Village of Bartonville v. Lopez , 2017 IL 120643 ( 2017 )


Menu:
  •                                                                             Digitally signed by
    Reporter of Decisions
    Illinois Official Reports                        Reason: I attest to the
    accuracy and
    integrity of this
    document
    Supreme Court                             Date: 2017.07.17
    10:06:47 -05'00'
    Village of Bartonville v. Lopez, 
    2017 IL 120643
    Caption in Supreme   THE VILLAGE OF BARTONVILLE, Appellant, v. SALVADOR
    Court:               LOPEZ et al., Appellees.
    Docket No.           120643
    Filed                January 20, 2017
    Decision Under       Appeal from the Appellate Court for the Third District, heard in that
    Review               court on appeal from the Circuit Court of Peoria County, the Hon.
    James A. Mack, Judge, presiding.
    Judgment             Appellate court judgment reversed.
    Circuit court judgment affirmed.
    Counsel on           Kenneth M. Snodgrass, Jr., and Kevin D. Day, both of Hasselberg
    Appeal               Grebe Snodgrass Urban & Wentworth, of Peoria, for appellant.
    Charles R. Crowley, of Policemen’s Benevolent Labor Committee,
    Inc., of Springfield, for appellees.
    Justices             JUSTICE THOMAS delivered the judgment of the court, with
    opinion.
    Chief Justice Karmeier and Justices Freeman, Garman, Burke, and
    Theis concurred in the judgment and opinion.
    Justice Kilbride took no part in the decision.
    OPINION
    ¶1       At issue in this case is whether defendants, Salvador Lopez and Policemen’s Benevolent
    Labor Committee, Inc., are precluded from seeking grievance arbitration of Lopez’s
    termination from his employment with plaintiff Village of Bartonville’s police department.
    The trial court granted summary judgment in favor of plaintiff on its complaint for declaratory
    judgment and to stay arbitration. The appellate court, with one justice specially concurring and
    one justice dissenting, reversed the trial court and remanded the case to the trial court with
    directions to order the parties to proceed to arbitration. 
    2016 IL App (3d) 150341
    . This court
    allowed plaintiff’s subsequent petition for leave to appeal. Ill. S. Ct. R. 315 (eff. Mar. 15,
    2016).
    ¶2                                           BACKGROUND
    ¶3       This case has a complicated history, so we will set forth the facts in some detail. Defendant
    Salvador Lopez was a law enforcement officer employed by the plaintiff’s police department
    from February 2012 until October 3, 2014. Defendant Policemen’s Benevolent Labor
    Committee, Inc. (the Union), is the exclusive representative and bargaining agent for all of
    plaintiff’s police officers. At all relevant times, a labor contract was in effect between plaintiff
    and defendants.
    ¶4       Article V of the labor contract addressed the grievance procedure. Section 5.1 of the labor
    contract defined “grievance” as “a dispute or difference of opinion raised by an Officer
    covered by this Agreement or by the Union involving the meaning, interpretation or
    application of provisions of this Agreement.” Section 5.2 sets forth a three-step grievance
    procedure. Section 5.3 provides that the Union may refer the grievance to arbitration if it is not
    settled within the three-step procedure. Section 5.6 states that the grievance procedure set forth
    in section 5 “shall be the sole and exclusive procedure for resolving any grievance or dispute
    which was or could have been raised by an Officer covered by this Agreement or the Union.”
    ¶5       Article VI of the labor contract addressed discipline. Section 6.1 of article VI provided that
    “[d]iscipline shall be progressive and corrective and shall be designed to improve behavior and
    not merely punish it. No employee covered by this Agreement shall be suspended, relieved
    from duty or disciplined in any manner without just cause.” Section 6.2 of article VI stated that
    “[d]isciplinary actions with just cause shall be limited to verbal reprimand, written reprimand,
    suspension and, in extreme cases, termination.”
    ¶6       In August 2014, plaintiff’s police chief, Brian Fengel, signed a complaint for termination
    against Lopez. That complaint was filed with plaintiff’s board of fire and police
    commissioners (the Board). The complaint alleged that Lopez violated certain police
    department procedures and field training directives during and immediately after a July 7,
    2014, traffic stop.
    ¶7       With regard to termination, section 10-2.1-17 of the Illinois Municipal Code (Municipal
    Code) provides:
    “Except as hereinafter provided, no officer or member of the fire or police department
    of any municipality subject to this Division 2.1 shall be removed or discharged except
    for cause, upon written charges, and after an opportunity to be heard in his own
    defense. The hearing shall be as hereinafter provided, unless the employer and the labor
    -2-
    organization representing the person have negotiated an alternative or supplemental
    form of due process based upon impartial arbitration as a term of a collective
    bargaining agreement. Such bargaining shall be mandatory unless the parties mutually
    agree otherwise. Any such alternative agreement shall be permissive.
    *** The board of fire and police commissioners shall conduct a fair and impartial
    hearing of the charges, to be commenced within 30 days of the filing thereof, which
    hearing may be continued from time to time. *** In the conduct of this hearing, each
    member of the board shall have power to administer oaths and affirmations, and the
    board shall have power to secure by its subpoena both the attendance and testimony of
    witnesses and the production of books and papers relevant to the hearing.” 65 ILCS
    5/10-2.1-17 (West 2014).
    ¶8          Counsel for defendant Union represented defendant Lopez throughout the proceedings. On
    August 28, 2014, counsel for the Board spoke with defendants’ counsel by telephone and
    proposed that a hearing on the termination complaint take place between September 2 and 5,
    2014. Defendants’ counsel responded that those dates would not work, as he would not have
    enough time to prepare. On September 2, 2014, the Board’s counsel sent an e-mail to
    defendants’ counsel stating that the next available hearing date was September 25, 2014.
    Defendants’ counsel responded that same day, suggesting that the hearing be set for October 3
    or 10, 2014. On September 3, 2014, counsel for the Board confirmed that the hearing would be
    set for October 3, 2014.
    ¶9          On September 29, 2014, prior to the agreed upon October 3 hearing, Lopez filed a
    complaint for declaratory judgment in Peoria County circuit court arguing that the Board was
    divested of jurisdiction over the termination complaint because the Board had failed to
    commence a termination hearing within the mandatory 30-day time limit for a hearing under
    section 10-2.1-17 of the Municipal Code. The Board responded that it did not lose jurisdiction
    because it was at Lopez’s request that the hearing was set more than 30 days after the filing of
    the charges against Lopez.
    ¶ 10        Both parties filed motions for summary judgment in Lopez’s declaratory judgment action
    in January 2015. The trial court granted summary judgment in favor of the Board and denied
    Lopez’s motion for summary judgment. The trial court also denied Lopez’s postjudgment
    motion to vacate the judgment, finding that the delay in the commencement of the hearing was
    attributable to Lopez. The appellate court, with one justice dissenting, affirmed the trial court.
    
