Scarsella Brothers, Inc., App/cr-resp v. Flatiron Constructors Inc., Resp/cr-app ( 2020 )


Menu:
  •    IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON
    SCARSELLA BROTHERS, INC.,
    a Washington Corporation,                      No. 78543-5-I
    Appellant/ Cross-Respondent,          DIVISION ONE
    v.                                  UNPUBLISHED OPINION
    FLATIRON CONSTRUCTORS, INC.,
    a Delaware Corporation;
    WASHINGTON STATE DEPARTMENT
    OF TRANSPORTATION;
    LIBERTY MUTUAL INSURANCE
    COMPANY (Bond No. 015035206);
    TRAVELERS CASUALTY AND
    SURETY COMPANY OF AMERICA
    (Bond No. 105688202);
    FIDELITY AND DEPOSIT COMPANY
    OF MARYLAND/ZURICH AMERICAN
    INSURANCE COMPANY
    (Bond No. 9070286);
    FEDERAL INSURANCE COMPANY
    (Bond No. 82292503),
    THE CONTINENTAL
    INSURANCE COMPANY
    (Bond No. 929539824), and
    XL SPECIALTY INSURANCE
    COMPANY (Bond No. SUR7401972),
    Respondent/ Cross-Appellant.
    LEACH, J. — The Washington State Department of Transportation (WSDOT)
    contracted with Flatiron Constructors, Inc. (Flatiron) to be the prime contractor on a
    Citations and pin cites are based on the Westlaw online version of the cited material.
    No. 78543-5-I/2
    “design-build project” known as the I-405 Bellevue to Lynnwood Project.              Flatiron
    subcontracted with Scarsella Brothers, Inc. (Scarsella) for earthwork.        Flatiron and
    Scarsella both appeal the trial court’s decision made after a lengthy bench trial.
    Scarsella challenges the trial court decisions that the prime contract notice and claim
    provisions applied to its claims, the denial of its claims that Flatiron waived enforcement
    and is estopped from enforcing the notice and claim provisions, and the denial of its
    claims for quantum meruit recovery, foreclosure of its retainage lien, attorney fees and
    costs, and for prejudgment interest. Flatiron challenges the trial court’s decision that it
    breached the Scarsella subcontract and awarded judgment against its payment bond.
    We affirm.
    FACTS
    The Project and Parties
    On January 11, 2012, WSDOT contracted with Flatiron to serve as the prime
    contractor on a design-build project to widen and add express toll lanes to a segment of
    I-405 from Bellevue to Lynnwood.        On July 21, 2012, Flatiron subcontracted with
    Scarsella to perform earthwork, retaining wall installation, and drainage construction.
    The value of the subcontract was $14,865,476.68. The subcontract identifies three
    categories of work: (1) bid item work; (2) extra work; and (3) force account work.
    Sureties on Flatiron’s “Contract Bond and Retainage Bond” include Liberty
    Mutual Insurance Company, Travelers Casualty and Surety Company of America,
    Fidelity and Deposit Company of Maryland/Zurich American Insurance Company,
    Federal Insurance Company, The Continental Insurance Company, and XL Specialty
    2
    No. 78543-5-I/3
    Insurance Company. Liberty Mutual Insurance Company is the surety on Scarsella’s
    “Performance and Payment Bonds.”
    Payment Procedures
    Flatiron required Scarsella to submit monthly “pay applications” with supporting
    documentation showing the work it performed for the month. From August 2012, to
    January 2015, Flatiron reviewed each pay application, met with Scarsella to discuss
    discrepancies, negotiated payment for quantities and extra work using force account
    worksheets, and would issue a determination about Scarsella’s work and payment.
    During that time, Flatiron’s engineers reviewed the pay estimates and verified
    Scarsella’s work. Flatiron used Scarsella’s pay applications to prepare its own monthly
    pay applications to WSDOT.     After WSDOT paid Flatiron, Flatiron paid Scarsella a
    “progress payment.”
    Payment Dispute
    In November 2014, Flatiron exercised its subcontract right to withhold Scarsella’s
    payment.    Flatiron claimed Scarsella did not document its work, follow required
    procedures, maintain documentation, substantiate force account billings,            and
    substantiate pay applications as the subcontract required.       Flatiron also claimed
    Scarsella caused project delays in breach of the subcontract.       Before withholding
    payments, Flatiron raised these issues with Scarsella. Scarsella gave Flatiron some of
    the required documentation but not all. Flatiron told Scarsella it intended to pursue
    damages and intended to withhold payments because Scarsella did not provide full
    documentation.
    3
    No. 78543-5-I/4
    For Scarsella’s work on the project, Flatiron approved a total value of
    $17,788,284.60. Flatiron withheld $1,849,196.55 for bid item work; $194,150.01 for
    non-force account extra work, and $709,362.35 for force account work.
    Procedural History
    On August 14, 2015, Scarsella delivered a “Notice of Claim Lien” to WSDOT,
    Flatiron, and the sureties. Scarsella claimed $5,680,598.94 plus fees and costs.
    On December 11, 2015, Scarsella sued Flatiron and the sureties.           Scarsella
    claimed breach of contract, recovery against the payment bond, foreclosure on the lien
    against retainage, estoppel and waiver of prime contract provisions, breach of a
    covenant of good faith and fair dealing, and violation of RCW 39.76.011. Scarsella
    sought $12,135,173 plus prejudgment interest, attorney fees, and costs.            Flatiron
    counterclaimed arguing Scarsella significantly delayed the completion of the project.
    Trial occurred from July 5, 2017 to September 26, 2017. During trial, Flatiron
    acknowledged it withheld $2,731,437.97 in earned payments from Scarsella.
    Type of Work                          Amount Withheld
    Force account work                                          $709,362.35
    Non-force account extra work                                $194,150.01
    Bid item work                                             $1,849,196.55
    Minus back charges                                          $(21,270.94)
    Total                                                     $2,731,437.97
    On November 2, 2017, the trial court determined that subcontract section 2.6
    authorized Flatiron to withhold payments, and Flatiron acted in good faith when it did so.
