UDOT v. Coalt Inc. , 382 P.3d 602 ( 2016 )


Menu:
  •                        
    2016 UT App 169
    THE UTAH COURT OF APPEALS
    UTAH DEPARTMENT OF TRANSPORTATION,
    Appellee,
    v.
    COALT INC.,
    Appellant.
    Opinion
    No. 20150149-CA
    Filed August 4, 2016
    Second District Court, Farmington Department
    The Honorable John R. Morris
    No. 080700367
    Michael R. Carlston, Rodney R. Parker, and Robert T.
    Denny, Attorneys for Appellant
    Sean D. Reyes, Brent A. Burnett, and Randy S.
    Hunter, Attorneys for Appellee
    JUDGE STEPHEN L. ROTH authored this Opinion, in which JUDGE
    GREGORY K. ORME and SENIOR JUDGE RUSSELL W. BENCH
    concurred.1
    ROTH, Judge:
    ¶1    In connection with the construction of the Legacy
    Parkway Project (also known as the Legacy Highway), the Utah
    Department of Transportation (UDOT) exercised its power of
    eminent domain to condemn approximately sixty-five acres of
    property (Parcel 84) in Davis County, Utah, that Coalt Inc.
    owned. Following a four-day bench trial, the court ruled that
    UDOT had authority to condemn Coalt’s land and that Coalt,
    1. Senior Judge Russell W. Bench sat by special assignment as
    authorized by law. See generally Utah R. Jud. Admin. 11-201(6).
    UDOT v. Coalt Inc.
    although entitled to compensation, was not entitled to any
    incremental increase in value attributable to the Legacy Parkway
    Project itself. Coalt argues on appeal that the district court erred
    in deciding that UDOT had authority to condemn its property.
    Alternatively, Coalt contends that if UDOT had condemnation
    authority, then the court erred by not considering any enhanced
    value attributable to the project in determining just
    compensation for the taking of Parcel 84. We conclude that the
    district court did not err when it determined that UDOT’s
    condemnation of Parcel 84 was ‚a proper exercise of eminent
    domain.‛ But we also conclude that the district court should
    have considered the effect of the Legacy Parkway Project in
    determining just compensation for the taking. Accordingly, we
    remand to the district court to redetermine the amount to be
    awarded to Coalt for the taking.
    BACKGROUND2
    ¶2     Planning for the Legacy Parkway Project began over
    twenty years ago with the goal of easing traffic congestion
    between Salt Lake and Davis counties. The Legacy Highway was
    slated for construction west of the existing interstate, and due to
    its proximity to the Great Salt Lake and the lake’s ecosystem,
    environmental impacts were a concern from the outset. UDOT
    began acquiring land, not only to build the highway itself, but
    also to mitigate the ‚environmental impacts of the construction,
    operation, and maintenance of the Legacy Parkway.‛ As part of
    this process, UDOT, the United States Federal Highway
    Administration (the FHA), and the United States Army Corps of
    Engineers (the Corps) completed a Final Environmental Impact
    2. ‚On appeal from a bench trial, we review the evidence in a
    light most favorable to the trial court’s findings, and therefore
    recite the facts consistent with that standard.‛ Alvey Dev. Corp. v.
    Mackelprang, 
    2002 UT App 220
    , ¶ 2, 
    51 P.3d 45
     (citation and
    internal quotation marks omitted).
    20150149-CA                     2                
    2016 UT App 169
    UDOT v. Coalt Inc.
    Statement (the Final EIS) in June 2000. The Final EIS set forth in
    detail the scope of the Legacy Parkway Project, including
    identification of the land needed for mitigation of the
    environmental impacts of the project. Notably, Parcel 84 was not
    identified as part of the project in the Final EIS, although other
    parcels of Coalt’s land were identified for mitigation purposes.
    ¶3     In January 2001, the Corps issued a Record of Decision
    approving the route for the Legacy Parkway along with the
    necessary federal permits. Just weeks later, several public
    interest environmental groups (public interest litigants) 3 brought
    suit in the United States District Court for the District of Utah,
    asserting that the Final EIS did not comply with federal
    environmental law and sought to vacate the permit. See generally
    Utahns for Better Transp. v. United States Dep’t of Transp., 
    180 F. Supp. 2d 1286
     (D. Utah 2001). When the court ruled in UDOT’s
    favor, the public interest litigants filed an appeal with the Tenth
    Circuit Court of Appeals. While that appeal was pending, the
    public interest litigants also filed an emergency motion for a
    preliminary injunction, which the Tenth Circuit granted. The
    preliminary injunction prohibited UDOT from ‚any further
    action that will disturb the ground or vegetation in the proposed
    right of way,‛ essentially bringing the project to a halt. Utahns for
    Better Transp. v. United States Dep’t of Transp., Nos. 01-4216, 01-
    4217, 01-4220, 
    2001 WL 1739458
    , at *5 (10th Cir. Nov. 16, 2001). In
    September 2002, the Tenth Circuit ruled that portions of the
    Final EIS were inadequate and remanded the case for further
    review. See generally Utahns for Better Transp. v. United States
    Dep’t of Transp., 
    305 F.3d 1152
     (10th Cir. 2002). Over the next two
    years, UDOT, the FHA, and the Corps completed additional
    environmental reviews and subsequently put out for public
    3. Initially, the public interest litigants included Utahns for Better
    Transportation, Salt Lake City Mayor Rocky Anderson, and the
    Sierra Club. Eventually, the group grew to include the Future
    Moves Coalition, FRIENDS of Great Salt Lake, Great Salt Lake
    Audubon, and the League of Women Voters of Salt Lake as well.
    20150149-CA                      3                
    2016 UT App 169
    UDOT v. Coalt Inc.
    comment an updated Draft Supplemental Environmental Impact
    Statement in December 2004. Again, Parcel 84 was not identified
    as part of the project.
