Ellis v. ICC Group, Inc. , 2022 IL App (1st) 211581-U ( 2022 )


Menu:
  •                                           
    2022 IL App (1st) 211581-U
    NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the
    limited circumstances allowed under Rule 23(e)(1).
    SECOND DIVISION
    December 13, 2022
    No. 1-21-1581
    ______________________________________________________________________________
    IN THE
    APPELLATE COURT OF ILLINOIS
    FIRST DISTRICT
    ______________________________________________________________________________
    JOSEPH ELLIS,                                                  )
    )      Appeal from the
    Plaintiff-Appellant,                    )      Circuit Court of
    )      Cook County
    v.                                                         )
    )      No. 17 L 10936
    ICC GROUP, INC. d/b/a ILLINOIS CONSTRUCTORS                    )
    CORPORATION and WBK ENGINEERING, LLC,                          )      The Honorable
    )      Rena Van Tine,
    Defendants                              )      Judge Presiding.
    )
    (ICC Group, Inc., Defendant-Appellee).                         )
    PRESIDING JUSTICE FITZGERALD SMITH delivered the judgment of the court.
    Justices Ellis and Cobbs concurred in the judgment.
    ORDER
    ¶1   Held: Trial court’s granting of summary judgment in favor of defendant is reversed, where
    defendant owed a duty of care to the plaintiff under a negligence theory of premises liability
    and a genuine issue of material fact existed as to proximate cause.
    ¶2        The plaintiff, Joseph Ellis, appeals from the trial court’s granting of summary judgment in
    favor of the defendant, ICC Group, Inc. d/b/a Illinois Constructors Corporation, on all counts of
    his complaint for negligence. The basis of the trial court’s ruling was that the defendant, a general
    contractor, owed no duty of care to the plaintiff, an employee of a subcontractor. The trial court
    No. 1-21-1581
    also found that the element of proximate cause was not satisfied. We reverse and remand.
    ¶3                                           I. BACKGROUND
    ¶4        The summary judgment record discloses the following facts, which we set forth in the light
    most favorable to the plaintiff, as the party opposing summary judgment. In 2015, the defendant
    served as the general contractor on a project to modify a dam at the Busse Woods Reservoir, which
    was part of a flood control project undertaken by the Village of Elk Grove Village (Village). This
    project involved modification of the dam to install two new dam “gates” that could be operated
    hydraulically via remote control. The work was divided into two stages, with a gate for the west
    half of the dam being installed first, followed by the gate for the east half of the dam. To hold back
    water and create a dry area where work could be performed, the defendant first built a temporary
    cofferdam around the west side of the dam. A new concrete platform was built next, which was
    approximately eight feet wide, and the dam gate was then installed on top of that platform. The
    plaintiff’s fall occurred in the final days of the project’s first stage, when the west side cofferdam
    was in place, the west platform was built, and the west gate had been installed.
    ¶5        The plaintiff was a commercial electrician employed by the electrical subcontractor on the
    project, Lyons & Pinner (Lyons). On October 28, 2015, Lyons had assigned the plaintiff to help
    Kevin McLaughlin, the Lyons electrician primarily working on the dam project, run electrical
    wires through conduit to reach the dam. This was the plaintiff’s first day working at this site, and
    the plan was for it to be his only day working there. The two men spent the morning pulling the
    wires through the conduit, from the shed where it was stored toward the dam itself. They reached
    the dam in mid-afternoon. There, wires had to be run to reach equipment on both the north and
    south sides of the gate platform.
    ¶6        As stated, by this time the gate was in place atop the concrete platform. It had been installed
    -2-
    No. 1-21-1581
    eight days earlier, on October 20-21. From the evidence, we would describe the gate as a curved
    steel structure, approximately five feet in height. Horizontally, it extends the full length of the
    concrete platform, between vertical pillars on both sides that run to the bridge above. Neither of
    the gate’s sides are flat. The gate’s north side (i.e., the side facing the reservoir) curves in a convex
    fashion, while its south side is concave. Also, when upright, the gate is not fully perpendicular to
    the platform below, but instead it rises at a southward angle.
    ¶7        The platform was accessible by a ramp that ran from the road above to the platform’s north
    side, and this was how the plaintiff and McLaughlin first accessed the area. Once there, the plaintiff
    found no evident method of access to reach the platform’s south side. He testified that he did not
    ask McLaughlin for a method to cross over the gate but that McLaughlin told him that he had
    simply been jumping across the gate and sliding down. McLaughlin testified that this was the
    method he had seen other tradesman use to get back and forth over the gate since it had been
    installed eight days earlier, although he had also seen workers use a ladder to climb up one of the
    sides. The plaintiff saw McLaughlin grab the top of the rail, swing himself up, and flip over to the
    other side. The plaintiff, then age 59, said that he was “too old for that” and did not believe it was
    safe to jump over the gate. He saw that an extension ladder was on the south side of the gate, and
    he asked McLaughlin if they needed a second ladder to get across it. McLaughlin answered yes,
    that one was by the road. The plaintiff then went to the road and retrieved a second ladder. He
    positioned it against the north side of the gate, adjacent to the ladder that was already positioned
    against its south side. He then tied the two ladders together with mule tape, which is a heavy nylon
    cord that the electricians used on the job site. He testified that the reason he tied the two ladders
    together was because he thought this would make it safer for him to cross the gate using the two
    ladders. McLaughlin did not help him do this, but he said that it was fine after seeing what the
    -3-
    No. 1-21-1581
    plaintiff was doing.
    ¶8          After that, the plaintiff successfully used the ladders to climb across the gate to the south side
    of the platform, and he and McLaughin did work there for approximately one hour. After
    completing his work, the plaintiff attempted to return to the north side by climbing the ladders to
    cross the gate. As he was in the process of pivoting to transfer from the south-side ladder to the
    north-side ladder, he lost his balance and fell backwards onto the concrete ledge and water below.
