Michael Durland, App/cross Resp v. Wes Heinmiller & Alan Stameisen, Cross Resp ( 2012 )


Menu:
  •            IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON
    'J> o
    MICHAEL DURLAND, KATHLEEN                                                           -C      m
    FENNELL, and DEER HARBOR                         No. 67429-3-                       x*»
    •zo
    o
    O-T-;
    ~H   '
    BOATWORKS,                                                                          ro
    •fc*t
    'J>~c
    rn
    Appellants,                                                    x**>
    IX      -i. J>
    -,-r-
    ORDER GRANTING MOTION              ——
    ow
    #-
    v.                                         TO PUBLISH OPINION                 ro
    —"'Ct2
    cr.     ".:'    -
    SAN JUAN COUNTY, WES
    HEINMILLER, and ALAN STAMEISEN,
    Respondents.
    Appellants, Michael Durland, Kathleen Fennell, and Deer Harbor Boatworks
    (collectively, Durland) moved this Courtto publish, in part, the unpublished decision filed
    in this matter on October 29, 2012 and the respondents San Juan County, Wes
    Heinmiller, and Alan Stameisen filed an answer to the motion to publish.
    A majority of the panel has determined the motion to publish should be granted.
    Now, therefore, it is hereby
    IT IS ORDERED
    That the appellants' motion to publish the opinion is granted.
    DATED this ^ ^ clay of 'JJOo^rch^                        2013.
    FOR THE PANEL:
    Ujx\     MS.
    esiding Judge
    Judc
    IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON
    MICHAEL DURLAND, KATHLEEN
    FENNELL, and DEER HARBOR                       No. 67429-3-1
    BOATWORKS,
    Appellants,                DIVISION ONE
    SAN JUAN COUNTY, WES                               PUBLISHED OPINION
    HEINMILLER, and ALAN STAMEISEN,
    Respondents.               FILED: October 29. 2012
    __     _l£
    Spearman, A.C.J. — Under the Land Use Petition Act, chapter 36.70Co
    RCW (LUPA), a petition challenging a land use decision must be filed within & -=2
    days of the issuance of the land use decision. Furthermore, a party may not -±      ~p
    collaterally challenge a land use decision for which the appeal period has pa@ed§:~
    through a challenge to a subsequent land use decision. The main question
    presented in this appeal is whether compliance plans between respondent San
    Juan County and respondents Wesley Heinmiller and Alan Stameisen (Heinmiller
    and Stameisen referred to collectively as "Heinmiller") were "land use decisions"
    under LUPA. If they were, the appellants, Michael Durland, Kathleen Fennel, and
    Deer Harbor Boatworks (collectively, "Durland"), are barred from raising certain
    issues in their LUPA petition because they did not bring a LUPA petition
    challenging the compliance plans within 21 days. Other issues on appeal and
    cross-appeal are whether the County properly calculated the pitch for a proposed
    No. 67429-3-1/2
    roof on Heinmiller's barn; whether the County properly calculated the "living area"
    of an alternative dwelling unit (ADU) constructed inside the barn; and whether the
    superior court erred in awarding statutory costs to Durland.
    We hold that the compliance plans in this case were not land use
    decisions because they were not final determinations that left nothing open to
    further dispute. We also hold that while the County did not err in calculating roof
    pitch because the relevant code provision did not specify how to measure pitch,
    the County did err in calculating living area because the relevant code provisions
    were not ambiguous and did not allow for exclusion of areas with a ceiling height
    below five feet. We find no abuse of discretion in the award of statutory costs to
    Durland.
    FACTS
    Durland owns property in Deer Harbor on Orcas Island, in San Juan
    County, which is currently used as a boat yard and marina. Heinmiller's
    predecessor-in-interest, William G. Smith, owned the property adjacent to and
    south of the Durland property ("Heinmiller property"). In 1981, the County issued
    a building permit for a storage barn to Smith. The permit approved a barn that
    was to be built ten feet from the property line shared with the Durland property.1
    A barn was constructed that year. In 1990, Durland sought a conditional use
    permit and a shoreline permit. A property line survey revealed that the barn on
    1San Juan County Resolution No. 224, in effect at that time, required the barn to be at
    least ten feet away from the property line.
    No. 67429-3-1/3
    the Heinmiller property was in fact located only 1.4 feet from the property line. To
    address this issue, Durland and Smith executed a "Boundary Line Agreement
    and Easement" that prevented Durland from building within 20feet of the barn.2
    Around 1995, Heinmiller purchased the property from Smith. In 1997, he
    converted a portion of the barn to an ADU but did not secure any building or
    shoreline permits for this work, in violation of San Juan County Code (SJCC)
    requirements. In 2008, Heinmiller filed an application for an upland conditional
    use permit seeking authorization to use the ADU as a vacation rental unit.
    Because of the application, the County became aware of the ADU conversion. In
    February 2008, the County issued a "notice of correction" to Heinmiller, requiring
    the ADU to be demolished.3
    Heinmiller negotiated with the County regarding the notice of correction.