    ¶4      During the public comment period, the public interest
    litigants asserted that UDOT, the FHA, and the Corps had again
    failed to comply with federal environmental law, and they
    threatened further litigation if UDOT did not take steps to
    resolve the problems that the public interest litigants had
    identified. In September 2005, UDOT and the public interest
    litigants began settlement negotiations and eventually reached
    an ‚Agreement in Principle‛ that would ‚resolve and settle
    differences over the Legacy Parkway project.‛ That agreement,
    among other things, provided for additional environmental
    mitigation:
    Mitigation
    UDOT will acquire approximately 125 acres
    of land located west of the Legacy Parkway at 500
    South as long as this land is accepted by the U.S.
    Army Corps of Engineers for use for mitigation for
    other (non-Legacy Parkway) transportation
    projects in the North Corridor. Corps approval is a
    condition precedent to completion of a final
    settlement.
    This Mitigation Property will be managed as
    nature preserve in coordination with Legacy
    Nature Preserve.
    Parcel 84 was a part of the acreage described in this provision.
    One month later, UDOT and the FHA approved the Final
    Supplemental Environmental Impact Statement (the Final
    Supplemental EIS) for the Legacy Parkway Project without
    including Parcel 84. At about the same time, UDOT sent a letter
    to the Corps stating that the 125 acres (the Mitigation Property)
    identified in the Agreement in Principle would be ‚in addition to
    20150149-CA                    4               
    2016 UT App 169
    UDOT v. Coalt Inc.
    the mitigation proposed for *permitting+ the Legacy Parkway‛
    and that ‚UDOT would like to work with the Corps . . . to
    establish procedures for utilizing any excess mitigation credits
    generated from this additional mitigation property‛ ‚for other
    projects in the future.‛ The Corps agreed that the ‚acquisition of
    the [additional] lands would be a benefit to the Legacy Nature
    Preserve‛ and therefore ‚the property *could] be used to
    generate wetland mitigation credit‛ that in the future could be
    ‚applied to a *different+ transportation project located in the
    North Corridor.‛
    ¶5      UDOT and the public interest litigants eventually signed
    the Settlement Agreement, thereby ending the years-long
    litigation that had delayed the Legacy Parkway Project. The
    Settlement Agreement provided,
    UDOT will establish additional consolidated
    offsite mitigation for transportation projects by
    obtaining approximately 121 acres of mitigation
    property located in the vicinity of 500 South, west
    of the Legacy Parkway alignment (‚Mitigation
    Property‛) . . . .
    (1) The U.S. Army Corps of Engineers has
    provided a letter advising that it will
    allow credits from this Mitigation
    Property to be used as mitigation for
    transportation projects.
    (2) This Mitigation Property will be
    managed in coordination with the
    Legacy Nature Preserve, for purposes of
    a nature preserve and the property will
    be subject to the same deed restrictions
    as apply in the [permit] to property in
    the Legacy Nature Preserve.
    20150149-CA                     5              
    2016 UT App 169
    UDOT v. Coalt Inc.
    (3) UDOT may, with approval of the U.S.
    Army Corps of Engineers, adjust the
    boundaries of the Legacy Nature
    Preserve by using some or all of the
    Advanced Mitigation Property.
    The Mitigation Property included the approximately sixty-five
    acres that comprised Parcel 84. While UDOT considered
    acquisition of the Mitigation Property to be integral to resolution
    of the litigation and hence to the viability of the project, neither
    of the federal permitting agencies—the FHA and the Corps—
    required such ‚additional mitigation‛ as a condition of ‚Federal
    approval of the Legacy Parkway Project or the issuance of the
    necessary Federal records of decisions and permits.‛ With
    support from the governor, the Utah Legislature held a special
    session in November 2005 to approve UDOT’s execution of a
    settlement agreement ‚to resolve all pending litigation and
    potential future claims of the [public interest litigants] and allow
    for the construction of the Legacy Parkway.‛ The legislature
    approved the expenditure of more than $1,000,000 for the costs
    of this resolution, including purchase of the Mitigation Property.
    ¶6      In January 2006, the FHA issued a Record of Decision
    approving the Final Supplemental EIS. This Record of Decision
    contained a section titled, ‚STATE OF UTAH SETTLEMENT
    AGREEMENT,‛ which began, ‚After the previous litigation
    delayed the project, resulting in higher construction project costs
    and adverse transportation impacts, a compromise to end that
    litigation and avoid future litigation was desirable.‛ The
    Settlement Agreement included ‚certain design and operational
    configurations‛ for the Legacy Parkway, including a ‚restriction
    on large trucks,‛ the use of ‚noise-reducing pavement,‛
    increasing the ‚curvature to the roadway‛ in order to ‚enhance
    the parkway setting,‛ ‚meander*ing+ the alignment of the
    *parkway’s+ footprint . . . *to+ reduce*+ impacts on wetlands and
    other sensitive environmental features,‛ and a maximum speed
    of fifty-five miles per hour—to the end that ‚the former *public
    20150149-CA                     6                
    2016 UT App 169
    UDOT v. Coalt Inc.
    interest litigants] and other interested parties will not bring
    suit.‛ In addition, this section included a subsection titled
    ‚Terms Not Specific to the Legacy Parkway Project,‛ which
    began, ‚Although technically unrelated to Legacy Parkway,
    UDOT will also undertake the following steps pursuant to the
    Settlement Agreement.‛ One of those steps was that UDOT
    would ‚*o+btain additional mitigation property (121 acres) west
    of Legacy Parkway near 500 South to be managed for wetlands
    and wildlife mitigation,‛ and the ‚*m+itigation credits for this
    property will be available for other transportation projects.‛ The
    Record of Decision noted that the Settlement Agreement
    provided that:
    [t]he 121-ac[re] parcel . . . will not be used as
    mitigation for Legacy Parkway, but rather as
    possible mitigation for other transportation
    projects in the North Corridor, such as I-15
    reconstruction. Once acquired, the site will be
    managed as part of the Preserve. In a letter from
    the Corps to UDOT, dated October 31, 2005, the
    Corps recognized that acquisition of the site will
    benefit the Preserve because the land will buffer
    the    Preserve    from     planned     commercial
    development that could indirectly impact wetlands
    on the Preserve. The amount of wetland mitigation
    credit for this additional 121-ac[res] of land will
    depend on the acres of wetlands on the site and the
    degree that the protection and management of the
    property will increase the overall functioning of
    neighboring wetlands on the Preserve.