    The trial court decided Scarsella could not recover additional compensation for force
    account work and extra work because of its noncompliance with section 1-04.5(1) of the
    4
    No. 78543-5-I/5
    Prime Contract. The trial court ordered Flatiron to pay Scarsella $2,731,437.97 for its
    work.       It denied Scarsella’s claims that Flatiron waived compliance with and was
    estopped from enforcing the prime contract notice and claim provisions.           It denied
    Scarsella’s claims against the retainage as premature.          The trial court also found
    Scarsella’s documentation inconsistent and unreliable, and that Scarsella did not
    substantiate its work and claims. The trial court denied Flatiron’s claim that Scarsella
    caused substantial project delays.
    On January 19, 2018, Scarsella and Flatiron independently filed requests for
    entry of judgment, attorney fees and costs, and prejudgment interest.          On May 14,
    2018, the trial court partially granted Scarsella’s and Flatiron’s requests.
    Scarsella appeals and Flatiron cross-appeals.
    STANDARD OF REVIEW
    We review a trial court’s decision in a bench trial for whether substantial evidence
    supports the trial court’s findings of fact and whether those findings support the court’s
    conclusions of law. 1 Substantial evidence is evidence sufficient to persuade a fair-
    minded person of its truth. 2 We review questions of law and statutory interpretation de
    1
    Standing Rock Homeowners Ass’n v. Misich, 
    106 Wash. App. 231
    , 243, 
    23 P.3d 520
    (2001); Hegwine v. Longview Fibre Co., Inc., 
    132 Wash. App. 546
    , 555-56, 
    132 P.3d 789
    (2006).
    2 
    Hegwine, 132 Wash. App. at 555-56
    .
    5
    No. 78543-5-I/6
    novo. 3 So, we review a trial court’s conclusions of law about contract interpretation de
    novo. 4
    ANALYSIS
    Prime Contract Notice and Claim Provisions
    Scarsella argues the prime contract notice and claim provisions do not apply to
    its claims for extra work. We disagree.
    “If the parties to a contract clearly and unequivocally incorporate by reference
    into their contract some other document, that document becomes part of their
    contract.”5 A prime contract incorporated by reference in a subcontract is binding on the
    subcontractor. 6
    The subcontract between Scarsella and Flatiron provides, “Subcontractor
    assumes toward Contractor all obligations that Contractor assumes toward Owner,
    insofar as applicable to the Work to be performed under this Subcontract.”7 As the
    subcontractor, Scarsella assumed toward Flatiron all obligations applicable to its work
    that Flatiron assumed under the prime contract toward WSDOT for Scarsella’s work.
    3In re Estate of Jones, 
    152 Wash. 2d 1
    , 8-9, 
    93 P.3d 147
    (2004); Sunnyside Valley
    Irr. Dist. v. Dickie, 
    149 Wash. 2d 873
    , 880, 
    73 P.3d 369
    (2003).
    4 Viking Bank v. Firgrove Commons 3, LLC, 
    183 Wash. App. 706
    , 712, 
    334 P.3d 116
    (2014); Panorama Village Homeowners Ass’n v. Golden Rule Roofing, Inc., 
    102 Wash. App. 422
    , 425, 
    10 P.3d 417
    (2000).
    5 Satomi Owners Ass’n v. Satomi, LLC, 
    167 Wash. 2d 781
    , 801, 
    225 P.3d 213
    (2009).
    6 Washington State Major League Baseball Stadium Public Facilities Dist. v.
    Huber, Hunt & Nichols-Kiewit Const. Co., 
    176 Wash. 2d 502
    , 518, 
    296 P.3d 821
    (2013).
    7 Subcontract Attachment B, Art. 1, § 1.6.
    6
    No. 78543-5-I/7
    The prime contract also provides procedures for Flatiron to submit notices, claims, and
    protests to WSDOT:
    If in disagreement with anything required in a Change Order, or any other
    written order from the WSDOT Engineer, including any direction,
    instruction, interpretation, or determination by WSDOT, the Design-Builder
    shall:
    1.     Immediately give a signed written notice of protest to WSDOT
    before doing the Work;
    2.     Supplement the written protest within 30 Calendar Days with a
    written statement and supporting documents [. . .]; and
    3.     If the protest is continuing, the information required above shall be
    supplemented monthly until the protest is resolved.
    Because Scarsella assumed these same obligations toward Flatiron, Scarsella was
    required to comply with the prime contract’s notice, claim, and protest provisions.
    Next, Scarsella argues it did not waive certain claims when it did not follow the
    prime contract notice and claim provisions. We disagree.
    Section 1-04.5 of the prime contract states, “By not protesting as this section
    provides, the Design-Builder also waives any additional entitlement and accepts from
    WSDOT any written order (including directions, instructions, interpretations, and
    determinations).”
    In NOVA Contracting, Inc. v. City of Olympia, the Washington State Supreme
    Court upheld an identical protest provision. 8 It determined the phrase “waives any
    additional entitlement” applies to “‘all’ claims related to the ‘protested [w]ork’” including
    damages. 9
    
    8191 Wash. 2d 854
    , 865, 
    426 P.3d 685
    (2018) (citing Mike M. Johnson, Inc. v.
    County of Spokane, 
    150 Wash. 2d 375
    , 391, 
    78 P.3d 161
    (2003)).
    9 NOVA Contracting, 
    Inc., 191 Wash. 2d at 866
    .
    7
    No. 78543-5-I/8
    Because the subcontract incorporated the prime contract, Scarsella assumed
    toward Flatiron the same procedural obligations Flatiron owed WSDOT.           So, under
    section 1-04.5 of the prime contract, Scarsella waived its right to protest if it did not
    comply with the prime contract’s protest provisions.
    Scarsella also argues the plain language of the subcontract replaces the prime
    contract notice and claim provisions because the subcontract provides a specific
    mechanism for calculating payments including payment for extra work.
    The subcontract provides:
    Extra work without a Bid Item that is directed by Flatiron will be marked up
    cost plus 10%. Extra work directed by WSDOT will be marked up
    according to the Contract Documents. Extra work shall be authorized by
    Flatiron personnel and quantities shall be mutually agreed to prior to
    performing work.
    But, this provision does not provide procedures for submitting notices, claims, and
    protests or describe the consequences of not following those procedures. It does not
    replace or supersede section 1-04.5 of the prime contract.
