Appeal of Angelino ( 2003 )


Menu:
  •                                      STATE OF VERMONT
    ENVIRONMENTAL COURT
    Appeal of Richard Angelino       }
    }
    }     Docket No.261-11-02 Vtec
    }
    }
    Decision and Order on Cross-Motions for Summary Judgment
    Appellant Richard Angelino appeals from a decision of the Zoning Board of Adjustment (ZBA)
    of the Town of Underhill, denying his application for a variance from the streambank setback
    requirements of the Zoning Regulations. Appellant is represented by Donald B. Maddocks, Esq.
    and the Town is represented by Paul Gillies, Esq.
    Appellant= s Statement of Questions, as amended, raised the following five issues: 1) whether
    the ZBA timely rendered a decision under 24 V.S.A. ' 4470(a); 2) whether the ZBA= s written
    decision included sufficient findings of fact; 3) whether the definitions of the terms > stream=
    and > streambank= are sufficiently defined in the Zoning Regulations, and, if so, whether
    Appellant= s land falls within that definition; 4) whether the answer to the first three questions
    requires the so-called deemed approval of Appellant= s application under 24 V.S.A. ' 4470(a);
    and 5) whether the ZBA considered Appellant= s new camp as a replacement of a pre-existing
    structure which had a septic system installed prior to the adoption of > Septic Regulations= in
    the Town. We note that Appellant did not challenge the merits of the ZBA= s denial of his
    variance application; that is, Appellant does not claim that the application in fact meets all five of
    the criteria for a variance to be granted.
    The following facts are undisputed unless otherwise noted. Appellant owns an approximately 15-
    acre parcel of land located in the Town of Underhill at 40 Downs Road. For the purposes of this
    decision, we will assume that a sugar house existed on the parcel prior to the adoption of the
    Zoning Regulations in 1963, and that the sugar house was not used for human habitation prior to
    the adoption of IX(L)(1) of the Zoning Regulations.
    Approximately in 2000 or 2001, Appellant constructed a 12 -story camp (seasonal residential
    building), on a foundation of concrete piers (sonotubes), connected to a 300-gallon septic tank1
    and approximately 100 feet of leach line, but not served by electricity. The new camp building is
    located approximately 20 feet from the bank of a watercourse passing through the property. The
    watercourse only contains water on a seasonal basis. The parties seem to dispute whether
    Appellant at some time diverted the course of the water flowing through that watercourse, but the
    issue of diversion is not necessary to the decision of the present appeal. Appellant did not obtain
    a zoning permit prior to constructing the camp.
    Section IX(L)(1) of the Zoning Regulations requires that A no structure for human habitation or
    septic systems will be permitted within 100 feet of the streambank of any watercourse.@
    Reading together the definitions of the terms > stream,= > streambank,= and > watercourse,= all
    of which are defined in the Zoning Regulations, the term > watercourse= includes A any river,
    stream, brook, waterway, lake, pond, marsh, swamp, bog, wetland or other body of water, natural
    or artificial, public or private;@ and includes A any depression two feet or more below the
    elevation of surrounding land serving to give direction to a current or flow of water having a bed
    and a well-defined bank.@
    After the existence of the camp came to the attention of the zoning authority, on June 26, 2002,
    Appellant applied for an 80-foot variance from the 100-foot streambank setback of ' IX(L)(1).
    Appellant did not request a ruling that the camp or its septic system was exempt from ' IX(L)(1)
    as a pre-existing non-conforming structure or use under ' IX(G) or (H), and did not apply for
    approval of the ZBA to modify the structure or the use under those sections.
    The ZBA held a public hearing on the matter on August 12, 2002, concluded the hearing the
    same day, and entered into deliberative session to discuss Appellant= s application. The ZBA
    voted to continue the deliberative session at its next meeting on September 9, 2002. At the
    September 9, 2002 meeting, the ZBA voted to deny Appellant= s request for a variance. The
    ZBA approved a written decision and it was signed by the ZBA Chair on September 23, 2002,
    but the Clerk of the ZBA failed to send out the approved written decision to Appellant until
    eighteen days later, on October 11, 2002, when she discovered it among a pile of papers,
    endorsed it with the October 11, 2002 date, and immediately mailed it to Appellant.
    The ZBA rendered a timely decision under 24 V.S.A. ' 4470(a) on September 9, 2002, when it
    voted to deny Appellant= s request for a variance. Its written decision approved and signed on
    September 23, 2002 was also timely under ' 4470(a). The only question is whether the clerk= s
