Credit Acceptance Corp. v. Robert J. and Billye S. Front, etc. , 231 W. Va. 518 ( 2013 )


Menu:
  • IN THE SUPREME COURT OF APPEALS OF WEST VIRGINIA
    January 2013 Term
    FILED
    June 19, 2013
    released at 3:00 p.m.
    RORY L. PERRY II, CLERK
    No. 11-1646           SUPREME COURT OF APPEALS
    OF WEST VIRGINIA
    CREDIT ACCEPTANCE CORP.,
    Defendant Below, Petitioner
    V.
    ROBERT J. FRONT AND BILLYE S. FRONT,
    Plaintiffs Below, Respondents
    Appeal from the Circuit Court of Raleigh County
    Honorable Harry L. Kirkpatrick, III, Judge
    Civil Action Nos. 11-C-289(K) and 11-C-290(K)
    REVERSED AND REMANDED
    AND
    No. 12-0545
    CREDIT ACCEPTANCE CORP.,
    Defendant Below, Petitioner
    V.
    OCIE SHREWSBURY,
    Plaintiff Below, Respondent
    Appeal from the Circuit Court of Raleigh County
    Honorable John A. Hutchison, Judge
    Civil Action No. 11-C-391-H
    REVERSED AND REMANDED
    Submitted: April 10, 2013
    Filed: June 19, 2013
    Don C. A. Parker                                 Ralph C. Young
    Bruce M. Jacobs                                  Christopher B. Frost
    Nicholas P. Mooney                               Hamilton Burgess Young & Pollard
    Spilman Thomas & Battle, PLLC                    Fayetteville, West Virginia
    Charleston, West Virginia                        Attorneys for the Respondents,
    Attorneys for the Petitioner                     Robert J. Front & Billye S. Front
    Ralph C. Young
    Christopher B. Frost
    Steven R. Broadwater, Jr.
    Hamilton Burgess Young & Pollard
    Fayetteville, West Virginia
    Attorneys for the Respondent,
    Ocie Shrewsbury
    JUSTICE DAVIS delivered the Opinion of the Court.
    JUSTICE KETCHUM concurs and reserves the right to file a concurring opinion.
    SYLLABUS BY THE COURT
    1.     An order denying a motion to compel arbitration is an interlocutory
    ruling which is subject to immediate appeal under the collateral order doctrine.
    2.     “‘A contract term is unenforceable if it is both procedurally and
    substantively unconscionable. However, both need not be present to the same degree.
    Courts should apply a ‘sliding scale’ in making this determination: the more substantively
    oppressive the contract term, the less evidence of procedural unconscionability is required
    to come to the conclusion that the clause is unenforceable, and vice versa.’ Syllabus Point
    20, Brown v. Genesis Healthcare Corp., 
    228 W. Va. 646
    , 
    724 S.E.2d 250
    (2011)[, overruled
    in part on other grounds by Marmet Health Care Center, Inc. v. Brown, ___ U.S. ___, 
    132 S. Ct. 1201
    , 
    182 L. Ed. 2d 42
    (2012) (per curiam).]” Syllabus point 9, Brown v. Genesis
    Healthcare Corp., 
    229 W. Va. 382
    , 
    729 S.E.2d 217
    (2012).
    3.     Where an arbitration agreement names a forum for arbitration that is
    unavailable or has failed for some reason, a court may appoint a substitute forum pursuant
    to section 5 of the Federal Arbitration Act, 9 U.S.C. § 5 (1947) (2006 ed.), only if the choice
    of forum is an ancillary logistical concern. Where the choice of forum is an integral part of
    i
    the agreement to arbitrate, the failure of the chosen forum will render the arbitration
    agreement unenforceable.
    4.     “A state statute, rule, or common-law doctrine, which targets arbitration
    provisions for disfavored treatment and which is not usually applied to other types of contract
    provisions, stands as an obstacle to the accomplishment and execution of the purposes and
    objectives of the Federal Arbitration Act, 9 U.S.C. § 2, and is preempted.” Syllabus point
    8, Brown ex rel. Brown v. Genesis Healthcare Corp., 
    228 W. Va. 646
    , 
    724 S.E.2d 250
    (2011), overruled in part on other grounds by Marmet Health Care Center, Inc. v. Brown,
    ___ U.S. ___, 
    132 S. Ct. 1201
    , 
    182 L. Ed. 2d 42
    (2012) (per curiam).
    ii
    Davis, Justice:
    Two appeals have been consolidated for decision in this matter. In these
    consolidated appeals, Credit Acceptance Corp., petitioner (hereinafter “Credit Acceptance”),
    appeals orders issued by the Circuit Court of Raleigh County in each case that denied Credit
    Acceptance’s motion to compel arbitration.1 Credit Acceptance contends that, in both of
    these cases, the circuit courts erred by concluding that the arbitration agreements were
    unconscionable based upon the unavailability of arbitration forums named therein, and
    because the debtors in the agreements waived their respective rights to a jury trial. Because
    we find that one of the arbitration forums named in the agreements remains available to
    arbitrate the parties’ disputes, and because an arbitration agreement is not rendered
    unenforceable solely because a party thereto waives his or her right to a jury trial, we reverse
    both of these cases and remand for entry of orders compelling arbitration.
    I.
    FACTUAL AND PROCEDURAL HISTORY
    The cases underlying these consolidated appeals all involve the purchase of an
    automobile. We relate the particular facts of each case separately below.
    1
    The motions each sought to have the case dismissed or, in the alternative,
    stayed pending arbitration.
    1
    A. Front Plaintiffs
    On August 17, 2007, Robert and Billye Front (hereinafter collectively “the
    Fronts”) purchased a 2003 Chevrolet Cavalier automobile from Finish Line Pre-Owned Auto
    Sales (hereinafter “Finish Line”). To purchase this vehicle, the Fronts executed a retail
    installment and security agreement with Finish Line. Finish Line assigned all its rights, title,
    and interest in the contract and the vehicle to Credit Acceptance in exchange for Credit
    Acceptance financing the purchase.
    Thereafter, on April 17, 2008, the Fronts purchased a 2005 Ford Focus vehicle
    from Prestige Ford Lincoln-Mercury, Inc. (hereinafter “Prestige”). As with their first
    automobile purchase, the Fronts executed a retail installment contract with Prestige. Prestige
    subsequently assigned all its rights, title, and interest in the contract to Credit Acceptance.
    Both of the retail installment contracts executed by the Fronts in connection
    with their vehicle purchases contained arbitration clauses. The clauses were nearly identical2
    and stated, in part:
    The Federal Arbitration Act governs this Arbitration Clause.
    You and we understand and agree that You and we choose
    arbitration instead of litigation to resolve Disputes. You and we
    2
    Differences in the two contracts are noted below.
    2
    voluntarily and knowingly waive any right to a jury trial. . . .[3]
    ....
    You or we may elect to arbitrate under the rules and procedures
    of either the National Arbitration Forum or the American
    Arbitration Association; however in the event of a conflict
    between these rules and procedures and the provisions of this
    Arbitration Clause, You and we agree that this Arbitration
    Clause governs for that specific conflict. You may obtain the
    rules and procedures, information on fees and costs (including
    waiver of the fees), and other materials, and may file a claim by
    contacting the organization of your choice. . . .
    ....
    It is expressly agreed that this Contract evidences a transaction
    in interstate commerce.[4] The Arbitration Clause is governed by
    the Federal Arbitration Act, 9 U.S.C. §§ 1 et seq. (“FAA”) and
    not by any state arbitration law.
    (Footnotes added). After the Fronts executed the aforementioned contracts, one of the
    selected arbitration forums, the National Arbitration Forum (hereinafter “NAF”), was sued
    by the State of Minnesota. As a result of this suit, the NAF entered into a consent decree
    forbidding it from conducting consumer arbitration. See CompuCredit Corp. v. Greenwood,
    ___ U.S. ___, ___ n.2, 
    132 S. Ct. 665
    , 677 n.2, 
    181 L. Ed. 2d
    . 586 (2012) (“In 2009, after
    the Attorney General of Minnesota filed an action alleging that NAF had engaged in
    numerous violations of consumer-protection laws, NAF entered into a consent decree barring
    3
    This language was not underlined in the contract for the purchase of the 2003
    Chevrolet Cavalier.
    4
    This sentence did not appear in the contract for the purchase of the 2003
    Chevrolet Cavalier.
    3
    it from handling consumer arbitrations.”). Shortly thereafter, “[i]n July 2009, AAA issued
    a moratorium on arbitrating cases concerning consumer debt collections if those cases were
    brought by the company and the consumer did not consent to the arbitration.” Montgomery
    v. Applied Bank, 
    848 F. Supp. 2d 609
    , 613 (S.D.W. Va. 2012). Thus, one of the contractually
    designated arbitrators, NAF, was no longer available to arbitrate any dispute that arose under