    2016 IL App (3d) 150520
    . Lopez has not petitioned this court for leave to appeal that decision.
    ¶ 11        Although Lopez had filed a complaint for declaratory judgment contesting the Board’s
    jurisdiction to conduct the termination hearing, the hearing nonetheless proceeded on October
    3, 2014. At the outset of the hearing, defendants’ attorney noted he had filed a complaint with
    the circuit court contesting the Board’s jurisdiction to conduct the hearing because more than
    30 days had passed since the charge against Lopez had been issued. Defense counsel stated that
    if the Board determined that it had jurisdiction despite the passing of the 30-day time limit,
    defendants would participate without waiving the issue of jurisdiction. Counsel also stated that
    the Union’s presence did not waive its contractual right to grieve a suspension or termination,
    if ordered by the Board.
    ¶ 12        At the hearing, five witnesses testified, as well as Lopez. Defense counsel participated in
    the hearing. Defense counsel cross-examined the witnesses and made a closing argument.
    -3-
    Defendants’ counsel again reiterated in his closing argument that the presence of the Union
    and of Lopez did not waive defendants’ argument that the Board lost jurisdiction by failing to
    commence a hearing within 30 days and did not waive defendants’ right to grievance
    arbitration under the contract if discipline was issued.
    ¶ 13        At the conclusion of the hearing, the Board issued an order of discharge. The Board found
    that it had jurisdiction of the subject matter of the charges and of Lopez. The Board then found
    that cause existed for Lopez’s termination from his position as a police officer and as a member
    of the plaintiff’s police department. The Board therefore ordered that Lopez be discharged and
    removed from his position as a police officer and as a member of plaintiff’s police department
    as of October 3, 2014.
    ¶ 14        Section 10-2.1-17 of the Municipal Code provides for review of Board decisions. The
    statute provides that:
    “The provisions of the Administrative Review Law [735 ILCS 5/3-101 et seq.
    (West 2014)] and all amendments and modifications thereof, and the rules adopted
    pursuant thereto, shall apply to and govern all proceedings for the judicial review of
    final administrative decisions of the board of fire and police commissioners hereunder.
    The term ‘administrative decision’ is defined as in Section 3-101 of the Code of Civil
    Procedure.” 65 ILCS 5/10-2.1-17 (West 2014).
    Defendants never sought judicial review of the Board’s final decision pursuant to the
    Administrative Review Law.
    ¶ 15        However, on October 10, 2014, defendants filed a grievance with plaintiff’s police
    department. The grievance asserted that Lopez was terminated without just cause in violation
    of article VI, section 6.1, of the parties’ labor contract. The grievance stated that, pursuant to
    article VI, section 6.2, of the labor contract, plaintiff was required to reserve termination solely
    for “extreme cases” and Lopez’s case was not an extreme case. The termination also violated
    the labor contract because the termination was not progressive or corrective as required by
    article VI, section 6.1. Finally, the grievance alleged that in conducting a hearing before the
    Board, plaintiff violated article V, section 5.6, which states that the contractual grievance
    procedure “shall be the sole and exclusive procedure for resolving any grievance or dispute
    which was or could have been raised by an Officer covered by this Agreement or the Union.”
    When the grievance was not resolved by the three-step grievance process identified in the
    parties’ labor contract, defendants referred the grievance to grievance arbitration on October
    28, 2014.
    ¶ 16        Plaintiff then filed a complaint for declaratory judgment and for stay of arbitration on
    November 21, 2014, alleging that Lopez’s termination and subsequent grievance were not
    arbitrable matters. Plaintiff noted that defendants’ September 29, 2014, complaint for
    declaratory judgment sought an injunction solely on the grounds that the 30-day time period
    for conducting the termination period had run, in violation of section 10-2.1-17 of the
    Municipal Code. Plaintiff argued that in relying on section 10-2.1-17, which granted the Board
    the authority to hear disciplinary proceedings, defendants essentially admitted that the Board
    initially had jurisdiction to conduct the termination procedure but lost that jurisdiction when it
    did not conduct the hearing within 30 days. Because the Board had jurisdiction and issued a
    final decision on the merits, any review of the Board’s decision was subject to the
    Administrative Review Law, which was the exclusive means to review the Board’s decision to
    -4-
    terminate Lopez. Plaintiff contended that by attempting to grieve and arbitrate Lopez’s
    termination, defendants were improperly seeking review of the Board’s final decision in
    violation of the Municipal Code and the Administrative Review Law.
    ¶ 17       Plaintiff also argued that the grievance and arbitration provisions in the labor contract did
    not apply to termination or discharge proceedings because the parties did not negotiate an
    alternative form of due process based upon impartial arbitration in their labor contract.
    Plaintiff sought an order declaring that Lopez’s grievance was not arbitrable and staying any
    arbitration proceedings requested by defendants.
    ¶ 18       Plaintiff filed a motion for summary judgment on January 14, 2015, noting that defendants
    had failed to file a timely answer or appearance in response to its complaint for declaratory
    judgment. Plaintiff also sought summary judgment on the basis that defendants had failed to
    review the Board’s decision under Administrative Review Law and on the basis of
    res judicata.
    ¶ 19       On February 25, 2015, defendants were given leave to file their answer and affirmative
    defenses to plaintiff’s complaint for declaratory judgment, as well as a counterclaim setting
    forth a motion to compel arbitration of their grievance. On March 11, 2015, plaintiff filed a
    second motion for summary judgment and a motion to dismiss defendants’ counterclaim.
    ¶ 20       The motions proceeded to a hearing on April 1, 2015. The parties agreed to focus their
    argument on plaintiff’s January 14, 2015, motion for summary judgment, as a ruling in favor of
    plaintiff on that motion would render the remaining motions moot. Plaintiff argued that it was
    entitled to a declaratory judgment and a permanent stay of arbitration based on the fact that a
    full hearing had been held before the Board. Because defendants did not seek administrative
    review of the Board’s decision terminating Lopez, that decision became final, and the doctrine
    of res judicata barred defendants from proceeding with further arbitration of the matter.
    ¶ 21       Defendants responded that under the parties’ labor contract, as well as Illinois statute, the
    issuance of discipline by plaintiff is subject to the arbitration procedure set forth in the labor
    contract. Defendants relied on the Illinois Public Labor Relations Act (5 ILCS 315/1 et seq.
    (West 2014)), as well as the Uniform Arbitration Act (710 ILCS 5/1 et seq. (West 2014)), in
    support of their argument.
    ¶ 22       Defendants asserted that there was no adverse disciplinary action until the Board issued its
    decision terminating Lopez. Once the Board terminated Lopez, it was up to the arbitrator to
    decide whether the termination violated the labor contract. Defense counsel stated that the
    arbitrator would not be limited to reviewing the findings of the Board, as would happen in an
    administrative review, but rather could look at the termination itself and determine whether the
    labor contract applied. Defense counsel agreed with the trial court that in such a case, the
    decision of the Board essentially would have been for naught, other than to get the case to the
    arbitrator so the parties could start all over again.
    ¶ 23       Following hearing, the trial court took the matter under advisement. The trial court then
    issued a written order granting plaintiff’s motion for summary judgment, finding that there
    were no material issues of fact and that plaintiff was entitled to judgment as a matter of law.
    The trial court’s order did not address plaintiff’s res judicata argument. The order found,
    “There is no provision in the contract between the Village of Bartonville and the Policemen’s
    Benevolent Labor Committee, Inc [sic] stating, or even inferring, that the grievance procedure
    -5-
    should, or could, be used to determine disciplinary matters. As such, Plaintiff is entitled to
    judgment as a matter of law.”
    ¶ 24        Defendants appealed the trial court’s order. The appellate court, with one justice specially
    concurring and one justice dissenting, reversed and remanded. 
    2016 IL App (3d) 150341
    .
    ¶ 25        On appeal, defendants argued that the trial court applied the wrong legal standard in
    determining that arbitration was not required in this case. Defendants stated that the trial court
    incorrectly believed that arbitration of the disciplinary grievance was not required unless the
    parties specifically agreed in the labor contract to arbitrate disciplinary matters. Defendants
    asserted that the correct standard was the opposite: that arbitration was required unless the
    parties mutually agreed in the labor contract not to arbitrate disciplinary matters. Defendants
    acknowledged that the labor contract at issue was silent concerning whether disciplinary
    matters were subject to grievance arbitration but contended that the silence favored their
    position.
    ¶ 26        Plaintiff responded that grievance arbitration was barred by (1) the Municipal Code and the
    Administrative Review Law, which provided that the filing of a complaint for administrative
    review was the only way defendants could challenge the Board’s decision, (2) the doctrine of
    res judicata, which barred defendants from relitigating Lopez’s termination, and (3) the
    principle of judicial economy because it was improper for defendants to attempt to use a
    second procedure—grievance arbitration—to try to obtain a more favorable result than what
    they received in the first procedure. Plaintiff also argued that established law required only that
    the labor contract evidence the parties’ intent to exclude the matter from arbitration and did not
