Primrose Retirement Communities, LLC and Gillette Retirement, LLC v. Ghidorzi Construction Company, LLC , 2023 WY 15 ( 2023 )


Menu:
  •               IN THE SUPREME COURT, STATE OF WYOMING
    
    2023 WY 15
    OCTOBER TERM, A.D. 2022
    February 8, 2023
    PRIMROSE RETIREMENT COMMUNITIES, LLC
    and GILLETTE RETIREMENT, LLC,
    Appellants
    (Plaintiffs),
    S-22-0162
    v.
    GHIDORZI CONSTRUCTION COMPANY, LLC,
    Appellee
    (Defendant/Third-party Plaintiff).
    Appeal from the District Court of Campbell County
    The Honorable Bill Simpson, Judge
    Representing Appellants:
    Amanda K. Roberts and J. Kyle Hendrickson, Lonabaugh and Riggs, LLP,
    Sheridan, Wyoming; Ryan W. McGrath and J. David Horning, Horning, Horning &
    McGrath, LLC, Gillette, Wyoming. Argument by Mr. Hendrickson.
    Representing Appellee:
    Stephenson D. Emery, Williams, Porter, Day & Neville, P.C., Casper, Wyoming;
    Nicholas D. Harken and Eugene M. LaFlamme, McCoy Leavitt Laskey, LLC,
    Waukesha, Wisconsin. Argument by Mr. Harken.
    Before FOX, C.J., and KAUTZ, BOOMGAARDEN, GRAY, and FENN, JJ.
    NOTICE: This opinion is subject to formal revision before publication in Pacific Reporter Third. Readers are
    requested to notify the Clerk of the Supreme Court, Supreme Court Building, Cheyenne, Wyoming 82002, of
    any typographical or other formal errors so that correction may be made before final publication in the
    permanent volume.
    GRAY, Justice.
    [¶1] In this construction contract dispute, Primrose Retirement Communities, LLC and
    its local affiliate Gillette Retirement, LLC (together Primrose) 1 appeal from the district
    court’s grant of summary judgment in favor of Ghidorzi Construction Company, LLC
    (Ghidorzi) on claims of breach of contract and breach of the implied covenant of good faith
    and fair dealing. The district court determined that Primrose failed to submit evidence that
    Ghidorzi’s alleged breach caused Primrose’s damages and that the contract language
    obviated any need to impose an implied covenant. We reverse in part and affirm in part.
    ISSUES
    [¶2]    The issues are:
    1.      Did the district court err in granting summary judgment
    on Primrose’s breach of contract claim?
    2.      Did the district court err in granting summary judgment
    on Primrose’s breach of the implied covenant of good
    faith and fair dealing?
    FACTS
    [¶3] In 2008, Primrose found a location for a new assisted living facility in Gillette,
    Wyoming. Primrose retained WAI Continuum as the project architect and Terracon
    Consultants, a geotechnical consulting firm, to assess the soils, prepare a soils report, and
    make structural recommendations for construction and to inform potential bidders. On
    August 5, 2008, Terracon issued its report—the Terracon Report—which identified
    expansive soils under the construction site and provided recommendations “to help
    mitigate the effects of soils shrinkage and expansion” on the proposed facility. Terracon’s
    first recommendation was that “the proposed structure be supported on a drilled
    pier/caisson foundation system bearing on sandstone bedrock.” The report contained an
    alternate recommendation that, “[i]f the owner is willing to assume additional risk
    associated with soil shrinkage and expansion, spread footings bearing on a minimum of 5
    feet of new, non-expansive, low-permeability, engineered fill may be used to support the
    proposed structure.”         The report included specific design and construction
    recommendations for the foundation systems, pavements, and other earth-related phases of
    the project should the owner choose the alternate method. These recommendations were
    1
    Primrose constructs, develops, and manages independent and assisted living facilities. Gillette Retirement
    is an independent group of investors who own the facility and contract with Primrose for management
    services.
    1
    intended to result in construction that would allow a tolerance of one inch of differential
    movement. Primrose chose the alternate construction method.
    [¶4] Primrose selected Ghidorzi as the general contractor for the project. The
    construction contract (Contract) was signed on September 11, 2009. The Contract
    specifically excludes the Terracon Report as part of the Contract but contains a drawing
    with an annotation that states the Terracon soils report specifications must be strictly
    adhered to. The project was completed in 2010. In 2011, Primrose noticed some
    movement of the slabs and walls in and near the water service room where the water main
    entered the building (Area A). Primrose notified Ghidorzi of the problem and a Ghidorzi
    representative was sent to inspect the situation. After its inspection, Ghidorzi wrote to
    Primrose stating it had tested the soils and there was an increase in water saturation in Area
    A. It also pointed out that the “construction of the building is per the construction
    documents.” Ghidorzi suggested that “[m]ovement in the building is the nature of this site
    when building with spread footings.”
    [¶5] The problems continued to escalate into 2012 when Primrose contacted the City of
    Gillette. The City pressure-tested the water main for a leak but did not find one. The soil
    movement continued to cause cracks and separation in the floors and walls of the building.
    Primrose observed heavy ground saturation in the vicinity of the water service room and
    evidence of standing and subsurface water. In September 2013, Primrose again contacted
    the City and the City conducted another pressure test. This time it identified a leak where
    the service line connected to the water main just outside the water service room. At roughly
    the same time, Primrose excavated the affected area and discovered water was “gushing
    [and] boiling up into the holes.” An inspection of the service line installed by a Ghidorzi
    subcontractor revealed the leak was at the “T” connection between the service line and the
    City water line. The connection was missing “all thread” necessary to hold the pipes
    together. The connection was repaired but the differential movement continued.
