Sheffield Wind Project ( 2010 )


Menu:
  •                                  STATE OF VERMONT
    SUPERIOR COURT                                          ENVIRONMENTAL DIVISION
    Docket No. 252-10-08 Vtec
    }
    In re Sheffield Wind Project                    }
    Amended Individual Stormwater Permit           }     Docket No. 252-10-08 Vtec
    (No. 5535-INDC.A)                        }
    (Appeal of Brouha et al.)                }
    }
    Decision and Order on Motion for Stay
    The Court issued a decision on August 26, 2010, approving an amended
    individual construction stormwater discharge permit; this permit is applicable only to
    the period during construction of the Sheffield Wind Project (the Project) in Sheffield,
    Vermont.1 Appellants moved for reconsideration of that decision. While that motion
    was pending, Vermont Wind proceeded with the logging work that the Court had ruled
    was not governed by the individual construction stormwater permit, and began
    construction of the project. Appellants have now moved to stay construction of the
    project pending the Court’s ruling on the motion for reconsideration and pending
    Appellants’ filing of an appeal to the Supreme Court. If the motion for stay is denied,
    Appellants request the Court to “at least require more frequent and unannounced
    inspections by ANR” and to “order First Wind and ANR to continue to disclose to
    Appellants all documentation of activities at the site, including changes to the EPSC
    Plan.”
    Appellants are represented by Stephanie J. Kaplan, Esq., and Jared M. Margolis
    1
    The permitting status quo of this project is that it holds other permits and approvals
    from the Public Service Board and the Vermont Agency of Natural Resources (ANR)
    that were not appealed, including the ANR’s approval of the project’s operational
    stormwater discharge management system.
    1
    Esq.; Appellee-Applicants Signal Wind Energy, LLC and Vermont Wind, LLC (referred
    to in the singular as “Vermont Wind” or “First Wind”) are represented by Ronald A.
    Shems, Esq., Andrew N. Raubvogel, Esq., Geoffrey H. Hand, Esq., and Elizabeth H.
    Catlin, Esq. The Vermont Agency of Natural Resources (ANR) is represented by Judith
    L. Dillon, Esq.
    Vermont Wind, LLC proposes to construct and operate a wind electrical
    generating facility (the Project) on property on Granby Mountain and Libby Hill in
    Sheffield, Vermont, near the headwaters of small unnamed tributaries of Calendar
    Brook, Nation Brook, Annis Brook, Willoughby Brook, and Clark Brook.
    The Project consists of an array of sixteen wind turbines, each located on a
    concrete pad, along a 16-foot-wide access roadway.          The project also includes a
    permanent meteorological tower, which appears on the project plans and narrative but
    was not specifically at issue during trial. During construction, the access roadways will
    be constructed to the 25-foot width necessary for crane access for the equipment used to
    erect the wind turbine structures; at the conclusion of the need for crane access, the
    Project’s permanent roadways will be reduced to the 16-foot width by seeding and
    mulching the areas outside that width.
    An electrical substation and a small operations and maintenance building are
    also proposed as part of the Project. They are located on the lower portion of the
    property, on either side of the project access road, near the public roadway. Electricity
    will be conducted by underground and above-ground transmission lines from the
    turbines down to the electrical substation. The Project is located adjacent to and will tie
    into an existing VELCO electrical transmission line. The overall property on which the
    Project is located consists of approximately three thousand acres leased from
    Meadowsend Timberlands, some of which has been logged in the past. The Project is
    proposed to follow the path of existing logging roads and to use already-cleared areas
    2
    to the greatest extent possible.
    The permanent operational stormwater system for the project was approved in a
    separate permit and was not appealed. This consists of a system of berms, channels,
    check dams, detention ponds, and other stormwater control features designed to direct
    and slow the flow of stormwater from the site, to prevent sediment and contaminants
    from reaching streams.
    As described more fully in the August 26, 2010 Decision and Order, in the