    require a specific provision to that effect.
    ¶ 27        In reversing the trial court, the appellate court majority found that the intent of the parties
    on disciplinary matters was unclear and that the parties must proceed to arbitration so that an
    arbitrator could decide whether the disciplinary matter at issue was subject to grievance
    arbitration under the parties’ contract. 
    2016 IL App (3d) 150341
    , ¶ 21. With regard to
    plaintiff’s claim that defendants could only challenge the Board’s decision through the
    Municipal Code and the Administrative Review Law, the appellate court majority stated that
    whether application of those statutes would bar grievance arbitration would turn on whether
    the parties’ intent in their labor contract was for the disciplinary matter to be subject to
    grievance arbitration. 
    Id. ¶ 22.
    ¶ 28        The appellate court majority also found that res judicata did not apply. The court
    distinguished the case before it from Monmouth Public Schools, District No. 38 v. Pullen, 
    141 Ill. App. 3d 60
    (1985), relied upon by the plaintiff. The court stated, “[t]he instant case does not
    involve a situation such as in the Monmouth case, which is relied upon by the Village, where
    the same party was seeking to submit the same issue to arbitration a second time after that issue
    had already been resolved by the arbitrator’s decision in the first arbitration.” 
    2016 IL App (3d) 150341
    , ¶ 23.
    ¶ 29        Finally, the court concluded that judicial economy would not prevent the Board’s
    termination decision from being subject to grievance arbitration if that was the agreement of
    the parties. 
    Id. ¶ 24.
    ¶ 30        The concurring justice did not believe there was any ambiguity in the labor contract or that
    this type of grievance resolution was specifically excluded from the arbitration provision. 
    Id. -6- ¶
    29 (O’Brien, P.J., specially concurring). For that reason, the concurring justice would reverse
    and send the matter to arbitration without any further proceedings. 
    Id. ¶ 31
          In contrast, the dissent would affirm the trial court on the basis of waiver and res judicata.
    The dissent stated, with regard to waiver:
    “I would argue that by failing to grieve the complaint for termination when notice of its
    filing with the board was received, by raising timing as their only objection in this
    tribunal to the Board’s hearing, by participating in that hearing[,] and by failing to
    argue there was a requirement to arbitrate and the [sic] forestalling a decision by the
    Board, the defendants implicitly acknowledged the right of the Board to make the
    decision and implicitly waived the right, if any, to arbitrate. They thereby mooted the
    arbitration issue.” 
    Id. ¶ 33
    (McDade, J., dissenting).
    ¶ 32       The dissent also believed that the elements of res judicata had been met in this case. The
    hearing before the Board involved the same village and the same defendants that would be
    parties to an arbitration proceeding pursuant to the labor contract. 
    Id. ¶ 36.
    The hearing was
    conducted by a court of competent jurisdiction, and the hearing resulted in a final judgment on
    the merits. 
    Id. Therefore, to
    allow for arbitration of the matter would be in direct contradiction
    to the purpose of the doctrine of res judicata—judicial economy. 
    Id. ¶ 33
                                               ANALYSIS
    ¶ 34       This case comes to us on appeal of the trial court’s order granting summary judgment in
    favor of plaintiff. Summary judgment is properly granted when the pleadings, depositions,
    admissions, and affidavits on file, viewed in the light most favorable to the nonmoving party,
    show that there is no genuine issue of material fact and that the moving party is entitled to
    judgment as a matter of law. Home Insurance Co. v. Cincinnati Insurance Co., 
    213 Ill. 2d 307
    ,
    315 (2004). Rulings on motions for summary judgment are reviewed de novo. 
    Id. This court
           may affirm a grant of summary judgment on any basis appearing in the record, regardless of
    whether the lower courts relied upon that ground. 
    Id. ¶ 35
          Turning to the substance of the instant appeal, we note that the focus of the parties’
    arguments differs significantly. As in the lower courts, the focus of plaintiff’s argument on
    appeal is that res judicata bars defendants from proceeding with arbitration of their grievance.
    ¶ 36       Defendants respond that the relevant inquiry in this case is whether the parties excluded
    disciplinary matters from arbitration. Defendants focus the majority of their brief addressing
    their right to grievance arbitration. Defendants note that the labor contract contains a grievance
    procedure in article V and provides for employee discipline in article VI, although the contract
    is silent with regard to the arbitrability of discipline. Defendants assert that case law and
    statutory law dictate that a labor contract’s silence with regard to the arbitrability of discipline
    means that discipline matters are subject to grievance arbitration, because parties must show an
    intent to exclude the matter from arbitration. Defendants contend the singular issue in this case,
    then, is whether there was an agreement to arbitrate employee discipline, which is an issue for
    the arbitrator to decide. Defendants argue that the Municipal Code and the Administrative
    Review Law cannot divest defendants of their statutory right to grievance arbitration.
    ¶ 37       At the outset, we note that we agree with defendants that their labor contract is silent
    concerning the arbitrability of discipline and that this court has held that “when the language of
    an arbitration clause is broad and it is unclear whether the subject matter of the dispute falls
    -7-
    within the scope of arbitration agreement, the question of substantive arbitrability should
    initially be decided by the arbitrator.” Donaldson, Lufkin & Jenrette Futures, Inc. v. Barr, 
    124 Ill. 2d 435
    , 447-48 (1988). It also is correct that the Illinois Uniform Arbitration Act embodies
    a legislative policy favoring enforcement of agreements to arbitrate future disputes. 
    Id. at 443.
           Moreover, defendants are correct that rather than divest defendants of their statutory right to
    grieve arbitration, the Municipal Code provides for a hearing “unless the employer and the
    labor organization representing the person have negotiated an alternative or supplemental form
    of due process based upon impartial arbitration as a term of a collective bargaining
    agreement,” in which case such bargaining is mandatory unless the parties mutually agree
    otherwise. 65 ILCS 5/10-2.1-17 (West 2014).
    ¶ 38        As our appellate court has recognized, however, a contractual right to arbitrate can be
    waived like any other contractual right. Schroeder Murchie Laya Associates, Ltd. v. 1000 West
    Lofts, LLC, 
    319 Ill. App. 3d 1089
    , 1095-96 (2001). While a waiver of arbitration rights is
    disfavored, a waiver may occur when a party acts in a manner that is inconsistent with the
    arbitration clause in an agreement, thus indicating an abandonment of the right to arbitration.
    Yates v. Doctor’s Associates, Inc., 
    193 Ill. App. 3d 431
    , 440 (1990).
    ¶ 39        The dissent in this case believed that defendants implicitly waived the right, if any, to
    arbitrate. 
    2016 IL App (3d) 150341
    , ¶ 33 (McDade, J., dissenting). Therefore, the dissent
    below would find that defendants’ waiver of their right to arbitration mooted the issue of
    arbitration on appeal. 
    Id. We agree.
    ¶ 40        The chief of police in this case filed his complaint with the Board to terminate Lopez on or
    around August 18, 2014. Counsel for the Board had two conversations with counsel for
    defendants on August 28 and September 2, 2014, concerning the scheduling of a date for the
    hearing before the Board. There was no testimony that, in either conversation, counsel for
    defendants claimed that the proper avenue for discipline was pursuant to the parties’ labor
    contract, nor did counsel assert Lopez’s right to proceed pursuant to the labor contract. Further,
    although counsel for defendants filed a complaint for declaratory judgment and injunctive
    relief prior to the Board hearing on October 3, 2014, that complaint alleged only that the Board
    was without jurisdiction to conduct the hearing because the termination complaint had not
    been heard within 30 days of when it was filed. The complaint for declaratory judgment and
    other relief did not seek to stay the hearing before the Board on the basis that disciplinary
    matters could only be pursued as set forth in the parties’ labor contract.
    ¶ 41        Defendants then participated in the hearing before the Board. Lopez testified, and defense
    counsel cross-examined witnesses and gave a closing argument. Although defense counsel
    stated during the hearing that the presence and participation of the Union and the Board did not
    waive their right to file a grievance, defense counsel never questioned the Board’s jurisdiction
    to conduct the hearing based upon defendants’ right to grievance arbitration under the parties’
    labor contract, nor did defense counsel ask the Board or the circuit court to stay the
    proceedings pending defendants’ filing of a grievance.
    ¶ 42        In the trial court hearing on plaintiff’s motion for summary judgment, defendants stated
    that there was no adverse disciplinary action until the Board issued its decision terminating
    Lopez, implicitly suggesting that defendants could not have filed their grievance until the
    Board hearing was concluded. That claim is belied by the grievance itself. The grievance
    alleged that in conducting a hearing before the Board, plaintiff violated article V, section 5.6,
    -8-
    of the labor contract, which provides that the grievance procedure “shall be the sole and
    exclusive procedure for resolving any grievance or dispute which was or could have been
    raised by an Officer covered by this Agreement or the Union.”
    ¶ 43        Moreover, defendants were aware from the outset that plaintiff was seeking to terminate
    Lopez’s employment and that employee termination was addressed in the discipline section of
    the labor contract. The proceedings in this case were initiated when the police chief signed and
    filed a complaint for termination against Lopez. Counsel for defendant Union represented
    Lopez at the termination hearing. Had defendants believed that the labor contract divested the