    [¶6] On April 7, 2016, Primrose filed a complaint against Ghidorzi alleging negligence,
    breach of contract, and breach of the implied covenant of good faith and fair dealing.
    Primrose also alleged negligence claims against the City of Gillette. Primrose later
    amended its complaint to add claims against WAI, the architect, who, in turn, brought a
    third-party complaint against Ghidorzi’s engineering subcontractor. Eventually, all claims
    against the entities named in the action—except Ghidorzi—were dismissed by stipulation.
    Ghidorzi moved for summary judgment on all of Primrose’s claims on May 15, 2020.
    [¶7] After a hearing, the district court granted summary judgment in favor of Ghidorzi. 2
    Relevant to this appeal, the district court concluded the Terracon Report was excluded from
    the Contract documents, Primrose failed to establish evidence demonstrating that
    Ghidorzi’s alleged breach caused Primrose damages, and the duty of good faith and fair
    2
    Primrose does not appeal from the summary judgment awarded on the negligence claim.
    2
    dealing was inapplicable because the duties of the parties were fully incorporated through
    the terms of the Contract.
    STANDARD OF REVIEW
    [¶8]   Our standard of review on summary judgment is well established:
    A grant of summary judgment is appropriate when “the
    movant shows that there is no genuine dispute as to any
    material fact and the movant is entitled to judgment as a matter
    of law.” W.R.C.P. 56(a).
    This Court reviews a district court’s order granting
    summary judgment de novo and may affirm on any basis in the
    record.
    [W]e review a summary judgment in the same light as
    the district court, using the same materials and
    following the same standards. We examine the record
    from the vantage point most favorable to the party
    opposing the motion, and we give that party the benefit
    of all favorable inferences that may fairly be drawn
    from the record. A material fact is one which, if proved,
    would have the effect of establishing or refuting an
    essential element of the cause of action or defense
    asserted by the parties.
    The movant bears the initial burden of establishing a
    prima facie case for summary judgment using admissible
    evidence. If the movant establishes a prima facie case for
    summary judgment, the burden shifts to the opposing party to
    present admissible evidence demonstrating a genuine dispute
    of material fact for trial.
    Peterson v. Meritain Health, Inc., 
    2022 WY 54
    , ¶¶ 14–16, 
    508 P.3d 696
    , 704 (Wyo. 2022)
    (internal citations and quotation marks omitted); see also W.R.C.P. 56(c) (requiring
    evidence supporting and opposing summary judgment to be admissible).
    [¶9] The parties agree that the claims arising from the Contract are reviewed under South
    Dakota law. “Contract interpretation is a question of law reviewed de novo.” Prunty
    Constr., Inc. v. City of Canistota, 
    2004 SD 78
    , ¶ 10, 
    682 N.W.2d 749
    , 753 (citing Fenske
    Media Corp. v. Banta Corp., 
    2004 SD 23
    , ¶ 8, 
    676 N.W.2d 390
    , 393). The intent of the
    parties is ascertained from the contract’s language and, to the extent possible, “we must
    3
    give meaning to all the provisions of a contract.” 
    Id.
     (quoting Fenske, ¶ 8, 
    676 N.W.2d at 393
    ).
    DISCUSSION
    I.      Did the district court err in granting summary judgment on Primrose’s breach of
    contract claim?
    [¶10] Primrose contends the district court erred in granting summary judgment on the
    breach of contract claim because it failed to recognize a material issue of fact as to whether
    Ghidorzi breached the Contract by failing to follow the specifications from the Terracon
    Report 3 incorporated into the Contract documents. Primrose also argues the district court
    misapplied South Dakota law and material issues of fact remain as to causation.
    A.      Terms of Contract
    [¶11] It is undisputed that the Terracon Report recommended specific structural
    requirements and made clear these were necessary if Primrose chose the spread footing
    foundation option in moving forward with the project. It is also undisputed that Ghidorzi
    did not follow these recommendations during construction. Ghidorzi claims the
    specifications in the Terracon Report were directly and unambiguously excluded from the
    Contract requirements by the Project Manual, Division 2, Section 02010, 1.2, which states,
    “[the Terracon] report is not a part of the Contract Documents.” Primrose disagrees,
    arguing the Terracon specifications for the spread footings were incorporated into the
    Contract through a drawing submitted by Ghidorzi’s structural engineer on February 13,
    2009, prior to the execution of the Contract. The drawing had an annotation that read, “All
    footings shall bear on new engineered fill as per soils report by Terracon project
    # A5085035. The soils report must be strictly adhered to.” Ghidorzi concedes that the
    drawing was part of the Contract, but claims the note on a structural drawing did not modify
    Section 1.2 of the Project Manual. Ghidorzi admits under the terms of the Contract it was
    required to review the Contract documents, including the drawings, but asserts that the
    Contract also states that the requirement to review was “not for the purpose of discovering
    errors, omissions, or inconsistencies.”
    3
    The district court referred to the Terracon Report solely in relation to Primrose’s claim for breach of good
    faith and fair dealing. It stated:
    Primrose directs the Court specifically to the Terracon geotechnical report
    and Ghidorzi’s failure to install subsurface drainage discussed in the
    report, and suggests this failure violates the “spirit of the deal.” However,
    the Terracon report was not part of the contract documents and subsurface
    drainage was not designed into the plans. Primrose sued its architect for
    that failure. Ghidorzi followed the contract documents and there [was]
    nothing to show they did so in bad faith . . . .
