Donald Bishop v. Town of Springfield ( 2016 )


Menu:
  • Note: Decisions of a three-justice panel are not to be considered as precedent before any tribunal.
    ENTRY ORDER
    SUPREME COURT DOCKET NO. 2016-128
    NOVEMBER TERM, 2016
    Donald Bishop                                         }    APPEALED FROM:
    }
    }    Superior Court, Windsor Unit,
    v.                                                 }    Civil Division
    }
    }
    Town of Springfield                                   }    DOCKET NO. 205-4-15 Wrcv
    Trial Judge: Theresa S. DiMauro
    In the above-entitled cause, the Clerk will enter:
    Plaintiff appeals from a superior court judgment affirming a decision by the select board
    of the Town of Springfield declaring a building owned by plaintiff to be a public nuisance and
    ordering that it be demolished. Plaintiff contends: (1) the decision violated his constitutional right
    to due process of law by failing to afford him an opportunity to repair the building; and (2) the
    evidence did not support the board’s findings and conclusions. We affirm.
    The material facts may be summarized as follows. The building in question was damaged
    by a fire in November 2012. Two years later, in November 2014, the Town’s fire chief filed a
    complaint with the Board under the Town’s nuisance ordinance asserting that the fire-damaged
    structure was unsafe. As required by the ordinance, the Board appointed a three-person committee
    to inspect the premises and report to the Board. Based on the committee’s report, filed with the
    Board in December 2014, the Board found that the building was a public nuisance and ordered
    that it be demolished.
    Plaintiff appealed, and the Board held an evidentiary hearing on the matter in January 2015.
    A representative of the committee and a licensed structural engineer presented testimony on behalf
    of the Town. Plaintiff appeared with counsel, who questioned the Town’s witnesses, and plaintiff
    testified on his own behalf but called no other witnesses. At the conclusion of the hearing, the
    Town granted plaintiff’s request to continue the hearing to its next meeting in February 2015 to
    afford plaintiff an opportunity to present testimony from his own engineer. At the continued
    hearing, however, plaintiff presented no additional testimony or other evidence. Plaintiff’s
    attorney informed the Board that plaintiff did not intend to take any action pending an insurance
    settlement, which he expected in May 2015, and that his engineer was working on a plan to
    demolish part of the building and rehabilitate another part.
    The Board issued a written decision in late February 2015. The Board found that, as a
    result of the fire and lack of repair, the building was in a seriously dilapidated and unstable
    condition, including damage to about a third of its supporting members and fifty percent or more
    of its nonsupporting or outside walls; that substantial portions of the walls and framing and rafters
    had been destroyed or damaged and continued to deteriorate; that the roof was bowed and leaking;
    and that the foundation contained cracks. The Board concluded that the building was structurally
    unsafe, was liable to collapse, and presented a danger to the public health and safety. Based on
    these findings and conclusions, the Board concluded that the building constituted a public nuisance
    under the ordinance and ordered that it be demolished.
    Plaintiff appealed to the superior court pursuant to Vermont Rule of Civil Procedure 75.
    The court reviewed the entire record, including video recordings of the hearings before the Board
    and the photographic exhibits, heard argument from counsel for plaintiff and the Town at a hearing
    in November 2015, and issued a written ruling in March 2016. The court initially observed that
    although plaintiff’s notice of appeal appeared to allege an unconstitutional taking without just
    compensation, plaintiff had not pursued this argument at the hearing. Nevertheless, the court found
    no merit to the claim, relying on substantial state and federal authority holding that a state need
    not provide compensation when it demolishes a property that was properly determined to constitute
    a nuisance.
    Next the court addressed plaintiff’s assertion, raised at the hearing, that the Town’s
    ordinance and procedures did not comport in some respect with the statutory provisions for the
    condemnation of an unsafe structure. See 24 V.S.A. §§ 3113-3116. The court rejected the claim,
    observing that the Town was proceeding under a separate statutory authorization for the removal
    of a public nuisance under 24 V.S.A. § 2291(14).
    Finally, the court rejected plaintiff’s challenge to the sufficiency of the evidence underlying
    the Board’s findings and conclusion that the structure was a public nuisance requiring demolition.
    The court concluded that the decision was amply supported by the extensive testimony of the
    Town’s witnesses. This appeal followed.
    Plaintiff first contends that “constitutional due process” required the Board to afford him
