J.F. Allen Corporation v. The Sanitary Board of the City of Charleston and Burgess and Niple v. J.F. Allen Corporation ( 2020 )


Menu:
  •                                  STATE OF WEST VIRGINIA
    SUPREME COURT OF APPEALS
    J. F. Allen Corporation, a
    West Virginia corporation,
    Plaintiff Below, Petitioner,                                                       FILED
    vs) No. 19-0369 (Kanawha County 14-C-1182)                                     October 16, 2020
    released at 3:00 p.m.
    EDYTHE NASH GAISER, CLERK
    The Sanitary Board of the City of Charleston,                                   SUPREME COURT OF APPEALS
    OF WEST VIRGINIA
    West Virginia, a municipal utility, and
    Burgess and Niple, Inc., an Ohio corporation,
    Defendants Below, Respondents,
    And
    Burgess and Niple, Inc., an Ohio corporation,
    Defendant Below, Petitioner,
    vs) No. 19-0394 (Kanawha County 14-C-1182)
    J. F. Allen Corporation, a West Virginia corporation,
    Plaintiff Below/Respondent.
    MEMORANDUM DECISION
    These consolidated appeals were filed by parties to a breach of contract/negligence
    action arising out of a sewer improvement project, which action was tried to jury verdict in the
    Circuit Court of Kanawha County. The jury rendered a verdict in favor of plaintiff J. F. Allen
    Corporation (hereinafter “J. F. Allen”), 1 finding that defendant The Sanitary Board of the City of
    Charleston (hereinafter “the Sanitary Board”) breached its contract with J. F. Allen and awarded
    damages in the amount of $1,300,000.20. The jury further determined that defendant Burgess &
    Niple, Inc. (hereinafter “B & N”), 2 had committed professional negligence, awarding damages in
    the amount of $3,000,000.20, which was reduced by a 10% apportionment of comparative
    negligence against J. F. Allen, resulting in a net judgment of $2,700,000.18.
    Upon post-trial motions filed by the Sanitary Board and B & N (collectively
    “defendants”), the circuit court granted a new trial on damages only, finding that the jury’s verdict
    was inconsistent, unsupported by evidence, violated the “single recovery” rule, and could not be
    1
    J. F. Allen is represented by counsel, Charles M. Johnstone, II, and Johnson W. Gabhart,
    Esq., Johnstone & Gabhart, LLP, Charleston, West Virginia.
    2
    B & N is represented by counsel, Peter T. DeMasters, Esq. and Michael A. Secret, Esq.,
    Flaherty Sensabaugh Bonasso, PLLC, Charleston, West Virginia.
    1
    corrected with remittitur. More specifically, the circuit court found that J. F. Allen had submitted
    evidence in support of only $1.2 million in damages, yet the jury awarded well in excess of that
    amount both as against each defendant and in the aggregate. Because of such excess, the court
    concluded that while it could theoretically remit the verdict, it could not properly apportion
    damages between the defendants. The circuit court also denied defendants’ renewed motions for
    judgment as a matter of law, finding that in viewing the evidence in the light most favorable to J.
    F. Allen, the jury’s liability verdict should stand. All three parties appealed, which appeals were
    consolidated for consideration by the Court. 3
    This Court has considered the parties’ briefs, oral arguments, and the record on
    appeal. Upon consideration of the standard of review and the applicable law, we find no substantial
    question of law presented nor prejudicial error. For these reasons and those set forth herein, a
    memorandum decision affirming the circuit court’s order is appropriate under Rule 21 of the West
    Virginia Rules of Appellate Procedure.
    I. Factual and Procedural History
    J. F. Allen contracted with the Sanitary Board to serve as contractor for a sanitary
    sewer replacement project on Kanawha Two-Mile Creek; B & N contracted separately with the
    Sanitary Board to serve as engineer/architect for the project, providing design and contract
    administration services including review of disputes and requests for adjustments. The project
    began on January 9, 2012, and was scheduled for completion by February 1, 2013; however,
    certain delays occurred which were caused by strikes on unmarked or mismarked underground
    facilities.
    J. F. Allen submitted its request for final payment on November 4, 2013, which
    payment was issued on November 20, 2013. Nearly six months later, on May 7, 2014, J. F. Allen
    submitted a “Request for Equitable Adjustment” (“REA”) in the amount of $1,309,943.00 pursuant
    to the contract, for additional costs and expenses resulting from delays occasioned by the
    underground facility strikes. B & N, as arbiter of disputes under the contract, advised that since
    the construction phase had been completed, it was “no longer authorized to provide professional
    services for this project.” Accordingly, the REA was rejected, prompting the filing of the instant
    action.
    The parties’ handling of the delays caused by the underground utility strikes and
    the resultant extra costs are primarily at issue in the instant action. 4 In the trial below, J. F. Allen
    admitted that it did not file a written claim for additional delay costs as described in its contract
    3
    An appeal was also filed by the Sanitary Board which was consolidated with the instant
    appeals. Prior to oral argument, the Sanitary Board reached a settlement with J. F. Allen and
    withdrew its appeal. J. F. Allen likewise withdrew its appeal as against Sanitary Board, leaving
    only the issues raised with regard to B & N in its appeal.
    4
    In addition to the underground utility strikes, J. F. Allen also alleged that work performed
    by other contractors caused additional delay and that certain restoration and paving work was
    required that was not otherwise accounted for in the contract price.
    2
    with the Sanitary Board. However, witnesses testified that the Sanitary Board’s contractual
    representative—B & N—provided resident project representatives who were onsite daily and
    maintaining written reports about the strikes. J. F. Allen presented evidence that these
    representatives were made aware of the resulting delays and told to take careful notes about them
    for purposes of a future claim for reimbursement. Alan Shreve, an employee of J. F. Allen, testified
    that he regularly advised B & N representatives of the strikes, delays, and mounting costs and was
    told, “We’ll make you good on it.” Testimony was also adduced that change orders for additional
    costs were handled in a manner that did not strictly comply with the contract, but rather through
    informal dealings. J. F. Allen contended B & N was advised through a series of letters about delays
    and interruptions in the work and that the contract required B & N to immediately address such
    unexpected delays by way of change orders.
    In its defense, B & N argued that J. F. Allen admittedly failed to comply with the
    contract’s claims process, which was the exclusive remedy for any additional costs and required
    timely written notice of such claims. It argued further that the contract expressly provided that
    any claims not made or identified by submission of the request for final payment were waived. B
    & N countered that it was not made aware that the strikes were causing significant delays and that,
    in fact, J. F. Allen reported “no delays” during monthly meetings. It maintained that the project
    was expected to be finished on time until a few months prior to the original completion date. B &
    N also adduced evidence that it urged J. F. Allen to submit any claims for additional payments “as
    soon as possible,” but J. F. Allen failed to do so. When J. F. Allen submitted its request for final
    payment, no outstanding claims were identified as required by the contract. B & N argued that,
    after the final payment was issued, the “construction phase” as defined by the contract was
    completed and therefore, its authority to act on any further claims relating to the contract had
    ended.