    The County agreed to allow him to seek after-the-fact permits for the ADU before
    requiring demolition. Accordingly, on April 25, 2008, Heinmiller and the County
    executed an agreed compliance plan ("compliance plan"). The compliance plan
    included a section titled "Correction of Violations and Compliance Schedule" that
    outlined what actions were necessary to bring the property into compliance with
    2The agreement established a common boundary line and, because the new line did not
    correct the barn's location with respect to setback requirements, created a 20-foot-wide
    "easement" (actually a restrictive covenant) on Durland's property that terminated upon the
    removal or destruction of the barn. Durland agreed to the restrictive covenant because he saw a
    benefit from the barn, which provided a buffer between his industrial property and any residential
    uses on the far side of the barn. He did not, however, want the barn to be used for residential
    purposes for fear of conflicts with the industrial use of his property.
    3The notice of correction is not in the record. The County hearing examiner's opinion
    indicates that before the compliance plans were entered into, the County required the ADU to be
    destroyed.
    3
    No. 67429-3-1/4
    the SJCC. It also stated, in the "Background" section, that the County recognized
    that the private restrictive covenant brought the barn into conformance with the
    ten-foot setback requirement that applied when the barn was constructed.
    One year later, on April 28, 2009, the County and Heinmiller executed a
    supplemental agreed compliance plan ("supplemental compliance plan"; both
    plans will be referred to collectively as "compliance plans"). The supplemental
    compliance plan stated that Heinmiller could avoid the need for a shoreline
    substantial development permit and a conditional use permit if certain steps were
    taken, including reducing the height of the barn to 16 feet4 Heinmiller planned to
    reduce the height of the barn by reconfiguring the peak ofthe gable roof to create
    a flat portion.
    On June 4, 2009, Durland filed an administrative appeal of the
    supplemental compliance plan with the County. In a June 8, 2009 letter to
    Durland, the county planning director wrote:
    I write to inform you that there is no administrative appeal process
    for a neighbor to challenge a Compliance Plan or Amended
    Compliance Plan. A Compliance Plan is a code enforcement tool
    that is available to the Administrator to assure compliance with the
    County Code and is authorized by SJCC 18.100.040(d). Code
    Enforcement is a matter between the County and the offender and
    is not subject to administrative appeal by a neighbor.
    Clerk's Papers (CP) at 3-4. On August 13, 2009, the County hearing examiner
    dismissed Durland's appeal on the basis that it was filed one day late.
    4SJCC 18.50.330(E) exempts certain structures from shoreline permitting requirements if
    the structure is no taller than 16 feet.
    4
    No. 67429-3-1/5
    Heinmiller applied for a building permit, change-of-use permit, and ADU
    permit as contemplated by the compliance plans.5 The County approved the
    permits on November 23 and 24, 2009. On December 11, Durland filed an
    administrative appeal challenging the permits. He raised the following issues:
    1. Whether the permits are consistent with regulations regarding
    land developed in violation of local regulations.
    2. Whether the barn complies with setback requirements.
    3. Whether the barn complies with building width limitations for
    properties with shoreline frontage.
    4. Whether the barn complies with waterfront setback requirements
    for accessory structures.
    5. Whether the appropriate shoreline approvals, such as a
    shoreline conditional use permit, substantial development permit, or
    shoreline exemption have been obtained.
    6. Whether the ADU complies with the living area limitation of 1,000
    square feet.
    7. Whether the barn complies with roof pitch requirements in the
    Deer Harbor Hamlet Plan.
    See CP at 68-69.
    The County hearing examiner considered Durland's appeal at an
    evidentiary hearing on May 6, 2010. The hearing examiner determined that the
    compliance plans were land use decisions subject to LUPA's requirement that
    appeals be filed within 21 days of issuance. He concluded the compliance plans
    had resolved certain issues that were now time-barred and could not be raised in
    an appeal of the permits. With respect to the ADU permit, however, he concluded
    5Durland contends he actively participated in the County's review process for these three
    permits, but his citations to the record do not show participation during the review process. The
    record reflects that on October 6, 2007, Durland sent an email to SJC Community Development
    and Planning raising various concerns about Heinmiller's ADU application, but this was well
    before the date of the compliance plans. Also, in Durland's notice of appeal to the hearing
    examiner, he stated that "[appellants have participated in the administrative review process
    leading up to issuance of the challenged permits." CP at 68. The record is unclear as to the
    nature and extent of Durland's participation in the permit review process.
    5
    No. 67429-3-1/6
    that the compliance plans "do not substitute for ADU review and approval" and
    addressed the living area issue on the merits. He found that the ADU complied
    with the 1,000-square-foot living area limit set forth in the SJCC, reasoning that
    "living area" did not include spaces where the ceiling height was less than five
    feet. As for whether the barn complied with roof pitch requirements, the hearing
    examiner concluded:
    As noted in the current version of the Deer Harbor Hamlet Plan
    (adopted 2007), specific regulations for the Deer Harbor area were
    only first put together in 1999, which was well after the building was
    constructed in 1981. The pitch requirement referenced by the
    appellant. . . was adopted in 2007. As a nonconforming use, the
    subsequently enacted Deer Harbor roof pitch requirements do not
    apply.
    CP at 32.