    an opportunity “to repair the building to prevent demolition.” The trial court did not address this
    argument for the simple reason that it was not raised below, and therefore the claim was waived
    on appeal. See Miller-Jenkins v. Miller-Jenkins, 
    2010 VT 98
    , ¶ 28, 
    189 Vt. 518
    (mem.) (“Failure
    to preserve issues below results in waiver, even of constitutional issues.”). As discussed, plaintiff’s
    notice of appeal asserted that the Board’s action constituted a taking without compensation, but
    the record reveals no claim or argument that the Board violated due process by not affording
    plaintiff an opportunity to repair. Although plaintiff asserts that the issue was raised, his citations
    are to one statement by counsel that due process required the court to make findings independent
    of the Board, and several others where counsel argued that plaintiff should be given the opportunity
    to repair. The court addressed the latter argument in upholding the Board’s determination that the
    fire damage, combined with two years of neglect, had rendered the building so structurally
    unsound and dangerous to the public that demolition was required under the ordinance. * The
    record does not, however, show that plaintiff gave the trial court any reasonable notice or
    opportunity to address his asserted due process claim. See 
    id. (“Issues not
    raised with specificity
    and clarity, and in a manner which gives the trial court a fair opportunity to rule on them, are . . .
    waived.”). Accordingly, the claim was not properly preserved for review on appeal.
    *
    Indeed, the Town’s ordinance specifically requires that, if the building could “reasonably
    be repaired so that it will no longer exist in violation of the terms of this article, it shall be ordered
    repaired or secured.” The extent of structural damage to the building found by the Board, however,
    supported demolition under the ordinance.
    2
    Plaintiff also asserts that the record did not support the Board’s findings concerning the
    extent of damage to the building and the determination that it must be demolished. He appears to
    raise three claims in this regard. First, he asserts that the court applied an incorrect standard of
    review. The court applied the proper standard articulated by this Court in Garbitelli v. Town of
    Brookfield, 
    2011 VT 122
    , 
    191 Vt. 76
    , to the effect that “[r]eview of evidentiary questions is limited
    to whether there is any competent evidence to justify the adjudication.” 
    2011 VT 122
    , ¶ 6, 
    191 Vt. 76
    (quotation omitted). The principal case cited by plaintiff is not to the contrary. In Eno v.
    City of Burlington, 
    125 Vt. 8
    (1965), the Court observed that a municipal determination of a
    nuisance is “persuasive and not conclusive,” but the Court’s reaffirmation that a municipal board’s
    findings are “presumed correct” and afforded “every presumption” show that it was not attempting
    to create a separate or less deferential standard of 
    review. 125 Vt. at 14
    .
    Plaintiff further maintains that the demolition ordered by the Board was premature in view
    of his pending insurance claim, but the Board was aware of plaintiff’s position and was not
    required to wait several more months to demolish a building that it found, based on the evidence,
    to be unsafe and a danger to the public.
    Finally, plaintiff asserts that the evidence was insufficient to demonstrate that demolition
    was necessary “to protect the public,” that the damage was not “reparable,” and that the damage
    or deterioration involved at least fifty percent of the structure, as required by the ordinance’s
    standard for the demolition of a building.
    As the trial court here noted, the Board’s findings were based on the “extensive testimony”
    and photographic exhibits of a structural engineer, who described the deteriorated condition “of
    the structure generally, its individual components specifically, and the likelihood that the nuisance
    could be abated.” The witness testified to load-carrying rafters and members that were completely
    destroyed, and to damage from the fire and two years of exposure that he characterized as
    substantial and massive and involving over fifty percent of the structure. He described all parts of
    the building as being unsafe, and, when questioned by plaintiff’s attorney, rejected the possibility
    of stabilizing and repairing the existing structure as unreasonable and irresponsible. The witness’s
    testimony was more than sufficient and competent to support the Board’s finding under the
    ordinance that demolition of the building was required. Accordingly, we discern no basis to disturb
    the judgment.
    Affirmed.
    BY THE COURT:
    _______________________________________
    Paul L. Reiber, Chief Justice
    _______________________________________
    John A. Dooley, Associate Justice
    _______________________________________
    Harold E. Eaton, Jr., Associate Justice
    3
    

Document Info

Docket Number: 2016-128

Filed Date: 11/4/2016

Precedential Status: Non-Precedential

Modified Date: 11/4/2016