    4
    [¶12] “[T]he interpretation of a contract is a question of law, which is reviewed de novo.”
    Koopman v. City of Edgemont by Dribble, 
    2020 SD 37
    , ¶ 14, 
    945 N.W.2d 923
    , 926–27,
    reh’g denied (Aug. 4, 2020) (quoting Weitzel v. Sioux Valley Heart Partners, 
    2006 SD 45
    ,
    ¶ 18, 
    714 N.W.2d 884
    , 892). “If in dispute, however, the existence and terms of a contract
    are questions for the fact finder.” 
    Id.
     (quoting Behrens v. Wedmore, 
    2005 SD 79
    , ¶ 20, 
    698 N.W.2d 555
    , 566 (quoting Morrisette v. Harrison Int’l Corp., 
    486 N.W.2d 424
    , 427 (Minn.
    1992))).
    [¶13] Primrose asserts that, at minimum, the conflicting provisions in the Contract create
    an ambiguity which must be decided by the jury. “[A] contract is not rendered ambiguous
    simply because the parties do not agree on its proper construction or their intent upon
    executing the contract.” Gail M. Benson Living Tr. v. Physicians Off. Bldg., Inc., 
    2011 SD 30
    , ¶ 11, 
    800 N.W.2d 340
    , 343 (quoting Pesicka v. Pesicka, 
    2000 SD 137
    , ¶ 10, 
    618 N.W.2d 725
    , 727). “Rather, a contract is ambiguous only when it is capable of more than
    one meaning when viewed objectively by a reasonably intelligent person who has
    examined the context of the entire integrated agreement.” Benson Living Tr., ¶ 11, 
    800 N.W.2d at 343
     (quoting Pesicka, ¶ 10, 
    618 N.W.2d at 727
    ); Edgar v. Mills, 
    2017 SD 7
    ,
    ¶ 26, 
    892 N.W.2d 223
    , 230 (“A contract is ambiguous when application of rules of
    interpretation leave[s] a genuine uncertainty as to which of two or more meanings is
    correct.” (quoting Ziegler Furniture & Funeral Home, Inc. v. Cicmanec, 
    2006 SD 6
    , ¶ 16,
    
    709 N.W.2d 350
    , 355)). An ambiguity is determined by examining “the language of an
    agreement as a whole to determine the terms and conditions.” Edgar, ¶ 26, 
    892 N.W.2d at
    230 (citing Poeppel v. Lester, 
    2013 SD 17
    , ¶ 16, 
    827 N.W.2d 580
    , 584). The Court will
    not rewrite the parties’ contract or add to its language in ascertaining the parties’ intent.
    Detmers v. Costner, 
    2012 SD 35
    , ¶ 21, 
    814 N.W.2d 146
    , 151. “Contracting parties are held
    to the terms of their agreement, and disputes cannot be resolved by adding words the parties
    left out.” Gettysburg Sch. Dist. 53-1 v. Larson, 
    2001 SD 91
    , ¶ 11, 
    631 N.W.2d 196
    , 200–
    01.
    [¶14] The Contract between Primrose and Ghidorzi encompassed numerous documents.
    The following provisions are relevant to our discussion.
    [¶15] The General Conditions of the Contract, Section 00700 states:
    1.01   CONDITIONS OF THE CONTRACT
    Primrose General Conditions of the Contract for
    Construction, is hereby made a part of this Project
    Manual except as it may be modified or amended
    herein.
    Related items contained within this Project Manual
    include administrative and work related items which
    5
    may amend, expand upon, or modify specific Articles
    or paragraphs of the General Conditions for this project.
    ARTICLE 1: GENERAL PROVISIONS
    1.1   BASIC DEFINITIONS
    1.1.1 THE CONTRACT DOCUMENTS
    The Contract Documents consist of the Agreement
    between Primrose and Contractor (hereinafter the
    Agreement), Conditions of the Contract (General,
    Supplementary and other Conditions), Drawings,
    Specifications, Addenda issued prior to execution of the
    Contract, other documents listed in the Agreement and
    Modifications issued after execution of the Contract. A
    Modification is (1) a written amendment to the Contract
    signed by both parties, (2) a Change Order, (3) a
    Construction Change Directive or (4) a written order for
    a minor change in the Work issued by the Architect.
    Unless specifically enumerated in the Agreement, the
    Contract Documents do not include other documents
    such as bidding requirements . . . .
    1.1.2 THE CONTRACT
    The Contract Documents form the Contract for
    Construction. The Contract represents the entire and
    integrated agreement between the parties hereto and
    supersedes prior negotiations, representations or
    agreements, either written or oral. The Contract may be
    amended or modified only by a Modification.
    .    .    .
    1.1.5 THE DRAWINGS
    The Drawings are the graphic and pictorial portions of
    the Contract Documents showing the design, location
    and dimensions of the Work, generally including plans,
    elevations, sections, details, schedules and diagrams.
    1.1.6 THE SPECIFICATIONS
    The Specifications are that portion of the Contract
    Documents consisting of the written requirements for
    materials, equipment, systems, standards and
    6
    workmanship for the Work, and performance of related
    services.
    1.1.7 THE PROJECT MANUAL
    The Project Manual is a volume assembled for the Work
    which may include the bidding requirements, sample
    forms, Conditions of the Contract and Specifications.
