Stein Eriksen Lodge v. MX Technologies , 2022 UT App 30 ( 2022 )


Menu:
  •                         
    2022 UT App 30
    THE UTAH COURT OF APPEALS
    STEIN ERIKSEN LODGE OWNERS ASSOCIATION INC. AND
    STEIN ERIKSEN LODGE MANAGEMENT CORP.,
    Appellees,
    v.
    MX TECHNOLOGIES INC.,
    Appellant.
    Opinion
    No. 20200256-CA
    Filed March 10, 2022
    Third District Court, Salt Lake Department
    The Honorable Su Chon
    No. 169903978
    Alexander Dushku, Justin W. Starr, Robert E.
    Mansfield, and Megan E. Garrett, Attorneys
    for Appellant
    Troy L. Booher, Taylor Webb, Joelle S. Kesler,
    Jonathan W. Gold, Steven M. Rudner, and John C.
    Josefsberg, Attorneys for Appellees
    JUDGE RYAN M. HARRIS authored this Opinion, in which
    JUDGES JILL M. POHLMAN and DIANA HAGEN concurred.
    HARRIS, Judge:
    ¶1     After being asked by her superiors to help plan a major
    corporate conference, the Events Manager of MX Technologies
    Inc. (MX) signed contracts—totaling more than $350,000—for
    rooms, food, and services at the Stein Eriksen Lodge (Stein). MX
    later decided not to hold the conference, and claimed that the
    contracts were invalid, in whole or in part, because Events
    Manager did not have authority to sign them, and because the
    contracts’ liquidated damages provisions were unconscionable.
    Stein sued MX for breach of contract, and the district court
    Stein Eriksen v. MX Technologies, Inc.
    entered summary judgment in Stein’s favor, concluding that, as
    a matter of law, Events Manager had authority to sign the
    contracts and the liquidated damages provisions are not
    unconscionable.
    ¶2     MX now appeals, and we affirm in part and reverse in
    part. We agree with the district court that, as a matter of law, the
    liquidated damages provisions are not unconscionable, and
    affirm that portion of the court’s ruling. We also affirm the
    court’s implied determination that MX did not cancel any
    contractual relationship between the parties until just sixty days
    before the event was to begin. But we conclude that questions of
    fact preclude summary judgment on the other issues presented,
    including whether Events Manager had authority to execute the
    contracts, and whether MX ratified those contracts following
    their execution. We therefore vacate that portion of the court’s
    ruling and remand the case for further proceedings.
    BACKGROUND1
    ¶3     In October 2015, MX began internal discussions about
    hosting a major corporate conference, to which it planned to
    invite current and prospective clients. In an attempt to “get
    something on the calendar” for the event, the company’s
    Director of Community and Client Advocacy sent an email
    explaining the vision, goals, and potential agenda of the event.
    Among the recipients of this email were—in order of placement
    on the corporate organizational chart—the company’s Chief
    Financial Officer (CFO), Marketing Director, Events Manager,
    1. When reviewing a grant of summary judgment, we view “the
    facts in a light most favorable to the losing party below.”
    Goodnow v. Sullivan, 
    2002 UT 21
    , ¶ 7, 
    44 P.3d 704
     (quotation
    simplified).
    20200256-CA                     2                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    and Events Coordinator. At the time, Events Manager was
    twenty-four years old, and had been hired by MX only a few
    months earlier. Events Coordinator reported to Events Manager,
    who reported to Marketing Director, who reported to the
    company’s newly hired Chief Marketing Officer (CMO). Events
    Manager and Events Coordinator were tasked with the
    assignment of negotiating a prospective contract with Stein,
    which had been tentatively selected as the site for the potential
    event. The pair soon began correspondence with Stein, and in
    November they participated in a site visit, during which they
    toured Stein’s facilities.
    ¶4     After the site visit, Events Coordinator continued to
    correspond with Stein, expressing continued interest in the
    venue but noting that, because MX had just hired a new CMO,
    she needed “to get approval from him before moving forward.”
    Stein responded that other groups were also interested in
    booking its facilities during the same time period and expressed
    some sense of urgency, indicating that it needed a commitment
    from MX in order to hold the rooms open.
    ¶5     The following week, MX’s marketing department—
    including Marketing Director, Events Manager, and the new
    CMO—met to discuss the event. At this meeting, the group
    made the decision to move forward with the conference, and
    CMO noted that they needed to “get cranking” to lock down the
    venue by the end of the year.
    ¶6     Events Manager called Stein later that day to discuss
    contract terms, including deposits, cancellation, and liquidated
    damages. A few days later, Stein emailed proposed contracts to
    both Events Manager and Events Coordinator. Events Manager
    informed Stein that MX would need some time to review the
    contracts “and have [its] legal team also glance over [them]”
    before they could be executed.
    20200256-CA                    3                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ¶7     More than two weeks went by without a response. On
    New Year’s Eve, Stein followed up with Events Manager,
    alerting her that another group had submitted a proposal that
    conflicted with MX’s proposed dates and asking to “confirm
    everything and finalize the contract.” Apprehensive about the
    possibility of losing the dates, Events Manager signed the
    contracts2 on December 31, 2015. According to the contracts, the
    conference was to begin on August 1, 2016.
    ¶8     Under the terms of the contracts, MX agreed to pay for
    720 room nights (the room charges totaled $176,080) and for at
    least $146,000 for food and drink charges, plus a 23% service
    charge. In total, the contracts obligated MX to pay more than
    $350,000 to Stein for services related to the conference. The
    contracts also contained liquidated damages provisions
    specifying the amount MX would pay if it cancelled the event. If
    cancellation occurred between sixty-one and ninety days prior to
    the event, MX would be required to pay 90% of the contracted
    amount. But if cancellation occurred sixty or fewer days prior to
    the event, MX would be required to pay the entire contracted
    amount. During some of the back-and-forth prior to the
    contracts being signed, Stein had told Events Manager that it
    would be “flexible” with its deposit and cancellation policies.
    ¶9     Pursuant to MX company policy, any payment over
    $20,000 had to be approved by the CFO. Prior to Events Manager
    signing the contracts, however, no such approval was obtained.
    During her deposition, Events Manager testified that she had
    received approval from Marketing Director, if not from CFO, but
    2. There were two contracts: one for rooms at the Stein Eriksen
    Lodge itself and one for rooms at the Chateaux Deer Valley, a
    related property. For ease of reference, we refer to both
    properties simply as “Stein.”
    20200256-CA                    4                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    Marketing Director disputes this testimony.3 As Marketing
    Director tells it, not only did she not provide approval for Events
    Manager to sign the contracts, she did not even learn, until many
    months later when MX received a demand for payment from
    Stein, that the contracts had been signed.
    ¶10 A few months before signing the contracts at issue, Events
    Manager had executed at least one other similar contract, this
    one with Sundance Resort. The full details of the Sundance
    contract are not contained in the appellate record; for example,
    the record does not tell us whether Events Manager obtained
    prior approval from MX executives to sign it, nor does it tell us
    the total value of the contract. The record does, however,
    indicate that the Sundance contract was for 105 room nights,
    which likely would have been valued at more than $20,000, thus
    triggering MX’s company approval policy described above.
    ¶11 The Stein contracts required two relatively small ($2,500)
    deposits to be paid upon signing, with an additional larger
    ($75,000) deposit due a few weeks later. Events Manager paid
    the $2,500 deposits on January 5, 2016, and did so using
    Marketing Director’s company credit card. Marketing Director
    testified, however, that her awareness of these small deposits did
    not equate to awareness of executed contracts, because she
    3. Events Manager also later attempted to dispute her own prior
    testimony. About nine months after her deposition, in
    connection with its motion for summary judgment, MX
    submitted a sworn declaration from Events Manager in which
    she expressly denied receiving any sort of permission from
    Marketing Director to sign the contracts. Stein moved to strike
    that declaration, in part because it contradicted Events
    Manager’s deposition testimony, and the district court granted
    that motion. MX does not appeal the court’s decision to strike
    that declaration.
    20200256-CA                     5                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    thought these charges were merely for Stein to “hold” the dates.
    The new CMO was apparently under the same impression.