    ¶7     The Corps issued a separate Record of Decision, also in
    January 2006, that approved the Final Supplemental EIS. This
    document also contained a section titled, ‚SETTLEMENT
    AGREEMENT.‛ The Corps, like the FHA, recognized that the
    Settlement Agreement included ‚certain design and operational
    configurations for Legacy Parkway‛ and that additional ‚steps,
    20150149-CA                     7              
    2016 UT App 169
    UDOT v. Coalt Inc.
    which are unrelated to the Legacy Parkway,‛ would be taken by
    UDOT, including the acquisition of ‚additional 121-acre
    mitigation property west of the Legacy Parkway near 500 South
    to be managed for wetlands and wildlife mitigation, with credits
    available for other transportation projects.‛ The Corps’ Record of
    Decision also contained a paragraph that was similar to the
    FHA’s, indicating that this additional acreage ‚will not be used
    as mitigation for the Legacy [Parkway Project], but rather as
    possible mitigation for other transportation projects in the north
    corridor, such as I-15 reconstruction.‛ The Corps’ Record of
    Decision also acknowledged that as a result of the Settlement
    Agreement, the public interest litigants ‚will not bring suit‛
    challenging the Final Supplemental EIS or any Record of
    Decision or permit.
    ¶8     In June 2008, UDOT began proceedings to acquire Parcel
    84 by eminent domain. See generally Utah Code Ann. § 78B-6-501
    (LexisNexis Supp. 2015).4 UDOT asserted that the condemnation
    was ‚necessary and in the public interest‛ for a state public
    transportation purpose pursuant to sections 72-5-103 and 78B-6-
    501 of the Utah Code. The case went to trial in March 2014.
    Ultimately, the district court ruled that UDOT had ‚authority to
    condemn property for the Legacy Parkway Project, as a state
    transportation purpose‛; that condemning Coalt’s property
    (including Parcel 84) ‚was necessary to effect a lifting of the stay
    on construction of the Legacy Parkway imposed by the Tenth
    Circuit Court of Appeals‛; that UDOT ‚had authority to
    condemn *Coalt’s+ property‛; that ‚the taking was for a public
    state transportation purpose‛; and that, therefore, ‚*g+iven the
    public purpose served by *UDOT’s+ taking of *Coalt’s+ property,
    the taking was not merely for the purpose of conveying a benefit
    on one or more private parties,‛ i.e., the public interest litigants.
    4. Because the statutory provisions in effect at the relevant times
    do not differ materially from the statutory provision now in
    effect, we cite the current version of the Utah Code Annotated
    for convenience.
    20150149-CA                      8               
    2016 UT App 169
    UDOT v. Coalt Inc.
    The court also found that the scope of the Legacy Parkway
    Project was ‚broader‛ than the Final EIS and the Final
    Supplemental EIS. Therefore, the court concluded that the taking
    of Coalt’s property for the Legacy Nature Preserve was ‚within
    the scope‛ of the project because ‚at some point‛ Coalt’s
    property ‚would be needed‛ for the Legacy Parkway Project. In
    sum, the court concluded that UDOT’s taking of Parcel 84 was ‚a
    proper exercise of eminent domain‛ under sections 72-5-102(2),
    72-5-102(12), and 72-5-103(1) of the Utah Code. The court further
    determined that although Coalt was entitled to just
    compensation for the taking, it was not entitled to compensation
    for any increase in value resulting from the property’s proximity
    to the Legacy Parkway Project. Coalt appeals.
    ISSUES AND STANDARDS OF REVIEW
    ¶9      Coalt raises two issues on appeal. First, Coalt argues that
    section 72-5-102(12) of the Utah Code, ‚which authorizes
    condemnation for ‘the mitigation of impacts from public
    transportation projects,’‛ does not authorize ‚the condemnation
    of property for the sole purpose of settling ‘public interest’
    litigation that is interfering with completion of a project.‛
    (Quoting 
    Utah Code Ann. § 72-5-102
    (12) (LexisNexis 2009).) ‚We
    review questions of statutory interpretation for correctness.‛
    Utah Dep’t of Transp. v. FPA West Point, LLC, 
    2012 UT 79
    , ¶ 9, 
    304 P.3d 810
    .
    ¶10 Coalt next argues that ‚*i+f UDOT had authority to
    condemn Coalt’s property,‛ then ‚the significant positive impact
    of the Legacy project on the property’s value *should+ have been
    considered [by the district court] in fixing the property’s fair
    market value.‛ The issue of whether to include enhancement in
    value as a result of project proximity is a question of law
    reviewed for correctness. Board of County Comm’rs of Tooele
    County v. Ferrebee, 
    844 P.2d 308
    , 309 (Utah 1992) (reviewing
    ‚whether the trial court properly included an enhancement in
    20150149-CA                     9               
    2016 UT App 169
    UDOT v. Coalt Inc.
    [property] value based on proximity to the [project]‛ for
    correctness).
