TransCanada Hydro Ne. Inc. v. Town of Vernon ( 2011 )


Menu:
  • TransCanada Hydro Ne. Inc. v. Town of Vernon, No. 544-10-10 Wmcv (Wesley, J., Aug. 8, 2011)
    [The text of this Vermont trial court opinion is unofficial. It has been reformatted from the original. The accuracy of the text and the
    accompanying data included in the Vermont trial court opinion database is not guaranteed.]
    STATE OF VERMONT
    SUPERIOR COURT                                                                             CIVIL DIVISION
    Windham Unit                                                                               Docket No. 544-10-10 Wmcv
    TransCanada Hydro Northeast Inc.
    Plaintiff
    v.
    Town of Vernon
    Defendant
    Order Denying Plaintiff’s Motion for Summary Judgment
    Plaintiff, TransCanada Hydro Northwest Inc. (“TransCanada”), appeals a property
    assessment made by the Town of Vernon (“the Town”) of the hydropower facility it owns in
    Vernon, Vermont. TransCanada owns and operates a power plant located partially in Vernon,
    Vermont and partially in Hinsdale, New Hampshire. The Town determined the listed value of
    the property to be $32,075,500 as of April 1, 2010. TransCanada challenges this valuation, and
    asserts that the value was established by a determination made by the Director of the Division of
    Property and Review as $25,169,800 as of April 1, 2009. The Director made this valuation
    following an appeal of the Town’s 2009 appraisal.
    TransCanada has moves for summary judgment claiming that the so-called “Freeze Act”
    (32 V.S.A. § 4468) requires that the listed value of the property as of April 1, 2010 be set at the
    value determined by the Director as of April 1, 2009. The Freeze Act provides, in relevant part,
    that:
    “… [an] appraisal so fixed by the director… shall become the basis for the grand list of a
    taxpayer for the year in which the appeal is taken and … for the two next ensuing years.
    … The appraisal however may be changed in the ensuing two years if the taxpayer’s
    property is materially altered, changed, damaged, or if the municipality, city or town in
    which it is located has undergone a complete reevaluation of all taxable real estate.”
    32 V.S.A. § 4468 (emphasis added).
    TransCanada claims, and the Town does not dispute, that no material change to the
    physical structure of the property occurred between April 1, 2009 and April 1, 2010, nor did the
    Town undertake a revaluation of all taxable real estate in Vermont. In the absence of such
    changed circumstances, TransCanada maintains that the 2010 revaluation was in violation of the
    Freeze Act and must be set aside by the Court as a matter of law.
    However, the Town maintains that the Freeze Act is inapplicable here, and that the
    reappraisal was valid and justified. The Town acknowledges that no material change to the
    generating capacity of TransCanada’s power plant has taken place since April 1, 2009, nor does
    it attack the Director’s decision as to the 2009 valuation appeal. Rather, the Town asserts that,
    although significant improvements to the plant’s generating capacity were completed by the time
    of the 2009 appeal, the recognized methodology for fully accounting for the revenue anticipated
    associated with those improvements included a “lag”, such that those anticipated revenues
    increased significantly between April 1, 2009 and April 1, 2010, resulting in a higher assessment
    using the income approach to valuation. The Town insists that this “lag” effect must be
    recognized as a material change that prevents the application of the Freeze Act. The Court
    agrees.
    Factual Background
    The Town supports its claims for disputed and uncontested facts with the affidavit of
    George E. Sansoucy, a licensed engineer and licensed appraiser, who has been employed by the
    Town of Vernon to appraise and assess the power facility for the last fifteen years. Mr.
    Sansoucy explains that the most recent and final phase of an overall site upgrade project, in the
    works for many years, was TransCanada’s replacement of four turbines. The replacement
    resulted in an increase in power generating capacity for the plant. The method of accounting for
    the value to the plant added by the improved generating capacity is at the heart of the current
    dispute.
    As observed in the Director’s opinion as to TransCanada’s appeal of the 2009
    assessment, (“Director’s opinion”), issued on Nov. 16, 2010: “The income approach to value is
    the most appropriate since information on an income stream is available and the cost and market
    approaches are not appropriate for use in this evaluation.” Neither party disputed the use of the
    income approach, then or now; thus, the crux of any dispute as to value turns upon variations in
    the data that are used to generate projected income streams associated with the manufacture of
    electricity. Once projected, those income streams are discounted to present value to establish the
    value of the facilities that produce them. See US Gen New England, Inc. v. Town of
    Rockingham, 