    ¶12 Aside from making the small deposit payments, MX took
    other actions, after the contracts were signed, in preparation for
    the conference. In February 2016, Marketing Director contacted
    an audiovisual technician about potential needs for the event.
    And in April, MX’s creative director spoke by phone with Stein
    about video footage that MX might use in promoting the event.
    Several MX representatives, including Events Manager, also
    traveled to Stein for a planning visit. And MX recruited—and
    signed a contract with—a keynote speaker for the event, and
    began to promote the conference internally. Indeed, Events
    Manager—at the direction of Marketing Director—sent a
    company-wide email promoting the conference, stating as
    follows:
    We’re excited to announce we’ll be holding our
    inaugural MX conference [during the first week of
    August] at the Stein Eriksen in Deer Valley, UT.
    This conference will be a mix of both current clients
    and prospects and very similar to [previous
    conferences] but on a larger scale. All prospects
    and clients are welcome to attend . . . . Please start
    reaching out to your clients now so they have these
    dates on their schedules. We have created a save
    the date [web]page with more details on it for you
    to send along with your invitations . . . . You can
    expect to receive more details in the coming weeks.
    In the meantime let me know if you have any
    questions.
    The “save the date” webpage identified the location, date, and
    speakers for the conference, including the aforementioned
    keynote speaker.
    20200256-CA                     6                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ¶13 Both CFO and CMO testified that, at the time this email
    went out, they were unaware of the existence of the signed
    contracts. As CMO saw it, MX was still “testing the waters” at
    this point, and the purpose of the email was to see if there were
    enough interested and available clients to move forward. And
    CFO reasoned that it was necessary to reach out to clients before
    making a contractual commitment because, until the company
    knew how many clients planned to attend, it would not know
    how many rooms to reserve.
    ¶14 MX had not, however, paid the larger $75,000 deposit
    which, pursuant to the contracts, was due in February. In March,
    after Stein had contacted Events Manager to inquire about the
    past-due deposit, Events Manager raised the issue with CMO
    and Marketing Director. Both of them were under the
    impression that payment of the $75,000 deposit is what would
    formally commit MX to the event. At their instruction, Events
    Manager asked Stein if MX could defer the deposit until “Q2,”
    and Stein agreed.
    ¶15 In late April, Events Manager sent a $75,000 invoice—for
    the Stein deposit—to MX’s accounting department. The
    accounting department told Events Manager that the invoice,
    along with any corresponding contract, needed to go through
    MX’s accounting software for approval. Thereafter, the invoice
    reached CFO, who responded that it was “not approved.”
    ¶16 When Stein inquired again about the late deposit, Events
    Manager replied that CFO had been “road blocking this” and
    was out of town, but that they were “planning on discussing this
    with him first thing so we can get it paid ASAP.” Stein
    responded by expressing its concern that CFO was “delaying a
    contractual obligation” and—for the first time—taking the view
    that MX was “in default” and had committed “a breach of
    agreement.”
    20200256-CA                    7                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ¶17 This email exchange caught the attention of Marketing
    Director, who emailed CFO and CMO, alerting them that she
    was “atwitter regarding the news that [CFO] is considering
    pulling the plug” on the conference and noting that MX had
    “signed a contract with Stein Eriksen that we cannot get out of.”
    According to CFO and CMO, this email—sent on May 13—was
    how they first became aware of the existence of signed contracts.
    ¶18 Thereafter, on May 25, CFO attempted to negotiate a
    resolution with Stein, explaining in an email that, in his view, the
    contracts had not been approved per corporate policy, and had
    been “executed by an employee who [was] not authorized to
    sign on behalf of or legal[ly] bind MX.” He proposed, however,
    that MX could hold a smaller conference on the August 2016
    dates or, alternatively, could bump the larger conference to the
    following summer. His email concluded by stating that,
    “[a]lthough this is not an optimal start to a future partnership, I
    am looking forward to a valuable relationship between MX” and
    Stein. After learning, however, that Stein was not interested in
    either of those options, CFO sent a follow-up letter stating that
    MX did not intend to stage any conference at Stein in 2016 and
    “providing notice that MX [did] not intend to do business with
    [Stein] now or in the future.” That letter was dated June 2,
    2016—exactly sixty days before August 1, the day the conference
    was to begin.
    ¶19 A few weeks later, Stein filed suit for breach of contract,
    seeking $350,660 in liquidated damages—or, in the alternative,
    actual damages in an amount to be proved at trial—plus interest
    and attorney fees. Eventually, both sides filed competing
    motions for summary judgment. Stein asserted that, as a matter
    of law and undisputed fact, Events Manager either had authority
    to sign the contracts or, alternatively, that MX ratified the
    contracts after execution. In addition, Stein asserted in a separate
    motion that it was entitled to liquidated damages because the
    relevant contractual provisions were enforceable and MX’s
    20200256-CA                     8                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    unconscionability defense failed as a matter of law. MX filed
    memoranda opposing Stein’s motions, and in addition filed its
    own motion, asserting that as a matter of law and undisputed
    fact, Events Manager had no authority to bind MX and that MX
    had not ratified the contracts. MX did not file a cross-motion
    regarding the enforceability of the liquidated damages
    provision. Both parties presented reports from expert witnesses
    in support of their positions: Stein’s expert asserted that—within
    the hospitality industry—it is reasonable to assume that an
    employee who carries the title of “events manager” has
    authority to sign large contracts on behalf of her company. MX’s
    expert disagreed. The experts also disagreed as to whether the
    liquidated damages provision was standard within the industry.
    ¶20 After full briefing and oral argument, the district court
    granted Stein’s motions and denied MX’s. The court determined
    that Events Manager had authority to sign the contracts and that,
    even if she did not, her “actions were ratified by MX upper
    management.” The court also determined that the liquidated
    damages provisions were not unconscionable, concluding that
    they “appear[] to be standard in the hospitality industry.”
    ¶21 Following its ruling, the court entered judgment in Stein’s
    favor in the amount of $651,818.83, an amount that included
    liquidated damages totaling $350,660 and prejudgment interest
    totaling $301,158.83. The liquidated damages total was based on
    the assumption that the contracts were cancelled on June 2,
    2016—sixty days before the conference was to begin—and thus
    represented 100% (rather than 90%) of the contracted amount.
    The court later issued an award of attorney fees and costs to
    Stein, augmenting the judgment not only in the amount of the
    attorney fees award ($377,430.77) but also to account for
    additional interest on the original award. The total judgment
    amount against MX now exceeds $1 million.
    20200256-CA                     9                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ISSUE AND STANDARD OF REVIEW
    ¶22 MX appeals from the district court’s summary judgment
    order and the resulting judgment. Specifically, however, it does
    not appeal the denial of its own motion, just the grant of Stein’s,
    contending on appeal that “[n]umerous disputed issues of
    material fact preclude summary judgment on the issues of
    authority and ratification,” and that the court erred by deciding
    the liquidated damages issue on summary judgment and “not
    after a full and fair trial where witnesses could be assessed.”4
    ¶23 Summary judgment is appropriate only “if the moving
    party shows that there is no genuine dispute as to any material
    fact and the moving party is entitled to judgment as a matter of
    law.” Utah R. Civ. P. 56(a). In determining whether a genuine
    issue of material fact exists, we ask “whether reasonable jurors,
    properly instructed, would be able to come to only one
    conclusion, or if they might come to different conclusions,
    thereby making summary judgment inappropriate.” Heslop v.
    Bear River Mutual Ins. Co., 
    2017 UT 5
    , ¶ 20, 
    390 P.3d 314
    (quotation simplified). “We review a [district] court’s legal
    conclusions and ultimate grant or denial of summary judgment
    for correctness, viewing the facts and all reasonable inferences
    drawn therefrom in the light most favorable to the nonmoving
    4. It appears MX may be attempting to argue, here on appeal,
    that issues relating to the unconscionability of the liquidated
    damages provisions can be decided as a matter of law in its
    favor. But MX did not make a summary judgment motion of its
    own on this point below; instead, it merely resisted Stein’s,
    asking the court to deny Stein’s motion “because there are
    disputed issues of material fact.” Thus, any request for judgment
    as a matter of law in MX’s favor on these issues is unpreserved.