    Scarsella also argues that Flatiron’s breach of the subcontract bars it from
    enforcing its compliance with the prime contract provisions and that Flatiron prevented it
    from complying with the prime contract provisions. Scarsella’s briefs do not cite to the
    record or otherwise demonstrate that it raised these issues. Because Scarsella did not
    raise them below, we do not consider them on appeal. 10
    10   RAP 2.5(a).
    8
    No. 78543-5-I/9
    Waiver and Estoppel
    Scarsella argues that Flatiron waived the prime contract provisions and is
    estopped from enforcing those provisions. We disagree. Flatiron did not waive the
    prime contract provisions and Scarsella did not establish the elements of estoppel.
    Waiver
    “A party to a contract may waive a contract provision, which is meant for its
    benefit, and may imply waiver through its conduct.” 11 Waiver by conduct “requires
    unequivocal acts of conduct evidencing an intent to waive.” 12 We enforce procedural
    contract requirements unless the benefiting party waives the contract provision or the
    parties agreed to modify the contract. 13
    Here, the trial court determined:
    55.    Under Attachment B, ¶ 2.6 of the Subcontract, Flatiron had
    the right to deduct from payment due to Scarsella any amounts owed by
    Scarsella to Flatiron, and Flatiron was entitled to withhold payment from
    Scarsella in an amount sufficient to protect Flatiron from any actual or
    anticipated loss due to Scarsella’s alleged breach of the Subcontract.
    56.    Scarsella has not proved by a preponderance of the
    evidence that Flatiron expressly waived the rights and powers specified
    above to deduct amounts paid to which Scarsella was not entitled under
    the Subcontract.
    Scarsella argues that Flatiron waived compliance when it “(1) directed,
    demanded, acknowledged, and approved Scarsella[’s] work, both before and after
    11 Mike M. Johnson, 
    Inc., 150 Wash. 2d at 386
    (citing Reynolds Metals Co. v.
    Electric Smith Const. & Equipment Co., 
    4 Wash. App. 695
    , 700, 
    483 P.2d 880
    (1971)).
    
    12 150 Wash. 2d at 386
    (citing Absher Const. Co. v. Kent School Dist. No. 415, 
    77 Wash. App. 137
    , 143, 
    890 P.2d 1071
    (1995)).
    
    13 150 Wash. 2d at 386-87
    (citing American Sheet Metal Works, Inc. v. Haynes, 
    67 Wash. 2d 153
    , 157, 
    407 P.2d 429
    (1965)).
    9
    No. 78543-5-I/10
    ceasing payment to Scarsella, and (2) continued negotiating and agreeing to bid item
    quantities with Scarsella.”
    Subcontract section 2.6 permits Flatiron to withhold payments, and prime
    contract section 1-04.5(1) requires Flatiron and Scarsella to protest changes using the
    notice and claim procedures. The payment and notice and claim provisions are distinct
    contract provisions. Here, Flatiron’s continued directions to Scarsella did not waive the
    prime contract provisions.
    We affirm the trial court’s finding that Flatiron did not waive the prime contract
    notice and claim provisions.
    Estoppel
    Scarsella argues that promissory estoppel prevents Flatiron from enforcing the
    prime contract provisions. 14 We disagree.
    Promissory estoppel has five elements:
    (1) a promise, (2) that promisor should reasonably expect to cause the
    promisee to change his position, and (3) actually causes the promisee to
    change position, (4) justifiably relying on the promise, (5) in such a
    manner that injustice can be avoided only by enforcement of the
    promise.[15]
    14 Scarsella also argues the trial court improperly shifted the burden of proof from
    Flatiron to Scarsella to show that Flatiron was estopped from withholding payment.
    Scarsella cites to Conclusion of Law number 56 and subcontract section 2.6 but does
    not cite to any legal authority. We decline to address this issue. Palmer v. Jensen, 
    81 Wash. App. 148
    , 153, 
    913 P.2d 413
    (1996).
    15 McCormick v. Lake Washington School Dist., 99 Wn. App 107, 117, 
    992 P.2d 511
    (1999).
    10
    No. 78543-5-I/11
    “A promise is ‘a manifestation of intention to act or refrain from acting in a
    specified way, so made as to justify a promisee in understanding that a commitment has
    been made.’” 16
    The subcontract provides that “[n]o progress payment to Subcontractor shall
    operate as an approval or acceptance of Work done,” and “Contractor may deduct from
    any amounts due to Subcontractor…any sum or sums owed by Subcontractor to
    Contractor under this Subcontract.” The contract also provides, “the parties shall not be
    bound by, or be liable for, any statements, representations, promises, or agreements
    not specifically set forth in this Subcontract.”
    The trial court determined that “Scarsella could not reasonably rely on Flatiron’s
    prior progress payments as a promise not to deduct payment from future progress
    payments if it discovered that amounts paid were not actually due to Scarsella.” And,
    “Scarsella could not justifiably rely on Flatiron’s direction to perform extra work as a
    promise not to enforce [the notice and claim] and independent provisions.”
    The plain wording of the subcontract defeats Scarsella’s claim that it reasonably
    relied on Flatiron’s prior payments or direction to perform extra work as promises not to
    deduct payment and not to enforce the contract provisions. Because Flatiron made no
    promise, Scarsella’s estoppel claim fails. We affirm the trial court’s determination that
    Scarsella could not reasonably rely on Flatiron’s prior progress payments as a promise
    16 Havens v. C & D Plastics, Inc., 
    124 Wash. 2d 158
    , 172, 
    876 P.2d 435
    (1994)
    (citing Restatement (Second) of Contracts § 2(1)).
    11
    No. 78543-5-I/12
    not to deduct future progress payments and Flatiron was not estopped from deducting
    payments.
    Breach of Subcontract
    Flatiron argues the trial court should not have found that it breached the
    Scarsella subcontract and imposed liability against its payment bond because the trial
    court found that Flatiron withheld the payment from Scarsella in good faith. 17 Flatiron
    asserts the trial court improperly conflated the issues of (1) who was at fault for delaying
    the project and (2) Flatiron’s right to withhold Scarsella’s payments. We disagree.