    ANALYSIS
    ¶11 An appellate court’s power to review a public entity’s
    decision to condemn a particular piece of property is limited. For
    example, in Utah Department of Transportation v. Fuller the Utah
    Supreme Court stated,
    ‚It may be said to be a general rule that, unless a
    corporation exercising the power of eminent
    domain acts in bad faith or is guilty of oppression,
    its discretion in the selection of land will not be
    interfered with. With the degree of necessity or the
    extent which the property will advance the public
    purpose, the courts have nothing to do. When the
    use is public, the necessity or expediency of
    appropriating any particular property is not a
    subject of judicial cognizance.‛
    
    603 P.2d 814
    , 817 (Utah 1979) (quoting Postal Tel. Cable Co. of Utah
    v. Oregon Short Line R.R., 
    65 P. 735
    , 739 (Utah 1901)). Further,
    ‚*w+e do not review the internal processes of, or external
    influences on, UDOT in arriving at its decision to condemn
    particular properties for transportation purposes, except for
    indications of bad faith.‛ Utah Dep’t of Transp. v. G. Kay, Inc., 
    2003 UT 40
    , ¶ 11, 
    78 P.3d 612
    . Here, Coalt has not alleged that UDOT
    acted in bad faith or is guilty of oppression; instead, Coalt argues
    that the taking of Parcel 84 was not for a public purpose and that
    the condemnation was only ‚a response to a demand by private
    litigants challenging the Legacy Parkway environmental
    assessment.‛ UDOT does not disagree with this characterization:
    ‚The sole purpose for condemning Coalt’s property was to settle
    litigation that had halted completion of the Legacy Parkway
    Project.‛ Thus, the question then becomes whether UDOT’s
    20150149-CA                      10               
    2016 UT App 169
    UDOT v. Coalt Inc.
    decision to condemn Parcel 84—a piece of land not required for
    environmental mitigation by the federal government in either
    the Final EIS or the Final Supplemental EIS for the completion of
    the Legacy Highway—was done for a state transportation
    purpose. Coalt has not persuaded us that UDOT’s reasons for
    acquiring Parcel 84 exceed the broad reach of public purpose.
    I. The Public Transportation Purpose of Parcel 84
    ¶12 Coalt does not dispute that the Legacy Highway Project
    itself is a transportation project authorized by the state
    legislature for public use and therefore within the scope of a
    ‚public purpose‛ for which the power of eminent domain may
    be exercised. Rather, Coalt argues that ‚there was no public
    purpose‛ for taking Parcel 84 by eminent domain for the Legacy
    Highway Project. Coalt points us to decisions from the Utah
    Supreme Court to support its assertion that, ‚[t]he condemning
    authority bears ‘the burden of coming forward with the evidence
    of, and the burden of persuasion to establish, its right to
    condemn.’‛ (Quoting Utah State Road Comm’n v. Friberg, 
    687 P.2d 821
    , 832 (Utah 1984), and citing Salt Lake County v. Ramoselli, 
    567 P.2d 182
    , 183 (Utah 1977); Monetaire Mining Co. v. Columbus
    Rexall Consol. Mines Co., 
    174 P. 172
    , 177 (Utah 1918); Tanner v.
    Provo Bench Canal & Irrigation Co., 
    121 P. 584
    , 589 (Utah 1911).)
    And, according to Coalt, ‚UDOT has all but admitted that it
    cannot identify a public purpose‛ for taking Parcel 84 by
    eminent domain, because ‚*t+he undisputed facts show that the
    taking was a response to a demand by private litigants
    challenging the Legacy Parkway environmental assessment‛ and
    that ‚neither UDOT nor the Corps believed the property was
    necessary to the project, either directly or as environmental
    mitigation.‛ Coalt argues that section 72-5-103 of the Utah Code
    only permits UDOT ‚to condemn real property that is necessary
    for temporary, present, or reasonable future state transportation
    purposes‛ and that, as a result, ‚land in excess of that needed for
    a particular present or future project cannot be deemed
    necessary for a state transportation purpose.‛ (Emphasis and
    internal quotation marks omitted.)
    20150149-CA                    11               
    2016 UT App 169
    UDOT v. Coalt Inc.
    ¶13 The district court concluded that UDOT ‚ha*d+ authority
    to condemn property for the Legacy Parkway Project, as a state
    transportation purpose‛; that UDOT’s ‚taking of property,
    including the property identified in the Settlement Agreement,
    was necessary to effect a lifting of the stay on construction of the
    Legacy Parkway imposed by the Tenth Circuit Court of
    Appeals‛; that UDOT ‚had authority to condemn *Coalt’s+
    property‛; that ‚the taking was for a public state transportation
    purpose‛; and that ‚*g+iven the public purpose served by
    *UDOT’s+ taking of [Parcel 84], the taking was not merely for the
    purpose of conveying a benefit on one or more private parties.‛
    The district court cited sections 72-5-102(2), 72-5-102(12), and 72-
    5-103(1) of Utah’s Rights-of-way Act to conclude that UDOT’s
    taking of Parcel 84 was ‚a proper exercise of eminent domain.‛
    See generally 
    Utah Code Ann. § 72-5-101
     to -406 (LexisNexis
    2009). Subsection (2) of section 72-5-102 provides that a ‚state
    transportation purpose*+‛ includes the ‚mitigation from the
    effects‛ of construction, while subsection (12) provides that a
    state transportation purpose includes ‚the mitigation of impacts
    from public transportation projects.‛ Further, the Rights-of-way
    Act provides that UDOT ‚may acquire any real property or
    interests in real property necessary for temporary, present, or
    reasonable future state transportation purposes by gift,
    agreement, exchange, purchase, condemnation, or otherwise.‛
    
    Id.
     § 72-5-103(1). We readily conclude that the condemnation of
    Parcel 84 fell within the broad public purpose encompassed by
    these provisions.