    Board of its authority to terminate Lopez’s employment, defendants could have sought an
    injunction to stay the Board from continuing the hearing. Defendants did not do so, choosing
    instead to participate in the hearing before the Board. Defendants cannot now complain of that
    choice.
    ¶ 44        Defendants then suggest that the portion of the Municipal Code providing for an
    “alternative or supplemental form of due process” means that they could elect to have the
    Board proceedings and arbitration proceedings operate in conjunction with one another or
    could elect to forgo a hearing before the Board and proceed directly to arbitration. The dissent
    below found this suggestion illogical because an arbitrator would be able to override any
    administrative review decision, even administrative review from this court, on the basis that
    arbitration was a supplemental form of due process. 
    2016 IL App (3d) 150341
    , ¶ 39 (McDade,
    J., dissenting).
    ¶ 45        The court in Village of Creve Coeur v. Fletcher, 
    187 Ill. App. 3d 116
    (1989), hypothesized
    such a scenario in holding that the defendant police officer could not pursue both
    administrative review and arbitration of the same decision. The court explained:
    “In this case, for instance, supposing that the parties proceeded pursuant to the fire and
    police commission act by going through the Board of Police and Fire Commissioners,
    the circuit court, the appellate court to the supreme court of Illinois, one of the parties,
    dissatisfied by the result of the supreme court, could then, according to the circuit
    court’s interpretation, proceed through the regular grievance procedure where a police
    officer’s immediate sergeant could review and decide contrary to the decision of the
    supreme court.” 
    Id. at 118.
    ¶ 46        The concerns of the court in Village of Creve Coeur are well taken. The dissent below
    correctly concluded that “[t]he Municipal Code’s allowance of arbitration as an alternative or
    supplemental form of due process means either/or and not a combination of jurisdictional
    proceedings and mixed tribunals providing an opportunity for a higher level court to be
    overruled by a lower level proceeding.” 
    2016 IL App (3d) 150341
    , ¶ 40 (McDade, J.,
    dissenting).
    ¶ 47        We therefore reject defendants’ claim that they could elect to have proceedings before the
    Board and arbitration proceedings operate in conjunction with one another. Defendants chose
    to participate in the hearing before the Board rather than seek to stay the hearing and proceed in
    accordance with their labor contract. In so doing, defendants acted inconsistently with their
    right to arbitrate. The crucial inquiry in determining whether a party has waived its contractual
    right to arbitrate is whether the party has acted inconsistently with its right to arbitrate.
    Schroeder Murchie 
    Laya, 319 Ill. App. 3d at 1098
    . Defendants’ actions in participating in the
    -9-
    Board hearing prior to filing their grievance waived any potential right to statutory arbitration
    of that grievance.
    ¶ 48       Moreover, as argued by plaintiff and discussed by the dissent below, res judicata provides
    an alternative bar that prevents defendants from further litigating Lopez’s termination through
    arbitration. In addition to waiver, the right to pursue an arbitration action may be limited by the
    effect of the res judicata doctrine. Peregrine Financial Group, Inc. v. Ambuehl, 
    309 Ill. App. 3d
    101, 107 (1999). Thus, if the arbitration action involves issues previously reached,
    arbitration is barred notwithstanding the parties’ contractual rights to bring such actions. 
    Id. ¶ 49
          This court has long recognized that few rules are more essential or more firmly embedded
    in our jurisprudence than that of res judicata. Hughey v. Industrial Comm’n, 
    76 Ill. 2d 577
    , 582
    (1979). Res judicata is a judicially created doctrine resulting from the practical necessity that
    there be an end to litigation and that controversies once decided on their merits shall remain in
    repose. 
    Id. Thus, under
    the doctrine of res judicata, a final judgment on the merits rendered by
    a court of competent jurisdiction acts as a bar to a subsequent suit between the parties
    involving the same cause of action. River Park, Inc. v. City of Highland Park, 
    184 Ill. 2d 290
    ,
    302 (1998). The bar extends to what was actually decided in the first action, as well as those
    matters that could have been decided in that action. 
    Id. Res judicata
    embraces all grounds of
    recovery and defense involved and which might have been raised in the first action. 
    Hughey, 76 Ill. 2d at 583
    .
    ¶ 50       Three requirements must be satisfied in order for the doctrine of res judicata to apply.
    There must be (1) a final judgment on the merits rendered by a court of competent jurisdiction,
    (2) an identity of cause of action, and (3) an identity of parties or their privies. River Park, 
    Inc., 184 Ill. 2d at 302
    . This court applies a transactional test to determine whether there is an
    identity of cause of action. Under the transactional test, the assertion of different theories or
    kinds of relief still constitutes a single cause of action if a single group of operative facts gives
    rise to the assertion of relief. 
    Id. at 311.
    ¶ 51       With these principles in mind, we examine the case before us. Plaintiff argues that
    res judicata applies because the Board, with competent jurisdiction, has issued a final
    judgment on the merits of Lopez’s termination. There is identity of the parties for purposes of
    res judicata because the parties to this matter have remained the same since the inception of
    the termination process. In addition, there is identity of the cause of action for purposes of
    res judicata under the transaction test. Because the Board issued a final judgment on the merits
    of Lopez’s termination and because defendants have failed to seek administrative review of the
    Board’s decision, any attempt by defendants to relitigate the same cause of action is barred by
    the doctrine of res judicata.
    ¶ 52       Defendants respond that plaintiff cannot establish two of the three prongs of the test for
    determining whether res judicata applies. Defendants assert that plaintiff cannot establish that
    there was a final judgment rendered by a court of competent jurisdiction. Defendants also
    contend that plaintiff cannot establish an identity of cause of action.
    ¶ 53       The appellate court in this case summarily rejected plaintiff’s res judicata argument. As
    noted, the appellate court majority found that this case did not involve a situation such as that
    in Monmouth Public Schools because the court in that case held that an arbitration was barred
    by the res judicata effect of the prior arbitration award involving the same parties and the same
    issue. 
    Monmouth, 141 Ill. App. 3d at 60
    . Without analysis, the appellate court in this case
    - 10 -
    found the situation presented in Monmouth was not present in this case, presumably because
    this case involved a prior Board hearing and not a prior arbitration. 
    2016 IL App (3d) 150341
    ,
    ¶ 23.
    ¶ 54        As pointed out by the dissent below, however, the majority never acknowledged other
    analogous appellate decisions, which found prior board hearings had a res judicata effect on
    grievance arbitration. For example, in Board of Governors of State Colleges & Universities v.
    Illinois Educational Labor Relations Board, 
    170 Ill. App. 3d 463
    (4th Dist. 1988),
    Northeastern University filed charges seeking the discharge of Shellie Brown. Brown filed a
    step III grievance, which the university returned to Brown, informing her that her only option
    was to appeal her discharge through the merit board. Brown sent a letter to the merit board
    requesting a hearing to contest her discharge. A hearing was held, in the middle of which
    counsel for Brown moved to terminate the hearing on the theory that the hearing was
    premature and without jurisdiction because the collective bargaining grievance procedure
    should take precedence. Counsel’s motion was denied, and the hearing officer found the
    university had shown cause for discharge. Brown’s collective bargaining representative then
    filed an unfair labor practice charge against the plaintiff for its refusal to process Brown’s
    grievance. A hearing officer at the hearing on Brown’s unfair labor practice charge
    recommended that the Illinois Educational Labor Relations Board order the plaintiff to process
    Brown’s grievance pursuant to the collective bargaining agreement. The board adopted the
    hearing officer’s recommended order.
    ¶ 55        The plaintiff appealed. One of the issues plaintiff raised on appeal was that res judicata
    should apply to preclude an arbitrator from determining the issue of good cause for discharge
    because allowing the grievance to go to arbitration would allow a collateral attack on the merit
    board’s decision. 
    Id. at 481.
    The appellate court agreed, finding that under the current Illinois
    law and the bargaining agreement, Brown had the option of pursuing the statutory merit board
    proceedings or the collective bargaining agreement. 
    Id. at 483.
    The court found that Brown
    could not now complain given her request to the merit board for a hearing and her failure to
    request a stay of the merit board proceedings. 
    Id. The court
    explained:
    “While the result here may seem harsh, it is no more so than in myriad other
    proceedings where a litigant or party is required to raise their objections to a
    proceeding in which they appear, and also to pursue the objections through final review
    in order to preserve them. The fact that the employee’s grievance was returned to her
    prior to the proceeding before the Merit Board did not eliminate her duty to pursue her
    objections to that proceeding, rather than permitting its decision to become final.
    In this case, Brown did not seek judicial review of the Merit Board decision and did
    not seek a stay of its enforcement. ***
    *** Interests of judicial economy and principles of res judicata require affirmance
    of the determination of the Merit Board once the employee has elected to follow civil
    service discharge procedures.” 
    Id. at 483-84.
    ¶ 56        Another case overlooked by the appellate court majority was Village of Creve Coeur,
    
