Sunrise Resort Association Inc v. Cheboygan County Road Commission ( 2023 )


Menu:
  •                                                                                      Michigan Supreme Court
    Lansing, Michigan
    Syllabus
    Chief Justice:             Justices:
    Elizabeth T. Clement      Brian K. Zahra
    David F. Viviano
    Richard H. Bernstein
    Megan K. Cavanagh
    Elizabeth M. Welch
    Kyra H. Bolden
    This syllabus constitutes no part of the opinion of the Court but has been              Reporter of Decisions:
    prepared by the Reporter of Decisions for the convenience of the reader.                Kathryn L. Loomis
    SUNRISE RESORT ASSOCIATION, INC v CHEBOYGAN COUNTY ROAD COMMISSION
    Docket No. 163949. Argued on application for leave to appeal May 10, 2023. Decided
    July 24, 2023.
    Sunrise Resort Association, Inc., Gregory P. Somers, and others brought an action in the
    Cheboygan Circuit Court against the Cheboygan County Road Commission asserting a statutory
    claim under the sewage-disposal-system-event (SDSE) exception, MCL 691.1416 through MCL
    691.1419, to governmental immunity provided by the governmental tort liability act (GTLA),
    MCL 691.1401 et seq.; asserting a gross-negligence claim; and requesting injunctive relief for a
    common-law claim of trespass-nuisance. Plaintiffs owned real property along West Burt Lake
    Road in Cheboygan County. In 2013, a bicycle trail was constructed on the west side of that road,
    necessitating modifications by defendant to the drainage system. Defendant modified the drainage
    system again in 2015 after the bicycle trail washed out in 2014. In 2015, Sunrise Resort informed
    defendant that those modifications had caused minor damage to plaintiffs’ properties and that more
    severe damage would likely result if the system was not fixed. In May 2018, plaintiffs’ properties
    were damaged by an overflow and backup of the drainage system. Plaintiffs filed the instant action
    in February 2020, seeking monetary damages as well as injunctive relief to abate the alleged
    ongoing trespass or nuisance. Defendant moved for summary disposition under MCR 2.116(C)(7),
    arguing that plaintiffs’ SDSE claim was barred by the relevant three-year statutory period of
    limitations and by plaintiffs’ failure to provide timely notice of their claim as required by MCL
    691.1419(1). Plaintiffs asserted that their action was timely because the limitations period began
    running following the 2018 event, which was the basis of their claim, not the 2015 event; however,
    plaintiffs conceded that their gross-negligence claim was barred by governmental immunity, and
    that claim was dismissed. The court, Aaron J. Gauthier, J., granted defendant summary disposition
    on the remaining claims, concluding that (1) plaintiffs’ claims accrued in 2015 and the claims were
    therefore not timely, (2) the request for injunctive relief was not a separate cause of action and
    could not be premised on untimely claims, and (3) injunctive relief was not available under MCL
    691.1417(2). Plaintiffs appealed. In a published opinion, the Court of Appeals, RONAYNE
    KRAUSE, P.J., and CAMERON and RICK, JJ., reversed the trial court order and remanded for further
    proceedings. 
    339 Mich App 440
     (2021). In doing so, the Court of Appeals concluded that (1) both
    the statutory SDSE claim and the common-law trespass-nuisance claim were timely because the
    claims did not accrue until 2018 and (2) injunctive relief was broadly available under the SDSE
    exception. Defendant sought leave to appeal the Court of Appeals judgment. The Supreme Court
    ordered and heard oral argument on whether to grant defendant’s application for leave to appeal
    or take other action. 
    509 Mich 983
     (2022).