    “To prevail on a breach of contract claim, the plaintiff must show an agreement
    between the parties, a parties’ duty under the agreement, and a breach of that duty.” 18
    First, Flatiron argues substantial evidence does not support the trial court’s
    finding that Flatiron breached the subcontract when it caused substantial project delays.
    Flatiron also argues it did not have a duty not to delay the project and instead had
    unilateral power to alter the project schedule.
    Subcontract article 3, section 3.1 provides, “Contractor may at any time by
    written order of Contractor’s authorized representative, and without notice to
    Subcontractor’s sureties, make changes in, additions to and deletions from the Work,
    and Subcontractor shall promptly proceed with the Work so changed.” And, section 3.2
    17 Flatiron also agues that even absent the subcontract’s express withholding
    clause, it could withhold payments under the common law of contracts. Because
    Flatiron’s withholding is separate from the issue of breach of contract, we decline to
    address it.
    18 Fidelity and Deposit Co. of Maryland v. Dally, 
    148 Wash. App. 739
    , 745, 
    201 P.3d 1040
    (2009).
    12
    No. 78543-5-I/13
    states that Scarsella waives its rights to assert claims against Flatiron for changes it
    makes when it provides Scarsella with five days notice.            Under these subcontract
    provisions, Flatiron could breach the subcontract even if Scarsella waived its right to
    assert a claim for the breach.
    The trial court found:
    Based on the evidence presented by both parties, the court finds that, to
    the extent there were delays, such delays more probably than not were
    caused by Flatiron’s failure to prepare timely and accurate construction
    plans, and its failure to properly plan, supervise and direct the sequence of
    work on the Project, including Scarsella’s work.
    In its order granting in part Flatiron’s request for fees and costs, the trial court
    clarified, “if it is not clear from the court’s earlier findings and conclusions, the court now
    finds and concludes that Flatiron breached the parties’ contract by causing the
    substantial project delays that were the factual basis of Flatiron’s counterclaim against
    Scarsella.”
    Failure to timely and accurately prepare construction plans, supervise, and direct
    the project, are not delays permitted under subcontract article 3, section 3.1. So, we
    affirm the trial court’s finding that Flatiron breached the subcontract.
    Second, Flatiron argues it did not have a duty to pay Scarsella $2,731,437.97.
    So, its withholding of that amount was not a contract breach. Flatiron conceded that it
    owed Scarsella $2,731,437.97 and the trial court found that Flatiron withheld that
    payment in good faith.      But, the trial court did not rely on Flatiron’s withholding to
    support its finding that Flatiron breached the subcontract. It relied on Flatiron’s failure to
    prove at trial the factual basis for the withholding to support its decision that Scarsella
    13
    No. 78543-5-I/14
    was entitled to recover the withheld amount. It relied on other conduct described above
    to support its finding that Flatiron breached the subcontract. Scarsella’s claims based
    on these breaches failed because it did not comply with procedural requirements for
    asserting these claims.
    Third, Flatiron asserts that “[e]ven if the subcontract authorized Flatiron to
    withhold payment only in the event of Scarsella’s actual breach, Flatiron’s withholding
    would not constitute breach because Scarsella was in actual breach” when it did not
    fulfill its scheduling and documentation obligations. But, the trial court found Flatiron did
    not meet its burden of proving Scarsella caused the delays. So, this claim is without
    merit. Substantial evidence supports the trial court’s finding that Flatiron breached the
    subcontract.
    Quantum Meruit Recovery
    Scarsella argues the trial court incorrectly denied its claim for quantum meruit
    recovery because (1) Flatiron used Scarsella to perform work outside the scope of the
    subcontract; (2) the work was not within the method and manner contemplated by the
    parties; (3) the trial court incorrectly applied the force majeure standard; and (4) the trial
    court incorrectly determined the prime contract notice and claim provisions barred
    quantum meruit recovery. We disagree.
    “Quantum meruit is an appropriate basis for recovery when substantial changes
    occur which are not covered by the contract and are not within the contemplation of the
    parties, and the effect of such changes is to require extra work or to cause substantial
    14
    No. 78543-5-I/15
    loss to the contractor.” 19 Quantum meruit is a mixed question of fact and law: Does the
    contract indicate the parties contemplated the changed conditions? 20 If the “contract
    unambiguously contemplates the changed conditions,” the complaining party is not
    entitled to any quantum meruit recovery. 21 If the contract is ambiguous, “issues of fact
    would exist, and resolution of the question would be for the trier of fact.” 22 Recovery is
    available when neither party could have reasonably anticipated the changed condition. 23
    In General Construction Company v. Public Utility District No. 2 of Grant County,
    we determined for work within the scope of a contract, a party must comply with the
    terms of the contract unless there is evidence the complaining party waived compliance
    with the contract’s notice and claim requirements. 24 Notice and claim provisions are
    valid unless there is “unequivocal evidence of an intent to waive” the protection. 25 “For
    work outside of the contract, and changed work within the scope of the contract where
    [the party] satisfied the contractual notice and claim provisions, quantum meruit
    applies.”26
    First, Scarsella argues it is entitled to quantum meruit recovery because Flatiron
    directed it to perform work outside the scope of the subcontract.         Flatiron argues
    19   Hensel Phelps Const. Co. v. King County, 
    57 Wash. App. 170
    , 174, 
    787 P.2d 58
    (1990).
    20  
    Hensel, 57 Wash. App. at 175-76
    .
    21  
    Hensel, 57 Wash. App. at 176
    .
    22 
    Hensel, 57 Wash. App. at 176
    .
    23 Basin Paving Co. v. Mike M. Johnson, Inc., 
    107 Wash. App. 61
    , 65, 
    27 P.3d 609
    (2001), review denied, 
    145 Wash. 2d 1018
    (2002).
    24 
    195 Wash. App. 698
    , 700, 709-10, 
    380 P.3d 636
    (2016).
    25 General Construction 
    Company, 195 Wash. App. at 709
    (citing Mike M. Johnson,
    Inc. v. County of Spokane, 
    150 Wash. 2d 375
    , 391-92, 
    78 P.3d 161
    (2003)).
    
    26 195 Wash. App. at 709-10
    .