    present application for approval of an erosion prevention and sediment control plan to
    control discharges due to stormwater during the construction of the project, Applicant
    proposed to construct and install the permanent stormwater control features approved
    for the project’s operation in advance of construction of each segment of the project that
    would drain into those features. In addition to these permanent engineering features,
    Applicant proposed temporary features, such as silt fencing, and proposed a series of
    methodologies to minimize the risk of erosion and sediment transport during
    construction, including limitations on the construction area open at any time,
    limitations on the length of time an area may remain open, and monitoring techniques
    that require additional measures to be taken, including stopping construction, if
    sediment in stormwater runoff is not successfully controlled using the required
    engineering features and other techniques.
    Standards for Issuing a Stay
    Under V.R.E.C.P. § 5(e), when a stay is not automatically issued under 10 V.S.A.
    § 8504(f)(1), the Court, on its own motion or the motion of a party, may issue a stay to
    preserve the rights of the parties “upon such terms and conditions as are just.” The
    3
    present case is not automatically stayed under the provisions of 10 V.S.A. § 8504(f)(1)2,
    nor is it an appeal of a municipal land use or zoning permit subject to an automatic stay
    under 24 V.S.A. § 4449. Appellants also did not request a stay of the ANR-issued
    permit during the twenty-two months that the ANR-issued permit was in effect and the
    litigation was pending before this Court.
    Appellants’ current motion for an emergency stay now seeks to stay the permit
    as issued by the Court, first, during the pendency of Appellants’ motion to alter under
    V.R.C.P. § 59(e) and, if that motion is denied, pending the outcome of their appeal to the
    Supreme Court.
    To prevail on a motion for a stay, the movant must demonstrate: (1) a strong
    likelihood of success on the merits; (2) irreparable injury if the stay is not granted; (3)
    that the stay will not substantially harm other parties; and (4) that the stay will serve the
    best interests of the public. Gilbert v. Gilbert, 
    163 Vt. 549
    , 560 (1995). Appellants must
    demonstrate all four of these elements for the stay to be granted. See In re: Champlain
    College, Inc., Docket No. 145-7-05 Vtec, slip op. at 2 (Vt. Envtl. Ct. Apr 17, 2007)
    (Wright, J.); In re: Route 103 Quarry, Docket No. 205-10-05 Vtec, slip op. at 3 (Vt. Envtl.
    Ct. Sept. 14, 2007) (Durkin, J.) aff’d In re: Route 103 Quarry, 
    2008 VT 88
    , 
    184 Vt. 283
    (citing Gilbert v. Gilbert, 
    163 Vt. 549
    , 560 (1995)). Under V.R.A.P. § 8(b), the granting of
    a stay pending the outcome of an appeal to the Supreme Court may be conditioned
    upon the filing of a bond with the trial court. Similarly, under V.R.E.C.P. § 5(e), the
    Court may require Appellants to post a bond, under its authority to “make such other
    orders as are necessary to preserve the rights of the parties.”        Vermont Wind has
    requested that the Court require such a bond in the event that the requested stay is
    2
    With regard to appeals from decisions of the ANR, 10 V.S.A. § 8504(f)(1) provides for
    an automatic stay only in appeals of stream alteration permits and shoreline
    encroachment permits. Section 8504(f)(1) also provides for automatic stays in appeals of
    the denial of interested person status by a municipal panel. Otherwise, permits that
    have been appealed are in effect unless the Court grants a stay under § 8504(f)(2).
    4
    granted.
    Appellants have not demonstrated a strong likelihood of success on the merits.
    or irreparable injury if the stay is not granted. The Court’s August 26, 2010 Decision
    carefully analyzed all of the issues remaining in this appeal after trial, and concluded
    that the issuance of the construction stormwater permit, substantially as it had been
    issued by the ANR, was warranted.         Although the Court’s ruling on the pending
    motion for reconsideration may result in clarification or further analysis of certain
    issues, it is not likely to result in a different outcome on the merits of the construction
    stormwater permit.
    Appellants have not demonstrated irreparable injury if the stay is not granted.