    He sustained injuries, which apparently included a lumbar spine fracture requiring surgery,
    impingement syndrome in his left rotator cuff, and a concussion.
    ¶9          Following this incident, the plaintiff filed a three-count complaint against the defendant.
    Count I was a for general negligence. It alleged that the defendant had a duty to exercise reasonable
    care in ensuring that the project site was a safe workplace for the plaintiff and others, and the
    defendant breached that duty, inter alia, by allowing workers to use unsecured ladders to cross the
    gate. Count II pled a claim under section 414 of the Restatement (Second) of Torts, alleging that
    the defendant was negligent, inter alia, by failing to exercise control over job site activities with
    reasonable care so as to provide the plaintiff and others with a safe place to work. Finally, count
    III plead a claim of premises liability. It alleged that the defendant was negligent, inter alia, in
    allowing an unsecured ladder to exist on the project site as the presumptive method of scaling the
    dam gate while working on it, failing to ensure that the ladder was secure, allowing workers
    including the plaintiff to work on an unsecured ladder, failing to warn, and failing to discover and
    remedy the dangerous condition.
    ¶ 10        Following discovery, the defendant filed a motion for summary judgment. It argued that the
    evidence was insufficient to show that it had “retained control” over the work done by the Lyons
    electricians on the job site sufficient to impose on it a duty under section 414 of the Restatement
    -4-
    No. 1-21-1581
    (Second) of Torts. The defendant argued that its subcontract with Lyons showed that Lyons had
    full control over the means and methods of its own work, and there was no evidence of conduct
    by the defendant’s employees retaining control over the safety or the details of the subcontractors’
    work. It also argued that the evidence did not support a claim of premises liability, because the
    undisputed evidence showed that the defendant was not the possessor of the premises, that the
    incident did not involve a condition of the land, that it did not have notice of any unsafe condition,
    and that the plaintiff’s ladder set-up was itself an open and obvious danger. The defendant further
    argued that there was no evidence to satisfy the element of proximate cause.
    ¶ 11        In response, the plaintiff argued that as general contractor, the defendant was responsible for
    creating a safe means of access to both sides of the dam gate for all tradesman who needed to work
    there, and the defendant breached this duty by leaving it up to each trade to fashion its own way
    over the gate to do its work. He relied on the knowledge that the defendant should have had from
    constructing the dam gate, its being on site to recognize that tradesmen were working on both sides
    of the gate, and its responsibility to coordinate the work of the various subcontractors. He relied
    on contractual provisions concerning the defendant’s responsibilities. As evidence of control, he
    cited evidence that the defendant’s carpenters did in fact construct a wooden platform over the
    gate after his injury and had also constructed a safety rail down the ramp to the dam. He also cited
    the affidavit of Frank Burg, his expert in construction matters and safety, attesting that the
    defendant had violated OSHA regulations and that the duty to create safe access within a jobsite
    is understood to be the role of the general contractor. He further cited additional deposition
    testimony by occurrence witnesses concerning their expectation that the general contractor, not an
    electrical subcontractor, would have the responsibility of providing a temporary structure to enable
    workers to cross a dam gate. He cited deposition testimony from the defendant’s superintendent
    -5-
    No. 1-21-1581
    on the project, Scott Lampson, who was not on site that afternoon, that he would have stopped the
    plaintiff and removed him from the job if he had seen him using two ladders to cross over the gate.
    ¶ 12        The trial court granted the defendant’s motion for summary judgment. It found that the
    defendant did not owe a duty of care to the plaintiff under either a “retained control” or premises
    liability theory of negligence. It found that the defendant had no actual or constructive notice of
    any dangerous condition. It found no facts supporting an inference that the defendant retained the
    degree of control, supervision, or monitoring of the jobsite comparable to cases in which a duty
    has been imposed under section 414. It further found no proximate cause between any alleged
    negligence and the plaintiff’s injuries. It found that the dam gate was a “condition” rather than the
    “cause” of injury, with the cause being the plaintiff’s own conduct in using the ladders to transfer
    across the dam gate. It also found no evidence of foreseeability to satisfy the “legal cause” aspect
    of the proximate causation analysis. The trial court later denied a motion to reconsider filed by the
    plaintiff. This appeal then followed.
    ¶ 13                                              II. ANALYSIS
    ¶ 14        This appeal involves the trial court’s granting of a motion for summary judgment, which we
    review de novo. Johnson v. Armstrong, 
    2022 IL 127942
    , ¶ 31. For the granting of a motion for
    summary judgment to be proper, the pleadings, depositions, and admissions on file, together with
    the affidavits, if any, must show that there is no genuine issue as to any material fact and that the
    moving party is entitled to a judgment as a matter of law. 735 ILCS 5/2-1005(c) (West 2020). A
    genuine issue of material fact exists where the material facts are disputed or, if they are undisputed,
    where reasonable persons might draw different inferences from them. Johnson, 
    2022 IL 127942
    ,
    ¶ 31. In evaluating whether a genuine issue of material fact exists, a court construes the evidence
    in the light most favorable to the nonmoving party and strictly against the movant. 
    Id.
    -6-
    No. 1-21-1581
    ¶ 15                                                 A. Duty
    ¶ 16        In any negligence case, the plaintiff must establish the existence of a duty of care owed by
    the defendant to the plaintiff, a breach of that duty, and an injury proximately caused by that
    breach. Carney v. United Pacific R.R. Co., 
    2016 IL 118984
    , ¶ 26. Whether a duty exists is a
    question of law appropriate for summary judgment. 
    Id.
     Absent a showing from which the court
    could infer the existence of a duty, a plaintiff may not recover as a matter of law and summary
    judgment in favor of the defendant is properly granted. 