    15
    No. 78543-5-I/16
    Scarsella cannot recover quantum meruit because the subcontract expressly included
    provisions for directing, authorizing, and compensating extra work. 27 The trial court
    determined the subcontract contemplated “extra work outside the scope of the bid
    items” and “specifies the measurement of payment for all such work.” The subcontract
    states, “For work outside previously agreed upon the Subcontractor shall notify
    Contractor and agree upon quantities and scope before performing work.” The price for
    extra work is marked up cost plus 10 percent. Because the contract unambiguously
    contemplates additional work, we affirm the trial court’s decision not to award quantum
    meruit recovery.
    Second, Scarsella argues it is entitled to recovery because the work did not
    proceed in the method and manner contemplated by the parties.              The trial court
    determined Scarsella did not prove there were substantial changes that neither party
    could reasonably anticipate. Article 3 of the subcontract discusses changes and delays.
    In order to recover for defects in specifications, differing conditions, and delays,
    Scarsella was required to provide Flatiron with a written claim or else it would waive
    recovery. Because the contract reasonably contemplated changes, we agree with the
    trial court that Scarsella did not prove it could not reasonably anticipate the delays that
    affected the method and manner of the work.
    Third, Scarsella asserts the trial court improperly applied the force majeure
    standard rather than the quantum meruit standard.         The trial court stated, “I think
    27Flatiron argues this court rejected an analogous argument in Hensel Phelps
    Const. Co. v. King County, 
    57 Wash. App. 170
    , 174, 
    787 P.2d 58
    (1990).
    16
    No. 78543-5-I/17
    quantum meruit might be applicable had we, for example, had a giant earthquake that
    created crevices and cracks and chasms across the freeway, or if there had been some
    totally unforeseen disaster that nobody had planned for.” But, the trial court did not
    actually apply a force majeure standard.          The trial court continued to explain the
    “extraordinary amount of delay” and “huge number of change orders” were not
    substantial changes not contemplated by the subcontract.           Because the trial court
    properly applied the quantum meruit standard, Scarsella’s argument fails.
    Fourth, Scarsella asserts the trial court incorrectly determined the prime contract
    notice and claim provisions barred quantum meruit recovery. Flatiron asserts the trial
    court correctly determined that Scarsella’s non-compliance with the subcontract’s
    provisions bars it from quantum meriut recovery. The trial court denied Scarsella’s
    request for quantum meruit recovery for work it performed but did not invoice before
    January 20, 2015. The trial court determined that when Scarsella did not comply with
    the provisions, it waived its rights to bring a claim. And, because it waived its rights, the
    trial court determined that Scarsella could not bring a claim for quantum meruit
    recovery. We agree and affirm the trial court’s determination that Scarsella was not
    entitled to quantum meruit recovery.
    Lien on Retainage
    Scarsella argues the trial court should have allowed its claim under RCW 60.28
    for recovery against the contract retainage held by WSDOT. We disagree.
    RCW 60.28.030 provides that after a party files a claim against the reserve fund,
    it has four months to bring an action to foreclose a lien on retainage.
    17
    No. 78543-5-I/18
    RCW 60.28.011(1)(a) provides that contract retainage may not exceed five percent.
    Here, the subcontract’s retainage provision “provides that Flatiron may withhold
    5 percent of all progress payments to Scarsella as retainage.” RCW 60.28.011(3)(a)(b)
    and the prime contract provide that within 60 days of the project’s final completion, the
    public body WSDOT must release the retainage.            The subcontract provides that
    retainage is due “upon acceptance of the work by WSDOT,” which occurs after the
    project’s final completion.
    “[P]arties may contractually select as the date of completion of the work either
    the date of substantial completion or the date of final completion.”28 “Unless otherwise
    defined by the contract to mean ‘final completion[,]’ the date on which the work is
    100 [percent] complete ‘completion’ ordinarily is understood to mean ‘substantial
    completion’ - the date on which all material elements of the work are sufficiently
    complete in conformance with the contract so that the owner can use the work for its
    intended purpose.”29
    The trial court found the project was substantially completed by October 31,
    2015, but the contract date of completion had not arrived by the time of trial.         It
    determined that “[b]ased on the evidence presented at trial, it [wa]s not possible for the
    court to reach a conclusion as to whether or when the retainage will be due to
    Scarsella.” It explained,
    I’m assuming that the retainage will be paid when the time comes, but I
    don’t have enough evidence, and the project had not been completed by
    28State Construction, Inc. v. City of Sammamish, 
    11 Wash. App. 2d
    892, 911, 
    457 P.3d 1194
    (2020).
    29 State Construction, 
    11 Wash. App. 2d
    at 911.
    18
    No. 78543-5-I/19
    the time of trial, at least not so far as I was told. So it would have been
    premature to rule on the retainage claim.
    It determined because the date of completion had not arrived by the time of trial,
    Scarsella’s claim for foreclosure of the lien on retainage was premature.
    We agree. Because Scarsella prematurely asserted its claim, we affirm the trial
    court’s denial of this claim. 30
    Prevailing Party
    Scarsella and Flatiron request attorney fees and costs under various statutes.31
    Their competing claims require determining whether either party is the prevailing party.
    None of the statutes relied on define “prevailing party.” So, we must consider “case law
    governing the determination of a prevailing party with respect to other statutes
    governing attorney fees and costs.”32
    “In Washington, the prevailing party is the one who receives judgment in that
    party’s favor.” 33 “A party need not recover its entire claim in order to be considered the
    prevailing party.” 34 “However. . . where both parties prevail on major issues, neither is
    30  Flatiron argues the absence of a finding on the issue of retainage is a
    presumptive negative finding on that issue under Taplett v. Khela, 
    60 Wash. App. 751
    ,
    759, 
    807 P.2d 885
    (1991). Because the issue was premature, we do not reach
    Flatiron’s claim.
    31 RCW 60.28.030, RCW 39.08.030, RCW 39.04.250, RCW 39.76.040,
    RCW 39.76.011.
    32 In re Marriage of Nelson, 
    62 Wash. App. 515
    , 518-19, 
    814 P.2d 1208
    , 1211
    (1991).