    And in any event, as discussed below, we affirm the district
    court’s grant of summary judgment to Stein on these issues.
    20200256-CA                     10                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    party.” Heartwood Home Health & Hospice LLC v. Huber, 
    2020 UT App 13
    , ¶ 11, 
    459 P.3d 1060
     (quotation simplified).
    ANALYSIS
    ¶24 In challenging the district court’s summary judgment
    order, MX asserts three distinct arguments. First, it contends that
    the court erred by determining, as a matter of law, that the
    contracts were valid. In particular, MX asserts that questions of
    fact remain as to whether Events Manager had authority to sign
    the contracts, and if not, whether MX ratified Events Manager’s
    unauthorized act. Second, MX argues that, even if the contracts
    were authorized, they contain liquidated damages provisions
    that are unconscionable, and that the court erred by determining
    otherwise. Finally, MX contends that the court erred by
    assuming—and impliedly determining as a matter of law—that
    the cancellation of any supposed contracts occurred on June 2,
    and not on May 25. We discuss each of MX’s arguments, finding
    merit in its first argument but rejecting the others.
    I. The Validity of the Contracts
    ¶25 It is well established that, “[u]nder agency law, an agent
    cannot make its principal responsible for the agent’s actions
    unless the agent is acting pursuant to either actual or apparent
    authority.” Zions First Nat’l Bank v. Clark Clinic Corp., 
    762 P.2d 1090
    , 1094 (Utah 1988). While it is clear that the district court
    concluded, as a matter of law, that Events Manager had
    authority to sign the contracts, it is unclear whether the court
    determined that she had actual or apparent authority (or both).
    And the court concluded, in the alternative, that MX ratified the
    contracts in any event. On appeal, MX takes issue with these
    rulings, asserting that genuine disputes of material fact exist
    with regard to each one, rendering summary judgment
    inappropriate. We discuss these topics, in turn.
    20200256-CA                     11                  
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    A.     Actual Authority
    ¶26 In assessing whether Events Manager had actual
    authority to sign the contracts, we must examine “the acts of the
    principal from the agent’s perspective.” Diston v. EnviroPak Med.
    Products, Inc., 
    893 P.2d 1071
    , 1076 (Utah Ct. App. 1995). At root,
    this inquiry turns on the reasonableness of the agent’s belief that
    she possessed sufficient authority. See Restatement (Third) of
    Agency § 2.01 (Am. L. Inst. 2006) (“An agent acts with actual
    authority when . . . the agent reasonably believes, in accordance
    with the principal’s manifestations to the agent, that the
    principal wishes the agent so to act.”); see also 1-800 Contacts, Inc.
    v. Lens.com, Inc., 
    722 F.3d 1229
    , 1251 (10th Cir. 2013). The inquiry
    contains both an objective and a subjective component: the agent
    must subjectively hold the belief that she possesses authority,
    and that belief must be objectively reasonable in light of the
    principal’s actions. See Restatement (Third) of Agency § 2.02 cmt.
    e (“This standard requires that the agent’s belief be reasonable,
    an objective standard, and that the agent actually hold the belief,
    a subjective standard.”). On appeal, MX does not argue that
    Events Manager lacked a subjective belief that she was
    authorized to sign the contracts, and we therefore assume for
    purposes of our analysis that Events Manager—in accordance
    with her deposition testimony—possessed such a belief. But we
    agree with MX that questions of fact preclude summary
    judgment on the question of whether Events Manager’s belief
    was objectively reasonable.
    ¶27 In evaluating the objective part of the test, we examine
    whether the agent’s belief was reasonable under the
    circumstances, in light of the actions and manifestations of the
    principal. See id. (“Whether an agent’s belief is reasonable is
    determined from the viewpoint of a reasonable person in the
    agent’s situation under all of the circumstances of which the
    agent has notice.”). A principal may confer actual authority
    expressly, or it may do so through other less overt actions that
    20200256-CA                      12                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    nevertheless imply a grant of authority. See Hussein v. UBS Bank
    USA, 
    2019 UT App 100
    , ¶ 32, 
    446 P.3d 96
     (“Actual authority may
    either be express or implied.”). Express authority is present
    when “the principal directly states that its agent has the
    authority to perform a particular act on the principal’s behalf.”
    
    Id.
     (quotation simplified). Implied authority stems “from the
    words and conduct of the parties and the facts and
    circumstances attending the transaction in question.” 
    Id.
    (quotation simplified).
    ¶28 On the issue of express authority, there was evidence that,
    pursuant to MX company policy, any payment over $20,000 had
    to be run through company software and approved by CFO. But
    CFO unequivocally testified that Events Manager “did not have
    authority to sign” the Stein contracts on behalf of MX. Even
    Events Manager, in her deposition testimony, did not assert that
    CFO gave her authorization to sign; instead, she claimed only
    that she received authority from Marketing Director. That claim
    is not only contested by Marketing Director as a factual matter,
    but it is also unclear whether—in light of the evidence regarding
    MX company policy—Marketing Director herself had authority
    to authorize Events Manager to sign the contracts, or whether
    Events Manager might reasonably have so believed. We agree
    with MX that, in light of these disputed factual issues, Events
    Manager cannot be said to have possessed express actual
    authority as a matter of law.
    ¶29 With regard to implied actual authority, we reach the
    same conclusion. In defense of the district court’s summary
    judgment ruling, Stein points principally to the Sundance
    contract, and asserts that Events Manager had to have
    reasonably believed that she had authority to sign the Stein
    contracts because she had previously signed the similar
    Sundance contract. But the presence of the Sundance contract—
    while perhaps indicative of implied authority—is not enough to
    establish the reasonableness of Events Manager’s belief as a
    20200256-CA                    13                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    matter of law. As noted, see supra ¶ 10, the record submitted to
    us on appeal does not tell us enough about the Sundance
    contract to warrant summary judgment. Indeed, we do not know
    the total value of the Sundance contract, nor do we know
    whether Events Manager received express approval from CFO to
    sign it. For instance, in the event that she received the necessary
    express approval to sign the Sundance contract, but not the Stein
    contracts, and that she was aware of prevailing company policy
    regarding contracts, a reasonable factfinder could conclude that
    any belief she might have held that she actually had authority to
    sign the Stein contracts was unreasonable.
    ¶30 In sum, we discern factual disputes that preclude
    summary judgment on the issue of whether Events Manager
    possessed actual authority from MX to sign the Stein contracts.
    B.     Apparent Authority
    ¶31 Next, we must examine whether Events Manager had
    apparent authority—as a matter of law and undisputed fact—to
    sign the Stein contracts. One key difference between actual and
    apparent authority is the point of view from which these
    doctrines are assessed. As noted above, actual authority is
    evaluated “from the agent’s perspective.” See Diston, 
    893 P.2d at 1076
    . Proper analysis of apparent authority, by contrast, “focuses
    on the acts of the principal from a third party’s perspective.” 
    Id.
    ¶32 Apparent authority exists “when a third party reasonably
    believes the actor has authority to act on behalf of the principal
    and that belief is traceable to the principal’s manifestation.”
    Burdick v. Horner Townsend & Kent, Inc., 
    2015 UT 8
    , ¶ 21, 
    345 P.3d 531
     (quotation simplified). The agent’s manifestations to the
    third party are alone insufficient; that is, the principal must have
    taken some action, known to the third party, that causes the
    third party to reasonably believe that the agent had authority.
    See id. ¶ 22 (“The authority of an agent is not apparent merely
    20200256-CA                     14                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    because it looks so to the person with whom he deals, but rather,
    it is the principal who must cause third parties to believe that the
    agent is clothed with apparent authority.” (quotation
    simplified)); see also Grazer v. Jones, 
    2012 UT 58
    , ¶ 11, 
    289 P.3d 437
    (“Where the principal does something to support a third party’s
    reasonable belief that the agent has the authority to act, that
    agent is vested with apparent authority to bind the principal.”).
