims to an Initial Decision
    Maker who “declined to address the claims.” Willow Creek
    further argues that an arbitration agreement is “unenforceable”
    when a plaintiff alleges fraud.
    20200260-CA                     9               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    ¶28 First, we reject Willow Creek’s argument that its claims
    were “outside the contract.” Because Willow Creek’s claims
    “arose out of or related to” the contract, Willow Creek needed to
    submit them to the Initial Decision Maker. And because Willow
    Creek did not do so, the district court correctly dismissed those
    claims.
    ¶29 Second, we cannot consider Willow Creek’s arguments
    regarding the Initial Decision Maker’s refusal to hear the claims
    or the applicability of arbitration agreements to fraud claims.
    Willow Creek’s claim in this regard arose after the notice of
    appeal was filed, but it never filed a new or amended notice of
    appeal. As a result, we do not have appellate jurisdiction to
    consider these arguments.
    I. Willow Creek’s Claims “Arose Out of or Related to” the
    Contract9
    ¶30 As noted, Willow Creek and Hy Barr agreed in their
    contract that all claims “arising out of or relating to the
    Contract” must be presented to the Initial Decision Maker. After
    Willow Creek later filed twelve claims against Hy Barr and
    Barlow in district court, the court concluded that all of the claims
    “arose out of or related to” the contract and dismissed the claims
    that Willow Creek had not first submitted to the Initial Decision
    Maker.
    ¶31 On appeal, Willow Creek maintains that its claims “arise
    outside the scope of the contract and are therefore not subject to”
    the arbitration agreement. We hold that the phrase “arising out
    of or relating to” should be interpreted broadly and that Willow
    9. Willow Creek makes similar arguments about this language
    with respect to its claims against Hy Barr and Barlow. Our
    resolution applies to both.
    20200260-CA                     10               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    Creek’s claims “arose out of or related to” the contract. As such,
    Willow Creek should have first submitted them to the Initial
    Decision Maker. Because it did not, the district court correctly
    dismissed them.
    ¶32 If parties have “an agreement to arbitrate” and one party
    refuses to arbitrate, “the court shall proceed summarily to decide
    the issue and order the parties to arbitrate unless it finds that
    there is no enforceable agreement to arbitrate.” Utah Code Ann.
    § 78B-11-108(1)(b) (LexisNexis 2017).
    ¶33 This directive reflects Utah’s “strong public policy in
    favor of arbitration.” Chandler v. Blue Cross Blue Shield of Utah,
    
    833 P.2d 356
    , 358 (Utah 1992). Utah courts have repeatedly
    recognized that it “is the policy of the law in Utah to interpret
    contracts in favor of arbitration.” Central Fla. Invs., Inc. v.
    Parkwest Assocs., 
    2002 UT 3
    , ¶ 16, 
    40 P.3d 599
     (quotation
    simplified); see also Reed v. Davis County School Dist., 
    892 P.2d 1063
    , 1065 (Utah 1995) (stating that it “is the policy of the law in
    Utah to interpret contracts in favor of arbitration”); Docutel
    Olivetti Corp. v. Dick Brady Sys., Inc., 
    731 P.2d 475
    , 479 (Utah
    1986) (noting Utah’s “policy of encouraging extrajudicial
    resolution of disputes when the parties have agreed not to
    litigate”).
    ¶34 Before enforcing an arbitration agreement, we must
    resolve two questions.
    ¶35 First, we must decide if there is an “enforceable
    agreement to arbitrate.” Utah Code Ann. § 78B-11-108(1)(b).
    When doing so, we remain cognizant of Utah’s “strong public
    policy in favor of arbitration.” Chandler, 833 P.2d at 358. But,
    ultimately, “the intentions of the parties are controlling.” Central
    Fla. Invs., 
    2002 UT 3
    , ¶ 12. “[W]e first look to the plain language
    within the four corners of the agreement to determine the
    intentions of the parties.” 
    Id.
     And “[i]f the language within the
    20200260-CA                     11               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    four corners of the contract is unambiguous, the parties’
    intentions are determined from the plain meaning of the
    contractual language, and the contract may be interpreted as a
    matter of law.” 