    ¶14 The district court concluded that the condemnation of
    Parcel 84 was for a public purpose because it ‚was necessary‛ as
    a component of the overall plan to move the Legacy Parkway
    Project forward by effectively ‚lifting . . . the stay on
    construction.‛ Here, UDOT had designated that a certain
    amount of the land it had acquired for the Legacy Highway
    Project be set aside as the Legacy Nature Preserve and managed
    for the purpose of mitigating the environmental impact of the
    project on wetlands and wildlife in the area. UDOT believed that
    the land already acquired and set aside for this purpose was
    20150149-CA                     12               
    2016 UT App 169
    UDOT v. Coalt Inc.
    sufficient to mitigate the project’s anticipated effects, and the
    Corps and the FHA agreed. But the public interest litigants did
    not. Cf. Utahns for Better Transp. v. United States Dep’t of Transp.,
    
    305 F.3d 1152
    , 1180 (10th Cir. 2002) (holding, in response to the
    public interest litigants’ arguments, ‚that limiting the wildlife
    impact analysis so that migratory birds are beyond its scope
    renders the FEIS inadequate‛); cf. 
    id. at 1192
     (holding, in
    response to the public interest litigants’ arguments, that by
    limiting its ‚wildlife impact analysis . . . to consideration of
    impacts within 1000 feet of the project,‛ the Corps had ‚acted
    arbitrarily and capriciously in granting the [Clean Water Act]
    permit‛ for the Legacy Parkway Project). And, among other
    things, the public interest litigants sought to have additional
    land immediately adjacent to the Legacy Nature Preserve set
    aside in order to provide further environmental mitigation as a
    condition of resolving the second round of project-related
    environmental litigation in the federal courts. As part of the
    Settlement Agreement, UDOT agreed to acquire the Mitigation
    Property, which included Parcel 84, to establish additional offsite
    mitigation for transportation projects, and though the acquisition
    of the Mitigation Property was ostensibly unrelated to the
    federal permitting process for the Legacy Parkway Project, this
    property was certainly associated with it. For instance, the
    Mitigation Property was to ‚be managed in coordination with
    the Legacy Nature Preserve, for the purpose of a nature
    preserve‛ and could later be incorporated within the preserve’s
    boundaries with the approval of the Corps. Because neither
    UDOT nor the Corps considered the additional property
    ‚technically‛ necessary to meet their own calculation of
    mitigation for the project or as a condition of the required
    ‚Federal approval of the Legacy Parkway Project,‛ they agreed
    that ‚*m+itigation credits for *the Mitigation Property] will be
    available for other transportation projects.‛ The Settlement
    Agreement incorporated this concept, providing that the
    Mitigation Property may be ‚used as mitigation for [different]
    transportation projects.‛
    20150149-CA                     13               
    2016 UT App 169
    UDOT v. Coalt Inc.
    ¶15 Further, even though the land would not officially be a
    part of the Legacy Parkway Project, ‚the Corps recognized that
    acquisition of the site will benefit the Preserve because the land
    will buffer the Preserve from planned commercial development
    that could indirectly impact wetlands on the Preserve.‛ Thus,
    although beyond what the agencies themselves considered
    necessary for regulatory purposes, the acquisition of the
    Mitigation Property was still seen by UDOT, the FHA, and the
    Corps as related both in location and environmental effect to the
    Legacy Nature Preserve (a part of the Legacy Parkway Project)
    and as essential to resolution of the ongoing litigation. In
    addition, while UDOT and the federal agencies did not consider
    the additional land necessary to comply with applicable federal
    environmental regulations, the public interest litigants
    apparently did consider it an integral part of the resolution of
    their own concerns over the adequacy of environmental
    mitigation for the project. Thus, UDOT was faced with the choice
    of proceeding with litigation over the environmental impacts of
    the Legacy Parkway Project, which had already produced years-
    long delays and whose results could not be guaranteed, or
    compromising with the public interest litigants by making
    changes to the project, including an enlargement of the
    functional wildlife and wetlands mitigation footprint beyond
    what was needed for regulatory approval. UDOT decided to
    exchange certain environmentally related changes to the project,
    together with the creation of an additional mitigation area
    beyond the bounds of the project, for an end to the lengthy
    litigation and the burden of the uncertainty of the substance and
    timing of the ultimate outcome. The side agreement with the
    Corps that enabled UDOT to use the property as mitigation
    credits for future projects in the area enhanced the value of the
    settlement to UDOT.
    ¶16 Coalt does not contend that UDOT’s decision to settle the
    litigation or the components of the Settlement Agreement were
    unreasonable under the circumstances. Rather, Coalt argues that
    the condemnation of Parcel 84—land that both UDOT and the
    Corps agree was not necessary to fulfill the environmental
    20150149-CA                    14              
    2016 UT App 169
    UDOT v. Coalt Inc.
    regulations applicable to the project—‚was a response to a
    demand by private litigants challenging the Legacy Parkway
    environmental assessment,‛ and thus was for the benefit of a
    private party and not for an authorized public purpose. But this
    characterization is far too simple a description of what was at
    stake and what occurred here. After years of planning, UDOT
    had finally obtained a Record of Decision and the necessary
    Clean Water Act permit from the federal government to proceed
    with the Legacy Parkway Project, a transportation project it
    considered essential to reduce traffic congestion and meet
    increasing public transportation needs in the area. Before
    construction could begin, the project was halted by a lawsuit
    filed in federal district court by several public interest litigants
    arguing that the environmental impact of the Legacy Parkway
    Project had not been adequately assessed and would likely be
    significantly more substantial than the environmental studies
    asserted. UDOT’s initial success in federal district court was
    reversed on appeal, and an injunction effectively halted the
    project for years. Eventually the Tenth Circuit Court of Appeals
    ruled in favor of the public interest litigants and remanded the
    matter to the district court for further review of the
    environmental impact statements. On remand, as is often the
    case with environmental litigation as complex as this case was, it
    appears that neither UDOT nor the public interest litigants could
    be assured of the outcome. Faced with the uncertainties inherent
    in the circumstances and having already experienced a lengthy
    and costly delay, UDOT agreed to ‚resolve and settle‛
    differences with the public interest litigants regarding the
    Legacy Parkway Project so that it could move forward with
    highway construction. That resolution included UDOT’s
    agreement to condemn an additional 121 acres of property,
    including Coalt’s Parcel 84, to be preserved in its natural state
    for purposes of wildlife and wetlands mitigation.