    The Contracts
    At trial, the parties introduced the pertinent contracts between J. F. Allen and the
    Sanitary Board (the “Contractor Agreement”) and the Sanitary Board and B & N (the “Engineer
    Agreement”). With respect to underground facilities, the Contractor Agreement contains a section
    regarding “Underground Facilities” entitled “Not Shown or Indicated.” It states that if
    underground facilities are revealed that were not shown or indicated in the contract documents, the
    contractor shall, inter alia,
    give written notice to . . . [the] Engineer. Engineer will promptly
    review the Underground Facility and determine the extent, if any, to
    which a change is required in the Contract Documents to reflect and
    document the consequences of the existence or location of the
    Underground Facility. . . . If Engineer concludes that a change in
    the Contract Documents is required, a Work Change Directive or a
    Change Order will be issued to reflect and document such
    consequences. An equitable adjustment shall be made in the
    Contract Price or Contract Times, or both, to the extent that they are
    attributable to the existence or location of any Underground Facility
    that was not shown or indicated or not shown or indicated with
    3
    reasonable accuracy in the Contract Documents and that Contractor
    did not know of and could not reasonably have been expected to be
    aware of or to have anticipated. If Owner and Contractor are unable
    to agree on entitlement to or on the amount or extent, if any, of any
    such adjustment in Contract Price or Contract Times, Owner or
    Contractor may make a Claim therefor . . . .
    (emphasis added). With respect to the handling of any such “claims,” the Contractor Agreement
    provides that
    [a]ll Claims, 5 except those waived . . . shall be referred to the
    Engineer for decision. A decision by Engineer shall be required as
    a condition precedent to any exercise by Owner or Contractor of any
    rights or remedies either may otherwise have under the [contract] . .
    . or by Laws and Regulations in respect of such Claims.
    (footnote added). The Contractor Agreement further requires that “[w]ritten notice stating the
    general nature of each Claim shall be delivered by the claimant to Engineer . . . promptly (but in
    no event later than 30 days) after the start of the event giving rise thereto” and that “[i]n the event
    that Engineer does not take action on a Claim within said 30 days, the Claim shall be deemed
    denied.” Further, “[n]o Claim for an adjustment in Contract Price . . . will be valid if not submitted
    in accordance with [the contract].”
    With respect to “Final Application for Payment,” the Contractor Agreement
    provides that such application “shall be accompanied by . . . a list of all Claims against Owner that
    Contractor believes are unsettled[.]” More specifically,
    [t]he making and acceptance 6 of final payment will constitute . . . a
    waiver of all Claims by Owner against Contractor . . . [and] a waiver
    of all Claims by Contractor against Owner other than those
    previously made in accordance with the requirements herein and
    expressly acknowledged by Owner in writing as still unsettled.
    (footnote added).
    The pertinent portions of the Engineer Agreement state, inter alia, that “Engineer
    will be Owner’s representative during the construction period” and “[t]he Construction Phase . . .
    5
    A “claim” is defined in the contract as a “demand or assertion . . . seeking an adjustment
    of Contract Price . . . or other relief with respect to the terms of the Contract.” The contract
    provides that “if Owner and Contractor are unable to agree on entitlement to or on the amount or
    extent, if any, of any adjustment in the Contract Price or Contract Times that should be allowed as
    a result of such other work, a Claim may be made therefor . . . .”
    6
    J. F. Allen never cashed the check for this final payment and therefore argued at trial that
    it was not “accepted.”
    4
    will terminate upon written recommendation by Engineer for final payment to Contractors.” It
    provides further that B & N will be the “initial interpreter of the requirements of the contract and
    all disputes regarding the interpretation of the contract or acceptability of the work are to be
    submitted to B & N for resolution.” In that regard, “[w]hen functioning as interpreter and judge .
    . . Engineer will not show partiality to Owner or Contractor and will not be liable in connection
    with any interpretation or decision rendered in good faith in such capacity.” Moreover,
    [n]either Engineer’s authority or responsibility under [the contract]
    . . . nor any decision made by Engineer in good faith either to
    exercise or not exercise such authority or responsibility or the
    undertaking, exercise, or performance of any authority or
    responsibility by Engineer shall create, impose, or give rise to any
    duty in contract, tort, or otherwise owed by Engineer to Contractor
    ....
    The Civil Action and Prior Appeal
    Upon rejection of the REA, J. F. Allen filed suit against the defendants, alleging
    breach of contract and unjust enrichment 7 against the Sanitary Board and negligence against B &
    N. More specifically, J. F. Allen contended that B & N failed to investigate or initiate change
    orders or other reimbursement for delays and costs stemming from the underground facility strikes
    despite actual notice of these events. It further alleged more generally that B & N failed to properly
    administer the project by refusing to recommend payment of the REA. As against the Sanitary
    Board, J. F. Allen alleged that the contract unequivocally required it to reimburse J. F. Allen for
    delay costs resulting from unmarked or mismarked utilities. Neither defendant filed a cross-claim
    for indemnification or contribution. 8
    The circuit court dismissed the case against the Sanitary Board, which dismissal
    was appealed to this Court. See J. F. Allen Corp. v. Sanitary Bd. of City of Charleston, 237 W.
    Va. 77, 
    785 S.E.2d 627
    (2016) (“J. F. Allen I”). The Court reversed and remanded, rejecting the
    circuit court’s dispositive conclusion that the contract placed the burden of investigation regarding
    underground facilities on J. F. Allen. The Court concluded, instead, that the contract “expressly
    provided for a possible equitable adjustment of the contract price as a result of the existence of an
    underground facility not shown on the construction plans[.]”
    Id. at
    82, 785 
    S.E.2d at 632. In
    response to the Sanitary Board’s contention that the case was barred by J. F. Allen’s failure to
    comply with the written notice contractual provisions, the Court found that “the complaint alleged
    that [the Sanitary Board] had actual notice through its onsite representative who documented each
    event as it occurred [which] . . . . could constitute a written notice if viewed in the light most
    7
    The circuit court dismissed the unjust enrichment claim and that dismissal was not
    appealed. It was likewise omitted from the amended complaint.
    8
    The Sanitary Board filed a counter-claim against J. F. Allen seeking liquidated damages
    under the contract for the delays. The jury found that the Sanitary Board was not entitled to such
    damages.
    5
    favorable to J. F. Allen.”
    Id. Alternatively, the Court
    found that factual development may reveal
    that the Sanitary Board waived the notice requirement “by failing itself to comply with the
    provision.”
    Id. Specifically, the Court
    concluded:
    [W]hether J. F. Allen did, in fact, satisfy the requirements of the
    contract, and whether [the Sanitary Board] did, in fact, breach its
    obligations under the contract or whether elements of the contract
    were waived or amended by the parties, are questions of fact that
    should only be resolved after the parties have had an opportunity to
    engage in discovery.