    the Credit Acceptance/Front contracts, and the other designated arbitrator, AAA, was
    available only on a limited basis.
    The Fronts commenced two civil actions against Credit Acceptance in the
    Circuit Court of Raleigh County in May 2011. The claims related to communications the
    Fronts allegedly received from Credit Acceptance after their debt under the two retail
    installment contracts was in arrears. Each complaint set forth four causes of action: (1)
    violations of the West Virginia Consumer Credit and Protection Act (hereinafter “the
    WVCCPA”); (2) negligence; (3) intentional infliction of emotional distress; and (4) invasion
    of privacy. In each case, Credit Acceptance filed a motion to compel arbitration and dismiss,
    or, in the alternative, to stay the action pending arbitration. The circuit court consolidated
    the two cases and ultimately denied Credit Acceptance’s motions. The circuit court found
    that the contracts were not procedurally unconscionable at the time of their formation, but
    the subsequent unavailability of one of the selected arbitration forums materially changed the
    contracts and rendered them procedurally unconscionable. The court additionally found that
    4
    the unavailability of one of the selected forums rendered the contracts substantively
    unconscionable. Finally, the circuit court found that the arbitration agreements violated the
    Fronts’ fundamental right under the West Virginia Constitution to use the court system to
    seek justice and violated the WVCCPA, which the circuit court interpreted as prohibiting a
    consumer from waiving the right to a jury trial. The court designated the order as a “final
    order.” It is from this order that Credit Acceptance appeals.
    B. Shrewsbury Plaintiff
    Ocie Shrewsbury and Virgil Shrewsbury5 (hereinafter collectively “the
    Shrewsburies”) purchased a 2000 Ford Expedition from Greg Lilly Auto Sales, Inc.
    (hereinafter “Lilly Auto”), on July 11, 2010. In connection with this purchase, the
    Shrewsburies executed a retail installment contract and security agreement with Lilly Auto.
    Lilly Auto then assigned all its rights, title, and interest in the contract and the vehicle to
    Credit Acceptance, who financed the purchase. The retail installment contract executed by
    the Shrewsburies in connection with their vehicle purchase contained an arbitration clause
    using the same language as that quoted above from the 2005 Front contract. Notwithstanding
    the fact that the NAF was no longer available to arbitrate any dispute that arose under the
    contract, and the AAA was available only on a limited basis,6 the contract nevertheless
    5
    Virgil Shrewsbury is not a party to this action.
    6
    For an explanation of the unavailability of the NAF and the AAA, see supra
    (continued...)
    5
    designated those two organizations as arbitrators of any disputes in the same manner as those
    organizations had been designated in the Credit Acceptance/Front contracts.
    On May 17, 2011, Ocie Shrewsbury (hereinafter “Ms. Shrewsbury”) filed a
    civil action against Credit Acceptance in the Circuit Court of Raleigh County alleging: (1)
    violations of the WVCCPA; (2) negligence; (3) intentional infliction of emotional distress;
    and (4) invasion of privacy related to communications she allegedly received from Credit
    Acceptance after her debt under the retail installment contract was in arrears. Credit
    Acceptance then filed a motion to compel arbitration or, in the alternative, to stay the action
    pending arbitration. The circuit court ultimately denied the motion finding the arbitration
    agreement was not enforceable. Similar to the circuit court’s order in the Front case, the
    circuit court found that the contract was not procedurally unconscionable insofar as “it
    provided an adequate means for the Plaintiff to opt out.” However, the circuit court further
    observed that the unavailability of the selected arbitration forums materially changed the
    contract such that there was no meeting of the minds. Therefore, the circuit court concluded
    that the contract was unenforceable “as it exists today.” The circuit court additionally found
    that the unavailability of the selected forums materially altered the terms of the contract and
    rendered the contract substantively unconscionable. Finally, the circuit court found the
    6
    (...continued)
    Section I.A. titled “Front Plaintiffs.”
    6
    arbitration agreement was unenforceable in that it essentially eliminated Ms. Shrewsbury’s
    constitutional right to file suit. It is from this order that Credit Acceptance appeals.
    II.
    STANDARD OF REVIEW
    Before we reiterate the proper standard for our review of these consolidated
    cases, we first consider whether these appeals are appropriate. These two appeals are before
    this Court from circuit court orders that denied motions to dismiss and to compel arbitration.
    Thus, these consolidated cases seek this Court’s review of interlocutory orders.
    “[O]rdinarily the denial of a motion to dismiss is an
    interlocutory order and, therefore, is not immediately
    appealable. See, e.g., Syl. pt. 2, State ex rel. Arrow Concrete
    Co. v. Hill, 
    194 W. Va. 239
    , 
    460 S.E.2d 54
    (1995) (“Ordinarily
    the denial of a motion for failure to state a claim upon which
    relief can be granted made pursuant to West Virginia Rules of
    Civil Procedure 12(b)(6) is interlocutory and is, therefore, not
    immediately appealable.”). See also Hutchison v. City of
    Huntington, 
    198 W. Va. 139
    , 147, 
    479 S.E.2d 649
    , 657 (1996)
    (indicating that this Court rarely addresses a circuit court’s
    denial of a motion to dismiss since such an order is
    interlocutory).
    Ewing v. Board of Educ. of Cnty. of Summers, 
    202 W. Va. 228
    , 235, 
    503 S.E.2d 541
    , 548
    (1998). Typically, interlocutory orders are not subject to this Court’s appellate jurisdiction.
    See Coleman v. Sopher, 
    194 W. Va. 90
    , 94, 
    459 S.E.2d 367
    , 371 (1995) (“The usual
    prerequisite for our appellate jurisdiction is a final judgment, final in respect that it ends the
    case.”). This “rule of finality” is not an absolute rule. Rather, there is a “narrow category
    7
    of orders that are subject to permissible interlocutory appeal.” Robinson v. Pack, 
    223 W. Va. 828
    , 831, 
    679 S.E.2d 660
    , 663 (2009). The Robinson Court explained that,
    [o]bjections to allowing an appeal from an interlocutory
    order are typically rooted in the need for finality. The
    provisions of West Virginia Code § 58-5-1 (2005) establish that
    appeals may be taken in civil actions from “a final judgment of
    any circuit court or from an order of any circuit court
    constituting a final judgment.” 
    Id. Justice Cleckley elucidated
                  in James M.B. v. Carolyn M., 
    193 W. Va. 289
    , 
    456 S.E.2d 16
                  (1995), that “[t]his rule, commonly referred to as the ‘rule of
    finality,’ is designed to prohibit ‘piecemeal appellate review of
    trial court decisions which do not terminate the 
    litigation[.]’” 193 W. Va. at 292
    , 456 S.E.2d at 19 (quoting U.S. v. Hollywood
    Motor Car Co., 
    458 U.S. 263
    , 265, 
    102 S. Ct. 3081
    , 
    73 L. Ed. 2d 754
    (1982)). Exceptions to the rule of finality include
    “interlocutory orders which are made appealable by statute or by
    the West Virginia Rules of Civil Procedure, or . . . [which] fall
    within a jurisprudential exception” such as the “collateral order”
    doctrine. James 
    M.B., 193 W. Va. at 292–93
    , 456 S.E.2d at
    19–20; accord Adkins v. Capehart, 
    202 W. Va. 460
    , 463, 
    504 S.E.2d 923
    , 926 (1998) (recognizing prohibition matters,
    certified questions, Rule 54(b) judgment orders, and “collateral
    order” doctrine as exceptions to rule of 
    finality). 223 W. Va. at 832
    , 679 S.E.2d at 664 (footnote omitted). See also C & O Motors, Inc. v.
    West Virginia Paving, Inc., 
    223 W. Va. 469
    , 475, 
    677 S.E.2d 905
    , 911 (2009) (“In addition
    to the ‘ministerial’ acts exception, this Court has recognized a limited number of other
    exceptions to the rule of finality. Our cases have pointed out that we may address specific
    issues decided by an interlocutory order under the collateral order doctrine or ‘by writs of
    prohibition, certified questions, or by judgments rendered under Rule 54(b) of the West
    Virginia Rules of Civil Procedure.’” (quoting James 
    M.B., 193 W. Va. at 292
    n.3, 
    456 S.E.2d 8
    at 19 n.3)). The exception referred to as the “collateral order” doctrine, which was
    established by the United States Supreme Court in Cohen v. Beneficial Industrial Loan Corp.,
    