    ¶17 From the public interest litigants’ perspective, the
    additional acreage was necessary for additional mitigation
    against the environmental impacts of the Legacy Parkway
    Project. From UDOT’s perspective, the acquisition was an
    20150149-CA                     15               
    2016 UT App 169
    UDOT v. Coalt Inc.
    essential part of a settlement that permitted an important
    transportation project to proceed after years of delay and, in
    addition, it could be used as mitigation for anticipated future
    projects in the area. And as a practical matter, because the
    additional property was immediately adjacent to the Legacy
    Nature Preserve, it effectively increased the environmental
    mitigation area for the Legacy Parkway Project, even if not
    officially part of it and even if any dispute whether it was
    necessary for such a purpose was unresolved. Thus, under the
    circumstances, UDOT’s decision to acquire additional property
    was pervaded with public purpose and intimately related to the
    viability of a public transportation project. These complexly
    intertwined purposes cannot be narrowly characterized as
    ‚private‛ simply because the provision of the Settlement
    Agreement that led to the condemnation of Coalt’s property also
    met the goal of the public interest litigants to enhance the
    environmental mitigation associated with a major public
    transportation project. See Utah Dep’t of Transp. v. G. Kay, Inc.,
    
    2003 UT 40
    , ¶ 11, 
    78 P.3d 612
    . Certainly, that aspect of the
    Settlement Agreement cannot reasonably be seen as invoking the
    misuse of condemnation authority to confer a private rather than
    a public benefit. Rather, it fits within UDOT’s broad authority to
    ‚acquire any real property . . . necessary for . . . present, or
    reasonable future state transportation purposes,‛ 
    Utah Code Ann. § 72-5-103
    (1) (LexisNexis 2009), including ‚the mitigation
    of impacts from public transportation projects,‛ 
    id.
     § 72-5-
    102(12). See also Town of Perry v. Thomas, 
    22 P.2d 343
    , 346 (Utah
    1933) (‚The phrase ‘public use,’ as used in the eminent domain
    statute, has been given a liberal interpretation by this court.‛).
    ¶18 This analysis also resolves Coalt’s arguments related to
    Salt Lake County v. Ramoselli, 
    567 P.2d 182
     (Utah 1977). Coalt
    quotes Ramoselli for the proposition that ‚‘[t]he question of
    necessity of the taking is the functional prerogative of the
    judicial system . . . . In every case, therefore, there is a judicial
    question whether the taking is of such a nature that it is or may
    be founded on public necessity.’‛ (Quoting Ramoselli, 567 P.2d at
    183.) Coalt then asserts that this court cannot ‚fulfill its
    20150149-CA                     16               
    2016 UT App 169
    UDOT v. Coalt Inc.
    ‘functional prerogative’ to decide ‘the question of necessity’
    when the project for which the project is ‘necessary’ is not
    identified, and [when there is] no time line or illumination of
    events that would create a time line[.]‛ In this regard, Coalt
    argues that UDOT cannot state that Parcel 84 was ‚necessary‛ to
    resolve the litigation surrounding the Legacy Parkway Project
    and then also state that Parcel 84 was ‚excess‛ because it ‚would
    be condemned for use for mitigation for other (non-Legacy
    Parkway) transportation projects.‛ (Internal quotation marks
    omitted.) According to Coalt, ‚*e+ither *Parcel 84+ is ‘necessary’
    or it is ‘excess,’ but it cannot be both.‛ But as we have discussed,
    the relationship of the acquisition of the Mitigation Property to
    the Legacy Parkway Project is both direct (it is integral to
    settlement of the lawsuit which had halted project construction)
    and indirect (it is immediately adjacent to the project’s Legacy
    Nature Preserve and, as a practical matter, extends the
    environmental mitigation area for the project). The ability to use
    the acreage for mitigation credit in future projects in the area5 is
    not the only public purpose; rather, these purposes are
    interrelated. As we have discussed, it appears that UDOT and
    the federal agencies made a conscious effort to technically isolate
    the Mitigation Property from the Legacy Parkway Project for
    regulatory purposes in order to ensure that the land could be
    credited to other projects in the area, while also recognizing its
    practical benefit to the Legacy Parkway Project itself and its
    5. The Corps’ agreement that the Mitigation Property ‚can be
    used to generate wetland mitigation credit‛ was based on the
    explicit condition that ‚mitigation credits would need to be
    applied to a transportation project located in the North
    Corridor.‛ And the Record of Decision noted that the Settlement
    Agreement between UDOT and the public interest litigants
    recognized this condition: ‚The 121-acre parcel . . . will not be
    used as mitigation for Legacy Parkway, but rather as possible
    mitigation for other transportation projects in the North
    Corridor, such as I-15 reconstruction.‛
    20150149-CA                     17               
    2016 UT App 169
    UDOT v. Coalt Inc.
    importance to settlement of the project-related litigation.6 See
    Utah Dep’t of Transp. v. Fuller, 
    603 P.2d 814
    , 817 (Utah 1979)
    (‚‘[U]nless a corporation exercising the power of eminent
    domain acts in bad faith or is guilty of oppression, its discretion
    in the selection of land will not be interfered with.’‛ (quoting
    Postal Tel. Cable Co. of Utah v. Oregon Short Line R.R., 
    65 P. 735
    ,
    739 (Utah 1901))).
    ¶19 And in the end, implicit in the Utah Legislature’s
    approval of the Settlement Agreement to ‚allow for the
    construction of the Legacy Parkway‛ and the expenditures
    necessary to implement its terms (including the purchase of the
    Mitigation Property), was its view that this condemnation was
    for a public transportation purpose. See Utah Dep’t of Transp. v.
    Carlson, 
    2014 UT 24
    , ¶ 20, 
    332 P.3d 900
     (stating that the eminent
    domain statute ‚not only enumerates authorized public uses but
    also includes an open-ended catchall‛ provision that
    ‚authorize*s+ eminent domain for all other public uses
    authorized by the Legislature‛ (citation and internal quotation
    marks omitted)).
    ¶20 Accordingly, we conclude that the district court correctly
    determined that UDOT’s condemnation of Parcel 84 under the
    circumstances here fulfilled a state public transportation
    purpose.