    Id. at
    83, 785 
    S.E.2d at 633 (emphasis added).
    The Trial
    The trial lasted eight days. In addition to evidence in support of their respective
    positions 
    outlined supra
    , J. F. Allen presented the testimony of Charles Dutill, an engineering
    expert offered in the field of design and administration of public works utility construction
    projects. Mr. Dutill testified that B & N failed to comply with the applicable standard of care in
    administering the contract. Neither defendant offered an expert in rebuttal.
    J. F. Allen also introduced the REA into evidence, along with testimony from its
    author, Bryon Willoughby. During his testimony, Mr. Willoughby briefly referenced that J. F.
    Allen was over budget $3 million but did not provide a further itemization of this amount. J. F.
    Allen’s president, Greg Hadjis, also made reference during his testimony to the various effects of
    the delays caused by underground utility strikes, such as costs of accelerating the project work,
    extending work hours, increased costs for home office support and management, additional jobsite
    visits, surveying, and additional costs incurred to maintain its safety program.
    During closing arguments, while referencing the verdict form, counsel for J. F.
    Allen stated:
    If you answer questions 1 and 2 yes, please assess damages. . . . The
    damages are the same that we assert against both of these entities.
    Okay. So of this amount, you’ve got to decide how much you want
    to put against the Sanitary Board and what you want to put against
    [B & N].
    (emphasis added). Later, while explaining the verdict form and how to respond to the
    interrogatories, counsel (referring to the interrogatories against B & N) stated: “Finally, so there
    would be no [comparative fault] percentage and you put in number 3 hopefully the rest of the
    money . . . .” (emphasis added). Counsel utilized a demonstrative exhibit which identified
    $1,252,392.43 in damages and made reference to “this number” in explaining the verdict form.
    After initial deliberations, the jury submitted a question to the circuit court, asking
    “Do we assess the dollar amount, Question 3, Part II [damages for breach of contract against the
    6
    Sanitary Board], and if yes, on what basis?” Later (and apparently before the first question was
    answered), the jury returned to the courtroom, submitting additional questions. The first question
    appears to reiterate the unanswered question regarding breach of contract damages, inquiring
    “What is this amount based on?” After the circuit court answered the question by advising the
    jury to recall the witnesses, evidence, and exhibits, the foreperson inquired as to whether the jury
    had the demonstrative exhibit utilized by J. F. Allen’s counsel during closing in its possession; the
    jury had also prepared a written question to this effect. Finally, the court read an additional
    question referencing the verdict form’s instruction to “assign a percentage of fault below,”
    whereupon the jury inquired “what is this and is it based [sic]?” with the foreperson’s addition that
    “[w]hat does the hundred percent equal?” The court re-read the comparative fault instruction to
    the jury, prompting the foreperson to advise, “That helps.”
    Thereafter, the jury returned to deliberate and ultimately returned a verdict in favor
    of J. F. Allen, finding breach of contract by the Sanitary Board and negligence by B & N. Upon
    entering the courtroom, the foreperson stated, “We got it right, this time.” It found 90% negligence
    against B & N and 10% negligence against J. F. Allen. However, on the verdict form, it only
    awarded damages in the section addressing the breach of contract by the Sanitary Board, leaving
    the damages portion of the verdict form pertaining to B & N blank. It awarded damages against
    the Sanitary Board in the amount of $1,300,000.20.
    Defendants both moved for a mistrial, which was denied. The circuit court noted
    that the jury “got that they [were] supposed to give one recovery but may not have apportioned it
    among the defendants.” The court indicated that it needed to “flesh out” if the jury intended to
    assess the entire verdict against the Sanitary Board or intended to apportion it between the
    defendants. Counsel for J. F. Allen agreed, stating, “Yes, your Honor. Did they intend for that to
    be zero damages [against B & N] or was it their intention that the one-point three-million be split
    between the defendants[?]” The circuit court reassembled the jury and asked them to return to the
    jury room and “focus on” question 3, telling them “what I need to know . . . was it your intent to
    award zero damages against Burgess and Niple?”
    After returning for further deliberations, the jury submitted yet another question:
    “What dollar amount are we assessing for (in question 3) [damages for negligence against B & N]
    or do we come up with the dollar amount?” Before the question was answered, the jury returned
    a verdict, having filled in the damages blank against B & N, awarding $3,000,000.20. Upon
    entering the courtroom, the foreperson allegedly stated “We did get it right this time,” although B
    & N maintains that this statement was not accurately transcribed and that the foreperson actually
    said, “If we didn’t get it right this time, we quit.” (emphasis added). Defendants again moved for
    a mistrial, which the circuit court denied.
    On March 20, 2019, the circuit court issued an order granting a new trial on
    damages and denying the defendants’ renewed motions for judgment as a matter of law. As
    pertained to the new trial on damages, the circuit court found that the verdict was “inconsistent,
    []not based on the evidence or [] against the clear weight of the evidence, [and] impermissibly
    award[ed] damages in excess of a single recovery[.]” The circuit court found that J. F. Allen
    sought only “$1.25 million total in damages for the recovery of a single injury” and that the jury’s
    verdict—both individually against each defendant and collectively—exceeded that amount. The
    7
    court further noted the jury’s “general confusion and misunderstanding[.]” Further, it found that
    given the “multiplicity of claims and defendants with respect to the single injury in this case . . . it
    is impossible for the [c]ourt to discern which of the two Defendants should have to pay if the
    [c]ourt were to remit damages . . . without additional factual findings.”
    With respect to the defendants’ renewed motions for judgment as a matter of law,
    the circuit court found that, giving J. F. Allen the benefit of all reasonable inferences, the liability
    verdicts were proper. These appeals followed.
    II. Standard of Review
    Multiple standards of review are implicated here. As to B & N’s motion for
    judgment as a matter of law, “[t]he appellate standard of review for an order granting or denying
    a renewed motion for a judgment as a matter of law after trial pursuant to Rule 50(b) of the West
    Virginia Rules of Civil Procedure [1998] is de novo.” Syl. Pt. 1, Fredeking v. Tyler, 
    224 W. Va. 1
    ,
    
    680 S.E.2d 16
    (2009). Further,
    [w]hen this Court reviews a trial court’s order granting or denying a
    renewed motion for judgment as a matter of law after trial under
    Rule 50(b) of the West Virginia Rules of Civil Procedure [1998], it
    is not the task of this Court to review the facts to determine how it
    would have ruled on the evidence presented. Instead, its task is to
    determine whether the evidence was such that a reasonable trier of
    fact might have reached the decision below. Thus, when considering
    a ruling on a renewed motion for judgment as a matter of law after
    trial, the evidence must be viewed in the light most favorable to the
    nonmoving party.
    Syl. Pt. 2, Fredeking, 
    224 W. Va. 1
    , 
    680 S.E.2d 16
    . (emphasis added). With respect to the circuit
    court’s ruling on the motions for a new trial:
    In reviewing challenges to findings and rulings made by a
    circuit court, we apply a two-pronged deferential standard of review.