    Id.
    ¶ 17        Every person owes a duty of ordinary care to all others to guard against injuries that naturally
    flow as a reasonably probable and foreseeable consequence of an act, and such duty does not
    depend upon contract, privity of interest, or the proximity of relationship. Bogenberger v. Pi Kappa
    Alpha Corp., 
    2018 IL 120951
    , ¶ 22. Accordingly, where a party’s course of action creates a
    foreseeable risk of injury, that party has a duty to protect others from such injury. 
    Id.
     The duty
    inquiry asks whether the defendant and the plaintiff stood in such a relationship to one another that
    the law imposed upon the defendant an obligation of reasonable conduct for the benefit of the
    plaintiff. 
    Id.
     (citing Ward v. K Mart Corp., 
    136 Ill. 2d 132
    , 140 (1990)). Whether a duty exists is
    also an inquiry shaped by public policy. Bogenberger, 
    2018 IL 120951
    , ¶ 22 (citing LaFever v.
    Kemlite Co., 
    185 Ill. 2d 380
    , 388 (1988)). The traditional duty test involves four factors: (1) the
    reasonable foreseeability of the injury, (2) the likelihood of the injury, (3) the magnitude of the
    burden of guarding against the injury, and (4) the consequences of placing that burden on the
    defendant. Bogenberger, 
    2018 IL 120951
    , ¶ 22.
    ¶ 18        On appeal, the plaintiff argues that the defendant owed him a duty of care under two separate
    theories of negligence. The first involves the duty owed by a party who has “retained control” over
    work entrusted to an independent contractor, governed by section 414 of the Restatement (Second)
    -7-
    No. 1-21-1581
    of Torts. The second involves the duty owed by a possessor of land for dangerous conditions on
    the land under a theory of premises liability. Whether a duty exists under the latter theory is
    governed by the principles of sections 343 and 343A of the Restatement (Second) of Torts. These
    are independent duties and theories of negligence, and a defendant can be found to owe a duty
    under one but not the other. Clifford v. Wharton Business Group, L.L.C., 
    353 Ill. App. 3d 34
    , 41
    (2004). As explained below, we find that to be the case here. We conclude that the defendant owed
    a duty to the plaintiff as a possessor of land under a theory of premises liability, but that the
    defendant did not sufficiently retain control of the work of a subcontractor such that it owed a duty
    under section 414.
    ¶ 19                                          1. Premises Liability
    ¶ 20        We choose to begin with the theory under which we find a duty to exist, which is that the
    defendant owed the plaintiff a duty of care under a premises liability theory of negligence. In such
    a claim, the foreseeability-of-injury prong of the duty test is determined with reference to section
    343 of the Restatement (Second) of Torts. LaFever, 185 Ill. 2d at 389. That section provides that
    a “possessor” of land is subject to liability for harm caused by a “condition on the land” if he:
    knows or by the exercise of reasonable care would discover the condition, and should realize that
    it involves an unreasonable risk of harm; should expect that invitees will not discover or realize
    the danger, or will fail to protect themselves against it; and fails to exercise reasonable care to
    protect invitees against the danger. Restatement (Second) of Torts § 343, at 215-16 (1965).
    ¶ 21        The foreseeability of an injury and its likelihood of occurring from a condition on the land is
    also affected by whether the danger posed by the condition is open and obvious to an invitee. The
    “open and obvious rule” is reflected in section 343A of the Restatement (Second) of Torts and has
    been adopted into Illinois law. See Deibert v. Bauer Brothers Construction Co., 
    141 Ill. 2d 430
    ,
    -8-
    No. 1-21-1581
    434-36 (1990). Under section 343A, “[a] possessor of land is not liable to his invitees for physical
    harm caused to them by any activity or condition on the land whose danger is known or obvious
    to them, unless the possessor should anticipate the harm despite such knowledge or obviousness.”
    (Emphasis added). Restatement (Second) of Torts § 343A(1), at 218 (1965). The rule impacts the
    foreseeability and likelihood of injury prongs of the duty test because it stems from the
    presumption that it is not foreseeable that a person will intentionally encounter the risk of an open
    and obvious danger, thereby making injury less likely. See Bruns v. City of Centralia, 
    2014 IL 116998
    , ¶ 19. However, exceptions exist to the open and obvious rule. The exception relevant to
    this case is the “deliberate encounter” exception, which provides that a possessor of land should
    anticipate harm when the possessor “ ‘has reason to expect that the invitee will proceed to
    encounter the known or obvious danger because to a reasonable man in his position the advantages
    of doing so would outweigh the apparent risk.’ ” Id. ¶ 20 (quoting Restatement (Second) of Torts
    § 343A, cmt. f, at 220 (1965)); LaFever, 185 Ill. 2d at 391. In instances where this exception is
    applicable, an injury is considered more foreseeable to a defendant and more likely to occur, thus
    weighing in favor of the imposition of a duty. Bruns, 
    2014 IL 116998
    , ¶ 20.
    ¶ 22        We first address the threshold argument raised by the defendant that it owes no duty under
    section 343 because it was not a “possessor” of the land where the plaintiff’s injury occurred. It
    argues that the dam where the plaintiff was injured was owned and operated by the Village and by
    the Forest Preserve District of Cook County, and there is no evidence that the defendant had any
    power to exclude anyone from the land, to control what was built there, or to take any other action
    indicating dominion over the property. We find no merit to this argument. This court has defined
    a possessor of land as “ ‘a person who is in occupation of the land with intent to control it.’ ”
    Madden v. Paschen, 
    395 Ill. App. 3d 362
    , 375 (2009) (quoting Restatement (Second) of Torts
    -9-
    No. 1-21-1581
    § 328E, at 170 (1965)); O’Connell v. Turner Construction Co., 
    409 Ill. App. 3d 819
    , 824 (2011).