    Id. ¶36
     Second, we must determine “which claims the parties
    intended to be subject to arbitration.” Peterson & Simpson v. IHC
    Health Services, Inc., 
    2009 UT 54
    , ¶ 18, 
    217 P.3d 716
    . On this
    question too, we recognize a preference for arbitration—i.e., “we
    encourage arbitration by liberal interpretation of the arbitration
    provisions themselves.” Cade v. Zions First Nat’l Bank, 
    956 P.2d 1073
    , 1077 (Utah Ct. App. 1998) (quotation simplified).
    ¶37 Here, we readily conclude that there was an enforceable
    arbitration agreement. Indeed, Willow Creek has conceded as
    much, stating that it “does not dispute that the parties’
    agreement contains an agreed upon [dispute-resolution]
    process.”
    ¶38 We also conclude that this arbitration agreement applied
    to claims against Barlow in his personal capacity. Under the
    contract, “claims” “include[d] other disputes and matters in
    question between the Owner and Contractor.” The contract
    primarily defined the term “Contractor” as “Hy Barr, Inc.,” but it
    also stipulated that the term “Contractor” included “the
    Contractor’s authorized representative.” The contract then
    identified “Hyrum Barlow” as the “Contractor’s representative.”
    ¶39 In its brief, Willow Creek notably “does not dispute” that
    Barlow qualified as a Contractor. Thus, because it stands
    undisputed that Barlow was a “Contractor” under this contract,
    Willow Creek was contractually required to first raise any claims
    it had against him to the Initial Decision Maker.
    ¶40 Because Willow Creek concedes that there was an
    enforceable arbitration agreement, and because that agreement
    20200260-CA                    12               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    applied to the claims made against both Hy Barr and Barlow, the
    remaining question is whether Willow Creek’s claims fell within
    the scope of that agreement. We conclude that they did.
    ¶41 “When we interpret a contract,” we start with its plain
    language. Brady v. Park, 
    2019 UT 16
    , ¶ 53, 
    445 P.3d 395
    . “If the
    language within the four corners of the contract is unambiguous,
    the parties’ intentions are determined from the plain meaning of
    the contractual language, and the contract may be interpreted as
    a matter of law.” Central Fla. Invs., 
    2002 UT 3
    , ¶ 12. And in
    “many cases, we need look no further than the plain language of
    the contract, because that language may unambiguously tell us
    what the parties intended.” Ocean 18 LLC v. Overage Refund
    Specialists LLC (In re Excess Proceeds from Foreclosure of 1107
    Snowberry St.), 
    2020 UT App 54
    , ¶ 22, 
    474 P.3d 481
    .
    ¶42 Our analysis is guided by “the ordinary and usual
    meaning of the words.” South Ridge Homeowners’ Ass’n v. Brown,
    
    2010 UT App 23
    , ¶ 1, 
    226 P.3d 758
     (quotation simplified); see also
    Pugh v. Stockdale & Co., 
    570 P.2d 1027
    , 1029 (Utah 1977); Berman
    v. Berman, 
    749 P.2d 1271
    , 1273 (Utah Ct. App. 1988). And when
    assessing such meaning, we often look to “standard, non-legal
    dictionaries.” Warburton v. Virginia Beach Fed. Sav. & Loan Ass’n,
    
    899 P.2d 779
    , 782 (Utah Ct. App. 1995).
    ¶43 Here, we start—and ultimately end—with the plain
    language of the arbitration agreement. Willow Creek and Hy
    Barr agreed that claims between them would go first to an Initial
    Decision Maker. They further agreed that “claims” included
    disputes “arising out of or relating to” the contract.
    ¶44 “Arising out of” means to “spring up, come into
    existence or notice.” Oxford English Dictionary online,
    “arise” (definition 18a). And the verb “arise” describes
    something that “originate[s] from a source.” Arise, Merriam-
    Webster online, (definition 1b), https://www.merriam-
    20200260-CA                    13               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    webster.com/dictionary/arise      [https://perma.cc/REE5-9ES2].
    “Arise” also means to “stem” or “result” from something. Arise,
    Black’s Law Dictionary (11th ed. 2019).