    Our supreme court has articulated a “three-part test for apparent
    authority,” all three parts of which must be met: (1) the principal
    must have “manifested his or her consent to the exercise of such
    authority or [have] knowingly permitted the agent to assume the
    exercise of such authority”; (2) the third party must “kn[o]w of
    the facts and, acting in good faith, ha[ve] reason to believe, and
    did actually believe, that the agent possessed such authority”;
    and (3) the third party must have “rel[ied] on [the agent’s]
    appearance of authority” and must have “changed his or her
    position and will be injured or suffer loss if the act done or
    transaction executed by the agent does not bind the principal.”
    Burdick, 
    2015 UT 8
    , ¶ 23 (quotation simplified).
    ¶33 In this case, Stein is the third party, and does not claim to
    have had any communication, prior to the execution of the
    contracts, with anyone at MX other than Events Manager and
    her subordinate, Events Coordinator. And MX quite sensibly
    points out that, if Events Manager cannot bind the company,
    then neither can her subordinate, Events Coordinator.
    ¶34 In the absence of any direct manifestations or
    communications from MX higher-ups, Stein asserts that
    apparent authority can be inferred from the fact that MX
    conferred the title “Events Manager” on its representative, and
    claims that such a title, by itself, communicates to third parties
    that Events Manager had authority to sign contracts on MX’s
    behalf related to corporate events. A reasonable jury, after
    hearing all the evidence, might well reach that conclusion. But
    20200256-CA                      15                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    we disagree with Stein that, on this record, such a conclusion is
    compelled as a matter of law.
    ¶35 Stein correctly asserts that, where a third person “of
    ordinary prudence,” and who is “conversant with business
    usages and the nature of the particular business, is justified in
    presuming” that the agent has the requisite authority, “the
    principal is estopped,” by virtue of apparent authority, “from
    denying the agent’s authority.” See Grazer, 
    2012 UT 58
    , ¶ 11
    (quotation simplified). Thus, if Stein could establish, as a matter
    of law, that in the hospitality industry the title “Events
    Manager” is commonly believed to confer authority to sign
    contracts related to events, then Stein would be entitled to
    summary judgment. But Stein cannot establish that on this
    record.
    ¶36 To be sure, Stein’s expert opines that “it is custom and
    practice in the hospitality industry that Event Managers sign
    contracts,” and that this is true “regardless of the size of the
    event.” But MX’s expert disagrees with this opinion, and opines
    that, in the industry, an “Event Manager” “generally does not
    have authority to enter into large contracts for and on behalf of
    the event manager’s employer,” and that reasonable actors
    within the industry “do not accept that a person using the title
    ‘Event Manager’ is the person that can commit a company to a
    meeting space.” Thus, on this record, the dueling experts have
    created a classic question of fact as to the reasonableness of
    Stein’s belief that an Events Manager could bind MX to contracts
    of this size.
    ¶37 Finally, Stein asserts that it was entitled to infer authority
    from the fact that Events Manager told Stein that the contracts
    required legal and corporate review, and then two weeks later
    signed the contracts. As Stein sees it, it was at that point entitled
    to a reasonable belief “that the contracts had undergone internal
    and legal review.” The district court accepted this argument,
    20200256-CA                     16                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    concluding that Stein could have “reasonably assume[d] that the
    corporate hurdles had been satisfied.” But MX correctly points
    out that any valid manifestation of apparent authority needs to
    have come from the principal, not from the agent, and that no
    evidence of any direct manifestation is present in this record. At
    a minimum, inferring apparent authority from Events Manager’s
    actions in executing the contracts cannot, on this record, be
    appropriately accomplished as a matter of law.
    ¶38 In sum, we discern factual disputes that preclude
    summary judgment on the issue of whether Events Manager
    possessed apparent authority from MX to sign the Stein
    contracts.
    C.     Ratification
    ¶39 Next, we must consider whether MX—as a matter of law
    and undisputed fact—ratified the Stein contracts after Events
    Manager executed them. Under our law, contracts that are
    signed by an agent even in the absence of actual or apparent
    authority may nevertheless be ratified after the fact by the
    principal. See Bradshaw v. McBride, 
    649 P.2d 74
    , 78 (Utah 1982)
    (“A principal may impliedly or expressly ratify an agreement
    made by an unauthorized agent.”). Post-contract ratification, just
    like pre-contract bestowal of authority, can occur expressly or be
    implied from other actions. Id.; see also Bullock v. Utah Dep’t of
    Transp., 
    966 P.2d 1215
    , 1218 (Utah Ct. App. 1998) (“Ratification,
    like original authority, need not be express.” (quotation
    simplified)). There is no indication, in this case, that MX
    expressly ratified the Stein contracts after Events Manager
    signed them. But Stein contends—and the district court ruled—
    that MX impliedly ratified them through other actions.
    ¶40 Implied ratification occurs through “conduct which
    indicates assent by the purported principal to become a party to
    the transaction or which is justifiable only if there is ratification.”
    20200256-CA                      17                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    Bradshaw, 649 P.2d at 78 (quotation simplified). However, a court
    cannot “infer ratification of a contract unless [it] conclude[s] that
    the principal knowingly assented to the material terms of the
    contract.” Bullock, 
    966 P.2d at 1218
    . Ratification thus “requires
    the principal to have knowledge of all material facts and an
    intent to ratify.” Dillon v. Southern Mgmt. Corp. Ret. Trust, 
    2014 UT 14
    , ¶ 28, 
    326 P.3d 656
     (quotation simplified). “In essence, the
    doctrine of implied ratification protects both a principal’s agent
    and the co-parties to a contract by ensuring that the principal
    cannot repudiate the contract after the fact if any reasonable
    person would have concluded from the principal’s actions at the
    time of the transaction that the principal endorsed the contract.”
    Bullock, 
    966 P.2d at 1219
    .
    ¶41 In granting summary judgment in favor of Stein on the
    issue of ratification, the district court set forth a bullet-point list
    of apparently undisputed facts that it believed supported its
    decision. Stein relies on many of those same facts in arguing,
    here on appeal, that the court’s decision should be affirmed.
    While we acknowledge that many of these facts may be helpful
    to Stein when it argues its case to the factfinder on remand, we
    do not agree that those listed facts—or any others brought to our
    attention—compel the conclusion that MX, as a matter of law,
    ratified the contracts. In our view, a reasonable jury could find
    otherwise. More specifically, and as we explain below, the facts
    in the district court’s list are either irrelevant to the ratification
    inquiry or are the subject of a factual dispute.
    ¶42 The first fact listed by the district court was that
    both CMO and Marketing Director were “involved” in selecting
    Stein as the presumptive choice for the event from among its
    list of potential venues. This fact sheds little, if any, light on
    the ratification inquiry, because it describes events that took
    place before Stein sent Events Manager copies of the draft
    contracts, and several weeks before Events Manager signed
    them. The fact that MX executives instructed Events Manager to
    20200256-CA                      18                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    attempt to negotiate the terms of a contract with Stein does not
    tell us much, if anything, about whether those same executives
    later ratified the terms of the contracts Events Manager
    ultimately signed.
    ¶43 The next listed fact is that Marketing Director “directed
    [Events Manager] to sign the contract and charge the initial
    deposit.” But as previously noted, see supra ¶¶ 9, 28,
    Events Manager’s testimony that Marketing Director instructed
    her to sign the Stein contracts is the subject of a pointed factual
    dispute. As for the $2,500 deposits paid in January 2016,
    both Marketing Director and CMO—apparently the only MX
    executives who knew about those payments—believed them
    to serve merely as a “hold” for the dates at Stein, and not
    indicative of the fact that binding contracts had already been
    signed. A reasonable jury could elect to credit the MX
    executives’ testimony, and on that basis could determine that the
    deposits did not indicate corporate ratification of the
    Stein contracts.
    ¶44 Next, the district court relied on the fact that several
    employees of MX—including Events Coordinator, Marketing
    Director, and an assistant controller—learned about the existence
    of the signed contracts at an earlier point in time than did CFO
    or CMO. The fact that Events Coordinator—Events Manager’s
    subordinate—knew about the signed contracts is irrelevant to
    ratification, because not even Stein contends that Events
    Coordinator is the type of MX executive who could have bound
    the company. And the same goes for an assistant controller from
    MX’s accounting department: there exists at least a question of
    fact about what level of authority she held in the company
    hierarchy, as well as about whether her actions—helping Events
    Manager submit an invoice request through company
    software—are the sort of actions that would constitute
    ratification.