    Although a general contractor is not always considered a possessor of a site under construction,
    the evidence in this case shows that the defendant was the possessor of the dam platform where
    the plaintiff’s injury occurred. The defendant was hired as a general contractor to install a
    cofferdam and thereby create a dry construction site within the reservoir, upon which it erected a
    concreate platform and installed the dam gate. By doing this and acting as general contractor to
    oversee completion of the work to install the dam gates, the defendant effectively created the site
    where the plaintiff’s injury occurred and exercised control over it during the time construction was
    ongoing. Accordingly, the defendant is a possessor of the land at issue for purposes of section 343.
    ¶ 23        Next, we address the defendant’s argument that it owed no duty to the plaintiff under section
    343 because his injury was not caused by a “condition on the land.” The defendant characterizes
    the plaintiff’s injury as being caused by his own conduct “in creating an unsafe ladder set-up for
    himself,” which it contends is an unsafe work practice, not a condition on the land. By contrast,
    the plaintiff argues that the condition on the land that caused his injury was the existence of the
    dam gate on the platform without a safe means of access over it for workers required to perform
    work on the platform’s south side. The plaintiff has the correct argument here. The defendant’s
    argument about whether the plaintiff’s injury was caused solely by his own conduct is effectively
    one of proximate cause or comparative fault, not duty. Here, we are dealing with the legal issue of
    whether the defendant owed a duty, and more specifically whether an injury like the one that the
    plaintiff suffered was reasonably foreseeable to the defendant. If we were to accept the defendant’s
    argument, then effectively we would be evaluating the defendant’s duty based upon the conduct
    of the plaintiff, which is improper. Instead, the proper subject of our focus is the defendant and
    whether it could reasonably have foreseen an injury like the one the plaintiff suffered. See Ward,
    - 10 -
    No. 1-21-1581
    
    136 Ill. 2d at 148
     (“The scope of defendant’s duty is not defined by reference to plaintiff’s
    negligence or lack thereof. The focus must be on defendant. A major concern is whether defendant
    could reasonably have foreseen injury to the plaintiff.” (Emphasis in original)). Accordingly, we
    see the question as being whether the defendant could reasonably have foreseen that a tradesman
    in the plaintiff’s position would attempt to use ladders set on each side of the dam gate to cross
    over it and fall in the process of doing so. We believe that an injury of this nature was reasonably
    foreseeable to the defendant due to the gate’s blocking of land access to the entire south side of
    the platform despite the fact that tradesmen had work to perform there.
    ¶ 24        The record contains direct and circumstantial evidence from which a trier of fact could
    reasonably conclude that the defendant had actual or constructive knowledge of various facts
    bearing on its ability to reasonably foresee that workers would use ladders in an attempt to cross
    the dam gate and fall in the process. Constructive knowledge may be proven by demonstrating that
    a condition existed for a sufficient period of time such that the defendant could have discovered it
    through the exercise of reasonable care. Heider v. DJG Pizza, Inc., 
    2019 IL App (1st) 181173
    ,
    ¶ 34. Generally, whether a defendant is deemed to have constructive knowledge of the existence
    of a dangerous condition on its land is a question of fact. 
    Id.
    ¶ 25        There is no dispute that the defendant had knowledge of the dam gate itself and that its
    presence blocked access by land to the south side of the platform. As we described it above, the
    gate is a curved steel structure, approximately five feet in height. When upright, it is angled rather
    than perpendicular to the platform below. It runs the full length of the concrete platform between
    the vertical pillars on each side holding up the bridge above. The gate had been in place for seven
    to eight days prior to the plaintiff’s injury.
    ¶ 26        The evidence indicates that that the defendant’s employees were aware that, once the dam
    - 11 -
    No. 1-21-1581
    platform was installed, no easy method of access existed to reach the south side of the dam
    platform. Apart from the gate itself, access to the other sides of the platform were impeded by
    water from the reservoir and creek, the vertical pillars, and the walls of the cofferdam. Scott
    Lampson, who served as the defendant’s superintendent on the job, testified that after the gate was
    installed, he did not believe that workers should have had to get to the south side of the platform;
    but if they did, they should “come in by boat on the south side of the dam,” put boots on and walk
    through the water if it was low enough, or “use scaffolding.” David Krueger, the defendant’s
    project manager for this project, testified that after the gate’s installation, someone needing to
    access the platform’s south side could “take a boat,” “put waders on and walk[ ] through the gate
    [sic] depending on the river level,” “set up a scaffolding system,” or “request[ ] that the gate be
    lowered.” Lampson testified that the defendant’s own employees used a boat to get to and from
    the south side, but that the defendant’s boat was not available for use by the subcontractors.
    Krueger similarly testified that the subcontractors would have had to provide their own boats.
    ¶ 27        If the undisputed evidence showed how the defendant communicated these expectations to
    the subcontractors, we would be more likely to agree that an injury from a subcontractor’s
    employee attempting to cross the gate using ladders was unforeseeable. However, neither party
    draws our attention to any evidence on this point. Instead, a trier of fact could reasonably draw the
    inference from the evidence that nothing was ever communicated between the defendant and
    Lyons about accessing the south side of the platform. Both Lampson and Krueger testified that the
    defendant left it to the subcontractors to determine the means and methods by which they would
    access the platform’s south side. McLaughlin testified that the defendant did not provide him with
    any direction or instruction about how to transfer over the gate. Lampson testified that nobody
    ever asked him for a way to access one side of the dam from the other. Lampson testified that if
    - 12 -
    No. 1-21-1581
    he had been asked (specifically by the plaintiff or McLaughlin), he would have told them that the
    defendant could not provide them with ladders or a boat for liability reasons but instead that “they
    have to have *** their own people figure out what they need and okay it with us.”