    337 U.S. 541
    , 
    69 S. Ct. 1221
    , 
    93 L. Ed. 1528
    (1949), may be applied to allow appeal of an
    interlocutory order when three factors are met: “An interlocutory order would be subject to
    appeal under [the collateral order] doctrine if it (1) conclusively determines the disputed
    controversy, (2) resolves an important issue completely separate from the merits of the
    action, and (3) is effectively unreviewable on appeal from a final judgment.” Durm v.
    Heck’s, Inc., 
    184 W. Va. 562
    , 566 n.2, 
    401 S.E.2d 908
    , 912 n.2 (1991) (internal quotations
    and citation omitted). See also Robinson v. Pack, 
    223 W. Va. 828
    , 
    679 S.E.2d 660
    (applying
    three-part collateral order doctrine to circuit court’s denial of summary judgment on issue of
    qualified immunity and finding order immediately appealable).
    Applying the collateral order doctrine, the Robinson Court ultimately held that
    “[a] circuit court’s denial of summary judgment that is predicated on qualified immunity is
    an interlocutory ruling which is subject to immediate appeal under the ‘collateral order’
    doctrine.” Syl. pt. 2, 
    id. While Robinson involved
    a denial of immunity in the form of an
    order denying summary judgment, this Court has applied Robinson to a qualified immunity
    decision made in the form of a denial of a motion to dismiss. See Jarvis v. West Virginia
    State Police, 
    227 W. Va. 472
    , 
    711 S.E.2d 542
    (2010).
    9
    In concluding that the order denying the motion to dismiss was immediately
    appealable under the collateral order doctrine, the Jarvis Court adopted the rationale
    expressed in Robinson. In this respect, the Robinson Court explained that,
    [w]ith regard to the first factor of [the Cohen collateral
    order doctrine test], which requires that the ruling at issue must
    be conclusive, “the [trial] court’s denial of summary judgment
    [on the issue of qualified immunity] finally and conclusively
    determines the defendant’s claim of right not to stand trial on
    the plaintiff’s allegations.” [Mitchell v. Forsyth, 
    472 U.S. 511
    ,
    527, 
    105 S. Ct. 2806
    , 2816, 
    86 L. Ed. 2d 411
    (1985)]. Because
    a ruling denying the availability of immunity fully resolves the
    issue of a litigant’s obligation to participate in the litigation, the
    first factor of Cohen is easily met. As to the second factor[,]
    which focuses on whether the immunity ruling resolves
    significant issues separate from the merits, there is little question
    that the “claim of immunity is conceptually distinct from the
    merits of the plaintiff’s claim that his [or her] rights have been
    violated.” 
    Id. at 527–28, 105
    S. Ct. [at 2816, 
    86 L. Ed. 2d 411
    ].
    The final factor of the Cohen test requires us to consider
    whether a qualified immunity ruling is “effectively
    unreviewable” at the appeal stage. Postponing review of a
    ruling denying immunity to the post-trial stage is fruitless, as the
    United States Supreme Court reasoned in Mitchell, because the
    underlying objective in any immunity determination (absolute or
    qualified) is immunity from 
    suit. 472 U.S. at 526-27
    , 
    105 S. Ct. 2806
    ; see also Gray–Hopkins v. Prince George’s County, Md.,
    
    309 F.3d 224
    , 229 (4th Cir. 2002) (“Because qualified immunity
    is an immunity from having to litigate, as contrasted with an
    immunity from liability, it is effectively lost if a case is
    erroneously permitted to go to trial.”) (omitting internal
    citation); Jenkins v. Medford, 
    119 F.3d 1156
    , 1159 (4th Cir.
    1997) (observing that denial of qualified immunity defense
    “subjects the [government] official to the burdens of pretrial
    matters” and opining that “some of the rights inherent in a
    qualified immunity defense are [consequently] lost”).
    Traditional appellate review of a qualified immunity ruling
    10
    cannot achieve the intended goal of an immunity ruling: “the
    right not to be subject to the burden of trial.” Hutchison [v. City
    of Huntington, 
    198 W. Va. 139
    , 148, 
    479 S.E.2d 649
    , 658
    (1996)]. As a result, the third factor of Cohen is easily met.
    
