Gene Busroe And Sue Busroe, Apps. v. Dreamers Rod, Res. ( 2017 )


Menu:
  •        IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
    GENE BUSROE and SUE BUSROE,
    husband and wife,                                No. 74212-4-1
    Appellants,                 DIVISION ONE
    UNPUBLISHED OPINION
    DREAMERS ROD, CUSTOM &
    PICK-UPS N.W., INC.,
    Respondents.                FILED: January 17, 2017
    Leach, J. — Gene Busroe appeals the dismissal of his lawsuit against a
    business that did some restoration work on his classic pickup truck.      Because
    substantial evidence supports the trial court's challenged findings of fact and
    those findings support its conclusions of law, we affirm.
    FACTS
    According to unchallenged findings of fact entered after a 2015 bench trial,
    Gene Busroe purchased a 1955 Chevrolet pickup truck, planning to restore it as
    a retirement project.   When he purchased the truck, it had a heavily rusted
    exterior body and needed virtually all parts and mechanical systems replaced.
    Busroe enrolled in classes on body and electrical work at a local technical
    college.
    NO. 74212-4-1/2
    Dreamers Rod, Custom & Pick-ups N.W. Inc. operates two shops where it
    performs restoration work and fabricates vehicle parts.    Its owners agreed to
    allow Busroe to store his vehicle and to use shop space to do his own restoration
    work. Busroe did this for several years. During the same time, he also hired
    Dreamers to perform specific tasks. The arrangement with Dreamers amounted
    to a series of oral contracts.
    During this period, Busroe took the disassembled body of the truck to
    another business, Alternative Blasters, for "bead blasting," a process that
    prepares metal for painting by removing existing paint, primer, and rust, leaving
    only bare metal.      When Alternative Blasters completed that work, Busroe
    transported the body pieces on a flatbed trailer to Dreamers' shop.     Later, an
    employee of Dreamers prepared them for painting, and a Dreamers'
    subcontractor painted the truck.
    The restoration work was complete in 2009. Busroe then participated in
    car shows and other events, winning some awards.
    In 2011, Busroe noticed defects in the paint. On some areas of the truck
    body, small bubbles and blisters appeared on the surface of the paint. Since
    then, the bubbling and blistering has spread and become increasingly more
    pronounced.
    NO. 74212-4-1/3
    In August 2013, Busroe and his spouse (collectively "Busroe") sued
    Dreamers.1     Busroe contended that Dreamers' employees failed to "properly
    paint the vehicle" and that he incurred damages as a result. His complaint did
    not identify a specific legal cause of action.
    During a two-day trial, the court considered the testimony of ten witnesses
    and several exhibits. The trial court entered a judgment in favor of Dreamers that
    dismissed Busroe's complaint with prejudice. Busroe appeals.
    ANALYSIS
    Busroe challenges finding of fact 6 insofar as it specifies September 28,
    2006, as the date he delivered the truck parts from Alternative Blasters after
    bead blasting to Dreamers' shop.       He also challenges the finding, included in
    both findings of fact 11 and 17, that a "three year gap" occurred between the
    bead blasting process and the eventual priming and painting of the vehicle in
    2009.
    Busroe contends no evidence in the record supports the finding that the
    bead blasting took place in 2006. He further claims that without this finding, the
    record contains no factual support for several conclusions of law.        In these
    conclusions, the court explained that Busroe failed to establish that Dreamers'
    conduct proximately caused the deterioration of the paint:
    1 The record on review includes only the amended complaint filed in
    November 2013.
    -3-
    NO. 74212-4-1/4
    3.   Plaintiff's general theory of the case is that Defendant took
    some action, which they did not specify, that caused rust to