    ¶ 28        We recognize that the plaintiff is unable to cite direct evidence that the defendants were aware
    that the Lyons electricians had work to perform on the south side of the platform once the gate was
    installed and thus had reason to cross the gate. Nevertheless, we find that the circumstantial
    evidence is sufficient to show an issue of fact concerning the defendant’s actual or constructive
    knowledge that following the gate’s installation, tradesman had work to perform on the south side
    of the platform and were accessing it by jumping over the gate or using ladders to cross it.
    McLaughlin testified that following the gate’s installation, he observed workers from the various
    trades crossing the gate by hopping over it or by using a ladder to climb over it. McLaughlin
    testified that he never saw the gate in a lowered or down position after it was installed. The record
    contains various photographs taken between the time of the gate’s installation and the plaintiff’s
    injury showing workers on both sides of the gate, as well as various ladders on the ground and
    propped against the sides of the gate. Workers in vests with the defendant’s logo are shown in
    some of these photographs. Also, Lampson testified that he was at the site every day overseeing
    what was going on there (although he had left in the morning on the day of the plaintiff’s injury).
    Furthermore, there is evidence from the affidavit of Frank Burg, the plaintiff’s expert in
    construction matters and construction site safety, that the defendant was required by OSHA
    regulations to conduct frequent and regular inspections of the job site. See 
    29 C.F.R. § 1926.20
    (b)(1), (2) (2012).
    ¶ 29        Further bearing on the issue of whether an injury like the plaintiff’s was reasonably
    foreseeable to the defendant is evidence of the custom and practice of general contractors
    - 13 -
    No. 1-21-1581
    concerning safeguards within a job site and the expectations of invitees that come onto the
    premises. See Restatement (Second) of Torts § 343, cmt. d, at 217 (1965). John Ott, who was the
    project manager for Lyons on this project, testified that in his 32 years of professional experience,
    “it is the obligation of the general contractor to provide a structure, a platform, temporary safe
    condition platform over a structural non-electrical portion item to work over. To me it’s not Lyons
    and Pinner’s obligation to provide a temporary structure over a dam.” McLaughlin also testified
    that he believed that a general contractor was “supposed to provide the means of how to navigate
    their job site.” Burg’s affidavit states that on multi-employer worksites such as this, the custom
    and practice is that a general contractor will implement a program to assure proper access,
    coordination of work activities, communication of specific work rules, job site monitoring, and
    enforcement when rules are violated. Burg states that any reasonable safety program would have
    assured the general contractor will make certain that subcontractors will have proper access to their
    work area. All of this evidence supports the conclusion that it was reasonably foreseeable to the
    defendant that workers might fail to appreciate the need to bring equipment such as a boat, waders,
    or a scaffold to reach the south side of the platform and instead proceed to cross the gate by using
    ladders, which could result in a fall.
    ¶ 30        Notwithstanding the evidence discussed above, we must also consider whether the open and
    obvious nature of the condition negated the foreseeability of injury to the defendant, as well as the
    plaintiff’s argument that the “deliberate encounter” exception to the open and obvious rule applies.
    The plaintiff acknowledges in his brief that the gate over which he needed to traverse was open
    and obvious. He argues, however, that the obviousness of the danger does not make an injury like
    his unforeseeable, because the defendant should have anticipated that he or other workers would
    cross over the gate in order to complete the work that had to be done on the south side of the
    - 14 -
    No. 1-21-1581
    platform. As stated, this is the “deliberate encounter” exception to the open-and-obvious rule,
    which provides that a possessor of land should anticipate harm when the possessor “ ‘has reason
    to expect that the invitee will proceed to encounter the known or obvious danger because to a
    reasonable man in his position the advantages of doing so would outweigh the apparent risks.’ ”
    LaFever, 185 Ill. 2d at 391 (quoting Restatement (Second) of Torts § 343A, cmt. f, at 220 (1965)).
    This exception recognizes that individuals will make deliberate decisions to encounter hazards
    when faced with employment concerns, and those encounters are reasonably foreseeable to
    possessors of land. Grillo v. Yeager Construction, 
    387 Ill. App. 3d 577
    , 596 (2008) (citing
    LaFever, 185 Ill. 2d at 394-95). The focus of the deliberate-encounter analysis remains on what
    the possessor of land anticipates or should anticipate that the entrant will do. Grillo, 387 Ill. App.
    3d at 596.
    ¶ 31        In arguing that this exception applies, the plaintiff relies on evidence showing that on the day
    he fell, he had electrical work to perform on the south side of the platform. To access the south
    side to complete that work, he had to encounter and traverse the dam gate. To return, he had to
    traverse the gate again. The plaintiff further cites the following statement in Burg’s affidavit
    concerning what the defendant should have anticipated a tradesman in his position would do:
    “Human factors should be considered in this case. Mr. Ellis and all workers expect
    controlling employers to provide safe access and egress. Once they are on the job working
    on the coffer dam, it would be unusual to stop the project and demand an access ladder.
    Most workers like Mr. Ellis will figure out a way to get the job done.”
    ¶ 32        For its part, the defendant does not refute the plaintiff’s assertion that it should have
    anticipated that he would have attempted to cross the dam gate to complete his work. Instead, it
    argues that the plaintiff’s use of the two ladders tied together was itself an open and obvious
    - 15 -
    No. 1-21-1581
    danger. The defendant argues that the “deliberate encounter” exception involves reasonableness,
    that there is no evidence that it was reasonable for the plaintiff to use “his self-made, unsafe
    condition,” and that he could have asked his employer for a different method to reach his work.
