McCullough Crushing, Inc. Act 250 ( 2016 )


Menu:
  •                                    STATE OF VERMONT
    SUPERIOR COURT                                    ENVIRONMENTAL DIVISION
    McCullough Crushing, Inc. A250 Expansion                     Docket No. 3-1-10 Vtec
    McCullough Crushing, Inc. Amended CU                    Docket No. 179-10-10 Vtec
    Decision on Motions to Alter/Amend
    McCullough Crushing, Inc. (MCI) seeks an Act 250 land use permit amendment and
    municipal conditional use approval for the expansion of an existing quarry operation in Calais,
    Vermont. MCI’s Act 250 permit and conditional use applications were appealed to this Court and
    we coordinated our review in a multi-day trial. On June 24, 2016, we issued a decision on the
    merits approving, with conditions, the Act 250 permit amendment and conditional use
    applications.
    Now before the Court are motions to alter and amend our decision in both matters filed
    by MCI and by a group of neighbors opposed to the project (collectively, Appellants). The
    motions to alter and amend solely concern Condition #2 of our decision, which states, “The
    Western Expansion must preserve the existing tree line within the Rathburn field. MCI shall
    maintain, at a minimum, a 30-foot setback from the height of land and/or tree line, whichever
    limitation imposes a more north and easterly limit on the Western Expansion.”
    MCI argues that an amended decision is needed to clarify Condition #2 because it is
    unclear what natural features the Court intended to be the limitation for the western expansion
    area of the proposed operation. MCI also suggests that Condition #2 unreasonably restricts the
    extraction operation as it will only allow a small percentage of the material that was originally
    sought by the proposed project to be extracted. Appellants assert that an amended decision is
    necessary and that the evidence should be reopened to allow Appellants to present necessary
    evidence to clarify and effectively implement Condition #2, including a revised site plan to
    effectively mark the expansion limit and buffer, evidence about the adequacy of the 30-foot
    buffer to preserve the tree health, and evidence concerning replanting requirements should
    parts of the required buffer be impacted. Appellants also request that we remand the matter to
    the District #5 Environmental Commission and the Calais Development Review Board so they may
    reissue the Act 250 and conditional use permits incorporating the clarified condition.
    Rule 59(e) gives this Court broad power to alter or amend a judgment “if necessary to
    relieve a party against the unjust operation of the record resulting from the mistake or
    inadvertence of the court and not the fault or neglect of a party.” Rubin v. Sterling Enterprises,
    Inc., 
    164 Vt. 582
    , 588 (1996); Reporter’s Notes, V.R.C.P. 59(e). There are four principal reasons
    for granting a Rule 59(e) motion: (1) “to correct manifest errors of law or fact upon which the
    judgment is based”; (2) to allow a moving party to “present newly discovered or previously
    unavailable evidence”; (3) to “prevent manifest injustice”; and (4) to respond to an “intervening
    1
    change in the controlling law.” 11 Wright, Miller & Kane, Federal Practice and Procedure: Civil
    3d § 2810.1; see In re Zaremba Group Act 250 Permit, No. 36-3-13 Vtec, slip op. at 1 (Vt. Super.
    Ct. Envtl. Div. Apr. 10, 2014) (reviewing Rule 59(e) motion using the four factors outlined in the
    federal rule). A motion to alter or amend “a judgment after its entry is an extraordinary remedy
    which should be used sparingly.” Zaremba, No. 36-3-13 Vtec, at 2 (quoting 11 Wright, Miller &
    Kane, Federal Practice and Procedure: Civil 2d § 2810.1). Rule 59(e) motions are not intended as
    a means to reargue or express dissatisfaction with the Court’s findings of fact and conclusions of
    law, and a motion to alter or amend will be denied where it merely repeats arguments that have
    already been raised and rejected by the Court. See 11 Wright, Miller & Kane, Federal Practice &
    Procedure: Civil 3d § 2810.1.
    Central to both parties’ motions is the request to alter our decision in order to clarify
    Condition #2. In our merits decision, we were limited by the evidence provided and attempted
    to craft a written condition that would effectively mitigate the adverse impacts of the quarrying
    operation. We are not opposed to allowing limited additional evidence to clarify Condition #2
    and to ensure that all parties agree on the actual on-the-ground delineation of the western
    expansion parcel limits. To this end, the parties have entered into a stipulated settlement
    agreement that clarifies Condition #2. The settlement includes a site plan, last revised February
    9, 2017, which depicts the 30-foot buffer zone. The settlement further calls for the pit expansion
    and related buffer zone to be surveyed, and for that survey to be filed with the Town of Calais
    and to become an exhibit to the Act 250 and conditional use approvals. The actual buffer area
    will also be physically marked consistent with the survey. MCI will maintain the buffer area under
    the terms of the settlement agreement.
    In light of this agreement, the motions to alter are GRANTED in part insofar as they seek
    to clarify Condition #2 and admit the revised site plan depicting Condition #2 into evidence. We
    will issue an amended decision incorporating and referencing the settlement agreement and site
    plan.
    Beyond the question of clarification, Applicant suggests that Condition #2 is overly
    restrictive, while Appellants claim that it is insufficient. We disagree with both parties, and to
    the extent the parties’ motions ask us to curtail or expand the condition, those requests are
    DENIED. This includes Appellants’ request to allow additional evidence concerning the adequacy
    of the buffer to preserve tree health and appropriate replanting plans. Our approval requires
    MCI to maintain the tree line and a 30-foot buffer consistent with the terms of the settlement
    agreement. If MCI negatively impacts the buffer or tree line it will have violated Condition #2.
    While Appellants may wish to impose greater limitations on the quarry operation, our intent in
    Condition #2 was not to eliminate any and all view or noise from the operation; but rather, to
    appropriately mitigate the quarry’s impact on the Rathburn Field area and the area of Balentine
    and Batten Roads. Appellants have not demonstrated that Condition #2 fails to do this, and thus,
    we deny the remainder of their motion to alter and amend.
    2
    An Altered Merits Decision and Altered Judgment Order accompanies this Entry Order. This
    concludes the matter before the Court.
    Electronically signed on February 16, 2017 at 10:50 AM pursuant to V.R.E.F. 7(d).
    _________________________________________
    Thomas G. Walsh, Judge
    Superior Court, Environmental Division
    3
    

Document Info

Docket Number: 3-1-10 Vtec

Filed Date: 2/16/2016

Precedential Status: Precedential

Modified Date: 4/24/2018