    We review the rulings of the circuit court concerning a new trial and
    its conclusion as to the existence of reversible error under an abuse
    of discretion standard, and we review the circuit court’s underlying
    factual findings under a clearly erroneous standard. Questions of law
    are subject to a de novo review.
    Syl. Pt. 3, State v. Vance, 
    207 W. Va. 640
    , 
    535 S.E.2d 484
    (2000). “Although the ruling of a trial
    court in granting or denying a motion for a new trial is entitled to great respect and weight, the
    trial court’s ruling will be reversed on appeal when it is clear that the trial court has acted under
    some misapprehension of the law or the evidence.” Syl. Pt. 4, Sanders v. Georgia-Pac. Corp., 
    159 W. Va. 621
    , 
    225 S.E.2d 218
    (1976). With respect to the specific trial errors alleged, those are
    uniformly reviewed under an abuse of discretion standard. With these standards in mind, we
    proceed to the parties’ arguments.
    8
    III. Discussion
    The parties’ primary assignments of error pertain to the circuit court’s
    determination that the verdict was unsupported by the evidence and therefore a new trial on
    damages was necessary. However, as a threshold matter, B & N also assigns as error the circuit
    court’s denial of its motion for judgment as a matter of law, arguing that the contractual language
    warrants judgment in its favor. Finally, B & N also asserts a variety of trial errors including 1)
    allowing introduction of the REA as substantive evidence; 2) refusing to give an intervening cause
    instruction; 3) permitting a non-West Virginia licensed engineer to testify as an expert; and 4)
    allegedly prejudicial remarks made during closing argument.
    1.     JUDGMENT AS A MATTER OF LAW
    B & N initially assigns as error the circuit court’s refusal to grant it judgment as a
    matter of law. It argues that, notwithstanding J. F. Allen’s allegations of negligence against it, the
    contractual language entitles it to judgment as a matter of law because 1) J. F. Allen failed to follow
    the claims process as required by the contract; 2) it had no contractual authority to act after the
    final payment was rendered; and 3) it did not act in bad faith, as purportedly required for it to be
    liable under the contract. J. F. Allen responds that B & N owes a professional duty of care
    irrespective of the contract terms, but also, that B & N’s abrogation of its own contractual duties
    as contained in the Engineering Agreement is evidence of its negligence.
    Syllabus point six, in part, of Eastern Steel Constructors, Inc. v. City of Salem, 
    209 W. Va. 392
    , 
    549 S.E.2d 266
    (2001) holds that “[a] design professional (e.g. an architect or
    engineer) owes a duty of care to a contractor, who has been employed by the same project owner
    as the design professional and who has relied upon the design professional’s work product in
    carrying out his or her obligations to the owner . . . .” Importantly, syllabus point seven elaborates,
    in part, that “the duty of care owed by the design professional to the contractor must be defined on
    a case-by-case basis.”
    Id. (emphasis added). In
    that regard, the Eastern Steel Court explained
    further:
    We note that the exact nature of the specific duty owed by a design
    professional may be impacted by provisions contained in the various
    contracts entered among the parties (e.g. the contract between the
    owner and the design professional, and the contract between the
    owner and the contractor), provided that such contractual provisions
    do not conflict with the law.
    Id. at
    401, 549 S.E.2d at 275 
    (emphasis in original). Despite the Court’s emphasis on “may” in
    this dicta, B & N urges us to read this statement as conclusively holding that contractual language
    must nonetheless form the outer boundary of liability under a professional negligence cause of
    action.
    This Court has long held:
    “The questions of negligence, contributory negligence, proximate
    cause, intervening cause and concurrent negligence are questions of
    9
    fact for the jury where the evidence is conflicting or when the facts,
    though undisputed, are such that reasonable men draw different
    conclusions from them.” Syl. Pt. 2, Evans v. Farmer, 
    148 W. Va. 142
    , 
    133 S.E.2d 710
    (1963).
    Syl. Pt. 10, Harbaugh v. Coffinbarger, 
    209 W. Va. 57
    , 
    543 S.E.2d 338
    (2000). As 
    discussed supra
    ,
    this Court addressed much of the contract language at issue in J. F. Allen I—particularly as pertains
    to the claims process outlined in the Contractor Agreement—and found that, standing alone, it was
    not dispositive of even the breach of contract claim against the Sanitary Board. Rather, the Court
    properly recognized a variety of disputed factual issues which give rise to potential defenses to the
    contract such as modification and waiver. J. F. Allen 
    I, 237 W. Va. at 82
    , 785 S.E.2d at 632. The
    facts adduced at trial, viewed in the light most favorable to J. F. Allen, plainly support the
    availability of these defenses.
    Critically, these same factual disputes are centerpieces to J. F. Allen’s allegations
    of professional negligence and B & N’s commensurate allegations of comparative negligence.
    Indeed, the jury’s assessment of ten percent comparative negligence to J. F. Allen reflects a
    consideration of whether its conduct contributed to its losses, as argued by B & N. Moreover,
    while B & N adamantly insists the contract immunizes it for all but “bad faith” conduct, the
    appendix record reveals that it submitted no instructions requiring the jury to find “bad faith” in
    its contract administration, nor did B & N make this argument to the jury in closing. We therefore
    find that the issues surrounding B & N’s liability were matters properly reserved for the jury’s
    consideration and the circuit court committed no error in denying its motion for judgment as a
    matter of law. However, whether B & N is entitled to have the liability and damages
    determinations against it set aside and a new trial awarded as a result of irregularities in the jury’s
    verdict is a separate issue, to which we now turn.
    2.     NEW TRIAL
    We turn now to the central, two-pronged issue presented in these appeals. We
    consider whether the circuit court erred in granting a new damages trial and, if not, whether it erred
    in granting a new trial on damages alone, rather than both liability and damages. The circuit court
    found that the verdict was “inconsistent,” “excessive,” and potentially rendered a double recovery
    for a single injury, but that the liability verdict was not compromised by any deficiency in the
    verdict and should stand. 9 More specifically, the circuit court concluded that J. F. Allen only
    introduced evidence to support a damages award of approximately $1.2 million and therefore the
    9
    As pertains to damages, the court and the parties focus on the “double recovery”
    prohibition in Syllabus point seven, in part, of Harless v. First Nat’l Bank in Fairmont, 169 W.
    Va. 673, 
    289 S.E.2d 692
    (1982): “A plaintiff may not recover damages twice for the same injury
    simply because he has two legal theories.” While theoretically the verdict could be viewed as a
    double recovery since the jury split its allegedly excessive verdict between two defendants against
    whom two different theories of recovery were made, it is ultimately of no consequence whether it
    was a double recovery or merely excessive. Under either scenario, it must be properly supported
    by the evidence at trial.