    Durland appealed the hearing examiner's decision by filing a LUPA
    petition in Skagit County Superior Court on August 13, 2010. The court
    concluded that the compliance plans were land use decisions under LUPA and
    that Durland's challenge to the permits largely amounted to a collateral attack on
    the compliance plans. The court dismissed any issues resolved by the
    compliance plans. After a hearing on the merits, the court upheld the hearing
    examiner's decision on the roof pitch issue. It reasoned that the SJCC provides
    no guidelines for calculating pitch for a variable-pitch roof and that the 4:12 pitch
    requirement was susceptible to more than one interpretation, such that deference
    would be given to the County's interpretation. The court reversed the hearing
    examiner's computation of the ADU's living area, reasoning that the SJCC
    No. 67429-3-1/7
    definition of "living area" was unambiguous and did not allow for exclusion of
    areas with a ceiling height less than five feet. It remanded the ADU permit for
    further consideration of that issue and awarded statutory costs to Durland.
    Durland now appeals the superior court's ruling that the issues in the
    compliance plans were time-barred under LUPA6 and its ruling as to the barn's
    roof pitch. Heinmiller cross-appeals the superior court's ruling regarding the living
    area ofthe ADU and the court's award of statutory costs to Durland.7
    DISCUSSION
    Standard of Review
    LUPA, chapter 36.70C RCW, governs judicial review of land use decisions
    in Washington. RCW 36.70C.030. When conducting judicial review under LUPA,
    this court sits in the same position as the superior court. Griffin v. Thurston
    County. 
    165 Wash. 2d 50
    , 54-55, 
    196 P.3d 141
     (2008). We review the
    administrative record before the hearing examiner, the "local jurisdiction's body
    6Durland also contends the hearing examiner erred in concluding that his appeal was
    time-barred under LUPA because the "decision is outside the authority or jurisdiction of the body
    or officer making the decision." RCW 36.70C.130(1)(e). We agree. The hearing examiner
    determined that the compliance plan agreements were a land use decision under LUPA and that
    Durland's appeal was filed more than 21 days after the compliance plan agreements were
    executed. Thus, the hearing examiner concluded the appeal was time-barred under RCW
    36.70C.040(3). Butthe hearing examiner's authority is limited to that granted by the creating
    body. Chausee v. Snohomish County Council. 
    38 Wash. App. 630
    , 636, 
    689 P.2d 1084
     (1984).
    Here, SJCC 2.22.030 limits the hearing examiner's authority to consideration of "land use
    regulations as provided by ordinance." SJCC 2.22.100 sets forth the specific land use regulations
    the hearing examiner is authorized to consider. Whether a decision is a land use decision under
    LUPA is not among them. The resolution of this issue is reserved to the superior court.
    Nonetheless, as Durland concedes, the issue is properly before us because the issue was
    considered by the superior court.
    7The County submits briefing in supportof Heinmiller's position as to the LUPA issue but
    takes no position regarding the roof pitch or living area issues. For convenience, and because
    they make substantially the same arguments, the County's arguments will be attributed to
    Heinmiller when discussing the LUPA issue.
    7
    No. 67429-3-1/8
    or officer with the highest level of authority to make the determination ... ." RCW
    36.70C.020(2). Relief is granted only ifthe party seeking relief establishes that
    the hearing examiner erred under one of the six standards in RCW
    36.70C. 130(1). The following standards are relevant to our determination of the
    LUPA issue, roof pitch issue, and living area issue:
    (b) The land use decision is an erroneous interpretation of the law,
    after allowing for such deference as is due the construction of a law
    by a local jurisdiction with expertise;
    (c) The land use decision is not supported by evidence that is
    substantial when viewed in light of the whole record before the
    court;[8]
    (d) The land use decision is a clearly erroneous application of the
    law to the facts;
    (e) The land use decision is outside the authority or jurisdiction of
    the body or officer making the decision;
    RCW 36.70C.130(1). An appellate court"must give substantial deference to both
    the legal and factual determinations ofa hearing examiner as the local authority
    with expertise in land use regulations." Lanzce G. Douglass. Inc. v. City of
    Spokane Valley. 
    154 Wash. App. 408
    , 415-16, 
    225 P.3d 448
     (2010), rev. denied.
    
    169 Wash. 2d 1014
     (2010) (citation omitted).
    8 Under the substantial evidence standard, "there must be a sufficient quantum of
    evidence in the record to persuade a reasonable person that the declared premise is true."
    Wenatchee Sportsmen Ass'n v. Chelan County. 
    141 Wash. 2d 169
    , 176, 
    4 P.3d 123
     (2000).
    8
    No. 67429-3-1/9
    Compliance Plans as Land Use Decisions
    The first issue is whether the compliance plans between the County and
    Heinmiller were land use decisions under LUPA. A "land use decision" is defined
    under LUPA as:
    a final determination by a local jurisdiction's body or officer with the
    highest level of authority to make the determination, including those
    with authority to hear appeals, on:
    (a) An application for a project permit or other governmental
    approval required by law before real property may be improved,
    developed, modified, sold, transferred, or used, but excluding
    applications for permits or approvals to use, vacate, or transfer
    streets, parks, and similar types of public property; excluding
    applications for legislative approvals such as area-wide rezones
    and annexations; and excluding applications for business licenses;
    (b) An interpretative or declaratory decision regarding the
    application to a specific property of zoning or other ordinances or
    rules regulating the improvement, development, modification,
    maintenance, or use of real property; and
    (c) The enforcement by a local jurisdiction of ordinances regulating
    the improvement, development, modification, maintenance, or use
    of real property. . . .