    discussed supra
    . 
    187 Ill. App. 3d 116
    . There, the board of fire and police commissioners of the
    village of Creve Coeur disciplined the defendant police officer with a 30-day suspension.
    Thereafter, the police officer and his union filed a grievance pursuant to a collective bargaining
    agreement with the village contesting the board’s decision. The officer and the union also filed
    - 11 -
    a complaint for administrative review of the board’s decision. The village refused to consider
    the grievance. The village filed an action in the circuit court seeking a declaratory judgment
    that the board’s disciplinary action was not subject to the grievance procedure outlined in the
    parties’ collective bargaining agreement. The officer and the union filed a counterclaim
    seeking to compel the village to arbitrate. The circuit court entered summary judgment in favor
    of the officer and the union. The appellate court reversed, noting in the hypothetical set 
    forth, supra
    , that to hold otherwise could lead to illogical results. 
    Id. at 118.
    ¶ 57        The court in Peoria Firefighters Local 544 v. Korn, 
    229 Ill. App. 3d 1002
    (1992), found
    that the Village of Creve Coeur hypothetical was brought to life in the case before it. There, the
    plaintiff firefighters were charged by the city of Peoria with sexual misconduct while on duty
    and with insubordination concerning an incident occurring on July 13, 1986. Following a
    hearing before the fire and police commission, the firefighters were dismissed, and the
    appellate court affirmed the commission’s decision discharging the firefighters. On July 18,
    1988, the city of Peoria entered into a collective bargaining contract with plaintiff Peoria
    Firefighters Local 544, which was made retroactive to January 1, 1986. The firefighters then
    filed a grievance against the city, alleging that the commission’s actions violated certain
    provisions of the collective bargaining agreement. The grievance was referred to arbitration,
    but the parties agreed to delay arbitration in order to allow completion of the then-pending
    litigation arising from administrative review of the commission’s actions.
    ¶ 58        After that litigation was completed, the Union notified the city of its desire to proceed to
    arbitration. The city refused the request for arbitration, claiming that the firefighters had
    waived their right to arbitrate when they elected to pursue the fire and police commission
    option. The plaintiffs then filed a petition to compel arbitration. The circuit court granted the
    city’s motion to dismiss the petition.
    ¶ 59        On appeal, the plaintiffs, like the defendants in this case, argued that the doctrine of
    res judicata did not apply because the proceedings before the commission and the courts
    involved issues that were different from those which would be addressed in an arbitration
    hearing. 
    Id. at 1005.
    The plaintiffs claimed there was a difference between the standard of just
    cause that would be applied by an arbitrator under the collective bargaining agreement and the
    standard that had been applied by the commission and the courts in the prior litigation. 
    Id. The court
    found no such distinction existed, finding that
    “the underlying facts of the instant case are identical. The relief sought is also identical.
    This court therefore will not engage itself in a semantical exercise in order to skirt the
    judicially created doctrine of res judicata.” 
    Id. at 1006.
           The court further observed that the parties had proceeded before the board of fire and police
    commissioners, the circuit court, the appellate court, and even the supreme court and now,
    dissatisfied with the result, sought to take the matter to arbitration. 
    Id. at 1007.
    The court
    concluded that it should apply the rationale enunciated in Village of Creve Coeur to conserve
    judicial resources and time, and it therefore affirmed the circuit court. 
    Id. ¶ 60
           Again, in City of Rockford v. Unit Six of the Policemen’s Benevolent & Protective Ass’n,
    