    1.2    CORRELATION AND INTENT OF THE
    CONTRACT DOCUMENTS
    1.2.1 The intent of the Contract Documents is to include all
    items necessary for the proper execution and
    completion of the Work by the Contractor. The
    Contract Documents are complimentary, and what is
    required by one shall be as binding as if required by all;
    performance by the Contractor shall be required to the
    extent consistent with the Contract Documents and
    reasonably inferable from them as being necessary to
    produce the indicated results.
    .    .    .
    1.4    INTERPRETATION
    .    .    .
    1.4.2 If there is an inconsistency in the quality or quantity of
    Work indicated in the Contract Documents the better
    quality and quantity shall be provided in accordance
    with the Architect’s interpretation.
    .    .    .
    ARTICLE 3: CONTRACTOR
    .    .    .
    3.1.2 The Contractor shall perform the Work in accordance
    with the Contract Documents.
    .    .    .
    7
    3.2    REVIEW OF CONTRACT DOCUMENTS AND
    FIELD CONDITIONS BY CONTRACTOR
    3.2.1 Since the Contract Documents are compl[i]mentary,
    before starting each portion of the Work, the Contractor
    shall carefully study and compare the various Drawings
    and other Contract Documents relative to that portion of
    the Work, as well as information furnished by Primrose
    . . . , shall take field measurements of any existing
    conditions related to that portion of the Work and shall
    observe any conditions at the site affecting it. These
    obligations are for the purpose of facilitating
    construction by the Contractor and are not for the
    purpose of discovering errors, omissions, or
    inconsistencies in the Contract Documents, however,
    any errors, inconsistencies or omissions discovered by
    the Contractor shall be reported promptly to the
    Architect or Primrose’s designated representatives as a
    request for information in such form as the Architect
    may require.
    3.2.1.1 The Contractor shall carefully study and compare the
    Contract Documents with the existing conditions at the
    job site and shall immediately report to the Architect or
    Primrose’s designated representatives, in writing, any
    error, inconsistency or omission that the Contractor may
    discover, or any materials or systems that the Contractor
    has reason to believe are incorrect, inadequate, obsolete
    or unsuitable for the purpose indicated, or that the
    Contractor has reason to believe would constitute or
    result in a violation of the Contractor’s warranty or
    applicable law. The Contractor shall not proceed until
    written instructions are received from the Architect or
    Primrose’s designated representatives. The Contractor
    shall bear full responsibility for any additional costs,
    delays or damages resulting from failure to immediately
    report[] any such errors, inconsistencies or omissions
    that the Contractor may discover.
    3.2.2 Any design errors or omissions noted by the Contractor
    during this review shall be reported promptly to
    Primrose and the Architect, but it is recognized that the
    Contractor’s review is made in the Contractor’s
    8
    capacity as a contractor and not as a licensed design
    professional unless otherwise specifically provided in
    the Contract Documents.
    .    .    .
    3.5    WARRANTY
    3.5.1 The Contractor warrants to Primrose and Architect that
    materials and equipment furnished under the Contract
    will be of good quality and new unless otherwise
    required or permitted by the Contract Documents, that
    the Work will be free from defects not inherent in the
    quality required or permitted, and that the Work will
    conform to the requirements of the Contract
    Documents.       Work not conforming to these
    requirements, including substitutions not properly
    approved and authorized, may be considered defective.
    .    .    .
    ARTICLE 13: MISCELLANEOUS PROVISIONS
    13.1   GOVERNING LAW
    13.1.1 The Contract shall be governed by the laws of the State
    of South Dakota, without giving effect to conflicts of
    laws principles, unless otherwise mutually agreed.
    [¶16] The Project Manual provides:
    ARTICLE 1: THE CONTRACT DOCUMENTS
    The Contract Documents consist of this Agreement,
    Conditions of the Contract (General, Supplementary
    and other Conditions), Drawings, Specifications, other
    documents listed in this Agreement and Modifications
    issued after execution of this Agreement; these form the
    Contract, and are as fully a part of the Contract as if
    attached to this Agreement or repeated herein. The
    Contract represents the entire and integrated agreement
    between the parties hereto and supersedes prior
    negotiations, representations or agreements, either
    9
    written or oral. An enumeration of the Contract
    Documents, other than Modifications, appears in
    Article 8.
    .       .     .
    ARTICLE 8:         ENUMERATION                OF    CONTRACT
    DOCUMENTS
    8.1     The Contract Documents, except for Modifications
    issued after execution of this Agreement, are
    enumerated as follows:
    8.1.1 The Agreement is this executed Form of Agreement
    between Primrose and Contractor; and
    8.1.2 Project Manual and Project Specifications contained in
    the Project Manual dated February 13, 2009, Architects
    Job No. 92008.19; and
    8.1.3 Drawings dated February 13, 2009 and addendum # 1
    dated May 19, 2009; and
    8.1.4 The Supplementary and other Conditions of the
    Contract, if any.
    (Emphasis added.)
    [¶17] Section 02010 of the         Project       Manual    is   entitled   “SUBSURFACE
    INVESTIGATION” and states:
    1 PART 1 GENERAL
    1.1     SCOPE
    A.    This section includes soil investigation report:
    1.     A soils investigation report has been
    prepared for the site of this Work.
    2.     A copy is bound herein following this
    section.
    .       .     .
    10
    1.2    COORDINATION
    A.     Use of data:
    1.     This report is not a part of the Contract
    Documents.
