Gen Mtr Corp v. EPA ( 1999 )


Menu:
  •                         United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 19, 1998    Decided March 23, 1999
    No. 98-1027
    General Motors Corporation,
    Petitioner
    v.
    Environmental Protection Agency and
    Carol M. Browner,
    Administrator, U.S. Environmental Protection Agency,
    Respondents
    On Petition for Review of an Order of the
    Environmental Protection Agency
    Michael F. McBride argued the cause for petitioner.  With
    him on the briefs were LaJuana S. Wilcher, D. Randall
    Benn, Robert J. Kinney, Brenda Durham, and James P.
    Walle.
    Christopher S. Vaden, Attorney, U.S. Department of Jus-
    tice, argued the cause for respondents.  On the brief were
    Lois J. Schiffer, Assistant Attorney General, Karen L. Eg-
    bert, Attorney, and Richard T. Witt, Steven J. Sweeney, and
    Reginald Pallesen, Attorneys, Environmental Protection
    Agency.
    Scott M. DuBoff, Kenneth S. Kaufman, Saone Baron
    Crocker, Julie Becker, Thomas M. Sneeringer, George Vary,
    Charles H. Lockwood, Fred Main, Robin S. Conrad, J.
    Walker Henry, Jan Amundson, Marjorie E. Powell, and
    John W. Pettit were on the brief for amici curiae American
    Automobile Manufacturers Association, et al.
    Joseph M. Polito, Jay E. Brant, Christopher J. Dunsky,
    Kenneth C. Gold, and Daniella D. Landers were on the brief
    for amici curiae Dott Industries, Inc., et al.
    Before:  Williams, Ginsburg, and Rogers, Circuit Judges.
    Opinion for the Court filed by Circuit Judge Ginsburg.
    Ginsburg, Circuit Judge:  The Environmental Protection
    Agency determined that General Motors violated a Clean
    Water Act permit issued by the State of Michigan, for which
    the agency imposed an administrative penalty of $62,500.
    GM petitions for review, arguing primarily that the EPA
    erred in refusing to consider the Company's collateral attack
    upon the validity of the state-issued permit.  We conclude,
    first, that the EPA reasonably interpreted the Clean Water
    Act, 33 U.S.C. s 1311 et seq., to preclude such a collateral
    attack in the course of an enforcement proceeding and,
    second, that substantial evidence supports the EPA's finding
    that GM violated the permit.  Accordingly, we deny the
    Company's petition for review.
    I. Background
    Section 402 of the CWA, 
    id. s 1342,
    establishes the Nation-
    al Pollutant Discharge Elimination System (NPDES), a per-
    mitting program through which the EPA and the several
    States implement various regulatory limits upon the dis-
    charge of pollutants into navigable waters.  Forty-two States,
    including Michigan, administer the NPDES program within
    their borders.  See s 1342(b).  Although those States assume
    responsibility as the primary permitting authority, see
    s 1342(c), the EPA retains the power to enforce state-issued
    permits in federal court.  See, e.g., s 1319.
    In 1984 GM applied to the Michigan Department of Natural
    Resources for an NPDES permit to discharge stormwater
    from a point source, known as "Outfall 002," at a plant in
    Pontiac, Michigan.  The MDNR initially advised GM that it
    would not act upon the application until later that year, when
    GM would be applying to renew its NPDES permit for the
    other point sources at the plant.  Upon receiving the renewal
    application, however, the MDNR decided not to address the
    stormwater permit application for Outfall 002 but rather to
    revisit that matter "when EPA finalizes stormwater discharge
    permit regulations."  In 1987 the Congress put a stop to the
    EPA's ongoing attempt to craft stormwater permit regula-
    tions by prohibiting, except in limited circumstances, "the
    Administrator or the State ... [from requiring] a permit
    under this section for discharges composed entirely of storm-
    water."  33 U.S.C. s 1342(p)(1).*
    In June, 1988 the MDNR issued GM a stormwater NPDES
    permit for Outfall 002 based upon its 1984 application.  The
    permit advised GM that if aggrieved by its terms the Compa-
    ny could petition the MDNR for review but that the agency
    "may reject any petition filed more than 60 days after issu-
    ance as being untimely."  The permit, which specified limits
    upon GM's discharge of copper, lead, and zinc, was to be in
    effect through October 1, 1990.  GM could renew the permit
    by submitting the appropriate forms "no later than 180 days
    prior to the date of expiration."  GM did not challenge the
    terms of the permit.  Meanwhile, in August, 1988, the Pontiac
    plant ceased operating.