    In a unanimous opinion by Chief Justice CLEMENT, the Supreme Court, in lieu of granting
    leave to appeal, held:
    Plaintiffs’ SDSE claim was timely under MCL 600.5805(1) and (2). However, MCL
    691.1417(2), the SDSE exception to governmental immunity, abrogates all common-law
    exceptions to governmental immunity for damages resulting from the overflow or backup of a
    sewage disposal system, including the common-law claim for trespass-nuisance; accordingly,
    plaintiffs’ trespass-nuisance claim arising from the 2018 SDSE had to be dismissed. The Court of
    Appeals’ conclusion that plaintiffs could seek an injunction in connection with their common-law
    trespass-nuisance claim was reversed because plaintiffs only sought that relief in connection with
    the abrogated trespass-nuisance claim. Trial court order reversed in part and affirmed in part;
    Court of Appeals judgment vacated in part; and case remanded to the trial court for further
    proceedings.
    1. MCL 691.1417(2) provides that a governmental agency is immune from tort liability
    for the overflow or backup of a sewage disposal system unless the overflow or backup is an SDSE
    as that term is defined by the act and the governmental agency is an appropriate governmental
    agency. To recover compensation for the property damage or physical injury caused by an SDSE,
    MCL 691.1417(3) requires a plaintiff to show that the following existed at the time of the event:
    (1) the governmental agency was an appropriate governmental agency, (2) the sewage disposal
    system had a defect, (3) the governmental agency knew, or in the exercise of reasonable diligence
    should have known, about the defect, (4) the governmental agency, having the legal authority to
    do so, failed to take reasonable steps in a reasonable amount of time to repair, correct, or remedy,
    the defect, and (5) the defect was a substantial proximate cause of the event and the property
    damage or physical injury. Each SDSE, as defined by MCL 691.1416(k), may give rise to an
    independent cause of action for which the government may be liable if the elements in MCL
    691.1417(3) can be established with regard to that particular event.
    2. Claims under the GTLA are subject to the general laws respecting limitations of actions.
    Relevant here, under MCL 600.5805(1) and (2), the statutory period of limitation for claims
    brought under the SDSE exception is three years. MCL 600.5827 provides that the period of
    limitations runs from the time the claim accrues, which occurs when the wrong upon which the
    claim is based was done regardless of the time when damage results. A claim accrues for purposes
    of MCL 600.5827 when all the elements of the cause of action have occurred and can be alleged
    in a proper complaint. Stated differently, accrual occurs when the wrong is done, i.e., the moment
    when the plaintiff is harmed rather than when the defendant acted. In this case, while MCL
    691.1417(3) carves out several exceptions under which such an overflow or backup does not
    constitute an SDSE, none of those exceptions applied here. Taking plaintiffs’ allegations in their
    complaint as true, they sought only to recover for damages caused by the 2018 overflow or backup
    event. Indeed, while they referred in the factual section of their complaint to the alleged minor
    flooding in 2015, they argue in Count I that the 2018 flooding constituted an “event” for purposes
    of MCL 691.1417(3). Accordingly, because plaintiffs’ SDSE claim was filed in February 2020,
    the complaint was timely filed within the three-year limitations period. The trial court therefore
    erred by dismissing plaintiffs’ claim on statute-of-limitations grounds. Contrary to defendant’s
    assertion, plaintiffs did not rely on the now-abrogated continuing-wrongs doctrine—under which
    the period of limitations would not run until a wrong was abated when the defendant’s wrongful
    acts were of a continuing nature—to support their claim. The continuing-wrongs doctrine was not
    relevant to plaintiffs’ claim for relief because their amended complaint, brought under the SDSE
    exception, alleged harm caused by a discrete 2018 SDSE, and plaintiffs did not seek to reach back
    and recover for any potential harms that may have occurred before that date.
    3. Michigan caselaw recognized a trespass-nuisance exception to governmental immunity
    before the GTLA was enacted. MCL 691.1417(2), however, states that the SDSE exception
    abrogates common-law exceptions, if any, to immunity for the overflow or backup of a sewage
    disposal system and provides the sole remedy for obtaining any form of relief for damages or
    physical injuries caused by an SDSE regardless of the legal theory. Given this language, the SDSE
    exception clearly abrogates common-law exceptions to immunity when a plaintiff alleges there
    has been an overflow or backup of a sewage disposal system. For that reason, the common-law
    trespass-nuisance exception to governmental immunity was abrogated by MCL 691.1417(2).