    RCW 36.70C.020(2) (Emphasis added).
    A petition to review a land use decision is barred under LUPA unless it is
    filed within 21 days of the issuance of the land use decision.9 RCW
    36.70C.040(3). Furthermore, a party may not collaterally challenge a land use
    decision for which the appeal period has passed via a challenge to a subsequent
    9 It is not clear when the compliance plans were "issued" within the meaning of RCW
    36.70C.040(4). However, the parties do notdispute that the 21-day appeal period for the
    compliance plans, if such a period applied, had passed before Durland filed his appeal ofthe
    permits.
    9
    No. 67429-3-1/10
    land use decision. Habitat Watch v. Skagit County. 
    155 Wash. 2d 397
    , 410-11, 
    120 P.3d 56
     (2005) (challenge to grading permit amounted to untimely collateral
    attack of earlier special use permit, where authorization for grading permit came
    from special use permit, whose appeal period had passed, and where sole basis
    for challenging grading permit was that extensions of special use permit were
    improper); Wenatchee Sportsmen Ass'n v. Chelan County. 
    141 Wash. 2d 169
    , 180-
    82, 
    4 P.3d 123
     (2000) (challenge to county's approval of plat application based
    on challenge to density of plat was untimely collateral attack where petitioner had
    not challenged rezone decision establishing allowed density for project two years
    earlier). Because LUPA prevents a court from reviewing an untimely petition, a
    land use decision becomes valid once the opportunity to challenge has passed.
    Wenatchee Sportsmen Ass'n, 141 Wn.2d at 181.
    A land use decision is "final" for purposes of LUPA when it "leaves nothing
    open to further dispute" and "sets at rest [the] cause of action between the
    parties." Samuel's Furniture. Inc. v. State. Dep't of Ecology. 
    147 Wash. 2d 440
    , 452,
    
    54 P.3d 1194
     (2002). Afinal decision "'concludes the action by resolving the
    plaintiffs entitlement to the requested relief.'" |d. (quoting Purse Seine Vessel
    Owners v. State. 
    92 Wash. App. 381
    , 387, 
    966 P.2d 928
     (1998)). In contrast, an
    interlocutory decision intervenes between the commencement and the end ofa
    suit and decides some point or matter, but is not a final decision of the whole
    controversy. ]d.
    10
    No. 67429-3-1/11
    Furthermore, a final land use decision should memorialize the terms of the
    decision, not simply reference them, in a tangible and accessible way so that a
    diligent citizen may "know whether the decision is objectionable or, if it is,
    whether there is a viable basis for a challenge." Vogel v. City of Richland. 
    161 Wash. App. 770
    , 779-80, 
    255 P.3d 805
     (2011). It must be clear to a reviewing court
    what decision is presented for review. Id. at 780. Mere decisions about the
    process to be followed in making a land use decision are not final land use
    decisions. ]d. at 778-79. And where a local jurisdiction sets forth a process for
    making a land use decision, the land use decision is not final unless the
    jurisdiction has complied with the process and the entire process is complete.
    See Heller Bldg.. LLC (HBO v. City of Bellevue, 
    147 Wash. App. 46
    , 55-56, 
    194 P.3d 264
     (2008) (stop work order not final land use decision where it did not
    contain information required by city code, which would have informed landowner
    HBL of substance of violations in a way that would allow HBL to correct violation
    or make informed decision whether to challenge city's decision); WCHS. Inc. v.
    CitvofLvnnwood. 
    120 Wash. App. 668
    , 679-80, 
    86 P.3d 1169
     (2004) (letters from
    city to landowner not final land use decisions because, among other reasons,
    they did not comply with city's own code requirements for distributing notice of
    decisions).
    11
    No. 67429-3-1/12
    Applying these principles, we hold that the compliance plans in this case
    were not a "final determination," and therefore not land use decisions.10 First, the
    plans outline at least two possible courses of action and do not "set at rest" the
    cause of action, Samuel's Furniture. 147 Wn.2d at 452. What Heinmiller sought
    in negotiating with the County over the notice of correction was to maintain the
    ADU. But the compliance plans do not guarantee that he could do so. To
    illustrate, the "Correction of Violations and Compliance Schedule" section of the
    compliance plan provides, in full:
    The parties agree that the owners are required to take the following
    action to bring the property into compliance with the County Code:
    1. Immediately cease all use of the storage structure for
    habitable purposes.
    2. Submit a complete demolition permit for removal of the deck
    and carport no later than May 1, 2008. Remove the deck and
    carport no later than 45 days after issuance of the demolition
    permit.[11]
    3. The owners will take EITHER action (a) or (b) as follows:
    a. Submit necessary permit applications for conversion of a
    portion of the storage structure to an ADU or bunkhouse. The
    first step is submittal of complete Shoreline Substantial
    Development Permit and Conditional Use Permit applications,
    which will be submitted no later than June 21, 2008. The
    owners' next step is as follows:
    i. If the SDP and CUP are approved, the owners will
    submit complete applications for all other necessary land
    use approvals such as building permits within 45 days of
    the approval of the SDP and CUP. The owners will take
    10 That the compliance plans were not a land use decision as to the setback issue
    specifically is consistent with the fact that, when Durland requested a document showing a "Land
    Use Decision by the County recognizing the barn as a non-conforming structure," which
    Heinmiller now asserts the compliance plans did, the deputy prosecuting attorney responded in
    July 2008, "No land use decision 'recognized' the barn as a non-conforming structure or changed
    it to a non-conforming structure.'" CP at 180.