    ¶ 33        Mindful that we are addressing the foreseeability prong of the duty test, we agree with the
    plaintiff’s argument that the deliberate encounter exception applies. We find that the defendant
    should reasonably have anticipated that a worker in the plaintiff’s position would have proceeded
    to encounter the hazard posed by crossing over the dam gate in order to complete the work he was
    required to do on the south side. Although other ways may have existed to reach the platform’s
    south side, we believe the defendant should have anticipated that a tradesman would find procuring
    a boat, waders, or scaffolding far more onerous than simply attempting to cross the gate with
    ladders. This is especially true if the tradesman only had to work on the south side of the platform
    for a brief time. The defendant cannot escape owing a duty merely by asserting that the plaintiff’s
    use of ladders was itself unreasonable or unsafe. Rather, we find it reasonably foreseeable to the
    defendant that workers needing to work on the south side of the platform would deliberately
    attempt to cross the gate in some fashion. This includes attempting to do so by propping ladders
    against each side and attempting to pivot from one to the other. The plaintiff’s own conduct or
    method of crossing the gate may later affect the ultimate issue of liability or the parties’
    comparative fault, but it does not affect the existence of a duty. LaFever, 185 Ill. 2d at 396-97;
    Preze v. Borden Chemical, Inc., 
    336 Ill. App. 3d 52
    , 59 (2002).
    ¶ 34        Turning to the remaining factors of the duty test, we find that they also weigh in favor of
    imposing a duty in this case. While we find that the likelihood of injury here is lessened by the
    open and obvious danger posed by the dam gate, this is offset by the recognition that workers
    would be likely to proceed to deliberately encounter that risk in order to complete their job duties
    - 16 -
    No. 1-21-1581
    on the south side of the platform via one of the most evident methods of doing so, using ladders to
    climb over it. Further, we find that injuries from falling off a ladder are a likely result of attempting
    to cross the curved, angled dam gate by use of such ladders.
    ¶ 35        The final two factors of the duty test involve the magnitude of the burden of guarding against
    the injury and the consequences of placing that burden on the defendant. Bogenberger, 
    2018 IL 120951
    , ¶ 22. We find the magnitude of guarding against the injury to be slight and thus the
    consequences of placing that burden on the defendant to be unsubstantial. It may well be that the
    injury could have been guarded against by clearer warnings or direction to the subcontractors about
    the appropriate methods for their employees to cross the gate or access the platform’s south side.
    Also, the evidence suggests that the gate could simply be lowered from its upright position to
    enable easier passage. The evidence also shows that the defendant employed carpenters on its staff
    who were capable of constructing a structure to enable workers to safely cross over the gate.
    ¶ 36        For these reasons, we hold that application of the four factors of the duty test weigh in favor
    of the conclusion that the defendant owed the plaintiff a duty of care under a premises liability
    theory of negligence.
    ¶ 37                           2. Section 414 of the Restatement (Second) of Torts
    ¶ 38        In addition to any duty owed under a premises liability theory, the plaintiff argues that a duty
    should also be imposed on the defendant based on its “retained control” over the job site under
    section 414 of the Restatement (Second) of Torts. Section 414, which has been recognized as an
    accurate statement of Illinois law (see Carney, 
    2016 IL 118984
    , ¶ 35), provides as follows:
    “One who entrusts work to an independent contractor, but who retains control of any
    part of the work, is subject to liability for physical harm to others for whose safety the
    employer owes a duty to exercise reasonable care, which is caused by his failure to exercise
    - 17 -
    No. 1-21-1581
    his control with reasonable care.” Restatement (Second) of Torts § 414, at 387 (1965).
    This rule serves as a basis only for imposing direct liability on the party employing an independent
    contractor for its own negligence, not for imposing vicarious liability for the negligence of an
    independent contractor. Carney, 
    2016 IL 118984
    , ¶ 36.
    ¶ 39        In determining whether section 414 applies, the inquiry involves the level of a defendant’s
    “retained control” over the work of an independent contractor. Comment a to section 414 indicates
    that a defendant can be subject to liability under this section if it retains “supervisory control,” i.e.,
    “the power to direct the order in which the work shall be done, or to forbid its being done in a
    manner likely to be dangerous to himself or others.” Restatement (Second) of Torts § 414, cmt. a,
    at 387 (1965). Comment c to section 414 explains further:
    “ In order for the rule stated in this Section to apply, the employer must have retained
    at least some degree of control over the manner in which the work is done. It is not enough
    that he has merely a general right to order the work stopped or resumed, to inspect its
    progress or to receive reports, to make suggestions or recommendations which need not
    necessarily be followed, or to prescribe alterations and deviations. Such a general right is
    usually reserved to employers, but it does not mean that the contractor is controlled as to
    his methods of work, or as to operative detail. There must be such a retention of a right of
    supervision that the contractor is not entirely free to do the work in his own way.”
    Restatement (Second) of Torts § 414, cmt. c, at 388 (1965).
    ¶ 40        Consistent with these provisions, a general right to enforce safety does not amount to retained
    control under section 414. Carney, 
    2016 IL 118984
    , ¶ 47. Further, the existence of a safety
    program, safety manual, or safety director is insufficient to trigger liability. Madden, 395 Ill. App.
    3d at 382. Rather, the evidence must show such a retention of the right of supervision that the
    - 18 -
    No. 1-21-1581
    independent contractor is “ ‘not entirely free to do the work in his own way.’ ” Id. (quoting
    Restatement (Second) of Torts § 414, cmt. c, at 388 (1965)). Whether an employing defendant has
    retained sufficient control over an independent contractor’s work may be decided as a matter of
    law where the evidence is insufficient to create a fact question. Carney, 
    2016 IL 118984
    , ¶ 41. The
    best indicator of whether the employing defendant retained control sufficient to trigger liability
    under section 414 is the written contract between the employing defendant and the independent
    contractor. 
    Id.
     However, even if the contract does not provide evidence of retained control, such
    control may still be demonstrated by evidence of the employing defendant’s conduct at variance
    with the agreement. 