    2.     The report is available for bidders’
    information, but is not a warranty of subsurface
    conditions.
    3.     Bidders should visit the site and acquaint
    themselves with existing conditions.
    4.     Prior to bidding, bidders may make their
    own subsurface investigations to satisfy
    themselves as to site and subsurface conditions,
    but such investigations may be performed only
    under time schedules and arrangements
    approved in advance by the Architect.
    .    .    .
    1.3    QUALITY ASSURANCE
    A.     A soil engineer will be retained by the Contractor
    to observe performance of work in connection
    with excavating, trenching, filling, backfilling,
    and grading, and to perform compaction tests.
    B.     Readjust work performed that does not meet
    technical or design requirements, but make no
    deviation from the Contract Documents
    without specific and written approval from
    the Architect.
    (Emphasis added.)
    [¶18] The Enumeration of Contract Documents in Article 8.1.3 of the General Conditions
    specifically incorporates the February 13, 2009 drawing as a contract document. The
    drawing itself clearly noted that the specifications of the Terracon Report regarding spread
    footings must be “strictly” followed. The South Dakota court has recognized that, in the
    context of purchase agreements, the contract:
    “may incorporate by reference another document containing
    technical specifications for the product, and this will likely
    create an express warranty by description.” 67A Am. Jur. 2d
    11
    Sales § 739 (1985) (emphasis added). See White’s Elec.,
    Heating, Air & Plumbing v. Lewis Constr. Co., No. 02A01-
    9803-CH-00064, 
    1999 WL 605654
    , at *13 (Tenn. Ct. App.
    1999) (stating that neither physical attachment nor specific
    language is necessary to incorporate a document by reference;
    “[t]he incorporating instrument must clearly evidence an intent
    that the writing be made part of the contract”); U.S. v. Outer
    Harbor Dock & Wharf Co., 
    124 F. Supp. 337
    , 343 (S.D. Cal.
    1954) (holding that a contract may refer to another contract for
    details or conditions and that the contract referred to must be
    considered as a part of the contract in which the reference was
    made).
    James River Equip. Co. v. Beadle Cnty. Equip., Inc., 
    2002 SD 61
    , ¶ 21, 
    646 N.W.2d 265
    ,
    269. The drawing made specific reference to the Terracon Report and by stating that these
    requirements be “strictly” followed clearly evidenced an intent to make the specifications
    part of the Contract. On the other hand, Article 1.2.1 of the Project Manual excludes the
    Terracon Report, which was submitted for bidding purposes, from the Contract documents.
    [¶19] We are not persuaded by Ghidorzi’s claim that Article 3.2.1 of the Project Manual
    relieved Ghidorzi of any obligation to notify Primrose or the architect of its decision to
    ignore the note on the structural drawing. Ghidorzi was obligated to “promptly” report
    “any errors, inconsistencies or omissions discovered by the Contractor” through “a request
    for information in such form as the Architect may require.” See also Article 3.2.2—
    Contractor’s review obligation (risk allocation); 2 Philip Bruner & Patrick O’Conner, Jr.,
    Bruner and O’Connor on Construction Law § 5.67 (2020). In addition, Section 1.3 B of
    the Project Manual requires Ghidorzi to “make no deviation from the Contract Documents
    without specific and written approval from the Architect.” At this stage of the proceedings,
    there is nothing in the record to establish Ghidorzi did not discover the inconsistency or
    the basis for Ghidorzi’s decision to proceed without incorporating the engineer’s drawing
    note.
    [¶20] We conclude that the Contract provisions, read as a whole, are “capable of more
    than one meaning when viewed objectively by a reasonably intelligent person who has
    examined the context of the entire integrated agreement.” Benson Living Tr., ¶ 11, 
    800 N.W.2d at 343
     (quoting Pesicka, ¶ 10, 
    618 N.W.2d at 727
    ). “[W]hen there is an ambiguous
    contract, evidence must be introduced to determine what the intentions of the parties were
    and . . . such evidence creates a question of fact, which must be resolved by the jury.” 
    Id.
    ¶¶ 11–16, 
    800 N.W.2d at
    343–44 (citations omitted). Because we have determined that the
    Contract is ambiguous concerning the treatment of the Terracon Report, it is appropriate
    to reverse and remand the district court’s grant of summary judgment to allow the
    introduction of evidence regarding the intentions of the parties.
    12
    B.      Causation
    [¶21] The district court granted summary judgment to Ghidorzi on Primrose’s breach of
    contract claim based on Primrose’s failure to submit evidence that Ghidorzi’s alleged
    breach caused Primrose’s damages. The district court found that Primrose had not shown
    how their loss was clearly ascertainable because it sued various parties; it presented only
    various possibilities as to the source of water that caused the swelling soils; and Primrose
    took the risk of potential damage when it chose to incorporate a spread footing foundation.
    It further found that deposition testimony establishes Ghidorzi met the standard of care and
    did not demonstrate the damages were caused by Ghidorzi’s actions.
    [¶22] Primrose argues the district court misapplied South Dakota law and the record
    creates an issue of material fact as to causation. Ghidorzi maintains that under South
    Dakota law, Primrose’s failure to identify the source of the water causing the soil to swell
    defeats their claim.
    [¶23] In South Dakota, “[t]he elements of a breach of contract are (1) an enforceable
    promise; (2) a breach of the promise; and (3) resulting damages.” Shaw v. Wasko, No.