    33 Sardam v. Morford, 
    51 Wash. App. 908
    , 911, 
    756 P.2d 174
    (1988) (quoting Blair
    v. Washington State University, 
    108 Wash. 2d 558
    , 571, 
    740 P.2d 1379
    (1987)).
    34 Silverdale Hotel Associates v. Lomas & Nettleton Co., 
    36 Wash. App. 762
    , 774,
    
    677 P.2d 773
    (1984).
    19
    No. 78543-5-I/20
    entitled to attorney fees.” 35 And, under RCW 4.84.330, where each party prevails on a
    major issue, “there is no ‘prevailing party.’” 36
    In re Marriage of Nelson provides that because one party properly received an
    award of back child support under RCW 26.18.160, that party prevailed over the other
    party. 37 In Sardam v. Morford, the trial court concluded that because neither party was
    the prevailing party, it would not award attorney fees under a landlord-tenant statute. 38
    Division III of this court affirmed the trial court’s conclusion because it “would be
    inequitable to award substantial fees” where both parties successfully defended against
    each other’s major claims. 39
    In Crest Inc. v. Costco Wholesale Corp., we explained that under a contractual
    provision, rather than a statutory provision,
    [I]f neither party wholly prevails,. . . then the party who substantially
    prevails is the prevailing party. . . When there are several conflicting
    claims at issue, a defendant is awarded attorney fees for those claims it
    successfully defends, and plaintiff is awarded attorney fees for those
    claims upon which it prevails, and the awards should be the offset.[40]
    Here, the trial court determined that “Scarsella and Flatiron each prevailed on
    major issues,” but “[n]either party prevailed. . . on its own respective claims.”     So,
    neither was the “prevailing party.”
    35 
    Sardam, 51 Wash. App. at 911
    .
    36 Tallman v. Durussel, 
    44 Wash. App. 181
    , 990, 
    721 P.2d 985
    (1986); Rowe v.
    Floyd, 
    29 Wash. App. 532
    , 535-36, 
    629 P.2d 925
    (1981).
    
    37 62 Wash. App. at 518-19
    .
    
    38 51 Wash. App. at 910
    (citing RCW 59.18.290, RCW 4.84.330).
    39 
    Sardam, 51 Wash. App. at 911
    .
    40 
    128 Wash. App. 760
    , 772, 
    115 P.3d 349
    (2005).
    20
    No. 78543-5-I/21
    Scarsella argues the trial court incorrectly relied on Sardam in finding it was not
    the prevailing party. 41 Flatiron and the sureties argue the trial court properly referenced
    Sardam to explain how it would avoid inequitable results by denying attorney fees
    where neither party was the prevailing party.
    Using the approach where each party prevails on a major issue, “there is no
    ‘prevailing party,’” 42 neither Scarsella nor Flatiron is the prevailing party. The trial court
    determined that Scarsella failed on its claims for breach of contract, additional
    compensation, quantum meruit, retainage, waiver and estoppel, breach of good faith
    and fair dealing, and violation of payment statutes. It determined Scarsella was entitled
    to labor and material payment bonds totaling $2,731,437.97 because of Flatiron’s
    concession. It also determined Flatiron failed on its claims for damages for breach of
    contract and performance bonds.
    Scarsella argues the $2,731,437.97 award against Flatiron’s labor and material
    payment bonds make it the “prevailing party.”
    The trial court disagreed,
    Even though Flatiron conceded at trial that Scarsella had earned
    $2,731.437.97 more than Flatiron had paid Scarsella, Flatiron’s
    concession does not allow Scarsella to request an award of attorneys’
    fees incurred in recovering that amount pursuant to RCW 39.04.250 or
    RCW 39.76.040, because Flatiron withheld that sum from Scarsella in
    good faith.
    Based upon the trial court record, the court finds and concludes
    that neither Scarsella nor Flatiron is the “prevailing party.”
    
    4151 Wash. App. 908
    , 911, 
    756 P.2d 174
    (1988).
    42Tallman v. Durussel, 
    44 Wash. App. 181
    , 990, 
    721 P.2d 985
    (1986); Rowe v.
    Floyd, 
    29 Wash. App. 532
    , 535-36, 
    629 P.2d 925
    (1981).
    21
    No. 78543-5-I/22
    We agree with the trial court. Because the labor and material payment bonds issue was
    not a “major issue” in the case, Scarsella was not the “prevailing party.” Scarsella also
    failed on eight out of nine of its claims, and Flatiron failed on both of its claims. So, the
    trial court correctly determined neither was the prevailing party.
    Attorney Fees and Costs at Trial
    Scarsella argues the trial court should have considered whether to award fees
    under RCW 60.28.030, RCW 39.08.030, and Olympic S.S. Co., Inc. v. Centenniel Ins.
    Co. 43 Flatiron and the sureties argue this court should affirm the trial court’s order
    denying Scarsella’s request for attorney fees and costs.         Flatiron also argues it is
    entitled to reasonable attorney fees and costs it incurred defending itself because it
    prevailed under RCW 39.04.250.           We disagree.   Neither Scarsella nor Flatiron is
    entitled to trial fees and costs.
    “We apply a two-part standard of review to a trial court’s award or denial of
    attorney fees: ‘(1) we review de novo whether there is a legal basis for awarding
    attorney fees by statute, under contract, or in equity and (2) we review a discretionary
    decision to award or deny attorney fees and the reasonableness of any attorney fee
    award for an abuse of discretion.’” 44
    First, Scarsella argues the trial court incorrectly denied recovery of attorney fees
    under the Prompt Payment Act, RCW 39.04.250, RCW 39.76.040, and in determining
    the Prompt Payment Act was an exclusive remedy.
    43   
    117 Wash. 2d 37
    , 
    811 P.2d 673
    (1991).
    44   In re Washington Builders Ben. Trust, 
    173 Wash. App. 34
    , 83, 
    293 P.3d 1206
    (2013).
    22
    No. 78543-5-I/23
    RCW 39.04.250 provides, “In any action for the collection of funds wrongfully
    withheld, the prevailing party shall be entitled to costs of suit and reasonable attorneys’
    fees.” RCW 39.76.040 provides, “In any action brought to collect interest due under this
    chapter, the prevailing party is entitled to an award of reasonable attorney fees.”