    10
    jury’s verdict, which exceeded that amount—both individually and in the aggregate—must be set
    aside.
    J. F. Allen concedes that the initial $1.3 million award against the Sanitary Board
    only “approximates” the damages testified to by Mr. Willoughby and as more fully itemized in the
    REA. However, to justify the verdict, J. F. Allen argues that there was sufficient evidence of
    additional losses that “far exceeded” the $1.2 million upon which the jury’s approximate $4 million
    award could be based. It cites two pieces of testimony in support. First, Mr. Hadjis testified that,
    “In particular, this contract we lost a significant amount of money. More money than we are
    claiming here today.” (emphasis added). Second—and the only specific monetary figure
    purportedly assigned to those alleged additional losses—was the testimony of Mr. Willoughby,
    who made the following brief statement:
    . . . [A]gain, when you look at J. F. Allen’s cost—what they spent
    on this job—and I’ve got reports showing that they’ve spent $7.1
    million. At that time their budget was, I believe, $4.8, so that was
    $2.5 million not counting the markup they lost. So that is $3 million
    over budget. So there were a lot of costs incurred by J. F. Allen on
    this job.
    J. F. Allen states that these additional “losses” consisted of additional crews and equipment,
    “extending working hours” resulting in “increased costs of home office support, management time
    and attention, additional trips to the site, additional surveying, and maintenance of the safety
    program.” Finally, J. F. Allen suggests that any amount over $1.2 million may constitute the jury’s
    award of general damages for annoyance, aggravation and inconvenience, which has no definite
    measure.
    B & N counters that the jury’s verdict was unsupported by any evidence in excess
    of the approximate $1.2 million as set forth in the REA and that any argument to the contrary is
    disingenuous since J. F. Allen’s counsel specifically told the jury to split the $1.2 million between
    the two defendants in some manner. As indicated above, after utilizing a demonstrative exhibit
    itemizing the REA and upon which he had handwritten the total of “$1,252,392.43” counsel stated:
    “The damages are the same that we assert against both of these entities. . . . So of this amount,
    you’ve got to decide how much you want to put against the Sanitary Board and what you want to
    put against Burgess and Niple.”
    B & N notes that, in closing, counsel expressly limited his discussion of damages
    to “this number,” pointing to the $1.2 million, and made no reference to the $3 million “over
    budget” figure mentioned by Mr. Willoughby. In fact, B & N cites to the remainder of Mr.
    Willoughby’s discussion of the over-budget amount wherein he conceded he did not calculate J.
    F. Allen’s losses on this basis because the over budget amount included items which were not
    attributable to the defendants. Finally, B & N contends that the jury’s verdict is not supported by
    an award of general damages for annoyance and inconvenience because corporations are not
    entitled to such damages.
    11
    With respect to a trial court’s decision to set aside a jury’s allegedly unsupported
    verdict, this Court has held:
    “In determining whether the verdict of a jury is supported by
    the evidence, every reasonable and legitimate inference, fairly
    arising from the evidence in favor of the party for whom the verdict
    was returned, must be considered, and those facts, which the jury
    might properly find under the evidence, must be assumed as true.”
    Syllabus point 5, Poe v. Pittman, 
    150 W. Va. 179
    , 
    144 S.E.2d 671
                    (1965); syllabus point 3, Walker v. Monongahela Power Company,
    
    147 W. Va. 825
    , 
    131 S.E.2d 736
    (1963).
    Syl. Pt. 17, Jordan v. Bero, 
    158 W. Va. 28
    , 
    210 S.E.2d 618
    (1974). However, “[a] verdict which
    is not supported by the evidence or is so large that it indicates that the jury was influenced by
    passion, partiality, prejudice or entertained a mistaken view of the case, should be set aside.”
    Id. at
    60, 210 
    S.E.2d at 639. See also Syl. Pt. 3, Raines v. Faulkner, 
    131 W. Va. 10
    , 
    48 S.E.2d 393
    (1947) (“A verdict of a jury will be set aside where the amount thereof is such that, when
    considered in the light of the proof, it is clearly shown that the jury was misled by a mistaken view
    of the case.”); Linville v. Moss, 
    189 W. Va. 570
    , 575, 
    433 S.E.2d 281
    , 286 (1993) (preserving
    allocation of fault and awarding new trial on damages where “the jury’s award . . . must have been
    based upon some misinterpretation of the law of damages.”); Hall v. Groves, 
    151 W. Va. 449
    , 458,
    
    153 S.E.2d 165
    , 170 (1967) (“A verdict in excess of the amount which the evidence shows a
    plaintiff is justly entitled to recover should be set aside by the trial court.”).
    In that regard, this Court has expressly held that “[i]f the trial judge finds the verdict
    is against the clear weight of the evidence, is based on false evidence or will result in a miscarriage
    of justice, the trial judge may set aside the verdict, even if supported by substantial evidence, and
    grant a new trial.” Syl. Pt. 2, in part, Summers v. Martin, 
    199 W. Va. 565
    , 
    486 S.E.2d 305
    (1997).
    In the instant case, the circuit court found that the verdict must be set aside because the jury “based
    its verdict on speculation instead of the evidence, when it found [$4.3 million against defendants]
    despite the fact that J. F. Allen requested approximately $1.25 million in total damages for the
    single injury alleged.” After review of the substantial evidence in this case, we agree.
    First, we reject J. F. Allen’s contention that the verdict is properly supported by Mr.
    Willoughby’s brief mention of an “over budget” amount of $3 million during the eight-day trial.
    There was no indication of whether this amount did or did not include the $1.2 million already
    itemized in the REA and, more importantly, Mr. Willoughby explained that he did not approach
    the REA from a “total cost” standpoint because “there were other issues on the job that cost them
    money for which [defendants weren’t] responsible.” Secondly, irrespective of Mr. Hadjis’
    generalized discussions of extra manpower, work hours, surveying costs, etc., J. F. Allen
    introduced no documentation or itemizations for such expenses, which easily lend themselves to
    calculation. In fact, Mr. Hadjis himself stated that any such expenses were “more” than J. F. Allen
    was “claiming here today.”
    Finally, we likewise refuse J. F. Allen’s suggestion that the verdict amount in
    excess of $1.2 million constitutes the jury’s award of general damages for aggravation, annoyance,
    12
    and inconvenience. B & N correctly notes that this Court has never squarely held that corporations
    may recover such damages. 10 However, we find it unnecessary to pass on this particular issue
    inasmuch as the jury was not instructed on these types of damages, nor is there any indication that
    J. F. Allen ever requested any such instruction from the court.
    Instead, the only evidence presented in support of J. F. Allen’s damages were the
    itemizations set forth in the REA and its supporting documentation. Certainly, J. F. Allen’s
    counsel’s specific request for this amount in closing belies its position on appeal that the verdict
    was otherwise supported by competent evidence. As this Court long ago explained, “[t]he
    evidence must afford data, facts and circumstances, reasonably certain, from which the jury may
    find the actual loss.” Carpenter v. Hyman, 
    67 W. Va. 4
    , ___, 
    66 S.E. 1078
    , 1080 (1910). 11 We
    therefore find no abuse of discretion in the circuit court’s award of a new trial on damages.