    ¶45 The phrase “related to” more generally describes
    things that have “some connection with” each other. Oxford
    English Dictionary online, “relate” (definition 6a). Put
    differently, “relate to” is used “to connect (something) with
    (something else).” Relate to, Merriam-Webster online, (definition
    1),    https://www.merriam-webster.com/dictionary/relate%20to
    [https://perma.cc/GY9V-GK4V]. Something is “related” when it
    is “[c]onnected in some way” or has a “relationship to or with”
    the other thing. Related, Black’s Law Dictionary (11th ed. 2019).
    ¶46 When used together, the phrase “relating to” broadens
    the reach of “arising out of.” See Coregis Ins. v. American Health
    Found., Inc., 
    241 F.3d 123
    , 128–29 (2d Cir. 2001) (explaining that
    “‘related to’ is typically defined more broadly” than “arising out
    of”). In this sense, a claim “need only have some logical or causal
    connection to the agreement to be related to it.” In re Remicade
    (Direct Purchaser) Antitrust Litig., 
    938 F.3d 515
    , 524 (3d Cir. 2019)
    (quotation simplified).
    ¶47 Given these principles, courts have commonly given
    broad interpretations to provisions like the one at issue here. The
    United States Supreme Court, for example, held that an
    arbitration agreement that covered claims “arising out of or
    relating to” a contract was “easily broad enough to encompass”
    fraudulent-inducement claims. Prima Paint Corp. v. Flood
    & Conklin Mfg. Co., 
    388 U.S. 395
    , 406 (1967). And the Eighth
    Circuit held that an arbitration agreement that applied to claims
    “arising out of or relating to” an agreement was “the broadest
    language the parties could reasonably use to subject their
    disputes to [arbitration], including collateral disputes that relate
    to the agreement containing the clause.” Fleet Tire Service of N.
    Little Rock v. Oliver Rubber Co., 
    118 F.3d 619
    , 620–21 (8th Cir.
    20200260-CA                     14               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    1997). Other courts have held similarly. See, e.g., JLM Indus., Inc.
    v. Stolt-Nielsen SA, 
    387 F.3d 163
    , 172 (2d Cir. 2004); Polyflow,
    L.L.C. v. Specialty RTP, L.L.C, 
    993 F.3d 295
    , 303–04 (5th Cir. 2021);
    Gore v. Alltel Commc’ns, LLC, 
    666 F.3d 1027
    , 1034 (7th Cir. 2012);
    Newmont U.S.A. Ltd. v. Insurance Co. of N. Am., 
    615 F.3d 1268
    ,
    1274–75, 1275 n.5 (10th Cir. 2010).
    ¶48 Applied here, “arising out of or relating to” is broad
    enough to cover Willow Creek’s claims. Willow Creek’s cross-
    claim included general allegations, several of which alleged that
    Hy Barr and Barlow “failed” to do certain things “as required by
    the Contract.” Willow Creek alleged, for example, that Hy Barr
    and Barlow “failed to pay subcontractors and suppliers,” “failed
    to provide bonds,” and failed to “complete the Project”—all “as
    required by contract.” Willow Creek’s generalized reference to
    the fact that such claims stemmed from the “contract”
    demonstrates that those claims were subject to the contract’s
    arbitration agreement.
    ¶49 So too with the more specific language included in the
    claims themselves. For example, Willow Creek complained of
    Hy Barr and Barlow’s failures to “pay subcontractors” and
    “perform their work in competent, workmanlike manners.” But
    in the contract, the parties agreed that the Contractor would pay
    subcontractors: “The Contractor shall pay each Subcontractor no
    later than seven days after receipt of payment from [Willow
    Creek].” The parties also agreed that the Contractor would
    “require each Subcontractor to make payments to Sub-
    subcontractors in a similar manner.” And as explained above,
    “Contractor” included both Hy Barr and Barlow. The claims
    against Hy Barr and Barlow were therefore directly linked to
    specific contractual provisions.
    ¶50 Willow Creek also complained of Hy Barr and Barlow’s
    failure to “perform their work in competent, workmanlike
    manners.” But in the contract, the parties detailed the necessary
    20200260-CA                     15               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    renovations and agreed that the “Contractor” “shall be solely
    responsible for, and have control over, construction means,
    methods, techniques, sequences and procedures and for
    coordinating all portions of the Work under the Contract.” The
    contract also stated that the “Contractor” would ensure that the
    “materials and equipment” would be “of good quality” and that
    the work would be “free from defects.” And the contract further
    required the “Contractor” to comply with “laws, statutes,
    ordinances, codes, rules and regulations.” Because the contract
    explained what work Hy Barr and Barlow were required to do
    and how they were required to do it, Willow Creek’s claims that
    Hy Barr and Barlow “failed to perform their work in competent,
    workmanlike manners” originate from the contract.