    failure to send it out until 18 days later, approximately two weeks after the expiration of the 45-
    day time period, should result in deemed approval of the variance. It should not. As in Leo= s
    Motors, Inc. v. Town of Manchester, 
    158 Vt. 561
    , 564 (1992), the defect in the ZBA= s action
    was in not sending the written notice in a timely fashion to the landowner. The circumstances of
    this case do not reflect any ZBA indecision or protracted deliberations for which the remedy of
    deemed approval would be appropriate. See, e.g., Appeal of Newton Enterprises, 
    167 Vt. 459
    ,
    465 (1998); Appeal of Ashline, 14 Vt. L. Week 114 (March 28, 2003).
    The ZBA= s decision includes findings of fact. Even if these findings were insufficient to
    support the ZBA= s variance denial decision, that insufficiency would not result in a deemed
    approval of the application. Rather, in an appeal in which the ZBA= s conclusions on the
    variance criteria were contested, the Court would consider the evidence de novo as to whether
    the application met the criteria for a variance. In an extreme case, if there are no findings of fact
    at all, a case can be remanded to a municipal board for it to render a decision with adequate
    findings. But if a timely decision was made, however inadequate the findings, the deemed
    approval remedy would not be available.
    The terms > stream,= > streambank,= and > watercourse= are sufficiently defined in the Zoning
    Regulations to allow the ZBA or this Court to determine whether a watercourse on any particular
    applicant= s property triggers the setback requirements of ' IX(L)(1). Even if they were not
    sufficiently well-defined, that lack would not result in a deemed approval of a variance
    application. We note that in the present case, the parties have not provided the Court with
    undisputed facts about whether the watercourse on Appellant= s land is two feet or more below
    the elevation of surrounding land, with a bed and a well-defined bank. Assuming that it is a well-
    defined watercourse but that water only runs in it on a seasonal basis, it meets the definitions in
    the regulations to trigger the setback requirements of ' IX(L)(1), as nothing in the text or the
    logic of any of the regulatory sections exempts seasonal streams or watercourses. More
    importantly for this appeal, however, Appellant did not challenge the determination that '
    IX(L)(1) is applicable to his property. Rather, he applied for a variance from that provision. All
    that was before the ZBA was whether his application met all five requirements for the issuance
    of a variance, not whether the seasonal stream qualifies as a watercourse under that definition.
    Thus, as restated under the heading of Question 4, the answers to the first three questions of
    Appellant= s Statement of Questions do not result in the so-called deemed approval of
    Appellant= s application under 24 V.S.A. ' 4470(a).
    With regard to Question 5, Appellant did not apply to the ZBA for approval of his new camp
    under ' IX(H)(1) as a replacement of a pre-existing structure which had a septic system installed
    prior to the adoption of > Septic Regulations= in the Town, and therefore that question was not
    before the ZBA and is not before the Court. However, we note that all that could have been
    replaced under that theory would have been a sugar house. Appellant= s replacement of a sugar
    house with a structure for human habitation required the new structure to meet ' IX(L). Appellant
    would have to have shown that the prior structure had been used for human habitation at the time
    that ' IX(L) was adopted, in order for it to qualify for treatment as a pre-existing nonconforming
    structure or use. Moreover, even if the sugar house had a pre-existing septic system that predated
    the Town= s septic regulations and might be grandfathered with respect to ' IX(K), it would still
    be subject to ' IX(L) unless it predated the zoning regulations= adoption of ' IX(L).
    Accordingly, based on the foregoing, it is hereby ORDERED and ADJUDGED that Appellant= s
    Motion for Summary Judgment is DENIED and the Town= s Motion for Summary Judgment is
    GRANTED, concluding this appeal.
    Done at Barre, Vermont, this 22nd day of May, 2003.
    ___________________
    Merideth Wright
    Environmental Judge
    Footnotes
    1.
    Appellant’s Question 5 only asserts that the septic system was installed prior to the
    adoption of municipal septic regulations, not that it existed prior to the adoption of the zoning
    regulations. Although the date of the installation of the septic system may be disputed, or at least
    has not been provided to the Court, that fact is not material to this appeal, for the reasons
    discussed below regarding Question 5.
    

Document Info

Docket Number: 261-11-02 Vtec

Filed Date: 5/22/2003

Precedential Status: Precedential

Modified Date: 4/24/2018