    362 Ill. App. 3d 556
    (2005), the appellate court held that res judicata precluded the defendant
    union from filing a grievance seeking reinstatement of the defendant police officer. The officer
    had been terminated by the Rockford board of fire and police commissioners following a
    hearing. The union later filed a labor grievance with the deputy chief, alleging that the board
    - 12 -
    had violated the parties’ collective bargaining agreement by failing to progressively discipline
    the officer. The grievance was denied. The officer thereafter appealed his discharge to the
    circuit court, again arguing that his collective bargaining agreement required progressive
    discipline. The day after he filed his appeal in the trial court, the union demanded labor
    arbitration for the grievance. In response, the city filed a complaint for declaratory judgment
    and permanent stay of arbitration on the grievance. While the declaratory judgment remained
    pending, the trial court on administrative review affirmed the board’s findings and order
    terminating the officer’s employment. The officer did not appeal the trial court’s order on
    administrative review to the appellate court. The trial court subsequently granted summary
    judgment in favor of the city in its declaratory judgment action, finding that the elements of
    res judicata were present.
    ¶ 61        Citing Peregrine Financial, 
    309 Ill. App. 3d
    101, the appellate court held that the right to
    pursue labor arbitration is limited by the effect of the res judicata doctrine and where such
    actions involve issues previously reached, they are barred notwithstanding the parties’
    contractual right to bring them. City of 
    Rockford, 362 Ill. App. 3d at 561
    . The appellate court
    rejected the defendant’s claim that the causes of action were not identical for purposes of
    res judicata, noting that although the union’s grievance raised an additional claim regarding
    the discharge, the union’s goal was the same—to reinstate the officer on the police force. 
    Id. at 562.
    All the arguments the union now raised could have been raised by the officer or the union
    in the earlier proceeding. 
    Id. ¶ 62
           The City of Rockford court also questioned “why the Union waited until the Board issued
    its order to discharge [the officer] before seeking arbitration.” 
    Id. at 565.
    Both defendants were
    aware from the time of the hearing that the city was seeking a discharge, and the union
    president and a union representative were present throughout the hearing. 
    Id. The appellate
           court observed that “if the Union felt so strongly that the Board had no authority to discharge
    [the officer], it could have sought an injunction to stay the Board from continuing the hearing.”
    