    20200256-CA                     19                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ¶45 Marketing Director’s knowledge and actions are
    potentially helpful for Stein, but even these are not sufficient to
    indicate ratification as a matter of law. As noted above, see supra
    ¶ 28, there exists a factual question as to what authority
    Marketing Director had within the company—that is, whether
    she was high enough up in the company hierarchy to be able to
    confer authority on Events Manager to sign the contracts or to
    ratify them after the fact. Moreover, Marketing Director testified
    that she did not know of the existence of the signed contracts
    until receiving Stein’s “demand for payment,” an apparent
    reference to Stein’s May 13 email. At that point, she informed
    CFO and CMO that Events Manager had actually signed the
    contracts, and from that point forward MX took no actions that
    could constitute ratification—indeed, after May 13, MX took the
    position, in all its dealings with Stein, that the contracts were
    invalid.
    ¶46 Next, the district court listed certain actions taken by
    Events Manager, Events Coordinator, and other lower-level
    company employees geared toward preparation for the August
    conference. In particular, the court noted that Events Manager
    and Events Coordinator visited Stein in April for a site visit, a
    “creative director” called Stein to request video footage of the
    property for MX’s marketing efforts, and MX updated its
    website and sent internal emails discussing the event. These are
    all helpful facts for Stein, but they fall short of establishing
    ratification as a matter of law. As MX correctly points out, while
    these actions certainly show that MX employees were “planning
    for a possible event,” they do not necessarily compel the
    conclusion that MX employees were ratifying the terms of
    specific contracts. Any such conclusion requires certain
    inferences to be drawn, and those kinds of inferences will need
    to be made, if at all, by a factfinder.
    ¶47 Finally, the district court noted that MX, through its
    CMO, signed an actual contract with a keynote speaker for the
    20200256-CA                     20                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    conference. This is another helpful fact for Stein, but it too is
    subject to competing inferences. CMO apparently did not know
    about the existence of the contracts until Stein demanded
    payment, and he testified that the company’s planning and
    marketing efforts, including internal emails and other actions,
    were merely preparatory for a possible conference. Even Stein
    appears to acknowledge that this fact—as with many of the facts
    it advances in support of its ratification argument—is subject to
    a credibility determination, asserting that “[i]t is impossible to
    believe that MX could have contractually bound itself to have [a
    keynote speaker] speak at [Stein] if MX did not know that it had
    contracts with [Stein] for the conference.” This may be an
    excellent point to make to a factfinder, but for present purposes
    it is not quite enough. We cannot say that contracting for a
    keynote speaker necessarily compels the conclusion, as a matter
    of law, that MX ratified the Stein contracts Events Manager
    signed.
    ¶48 Thus, the facts relied upon by Stein and the district court
    in support of the court’s ratification conclusion are either
    irrelevant to the ratification question or are, to one degree or
    another, disputed by MX based on other evidence in the record.
    Even taken together, these facts are not sufficient to support a
    conclusion that, as a matter of law, MX ratified the Stein
    contracts. See Best v. Daimler Chrysler Corp., 
    2006 UT App 304
    ,
    ¶ 10, 
    141 P.3d 624
     (“It is not the purpose of the summary
    judgment procedure to judge the credibility . . . of the parties, or
    witnesses, or the weight of the evidence, and it only takes one
    sworn statement under oath to dispute the averments on the
    other side of the controversy and create an issue of fact.”
    (quotation simplified)). We certainly acknowledge the strength
    of Stein’s arguments, but remain convinced that disputed
    factual issues remain, and that a factfinder, in resolving
    those disputes, could reasonably conclude that MX did not ratify
    the contracts.
    20200256-CA                     21                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ¶49 Accordingly, because disputed factual issues prevent
    summary judgment in Stein’s favor on issues related to authority
    and ratification, the district court’s decision to grant Stein’s
    motion for summary judgment as to liability was erroneous. We
    therefore vacate that portion of the district court’s summary
    judgment order, and remand the case for further proceedings
    consistent with this opinion.
    II. The Liquidated Damages Provisions
    ¶50 Our conclusion to vacate part of the district court’s
    summary judgment order and remand for further proceedings is
    technically dispositive of this appeal. The other two fully briefed
    issues both concern the amount of damages to which Stein
    would potentially be entitled in the event it prevails at trial on
    issues related to contractual validity; these damages issues will
    be moot if MX were to prevail at trial on the contractual validity
    issues. However, in the event Stein prevails at trial on those
    issues, the damages issues will become relevant, and therefore
    we proceed to examine those issues, which stand before us fully
    briefed and submitted. See Bair v. Axiom Design, LLC, 
    2001 UT 20
    ,
    ¶ 22, 
    20 P.3d 388
     (proceeding to decide certain submitted issues,
    even though “resolution of [another] issue” had been
    “dispositive” of the appeal, because “where an appellate court
    finds that it is necessary to remand a case for further
    proceedings, it has the duty of passing on matters which may
    then become material” (quotation simplified)), abrogated on other
    grounds by A.S. v. R.S., 
    2017 UT 77
    , 
    416 P.3d 465
    ; see also Equine
    Holdings LLC v. Auburn Woods LLC, 
    2021 UT App 14
    , ¶ 36, 
    482 P.3d 880
     (continuing to discuss other issues, “in the hope that
    such discussion might be useful on remand,” despite reversing a
    summary judgment order and remanding for other reasons).
    ¶51 The first damages issue concerns whether the liquidated
    damages provisions in the Stein contracts are unconscionable as
    a matter of law and therefore unenforceable. Stein sought
    20200256-CA                     22                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    summary judgment on that point below, and the district court
    granted that motion, concluding that the liquidated damages
    provisions were neither procedurally nor substantively
    unconscionable. MX appeals that decision, but we affirm it,
    concluding that the court appropriately analyzed the matter.
    ¶52 Nearly a decade ago, our supreme court clarified Utah
    law regarding the enforcement of liquidated damages clauses. In
    Commercial Real Estate Investment, LC v. Comcast of Utah II, Inc.,
    
    2012 UT 49
    , 
    285 P.3d 1193
    , the court held that liquidated
    damages provisions “should be reviewed in the same manner as
    other contractual provisions,” and are “not subject to any form
    of heightened judicial scrutiny.” Id. ¶¶ 38, 40. In other words,
    parties who wish to challenge a liquidated damages provision
    must avail themselves of standard contractual concepts like
    “mistake, fraud, duress, or unconscionability.”5 Id. ¶ 40. In
    5. MX resists this reading of Commercial Real Estate Investment, LC
    v. Comcast of Utah II, Inc., 
    2012 UT 49
    , 
    285 P.3d 1193
    , and asserts
    that liquidated damages provisions can still be invalidated on
    grounds that they constitute an impermissible “penalty.” In
    Commercial Real Estate, the court disavowed a line of cases that
    had focused “on whether a contractual provision providing for
    liquidated damages constitutes a penalty,” referring to those
    cases as having imposed “an unnecessary additional check on
    the enforceability of” liquidated damages provisions. See 
    id.
    ¶¶ 22–23, 33–40. In doing so, however, it noted that most of the
    “penalty” cases had deemed the liquidated damages clauses
    unconscionable in any event, and on that basis stated that
    “[r]eviewing liquidated damages clauses for unconscionability
    still preserves challenges to penalty clauses.” Id. ¶ 39. The court
    also noted that the penalty cases had engaged in essentially “the
    same inquiry we engage in for claims of unconscionability.” Id.
    After Commercial Real Estate, as we understand it, liquidated
    (continued…)
    20200256-CA                     23                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    attacking the liquidated damages provisions found in the Stein
    contracts, MX invokes the doctrine of unconscionability, a
    doctrine that presents only legal issues for the court (rather than
    factual issues for a jury). See Sosa v. Paulos, 
    924 P.2d 357
    , 360
    (Utah 1996) (stating that “[t]he determination of whether a
    contract is unconscionable is . . . a question of law for the court”
    to decide).
    ¶53 MX, as the party claiming that a contractual provision is
    unconscionable, “bears a heavy burden.” See Ryan v. Dan’s Food
    Stores, Inc., 
    972 P.2d 395
    , 402 (Utah 1998); see also Resource Mgmt.