    Plaintiffs’ common-law trespass-nuisance claim, which alleged that there was an overflow or
    backup of a sewage disposal system onto their property, was abrogated by MCL 691.1417(2). As
    a result, defendant was immune from that claim, and it had to be dismissed. Further, plaintiffs
    could not seek injunctive relief because the request was tied expressly to the abrogated trespass-
    nuisance claim. Accordingly, the question whether injunctive relief is available for a properly pled
    SDSE claim was reserved for the future. The Court of Appeals erred by concluding that plaintiffs’
    claim for injunctive relief was permitted by 691.1417(2) and not prohibited by the elimination of
    the trespass-nuisance exception to governmental immunity. The Court of Appeals holding that the
    plaintiffs’ trespass-nuisance claim was timely was vacated as unnecessary given that the claim was
    abrogated by MCL 691.1417(2).
    Trial court order granting summary disposition to defendant of plaintiffs’ SDSE claim
    reversed; trial court order granting summary disposition to defendant of plaintiffs’ common-law
    trespass-nuisance claim affirmed; Court of Appeals’ holding that plaintiffs’ trespass-nuisance
    claim was timely vacated; and case remanded to the trial court for further proceedings.
    Michigan Supreme Court
    Lansing, Michigan
    OPINION
    Chief Justice:                Justices:
    Elizabeth T. Clement         Brian K. Zahra
    David F. Viviano
    Richard H. Bernstein
    Megan K. Cavanagh
    Elizabeth M. Welch
    Kyra H. Bolden
    FILED July 24, 2023
    STATE OF MICHIGAN
    SUPREME COURT
    SUNRISE RESORT ASSOCIATION, INC.,
    GREGORY P. SOMERS, MELISSA L.
    SOMERS, and KARL BERAKOVICH,
    Plaintiffs-Appellees,
    v                                                                No. 163949
    CHEBOYGAN COUNTY ROAD
    COMMISSION,
    Defendant-Appellant.
    BEFORE THE ENTIRE BENCH
    CLEMENT, C.J.
    The plaintiffs brought this action after the defendant modified a storm water
    drainage system, allegedly causing flooding onto their property. The plaintiffs raised two
    distinct claims that remain at issue on appeal: a claim under the sewage-disposal-system-
    event (SDSE) exception to governmental immunity under the governmental tort liability
    act (GTLA), MCL 691.1401 et seq., and a common-law trespass-nuisance claim seeking
    injunctive relief.
    The trial court dismissed both claims as untimely under the applicable three-year
    statute of limitations. Like the Court of Appeals, we disagree and hold that the SDSE
    claim, which seeks relief only in connection with flooding that occurred within the three-
    year window, was timely. However, unlike the Court of Appeals, we conclude that because
    the defendant is immune with respect to the plaintiffs’ common-law trespass-nuisance
    claim, that claim was properly dismissed. In light of this holding, we vacate as unnecessary
    the Court of Appeals’ holding that the trespass-nuisance claim was timely. Finally, because
    the plaintiffs only seek injunctive relief in connection with that claim, their request for an
    injunction is invalid. Therefore, we reverse the trial court’s grant of summary disposition
    to the defendant with respect to the plaintiff’s SDSE claim, affirm with respect to the
    common-law trespass-nuisance claim, and remand for further proceedings consistent with
    this opinion.
    I. FACTS AND PROCEDURAL HISTORY
    The plaintiffs 1 are a group of landowners who own property on West Burt Lake
    Road. In 2020, they initiated this lawsuit against the defendant, the Cheboygan County
    Road Commission. In their amended complaint, the plaintiffs alleged that the defendant
    oversees a storm water drainage system that directs water through a series of ditches and
    culverts, some of which pass through the plaintiffs’ respective properties. In 2013, when
    1
    Sunrise Resort Association, Inc., Gregory P. Somers, Melissa L. Somers, and Karl
    Berakovich.