    As required by its permit, GM began to submit to the
    MDNR periodic discharge monitoring reports (DMRs) for
    Outfall 002.  Beginning in May, 1989 the DMRs revealed that
    water discharged at Outfall 002 contained levels of metals in
    __________
    * This prohibition was to last until 1992, but was extended by
    statute to 1994 and then by regulation to 2001.  See Pub. L. No.
    102-580, s 364(1) (1992);  60 Fed. Reg. 40,230, 40,230/3 (1995).
    excess of the limits set in the permit.  GM determined that
    those levels were the result not of cross-connections to the
    plant's idled operations but of some combination of metals
    present in the rain and metals leached from the roofs of
    buildings and from copper gutters.
    In 1991 the EPA twice ordered GM to come into compli-
    ance with the terms of its permit.  GM responded by coating
    most of the roofs and gutters, which lowered the concentra-
    tions of metals in the discharges, but did not bring GM into
    full compliance with the terms of its permit.  In 1993 the
    EPA filed an administrative complaint against GM under
    s 1319(g)(1), alleging 92 violations of its NPDES permit and
    seeking the maximum administrative penalty ($125,000) per-
    mitted under s 1319(g)(2)(B).
    After a hearing an Administrative Law Judge held that GM
    had violated the terms of its permit.  First, the ALJ rejected
    GM's claims that when found in stormwater copper, lead, and
    zinc are not "pollutants" within the meaning of the CWA, see
    s 1362(6), (13), and that channeling stormwater to a point
    source does not constitute adding pollutants to navigable
    waters.  Second, the ALJ held that GM's failure to challenge
    its NPDES permit within 60 days of its issuance by the
    MDNR prevented the Company from mounting a collateral
    attack upon the permit in the course of the EPA enforcement
    action;  therefore he did not consider GM's claims that the
    permit was void both for mutual mistake and under the
    prohibition of stormwater permits in 33 U.S.C. s 1342(p).
    Third, based upon his reading of Michigan case law and upon
    GM's conduct after October 1, 1990--the Company continued
    to submit DMRs and thrice wrote to the MDNR requesting
    that it terminate the permit for Outfall 002--the ALJ held
    that the permit had not expired upon that date despite GM's
    failure to apply for an extension at least 180 days prior
    thereto.  Finally, the ALJ rejected GM's skeletal equal pro-
    tection and due process claims on the ground that GM's
    status as an NPDES stormwater permittee both distin-
    guished it from other companies with similar discharges and
    gave it notice of the basis for the enforcement action against
    it.
    The ALJ assessed GM a civil penalty of $62,500, half the
    amount sought by the EPA, because GM's violations were not
    willful and because but for the Company's apparently unique
    status as holder of an NPDES permit for discharges of
    stormwater it likely would have faced no penalty at all.  See
    s 1319(g)(3) ("In determining the amount of any penalty
    assessed under this subsection, the [agency] ... shall take
    into account ... such other matters as justice may require").
    The ALJ also held that if the Environmental Appeals Board
    or this court reversed his ruling that the permit continued in
    effect after October 1, 1990, then the 39 violations that
    occurred before that date would still warrant a penalty of
    $62,500.  The EAB affirmed the judgment of the ALJ.
    II. Analysis
    We review the EPA's finding of violations of a permit
    issued under the Clean Water Act for lack of "substantial
    evidence in the record, taken as a whole," and the assessment
    of an administrative penalty for "abuse of discretion," 33
    U.S.C. s 1319(g)(8), as we would under the Administrative
    Procedure Act, 5 U.S.C. s 706(2)(A), (E).  Cf. Buxton v.
    EPA, 
    961 F. Supp. 6
    , 9 (D.D.C. 1997).  Because in this case
    GM does not argue that the EPA abused its discretion in
    assessing the penalty, we address only the question whether
    substantial evidence supports the agency's finding that the
    Company violated the terms of its permit.
    GM raises a threshold challenge to the EPA's reliance upon
    the Clean Water Act rather than upon state law and, as a
    fallback position, challenges the EPA's interpretation of the
    Clean Water Act.  We dispose of those arguments before
    turning to GM's other objections to the EPA's decision.
    A.Federal versus State Law
    GM's initial argument is that the EAB erred in following
    federal rather than Michigan law, which arguably permits a
    collateral attack upon a state-issued permit when the State
    initiates the enforcement proceeding.  See Michigan v. Sper-
    andeo, 
    112 Mich. App. 337
    , 342, 
    315 N.W.2d 863
    , 865 (1981).
    Apparently, in GM's view the alternative to state law on the
    question of collateral attacks is federal common law, which
    would be inappropriate under the Supreme Court's teaching
    in O'Melveny & Myers v. FDIC, 
    512 U.S. 79
    (1994).  See 
    id. at 87
    (limiting federal common law to situations in which
    "there is a significant conflict between some federal policy or
    interest and the use of state law").