    Robinson, 223 W. Va. at 832-33
    , 679 S.E.2d at 664-65 (concluding that “[a]pplication of the
    Cohen test demonstrates that a circuit court’s denial of summary judgment that is predicated
    on qualified immunity is an interlocutory ruling which is subject to immediate appeal under
    the ‘collateral order’ doctrine.”).
    Following the rationale expressed by the Robinson Court, we will analyze an
    order compelling arbitration under the collateral order doctrine to ascertain if such an order
    is among that limited class of interlocutory orders that is immediately appealable.7
    7
    In McGraw v. American Tobacco Co., this Court addressed the issue of
    whether an order granting a motion to compel arbitration was immediately appealable and
    held:
    A circuit court order compelling arbitration is not subject
    to direct appellate review prior to the dismissal of the circuit
    court action unless the order compelling arbitration otherwise
    complies with the requirements of West Virginia Code § 58–5–1
    (1998) and Rule 54(b) of the West Virginia Rules of Civil
    Procedure. A party seeking this Court’s review of a circuit
    court order compelling arbitration prior to entry of a final order
    which complies with the requirements of West Virginia Code
    § 58-5-1 (1998) and Rule 54(b) of the West Virginia Rules of
    Civil Procedure must do so in an original jurisdiction
    proceeding seeking a writ of prohibition.
    Syl. pt. 1, McGraw, 
    224 W. Va. 211
    , 
    681 S.E.2d 96
    (2009) (first emphasis added). Thus,
    (continued...)
    11
    As to the first factor in the collateral order test, that the ruling at issue
    “conclusively determines the disputed controversy,” 
    Durm, 184 W. Va. at 566
    n.2, 401
    S.E.2d at 912 
    n.2, we find that a circuit court’s ruling that refuses to compel arbitration is
    conclusive as to the disputed controversy of whether the parties are required to arbitrate. By
    7
    (...continued)
    under McGraw, an interlocutory order compelling arbitration is not subject to direct appeal
    unless certain conditions are met. Insofar as the McGraw opinion addressed an order
    compelling arbitration, as opposed to an order refusing to compel arbitration, it is not
    applicable to the instant proceeding. The practice of denying appeals of orders compelling
    arbitration absent a final order while allowing direct appeals of orders refusing to compel
    arbitration is consistent with how many other courts have treated appeals of arbitration
    decisions under the FAA. See 
    McGraw, 224 W. Va. at 220
    , 681 S.E.2d at 105 (“Section 16
    of the FAA governs appellate review of motions to compel arbitration, permitting it in some
    circumstances, while denying it in other[s]. 9 U.S.C. § 16 (1990).”). Accord Guidotti v.
    Legal Helpers Debt Resolution, L.L.C., No. 12-1170, 
    2013 WL 2302324
    , at *12 (3d Cir. May
    28, 2013) (“We have jurisdiction to review a district court’s denial of a motion to compel
    arbitration under 9 U.S.C. § 16[(a)](1)(B).” (emphasis added)); Adams v. Monumental Gen.
    Cas. Co., 
    541 F.3d 1276
    , 1277 (11th Cir. 2008) (“We have no jurisdiction over this appeal
    because the district court compelled arbitration. 9 U.S.C. § 16(b)(2). Section 16 governs
    the appealability of interlocutory orders regarding arbitration, ConArt, Inc. v. Hellmuth,
    Obata + Kassabaum, Inc., 
    504 F.3d 1208
    , 1210 (11th Cir.2007), and subsection (b)(2) states
    that ‘an appeal may not be taken from an interlocutory order . . . directing arbitration to
    proceed,’ 9 U.S.C. § 16(b)(2).”); Augustea Impb Et Salvataggi v. Mitsubishi Corp., 
    126 F.3d 95
    , 99 (2d Cir. 1997) (“Section 16(a)(1)(C)’s language provides that a party may appeal from
    a district court order denying a motion to compel arbitration pursuant to 9 U.S.C. § 206,
    while under section 16(b)(2) and (3) a party cannot appeal an order compelling arbitration.”).
    See also David D. Siegel, Practice Commentary to 9 U.S.C.A. § 16 (West 1990)
    (“Subdivision (a) of § 16 enumerates the situations in which an immediate appeal from an
    arbitrability determination is allowed. It applies for the most part to determinations against
    arbitration. Subdivision (b) enumerates the situations in which an appeal is not to be allowed,
    and all of them are decisions in favor of arbitration. In trumpeting this pro-arbitration view,
    however, note that subdivision (b) addresses only an ‘interlocutory’ order. Hence a
    pro-arbitration decision that amounts to a final disposition in its particular judicial context
    remains appealable . . . .”).
    12
    denying such a motion, the circuit court thereby concludes that a case will proceed to trial.
    Such a ruling forecloses arbitration of the underlying claims asserted and, therefore,
    conclusively resolves the issue of arbitration.
    The second factor of the collateral order test asks whether the order “resolves
    an important issue completely separate from the merits of the action,” 
    Durm, 184 W. Va. at 566
    n.2, 401 S.E.2d at 912 
    n.2. We find there to be little doubt that the issue of arbitration
    is completely separate from the merits of the underlying claims in a given action.
    Furthermore, resolution of the arbitration question is important in that it resolves the
    foundational question of the manner in which the parties will resolve their dispute, either by
    arbitration or through the courts.
    The final consideration in the collateral order test is whether the order “is
    effectively unreviewable on appeal from a final judgment.” 
    Durm, 184 W. Va. at 566
    n.2,
    401 S.E.2d at 912 
    n.2. We find that an order refusing to compel arbitration is effectively
    unreviewable on appeal. The result of such an order is litigation. The purpose of arbitration
    is to avoid litigation in favor of a quicker and less costly method of dispute resolution. See
    Raymond James Fin. Servs., Inc. v. Bishop, 
    596 F.3d 183
    , 190 (4th Cir. 2010) (commenting
    that “‘the purpose of having arbitration at all [is] the quick resolution of disputes and the
    avoidance of the expense and delay associated with litigation’” (quoting Apex Plumbing
    13
    Supply, Inc. v. U.S. Supply Co., Inc., 
    142 F.3d 188
    , 193 (4th Cir.1998))); Grayiel v.
    Appalachian Energy Partners 2001-D, LLP, 
    230 W. Va. 91
    , __, 
    736 S.E.2d 91
    , 101 (2012)
    (identifying one purpose of arbitration as “providing a suitable alternative forum for
    plaintiff’s claims”); Board of Ed. of Berkeley County v. W. Harley Miller, Inc., 
    160 W. Va. 473
    , 479, 
    236 S.E.2d 439
    , 443 (1977) (describing the purpose of arbitration as “just, speedy,
    economical conflict resolution”). Thus, a party who is required to wait until the conclusion
    of litigation to appeal the denial of arbitration has already borne the financial and temporal
    cost of such litigation and has, therefore, effectively lost, irreparably, the right to arbitration.
    Having found that an order denying a motion to compel arbitration fulfils the
    requirements of the collateral order doctrine, we now hold that an order denying a motion to
    compel arbitration is an interlocutory ruling which is subject to immediate appeal under the
    collateral order doctrine. Applying this holding to the instant case, we find the appeals are
    proper.
    When an appeal from an order denying a motion dismiss is properly before this
    Court, our review is de novo. See, e.g., Syl. pt. 4, Ewing, 
    202 W. Va. 228
    , 
    503 S.E.2d 541
    (“When a party, as part of an appeal from a final judgment, assigns as error a circuit court’s
    denial of a motion to dismiss, the circuit court’s disposition of the motion to dismiss will be
    14
    reviewed de novo.”). Accordingly, we proceed to conduct our de novo review of the issues
    raised in these consolidated appeals.
    III.
    DISCUSSION
    Credit Acceptance asserts that two errors warrant reversing the circuit courts’
    orders denying its motions to compel arbitration in these cases. First, Credit Acceptance
    argues that the circuit courts erred in finding the contracts to be unconscionable based upon
    the unavailability of arbitration forums named in the agreements. Second, Credit Acceptance
    argues that the circuit courts erroneously concluded that the arbitration agreements were
    unenforceable because the debtors therein waived their rights to a jury trial. We address
    these issues separately below.
    A. Unconscionability
    On the topic of contractual unconscionability, this Court previously has held
    that
    “[a] contract term is unenforceable if it is both
    procedurally and substantively unconscionable. However, both
    need not be present to the same degree. Courts should apply a
    ‘sliding scale’ in making this determination: the more
    substantively oppressive the contract term, the less evidence of
    procedural unconscionability is required to come to the
    conclusion that the clause is unenforceable, and vice versa.”
    Syllabus Point 20, Brown v. Genesis Healthcare Corp., 228
    