    ¶51 In short, Willow Creek’s claims either directly stemmed
    from the contract or at least had “some logical or causal
    connection” to it. In re Remicade (Direct Purchaser) Antitrust Litig.,
    938 F.3d at 524. Given the broad interpretation that we give to
    the arbitration provision, we readily conclude that these claims
    “arose out of or related to” the contract. As a result, Willow
    Creek was required to submit them to the Initial Decision Maker.
    Because it failed to do so, the district court correctly dismissed
    those claims.10
    10. Willow Creek also argues that the arbitration agreement
    should be deemed unenforceable because it is “unfair” to make
    Willow Creek submit claims to someone who lacks “legal
    expertise.” But to properly preserve an issue for appeal, an
    “issue must be specifically raised” to the district court and
    “supported by evidence and relevant legal authority.” Donjuan v.
    McDermott, 
    2011 UT 72
    , ¶ 20, 
    266 P.3d 839
    . While Willow Creek
    made passing reference to this argument below, it did not
    support this reference with developed argument that was based
    on “relevant legal authority.” 
    Id.
     This argument is accordingly
    (continued…)
    20200260-CA                      16               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    II. This Court Lacks Appellate Jurisdiction to Consider the
    Arguments Willow Creek Raised in Its Rule 60 Motion
    ¶52 Willow Creek next argues that, even if its claims were
    required to go to the Initial Decision Maker, this court should
    still consider those claims because not doing so would be
    “unfairly prejudicial to Willow Creek’s ability to obtain
    substantial justice.” In Willow Creek’s view, this is so because
    the Initial Decision Maker “declined to address the claims” and
    (…continued)
    unpreserved. And because Willow Creek does not assert in its
    appellate brief that this argument is subject to a preservation
    exception, it fails. See State v. Johnson, 
    2017 UT 76
    , ¶¶ 14–17, 
    416 P.3d 443
    .
    In any event, the parties anticipated that the Initial
    Decision Maker might not be able to resolve all potential claims.
    This is presumably why they included a provision in the
    contract that allowed the Initial Decision Maker to “advise the
    parties” that it was “unable to resolve [a] Claim” if “it would be
    inappropriate for the Initial Decision Maker” to do so. But even
    with this recognition, the parties still also agreed that all claims
    “arising out of or relating to” the contract must first go to the
    Initial Decision Maker—which is the very thing that would
    allow the Initial Decision Maker to decide, for example, that it
    would be unable to resolve any particular claim.
    While Willow Creek now apparently regards this agreed-
    upon sequencing to be imprudent, this is not a basis for us to
    undo the contract. See Ted R. Brown & Assocs., Inc. v. Carnes Corp.,
    
    753 P.2d 964
    , 970 (Utah Ct. App. 1988) (“[A] court may not make
    a better contract for the parties than they have made for
    themselves . . . .”). As a result, these claims were subject to the
    arbitration agreement. And for the reasons explained above,
    Willow Creek’s failure to first submit them to arbitration was
    grounds for the district court to dismiss them.
    20200260-CA                     17               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    because arbitration agreements (allegedly) cannot apply to fraud
    claims. We cannot address these arguments, however, because
    Willow Creek raised them for the first time below after the notice
    of appeal was filed and yet never filed an amended notice of
    appeal. Moreover, Willow Creek has not presented us with any
    reason to review them as unpreserved grounds for overturning
    the district court’s ruling.