    Co. v. Weston Ranch & Livestock Co., 
    706 P.2d 1028
    , 1043 (Utah
    1985) (“A duly executed written contract should be overturned
    [on unconscionability grounds] only by clear and convincing
    evidence.”). “In determining whether a contract is
    unconscionable, we use a two-pronged analysis.” Commercial
    Real Estate, 
    2012 UT 49
    , ¶ 42 (quotation simplified). One prong,
    geared toward assessment of “procedural unconscionability[,]
    focuses on the negotiation of the contract and the circumstances
    of the parties.” Id. ¶ 43 (quotation simplified). The other prong,
    geared toward assessment of “substantive unconscionability[,]
    focuses on the contents of an agreement, examining the relative
    fairness of the obligations assumed.” Id. ¶ 44 (quotation
    simplified). A determination that an agreement is substantively
    (…continued)
    damages provisions that previously were deemed “penalty”
    clauses will often still be invalidated, but this will occur because
    those clauses will also usually meet the criteria for
    unconscionability. Put simply, now that our supreme court has
    eliminated the “conflicting approaches” to assessing the validity
    of liquidated damages provisions, there no longer exist valid
    separate criteria—other than unconscionability standards—to
    screen for “penalty” clauses. See id. ¶¶ 21, 33–40.
    20200256-CA                     24                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    unconscionable may, by itself, “support a               finding   of
    unconscionability.” Id. ¶ 42 (quotation simplified).
    A.     Procedural Unconscionability
    ¶54 In assessing whether an agreement is procedurally
    unconscionable, “the key inquiry is whether there was
    overreaching by a contracting party occupying an unfairly
    superior bargaining position.” Id. ¶ 43 (quotation simplified).
    To assist with this inquiry, our supreme court has set forth
    a non-exhaustive list of six factors that may “bear[] on
    procedural unconscionability.” See Ryan, 972 P.2d at 403. These
    factors are:
    (1) whether each party had a reasonable
    opportunity to understand the terms and
    conditions of the agreement; (2) whether there was
    a lack of opportunity for meaningful negotiation;
    (3) whether the agreement was printed on a
    duplicate or boilerplate form drafted solely by the
    party in the strongest bargaining position; (4)
    whether the terms of the agreement were
    explained to the weaker party; (5) whether the
    aggrieved party had a meaningful choice or instead
    felt compelled to accept the terms of the
    agreement; and (6) whether the stronger party
    employed deceptive practices to obscure key
    contractual provisions.
    Id. (quotation simplified).
    ¶55 Applying these factors, we readily conclude that the
    liquidated damages provisions in the Stein contracts are not
    procedurally unconscionable. Frankly, none of the six factors
    point toward procedural unconscionability in this case. Both
    contracting parties are sophisticated corporate entities with
    20200256-CA                     25                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    experience negotiating these kinds of contracts.6 MX had a
    reasonable opportunity to understand the terms and conditions
    of the contracts; after all, MX was in possession of the drafts for
    over two weeks after Events Manager told Stein that MX would
    need some time to review the contracts “and have [its] legal
    team also glance over [them]” before they could be executed. MX
    also had an opportunity for meaningful negotiation; Events
    Manager had pre-contract discussions with Stein about specific
    contract terms, including dates, number of rooms, deposits and
    liquidated damages. Even though the contracts were drafted by
    Stein using a form template, Stein indicated a willingness to
    negotiate the terms. And finally, MX certainly had a meaningful
    choice about whether to stage its conference at Stein, as opposed
    to elsewhere, and there is no indication that Stein was deceptive
    about the presence of liquidated damages provisions in the
    contracts.7
    6. This statement assumes that questions regarding Events
    Manager’s authority will be decided in favor of Stein. Indeed,
    this entire section of our opinion, as noted above, becomes
    relevant only if Stein prevails on the contractual validity
    questions at trial. In that event, it will have been established that
    Events Manager was authorized to sign the contracts or that MX
    ratified them post-execution, and Events Manager’s own relative
    inexperience or lack of sophistication will no longer matter. If
    MX—unquestionably a sophisticated company—chooses a
    relatively inexperienced representative to negotiate and sign a
    contract, that choice cannot operate to transform MX from a
    sophisticated company into something else.
    7. Stein’s statement that it would “be flexible with” and would
    “work with” MX regarding Stein’s “cancellation and payment
    policies” does not appear to have been false; indeed, Stein was
    (continued…)
    20200256-CA                     26                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ¶56 The best MX can do is point to the fact that Events
    Manager was twenty-four years old and relatively new to the
    job, and that Stein told her that other parties were interested in
    the same dates for their events and that the contracts needed to
    be signed soon to secure the desired dates. Aside from being
    somewhat paternalistic—after all, twenty-four-year-olds are
    adults, and many of them are capable of accomplishing difficult
    and complex tasks—this argument describes nothing more than
    the ordinary apprehension inherent in the negotiation and
    consummation of almost any commercial transaction. On these
    facts, MX falls well short of being able to establish procedural
    unconscionability.
    B.    Substantive Unconscionability
    ¶57 Next, we consider whether the liquidated damages
    provisions are substantively unconscionable. In making that
    assessment, we consider “whether there exists an overall
    imbalance in the obligations and rights imposed by the bargain
    (…continued)
    flexible with some of those policies, agreeing to allow MX to
    postpone payment of a $75,000 deposit for more than two
    months later than the contracts called for. Moreover, those
    comments were made in the context of a general discussion
    about Stein’s deposit, cancellation, and payment policies, and
    not in the context of a specific discussion about liquidated
    damages; in the absence of a more direct connection to the
    liquidated damages provisions, we do not believe that a later
    decision to enforce those provisions renders deceptive an earlier
    general commitment to “work with” MX. And in any event, even
    if we were to perceive some level of deception in Stein’s
    comments, such deception would not outweigh the other five
    factors of the procedural unconscionability test, all of which
    point in the other direction.
    20200256-CA                    27                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    according to the mores and business practices of the time
    and place.” Ryan, 972 P.2d at 402 (quotation simplified).
    However, a contract whose terms are clearly better for one
    side than the other is not necessarily unconscionable;
    indeed, parties are generally free to negotiate the terms of their
    own contracts, including unfavorable ones. See id. (“Even if a
    contract term is unreasonable or more advantageous to one
    party, the contract, without more, is not unconscionable. . . .”);
    see also Park Valley Corp. v. Bagley, 
    635 P.2d 65
    , 67 (Utah 1981)
    (stating that “sellers and buyers should be able to contract on
    their own terms without the indulgence of paternalism by
    the courts in the alleviation of one side or another from
    the effects of a poor bargain,” and that parties “should be
    permitted to enter into contracts that may actually be
    unreasonable or which may lead to hardship on one side”). In
    short, substantive unconscionability is present only where the
    terms of the contract are “so one-sided as to oppress an innocent
    party.” Ryan, 972 P.2d at 402 (quotation simplified). That is not
    the case here.
    ¶58 MX’s chief argument to the contrary is that the liquidated
    damages provisions were “purposely designed” to create a
    “massive windfall” for Stein. In particular, MX asserts that these
    provisions were set up to allow Stein to recover a sum of
    liquidated damages greater—in two specific ways—than its
    actual damages. First, MX asserts that, under these provisions,
    Stein reserved for itself the ability to recover an amount of
    liquidated damages that could, and would here, far exceed its
    actual lost profits. Second, and relatedly, MX laments that
    the liquidated damages provisions do not require Stein to
    mitigate its damages. Without question, the liquidated
    damages provisions in these contracts are favorable to Stein and
    would in this case—if applied—allow Stein to recover an
    amount of damages that is more than twice as high as its actual
    20200256-CA                    28                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    damages.8 But for the reasons discussed, these provisions are not
    substantively unconscionable.