    11 The demolition of the deck, carport, and other alterations are not at issue in this case.
    12
    No. 67429-3-1/13
    action to promptly complete construction and finalize the
    permits.
    ii. If either the SDP or CUP are denied, the owners will
    either (A): obtain a demolition permit for removal of the
    converted space inside the storage structure within 60
    days and restore the structure to its permitted
    configuration for storage no later than 45 days from
    demolition permit issuance; or (B) identify an alternative
    method of compliance within 60 days with the agreement
    of the County,
    b. Submit a complete demolition permit application for
    removal of the converted space inside the storage structure
    no later than June 21, 2008, and restore the structure to its
    permitted configuration for storage no later than 45 days
    from demolition permit issuance.
    4. Submit complete permit applications no later than June 21,
    2008 for the installation or removal of any other alterations of
    the storage structure which have occurred without the
    necessary building, electrical, mechanical, or plumbing permits
    and which are not addressed by a permit application submitted
    to comply with item (2) or (3) above. These alterations include
    but are not limited to the addition of exterior siding, extended
    eaves, heat, plumbing, and windows.
    CP at 81-82. As this language shows, the compliance plan did not determine the
    course of action between Heinmiller and the County with certainty. As far as such
    language indicated, there was nothing for Durland to appeal at that time.
    Significantly, one of the courses of action contemplated by the compliance
    plans-demolition of the ADU-was entirely satisfactory to Durland. It would have
    been premature, then, for him to bring a LUPA petition appealing the compliance
    plans when it was not apparent that Heinmiller would proceed in an objectionable
    manner. Furthermore, under section 3(a)(ii)(B), the compliance plan
    contemplated the possibility of an unknown course of action within 60 days if the
    shoreline permit or conditional use permitwere denied. Requiring Durland to
    13
    No. 67429-3-1/14
    appeal the compliance plans (and what was purportedly decided by them) within
    21 days, when Heinmiller had 60 days to pursue a third course not even
    described by them, would be illogical.
    Next, the compliance plan did not leave "nothing open to further dispute."
    Samuel's Furniture, 147 Wn.2d at 452. When Heinmiller approached the County
    a year after the compliance plan to propose a change, they agreed to a
    supplemental compliance plan. This confirms that the initial plan was not a final
    determination of Heinmiller's rights or obligations. The supplemental plan
    proposed "an alternative method of legalizing the ADU." CP at 83. Specifically,
    Heinmiller proposed obtaining a building permit that would allow remodeling a
    portion of the barn to an ADU and reducing the height of the barn to 16 feet,
    which "would not require either a shoreline substantial development permit or a
    conditional use permit." Id. The supplemental plan stated:
    The changes to the Agreed Compliance Plan are as follows:
    The parties agree that the owners may take the following action
    as an alternative to Correction of Violations and Compliance
    Schedule Action #3 as listed in the Agreed Compliance Plan
    dated April 25, 2008:
    Submit a complete building permit application by July 6, 2009,
    for the remodeling and conversion of a portion of the storage
    structure to an ADU and reduction in the height of the structure
    to no more than 16 feet above existing grade as measured
    along a plumb line at any point. Height shall be determined in
    accordance with the interpretation entitled "Height of Accessory
    Use Shoreline Structures" issued by Rene Beliveau on
    September 18, 2008. The owners will take action to promptly
    complete construction and finalize all permits to obtain legal
    occupancy of the structure.
    14
    No. 67429-3-1/15
    CP at 84. The supplemental plan concluded, "All provisions in the underlying
    Agreement shall remain in effect except as expressly modified by this
    supplement." Id. The compliance plan was modified by the supplemental
    compliance plan one year later and was evidently not final and binding on
    Heinmiller.
    Heinmiller asserts that the determination of whether the permits were
    authorized by the SJCC was made in the earlier compliance plans and could not
    be attacked collaterally when the permits were issued. But the compliance plans
    did not determine that the permits would be issued; they only stated that if the
    permits were obtained, the property would be brought into compliance with the
    SJCC. They implicitly acknowledge that the permits might not be granted and
    that one of the permits that might be issued is a demolition permit.
    Heinmiller also contends that permitting collateral challenges to
    compliance plans would eliminate their usefulness as code enforcement tools
    because they would provide no certainty, eliminating their benefits.12 But the
    plans in this case do not provide the certainty that Heinmiller claims; they do not
    12 Heinmiller points out that encouraging the voluntary correction ofviolations is a primary
    intent behind enforcement actions under SJCC 18.100.010. Development of compliance plans is
    one method for achieving compliance with the SJCC. If such a plan is developed, the SJCC
    states that no further code enforcement action will be taken:
    Following a notice of violation, the administrator and person in violation may
    develop a mutually agreeable compliance plan. The compliance plan shall
    establish a reasonable and specifictime frame for compliance. No further
    action will be taken if the terms of the compliance plan are met. If no
    compliance plan is established, enforcement of the violation will proceed.