    4:22-CV-04054-KES, 
    2022 WL 3369297
    , at *8 (D.S.D. Aug. 16, 2022) (quoting Bowes
    Constr., Inc. v. S. Dakota Dep’t of Transp., 
    2010 SD 99
    , ¶ 21, 
    793 N.W.2d 36
    , 43). To
    recover damages for breach of contract, the loss must be clearly ascertainable in both its
    nature and origin. 
    S.D. Codified Laws § 21-2-1
    . 4 “Essential to proving contract damages
    is evidence that damages were in fact caused by the breach.” McKie v. Huntley, 
    2000 SD 160
    , ¶¶ 18–19, 
    620 N.W.2d 599
    , 603–04.
    [¶24] Proximate cause was defined by the South Dakota Supreme Court in Garrido v.
    Team Auto Sales, Inc.:
    Proximate cause is defined as a cause that produces a
    result in a natural and probable sequence and without which
    the result would not have occurred. This Court has further
    defined proximate cause as an immediate cause and which, in
    natural or probable sequence, produced the injury complained
    4
    South Dakota statutes provide:
    21-2-1. General measure of damages for breach of contract--
    Uncertain damages not recovered.
    For the breach of an obligation arising from contract, the measure
    of damages, except where otherwise expressly provided by this code, is
    the amount which will compensate the party aggrieved for all the detriment
    proximately caused thereby, or which, in the ordinary course of things,
    would be likely to result therefrom. No damages can be recovered for a
    breach of contract which are not clearly ascertainable in both their
    nature and their origin.
    
    S.D. Codified Laws § 21-2-1
     (2022) (second emphasis added).
    13
    of. Furthermore, for proximate cause to exist, the harm
    suffered must be found to be a foreseeable consequence of the
    act complained of. Causation is generally a question of fact for
    the jury except when there can be no difference of opinion in
    the interpretation of the facts. It must be a clear case before a
    trial judge is justified in taking these proximate cause issues
    from the jury. Moreover, [a] mere surmise that a party will not
    prevail at trial is not a sufficient basis to grant summary
    judgment.
    Garrido v. Team Auto Sales, Inc., 
    2018 SD 41
    , ¶ 16, 
    913 N.W.2d 95
    , 100 (internal citations
    and quotation marks omitted).
    [¶25] Ghidorzi suggests that because Garrido was a negligence case, it is not applicable
    to the breach of contract claims in this case. It argues “a higher degree of proof” is required
    to obtain damages under South Dakota contract law. It cites to two cases for this
    proposition—Peska Properties, Inc. v. N. Rental Corp., 
    2022 SD 33
    , ¶ 22, 
    976 N.W.2d 749
    , 756; ISG, Corp. v. PLE, Inc., 
    2018 SD 64
    , ¶ 34, 
    917 N.W.2d 23
    , 34.
    [¶26] In Peska, a commercial landlord (Peska) sued for damages after lessees defaulted
    on their lease agreement. After a bench trial, the circuit court awarded damages using a
    “blended rate” formula to determine damages. Peska appealed, contending that the circuit
    court erred as a matter of law in determining that a “blended rate” was the commercially
    reasonable calculation for damages rather than calculating the damages based upon the
    actual loss sustained by Peska under the lease. Peska, ¶ 21, 976 N.W.2d at 755–56. Peska
    also claimed the circuit court’s proportional award for the cost of a build-out was an error
    of law because it failed to meet the ultimate goal of a damage award—to return Peska to
    the position it would have occupied if the contract had been performed. The South Dakota
    Supreme Court agreed with Peska noting damages for a breach of contract “must be
    reasonably certain and not speculative.” Id. ¶ 22, 976 N.W.2d at 756.
    [¶27] In ISG, ISG brought action against portable lift manufacturer, PLE, for breach of
    contract, fraud, and fraudulent misrepresentation after PLE delivered contractually
    noncompliant tactical observation platforms for use by law enforcement at a festival in
    Puerto Rico. After the jury found in favor of ISG and awarded compensatory and punitive
    damages, PLE moved for a new trial. The circuit court entered judgment on jury verdict
    for ISG as to liability but granted new trial as to damages. ISG appealed and the South
    Dakota Supreme Court reversed, holding the evidence was sufficient to support the jury’s
    award in all respects. ISG, ¶¶ 1, 41, 
    917 N.W.2d at 26
    , 35–36.
    [¶28] In affirming the damages under the fraud claim, the South Dakota Supreme Court
    distinguished the award for contract claims from the award for fraud claims:
    14
    SDCL 21-3-1 provides that “[f]or the breach of any
    obligation not arising from contract, the measure of damages
    . . . is the amount which will compensate for all the detriment
    proximately caused thereby, whether it could have been
    anticipated or not.” Further, “courts have some leeway in
    calculating damages and a lesser degree of certainty is required
    to prove tort damages as compared to contract damages.”
    [Weekley v.] Prostrollo, 
    2010 S.D. 13
    , ¶ 24, 778 N.W.2d [823,]
    830. However, “facts must exist and be shown by the evidence
    which afford a basis for measuring the loss of the plaintiff with
    reasonable certainty.” Id. ¶ 26.
    ISG, ¶ 34, 
    917 N.W.2d at 34
    .
    [¶29] Contrary to Ghidorzi’s argument, neither of these cases discuss causation or a higher
    standard of proof of causation at the summary judgment stage. Rather, they address the
    measure of damages and the evidentiary certainty necessary to prove damages. This is not
    the issue here. Both parties concede that the amount of damages is an issue of fact for trial.