    177 Vt. 193
    , 195-97 (2004) (examining the income capitalization approach to
    valuing a hydro-electric plant).
    Mr. Sansoucy further attests that the universal and customary convention for the
    valuation of public utility property is to base the valuation on the data available as of December
    31st of the next-to-previous year. Thus, with respect to the two years at issue in this case, the
    Town based its assessment for April 1, 2009 on projections from data on the books as of
    December 31, 2007; the Town based its assessment for April 1, 2010 on projections from data on
    the books as of December 31, 2008. This is done for a number of reasons: first, the lag permits
    more effective alignment with quarterly and end of year reporting requirements for utility
    companies, many of which are subsidiaries of larger companies; second, and particularly during
    periods of expansion in capital investment, the lag guards against over-estimating future income
    streams, which may lead to the need for later correction. Mr. Sansoucy states that the convention
    of using data from December 31st of the next-to-previous year is not isolated to TransCanada,
    2
    but is applied to all utilities and power generation facilities in Vernon equally, including the
    Vermont Yankee nuclear plant.
    It is apparent from the Director’s opinion that neither party contested the methodology
    involving reliance on lagged data in the appeal of the 2009 assessment. The Town had assessed
    the plant at $24,779,300 for the generating facilities, plus $390,500 for the value of the land,
    using the income capitalization approach based on an analysis undertaken by Mr. Sansoucy. As
    he indicates in his current affidavit, that analysis relied on income and expense data posted as of
    December 31, 2007. The basis for TransCanada’s appeal, however, was claimed error in: 1)
    failing to properly account for personal property; 2) failing to include certain expected costs for
    relicensing in the income capitalization analysis; and 3) failing to exempt the value of fish ladder
    structures from the taxable property. The Director rejected each of these challenges, finding
    “that the appellant was not able to overcome the presumption of value determined by the Town
    of Vernon for the real property.” Thus, the assessed value established as of April 1, 2009, as
    upheld by the Director, was based on Mr. Sansoucy’s methodology, incorporating the convention
    of reliance on lagged data for revenues and expenses which he claims is standard for the
    industry, and reflected in the history of assessments of the plant by the Vernon listers.
    In making its assessment for April 1, 2010, the listers relied on Mr. Sansoucy’s new
    capitalization analysis, which incorporated revenues and expenses as posted on Dec. 31, 2008.
    Mr. Sansoucy acknowledges that, as compared with the 2007 data used for the 2009 assessment,
    the ISO annual rated capacity of the plant was reduced to 34.4 megawatts from the previous
    rating of 36.79 megawatts. The reduced capacity was employed in the 2010 capitalization
    analysis. As further observed, however:
    The electric energy production was now separated between on-peak and
    off-peak historic production, and on-peak and off-peak qualifying renewable
    energy credit generating production, totaling a combined 191,900,000 kilowatts.
    The energy pricing revenue for the valuation of 2010, as compared to 2009, was
    broken out and forecasted separately for the completion of the 2010 appraisal.
    Most notably, with the final completion of the plant, the additional ancillary
    services revenue generated from the plant, as paid by ISO and reported by the
    company, was also priced into the valuation in 2010 for the first time. The final
    valuation of the entire facility as of April 1, 2010 was $119,500,000.00 which
    constitutes the assessment of the plant as finally completed. The Town of
    Vernon’s 28% share was $35,117,900.00.
    The Town maintains that for many years while its plant has undergone renovation and
    expansion, TransCanada officials and employees have had a mutual understanding with the
    listers as to the benefits of the lag in accounting for posted revenues and expenses. The Town
    observes that this convention actually benefitted TransCanada by delaying its tax exposure, and
    was an arrangement to which officials at TransCanada fully acquiesced. Nevertheless,
    TransCanada disputes any enforceable agreement, either explicit or tacit, to base its assessment
    on lagged data, Moreover, TransCanada argues that, since the Town has produced no written
    agreement, any reliance on a claim arising from oral discussions would violate the statute of
    3
    frauds since it would have extended beyond one year. TransCanada also challenges whether any
    agreement could supersede the plain and unambiguous language of the Freeze Act.
    Analysis
    Pursuant to V.R.C.P. 56(c)(3), a moving party is granted summary judgment when it has
    demonstrated that no genuine issues of material fact exist, and that it is entitled to judgment as a