    Id.
    ¶ 41        The plaintiff argues first that the subcontract between the defendant and Lyons, which
    incorporates the prime contract between the defendant and the Village, contains sufficient evidence
    that defendant retained control over Lyons’ work on the project. The plaintiff then goes on to cite
    and discuss many provisions of the subcontract and prime contract which, according to the
    plaintiff, amount to retained control. We need not belabor these provisions at length, as we have
    reviewed them and agree with the defendant that they do not rise to the level of showing retained
    control by the defendant over Lyons’ work. Most of the provisions cited by the plaintiff are
    completely inapposite to the issue of retained control. Importantly, no provision appears to address
    whether the defendant retained control over the aspect of Lyons’ work at issue, that being the
    ability of Lyons’ employees to access the areas of the job site where electrical work was to be
    performed. Instead, the subcontract provisions most closely on point place the responsibility on
    Lyons to furnish whatever equipment, services, tools, scaffolds, or other facilities were necessary
    to ensure its work could be fully performed. Specifically, the subcontract obligates Lyons to
    “furnish all of the *** equipment and services, including, but not limited to, *** tools and
    - 19 -
    No. 1-21-1581
    scaffoldings as are necessary for the proper performance of the Subcontractor’s Work.” It also
    obligates Lyons to “furnish all temporary services and/or facilities necessary to perform its work.”
    It provides that Lyons’ employees may not use the defendant’s equipment without express written
    permission from a representative of the defendant. Nothing about these provisions shows that the
    defendant retained control over Lyons’ work or that it was not free to do the work in its own way.
    ¶ 42        The plaintiff cites contract provisions requiring the defendant to conform to the standards of
    OSHA, requiring compliance by Lyons with the defendant’s safety program, and requiring Lyons’
    involvement in a pre-activity meeting to identify issues such as safety procedures and scaffolding.
    However, the plaintiff cites no evidence concerning the defendant’s safety program or what the
    defendant discussed at any pre-activity meeting. In any event, contract provisions requiring
    compliance with OSHA regulations do not create a duty of care under section 414, and the
    existence of a safety program, safety manual, or safety director also does not constitute retained
    control. Lee v. Six Flags Theme Parks, Inc., 
    2014 IL App (1st) 130771
    , ¶ 77; Madden, 395 Ill.
    App. 3d at 382. The plaintiff also cites provisions pertaining to the defendant’s coordination of
    Lyons’ work with that of the other subcontractors and requiring Lyons to follow the defendant’s
    instructions, orders, and directions. However, our review of these provisions again indicates that
    they involve only “general rights reserved to someone, like defendant, who employs a contractor,
    rather than evidence that defendant retained control over the manner in which work by [Lyons]
    was performed.” Carney, 
    2016 IL 118984
    , ¶ 46. Accordingly, we find no evidence of retained
    control within the contracts.
    ¶ 43        The plaintiff also argues that, apart from the contract language, the defendant’s retained
    control over the work of its subcontractors can be shown by the defendant’s conduct on the jobsite.
    Specifically, the plaintiff argues, the defendant’s conduct shows that it was responsible for safe
    - 20 -
    No. 1-21-1581
    access on the jobsite, particularly across the dam gate. First, the plaintiff cites evidence that the
    defendant had constructed a wooden handrail to assist workers on the site with negotiating the
    steep slope of the gravel ramp running from the road above to the platform where the dam gate
    was located. Second, the plaintiff cites the fact that, on the day after the plaintiff’s fall, the
    defendant’s carpenters constructed a wooden platform over the dam gate. McLaughlin testified
    that he thereafter used the platform to cross the gate, but he could not recall if the defendant had
    told him that he could use it.
    ¶ 44        Even assuming that the defendant’s post-occurrence construction of the platform is
    admissible evidence, we find that the defendant’s conduct on which the plaintiff relies is
    insufficient to demonstrate that it “retained control” of independent contractors’ work. We see no
    evidence of any conduct by the defendant that prevented the Lyons employees from being entirely
    free to do the work on their own way. This includes accessing the south side of the platform. The
    evidence indicates that the defendant retained no control over how the Lyons’ electricians reached
    the south side of the platform, and instead it placed all responsibility for accessing it on Lyons.
    Although we find that this hands-off approach by the defendant is part of what made an injury like
    the plaintiff’s reasonably foreseeable, it does not demonstrate retained control for purposes of
    section 414. Accordingly, the trial court properly determined that the defendant did not owe a duty
    of care under section 414 of the Restatement (Second) of Torts.
    ¶ 45                                         B. Proximate causation
    ¶ 46        The trial court also found no evidence of proximate cause between any alleged negligence by
    the defendant and the injuries suffered by the plaintiff. It found that the gate was a “condition”
    rather than the “cause” of the incident in which the plaintiff was injured, with the cause being “his
    decision to create and implement his ladder set-up idea to transfer himself to and from side to side
    - 21 -
    No. 1-21-1581
    of the dam gate.” The court also found no evidence of foreseeability to satisfy the “legal cause”
    aspect of proximate cause.
    ¶ 47        The plaintiff argues that the trial court erred in its analysis and conclusion. The plaintiff
    argues that the analysis of whether a defendant’s alleged negligence is a “condition” and not a
    “cause” of a plaintiff’s injury is inapplicable because this case does not involve evidence of an
    intervening act by a third party. The plaintiff also argues that his conduct in using ladders to cross
    the dam gate was foreseeable to the defendant and that the extent to which he was at fault for
    causing his own injuries is a question of fact about which reasonable minds could differ.
    ¶ 48        It is a fundamental principle of law that an injury may have more than one proximate cause.