    Ghidorzi does not direct us to a case which requires a higher degree of proof of proximate
    cause in a contract case as compared to a negligence case. We therefore rely on the
    definition set forth by the South Dakota Supreme Court in Garrido.
    [¶30] Ghidorzi asserts that without definitive evidence of the origin of the water that
    resulted in swelling soils, Primrose cannot demonstrate that Ghidorzi’s actions or inaction
    caused Primrose’s damages. Primrose argues that Ghidorzi misinterprets its claim. It is
    undisputed that the long-term exposure to moisture caused the differential movement.
    Primrose maintains it submitted evidence of more than one potential source of the water,
    such as the water leak in the mainline servicing the building in Area A, sprinkler heads
    located too close to the building, inadequate and negative grading around the building, and
    runoff from downspouts, all contrary to the requirements of the Contract documents. It
    claims that had Ghidorzi followed the specifications in the Contract documents as
    incorporated by reference in the engineering drawing, the amount of water in the soil, no
    matter the source, would have been reduced and the damage would have been limited to a
    1 to 1.1 inch of differential movement as opposed to the 3-inch shift found in Area A.
    Primrose cites to the deposition testimony of its expert, Joe Hall, a structural engineer
    employed by KL&A, Inc., as evidence of causation. He prepared a report where he
    concluded:
    Foundation and slab on grade movement is most
    typically caused by a change(s) in moisture in the soils
    supporting the foundation and slabs on grade. Presence of
    expansive clays exacerbates the potential movement. The
    Geotechnical Report allowed spread footing foundation system
    15
    with over-excavation and import of structural fill that was
    ultimately utilized on the project. For over-excavation, the
    Geotechnical Report provided an estimate of differential slab
    movement of 1” provided the measures laid out in the Report
    were followed to minimize the chance of moisture intrusion in
    the sensitive soils beneath the building.        Differential
    movements of upwards of 2” to 3” were observed in areas of
    the building.
    .    .    .
    As recommended in the Geotechnical Report, a
    subsurface drainage system beneath the slab and around the
    perimeter of the foundation is a common way to minimize the
    potential of increased moisture content from an external source
    of water . . . . There was no indication of a subsurface drainage
    system in the construction documents, nor in any of the test pits
    dug around the perimeter of the building.
    It is KLA’s professional opinion that a majority of the
    interior slabs on grade and interior column foundation
    movement, stresses, and cracks observed were caused by the
    swelling of the underlying clay soils that underwent an increase
    in moisture content. Interior footings appear to have less than
    the recommended structural fill specified in the Geotechnical
    Report, especially at the interior garage footings. The lack of
    structural fill causes these footings to be more susceptible to
    movement due to expansive soils. The exterior foundation
    wall movement and lateral rotation along the south side of the
    garage, and to a lesser extent, the exterior west wall of Area C,
    were indicative of differential movement of the footing due to
    eccentric loading of the wall, lateral swell pressures and
    varying moisture levels in the soils adjacent to and beneath the
    foundation wall and footings.
    The leak in the waterline discussed earlier in this report,
    the lack of positive drainage as called for by the Geotechnical
    Report, the lack of proper structural fill depths beneath
    footings, and the failure to locate the sprinkler heads away
    from the building the minimum distance called for by the
    Geotechnical Report have contributed to the increase in
    moisture content that has resulted in the differential movement
    of the building.
    16
    The intersection of exterior load bearing walls and
    interior non-load bearing walls were not constructed in a
    manner to allow differential movement between the slabs on
    grade and the foundations as recommended in the Geotechnical
    Report. The lack of slip joints has resulted in large cracks and
    extensive damage at the joints.
    Also, by casting the interior bearing wall footings
    integrally with the concrete slabs-on-grade, there is no
    isolation of the slab-on-grade from the interior footings.
    Therefore, any differential movement seen by the lightly
    loaded slab-on-grade is also seen by the interior footings, the
    walls supported by these footings, and in turn, the upper-level
    framing. The integral footing system does not follow the
    Geotechnical Report recommendation of isolating the slabs-
    on-grade from foundation elements to allow independent
    movement of the slabs-on-grade.
    There are also several instances that the construction
    observed did not match that shown in the structural plans. For
    example, some hold-downs were missing and others were not
    placed as shown in the structural plans. Interior strip footings
    appeared to be less than the specified width (or placed off-
    center) and depth. The slabs-on-grade appeared void of any
    reinforcement in locations where visible (cracks, borings, and
    test pits). Each of these, though not likely a primary cause of
    damage, contribute to the extent in which the damage has
    occurred.
    [¶31] At his deposition, Mr. Hall testified:
    Q.      The areas where we see this movement to this degree, 2
    to 3 inches, is it fair to say that it’s primarily in the south garage
    or south side area?
    A.      That is correct.
    Q.      Okay. The Terracon report said that there could—you
    could expect movement of up to an inch; correct?
    A.      Correct. If all of the . . . recommendations were
    followed, yes.
    [¶32] Mr. Hall’s report identifies specific deviations from the Contract documents
    (assuming the jury determines the parties’ intention was to include the Terracon
    17
    specifications as noted in the drawing) and that these deviations contributed to Primrose’s
    damages.