    SJCC 18.100.040(D).
    15
    No. 67429-3-1/16
    state that any of the named permits will be granted or that he will ultimately be
    able to maintain the ADU.13
    Heinmiller further argues that the compliance plans are a final
    determination because the County complied with the process for compliance
    plans, the compliance plans contained the elements required by the SJCC, and
    the process was complete because there was no administrative appeal available.
    While these may be necessary to find a final determination under Heller BIdg and
    WCHS. these cases do not say that these circumstances are sufficient for a final
    decision.
    We hold the compliance plans were not land use decisions and Durland's
    failure to file a LUPA petition regarding the compliance plans did not bar him from
    raising certain issues in his LUPA petition regarding the permits.14
    Roofs Compliance with SJCC Pitch Requirement
    Durland contends the hearing examiner erroneously approved a building
    permit because the modification to the barn's roof would violate roof pitch
    requirements. He argues the roof pitch regulation is unambiguous and the
    13 We do not suggest that a compliance plan can never be a final determination. We hold
    only that the compliance plans in this case do not bear the indicia of a final land use decision as
    described in Samuel's Furniture, 147 Wn.2d at 452.
    14 We decline Durland's invitation to decide the setback issue, which was not reached by
    the hearing examiner or the superior court. This issue involves Durland's argument that the
    County could not issue permits forthe ADU conversion because the barn was an illegal structure
    by virtue of the fact that itdid not comply with the ten-foot setback requirement under the original
    1981 building permitor then-existing SJCC provisions. He requests this court to rule that (1) the
    barn was built illegally; (2) the illegality was not cured by the private restrictive covenant; and (3)
    therefore, permits could not be issued to modify the barn until the illegality was cured, under
    SJCC 18.100.030(F) and SJCC 18.100.070(D). This issue should be considered by the hearing
    examiner with the other issues on remand.
    16
    No. 67429-3-1/17
    County had no authority to construe it. He contends the County's approach in
    excluding the flat portion of the roof by measuring from the outside edge of the
    flat portion of the roof (not from the center of the roof) was not authorized by the
    SJCC.
    We hold that the result reached by the hearing examiner on this issue was
    not an erroneous interpretation of the law or a clearly erroneous application of
    the law to the facts, and was supported by evidence that is substantial when
    viewed in light ofthe whole record before the court.15 See RCW 36.70C. 130(1).
    Though we agree with Durland that the roof pitch requirement under the code
    provision is unambiguous, stating a minimum pitch of 4:12, the provision sets
    forth no guidelines or methodology for calculating pitch.16 Nor does it require a
    particular type of roof. The roof pitch provision is ambiguous as to how to
    measure the pitch of the proposed roof in this case and is subject to more than
    one interpretation, such that we give the County's interpretation deference. See
    Bostain v. Food Express. Inc.. 
    159 Wash. 2d 700
    , 716, 
    153 P.3d 846
     (2007) (courts
    accord deference to agency's interpretation where (1) agency is charged with
    administration and enforcement of statute, (2) statute is ambiguous, and (3)
    statute falls within agency's special expertise); Citizens For A Safe Neighborhood
    15 The hearing examiner decided this issue by ruling that the Deer Harbor roof pitch
    requirements adopted in 2007 did not apply to the building because itwas constructed in 1981
    and was therefore a grandfathered nonconforming use. The superior court affirmed, but on the
    ground that the County's interpretation would be given deference. We agree with the superior
    court and affirm the hearing examiner's ruling on that basis
    16 SJCC 18.30.350(H) provides: Roof Pitch. The minimum permitted roof pitch in Deer
    Harbor is 4:12. The relevant portion of SJCC 18.30.320, Table 3.9, states: "Minimum Roof Pitch
    4:12." A flat roof has a pitch of 0:12.
    17
    No. 67429-3-1/18
    v. City of Seattle. 
    67 Wash. App. 436
    , 440, 
    836 P.2d 235
     (1992) "It is a well
    established rule of statutory construction that considerable judicial deference
    should be given to the construction of an ordinance by those officials charged
    with its enforcement.") (quoting Keller v. Bellingham. 
    92 Wash. 2d 726
    , 731, 
    600 P.2d 1276
     (1979)).
    Here, the County determined that the pitch of the proposed roof measured
    4:12. Associate planner Lee McEnery performed calculations using the building
    plans and a scale. She measured from the outside edge of the flat area of the
    proposed roof. Testimony presented to the hearing examiner was that the
    modification would be consistent with the purpose behind the roof pitch
    regulations. McEnery stated that the purpose behind the Deer Harbor roof pitch
    requirements is visual. She pointed to SJCC 18.10.020, which provides that one
    of the purposes of the Title 18 regulations is aesthetic: "To provide for the
    economic, social, and aesthetic advantages of orderly development through
    harmonious groupings of compatible and complementary land uses and the
    application of appropriate development standards . . ." SJCC 18.10.020(B)(4).
    McEnery explained the dominant visual impression from the ground would be
    that ofa roof with a 4:12 pitch.17
    Durland points to no authority to show that roof pitch for the type of roof
    proposed by Heinmiller must be measured differently, i.e., from the center-most
    17 Architectural designer Bonnie Ward also testified that the modified roof would have a
    4:12 pitch despite having a flattened portion on top, as the flat portion would constitute less than
    ten percent of the roofand would not be noticeable from the exterior.