    ¶59 First, the fact that the liquidated damages provisions may
    allow Stein to recover an amount greater than its actual lost
    profits does not necessarily render the provisions
    unconscionable. After all, “the purpose of a liquidated damages
    provision is to obviate the need for the nonbreaching party to
    prove actual damages.” Commercial Real Estate Inv., LC v. Comcast
    of Utah II, Inc., 
    2012 UT 49
    , ¶ 41, 
    285 P.3d 1193
     (quotation
    simplified). Liquidated damages provisions are often used by
    parties in situations “where the damages are likely to be
    uncertain and not easily proven.” See 22 Am. Jur. 2d Damages
    § 506. The relationship between potential liquidated damages
    and estimated actual damages, as measured at the time of
    contracting, is certainly a factor courts may consider when
    assessing the unconscionability of a liquidated damages
    provision. See Commercial Real Estate, 
    2012 UT 49
    , ¶ 45
    (examining, among other things, whether “the contractual
    amount of liquidated damages” was “unreasonable as
    compensation for breach” of the contract); see also 22 Am. Jur. 2d
    Damages § 528 (stating that courts may consider “whether the
    amount stipulated is reasonably proportionate or bears a rational
    relationship to the damages that have actually been caused by
    the breach”). But a liquidated damages clause is not
    unconscionable simply because it may allow, if developments
    play out a certain way, for recovery of an amount of damages
    8. In this case, because MX cancelled the contracts a full sixty
    days prior to the date the conference was scheduled to begin,
    Stein was able to mitigate some of its damages. For purposes of
    the dueling summary judgment motions, it was undisputed that
    Stein’s actual damages were just over $170,000, approximately
    half of the roughly $350,000 liquidated damages award.
    20200256-CA                    29                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    greater than a party’s actual damages. See Commercial Real Estate,
    
    2012 UT 49
    , ¶ 45 (rejecting the argument that a liquidated
    damages provision was unconscionable because it allowed for
    recovery of an amount allegedly “grossly disproportionate” to
    actual damages, and stating that “this type of post-hoc weighing
    does not bear on the question of substantive unconscionability,
    which focuses on the relative fairness of the obligations assumed
    at the time of contracting” (quotation simplified)).
    ¶60 In this case, the liquidated damages figure is not pulled
    out of thin air; it is specifically tied to the amount MX was
    obligated to pay under the contracts, with the percentage
    varying according to the date of cancellation. That amount is the
    sum of the room charges, the food charges, and a service fee,
    amounts that are relatively easy to compute. Stein correctly
    points out that this amount does not include all the profit centers
    associated with a full hotel, and specifically excludes profits
    anticipated from the provision of ancillary services, including
    things like gift shops, coffee stations, sandwich shops, bars, and
    equipment rental facilities. These ancillary profits are more
    difficult to compute, and Stein asserts that its liquidated
    damages figure—by including full room costs and food charges
    but excluding ancillary charges—is meant to be a rough but by
    no means precise prediction of its total lost profits. We agree
    with Stein that, on this record, its liquidated damages figure
    bears a reasonable relationship to its estimated potential lost
    profits.
    ¶61 Moreover, as applicable here, Stein is entitled to recover,
    as liquidated damages, 100% of that total if the contracts are
    cancelled sixty or fewer days before the conference. The parties’
    respective experts, though they disagree on many things, both
    agree that using a sixty-day window for “cancellation provisions
    on the highest scale” is appropriate and common in the
    20200256-CA                     30                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    industry.9 And once this fact is acknowledged, it becomes
    evident that these particular liquidated damages provisions
    cannot have been designed, from the outset,10 to necessarily
    create a windfall for Stein in every instance.
    ¶62 At the time the contracts were signed, neither party knew
    whether the contracts would ever be cancelled, and certainly did
    not know when any such cancellation would take place.
    Generally speaking, the earlier a cancellation occurs, the better
    equipped a hotel will be to manage its costs—for instance, by not
    purchasing food or employing staff for meals that will not be
    served, or not employing staff to manage rooms that will not be
    occupied—and to rent the rooms to someone else. If a party
    cancels on Day 60 (as MX did here), Stein will generally be (and
    was here) well-positioned to end up in a “windfall” position, in
    which it is able to utilize the advance notice to manage its costs,
    and in which it receives (from MX) 100% of the amount MX
    9. Indeed, the Sundance contract signed by Events Manager
    contained a liquidated damages provision that—although in
    other material respects is less onerous than the ones in the Stein
    contracts—also used a sixty-day window for cancellation
    purposes and specified that a cancellation within that window
    would result in the highest amount of liquidated damages.
    10. The propriety of liquidated damages provisions must be
    assessed at the time of contract formation, and not at the time of
    breach. See Commercial Real Estate, 
    2012 UT 49
    , ¶¶ 35–36
    (criticizing certain approaches to assessing liquidated damages
    provisions as faulty because they “tended to evaluate the
    enforceability” of such provisions “with the benefit of hindsight,
    rather than as of the time of contract formation”); see also id. ¶ 52
    (Lee, J., concurring) (agreeing with the majority that “post-hoc
    review” of liquidated damages provisions “is problematic”).
    20200256-CA                     31                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    agreed to pay, plus additional revenue (from other customers)
    related to its re-letting of the rooms. But if a party cancels on Day
    1—the day before the conference—Stein will be poorly
    positioned to avoid incurring unnecessary costs or to recoup its
    losses by re-letting the rooms. Under these circumstances, it is
    certainly not evident that the liquidated damages provisions in
    the Stein contracts will always result in a windfall for Stein.
    ¶63 Second, with regard to mitigation of damages, the general
    rule is that mitigation is not required in situations where the
    parties have agreed to a stipulated amount of damages. See 24
    Williston on Contracts § 65:31 (4th ed. 2020) (explaining that
    because a liquidated damages provision substitutes a
    predetermined amount for actual damages, “the existence of an
    enforceable liquidated damages provision has the effect of
    making the mitigation of damages irrelevant”); see also 22 Am.
    Jur. 2d Damages § 541 (“If a liquidated damages clause is valid,
    the nonbreaching party does not have a duty to mitigate
    damages following breach.”).11 MX asserts, as part of its
    argument, that the liquidated damages provisions are
    unconscionable precisely because they allow Stein to recover
    100% of the room and food costs without any duty to mitigate.
    11. Our supreme court’s decision in Commercial Real Estate is not
    to the contrary. See 
    2012 UT 49
    , ¶¶ 46–48. Although the court did
    include in its opinion a discussion of the duty to mitigate
    damages, it did so only because, in that particular case, the
    parties had agreed—by contract—to a mitigation-of-damages
    clause in addition to their liquidated damages clause. Id. ¶ 5.
    Certainly, parties are free to vary the general rule—that
    mitigation of damages is not required where a valid liquidated
    damages provision exists—by including in their contract, along
    with a liquidated damages provision, a clause requiring
    mitigation of damages. In this case, the parties did not do so.
    20200256-CA                     32                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    But this can’t be right: in the liquidated damages context, parties
    generally do not have a duty to mitigate. If a liquidated damages
    provision were considered unconscionable simply because it
    relieved a party of its duty to mitigate, many liquidated damages
    provisions would be invalid. Accordingly, we conclude that a
    liquidated damages provision is not unconscionable merely
    because that provision allows a party to recover more in
    damages than it would have if it were subject to a duty to
    mitigate.
    ¶64 Without doubt, these liquidated damages provisions are
    advantageous for Stein. They allow Stein to recover 100% of the
    room and food charges, without accounting for unincurred costs,
    and without the necessity of mitigating damages, if the contracts
    are cancelled inside sixty days prior to the conference date. In
    many situations, depending on when the cancellation occurs,
    such liquidated damages provisions will allow Stein to recover
    more than its actual lost profits. But that fact does not render
    these provisions substantively unconscionable. The liquidated
    damages amounts are directly linked to the contractual room
    and food charges, and are based on a sixty-day cancellation
    window that is apparently standard in the industry. Under the
    circumstances presented here, the liquidated damages
    provisions are not “so one-sided as to oppress or unfairly
    surprise” MX. See Commercial Real Estate, 
    2012 UT 49
    , ¶ 44.
    Accordingly, we affirm that portion of the district court’s
    summary judgment order in which it concluded that the
    liquidated damages provisions in the Stein contracts were valid
    and enforceable.