    form on the truck, thereby causing Plaintiff damage. Here
    the Court concludes that the metal body of the truck was in a
    rusted condition at the time it was purchased by Plaintiff as
    shown by the photos introduced into evidence. Plaintiff
    sought to remove that rust by having the metal pieces
    beadblasted by a third party. This work was ineffective to
    remove all of the rust as shown by Defendant in Invoice
    1428. (Exhibit 52).      The Plaintiff did not prove that it
    contracted with Defendant to remove any, let alone all of the
    rust on the truck. Further, the evidence showed the Plaintiff
    introduced water on the truck parts in delivering [them to the]
    Defendant. Defendant was not responsible for causing the
    metal to be in a wet condition. The evidence proved that
    Defendant was not responsible for causing the metal parts to
    rust. The Plaintiff failed to show that Defendant proximately
    caused the rust damage to the truck. Accordingly, the Court
    finds in favor of the Defendant as to this claim and dismisses
    the complaint with prejudice.
    4.    As an alternative theory of liability, viewing the Complaint
    more narrowly, it is possible that Plaintiff's complaint,
    although not specifically [pleaded], refers to the particular
    oral contract in which he hired Defendant [to] apply sealant
    to the truck after the beadblast work, and that Defendant's
    action in sealing the truck while it was in a wet and/or rusted
    condition breached a duty to Plaintiff to perform the sealant
    work in a "workmanlike manner." There is no dispute that
    this work was performed in 2006. However, the court finds
    that this argument must fail as well. Defendant put Plaintiff
    on notice of its actions ("removed the rust as best they
    could"), in Invoice 1428. Plaintiff had actual knowledge or
    should have known from the notation on the invoice that he
    had a rust problem under the sealant. Plaintiff seems to
    argue that he was ignorant to the significance of that
    problem because he was a novice. He claims he discovered
    the truck had a rust problem in 2011, when it became visible
    due to the bubbling of the paint job.
    -4-
    NO. 74212-4-1/5
    5.    Even if one could argue Plaintiff lacked actual knowledge of
    the spreading rust until 2011, the 2006 invoice at least put
    him on "inquiry notice" and he should have done further
    investigation about the rust issue at that time. This was not
    done. Assuming arguendo that Plaintiff had a cause of
    action for breach, it accrued on the date when he could have
    sought relief from the courts. Here, that date was on
    October 5, 2006. According to RCW 4.16.080, the statute of
    limitations ran on the oral contract three years later in
    October of 2009. The Complaint in this case was not filed
    until August of 2013, four years after the statute of limitations
    ran. Accordingly, under this theory, the Court finds in favor
    of the Defendant and dismisses the Plaintiffs claim with
    prejudice.
    We review a trial court's decision after a bench trial to determine whether
    substantial evidence supports the trial court's findings of fact and whether the
    findings of fact adequately support the conclusions of law.2 Substantial evidence
    is the quantum of evidence sufficient to persuade a rational, fair-minded person
    that the premise is true.3 We treat unchallenged findings of fact as verities on
    appeal.4
    The record amply supports the court's finding that the bead blasting
    occurred in 2006. The testimony at trial established that Dreamers' employees
    recorded tasks performed, time spent on each task, and parts used on a daily
    basis. Dreamers used this information to generate customer invoices. Dreamers
    2 Endicott v. Saul, 
    142 Wash. App. 899
    , 909, 
    176 P.3d 560
    (2008).
    3 
    Endicott, 142 Wash. App. at 909
    .
    4 Kitsap County v. Kitsap Rifle & Revolver Club, 
    184 Wash. App. 252
    , 267,
    