    2
    a bicycle path was constructed along West Burt Lake Road, the defendant modified the
    drainage system. In 2015, after the bicycle path was washed out, the defendant modified
    the drainage system again to prevent another washout.             Thereafter, Sunrise Resort
    Association, Inc., contacted the defendant to explain that it had suffered “minor damage”
    from these modifications and that more severe damage would likely result if the drainage
    system was not fixed. Then, in 2018, the plaintiffs’ properties sustained significant damage
    by way of erosion caused by an overflow and backup of the defendant’s storm water
    drainage system.
    In their amended complaint, the plaintiffs raised three counts. First, they brought a
    claim under MCL 691.1417(3) of the SDSE exception to the GTLA. Under this claim, the
    complaint stated that the “overflow and backup referenced previously in this complaint”—
    i.e., the 2018 overflow and backup—“was an ‘event’ as defined by MCL 691.1416(k).”
    The SDSE claim does not directly refer to the alleged minor flooding that occurred
    sometime around 2015.
    Second, the plaintiffs brought a gross-negligence claim. Because they conceded in
    the trial court that this claim was barred by governmental immunity, it is not at issue on
    appeal, and we will discuss it no further.
    And third, the plaintiffs brought a claim for injunctive relief to abate an ongoing
    trespass-nuisance. The complaint states that because the ongoing nuisance “cannot be
    remedied by money damages alone,” it can “only be remedied by injunctive relief . . . .”
    In their prayer for relief, the plaintiffs request both money damages and injunctive relief,
    but they expressly tie their request for injunctive relief to the trespass-nuisance claim alone.
    3
    In response to the plaintiffs’ amended complaint, the defendant moved for summary
    disposition under MCR 2.116(C)(7). It argued first that the SDSE claim was untimely
    under the applicable three-year statute of limitations. See MCL 600.5805(2). And second,
    it argued that the plaintiffs’ claim for injunctive relief to abate an ongoing trespass-nuisance
    must be dismissed because injunctive relief is categorically unavailable under the SDSE
    exception to the GTLA.
    Following a hearing, the trial court granted summary disposition under MCR
    2.116(C)(7) to the defendant. It held that the plaintiffs’ SDSE claim began to accrue in
    2015, when the minor flooding occurred and that, therefore, the claim was not timely under
    the three-year statute of limitations. Next, it held that the plaintiffs’ claim for injunctive
    relief failed for two reasons. First, it was also untimely. And second, because the SDSE
    exception abrogated the common-law trespass-nuisance exception to governmental
    immunity, the defendant was immune with respect to the claim.
    On appeal, the Court of Appeals reversed and remanded for further proceedings.
    Sunrise Resort Ass’n, Inc v Cheboygan Co Rd Comm, 
    339 Mich App 440
    ; 
    983 NW2d 436
    (2021). The Court of Appeals held that both the plaintiffs’ SDSE claim and common-law
    claim were timely. The panel reasoned that the claims did not accrue until 2018, when the
    overflow and backup occurred and that, therefore, the claims fell within the applicable
    statutory limitations period. 
    Id. at 451
    . It also concluded that injunctive relief was broadly
    available under the SDSE exception to avoid future harm rather than remedy past harms.
    
    Id. at 456-457
    . For those reasons, the panel concluded that the trial court erred by granting
    summary disposition with respect to both the SDSE claim and the common-law claim.
    4
    The defendant then sought leave to appeal in this Court, and we ordered oral
    argument on the application to address:
    (1) [W]hether the [plaintiffs’] claims accrued in 2015 and are barred by the
    applicable statute of limitations; and (2) whether the [plaintiffs’] claim for
    injunctive relief is barred by the Government Tort Liability Act, MCL
    691.1401 et seq., and/or other applicable law, or is otherwise not obtainable
    as the functional equivalent of a claim for a writ of mandamus. [Sunrise
    Resort Ass’n, Inc v Cheboygan Co Rd Comm, 
    509 Mich 983
    , 984 (2022).]