    Having determined that the circuit court did not err in awarding a new trial on
    damages, we turn to B & N’s contention that the jury’s questions and difficulties in returning its
    verdict demonstrate confusion so profound, its liability determinations must also be called into
    question. 12 With respect to ordering a new trial on damages alone, the Court has held:
    Rule 59(a), R.C.P., provides that a new trial may be granted
    to any of the parties on all or part of the issues, and in a case where
    the question of liability has been resolved in favor of the plaintiff
    leaving only the issue of damages, the verdict of the jury may be set
    aside and a new trial granted on the single issue of damages.
    10
    But cf. Syl. Pt. 5, AIG Domestic Claims, Inc. v. Hess Oil Co., 
    232 W. Va. 145
    , 
    751 S.E.2d 31
    (2013) (“A dissolved corporation that is asserting a claim solely in its corporate name under
    authority of West Virginia Code § 31D-14-1405(b)(5) (2009) may not recover damages for the
    personal aggravation, annoyance, and inconvenience of its non-party former shareholders.”).
    11
    Moreover, the jury, upon returning its initial verdict of only $1.3 million commented,
    “We got it right this time.” As noted by the circuit court, this comment, along with its subsequent
    inquiries after being sent back to deliberate on its specific award against B & N inquiring what
    such an award was to be “based on,” certainly suggests the jury believed it had fully discharged
    its duty as to an award of damages with its initial verdict. When it returned with an additional $3
    million in damages against B & N, it appears that the jury was attempting to satisfy the circuit
    court’s concern that it improperly completed the verdict form.
    12
    B & N casts this argument in terms of the “inconsistency” between the verdict and the
    evidence, such as to characterize it as an “inconsistent verdict” which typically warrants a retrial
    on both liability and damages. However, an inconsistent verdict lacks internal consistency and,
    as a result, makes it unclear which aspect of the verdict is flawed and should be set aside. The
    issue asserted with respect to this verdict is far more straightforward—simply that it was
    unsupported by the evidence.
    13
    Syl. Pt. 4, Richmond v. Campbell, 
    148 W. Va. 595
    , 
    136 S.E.2d 877
    (1964). However, “it must
    appear, to justify a new trial limited to a single issue, that such issue is clearly separable from the
    other issues in the case[.]” 
    Hall, 151 W. Va. at 459
    , 153 S.E.2d at 171.
    B & N fails to provide any rationale for why liability and damages are not separable
    in this case, asserting generally that “lack of understanding regarding the damages shows a lack of
    understanding regarding the essential elements of the claim from which the damages flow.” We
    disagree with this conclusory assertion and find no demonstrable reason why the jury’s liability
    determinations were in error and should be retried. As this Court observed in Hall:
    There has been a full and complete hearing on that branch of the
    case, and we find no fault with the judgment in respect thereto. The
    error is in the ascertainment of the amount of damages. The two
    matters are distinct and separable. When the only error relates solely
    to the quantum of damages, there would seem to be no sufficient
    reason for a new trial to determine again the right of recovery. In
    passing upon the entire case logically the jury would ascertain (1)
    whether the plaintiff is entitled to recover anything, and (2) if so,
    how much? The second proposition is wholly separate and distinct
    from the first
    Id. at
    457, 153 S.E.2d at 170 
    (quoting Chafin v. Norfolk and Western Railway Company, 80 W.
    Va. 703, 
    93 S.E. 822
    , 825 (1917)). The jury’s litany of questions pertained solely to damages and
    there is nothing demonstrably inconsistent or otherwise defective with its liability determination.
    We therefore affirm the circuit court’s determination that the verdict must be set aside and a new
    trial on damages is warranted. 13
    3.     ADMISSION OF REA
    As indicated above, B & N also asserts a variety of trial errors, which it contends
    warrants reversal for a new trial in its entirety. First, B & N claims that the circuit court committed
    reversible error by permitting the REA to be introduced as substantive evidence. It claims that the
    REA is a hearsay document prepared by J. F. Allen’s expert and was therefore inadmissible as
    substantive evidence and cumulative. B & N urges that the REA therefore constituted an expert
    report because it was 1) prepared by J. F. Allen’s retained expert, Mr. Willoughby, who called it
    his “expert report”; 2) submitted seven months after the final payment was tendered for the project;
    and, most importantly, 3) J. F. Allen’s representative testified in deposition that “the expectation
    13
    B & N further notes that, as observed by the circuit court, “a trial on damages necessitates
    a complete retrial of the matter,” and argues that this necessity supports its argument for a retrial
    in toto. However, as indicated above, prior to oral argument the Court was advised that the
    Sanitary Board has entered a settlement with J. F. Allen, leaving only B & N as a party defendant.
    The Court declines to speculate on how this settlement may affect the manner in which a retrial is
    effectuated and limits its decision to the circuit court’s general determination that the damages
    verdict must be set aside and a new trial on that issue awarded.
    14
    at the time [of the REA’s preparation] was this would be litigated because of [the] request to correct
    the adjustment.”
    J. F. Allen maintains this document was merely a business record kept in the
    ordinary course of its operations and reflected its documentation of a claim for equitable
    adjustment as part of the contract claims process. As is well-established, “[a] trial court’s
    evidentiary rulings, as well as its application of the Rules of Evidence, are subject to review under
    an abuse of discretion standard.” Syl. Pt. 4, State v. Rodoussakis, 
    204 W. Va. 58
    , 
    511 S.E.2d 469
    (1998).
    Rule 803(6) of the Rules of Evidence, commonly known as the “business records”
    exception, provides that such documents are not hearsay if
    (A)     the record was made at or near the time by—or from
    information transmitted by—someone with knowledge;
    (B)     the record was kept in the course of a regularly conducted
    activity of a business, organization, occupation, or calling, whether
    or not for profit;
    (C)     making the record was a regular practice of that activity;
    (D)     all these conditions are shown by the testimony of the
    custodian or another qualified witness, or by a certification that
    complies with Rule 902(11) or (12) or with a statute permitting
    certification; and
    (E)     neither the source of information nor the method or
    circumstances of preparation indicate a lack of trustworthiness.
    (emphasis added). In general, expert reports are inadmissible hearsay documents. See Wright v.
    Premier Elkhorn Coal Co., 
    16 S.W.3d 570
    , 572 (Ky. Ct. App. 1999) (“The reports, prepared in
    anticipation of litigation by experts retained for the trial, constitute out-of-court statements utilized
    to prove the truth of the matter asserted.”); Corcoran v. Sears Roebuck & Co., 
    711 A.2d 371
    , 376
    (N. J. Super. Ct. App. Div. 1998) (“[Expert] reports themselves are hearsay and generally are not
    admissible.”). Expert reports may also, as B & N here contends, 14 contain imbedded hearsay, i.e.
    hearsay within hearsay. West Virginia Rule of Evidence 703’s provision that an expert may, under
    certain circumstances, rely on otherwise inadmissible evidence in forming an opinion, “does not,
    however, authorize a fact-finder to consider hearsay communications contained in an expert’s
    report for their truth.” In re Soriah B., 
    8 A.3d 1256
    , 1261 (Me. 2010).