    II. The Valuation of Parcel 84
    ¶21 Coalt ‚challenges the trial court’s decision to ignore
    Legacy Parkway project influence in [the] valuation of [its]
    6. This is not a circumstance where, in order to settle a lawsuit
    over a public project, a state agency condemns a parcel of land
    physically and functionally unrelated to the project itself in
    order to satisfy a litigant’s private interests, also unrelated to the
    project. We have no occasion to consider the quite dissimilar
    issues those circumstances might raise.
    20150149-CA                      18                 
    2016 UT App 169
    UDOT v. Coalt Inc.
    property.‛ ‚The universal rule of damages in condemnation
    proceedings is one of just compensation. The condemnee [is] to
    be paid only so much as will compensate him for the damages to
    his property.‛ State v. Ward, 
    189 P.2d 113
    , 116–17 (Utah 1948); see
    also Utah Const. art. I, § 22 (‚Private property shall not be taken
    or damaged for public use without just compensation.‛).
    Further, ‚any enhancement or decrease in value attributable to
    the purpose for which the property is being condemned shall be
    excluded in determining the fair market value of the property.‛
    Redevelopment Agency of Salt Lake City v. Grutter, 
    734 P.2d 434
    , 437
    (Utah 1986). However, ‚if the land currently at issue was not
    within the original scope of the project but is merely adjacent
    property, then an enhancement would be appropriate.‛ Board of
    County Comm’rs of Tooele County v. Ferrebee, 
    844 P.2d 308
    , 311
    (Utah 1992). ‚The ‘scope of the project’ test requires only a
    showing that ‘during the course of the planning or original
    construction it became evident that land so situated would
    probably be needed for the public use.’‛ 
    Id.
     (quoting United
    States v. Reynolds, 
    397 U.S. 14
    , 21 (1970)).
    ¶22 While UDOT addressed Coalt’s first issue on appeal—
    whether the condemnation of Coalt’s property was for a public
    purpose—the agency made no effort to defend the district
    court’s decision regarding valuation. UDOT failed to include any
    response to Coalt’s arguments on this issue in its brief or any
    reference to the issue at all.
    ¶23 In Broderick v. Apartment Management Consultants, LLC,
    
    2012 UT 17
    , 
    279 P.3d 391
    , the Utah Supreme Court was
    confronted with an analogous briefing circumstance. In
    Broderick, an arson-caused fire resulted in property damage and
    personal injury to residential tenants of an apartment complex
    who subsequently alleged that the negligence of the
    management company contributed to their damages. Id. ¶¶ 1, 3–
    4. The district court granted summary judgment in favor of the
    management company and concluded that an exculpatory clause
    contained in the lease was ‚valid and enforceable‛ and
    ‚waiv*ed+ the right [of the tenants] to bring an action for
    20150149-CA                     19               
    2016 UT App 169
    UDOT v. Coalt Inc.
    negligence [against the management company].‛ Id. ¶ 1 (internal
    quotation marks omitted). On appeal, the tenants argued that the
    exculpatory clause was unenforceable because it ‚violate*d+
    Utah’s public policy of encouraging landlords to act with care‛
    and was against the public interest. Id. ¶¶ 2, 6. But the supreme
    court noted that the management company (the appellee)
    ‚ignore*d+‛ the tenants’ ‚main arguments on appeal‛ and
    ‚*i+nstead of addressing‛ the tenants’ arguments, chose to focus
    its response on other areas of the law. Id. ¶ 6. The court noted
    that rule 24(a) of the Utah Rules of Appellate Procedure
    ‚requires that the argument section of a brief contain the
    contentions and reasons of the appellant with respect to the
    issues presented . . . with citations to the authorities, statutes,
    and parts of the record relied on‛ and that a brief ‚must provide
    the reasoning and legal authority that will assist this court in
    resolving th*e+ concerns on appeal.‛ Id. ¶ 9 (alteration and
    omission in original) (citations and internal quotation marks
    omitted). The court then stated that
    Rule 24(b) makes the requirements of rule
    24(a) applicable to the brief of the appellee.
    Accordingly, we expect that both appellants and
    appellees will adhere to the standard of legal
    analysis set forth in rule 24(a). In addition, we also
    require the brief of the appellee [to] contain the
    contentions and reasons of the appellee with
    respect to the issues presented in the opposing
    brief.
    Under our rules of appellate procedure, we
    need not address briefs that fail to comply with
    rule 24. Specifically, rule 24(k) states that [b]riefs
    which are not in compliance may be disregarded or
    stricken, on motion or sua sponte by the court. And
    we have discretion to not address an inadequately
    briefed argument.
    20150149-CA                    20               
    2016 UT App 169
    UDOT v. Coalt Inc.
    
    Id.
     ¶¶ 10–11 (alterations in original) (citations, footnotes, and
    internal quotation marks omitted). Accordingly, the supreme
    court ‚reject*ed+‛ the management company’s brief ‚because
    of . . . inadequate briefing of the issues raised‛ by the tenants on
    appeal and, accordingly, accepted the tenants ‚plausible
    arguments.‛ 
    Id.
     ¶¶ 12–13, 18–21.
    ¶24 The same reasoning applies here. UDOT did not mention
    the issue of Parcel 84’s valuation either in its brief as the
    appellee. In light of UDOT’s failure to make any attempt to
    defend its position, this court is left with the burden of
    developing an argument in response, a burden ‚*w+e will not
    assume.‛ See id. ¶ 9 (‚Indeed, a reviewing court is not simply a
    depository in which [a] party may dump the burden of
    argument and research, and, accordingly, [w]e will not assume a
    party’s burden of argument and research.‛ (alterations in
    original) (citations and internal quotation marks omitted)). But
    because there is an institutional interest in the finality of the
    district court’s decision independent from the interests of the
    litigants, we are generally more willing to affirm in the face of
    inadequate briefing than we are to reverse. Cf., e.g., West Valley
    City v. Majestic Inv. Co., 
    818 P.2d 1311
    , 1313 n.1 (Utah Ct. App.