    The pertinent distinction between this case and O'Melveny,
    however, is that here there is a federal statute to apply.
    Accordingly, our task is but to "construe[ ] the language of
    [the] federal statute ... [an] enterprise [that] is, and always
    has been, a matter of federal law."  RTC v. Diamond, 
    45 F.3d 665
    , 671 (2d Cir. 1995);  see also Auction Co. of Am. v.
    FDIC, 
    132 F.3d 746
    , 749 (D.C. Cir. 1997) (statute applies "by
    its own terms ... not by virtue of any lawmaking power of
    federal courts").  Therefore, there is no choice of law issue.
    Nor do the cases GM cites provide any support for the
    proposition that state law governs which defenses a permittee
    may raise in the course of a federal proceeding to enforce the
    terms of a state-issued permit.  See United States v. Puerto
    Rico, 
    721 F.2d 832
    (1st Cir. 1983) (resolving question whether
    CWA ousts federal courts of their original jurisdiction, under
    28 U.S.C. s 1345, of all suits brought by the United States,
    not whether federal enforcement agency must apply state
    law);  District of Columbia v. Schramm, 
    631 F.2d 854
    , 863
    (D.C. Cir. 1980) (holding that CWA does not create "implied
    right of action" for private party to challenge state permitting
    decision, not that state law follows state permit into federal
    forum for enforcement of CWA).
    Accordingly, we reject GM's claim that the Environmental
    Appeals Board erred in looking to federal law in order to
    determine whether GM could raise a collateral attack upon
    the validity of its permit in an administrative penalty proceed-
    ing brought pursuant to s 1319(g).
    B.What Does Federal Law Allow?
    As noted above, under s 1319(g)(8) the standard for re-
    viewing the EPA's finding that a person has violated a permit
    is whether "there is ... substantial evidence in the record,
    taken as a whole, to support the finding of a violation."  In
    this case GM claims there is no substantial evidence that it
    violated its permit because the evidence demonstrates that
    the permit was invalid from the outset, but the EPA refused
    to hear this attack upon the validity of the permit.  The
    question now before us, therefore, is whether the EPA erred
    in interpreting the CWA to limit the grounds upon which GM
    may challenge the validity and applicability of its permit in
    this federal enforcement proceeding.  Cf. Hoffman Homes,
    Inc. v. EPA, 
    999 F.2d 256
    , 260-61 (7th Cir. 1993) (reviewing
    EPA's interpretation of CWA regulations in course of admin-
    istrative penalty proceeding).
    As GM suggests, because the EPA is charged with adminis-
    tering s 1319(g)(1), we review its decision per the familiar
    analysis of Chevron U.S.A. Inc. v. NRDC, 
    467 U.S. 837
    (1984).
    Our first task, using the "traditional tools of statutory con-
    struction" is to determine whether the Congress has spoken
    to "the precise question at issue," 
    id. at 843
    n.9.  If so, then
    we "must give effect to the unambiguously expressed intent
    of Congress."  
    Id. at 842-43.
     If the Congress has not
    expressed itself on that question, then Chevron step two
    requires the court to defer to the agency's interpretation if it
    "is reasonable and consistent with the statutory purpose."
    Ohio v. United States Dep't of Interior, 
    880 F.2d 432
    , 441
    (D.C. Cir. 1989).
    1.Chevron step one
    In its brief, GM raised two arguments against the EPA's
    interpretation.  First, GM claimed that the EPA required it
    to exhaust its state administrative remedies, despite the lack
    of an exhaustion requirement in the CWA and in the teeth of
    the Supreme Court's teaching that such a requirement can be
    imposed only by positive law--that is, by statute or agency
    rule.  See Darby v. Cisneros, 
    509 U.S. 137
    , 154 (1993);  see
    also Time Warner Entertainment Co. v. FCC, 
    144 F.3d 75
    , 79
    n.5 (D.C. Cir. 1998) ("[J]udge made notions of 'common law'
    [exhaustion] always yield to statutes--particularly in adminis-
    trative law").  An exhaustion requirement, however, is not
    the same as a prohibition upon collateral attack.  The former
    refers to administrative or judicial proceedings that must be
    completed as a prelude to federal judicial review;  in the
    reviewing forum, of course, such proceedings do not have res
    judicata effect.  For example, on a petition to review a
    decision of the NLRB, a federal court will not hear an issue
    that was not first raised before the agency;  an issue that was
    raised before the agency, however, is not res judicata but
    open to review.  See, e.g., Exxel/Atmos, Inc. v. NLRB, 
    147 F.3d 972
    , 978 (D.C. Cir. 1998);  see also 28 U.S.C.