    We now affirm the Court of Appeals’ conclusion that the plaintiffs’ SDSE claim
    was timely and not barred by the applicable three-year statute of limitations. However, we
    reverse its conclusion that injunctive relief was available to the plaintiffs. We hold that the
    common-law exception to immunity for trespass-nuisance claims was abrogated by the
    Legislature’s passage of the SDSE exception to the GTLA. MCL 691.1417(2). Because
    the plaintiffs only sought injunctive relief in connection with a claim from which the
    defendant is immune, we hold that the request for an injunction is invalid. Therefore, we
    reverse the trial court’s grant of summary disposition with respect to the SDSE claim
    because it is timely. But we affirm the trial court’s grant of summary disposition with
    respect to the common-law claim because the defendant is immune from it.
    II. LEGAL BACKGROUND
    A. STANDARD OF REVIEW
    The defendant moved for summary disposition under MCR 2.116(C)(7), which
    allows for “dismissal of the action” because of “immunity granted by law or statute of
    limitations . . . .” We review de novo a trial court’s decision on a motion for summary
    disposition. Maiden v Rozwood, 
    461 Mich 109
    , 118; 
    597 NW2d 817
     (1999). When a party
    brings a motion for summary disposition under MCR 2.116(C)(7), “[t]he contents of the
    5
    complaint are accepted as true unless contradicted by the documentation submitted by the
    movant.” 
    Id. at 119
    . For purposes of this appeal, the defendant concedes that the facts in
    the plaintiffs’ amended complaint are accepted as true.
    We also review de novo questions of statutory interpretation. Madugula v Taub,
    
    496 Mich 685
    , 695; 
    853 NW2d 75
     (2014). The goal of statutory interpretation is to
    effectuate the intent of the Legislature. Id. at 696. To do so, we “focus[] first on the
    statute’s plain language” and “examine the statute as a whole, reading individual words
    and phrases in the context of the entire legislative scheme.” Id. (citations and quotation
    marks omitted). “When a statute’s language is unambiguous, the Legislature must have
    intended the meaning clearly expressed, and the statute must be enforced as written.” Id.
    (citations and quotation marks omitted).
    B. THE SDSE EXCEPTION TO THE GTLA
    The GTLA established a general rule that a “governmental agency is immune from
    tort liability if the government agency is engaged in the exercise or discharge of a
    governmental function.” MCL 691.1407(1). This Court has explained that “the immunity
    conferred upon governmental agencies is broad, and the statutory exceptions thereto are to
    be narrowly construed.” Nawrocki v Macomb Co Rd Comm, 
    463 Mich 143
    , 158; 
    615 NW2d 702
     (2000).
    In 2002, the Legislature passed the SDSE exception to the GTLA. MCL 691.1416
    through MCL 691.1419. Under the SDSE exception:
    A governmental agency is immune from tort liability for the overflow
    or backup of a sewage disposal system unless the overflow or backup is a
    sewage disposal system event and the governmental agency is an appropriate
    governmental agency. [MCL 691.1417(2).]
    6
    In short, the SDSE exception immunizes governmental agencies unless (1) there is
    a sewage disposal system event and (2) the governmental agency is an appropriate
    governmental agency. The statute defines a “sewage disposal system event” to mean “the
    overflow or backup of a sewage disposal system onto real property.” MCL 691.1416(k).
    While the statute carves out several exceptions under which such an overflow or backup
    will not constitute a “sewage disposal system event,” accepting the allegations in the
    plaintiffs’ complaint as true, none of the exceptions applies here. 
    Id.
     Similarly, accepting
    the allegations as true, the defendant constitutes an “appropriate governmental agency”
    under the statutory definition. MCL 691.1416(b).