    Id. Rather than
    do so, the defendants allowed the board’s decision to become final before the
    union instituted the grievance procedure. 
    Id. ¶ 63
           As noted, the appellate court majority in this case never acknowledged the preceding
    appellate decisions in summarily rejecting plaintiff’s res judicata argument. Defendants
    acknowledge the decisions but discount the decisions without analysis on the basis that Peoria
    Firefighters and Creve Coeur were decided prior to the 1999 and 2007 amendments to the
    Municipal Code and City of Rockford was decided prior to the 2007 amendments. Defendants
    do not even discuss the decision in Board of Governors. Further, although defendants make the
    claim that the 1999 and 2007 amendments to the Municipal Code defeat any precedential value
    of the preceding cases, defendants never discuss those amendments, nor do they set forth how
    the amendments altered the Municipal Code.
    ¶ 64        The relevant portion of the Municipal Code prior to the 1999 amendment provided:
    “Except as hereinafter provided, no officer or member of the fire or police department
    of any municipality subject to this Division 2.1 shall be removed or discharged except
    for cause, upon written charges, and after an opportunity to be heard in his own
    defense.” 65 ILCS 5/10-2.1-17 (West 1998).
    ¶ 65        The 1999 amendment added the following, after the preceding sentence:
    - 13 -
    “The hearing shall be as hereinafter provided, unless the employer and the labor
    organization representing the person have negotiated an alternative or supplemental
    form of due process based upon impartial arbitration as a term of a collective
    bargaining agreement. In non-home rule units of government, such bargaining shall be
    permissive rather than mandatory unless such contract term was negotiated by the
    employer and the labor organization prior to or at the time of the effective date of this
    amendatory Act, in which case such bargaining shall be considered mandatory.” 65
    ILCS 5/10-2.1-17 (West 2000).
    ¶ 66       The 2007 amendment changed the language of the 1999 amendment to read as follows:
    “Such bargaining shall be mandatory unless the parties mutually agree otherwise. Any
    such alternative agreement shall be permissive.” 65 ILCS 5/10-2.1-17 (West 2008).
    ¶ 67       As noted, we do not have the benefit of an analysis from defendants concerning why the
    amendments to the Municipal Code render the previously discussed appellate decisions
    distinguishable from the instant case. It is possible defendants believe that if the preceding
    amendments had been enacted when those cases were decided, the appellate court would have
    found that res judicata did not apply to bar grievance arbitration because collective bargaining
    ultimately was made mandatory unless otherwise agreed.
    ¶ 68       Defendants’ posture on appeal, however, reveals that they do not understand the
    res judicata analysis applied in the previously discussed appellate decisions. It may be true that
    an arbitrator would find that Lopez’s disciplinary matter was subject to mandatory grievance
    arbitration. And it may be true that had the 1999 and 2007 amendments to section 10-2.1-17
    been enacted at the time the preceding appellate decisions were decided, the parties may have
    had a right to mandatory arbitration. Nevertheless, and as the previous appellate decisions
    clearly demonstrate, a party’s right to pursue mandatory grievance arbitration may be limited
    by the effect of the res judicata doctrine if the arbitration involves issues reached in a prior
    adjudication, which is manifestly the case here.
    ¶ 69       With regard to res judicata, defendants do not dispute that there is an identity of the parties
    or their privies. Defendants do deny that there was a final judgment on the merits rendered by a
    court of competent jurisdiction. Defendants claim that the Board has not and cannot issue a
    final judgment regarding a violation of the labor contract, so that plaintiff cannot establish
    res judicata.
    ¶ 70       Defendants are correct that the Board did not issue a final judgment regarding a violation of
    the labor contract. However, that is not the issue for purposes of this element of res judicata. At
    issue here is whether the Board was a court of competent jurisdiction and, if so, whether the
    Board issued a final judgment on the merits.
    ¶ 71       Administrative decisions have res judicata and collateral estoppel effect where the
    administrative determination is made in proceedings that are adjudicatory, judicial, or
    quasijudicial in nature. Marco v. Doherty, 
    276 Ill. App. 3d 121
    , 124-25 (1995). Here, there was
    an adversarial hearing conducted under oath and on the record. Lopez testified at the hearing
    before the Board, and counsel for defendants presented evidence, cross-examined witnesses,
    and made a closing argument. The Board’s administrative hearing, then, was judicial in nature.
    ¶ 72       Following the hearing, the Board issued a decision. Defendants failed to seek judicial
    review of the Board’s decision pursuant to the Administrative Review Law, so that decision
    became a final judgment on the merits. Consequently, plaintiff is correct that, for purposes of
    - 14 -
    res judicata, there was a final judgment on the merits rendered by a court of competent
    jurisdiction in this case.
    ¶ 73       Defendants next argue that res judicata does not apply in this case because there is no
    identity of cause of action. Defendants assert that there is no identity of cause of action because
    the issue of “just cause” has not been decided. Defendants point out that the labor contract
    between the parties sets forth a “just cause” standard for discipline, while the Board only
    applied the “cause” standard set forth in the Municipal Code. Defendants cite the decision in
    Ryherd v. General Cable Co., 
    124 Ill. 2d 418
    (1988), in support of their argument. Defendants
    note that in Ryherd, the court held that an employee that grieved her discharge to arbitration
    under federal labor law was not precluded from thereafter seeking to recover in state court for
    retaliatory discharge. Ryherd observed that an arbitrator would be deciding whether there was
    “just cause” to discharge a worker, while the tort of retaliatory discharge does not require “just
    cause” for all dismissals. 
    Id. at 427.
    Ryherd concluded that it would be “a fundamental error to
    equate dismissals which violate State tort law with dismissals violative of a typical
    collective-bargaining agreement.” 
    Id. ¶ 74
          We first note that Ryherd is not on point, as the court expressly pointed out that the appellee
    in that case had not invoked the doctrine of res judicata or collateral estoppel. 
    Id. at 432.
           Further, defendants misunderstand the identity of cause of action element of res judicata. As
    noted, this court applies a transactional test to determine whether the causes of action are the
    same for purposes of res judicata. River Park, 
    Inc., 184 Ill. 2d at 311
    . Pursuant to the
    transactional test, separate claims will be considered the same cause of action for purposes of
    res judicata if they arise from a single group of operative facts, regardless of whether they
    assert different theories of relief. 
    Id. ¶ 75
          Here, the claims in defendants’ grievance and the claims before the Board arose from a
    single group of operative facts. Plaintiff sought to terminate Lopez’s employment with
    plaintiff’s police department based upon misconduct. The facts underlying the complaint for
    termination that were heard before the Board are identical to the facts that would underlie a
    grievance filed by Lopez in response to plaintiff’s complaint for termination. Defendants’
    objective in the Board action was the same as their objective in the grievance—to defend
    Lopez from the misconduct charges and to prevent his termination from employment as a
    police officer.
    ¶ 76       Although defendants claim that res judicata does not apply because the Board did not
    consider just cause, the doctrine of res judicata acts as a bar not only to a subsequent suit
    between the parties involving the same cause of action but also extends to matters that could
    have been decided in the first action. 
    Id. Res judicata
    embraces all grounds of recovery and
    defense involved and which might have been raised in the first action. 
    Hughey, 76 Ill. 2d at 583
    . Defendants could have filed a grievance when they received the complaint for
    termination. Defendants could have raised the issue of just cause at the hearing before the
    Board. Defendants could have filed a complaint for declaratory judgment prior to the Board
    hearing, alleging that the Board was divested of jurisdiction pursuant to the parties’ labor
    contract. Defendants did none of these things.
    ¶ 77       Likewise, defendants now complain that the labor contract required discipline to be
    “progressive and corrective” and that termination be reserved for “extreme cases” but the
    Board did not apply that standard. Again, defendants could have raised these claims at the
    - 15 -
    Board hearing but did not do so. A party cannot assign “new reasons for holding the agreement
    invalid, which existed at the time that decision was rendered,” in order to relitigate the question
    settled by the prior decree. (Internal quotation marks omitted.) 
    Id. Because defendants’
    claims
    concerning the standards for discipline or termination of officers in the labor contract existed at
    the time the Board decision was rendered, we find that defendants are now barred from
    relitigating these claims.
    ¶ 78        The purpose of res judicata is to promote judicial economy by requiring parties to litigate,
    in one case, all rights arising out of the same set of operative facts, as well as to prevent
    imposing an unjust burden that would result if a party could be forced to relitigate what is
    essentially the same case. River Park, 
    Inc., 184 Ill. 2d at 319
    . These purposes would be
    undermined if defendants now were permitted to pursue their grievance after defending the
    same cause of action before the Board.
    ¶ 79        Because defendants’ grievance was barred pursuant both to principles of waiver as well as
    the doctrine res judicata, plaintiff was entitled to summary judgment in its favor on its
    complaint for declaratory judgment and for stay of arbitration. We therefore affirm the trial
    court’s judgment on that basis and reverse the appellate court’s order, which reversed the trial
    court and remanded the cause to the trial court to order the parties to proceed to arbitration.
    ¶ 80      Appellate court judgment reversed.
    ¶ 81      Circuit court judgment affirmed.
    ¶ 82      JUSTICE KILBRIDE took no part in the consideration or decision of this case.
    - 16 -
    