    1991) (‚We remind counsel that it is our prerogative to affirm the
    lower court decision solely on the basis of failure to comply with
    the Utah Rules of Appellate Procedure.‛). Where reversal is an
    option, we might first consider whether the appellant’s
    arguments for overturning the district court’s ruling are
    themselves visibly deficient or whether the lower court’s own
    explanation of the basis for its decision is itself strong enough to
    fill the void in the appellee’s briefing and carry the day,
    especially in a case of significant import.
    ¶25 The district court’s explanation of its decision here,
    whether ultimately right or wrong, is not extensive and has been
    competently called into question by Coalt’s arguments on
    appeal. See Salt Lake County v. Butler, Crockett & Walsh Dev. Corp.,
    
    2013 UT App 30
    , ¶ 36, 
    297 P.3d 38
     (limiting Broderick to cases
    where the appellant made a legally plausible claim on appeal).
    20150149-CA                     21               
    2016 UT App 169
    UDOT v. Coalt Inc.
    The district court based its conclusion that Coalt was not entitled
    to benefit from any enhanced value accruing from the project
    itself on UDOT’s argument that Parcel 84 was not ‚part of the
    Legacy Project.‛ The court relied upon Board of County
    Commissioners of Tooele County v. Ferrebee, 
    844 P.2d 308
    , 311–12
    (Utah 1992), and that opinion’s discussion of the ‚scope of the
    project test‛ to conclude that ‚it *was+ evident that *Coalt’s+
    property at some point would be needed for the Legacy
    Parkway Project‛ and that ‚*t+he taking was within the scope of
    the Legacy Parkway Project.‛
    ¶26 In Ferrebee, Tooele County planned to build an airport
    whose original design plan called for condemnation of an
    eighty-acre parcel of Ferrebee’s land, which included the parcel
    at issue in the case. 
    Id. at 309
    . Initially, the county acquired only
    thirty-seven of the acres by condemnation, and, due to
    budgetary constraints, approximately a decade passed before the
    county had funds to acquire the remaining land. 
    Id.
     at 309–10.
    The district court awarded Ferrebee compensation for the
    remaining property based on his appraisal, which included ‚an
    enhancement [in value] of 125 percent based upon proximity to
    the airport.‛ 
    Id. at 310
    . The Utah Supreme Court held that the
    district court should not have included in the award any
    enhancement in value based upon proximity to the airport
    because Ferrebee’s land was within the original scope of the
    project’s design (although it had taken several years to actually
    acquire it). 
    Id. at 312
     (requiring that for a condemnation award to
    include an increment of enhanced value from the project itself
    that ‚the land [not] be within the scope of the original project‛
    (emphasis omitted)).
    ¶27 Coalt contends that the district court’s reliance on Ferrebee
    in concluding that Parcel 84 was within the scope of the Legacy
    Highway Project is misplaced because ‚the subject property *in
    Ferrebee+ was always within the scope of the project,‛ while
    Parcel 84 was not added to the Legacy Parkway Project until
    well after the design of the project was complete—in fact, it had
    become the basis for the Final EIS. Additionally, and quite
    20150149-CA                     22               
    2016 UT App 169
    UDOT v. Coalt Inc.
    persuasively, Coalt argues that ‚UDOT should not be permitted
    to repeatedly state that [Parcel 84] is unrelated to the Legacy
    Parkway in order to preserve a bargaining chip with the Corps
    [for the purpose of mitigation credit on future projects], and then
    switch positions when compensation is the issue.‛ As a
    corollary, Coalt points out that ‚*i+f *Parcel 84] had been
    condemned as part of whatever future project it may eventually
    mitigate, then it would be clear that the influence of the
    property’s proximity to Legacy Parkway and the Legacy Nature
    Preserve would have to be considered in setting its value.‛
    According to Coalt, the question ‚is whether *Parcel 84 was]
    probably within the scope of the project from the time [UDOT]
    was committed to it,‛ and if it was not, but, instead, ‚merely
    adjacent‛ to the Legacy Parkway Project, then ‚the subsequent
    enlargement of the project to include [Parcel 84] . . . ought not to
    deprive [Coalt] of the value added in the meantime by the
    proximity of the improvement.‛ (Citing United States v. Reynolds,
    
    397 U.S. 14
    , 17 (1970).) Therefore, according to Coalt, ‚*f+or
    compensation to be fair and just, it must reflect the fair value of
    the land to the landowner,‛ with the effect of the project taken
    into account. (Citing Utah State Road Comm’n v. Friberg, 
    687 P.2d 821
    , 828 (Utah 1984).)
    ¶28 Coalt’s argument appears on its face to be a reasonable
    critique of the district court’s decision, and although a response
    from a motivated opponent might undermine its plausibility, no
    such response has been offered by UDOT. See Butler, Crockett
    & Walsh Dev. Corp., 
    2013 UT App 30
    , ¶ 36. Under the
    circumstances, then, we ‚may . . . treat such a failure . . . as an
    acknowledgment of the statement of facts contained in
    appellants’ brief, and also indulge a strong inference that the law
    is as cited and argued by appellants’ counsel.‛ See Fitzgerald v.
    Salt Lake County, 
    449 P.2d 653
    , 654 (Utah 1969) (footnote
    omitted).
    ¶29 Accordingly, we view the institutional interest of
    preserving the finality of the district court’s ruling in this case to
    be at low ebb. We therefore reverse the district court’s valuation
    20150149-CA                      23               
    2016 UT App 169
    UDOT v. Coalt Inc.
    decision and remand for the court to redetermine just
    compensation for the property at issue, taking into account any
    increase in value that may be attributable to the Legacy Parkway
    Project.
    CONCLUSION
    ¶30 We conclude that the district court did not err in holding
    that the condemnation of Parcel 84 was for a public
    transportation purpose. We also conclude that the district court
    erred regarding the valuation of Parcel 84 and, accordingly, we
    remand to the district court to determine the land’s value
    consistent with our decision.
    20150149-CA                   24              
    2016 UT App 169