    15 W. Va. 646
    , 
    724 S.E.2d 250
    (2011)[, overruled in part on other
    grounds by Marmet Health Care Center, Inc. v. Brown, ___
    U.S. ___, 
    132 S. Ct. 1201
    , 
    182 L. Ed. 2d 42
    (2012) (per
    curiam).]”
    Syl. pt. 9, Brown v. Genesis Healthcare Corp., 
    729 S.E.2d 217
    , 221 (2012).8
    The circuit court orders in each of the two consolidated appeals concluded that
    the arbitration contracts were both procedurally and substantively unconscionable based upon
    the unavailability of one or both of the two named arbitration forums. Thus, we will address
    both theories of unconscionability.
    1. Procedural Unconscionability. The circuit court’s order in the Front case,
    Appeal No. 11-1646, found the contract to be procedurally unconscionable as follows:
    The court is apprised of the fact that the original contract
    is not procedurally unconscionable, in as much [sic] as it
    provided an adequate means for the plaintiffs to opt out of it;
    was adequately brought to the attention of the plaintiffs; and,
    provided two separate arbitration forums. However, the fact
    that one of the specific arbitration forums has been eliminated,
    8
    The author of this opinion did not participate in the decision in Brown ex rel.
    Brown v. Genesis Healthcare Corp., 
    228 W. Va. 646
    , 
    724 S.E.2d 250
    (2011), overruled in
    part on other grounds by Marmet Health Care Center, Inc. v. Brown, ___ U.S. ___, 
    132 S. Ct. 1201
    , 
    182 L. Ed. 2d 42
    (2012). Separate from the majority, the author of this opinion
    independently questions the need for establishing both substantive and procedural
    unconscionability to find a contractual term is unenforceable. However, insofar as this
    opinion ultimately reaches the conclusion that the contractual terms at issue were not
    unconscionable, and the parties have not challenged this Court’s prior holding, the
    consolidated cases sub judice do not present the proper opportunity for such an analysis.
    16
    materially changing the terms of the contract, causes the court
    to determine that there was no meeting of the minds to create the
    contract as it exists today.
    The circuit court’s order in the Shrewsbury case, Appeal No. 12-0545,
    concluded that
    the contract in this matter is not procedurally unconscionable in
    that it provided an adequate means for the Plaintiff to opt out.
    Further, the arbitration agreement was clearly brought to the
    attention of the Plaintiff in the contract, and provided for
    arbitration by two separate forums, NAF and AAA. However,
    neither of the specified forums currently accepts creditor
    arbitration agreements requests. Because the specific arbitration
    forums have been eliminated, there has been a material change
    in the terms of the contract. The Court has therefore determined
    that there was no meeting of the minds to create the contract as
    it exists today, and the arbitration agreement is unenforceable.
    Notably, both of the orders quoted above concluded that the contracts at issue
    were not procedurally unconscionable at the time of their execution, but were rendered
    procedurally unconscionable by subsequent events. In Syllabus point 10 of Brown v. Genesis
    Healthcare Corp., 
    229 W. Va. 382
    , 
    729 S.E.2d 217
    (2012) (hereinafter referred to as “Brown
    II”), this Court explained that
    “[p]rocedural unconscionability is concerned with
    inequities, improprieties, or unfairness in the bargaining process
    and formation of the contract. Procedural unconscionability
    involves a variety of inadequacies that results in the lack of a
    real and voluntary meeting of the minds of the parties,
    considering all the circumstances surrounding the transaction.
    17
    These inadequacies include, but are not limited to, the age,
    literacy, or lack of sophistication of a party; hidden or unduly
    complex contract terms; the adhesive nature of the contract; and
    the manner and setting in which the contract was formed,
    including whether each party had a reasonable opportunity to
    understand the terms of the contract.” Syllabus Point 17, Brown
    v. Genesis Healthcare Corp., 
    228 W. Va. 646
    , 
    724 S.E.2d 250
                  (2011)[, overruled in part on other grounds by Marmet Health
    Care Center, Inc. v. Brown, ___ U.S. ___, 
    132 S. Ct. 1201
    , 
    182 L. Ed. 2d 42
    (2012) (per curiam).]”
    (Emphasis added). As the Brown II Court observed, procedural unconscionability relates to
    unconscionability at the time a contract is formed “in the bargaining process and formation
    of the contract.” 
    Id. Because this Court’s
    review must focus on the contract at the time it
    was agreed upon, the circuit courts’ conclusions that the contracts could be rendered
    procedurally unconscionable by subsequent events is erroneous.9
    2. Substantive Unconscionability. The circuit court’s order in the Front case,
    Appeal No. 11-1646, stated, with respect to substantive unconscionability, that
    [i]n examining the matter of substantive
    unconscionability, the court finds that the elimination of an
    arbitration forum is a substantive change in the terms of the
    contract. Public policy favors a plaintiff having his day in court
    9
    Ms. Shrewsbury argues that the NAF consent decree and AAA moratorium
    were already in place when her contract was executed naming the foregoing organizations
    as arbitrators. Thus, she contends that her contract was procedurally unconscionable at the
    time of its formation. We disagree. Ms. Shrewsbury fails to allege that Credit Acceptance
    named these forums in the contract for the purpose of achieving an unfair advantage, nor
    does she direct this Court to any evidence in the appendix record that would support such a
    theory. Therefore, we reject this argument.
    18
    should the terms of a contract be materially altered after the
    execution of said contract.
    The circuit court’s order in the Shrewsbury case, Appeal No. 12-0545, likewise
    stated that,
    [i]n examining substantive unconscionability, the court
    finds that the elimination of the arbitration forums is a material
    change in the terms of the contract. Public policy favors a
    plaintiff having his day in court should the terms of a contract be
    materially altered after the execution of the contract. Further,
    this court is reluctant to uphold an arbitration agreement which
    essentially eliminates a party’s constitutional right to file suit,
    especially when the agreement no longer exists in its original
    form. Although the right to assert one’s claim in the court
    system may be subject to a legally enforceable waiver, courts
    indulge every reasonable presumption against waiver of a
    fundamental constitutional right and will not presume
    acquiescence in the loss of such fundamental right. . . . For
    these reasons, the Court finds that the arbitration agreement in
    this case is unenforceable.
    (Internal citations and quotations omitted).
    This Court has clarified that,
    “[s]ubstantive unconscionability involves unfairness in
    the contract itself and whether a contract term is one-sided and
    will have an overly harsh effect on the disadvantaged party. The
    factors to be weighed in assessing substantive unconscionability
    vary with the content of the agreement. Generally, courts should
    consider the commercial reasonableness of the contract terms,
    the purpose and effect of the terms, the allocation of the risks
    between the parties, and public policy concerns.” Syllabus Point
    19, Brown v. Genesis Healthcare Corp., 
    228 W. Va. 646
    , 724
    