    III. The Date of Cancellation
    ¶65 Finally, we address the parties’ dispute regarding the date
    on which MX cancelled the contracts. This dispute matters,
    because under the terms of the contracts, Stein is entitled to
    liquidated damages equal to 90% of the contracted amounts if
    20200256-CA                     33                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    cancellation occurred between sixty-one and ninety days prior to
    the event, but is entitled to 100% of the contracted amounts if
    cancellation occurred sixty or fewer days prior to the event. MX
    contends that it officially cancelled the contracts on May 25
    (sixty-eight days prior to the event), when CFO sent an email to
    Stein offering two potential compromises in an apparent effort to
    resolve the parties’ dispute. Stein contends that the May 25 email
    was an attempt to renegotiate, not a cancellation, and that the
    actual cancellation did not occur until June 2, exactly sixty days
    prior to the event. The district court made no explicit ruling on
    the matter, but resolved the matter impliedly by awarding Stein,
    as damages, 100% of the contracted amounts. MX takes issue
    with that implied decision, contending that questions of fact
    preclude a resolution of the matter in the summary judgment
    setting.
    ¶66 As a general matter, “a notice of termination of
    cancellation of a contract must be clear and unequivocal.” Glenn
    v. Reese, 
    2009 UT 80
    , ¶ 19, 
    225 P.3d 185
    . Stein asserts that the May
    25 email was not clearly and unequivocally a cancellation, and
    that summary judgment in its favor on the issue is therefore
    appropriate. Stein’s interpretation of the email is certainly a
    reasonable one, given that CFO never actually said that MX was
    terminating any contractual relationship between the parties,
    and even used the email as an attempt to negotiate the terms of a
    future contractual relationship. Indeed, CFO stated that
    “[a]lthough the contract was executed by an employee who is
    not authorized,” he understood that “one of our employees has
    set expectations” with Stein and that he “want[ed] to reach an
    equitable resolution.” Even MX does not assert that Stein’s
    interpretation of the email is unreasonable.
    ¶67 Instead, it asserts that it can proffer a reasonable
    alternative interpretation of the email, and that under its
    interpretation, the email represents a cancellation of the
    contracts. In particular, MX points to CFO’s description of the
    20200256-CA                     34                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    contracts as having been executed by an employee without
    authorization to sign such contracts, and who had not been
    given authority to sign these specific contracts. It asserts that
    CFO therefore at least implied that the contracts were
    unenforceable. It thus contends that its interpretation is a
    reasonable one, that “a reasonable juror could have concluded”
    that the email “constituted ‘cancellation’” of the contracts, and
    that the email is therefore ambiguous on that point.
    ¶68 We agree with MX that its interpretation of the May 25
    email is a reasonable one, and agree that this fact renders the
    email ambiguous. See Mind & Motion Utah Invs., LLC v. Celtic
    Bank Corp., 
    2016 UT 6
    , ¶ 24, 
    367 P.3d 994
     (stating that ambiguity
    exists where a document’s “terms are capable of more than one
    reasonable interpretation because of uncertain meanings of
    terms, missing terms, or other facial deficiencies” (quotation
    simplified)). In many instances, a court’s legal determination
    that ambiguity exists will lead to the conclusion that summary
    judgment cannot be granted regarding the meaning of a
    document, and that a factfinder will need to weigh in on the
    matter. See, e.g., Ocean 18 LLC v. Overage Refund Specialists LLC
    (In re Excess Proceeds from Foreclosure of 1107 Snowberry St.), 
    2020 UT App 54
    , ¶ 29, 
    474 P.3d 481
     (“If a court determines, as a legal
    matter, that a contract is ambiguous, then a question of fact
    exists as to the parties’ intentions.”). But in this particular
    context, our determination that the email is ambiguous does not
    carry the day for MX.
    ¶69 There are some areas of the law in which clarity is so
    important that ambiguity itself results in judgment as a matter of
    law in one side’s favor. See, e.g., Geisdorf v. Doughty, 
    972 P.2d 67
    ,
    70 (Utah 1998) (stating that when an “optionee decides to
    exercise his option [to renew a contract] he must act
    unconditionally and precisely according to the terms of the
    option,” and that actions constituting mere substantial
    compliance—as opposed to strict compliance—will not suffice
    20200256-CA                     35                 
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    (quotation simplified)); Brady v. Park, 
    2013 UT App 97
    , ¶¶ 17–20,
    
    302 P.2d 1220
     (noting that compound interest “is not favored by
    the law” and that such interest will be awarded only where the
    parties “expressly agreed to compound interest,” and holding
    that an agreement that was unclear and left the matter to
    “inference and implication” had to be construed as providing for
    simple interest). Our supreme court has declared cancellation of
    contracts to be one of those areas. See Glenn, 
    2009 UT 80
    , ¶ 19
    (“Ambiguous conduct and language intended to signal contract
    termination will be deemed not to have terminated the contract.”
    (quotation simplified)). In this specific context, a communication
    that only ambiguously communicates intent to cancel a contract
    will be deemed, as a matter of law, insufficient to cancel that
    contract. “[N]otice of termination or cancellation of a contract
    must be clear and unequivocal,” and if it isn’t, it doesn’t operate
    to cancel the contract. 
    Id.
     In particular, a communication that
    “commingl[es] . . . a wish to cancel with a desire to negotiate and
    save the contract cannot be seen as an unequivocal notice of
    cancellation.” Id. ¶ 20.
    ¶70 The May 25 email is ambiguous. It might have been an
    attempt to cancel any contractual relationship the parties might
    have had,12 and can even be reasonably so interpreted, but it
    12. We recognize that MX’s position, both in the May 25 email
    and throughout this litigation, is that no valid contracts ever
    existed between MX and Stein. But we have determined, see
    supra Part I, that questions of fact remain to be adjudicated on
    this point. Of course, if the factfinder later determines that no
    contracts existed, then cancellation was never necessary, Stein
    will not be entitled to contractual damages, and this issue will be
    rendered moot. But if the factfinder sides with Stein, and
    determines that valid contracts were in effect as of May 25, the
    date of cancellation of the contract will become relevant to the
    (continued…)
    20200256-CA                     36                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    does not clearly and unequivocally set forth that intention. In
    this specific area of the law, ambiguity is not sufficient to stave
    off summary judgment. Because the May 25 email was
    ambiguous, and did not serve as a clear and unequivocal
    cancellation of the contracts, the district court correctly (if
    impliedly) determined that, as a matter of law, MX cancelled the
    contracts on June 2, just sixty days before the conference was to
    begin. Thus, in the event that Stein prevails on the contractual
    validity issues, it will be entitled to 100% of the contractual
    amount as liquidated damages.
    CONCLUSION
    ¶71 The presence of disputed factual issues prevents entry of
    summary judgment in Stein’s favor on issues related to validity
    of the contracts. In particular, a reasonable factfinder could
    conclude, on this record, that Events Manager did not have
    actual or apparent authority to sign the contracts, and that MX
    did not ratify them after the fact. Thus, the part of the district
    court’s summary judgment order granting Stein’s motion for
    summary judgment as to liability is erroneous. We vacate that
    portion of the order, and remand for further proceedings.
    (…continued)
    damages inquiry. We acknowledge MX’s point that it is not
    obligated to cancel contracts that did not exist, but a party who
    puts all its eggs in the contractual-nonexistence basket takes a
    risk that a factfinder may later disagree with it on that point. A
    prudent party in MX’s position would be well-advised to craft a
    notice that both maintains the position that no contract exists but
    also, in the alternative, clearly and unequivocally cancels any
    contractual relationship that might later be determined to exist.
    20200256-CA                     37                
    2022 UT App 30
    Stein Eriksen v. MX Technologies, Inc.
    ¶72 With regard to damages, the court’s summary judgment
    order is correct. The liquidated damages provisions in the
    contracts are, as a matter of law, not unconscionable, and MX
    did not clearly and unequivocally cancel the contracts until June
    2, just sixty days before the conference was to begin. We
    therefore affirm the remainder of the court’s summary judgment
    order, and remand with instructions that Stein, if it prevails at
    trial on the disputed issues regarding contractual validity, will
    be entitled to recover, as liquidated damages, 100% of the
    contractual amount.
    20200256-CA                    38                
    2022 UT App 30