    Here, the trial court explained:
    It bears repeating that, although Flatiron conceded at trial that it
    withheld $2,731,437.97 from Scarsella as an offset against the $8,940,962
    counterclaim that Flatiron was pursuing against Scarsella, Flatiron’s
    concession does not expose Flatiron to a claim for attorneys’ fees and
    costs or interest pursuant to RCW 39.04.250 or RCW 39.76.040, because
    Flatiron withheld that sum from Scarsella in good faith.
    Because Scarsella was not the prevailing party, it was not entitled to recover fees
    under RCW 39.04.250, and RCW 39.76.040. The trial court found Flatiron withheld
    payment in “good faith,” so Flatiron’s withholding did not meet the “wrongfully withheld”
    requirement of RCW 39.04.250.         And, because Scarsella’s claim for prejudgment
    interest fails, it is not entitled to an award under RCW 39.76.040.
    Second, Scarsella argues the trial court should have awarded it recovery against
    the contract retainage and attorney fees under RCW 60.28.030. In its trial complaint,
    Scarsella asserted a claim for “the retained percentage fund the principal amount of
    $6,564,370.73, plus pre-judgment interest, costs and attorney’s fees, pursuant to
    RCW 60.28.” RCW 60.28.030 provides, “In any action brought to enforce the lien, the
    claimant, if he or she prevails, is entitled to recover, in addition to all other costs,
    attorney fees in such sum as the court finds reasonable.”         Because the trial court
    23
    No. 78543-5-I/24
    properly denied Scarsella’s claim for recovery against the contract retainage, Scarsella
    did not prevail. So, we deny its claim for recovery under RCW 60.28.030.
    Third, Scarsella argues the trial court should not have denied it attorney fees and
    costs under RCW 39.08.030(1)(b). RCW 39.08.030(1)(b) provides, “in any suit or action
    brought against such surety or sureties by any such person or corporation to recover for
    any of the items specified in this section, the claimant is entitled to recover in addition to
    all other costs, attorneys’ fees in such sum as the court adjudges reasonable.”
    “RCW 39.08.030 authorizes attorney fees in an action brought against a performance
    bond where the surety contests a right to recover, denies the allegations in a complaint,
    and seeks dismissal of an action.”45 “A surety contests a right to recover when it denies
    the allegations in a complaint and seeks dismissal of an action.”46 The trial court denied
    Scarsella’s claim for attorney fees and costs under RCW 39.08.030(1)(b) because it
    determined Scarsella did not have a statutory basis for attorney fees and that Scarsella
    was not the prevailing party.
    Because Scarsella’s bond claim fails, its claim for attorney fees and costs under
    RCW 39.08.030(1)(b) also fails.
    Fourth, Scarsella argues the trial court should not have denied it attorney fees
    and costs under Olympic Steamship because it was the prevailing party, and to obtain
    the benefit of the surety, it had to litigate. In Olympic Steamship, the Washington State
    45Campbell Crane & Rigging Services, Inc. v. Dynamic Intern. AK, Inc., 145 Wn.
    App. 718, 727, 
    186 P.3d 1193
    (2008) (citing Diamaco, Inc. v. Mettler, 
    135 Wash. App. 572
    , 578, 
    145 P.3d 399
    (2006)).
    46 
    Diamaco, 135 Wash. App. at 578
    .
    24
    No. 78543-5-I/25
    Supreme Court explained, “an award of fees is required in any legal action where the
    insurer compels the insured to assume the burden of legal action, to obtain the full
    benefit of his insurance contract, regardless of whether the insurer’s duty to defend is at
    issue.” 47 “An award of attorney fees under Olympic Steamship is restricted to disputes
    where the insurer forces the insured to litigate coverage and then loses.” 48 Because we
    determined Scarsella is not the prevailing party, it is not entitled to recovery under
    Olympic Steamship.
    Fifth, Scarsella argues it is entitled to full attorney fees and costs without
    segregation. Flatiron asserts the trial court did not decide the issue of segregation
    because Scarsella’s claims were unsuccessful. We review a trial court’s determination
    of whether segregation is possible for abuse of discretion. 49 “[W]here the ‘plaintiff’s
    claims for relief. . . involve a common core of facts or [are] based on related legal
    theories,’ a lawsuit cannot be ‘viewed as a series of discrete claims’ and, thus, the
    claims should not be segregated in determining an award of fees.” 50 “A trial court need
    not segregate attorney fees if it determines that ‘the claims are so related that no
    reasonable segregation can be made.’” 51 Here, Scarsella’s claims relied on the same
    47  117 Wn.2d, 52, 
    811 P.2d 673
    (1991).
    48   King County v. Vinci Construction Grands Projets/Parsons RCI/Frontier-
    Kemper, JV, 
    188 Wash. 2d 618
    , 630, 
    398 P.3d 1093
    (2017).
    49 Vinici Construction Grands 
    Projects, 188 Wash. 2d at 632
    (citing Mayer v. Sto
    Industries, Inc., 
    156 Wash. 2d 677
    , 693, 
    132 P.3d 115
    (2006)).
    50 Fiore v. PPG Industries, Inc., 
    169 Wash. App. 325
    , 351-52, 
    279 P.3d 972
    (quoting Brand v. Department of Labor and Industries of State of Wash., 
    139 Wash. 2d 659
    , 672-73, 
    989 P.2d 1111
    (1999)).
    51 Everett Hangar, LLC v. Kilo 6 Owners Association, No. 76949-9-I, 
    7 Wash. App. 2d
    1029 (unpublished).
    25
    No. 78543-5-I/26
    “common core of facts.” Scarsella lost its primary claims and was not entitled to fees.
    Because Scarsella was not entitled to fees, segregation was not appropriate.
    Flatiron asserts the trial court incorrectly denied its claim for attorney fees under
    RCW 39.76.040 and RCW 39.04.250(3) because it prevailed against Scarsella’s
    RCW 39.04.250 and 39.76.011 claims. Because neither party is the prevailing party,
    we deny Flatiron’s claim.
    Prejudgment Interest
    Scarsella argues the trial court abused its discretion when determining the
    amount awarded was unliquidated, and that the trial court should have awarded
    prejudgment interest totaling $949,626.03. We disagree.