    The Court is mindful that it “at every stage of the proceeding must disregard any
    error or defect in the proceeding which does not affect the substantial rights of the parties.” W.
    Va. R. Civ. P. 61. In that regard, B & N identifies no prejudice which was occasioned by the
    introduction of the REA and in fact concedes that it was merely cumulative of Mr. Willoughby’s
    testimony. Accordingly, even if this Court were to find that the REA was improperly admitted as
    substantive evidence, its admission was plainly harmless and, more importantly, mooted by a new
    14
    Mr. Willoughby testified that the REA included “J. F Allen’s view [of] what had
    happened. I wasn’t there every day. I didn’t deal with these folks. . . .”
    15
    trial on damages. The REA is purely a damages document, as effectively conceded by the parties.
    Therefore, in view of our above conclusion that a new trial on damages is warranted, we find it
    unnecessary to pass on this issue.
    4.     QUALIFICATION OF EXPERT
    Next, B & N claims that J. F. Allen’s expert, Charles Dutill, was unqualified to
    offer opinions because he was not a West Virginia-licensed engineer, citing West Virginia Code §
    30-13-2 (1992), which prohibits the “practice of engineering” for non-State-licensed engineers. B
    & N further argues that permitting Mr. Dutill’s testimony was erroneous because he had never
    worked in this geographical area, had never designed a sewer system like the one at hand, had not
    administered a contract such as this one in over sixteen years, had never utilized the form contract
    at issue, and did not consider himself an expert on such a contract. J. F. Allen counters that the
    statutory provision does not supplant the Rules of Evidence regarding expert testimony and that
    attacks on the expert’s experience and credentialing were merely fodder for cross-examination.
    We first observe that “[t]he admissibility of testimony by an expert witness is a matter within the
    sound discretion of the trial court, and the trial court’s decision will not be reversed unless it is
    clearly wrong.” Syl. Pt. 6, Helmick v. Potomac Edison Co., 
    185 W. Va. 269
    , 
    406 S.E.2d 700
    (1991).
    West Virginia Code § 30-13-2 makes it unlawful to “practice or to offer to practice
    engineering in this state, as defined in the provisions of this article . . . .” The “practice of
    engineering” is defined as including: “consultation, investigation, evaluation . . . of engineering
    works and systems . . . and the review of construction for the purpose of assuring compliance with
    drawings and specifications any of which embraces such services or work, either public or private,
    in connection with any utilities . . . .” W. Va. Code § 30-13-3(e) (1992).
    West Virginia Rule of Evidence 702(a) provides: “If scientific, technical, or other
    specialized knowledge will assist the trier of fact to understand the evidence or to determine a fact
    in issue, a witness qualified as an expert by knowledge, skill, experience, training, or education
    may testify thereto in the form of an opinion or otherwise.” Further,
    [i]n determining who is an expert, a circuit court should conduct a
    two-step inquiry. First, a circuit court must determine whether the
    proposed expert (a) meets the minimal educational or experiential
    qualifications (b) in a field that is relevant to the subject under
    investigation (c) which will assist the trier of fact. Second, a circuit
    court must determine that the expert’s area of expertise covers the
    particular opinion as to which the expert seeks to testify.
    Syl. Pt. 5, Gentry v. Mangum, 
    195 W. Va. 512
    , 
    466 S.E.2d 171
    (1995).
    We find that this assignment of error has no merit. Mr. Dutill had over thirty-eight
    years of experience in engineering, as well as engineering degrees from Cornell University. Any
    purported inadequacies regarding his experience with contracts such as those at issue was a matter
    for cross-examination and consideration by the jury. Moreover, West Virginia Code § 30-13-3(e)
    does not prohibit an unlicensed engineer from providing expert testimony in a court of law. Similar
    16
    licensure statutes in other states have uniformly been rejected as implying such prohibition—even
    where the language of those statutes do ostensibly prohibit serving as an expert. See J.T. Baggerly
    v. CSX Transp., Inc., 
    635 S.E.2d 97
    , 103 (S. C. 2006) (rejecting use of licensure statute to
    disqualify expert engineer as same would “clearly contravene Rule 702” since expert’s services
    “were being offered to a South Carolina jury, not to the State’s citizens seeking traditional
    professional engineering services”); Tellus Operating Grp., LLC v. Texas Petroleum Inv. Co., 
    105 So. 3d 274
    , 279 (Miss. 2012) (finding engineer licensure statute “has no bearing on whether a
    witness is otherwise qualified as an expert” because public safeguarding objective “is not furthered
    by restricting evidence in a judicial proceeding between private parties”); Baerwald v. Flores, 
    930 P.2d 816
    (N. M. Ct. App. 1996) (same).
    5.     INTERVENING CAUSE INSTRUCTION
    B & N next asserts that the circuit court erroneously refused to instruct the jury on
    intervening cause, as it requested. B & N sought the instruction on the basis that J. F. Allen’s
    refusal to present a written claim prior to or contemporaneous with the final payment application
    as required by the contract was the intervening act which caused its losses, irrespective of any
    alleged negligence on the part of B & N. The circuit court initially agreed to the instruction, but
    later rejected it on the basis that J. F. Allen’s failure to submit a claim was a “deliberate” and not
    “negligent” act. The court also noted that it believed such a position was well-covered by the
    instructions on comparative negligence and therefore the instruction was improper. With the latter
    analysis, we agree. 15
    “As a general rule, the refusal to give a requested jury instruction is reviewed for
    an abuse of discretion.” Syl. Pt. 1, in part, State v. Hinkle, 
    200 W. Va. 280
    , 
    489 S.E.2d 257
    (1996).
    Further,
    [a] trial court’s refusal to give a requested instruction is reversible
    error only if: (1) the instruction is a correct statement of the law; (2)
    it is not substantially covered in the charge actually given to the jury;
    and (3) it concerns an important point in the trial so that the failure
    to give it seriously impairs a defendant’s ability to effectively
    present a given defense.
    15
    While we agree an intervening cause instruction was not proper in this case, the circuit
    court’s rationale that an intervening cause must necessarily be a negligent, rather than deliberate,
    act appears to be based on the language of our caselaw. However, we note that references to
    “negligent” acts may or may not be merely incidental to the facts of the particular cases, as opposed
    to a required element of the defense. As discussed infra, the Restatement (Second) of Torts § 440
    explains that “[a] superseding cause is an act of a third person or other force . . .” (1965). The
    Restatement further provides that “[a]n intervening force is one which actively operates in
    producing harm to another after the actor’s negligent act or omission has been committed.”