    337 P.3d 328
    (2014), review denied, 
    183 Wash. 2d 1008
    (2015).
    -5-
    NO. 74212-4-1/6
    presented evidence of an invoice it created for Busroe that included the following
    entry dated September 28, 2006:
    Steve helped Gene unload the bare metal from the trailer, into the
    shop. (Note) Some of the parts that were exposed to the morning
    moist air. These parts were wet with morning fog and water spray
    off the tires. Steve tried to dry those areas he could see and get to
    with a torch and a rag.
    The next entry on the same invoice, dated October 5, 2006, also records
    work performed by the same Dreamers' employee, Steve Strabeck. The entry
    states,
    Lay out parts and mask areas to be metal worked by owner at later
    time, one stepped deep pits that still had rust in them after the
    blast. One stepped the frame as best as we could, there was deep
    rust pits and heavy rust was laying in the shallowed parts of these
    areas.
    The final entry on this invoice, dated the following day, October 6, 2006, again
    records work performed by Strabeck: "Seal frame/fenders/doors and steps with
    D.P. Sealer materials."
    These entries support the court's finding that the bead blasting took place
    in 2006. The entry describes the parts that Busroe delivered to the shop in
    September 2006 as "bare metal," indicating that the delivery occurred after bead
    blasting. Busroe's testimony also corroborates this inference. Although he did
    not specify a date, Busroe said that after bead blasting he transported the parts
    to Dreamers' shop on a flatbed trailer and covered them with only a tarp. He
    NO. 74212-4-1/7
    acknowledged that the parts "very well" may have become wet in transit. The
    September 2006 entry also reflects Strabeck's concern that the bare metal parts
    had been exposed to moisture and water.
    Strabeck testified that he remembered the delivery because the metal was
    exposed to water, which caused him to be concerned about rust. Busroe also
    confirmed that Strabeck helped him unload the parts and performed the sealing
    work to prepare the truck body for painting.     Strabeck left his employment at
    Dreamers sometime around 2006. The October 5 entry further indicates that the
    bead blasting occurred on or before September 28 because it describes
    Strabeck's attempt to seal the metal despite rust remaining "after the blast."
    Still, Busroe claims that he brought the vehicle parts to the shop in
    September 2006 before they had been bead blasted. He points to the testimony
    of one of the owners of Dreamers who indicated that the September 2006 entry,
    also designated as work order number 1 ("WO#1"), was the first invoice
    Dreamers generated for Busroe and therefore reflected the "first time that the
    project showed up at the shop."       But this testimony does not undermine or
    contradict the court's finding that bead blasting occurred on or before September
    28, 2006. Busroe also relies on his own testimony that he believed two weeks to
    a month elapsed between bead blasting and painting.         But the court was not
    required to credit Busroe's unsubstantiated and vague recollection instead of
    -7-
    NO. 74212-4-1/8
    documents containing information recorded simultaneously with the events in
    question.
    Busroe does not challenge the court's finding that according to several
    experts who testified at trial, "the truck should have been primed and painted
    within 2-3 days after the sealant was applied, to protect the metal." Busroe's
    testimony about timing fails to establish compliance with this protocol. Perhaps
    more importantly, Busroe's argument fails to appreciate that there were multiple
    reasons why the court determined that Dreamers was not responsible for the
    eventual deterioration of the paint under either a tort of contract theory of liability.
    The court found that the proper procedure before painting is to "blast the parts to
    bare metal with all rust removed, and then to apply sealer as soon as possible
    without allowing any moisture onto the metal." Regardless of when the bead
    blasting took place,'the court found that the process failed to remove all rust and
    Busroe allowed the metal parts to be exposed to moisture and become wet.
    These findings alone provide sufficient support for the court's conclusion that
    Dreamers' conduct did not proximately cause the damage to the paint.
    Substantial evidence supports the court's finding about the timing of the
    bead blasting work.      This finding, together with other unchallenged findings,
    supports the court's conclusions of law. Because Busroe's challenges to the
    sufficiency of the evidence to support the trial court's findings fail, we need not
    -8-
    NO. 74212-4-1/9
    address his alternative arguments about the former "economic loss rule" and the
    statute of limitations.5
    Affirmed.
    WE CONCUR:
    S"n^T *-'                                 ^Q^v^g,a^
    5 See Eastwood v. Horse Harbor Found., Inc.. 
    170 Wash. 2d 380
    , 393-94,
    
    241 P.3d 1256
    (2010).
    -9-
    

Document Info

Docket Number: 74212-4

Filed Date: 1/17/2017

Precedential Status: Non-Precedential

Modified Date: 4/17/2021