    matter of law. Kremer v. Lawyers Title Ins. Corp., 
    2004 VT 91
    , ¶7, 
    177 Vt. 553
    (mem.) Here,
    the Court finds a genuine issue of material fact which remains in dispute, and must deny
    Plaintiff’s Summary Judgment Motion.
    As stated above, the Town concedes that the new appraisal made in 2010 was not spurred
    by any material alteration to the physical structure of the power plant, nor to any notable
    improvement made to generating capacity, between April 1, 2009 and April 1, 2010. Rather, the
    Town maintains that TransCanada’s interpretation of the Freeze Act is overly narrow, and that
    non-physical changes and alterations to the valuation of a given property, as reflected by the
    consistent application of the lagged accounting methodology employed in the assessment of the
    plant, also permit the Town to reappraise the property.
    To support this proposition, the Town relies on the Supreme Court’s discussion of the
    Freeze Act in Shetlant Properties Inc. v. Town of Poultney, 
    145 Vt. 189
    (1984). The Court noted
    that the intent of the “freeze” statute was to remedy the practice of repeated yearly increases in
    the assessed value of property, not evidently related to or justified by any changes increasing its
    market value, and resulting in harassment of the taxpayer by subjecting him to the trouble and
    expense of annual appeals. 
    Id. at 193-94
    (citing to similar legislation from New Jersey).
    The Court proceeded to define the “material alteration, change or damage” that is
    required before a Town can reappraise a property within three years of an assessment made by a
    Court or a director, as anything that “is relevant and of consequence to the value of the
    property.” 
    Id. at 194.
    Notably, the Court did not limit “material changes” to merely physical
    alterations to a real property. However, Shetlant Properties involved a distinctly different class
    of property, raising valuation issues considerably at variance with the unique problems posed in
    valuating electric generating facilities, as discussed in US Gen New England, Inc. v. Town of
    Rockingham. Nevertheless, the Court is persuaded that the holding in Shetlant Properties
    supports the conclusion that the economic changes reflected by the Town’s lagged accounting
    methodology is properly recognized as a “material change” which “is relevant and of
    consequence to the value of the property,” and therefore comes within the Freeze Act’s
    exclusions.
    In reaching the conclusion that the Town’s reliance on Mr. Sansoucy’s methodology
    arguably yields a material change exempting the 2010 appraisal from the effect of the Freeze
    Act, the Court is not required to directly address TransCanada’s statute of frauds argument. In
    the Court’s view, whether or not any tacit or explicit “agreement” arose between the parties
    regarding the application of the lagged methodology is not material. Rather, the Court is
    satisfied that the Town has established evidence that this ‘lagged’ methodology is typically
    employed in the valuation of electric generation facilities, and assuming that conclusion is
    4
    sustained after a full hearing, the use of such methodology could produce a material change in
    value that would be properly recognized as exempt from the effects of the Freeze Act.
    To be sure, TransCanada disputes both that the methodology is standard in the trade, and
    that its failure to appeal earlier appraisals represents an acknowledgment of the typicality of the
    approach, or acquiescence to its use in the future. However, such a dispute as to whether or not
    the lagged data approach was widespread and typical to the industry is material to the valuation
    issue here, and prevents summary judgment - distinct from any claim that Transcanada should be
    precluded from challenging the appraisal based on an agreement to be bound by the methodology
    that produced it. Furthermore, although not squarely informative of any claim of “contract”
    rights between the parties, evidence of past patterns and practice, including conversations,
    meetings and memoranda, may conceivably bear on the question as to whether or not it was
    reasonable for the Town to rely on the lagged data method of valuation.
    In sum, if after consideration of all the evidence, the Town establishes the reasonableness
    of its valuation methodology, and that the application of such a methodology produces a material
    change in the value of TransCanada’s plant between 2009 and 2010, the Court may very well
    conclude that such an appraisal is not precluded by the Freeze Act. Accordingly, at this time,
    summary judgment in favor of Plaintiff is inappropriate.
    ORDER
    WHEREFORE it is hereby ORDERED: Plaintiff’s Motion for Summary Judgment is
    DENIED.
    Dated at Newfane, Vermont this 8th        day of August, 2011.
    _____________________________
    Hon. John P. Wesley
    Presiding Judge
    5
    

Document Info

Docket Number: 544

Filed Date: 8/8/2011

Precedential Status: Precedential

Modified Date: 4/24/2018