    s 2254(b)(1)(A) (federal court shall not grant a state prison-
    er's petition for writ of habeas corpus unless "the applicant
    has exhausted the remedies available in the courts of the
    State").  In contrast, the state administrative and judicial
    proceedings that GM failed to pursue when the MDNR issued
    its permit would not have been but a prelude to further
    review by the EPA.  On the contrary, had GM pursued its
    state remedies and prevailed, then there would have been no
    permit for the EPA to enforce;  had GM done so and lost,
    then it would have been prevented, under the doctrine of res
    judicata, from relitigating the validity of its permit in a later
    enforcement proceeding before the EPA.
    At oral argument, GM in fact acknowledged that the EAB
    had merely been imprecise, using the language of exhaustion
    and of prohibition interchangeably;  the Board did not pur-
    port to require that the Company have exhausted its state
    remedies in order to challenge the validity of its permit in the
    EPA enforcement proceeding.  That is, the EAB did not even
    imply that it could have heard GM's challenge to the validity
    of its permit if only GM had previously sought state adminis-
    trative and judicial review of that permit (and presumably
    been denied relief in those fora).  Because the EAB did not
    interpret the CWA to require exhaustion of state remedies
    prior to raising a collateral attack upon the validity of a
    permit in a federal enforcement proceeding, GM's first argu-
    ment fails.  (For the same reason, the argument made by a
    number of Michigan companies appearing as amici--that even
    if the EAB correctly imposed an exhaustion requirement, GM
    nonetheless should be permitted collaterally to attack its
    permit under the authority of McKart v. United States, 
    395 U.S. 185
    (1969)--is irrelevant.)
    Second, GM (joined by the Michigan amici) argues that the
    CWA allows a collateral attack upon a state-issued NPDES
    permit in an enforcement proceeding because s 1369(b)(2)
    prohibits only collateral attacks against "[a]ction[s] of the
    Administrator with respect to which review could have been
    obtained under [s 1369(b)(1)]," of which one is "issuing or
    denying any [NPDES] permit."  A state-issued NPDES per-
    mit, GM points out, is neither an action of the Administrator
    nor otherwise made reviewable under s 1369(b)(1);  therefore,
    the argument goes, the prohibition of collateral attacks in
    s 1369(b)(2) does not bar its challenge in this federal proceed-
    ing to the validity of its state-issued permit.  Further, be-
    cause references to state-issued and EPA-issued permits are
    so often coupled in the Clean Water Act, see, e.g., 33 U.S.C.
    ss 1311(i) & (k), 1319(c)-(d) & (g), 1342(p), GM would have us
    infer that, by referring in s 1369(b)(2) solely to "[a]ction[s] of
    the Administrator," the Congress intended not to bar a
    collateral attack against a state-issued permit;  expressio uni-
    us est exclusio alterius.
    The inference GM would have us draw, however, simply
    does not follow.  Section 1369(b)(1) authorizes the federal
    courts of appeals to review certain actions of the EPA, not to
    review the permitting decisions of the States.  The failure of
    the Congress in s 1369(b)(2) expressly to forbid collateral
    attacks upon state permits is of no import, therefore.  That
    is, not having authorized any review of state permits in the
    first place, the Congress simply had no reason to single out
    and prohibit collateral review of state permits.
    In sum, neither of GM's arguments persuades us that the
    Congress resolved the question whether a state permittee
    may collaterally challenge the validity of its state-issued
    permit in the course of a federal enforcement proceeding.
    We must therefore proceed to Chevron step two and deter-
    mine whether the EPA reasonably interpreted the CWA to
    preclude such a collateral attack.
    2.Chevron step two
    Presumably, the EPA would not find a permit violation if a
    permit holder could demonstrate that a state court had
    previously decided that the permit was void ab initio;  cer-
    tainly we would not find reasonable an interpretation of the
    CWA that precluded such a challenge to an EPA enforcement
    action.  GM can point to no such decision, however, because it
    declined to take advantage of available state procedures to
    challenge its permit.  Cf. PIRG v. Powell Duffryn Terminals
    Inc., 
    913 F.2d 64
    , 78 & n.27 (3d Cir. 1990) (permittee "not
    denied due process" when denied opportunity collaterally to
    attack permit because "it simply failed to use the process
    available to it").  And the EPA persuasively argues that it
    reasonably interpreted the Act to prevent GM from doing in a
    federal enforcement proceeding what the Company had de-
    clined to do before the MDNR and the Michigan state courts.