    19 S.E.2d 250
    (2011)[, overruled in part on other grounds by
    Marmet Health Care Center, Inc. v. Brown, ___ U.S. ___, 
    132 S. Ct. 1201
    , 
    182 L. Ed. 2d 42
    (2012) (per curiam).]”
    Syl. pt. 12, Brown II, 
    229 W. Va. 382
    , 
    729 S.E.2d 217
    . The sole basis for the conclusions
    of the circuit courts that the Front and Shrewsbury contracts were substantively
    unconscionable was the unavailability of one or both of the arbitration forums designated in
    the agreement to govern arbitration between the parties to the respective contracts. Insofar
    as the determination of substantive unconscionability instructs a reviewing court to examine
    the general fairness of the contract through factors such as “the commercial reasonableness
    of the contract terms, the purpose and effect of the terms, the allocation of the risks between
    the parties, and public policy concerns,” we find this analysis simply is not applicable to the
    determination of whether the unavailability of a selected arbitration forum renders a contract
    unenforceable. There is nothing inherently unreasonable about a contract term in which the
    parties choose to select one or more forums to conduct arbitration of disputes that may arise
    between said parties.     The subsequent unavailability of a selected forum does not
    automatically render the contract unconscionable. Rather, courts have developed other tests,
    which will be discussed below, for determining whether the unavailability of a chosen
    arbitration forum renders a contract unenforceable. Accordingly, we find that both of the
    20
    circuit courts erred in finding the Front and Shrewsbury contracts to be substantively
    unconscionable based upon the unavailability of a chosen arbitration forum.10
    B. Forum Availability
    The essence of the unconscionability arguments made to this Court in these
    consolidated appeals is more properly framed as challenging whether the unavailability of
    a chosen arbitration forum renders an arbitration agreement unenforceable. We begin our
    analysis with the FAA, insofar as the arbitration agreements at issue all stated that they are
    governed thereby. Section 5 of the FAA requires a court to designate an arbitrator under
    certain circumstances:
    If in the agreement provision be made for a method of
    naming or appointing an arbitrator or arbitrators or an umpire,
    such method shall be followed; but if no method be provided
    therein, or if a method be provided and any party thereto shall
    fail to avail himself of such method, or if for any other reason
    there shall be a lapse in the naming of an arbitrator or arbitrators
    or umpire, or in filling a vacancy, then upon the application of
    either party to the controversy the court shall designate and
    10
    Ms. Shrewsbury additionally argues that her contract was substantively
    unconscionable because the arbitration clause was buried on the back of a densely-printed
    form. However, this argument was neither raised to or addressed by the circuit court.
    Accordingly, the issue is not properly before this Court for our review. See Syl. pt. 2, Trent
    v. Cook, 
    198 W. Va. 601
    , 
    482 S.E.2d 218
    (1996) (“‘[T]he Supreme Court of Appeals is
    limited in its authority to resolve assignments of nonjurisdictional errors to a consideration
    of those matters passed upon by the court below and fairly arising upon the portions of the
    record designated for appellate review.’ Syl. Pt. 6, in part, Parker v. Knowlton Const. Co.,
    Inc., 
    158 W. Va. 314
    , 
    210 S.E.2d 918
    (1975).”), overruled on other grounds by Gibson v.
    Northfield Ins. Co., 
    219 W. Va. 40
    , 
    631 S.E.2d 598
    (2005).
    21
    appoint an arbitrator or arbitrators or umpire, as the case may
    require, who shall act under the said agreement with the same
    force and effect as if he or they had been specifically named
    therein; and unless otherwise provided in the agreement the
    arbitration shall be by a single arbitrator.
    9 U.S.C. § 5. Federal courts have concluded that section 5 of the FAA may be applied when
    a chosen arbitrator is unavailable. See Khan v. Dell Inc., 
    669 F.3d 350
    , 354 (3d Cir. 2012)
    (“[S]ection 5 of the FAA . . . provides a mechanism for substituting an arbitrator when the
    designated arbitrator is unavailable.”); Brown v. ITT Consumer Fin. Corp., 
    211 F.3d 1217
    ,
    1222 (11th Cir. 2000) (“Where the chosen forum is unavailable, however, or has failed for
    some reason, § 5 applies and a substitute arbitrator may be named.”); Astra Footwear Indus.
    v. Harwyn Int’l, Inc., 
    442 F. Supp. 907
    , 910 (S.D.N.Y.), aff’d, 
    578 F.2d 1366
    (2d Cir.1978)
    (“The Court finds that 9 U.S.C. § 5 was drafted to provide a solution to the problem caused
    when the arbitrator selected by the parties cannot or will not perform.”).
    However, section 5 of the FAA does not warrant the automatic appointment
    of a substitute arbitrator when the chosen arbitrator is unavailable. A method for applying
    section 5 of the FAA under such circumstances was established by the Eleventh Circuit Court
    of Appeals in Brown v. ITT Consumer Financial Corp., 
    211 F.3d 1217
    . More recently, the
    Brown method was summarized by the Third Circuit Court of Appeals as follows:
    In determining the applicability of Section 5 of the FAA when
    an arbitrator is unavailable, courts have focused on whether the
    designation of the arbitrator was integral to the arbitration
    provision or was merely an ancillary consideration. . . . [O]nly
    22
    if the choice of forum is an integral part of the agreement to
    arbitrate, rather than an ancillary logistical concern, will the
    failure of the chosen forum preclude arbitration. . . . In other
    words, a court will decline to appoint a substitute arbitrator, as
    provided in the FAA, only if the parties’ choice of forum is so
    central to the arbitration agreement that the unavailability of that
    arbitrator brings the agreement to an end. . . . In this light, the
    parties must have unambiguously expressed their intent not to
    arbitrate their disputes in the event that the designated arbitral
    forum is unavailable.
    
    Kahn, 669 F.3d at 354
    (quotations and citations omitted). This formulation of the application
    of section 5 of the FAA is the majority rule.11 See Ranzy v. Tijerina, 393 Fed. Appx. 174,
    176 (5th Cir. 2010) (“Section 5 [of the FAA] does not, however, permit a district court to
    circumvent the parties’ designation of an exclusive arbitration forum when the choice of that
    11
    See Diversicare Leasing Corp. v. Nowlin, No. 11-CV-1037, 
    2011 WL 5827208
    , at *5 (W.D. Ark. Nov. 18, 2011) (“The majority of courts who have addressed
    whether a substitute can be appointed pursuant to Section 5 [when the specifically named
    forum in an arbitration agreement cannot hear the parties’ claims] have utilized the approach
    set out in Brown v. ITT Consumer Financial Corp., 
    211 F.3d 1217
    (11th Cir.2000)). See also
    Rivera v. American Gen. Fin. Servs., Inc., 
    259 P.3d 803
    , 812 (N.M. 2011) (observing
    “[m]any jurisdictions have . . . concluded that Brown’s “integral” versus “ancillary logistical
    concern” test is a proper way to determine whether a court may appoint a substitute
    arbitration provider.”).
    To the contrary, at least one federal court has found that section 5 of the FAA
    never applies to appoint a substitute for a named arbitration forum that is unavailable because
    the unavailability of a selected forum does not fall within the meaning of the term “lapse”
    as used in section 5. See In re Salomon Inc. Shareholders’ Derivative Litig. 91 Civ. 5500
    (RRP), 
    68 F.3d 554
    , 560 (2d Cir. 1995) (concluding that “[s]ection 5 applies when there is
    ‘a lapse in the naming of an arbitrator . . . or in filling a vacancy.’ 9 U.S.C. § 5 (emphasis
    added). We believe that the ‘lapse’ referred to in § 5 means ‘a lapse in time in the naming
    of the’ arbitrator or in the filling of a vacancy on a panel of arbitrators, Pacific Reins. Mgt.
    Corp.[ v. Ohio Reins. Corp], 814 F.2d[ 1324,] 1327 [(9th Cir.1987)], or some other
    mechanical breakdown in the arbitrator selection process[.]”).
    23
    forum is an integral part of the agreement to arbitrate, rather than an ancillary logistical
    concern.” (quotations and citations omitted)); Reddam v. KPMG LLP, 
    457 F.3d 1054
    ,
    1059–60 (9th Cir. 2006) (“When a court asks whether a choice of forum is integral, it asks
    whether the whole arbitration agreement becomes unenforceable if the chosen arbitrator
    cannot or will not act.”), overruled on other grounds as recognized in Atlantic Nat’l Trust
    LLC v. Mt. Hawley Ins. Co., 
    621 F.3d 931
    , 940 (9th Cir. 2010); Brown v. ITT Consumer Fin.
    