    18
    No. 67429-3-1/19
    point of the roof. He presented no expert testimony to the hearing examiner as to
    why the proposed roof cannot properly be determined to have a 4:12 pitch.
    ADU's Compliance with SJCC "Living Area" Restriction
    Heinmiller cross-appeals the superior court's ruling that the County
    erroneously computed the ADU's living area where the SJCC definition of "living
    area" was unambiguous and did not allow exclusion of areas with a ceiling height
    less than five feet. This issue involves SJCC 18.40.240(F) and 18.20.120. The
    former provides that an ADU "permitted subsequent to the adoption of this
    section shall not exceed 1,000 square feet in living area as defined in SJCC
    18.20.120." The latter defines "Living Area" as "the internal space measured from
    the interior of the exterior walls, excluding decks, overhangs, unenclosed
    porches or unheated enclosed porches, and the stairwell on one level of a two-
    story structure."
    Here, the County found that Heinmiller's ADU was 955 square feet in
    living area. The County's calculation excluded areas where the ceiling height was
    less than five feet.18 San Juan County Community Development and Planning
    Department director and chief building official Rene Beliveau testified before the
    hearing examiner that because the SJCC was silent as to measuring living area
    in a structure with a sloped roof, the County consulted the International
    Residential Code (IRC). The hearing examiner agreed with the County,
    18 Implicit in the parties' dispute is the conclusion that, had those areas been included in
    calculating the size of the ADU, the square-foot limit would not have been met.
    19
    No. 67429-3-1/23
    absurd results canon of statutory construction is applied sparingly. Five Corners
    Family Farmers v. State. 
    173 Wash. 2d 296
    , 311, 
    268 P.3d 892
     (2011) (citing Duke
    v. Bovd. 
    133 Wash. 2d 80
    , 87, 
    942 P.2d 351
     (1997)). Moreover, it is not clear that
    such an interpretation leads to absurd results. A property owner chooses where
    and how to build an ADU; it does not seem absurd to expect him or her to be
    aware of SJCC requirements when planning an ADU. Heinmiller also argues that
    Durland's interpretation would lead to the absurd result that all interior space of
    any structure in which an ADU is situated would count toward living area, in
    addition to the square footage of the ADU itself. He points out that the SJCC
    envisions that an ADU may be only part of a structure, such as a garage. See
    SJCC 18.20.010 (ADU may be "internal, attached or detached"). That issue is not
    presented here. Moreover, the SJCC 18.40.240(F) definition presumes that the
    living area of the ADU is being measured ("An accessory dwelling unit. . . shall
    not exceed . . .), not the entire building in which the ADU is located.
    Deference to the County's interpretation of its code depends on whether
    the provision is ambiguous; absent ambiguity, there is no need for the County's
    expertise in construing its regulations. Cowiche Canyon Conservancy v. Boslev.
    
    118 Wash. 2d 801
    , 813-14, 
    828 P.2d 549
     (1992). The SJCC provisions limiting an
    ADU's living area are not ambiguous.
    Superior Court's Award of Costs to Durland
    Heinmiller seeks reversal of the superior court's award of statutory costs
    to Durland under RCW 4.84.010. This court reviews an award of attorney's fees
    23
    No. 67429-3-1/24
    and costs for abuse of discretion. Ernst Home Center. Inc. v. Sato. 
    80 Wash. App. 473
    , 490, 
    910 P.2d 486
     (1996). "The determination as to who substantially
    prevails turns on the substance of the relief which is accorded the parties."
    Marine Enterprises. Inc. v. Security Pacific Trading Corp.. 
    50 Wash. App. 768
    , 772,
    
    750 P.2d 1290
     (1988). The prevailing party need not prevail on the entire claim.
    Silverdale Hotel Assocs. v. Lomas & Nettleton Co.. 
    36 Wash. App. 762
    , 774, 
    677 P.2d 773
     (1984).
    Heinmiller contends Durland was not the prevailing party because he
    prevailed only on the living area issue. He contends that the court's ruling,
    furthermore, did not destroy his ability to maintain the ADU because he can
    pursue planning revisions with the County and reconfigure the ADU's size.
    We conclude the superior court did not abuse its discretion. Durland
    succeeded in the sense that he halted Heinmiller's plan to maintain the ADU by
    invalidating the ADU permit. The superior court ruled that the ADU was not in
    conformance with the SJCC because of the living area and remanded the matter
    to establish compliance with SJCC 18.20.120. At this point it is uncertain whether
    Heinmiller will be able to maintain the ADU.
    Heinmiller's Request for Attorney's Fees on Appeal
    Heinmiller seeks attorney's fees on appeal under RCW 4.84.370, which in
    a land use decision "allows reasonable attorneys fees to a party who prevails or
    substantially prevails at the local government level, the superior court level, and
    before the court of appeals or the supreme court." Julian v. City of Vancouver.
    24
    No. 67429-3-1/25
    
    161 Wash. App. 614
    , 631-32, 
    255 P.3d 763
     (2011). We deny the request.
    Heinmiller did not substantially prevail before the superior court and he does not
    substantially prevail on appeal.