    First, the Clean Water Act assigns to the participating
    states the primary role in administering the NPDES permit-
    ting program.  See American Paper Inst., Inc. v. EPA, 
    890 F.2d 869
    , 874 (7th Cir. 1989) (stating it "seems beyond
    argument that we should construe the [Clean Water] Act to
    place maximum responsibility for permitting decisions on the
    states").  As the EPA states, precluding collateral attacks
    ensures that "the States [have] the opportunity as a threshold
    matter to address objections" to the permits they issue.
    Moreover, when a permit has been issued by a state agency,
    it alone will have the information pertinent to an attack upon
    the decisionmaking process that led to the issuance of that
    permit.  Not only would the EPA have to expend considera-
    ble resources to obtain the information from the state agency;
    it would also be second-guessing that agency, which is incon-
    sistent with the primary role of the States under the Act.
    Relatedly, the EPA argues that precluding collateral at-
    tacks is "consistent with Congress' desire to limit the scope of
    enforcement proceedings," as evidenced by a committee re-
    port on the 1972 Clean Water Act amendments:  "Enforce-
    ment of violations of requirements under this Act should be
    based on relatively narrow fact situations requiring a mini-
    mum of discretionary decisionmaking or delay."  S. Rep. No.
    92-414, at 64 (1971).  While we might not consider such a
    report indicative of the intent of the whole Congress, we do
    think it bolsters the agency's claim to have made a reasonable
    interpretation of the Act.  If the EPA cannot preclude a
    collateral attack upon a state-issued permit, then it will find
    enforcement proceedings burdened by all manner of objec-
    tions to the state proceedings leading up to issuance of the
    permit.  Enforcement will become a protracted rather than
    an expedited undertaking.
    Finally, this court, in a dictum in Schramm, noted that
    "congressional silence on federal court review of state permits
    is consistent with the view that challengers to those permits
    should be relegated to state law remedies in state 
    courts." 631 F.2d at 863
    n.15.  Certainly the EPA, acting in accor-
    dance with this dictum, the division of authority in the Act
    between state and federal permitting agencies, and the Sen-
    ate Committee's expectation that enforcement proceedings
    would be straightforward and speedy, could reasonably inter-
    pret the Act to remit to a state forum any attack upon the
    validity of a state permit.  Therefore, applying Chevron step
    two, we conclude that the EPA was not unreasonable in
    interpreting the CWA to preclude GM from attacking the
    validity of its state permit in this federal enforcement pro-
    ceeding.
    C.GM's Other Challenges
    GM raises two arguments that are not foreclosed by the
    conclusion reached immediately above.  Each may be re-
    solved in short order.
    First, GM contends the EPA erred in concluding that the
    permit for Outfall 002 did not expire on October 1, 1990.
    Recall the ALJ held that the appropriate penalty would be
    the same regardless of whether GM was responsible for the
    discharges after that date, and GM did not challenge the
    ALJ's penalty calculations before the EAB or this court.
    Therefore, we need not resolve whether substantial evidence
    supports the EPA's finding that GM violated the terms of its
    permit after October 1, 1990;  even if GM did not do so, its
    penalty would still be $62,500.
    Second, GM claims it was denied due process because it
    lacked notice that "metals present in rainfall or leached from
    roofs and gutters would be considered 'pollutants' that were
    the responsibility of the permit holder."  The permit for
    Outfall 002, however, clearly states that "the permittee is
    authorized to discharge an unspecified amount of stormwater
    runoff .... [which] shall be limited [to 140 F/l of copper, 75
    Fg/of lead, and 1000 Fg/l of zinc]."  GM, in its correspondence
    informing the MDNR of its permit violations, itself counted
    the ambient and leached metals as contributing to those
    violations.  Consequently, GM's lack of notice claim rings
    hollow, to say the least.  See NRDC v. EPA, 
    673 F.2d 400
    ,
    406-07 (D.C. Cir. 1982) ("Each individual subject to the
    [Consolidated Permit Regulations] will of necessity have par-
    ticipated in a permit proceeding before being punished for
    violating the conditions specified in his permit.  A polluter
    charged with violating those conditions will certainly be on
    notice of the duty he is alleged to have breached").
    This exhausts GM's challenges to the EPA's finding that
    the Company violated its NPDES permit for Outfall 002.
    GM does not contest the EPA's conclusion that the informa-
    tion contained in the DMRs it submitted constitutes substan-
    tial evidence that GM violated its permit on at least 39
    occasions prior to October 1, 1990.  Accordingly, we hold that
    substantial evidence supports the EPA's finding of violations.
    III. Conclusion
    For the foregoing reasons, the petition for review is
    Denied.