    Corp., 211 F.3d at 1222
    (“Where the chosen forum is unavailable . . . or has failed for some
    reason, § 5 applies and a substitute arbitrator may be named. . . . Only if the choice of forum
    is an integral part of the agreement to arbitrate, rather than an ancillary logistical concern will
    the failure of the chosen forum preclude arbitration.” (quotations and citations omitted));
    Green v. U.S. Cash Advance Illinois, LLC, No. 12-C-8079, 
    2013 WL 317046
    , at *3 (N.D. Ill.
    Jan. 25, 2013) (“A substitute arbitrator may not be appointed, however, if the provision
    naming the arbitrator was an integral part of the agreement. Thus, the court must decide
    before applying § 5 whether the chosen arbitration forum is integral to the agreement or
    merely an ancillary logistical concern.” (citations and quotations omitted)); Klima v.
    Evangelical Lutheran Good Samaritan Soc’y, No. 10-CV-1390-JAR-JPO, 
    2011 WL 5412216
    , at *3 (D. Kan. Nov. 8, 2011) (following majority based on finding “the approach
    taken by the Fifth, Ninth, and Eleventh Circuits consistent with both the purpose behind the
    FAA and general principles of contract law because it treats arbitration agreements like
    contracts and looks to the parties’ intent”); Adler v. Dell Inc., No. 08-CV-13170, 
    2009 WL 24
    4580739, at *2 (E.D. Mich. Dec. 3, 2009) (“As a general rule, when the arbitrator named in
    the arbitration agreement cannot or will not arbitrate the dispute, the court does not void the
    arbitration agreement. Instead, it appoints a different arbitrator, as provided in [§ 5 of] the
    Federal Arbitration Act[.] . . . The exception to this rule occurs when it is clear that the failed
    term is not an ancillary logistical concern but rather is as important a consideration as the
    agreement to arbitrate itself.” (internal quotations, citations, and footnote omitted));
    McGuire, Cornwell & Blakey v. Grider, 
    771 F. Supp. 319
    , 320 (D. Colo. 1991) (“[A]s a
    general rule, where the arbitrator named in the arbitration agreement cannot or will not
    arbitrate the dispute, a court does not void the agreement but instead appoints a different
    arbitrator. . . . There is an exception to this rule. Where it is clear that the failed term is not
    an ancillary logistical concern but rather is as important a consideration as the agreement to
    arbitrate itself, a court will not sever the failed term from the rest of the agreement and the
    entire arbitration provision will fail.” (internal quotations and citations omitted)); Carr v.
    Gateway, Inc., 
    241 Ill. 2d 15
    , 26, 
    944 N.E.2d 327
    , 333 (2011) (“[W]e agree with those
    federal courts that have held section 5 of the Act may be applied to name a substitute
    arbitrator where the parties’ designated arbitral forum fails, unless the designation of the
    arbitral forum is integral to the parties’ agreement to arbitrate.”); Rivera v. American Gen.
    Fin. Servs., Inc., 
    259 P.3d 803
    , 812 (N.M. 2011) (“We agree with the jurisdictions that have
    focused on the parties’ intent, as expressed in the contract, to determine whether § 5 of the
    FAA permits a court to substitute a different arbitration provider. The ‘integral’ or ‘ancillary
    25
    logistical concern’ test articulated by the Eleventh Circuit in 
    Brown, 211 F.3d at 1222
    , is
    consistent with New Mexico’s general principles of contract law in requiring courts to give
    effect to the intent of the parties.” (second internal quotation and citation omitted)).
    The majority rule is founded on the “liberal federal policy in favor of
    arbitration articulated in the FAA.” 
    Kahn, 669 F.3d at 356
    (internal quotations omitted). The
    rationale for the rule has been explained as follows:
    When the reference to arbitration rules or an arbitration
    forum is merely “an ancillary or logistical concern,” the
    application of Section 5 to appoint a different arbitrator does not
    do violence to the intentions of the parties. By contrast, when
    the choice of arbitration forum was integral to the agreement,
    such that the parties would not have agreed upon arbitration
    absent the selected forum, application of Section 5 to appoint a
    substitute arbitrator is more problematical.
    Jones v. GGNSC Pierre LLC, 
    684 F. Supp. 2d 1161
    , 1166 (D.S.D. 2010).
    We are persuaded by the foregoing authority, and, therefore, we now expressly
    hold that where an arbitration agreement names a forum for arbitration that is unavailable or
    has failed for some reason, a court may appoint a substitute forum pursuant to section 5 of
    the Federal Arbitration Act, 9 U.S.C. § 5 (1947) (2006 ed.), only if the choice of forum is an
    ancillary logistical concern. Where the choice of forum is an integral part of the agreement
    to arbitrate, the failure of the chosen forum will render the arbitration agreement
    unenforceable.
    26
    Turning to the facts of the instant consolidated cases, the three arbitration
    agreements involved in this appeal contained the following provision: “You or we may elect
    to arbitrate under the rules and procedures of either the National Arbitration Forum or the
    American Arbitration Association.” As we explained in the “Factual and Procedural
    History” section of this opinion, Section 
    I.A., supra
    , as a result of a suit filed by the State of
    Minnesota, the NAF entered into a consent decree forbidding it from conducting consumer
    arbitration. See CompuCredit Corp. v. Greenwood, ___ U.S. at ___ 
    n.2, 132 S. Ct. at 677
    n.2, 
    181 L. Ed. 2d
    . 586 (“In 2009, after the Attorney General of Minnesota filed an action
    alleging that NAF had engaged in numerous violations of consumer-protection laws, NAF
    entered into a consent decree barring it from handling consumer arbitrations.”). Thus, the
    NAF is unavailable to arbitrate the claims asserted by the Fronts and Ms. Shrewsbury against
    Credit Acceptance.
    Shortly after the NAF was barred from handling consumer arbitrations, the
    “AAA issued a moratorium on arbitrating cases concerning consumer debt collections if
    those cases were brought by the company and the consumer did not consent to the
    arbitration.” Montgomery v. Applied 
    Bank, 848 F. Supp. 2d at 613
    (emphasis added). It is
    significant that the moratorium issued by the AAA applies only to consumer debt collection
    cases brought by the company. Thus, as Credit Acceptance has asserted, because the claims
    against it were brought by consumers, the Fronts and Ms. Shrewsbury, the AAA remains an
    27
    available forum to arbitrate those claims. Indeed, during oral argument of this case, counsel
    for the Fronts and Ms. Shrewsbury rightfully conceded that the AAA remained available to
    arbitrate his clients’ disputes. See 
    Montgomery, 848 F. Supp. 2d at 614
    (“AAA indicates that
    it will continue to administer all demands for arbitration filed by consumers against
    businesses, and all other types of consumer arbitrations.” (quotations and citation omitted)).
    See also American Arbitration Association, “Notice on Consumer Debt Collection
    A r b i t r a t i o n s , ”                         a v a i l a b l e                   a t ,
    http://www.adr.org/cs/groups/governmentandconsumer/documents/document/dgdf/mdey/
    ~edisp/adrstg_012244.pdf (“[T]he AAA’s previously announced moratorium on debt
    collection arbitrations remains in effect. . . . Matters included in this moratorium are:
    consumer debt collection programs or bulk filings and individual case filings in which the
    company is the filing party and the consumer has not agreed to arbitrate at the time of the
    dispute, and the case involves a credit card bill, a telecom bill or a consumer finance matter.
    The AAA will continue to administer all demands for arbitration filed by consumers against
    businesses as well as all other types of consumer arbitrations.” (emphasis added)).
    Because one of the arbitration forums named in the arbitration agreements
    remains available to arbitrate the disputes underlying this appeal, it is not necessary for this
    Court to conduct an analysis as to whether the forum selection was merely an ancillary
    logistical concern, or was instead an integral part of the agreement to arbitrate. Due to the
    28
    availability of a chosen forum, the circuit courts erred in denying Credit Acceptance’s
    motions to compel arbitration. See, e.g., Montgomery v. Applied Bank, 
    848 F. Supp. 2d 609
    ,
    613 (finding arbitration agreement not unenforceable on grounds of unavailability of forum,
    in part, because AAA remained available); Conroy v. Citibank, N.A., No. CV 10–04930
    SVW (AJWx), 
    2011 WL 10503532
    , at *6 (C.D. Cal. July 22, 2011) (rejecting argument that
    arbitration agreement unenforceable due to potential unavailability of forum where AAA
    remained available); Smith v. ComputerTraining.com Inc., 
    772 F. Supp. 2d 850
    , 862 (E.D.
    Mich. 2011) (“This case is not covered by the moratorium. It does not involve a consumer
    debt collection, telecom bill, or consumer finance matter. Instead, this case constitutes a
    claim which would be filed by consumers against a business, which AAA’s website explicitly
    says that it will hear. . . . Plaintiffs can demand arbitration before AAA.” (citation omitted));
    In re Pfeiffer, Bankr. No. 11–13274, 
    2011 WL 4005504
    , at *8 (Bkrtcy. E.D. Pa. Sept. 8,
    2011) (finding FAA section 5 inapplicable due to availability of AAA).
    C. Right to a Jury Trial
    In the Front case, Appeal No. 11-1646, the circuit court found that the Fronts
    could not contractually waive their rights under the WVCCPA, stating:
    West Virginia Code § 46A-1-107 prohibits West Virginia
    consumers from waiving any rights under the West Virginia
    Consumer Credit and Protection Act (the “Act”’). The Act
    states:
    Except as otherwise provided in this chapter, a
    29
    consumer may not waive or agree to forgo rights
    or benefits under this chapter or under article
    two-a, chapter forty-six of this code.
    The court is of the opinion that a consumer’s . . . rights afforded
    under the Act include the right to a jury trial. This right cannot
    be waived by an agreement, especially an agreement which no
    longer exists in its original form.
    Similarly, in the Shrewsbury case, Appeal No. 12-0545, the circuit court stated:
    [T]his Court is reluctant to uphold an arbitration agreement
    which essentially eliminates a party’s constitutional right to file
    suit . . . . Although the right to assert one’s claim in the court
    system may be subject to a legally enforceable waiver, “[c]ourts
    indulge every reasonable presumption against waiver of a
    fundamental constitutional right and will not presume
    acquiescence in the loss of such fundamental right.” Syllabus
    Point 2, State ex rel. May v. Boles, 
    149 W. Va. 155
    , 
    139 S.E.2d 177
    (1964).
    Credit Acceptance argues that the foregoing rulings were erroneous. We agree.
    In Syllabus point 1 of Brown II, this Court held:
    Under the Federal Arbitration Act, 9 U.S.C. § 2, a written
    provision to settle by arbitration a controversy arising out of a
    contract that evidences a transaction affecting interstate
    commerce is valid, irrevocable, and enforceable, unless the
    provision is found to be invalid, revocable or unenforceable
    upon a ground that exists at law or in equity for the revocation
    of any contract.
    