Document Info

Docket Number: 120643

Citation Numbers: 2017 IL 120643

Filed Date: 7/17/2017

Precedential Status: Precedential

Modified Date: 3/3/2020

Cited By (26)

Ward v. Decatur Memorial Hospital , 2019 IL 123937 ( 2021 )

The Village of Bartonville v. Lopez , 2017 IL 120643 ( 2017 )

McHenry Savings Bank v. Moy , 2021 IL App (2d) 200099 ( 2021 )

Iwan Ries & Co. v. City of Chicago , 2019 IL 124469 ( 2021 )

Medponics Illinois LLC v. Dept. of Agriculture , 2021 IL 125443 ( 2021 )

Iwan Ries & Co. v. City of Chicago , 2019 IL 124469 ( 2019 )

Tonne v. TRF Distributing, Inc , 2021 IL App (1st) 201389-U ( 2021 )

895 Wood Dale, LLC v. City of Wood Dale , 2022 IL App (2d) 200450-U ( 2022 )

895 Wood Dale, LLC v. City of Wood Dale , 2022 IL App (2d) 200450-U ( 2022 )

People v. Patterson , 2022 IL App (3d) 200099-U ( 2022 )

Briggs v. SMG Food & Beverage, LLC , 2022 IL App (1st) 211640-U ( 2022 )

In re Marriage of Miller , 2022 IL App (2d) 210608-U ( 2022 )

Board of Education of the City of Chicago v. Illinois State ... , 2017 IL App (1st) 161147 ( 2017 )

Enbridge Pipeline (Illinois), LLC v. Temple , 2017 IL App (4th) 150346 ( 2017 )

Martinez v. Cook County State's Attorney's Office , 103 N.E.3d 351 ( 2018 )

Radiant Star Enterprises, L.L.C. v. Metropolis Condominium ... , 107 N.E.3d 877 ( 2018 )

Martinez v. Cook County State's Attorney's Office , 2018 IL App (1st) 163153 ( 2018 )

Enbridge Pipeline (Illinois), LLC v. Kiefer , 2017 IL App (4th) 150342 ( 2017 )

Caterpillar Inc. v. Century Indemnity Co. , 2019 IL App (3d) 190032 ( 2019 )

First Bank of Highland Park v. Sklarov , 2019 IL App (2d) 190210 ( 2019 )

View All Citing Opinions »