    Conclusion
    We affirm the superior court's rulings on the roof pitch and living area
    issues, as well as its award of statutory costs to Durland, but reverse its ruling
    that the compliance plans in this case were land use decisions under LUPA. We
    remand to the hearing examiner for consideration of the issues previously
    determined to be barred along with any other issues yet to be determined.
    Reversed in part, affirmed in part, and remanded to hearing examiner for
    further proceedings.
    •e^yy<- /1,6,0,
    WE CONCUR:
    f
    ^;yHOptrty
    25
    No. 67429-3-1/20
    reasoning that interpreting SJCC 18.20.120 to include such areas would lead to
    absurd or strained results.
    Durland argues that SJCC 18.20.120 and 18.20.240(F) are unambiguous
    and do not permit the subject areas to be excluded. Heinmiller argues that RCW
    19.27.031 imposes a mandatory duty on the County to apply provisions of the
    IRC in considering whether to issue a building permit. He contends that
    disregarding IRC provisions would lead to absurd results and that the County's
    interpretation is entitled to deference.
    We agree with Durland and hold that SJCC 18.20.120 does not allow the
    exclusion of areas with a ceiling height under five feet from the living area
    measurement. Initially, the parties agree that the state building code generally
    applies to the County and its interpretation of the SJCC. See RCW 19.27.031
    ("Except as otherwise provided in this chapter," International Building Code and
    IRC "shall be in effect in all counties"), SJCC 18.20.005(B) (SJCC definitions
    referencing UBC intended to mirror UBC definitions), SJCC 15.04.050(B) (IRC
    adopted "as iffully set out in this article"). For several reasons, however, IRC
    provisions do not apply in interpreting SJCC 18.40.240(F) or SJCC 18.20.120.
    First, the SJCC provisions are unambiguous. SJCC 18.40.240(F) limits the
    size of an ADU to 1,000 square feet of "living area," as that term is defined in
    SJCC 18.20.120. SJCC 18.20.120 sets forth areas to exclude from the living
    area calculation (decks, etc.), none of which is "areas with a ceiling height of five
    feet or less." This unambiguous language cannot be supplemented by other
    20
    No. 67429-3-1/21
    definitions. Unambiguous statutes are not subject to interpretation; one looks at
    the plain language of the statute without considering outside sources. State v.
    Delgado. 
    148 Wash. 2d 723
    , 727, 
    63 P.3d 792
     (2003). Furthermore, when the
    legislature has defined a term by statute, that definition controls its interpretation.
    State v. Watson. 
    146 Wash. 2d 947
    , 954, 
    51 P.3d 66
     (2002). Words cannot be
    added to an unambiguous statute when the legislative body has not included that
    language. Davis v. State Dep't of Licensing. 
    137 Wash. 2d 957
    , 964, 
    977 P.2d 554
    (1999).
    Second, the SJCC provisions at issue do not reference state law
    definitions. SJCC 18.20.005(B) provides:
    All definitions which reference the Revised Code of Washington
    (RCW), Washington Administrative Code (WAC), and Uniform
    Building Code (UBC) are intended to mirror the definitions in these
    codes at the effective date of the Unified Development Code (this
    code) or as amended. If the definition in this code conflicts with a
    definition under state law or regulation, the state definition shall
    control over this definition.
    But neither SJCC 18.40.240(F) nor SJCC 18.20.120 references any definition in
    the RCW, WAC, or UBC, and the definition of "living area" under SJCC
    18.20.120 does not conflict with any state law definitions.
    Furthermore, while Heinmiller argues that the IRC and SJCC provisions
    reference the same subject matter and should be harmonized, we disagree that
    they reference the same subject matter. The IRC provisions that Heinmiller
    21
    No. 67429-3-1/22
    contends were properly considered by the County in excluding the subject areas
    are IRC 305.1 (2003) and IRC 202 (2003).19 IRC 305.1 states, in pertinent part:
    Habitable rooms, hallways, corridors, bathrooms, toilet rooms,
    laundry rooms and basements shall have a ceiling height of not
    less than 7 feet (2134 mm).
    The required height shall be measured from the finish floor to the
    lowest projection from the ceiling.
    Exceptions:
    3. Not more than 50 percent of the required floor area of a room or
    space is permitted to have a sloped ceiling less than 7 feet (2134
    mm) in height with no portion of the required floor area less than 5
    feet (1524 mm) in height.
    IRC 202 defines "habitable space" as: "A space in a building for living, sleeping,
    eating or cooking. Bathrooms, toilet rooms, closets, halls, storage or utility
    spaces and similar areas are not considered habitable spaces." IRC 202 defines
    "living space" as "[sjpace within a dwelling unit utilized for living, sleeping, eating,
    cooking, bathing, washing and sanitation purposes." None of these IRC
    provisions pertain to the specific matter of measuring the living area of an ADU
    for the purpose of limiting the ADU's size. Nor do they use the same terminology;
    where the SJCC provision limits an ADU's "living area," the IRC definitions refer
    to "habitable space" and "living space."
    Finally, Heinmiller contends applying a literal interpretation of SJCC
    18.20.120, without reference to the IRC, would lead to absurd results because it
    would allow for the inclusion of areas that have no utility as living space. But the
    19 These provisions are part of the "2003 International Residential Code for One- and
    Two-Family Dwellings." CP at 170-71.
    22