    229 W. Va. 382
    , 
    729 S.E.2d 217
    (citation omitted). Thus, insofar as an arbitration
    agreement, by its very nature, requires a party to surrender his or her right to litigate, it may
    30
    not be invalidated solely upon that ground. See American Gen. Life & Acc. Ins. Co. v. Wood,
    
    429 F.3d 83
    , 91 n.6 (4th Cir. 2005) (“To the extent that Wood argues that any waiver of his
    constitutional right to access to state courts or trial by jury must be knowing and voluntary,
    we have already stated that ‘the loss of the right to a jury trial is a necessary and fairly
    obvious consequence of an agreement to arbitrate.’ Snowden v. CheckPoint Check Cashing,
    
    290 F.3d 631
    , 638 (4th Cir. 2002) (internal quotations and citations omitted).”); Lake James
    Cmty. Volunteer Fire Dep’t, Inc. v. Burke Cnty., N.C., 
    149 F.3d 277
    , 280 (4th Cir. 1998)
    (commenting “simply because a contract includes the waiver of a constitutional right does
    not render the contract per se unenforceable” and including the right to a jury trial in a list
    of waivers of rights that have been upheld). See also Harrington v. Atlantic Sounding Co.,
    Inc., 
    602 F.3d 113
    , 126 (2d Cir. 2010) (concluding “Harrington’s argument that the
    Agreement was substantively unconscionable because it takes away his right to a trial by jury
    fails because courts may not rely on the uniqueness of an agreement to arbitrate, which
    necessarily waives jury trial, as a basis for a state-law holding that enforcement would be
    unconscionable. . . . It is well-settled that waivers of jury trial are fully enforceable under the
    FAA,” and collecting cases (quotations and citations omitted)).
    Furthermore,
    [a] state statute, rule, or common-law doctrine, which
    targets arbitration provisions for disfavored treatment and which
    is not usually applied to other types of contract provisions,
    stands as an obstacle to the accomplishment and execution of
    31
    the purposes and objectives of the Federal Arbitration Act, 9
    U.S.C. § 2, and is preempted.
    Syl. pt. 8, Brown ex rel. Brown v. Genesis Healthcare Corp., 
    228 W. Va. 646
    , 
    724 S.E.2d 250
    , 261 (2011), overruled in part on other grounds by Marmet Health Care Ctr., Inc. v.
    Brown, ___ U.S. ___, 
    132 S. Ct. 1201
    , 
    182 L. Ed. 2d 42
    (2012) (per curiam). Insofar as the
    circuit courts’ rulings single out arbitration for disfavored treatment, such rulings must be
    rejected. Accordingly, we find that both circuit courts erred in their conclusions that the
    arbitration agreements were invalid as waiving the right to a jury trial.
    IV.
    CONCLUSION
    For the reasons expressed in the body of this opinion, in Appeal No. 11-1646,
    we reverse the October 20th, 2011, order of the Circuit Court of Raleigh County, in which
    the Fronts were plaintiffs, and remand the cases consolidated by that court for entry of an
    order compelling arbitration.
    We likewise, for the same reasons, in Appeal No. 12-0545, reverse the March
    28, 2012, order of the Circuit Court of Raleigh County, in which Ms. Shrewsbury was the
    plaintiff, and remand for entry of an order compelling arbitration.
    Appeal No. 11-1646, Reversed and Remanded.
    Appeal No. 12-0545, Reversed and Remanded.
    32
    

Document Info

Docket Number: 11-1646 & 12-0545

Citation Numbers: 231 W. Va. 518, 745 S.E.2d 556

Judges: Davis, Ketchum

Filed Date: 6/19/2013

Precedential Status: Precedential

Modified Date: 8/6/2023

Authorities (39)

Conart, Inc. v. Hellmuth, Obata + Kassabaum, Inc. , 504 F.3d 1208 ( 2007 )

Adams v. Monumental General Casualty Co. , 541 F.3d 1276 ( 2008 )

Harrington v. Atlantic Sounding Co., Inc. , 602 F. Supp. 3d 113 ( 2010 )

Augustea Impb Et Salvataggi, Scinicariello Augustea Ship ... , 126 F.3d 95 ( 1997 )

American General Life and Accident Insurance Company v. ... , 429 F.3d 83 ( 2005 )

in-re-salomon-inc-shareholders-derivative-litigation-91-civ-5500-rrp , 68 F.3d 554 ( 1995 )

Atlantic National Trust LLC v. Mt. Hawley Insurance , 621 F.3d 931 ( 2010 )

patricia-snowden-and-karen-dowhite-sheila-diane-dowhite-lilistyne-dowhite , 290 F.3d 631 ( 2002 )

Lake James Community Volunteer Fire Department, ... , 149 F.3d 277 ( 1998 )

Raymond James Financial Services, Inc. v. Bishop , 596 F.3d 183 ( 2010 )

Apex Plumbing Supply, Incorporated Harold Falchick v. U.S. ... , 142 F.3d 188 ( 1998 )

marion-gray-hopkins-in-her-individual-capacity-as-mother-personal , 309 F.3d 224 ( 2002 )

steven-douglas-jenkins-david-chris-bossard-william-martin-buckner-robert , 119 F.3d 1156 ( 1997 )

McGuire, Cornwell & Blakey v. Grider , 771 F. Supp. 319 ( 1991 )

Smith v. COMPUTERTRAINING. COM INC. , 772 F. Supp. 2d 850 ( 2011 )

Carr v. Gateway, Inc. , 241 Ill. 2d 15 ( 2011 )

Cohen v. Beneficial Industrial Loan Corp. , 69 S. Ct. 1221 ( 1949 )

United States v. Hollywood Motor Car Co. , 102 S. Ct. 3081 ( 1982 )

Mitchell v. Forsyth , 105 S. Ct. 2806 ( 1985 )

Astra Footwear Industry v. Harwyn International, Inc. , 442 F. Supp. 907 ( 1978 )

View All Authorities »