    ¶53 In the briefing and arguments on the motion to dismiss,
    Willow Creek argued that its claims were “completely outside
    the contract,” that the arbitration agreement could not “replace[]
    the legislature’s statutes of limitations,” and that the Initial
    Decision had given Hy Barr and Barlow “timely notice of Willow
    Creek’s claims.” But Willow Creek never argued that the Initial
    Decision Maker had refused to consider its claims or that
    arbitration agreements cannot apply to fraud claims. Instead, it
    raised those arguments for the first time in a rule 60 motion,
    which was after it had filed a notice of appeal from the earlier
    order dismissing its claims.11
    ¶54 Rule 60 allows a court to “relieve a party” from an order
    under certain circumstances. Utah R. Civ. P. 60(b). But when a
    party files a notice of appeal before the court enters an order
    disposing of a rule 60 motion, the notice of appeal “is effective to
    appeal only from the underlying judgment.” Utah R. App. P.
    4(b)(2). If the party wants the appellate court to also consider the
    district court’s disposition of the rule 60 motion, the “party must
    file a notice of appeal or an amended notice of appeal within the
    11. Indeed, Willow Creek could not have challenged the Initial
    Decision Maker’s refusal to hear these claims in its notice of
    appeal, because the Initial Decision Maker had not made that
    decision yet. This is likely why Willow Creek argued that the
    Initial Decision Maker’s decision was “newly discovered
    evidence” that justified relief from the district court’s order.
    20200260-CA                     18               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    prescribed time.” 
    Id.
     If there is no new or amended notice of
    appeal filed after the denial of the rule 60 motion, “an appellate
    court lacks jurisdiction to consider issues raised” in the rule 60
    motion. Li-Huang Pon v. Brewer, 
    2020 UT App 99
    , ¶ 7, 
    468 P.3d 581
    ; see also Dole v. Dole, 
    2018 UT App 195
    , ¶ 40, 
    437 P.3d 464
    (noting that a party’s failure to amend a notice of appeal after
    entry of judgment on a post-trial motion deprives a court of
    “jurisdiction to consider” its “arguments related to [a] post-trial
    motion”).
    ¶55 Again, Willow Creek did not raise these issues until its
    rule 60 motion, which was filed and ruled on after the notice of
    appeal, but Willow Creek did not file an amended notice of
    appeal after that ruling. As a result, we “lack jurisdiction to
    consider” those arguments now. See Dole, 
    2018 UT App 195
    ,
    ¶ 40.12
    12. In theory, Willow Creek could have argued that the district
    court committed plain error by not recognizing, in its initial
    dismissal of the claims, that fraud claims are not subject to
    arbitration agreements. But Willow Creek did not make that
    plain error argument in its brief, so it is not before us now. See
    State v. Peterson, 
    881 P.2d 965
    , 968 (Utah Ct. App. 1994) (refusing
    to consider an issue raised “for the first time on appeal” when
    the party did not argue plain error).
    In any event, plain error occurs only when the error
    “should have been obvious to the district court,” and to establish
    obviousness, the party “must show that the law governing the
    error was clear at the time the alleged error was made.” Veracity
    Networks LLC v. MCG S. LLC, 
    2019 UT App 53
    , ¶ 27, 
    440 P.3d 906
    (quotation simplified). This was not so here. Willow Creek
    points to Energy Claims Ltd. v. Catalyst Inv. Group Ltd., 
    2014 UT 13
    , 
    325 P.3d 70
    . But in that case, the supreme court held that a
    “forum selection clause [is] unenforceable” when a party claims
    (continued…)
    20200260-CA                    19               
    2021 UT App 116
    Willow Creek Assoc. v. Hy Barr Inc.
    CONCLUSION
    ¶56 Willow Creek’s claims against Hy Barr and Barlow “arose
    out of or related to” the contract. Willow Creek was therefore
    contractually obligated to take those claims to the Initial
    Decision Maker. Because it did not, the district court correctly
    dismissed those claims. Moreover, because Willow Creek’s
    additional arguments about the enforceability of the arbitration
    agreement are outside of this court’s appellate jurisdiction, we
    cannot consider them. We accordingly affirm.
    (…continued)
    that “the contract was entered into fraudulently.” 
    Id. ¶¶ 51
    –52
    (emphasis added). Here, however, Willow Creek does not claim
    that its contract with Hy Barr was “entered into fraudulently.”
    Rather, it complains only of fraud that it believes occurred
    during the parties’ subsequent business dealings. Willow Creek
    points to no authority that obviously establishes that parties
    cannot agree to arbitrate any claims of fraud that arise from their
    subsequent business dealings.
    20200260-CA                    20               
    2021 UT App 116