    Id. at
    § 441 (1965). This Court has not had occasion to examine the required nature of the intervening
    cause in the context of a deliberate act, nor do we find it necessary to do so to resolve the issues
    presented herein.
    17
    Syl. Pt. 11, State v. Derr, 
    192 W. Va. 165
    , 
    451 S.E.2d 731
    (1994).
    In this instance, the circuit court was correct that instructing the jury to assign
    comparative fault among J. F. Allen and B & N properly accounted for any alleged fault of J. F.
    Allen. Traditionally, an intervening cause instruction is proper where a third party’s acts are
    alleged to extinguish the causal chain. 16 The Restatement (Second) of Torts § 440 explains that
    “[a] superseding cause is an act of a third person or other force which by its intervention prevents
    the actor from being liable for harm to another which his antecedent negligence is a substantial
    factor in bringing about.” By implication, this does not include the acts of the plaintiff, against
    whom a percentage of comparative fault may be applied as the jury sees fit. 17 We note the
    importance of this distinction between the comparative fault of a plaintiff and that of a third party
    because “in cases in which a defendant alleges that a plaintiff’s negligence proximately caused his
    or her injury, [reference to both comparative fault] and the reference to independent intervening
    cause . . . unduly emphasize[s] a defendant’s attempt to shift fault to a plaintiff.” Torres v. El Paso
    Elec. Co., 
    987 P.2d 386
    , 393, overruled on other grounds by Herrera v. Quality Pontiac, 
    73 P.3d 16
               B & N cites two cases for the proposition that a defendant is entitled to an intervening
    cause instruction based on the conduct of the plaintiff: Sydenstricker v. Mohan, 
    217 W. Va. 552
    ,
    
    618 S.E.2d 561
    (2005) and Landis v. Hearthmark, LLC, 
    232 W. Va. 64
    , 
    750 S.E.2d 280
    (2013).
    Neither provide support for its position. Sydenstricker neither created nor cited to a syllabus point
    regarding allegations of intervening cause against the plaintiff and, in fact, the alleged intervening
    cause in that case was the conduct of a non-party who had settled.
    Id. at
    556, 618 S.E.2d at 565
    .
    In Landis, the only discussion of whether a party—not plaintiff—may constitute an intervening
    cause is dicta from Sydenstricker and Costoplos v. Piedmont Aviation, Inc., 
    184 W. Va. 72
    , 74, 
    399 S.E.2d 654
    , 656 (1990). Landis, 232 W. Va. at 
    76, 750 S.E.2d at 292
    . More importantly, Landis
    merely holds that parental immunity does not bar the defense of intervening causation against
    parents. See Syl. Pt. 4
    , id. (“In a product
    liability action brought for injury to a child, the parental
    immunity doctrine does not preclude a defendant from asserting, as a defense, that the conduct of
    a parent was an intervening cause of the child’s injuries.”). It did not examine the question of
    whether an intervening cause instruction is appropriate when the intervening cause asserted is the
    conduct of the plaintiff.
    17
    See also Restatement § 442(d) and (f) (identifying considerations for determining
    whether conduct is an intervening force including whether “the operation of the intervening force
    is due to a third person’s act or to his failure to act” and “the degree of culpability of a wrongful
    act of a third person which sets the intervening force in motion” (emphasis added)). See also Von
    der Heide v. Com., Dep’t of Transp., 
    718 A.2d 286
    , 288 (Pa. 1998) (“Superseding cause allows
    the unforeseeable acts of a third party, someone or something other than the plaintiff or the
    defendant, to supplant the defendant’s conduct as the legal cause of the plaintiff’s injuries.”);
    Brooks v. Logan, 
    903 P.2d 73
    , 80-81 (Idaho 1995), superseded by statute on other grounds as
    stated in Carrier v. Lake Pend Oreille Sch. Dist., 
    134 P.3d 655
    (Idaho 2006) (“[T]here is no
    allegation that a third party or some ‘other force’ was the intervening, superseding cause . . . . In a
    situation such as this, we believe the question is more appropriately one of comparative
    negligence.”).
    18
    181 (N. M. 2003). As the Torres court explained, an improper instruction regarding plaintiff’s
    fault under the auspices of intervening cause creates “an unacceptable risk that the jury will
    inadvertently apply the common law rule of contributory negligence” which would bar recovery
    altogether.
    Id. at
    393.
    We therefore conclude that the circuit court committed no error in refusing B &
    N’s intervening cause instruction.
    6.      REMARKS IN CLOSING
    Finally, B & N claims that J. F. Allen’s counsel improperly argued to the jury that
    neither defendant offered its own expert, thereby improperly reversing the burden of proof to the
    B & N. More specifically, B & N complains of the following statements made in closing:
    Now, the engineer who is supposed to be the independent arbiter,
    again, we’re the only person that put on an expert. Our expert said
    that for those same sections, it was negligence for the engineer not
    to act. It was negligent for them not to recommend payment.
    [Counsel for B &N] doesn’t like our expert, who was qualified by
    the Judge, and testified—the only person who testified. They
    couldn’t get an expert to refute it. Nobody from management—
    you’d think somebody—Mr. Richards or somebody would come in
    and say, that’s wrong.
    (emphasis added). J. F. Allen counters that B & N failed to object at the time of the comments and
    therefore waived any error; B & N attempts to cure its clear failure to object by arguing that it
    raised the issue in post-trial motions.
    This assignment of error has no merit. “Failure to make timely and proper objection
    to remarks of counsel made in the presence of the jury, during the trial of a case, constitutes a
    waiver of the right to raise the question thereafter either in the trial court or in the appellate court.”
    Syl. Pt 6, Yuncke v. Welker, 
    128 W. Va. 299
    , 
    36 S.E.2d 410
    (1945); see also Rowe v. Sisters of
    Pallottine Missionary Soc’y, 
    211 W. Va. 16
    , 26 n.6, 
    560 S.E.2d 491
    , 501 n.6 (2001) (declining to
    review remarks where “counsel did not make a contemporaneous objection to any of these
    arguments, nor did the appellant ask for a curative instruction before the jury retired for its
    deliberations”); State v. Asbury, 
    187 W. Va. 87
    , 91, 
    415 S.E.2d 891
    , 895 (1992) (“Generally the
    failure to object constitutes a waiver of the right to raise the matter on appeal.”).
    IV. Conclusion
    For the foregoing reasons, the March 20, 2019, order of the Circuit Court of
    Kanawha County ordering a new trial on damages and denying B & N’s motion for renewed
    judgment as a matter of law is hereby affirmed.
    Affirmed.
    19
    ISSUED: October 16, 2020
    CONCURRED IN BY:
    Chief Justice Tim Armstead
    Justice Margaret L. Workman
    Justice Elizabeth D. Walker
    Justice Evan H. Jenkins
    Justice John A. Hutchison
    20