    [¶33] Ghidorzi points to the fact that Primrose sued several entities and that the ultimate
    cause of the damages was Primrose’s decision at the outset to use the alternative spread
    footing foundation. The fact that Primrose alleged several entities caused their damages
    does not defeat its breach of contract claims against Ghidorzi. See Krause v. Reyelts, 
    2002 SD 64
    , ¶¶ 19–22, 
    646 N.W.2d 732
    , 735–36 (release of claims against one subcontractor
    did not prevent suit against general contractor for its own deficient work); W. Nat’l Mut.
    Ins. Co. v. Gateway Bldg. Sys., Inc., 
    2016 SD 85
    , ¶ 13, 
    887 N.W.2d 887
    , 891–92 (summary
    judgment is premature when underlying liability of several entities has not been
    determined, and the defendant has disputed whether it was solely responsible for the
    ultimate cause of the damages); 11 Joseph M. Perillo, Corbin on Contracts § 55.9 (2005).
    Ghidorzi also claims it is undisputed that Primrose’s damages “were caused by Plaintiffs’
    own design decisions rather than an increase in moisture content beneath the building that
    caused the soils to swell.” We find no basis in the record for this contention.
    [¶34] On summary judgment, “[a]ll reasonable inferences drawn from the facts must be
    viewed in favor of the non-moving party. The burden is on the moving party to clearly
    show an absence of any genuine issue of material fact and an entitlement to judgment as a
    matter of law.” Benson Living Tr., ¶ 9, 
    800 N.W.2d at
    342–43 (quoting W. Consol. Co-op.
    v. Pew, 
    2011 SD 9
    , ¶ 19, 
    795 N.W.2d 390
    , 396); see also Peterson, ¶¶ 14–16, 508 P.3d at
    704. Viewing the evidence in favor of Primrose, we conclude the district court erred in
    granting summary judgment of the issue of causation.
    II.    Did the district court err in granting summary judgment on Primrose’s breach of
    the implied covenant of good faith and fair dealing?
    [¶35] Primrose contends the district court erred in granting summary judgment on its
    claim that Ghidorzi violated the duty of good faith and fair dealing. Primrose argues that
    Ghidorzi reviewed the Terracon Report during the bidding process and knew that the
    specifications for the spread footings were essential to mitigate the effects of any increase
    in water content. It claims Ghidorzi’s failure to follow those specifications denied it “the
    benefit of its justified expectations” in having the report followed.
    [¶36] South Dakota recognizes that “[e]very contract contains an implied covenant of
    good faith and fair dealing [that] prohibits either contracting party from preventing or
    injuring the other party’s right to receive the agreed benefits of the contract.” Nygaard v.
    Sioux Valley Hosps. & Health Sys., 
    2007 SD 34
    , ¶ 20, 
    731 N.W.2d 184
    , 193–94 (citations
    omitted).
    This duty of good faith permits an aggrieved party to
    bring a breach of contract action when the other party:
    18
    [B]y [its] lack of good faith, limited or completely
    prevented the aggrieved party from receiving the
    expected benefits of the bargain. A breach of contract
    claim is allowed even though the conduct failed to
    violate any of the express terms of the contract agreed
    to by the parties.
    Id. ¶ 21, 
    731 N.W.2d at 194
     (quoting Garrett v. BankWest, Inc., 
    459 N.W.2d 833
    , 841
    (S.D. 1990)). “Ultimately, the duty ‘emphasizes faithfulness to an agreed common purpose
    and consistency with the justified expectations of the other party.’” 
    Id.
     (quoting Garrett,
    459 N.W.2d at 841 (citing Restatement (Second) of Contracts § 205 cmt. a (Am. Law Inst.
    1981))).
    [¶37] Nonetheless, “the duty of good faith and fair dealing ‘is not a limitless duty or
    obligation.’” Id. ¶ 22, 
    731 N.W.2d at 194
     (quoting Garrett, 459 N.W.2d at 841). It “does
    not create an amorphous companion contract with latent provisions to stand at odds with
    or in modification of the express language of the parties’ agreement.” Id. (quoting Farm
    Credit Servs. of Am. v. Dougan, 
    2005 SD 94
    , ¶ 9, 
    704 N.W.2d 24
    , 28). “The implied
    obligation ‘must arise from the language used or it must be indispensable to effectuate the
    intention of the parties.’” 
    Id.
     (quoting Garrett, 459 N.W.2d at 841). “‘[I]f the express
    language of a contract addresses an issue, then there is no need to construe intent or supply
    implied terms’ under the implied covenant.” Id. (quoting Dougan, ¶ 10, 
    704 N.W.2d at 28
    ).
    [¶38] As discussed above, Primrose raised material issues of fact regarding the intentions
    of the parties regarding the Terracon Report as a contract document and whether it had a
    duty to inform Primrose of the decision to forego strict compliance with the specifications
    of the Terracon Report. In addition, Primrose raised a material issue of fact as to whether
    the failure to comply with the specifications caused its injury. If Ghidorzi is found liable,
    the damages are contained in the Contract itself. Consequently, the jury will decide these
    questions as a matter of contract and there is no need to supply implied terms. We affirm
    the grant of summary judgment in favor of Ghidorzi on Primrose’s claim for a breach of
    the duty of good faith and fair dealing.
    CONCLUSION
    [¶39] There are material questions of fact precluding summary judgment on the
    interpretation of the Contract and whether Ghidorzi’s actions contributed to Primrose’s
    damages. The district court did not err in granting summary judgment of the breach of
    good faith and fair dealing claim. We affirm the summary judgment of the good faith and
    fair dealing claim but reverse and remand the remaining contract claim for further
    proceedings.