    We review prejudgment interest decisions for abuse of discretion. 52 A court may
    award prejudgment interest (1) for liquidated damages 53 or (2) “when the amount of an
    ‘unliquidated’ claim is for an amount due upon a specific contract for the payment of
    money and the amount due is determinable by computation with reference to a fixed
    standard contained in the contract, without reliance on opinion or discretion.” 54 “Where,
    however, the demand is for something which requires evidence to establish the quantity
    or amount of the thing furnished, or the value of the services rendered, interest will not
    be allowed prior to the judgment.” 55
    52Scoccolo Const., Inc. ex rel. Curb One, Inc. v. City of Renton, 
    158 Wash. 2d 506
    ,
    519, 
    145 P.3d 371
    (2006).
    53 Scoccolo 
    Const., 158 Wash. 2d at 519
    .
    54 Prier v. Refrigeration Engineering Co., 
    74 Wash. 2d 25
    , 32, 
    442 P.2d 621
    (1968).
    55 Wright v. City of Tacoma, 
    87 Wash. 334
    , 353-54, 
    151 P. 837
    (1915).
    26
    No. 78543-5-I/27
    A claim is liquidated “where the evidence furnishes data which, if believed,
    makes it possible to compute the amount with exactness, without reliance on opinion or
    discretion.”56   A claim is “ ‘unliquidated’ where the exact amount of the sum to be
    allowed cannot be definitely fixed from the facts proved, . . . but must in the last analysis
    depend upon the opinion or discretion of the judge or jury as to whether a larger or a
    smaller amount should be allowed.” 57
    In Prier, the Washington State Supreme Court explained, “the existence of a
    dispute over part or all of a claim does not change the claim from a liquidated to an
    unliquidated one. It is the character of the claim and not of the defense that determines
    the question.”58 There, the court determined there was data available to compute the
    exact costs of repairs, so the plaintiff’s claims were for a liquidated sum on which
    interest would be allowed. 59
    Here, the trial court determined, “Scarsella’s request for an award of prejudgment
    interest cannot be granted because Scarsella is not a prevailing party against Flatiron,
    and because the principal judgment amount is not based upon a liquidated sum.” The
    trial court compared this case to Wright v. City of Tacoma where the court permitted
    prejudgment interest on a sum that was not in dispute but denied prejudgment interest
    where “the items which made up this amount were in dispute.” 60 In Wright, the court
    explained, “It being necessary to establish by evidence the amount of the services
    56 
    Prier, 74 Wash. 2d at 32
    .
    57 
    Prier, 74 Wash. 2d at 33
    .
    58 
    Prier, 74 Wash. 2d at 35
    .
    59 
    Prier, 74 Wash. 2d at 34-35
    .
    60 87 Wash. at 354.
    27
    No. 78543-5-I/28
    furnished, or the quantity of material supplied, and not being able to establish these
    either by computation or by reference to a known standard, interest prior to the date of
    the judgment was improperly allowed.” 61
    Here, Flatiron calculated it owed Scarsella approximately $2,731,437.97. But,
    the trial court determined the amount Flatiron owed Scarsella was not, and could not be,
    calculated “with any certainty from the evidence, and thus it is not possible to compute
    prejudgment interest on that sum.”
    We agree the amount of Scarsella’s recovery is an unliquidated sum that is not
    “determinable by computation with reference to a fixed standard contained in the
    contract.”   For this reason, the trial court did not abuse its discretion in denying
    prejudgment interest.
    Scarsella   also   argues   it   is   entitled   to   prejudgment   interest   because
    RCW 39.04.250 and RCW 39.76.011 did not supersede common law rules for
    prejudgment. 62 “Where. . . the provisions of a later statute are so inconsistent with and
    repugnant to the prior common law that both cannot simultaneously be in force, the
    statute will be deemed to abrogate the common law.” 63
    RCW 39.04.250(3) provides a party may recover interest where a party
    wrongfully withheld the sum.       Scarsella cannot recover under RCW 39.04.250(3)
    61  87 Wash. at 354.
    62  Scarsella also argues the trial court improperly determined RCW 39.04.250
    and RCW 39.76.011 to be the exclusive remedy. This claim is without merit because
    the trial court did not state that RCW 39.04.250 and RCW 39.76.011 were exclusive
    remedies.
    63 State ex rel. Madden v. Public Utility Dist. No. 1 of Douglas County., 
    83 Wash. 2d 219
    , 222, 
    517 P.2d 585
    (1973).
    28
    No. 78543-5-I/29
    because Flatiron withheld payment in good faith. Because it cannot recover under
    RCW 39.04.250(3), Scarsella is not entitled to interest under that statute. The good
    faith safe harbor provided by the parties’ contract and RCW 39.04.250(3)’s requirement
    that a withholding be wrongful abrogate any previous inconsistent common law right of
    recovery. And, because the date of completion had not arrived by the time of trial, the
    retainage issue was premature and Scarsella is not entitled to interest on the retained
    sum under RCW 39.76.011.
    The trial court did not abuse its discretion in denying prejudgment interest. So,
    we affirm.
    Attorney Fees on Appeal
    Both Scarsella and Flatiron request attorney fees and costs on appeal. But,
    neither is the prevailing party on appeal. Each has prevailed on one or more major
    issues. So we deny both requests.
    CONCLUSION
    We affirm. The prime contract notice and claim provisions apply to Scarsella’s
    claim for extra work because the subcontract broadly incorporated the prime contract,
    Flatiron did not waive the prime contract provisions, and Scarsella’s claim for estoppel
    fails. Because Scarsella did not comply with the notice and claims requirements, it
    waived its right to recovery and quantum meruit is unavailable. Scarsella’s claim for
    foreclosure of the lien on retainage was premature because the prime contract date of
    completion had not arrived by the time of trial. Neither Scarsella nor Flatiron is the
    29
    No. 78543-5-I/30
    prevailing party, and neither party is entitled to trial fees and costs. Scarsella did not
    prevail on a liquidated claim, and the trial court did not abuse its discretion in denying
    prejudgment interest. Flatiron breached the subcontract “by causing the substantial
    project delays.” We deny Scarsella and Flatiron’s requests for attorney fees and costs
    on appeal.
    WE CONCUR:
    30