    Espinoza v. Elgin, Joliet & Eastern Ry. Co., 
    165 Ill. 2d 107
    , 118 (1995). A defendant is liable for
    its negligent conduct whether it contributed in whole or in part to the plaintiff’s injury, as long as
    proximate cause exists. Guo v. Kamal, 
    2020 IL App (1st) 190090
    , ¶ 23. To establish proximate
    cause, the defendant’s conduct must be shown to be an actual cause of the plaintiff’s injury, as
    well as a legal cause of it. Simmons v. Garces, 
    198 Ill. 2d 541
    , 558 (2002). Actual cause (also
    referred to as cause in fact) is established where “there is a reasonable certainty that a defendant’s
    acts caused the injury or damage.” 
    Id.
     (quoting Lee v. Chicago Transit Authority, 
    152 Ill. 2d 432
    ,
    455 (1992)). A defendant’s conduct is a cause in fact of the plaintiff’s injury only if that conduct
    is a material element and a substantial factor in bringing about the injury. First Springfield Bank
    & Trust v. Galman, 
    188 Ill. 2d 252
    , 258 (1999) (citing Lee, 
    152 Ill. 2d at 455
    ). A defendant’s
    conduct is a material element and a substantial factor in bringing about an injury if, absent that
    conduct, the injury would not have occurred. 
    Id.
     Legal cause, by contrast, involves an assessment
    of foreseeability. Steed v. Rezin Orthopedics & Sports Medicine, S.C., 
    2021 IL 125150
    , ¶ 37. Legal
    cause is established where the injury is the type of injury that a reasonable person would see as a
    - 22 -
    No. 1-21-1581
    “likely result” of his conduct and is not established where the injury is so “highly extraordinary”
    that imposing liability is not justified. 
    Id.
     Proximate cause is generally a question of fact, but its
    absence may be determined as a matter of law where the evidence fails to sufficiently demonstrate
    both cause in fact and legal cause. Young v. Bryco Arms, 
    213 Ill. 2d 433
    , 447 (2004).
    ¶ 49        As the trial court’s ruling indicates, courts analyzing proximate cause have also used the
    vocabulary of asking “whether the defendant’s conduct was a cause of the injury or simply
    furnished a condition by which the injury was made possible.” (Emphases added). See Galman,
    
    188 Ill. 2d at 259
    . In Galman, the supreme court clarified that an inquiry using these terms is “in
    effect asking whether the defendant’s conduct was a material and substantial element in bringing
    about the injury.” 
    Id.
     Thus, the trial court’s ruling was effectively a finding that the dam gate was
    not a material and substantial element in bringing about the plaintiff’s injury. We agree with the
    plaintiff that the trial court erred in this ruling. Reasonable minds could differ about whether the
    plaintiff’s injuries would have occurred absent the gate being in place with no means of access to
    the south side of the platform, as the plaintiff would have had no reason to use ladders to reach the
    area where he needed to work. By determining that the sole cause of the plaintiff’s injury was his
    own conduct in using ladders to cross the gate, the trial court essentially resolved a disputed issue
    of fact. As stated above, an injury may have more than one proximate cause, and whether the
    defendant’s negligence was a proximate cause of the plaintiff’s injury here is a question for the
    trier of fact. Accordingly, the trial court erred in its analysis of actual cause.
    ¶ 50        We also find that legal cause is present in this case. Our discussion on duty above illustrates
    that the plaintiff was the type of person to whom the defendant should reasonably have foreseen
    injury, i.e., a worker injured attempting to cross the dam gate using ladders. We similarly find that
    the injuries the plaintiff apparently suffered are a likely result of falling while attempting to cross
    - 23 -
    No. 1-21-1581
    the gate and thus also foreseeable as a result of the defendant’s conduct. Nothing about the
    concussion and orthopedic-type injuries apparently suffered by the plaintiff is so “highly
    extraordinary” that imposing liability would be unjustified.
    ¶ 51        We reject the defendant’s comparison of this case to Cannon v. Commonwealth Edison Co.,
    
    250 Ill. App. 3d 379
     (1993). There, the plaintiff was seriously injured during a power outage when
    he fell while descending stairs to his basement in an attempt to ascertain the cause of the loss of
    power to his home. 
    Id. at 380
    . He then sued Commonwealth Edison, alleging that its failure to
    maintain its equipment was a proximate cause of his injuries. 
    Id. at 380-81
    . This court affirmed
    dismissal of the plaintiff’s complaint on the grounds that no facts could be established showing
    proximate cause. The court found that it would impose an “insuperable burden” on Commonwealth
    Edison to “foresee every accident that may arise every time electric power is lost,” as no amount
    of foresight would have permitted it to take reasonable steps to prevent what occurred in that case.
    
    Id. at 385
    . It held as a matter of law that the blackout occasioned by the defendant’s conduct was
    condition that made the plaintiff’s fall possible, but it was not a proximate cause where the
    plaintiff’s own actions of walking down the stairs served as a superseding cause. 
    Id.
    ¶ 52        Cannon is simply inapposite. In Cannon, the plaintiff’s injuries from falling down the stairs
    during a power outage bore only a tenuous connection to Commonwealth Edison’s alleged
    negligence in failing to maintain its equipment. In this case, the connection between the
    defendant’s alleged negligence and the plaintiff’s injuries is far closer. Thus, unlike in Cannon,
    we cannot say as a matter of law that the plaintiff’s injury was unforeseeable or that the that dam
    was a condition and not a proximate cause of the plaintiff’s injury. A genuine issue of material fact
    exists as to proximate causation in this case, and we therefore reverse the trial court’s ruling on the
    element of proximate cause.
    - 24 -
    No. 1-21-1581
    ¶ 53                                         III. CONCLUSION
    ¶ 54        For the foregoing reasons, we reverse the trial court’s granting of summary judgment in favor
    of the defendant and remand the cause for further proceedings.
    ¶ 55        Reversed and remanded.
    - 25 -