    Given that the permanent unappealed stormwater features are incorporated into the
    construction stormwater permit, the question is whether irreparable injury will result
    during construction due to the temporary stormwater features and iterative monitoring
    and adjustment process that appear in the permit on appeal. Based on the extensive
    evidence as to how these features are designed to work during construction, and the
    iterative process in which adjustments are made in the field if problems arise,
    irreparable injury such as a catastrophic failure of the stormwater features is not likely
    to occur.
    Unlike a project that has been denied a permit and in which an applicant has
    appealed, or even a project that has been granted permits but for which all the required
    permits are within the scope of the appeal, in the present case the project holds all of its
    required permits, and only its individual construction stormwater permit is the subject
    of this appeal. That is, the “status quo” against which the Court must assess the motion
    for stay is that the project holds unappealed permits allowing the project, including the
    operational stormwater permit containing the stormwater detention ponds and other
    features to manage stormwater after the project is built. Applicant has shown that a
    stay of construction at this time would substantially harm it financially. Such harm
    5
    would not, of course, be irreparable, but could warrant a bond under V.R.A.P. 8 if a stay
    were to be granted.
    Finally, Appellants have not shown that the best interests of the public warrant a
    stay. The project holds its required permits so that its existence is not at issue in this
    appeal. The permit at issue in this litigation only governs the protection of the public
    interest in the surrounding streams during construction.           Based on the evidence
    presented at trial, the Court is convinced that the best interests of the public require
    strict adherence to the terms of the permit during construction, but do not warrant the
    imposition of a stay.
    Accordingly, based on the foregoing, Appellants’ motion to stay construction is
    DENIED. Due to this decision, it is not necessary to address Vermont Wind’s request
    for the posting of a bond.          The Court will address the pending motion for
    reconsideration as soon as possible.
    Appellants’ request for continuing disclosure of documentation
    As explained by the Vermont Supreme Court, during the pendency of litigation
    the Legislature exempted disclosure of public documents relevant to the ongoing
    litigation, reserving decisions regarding such disclosure to the trial judge in the pending
    litigation to avoid giving litigants “an unwarranted advantage . . . in litigation with the
    government.” Wesco, Inc. v. Sorrell, 
    2004 VT 102
    , ¶¶ 17–22, 
    177 Vt. 287
     (quoting
    Killington, Ltd. v. Lash, 
    153 Vt. 628
    , 646 (1990)). However, no further evidentiary
    hearing will occur in the present litigation; it will be out of the purview of the trial court
    as soon as the motion for reconsideration is addressed. As in this Court’s decision in
    Agency of Natural Resources v. Mountain Valley Marketing, Inc., et al. , Docket Nos.
    Docket Nos. 41-2-02, 278-12-02, 176-8-02, 175-8-02, Decision and Order on Motion to
    Compel, slip op. at 3 (Vt. Envtl. Ct. July 7, 2003) (Wright, J.), to facilitate Appellants’
    rights to monitor the implementation of permits in which they have a legitimate
    6
    interest, they are entitled to any information that would have been available to them
    under Vermont’s Access to Public Records law had this litigation not been pending. In
    particular, Appellants should be given (or be given access to) documentation of any
    changes to the EPSC Plan made in the field during the construction process; such field
    changes are specifically provided for in the permit. The parties shall comply with
    V.R.C.P. 26(h) before bringing any further problems with such disclosure or access to
    the attention of the Court.
    Done at Berlin, Vermont, this 17th day of November, 2010.
    _________________________________________________
    Merideth Wright
    Environmental Judge
    7
    

Document Info

Docket Number: 252-10-08 Vtec

Filed Date: 11/17/2010

Precedential Status: Precedential

Modified Date: 4/24/2018