    The SDSE statute also specifies the required showing that a plaintiff must make
    when seeking “compensation for the property damage or physical injury” caused by an
    “event.” MCL 691.1417(3). A plaintiff must “show[] that all of the following existed at
    the time of the event:”
    (a) The governmental agency was an appropriate governmental
    agency.
    (b) The sewage disposal system had a defect.
    (c) The governmental agency knew, or in the exercise of reasonable
    diligence should have known, about the defect.
    (d) The governmental agency, having the legal authority to do so,
    failed to take reasonable steps in a reasonable amount of time to repair,
    correct, or remedy the defect.
    (e) The defect was a substantial proximate cause of the event and the
    property damage or physical injury. [Id.]
    Therefore, even if a plaintiff can avoid governmental immunity by showing there
    was a “sewage disposal system event” from a sewage disposal system overseen by an
    7
    “appropriate governmental agency,” they must still provide additional proof to recover
    compensation through the SDSE exception’s statutory cause of action under § 1417(3).
    MCL 691.1417(2) and (3).
    III. THE TIMELINESS OF THE PLAINTIFFS’ SDSE CLAIM
    A. THE STATUTE OF LIMITATIONS UNDER THE SDSE EXCEPTION
    Under the GTLA, “[e]very claim against any government agency shall be subject to
    the general law respecting limitations of actions . . . .” MCL 691.1411(1). This provision
    applies to claims brought under the SDSE exception to the GTLA. The applicable statutory
    period of limitations here is three years. MCL 600.5805(1) and (2). Under MCL 600.5827,
    “the period of limitations runs from the time the claim accrues.” “[T]he claim accrues at
    the time the wrong upon which the claim is based was done regardless of the time when
    damage results.” Id.
    We have explained that the claim “accrues” under MCL 600.5827 “when all of the
    elements of the cause of action have occurred and can be alleged in a proper complaint.”
    Connelly v Paul Ruddy’s Equip Repair & Serv Co, 
    388 Mich 146
    , 150; 
    200 NW2d 70
    (1972). Accrual occurs when the “wrong is done,” meaning the moment “when the
    plaintiff is harmed rather than when the defendant acted.” Trentadue v Buckler Automatic
    Lawn Sprinkler Co, 
    479 Mich 378
    , 388; 
    738 NW2d 664
     (2007) (quotation marks omitted),
    quoting Boyle v Gen Motors Corp, 
    468 Mich 226
    , 231 n 5; 
    661 NW2d 557
     (2003).
    B. THE PLAINTIFFS’ SDSE CLAIM ACCRUED IN 2018
    We agree with the Court of Appeals that because the plaintiffs’ SDSE claim did not
    accrue until 2018, they timely filed their complaint for that claim. Therefore, we agree that
    8
    the trial court erred by granting summary disposition under MCR 2.116(C)(7) on statute-
    of-limitations grounds. The Court of Appeals explained that a claim “ ‘accrues when all
    of the elements of the cause of action have occurred and can be alleged in a proper
    complaint,’ ” and that a claim under § 1417(3) of the SDSE exception requires an
    “ ‘overflow or backup’ ” of a sewage system onto property. Sunrise Resort, 339 Mich App
    at 450-451, quoting Connelly, 
    388 Mich at 150
    , and MCL 691.1416(k). The panel
    concluded that “[a] plain reading of plaintiffs’ complaint shows that it is premised on a
    specific, discrete backup event” in 2018, and that “plaintiffs are seeking to recover for
    damages that occurred only on that occasion.” Sunrise Resort, 339 Mich at 451. Therefore,
    the panel concluded, the claim did not accrue until 2018 and the complaint was timely filed.
    We agree that the plaintiffs’ amended complaint, on its face, only seeks to recover
    for damage caused by the 2018 overflow or backup event. Each “sewage disposal system
    event,” as defined by MCL 691.1416(k), may give rise to an independent cause of action
    for which the government may be liable under the SDSE exception if the remaining
    elements in MCL 691.1417(3) can be established in relation to that particular “event.” See
    Connelly, 
    388 Mich at 150
     (stating that a claim accrues “when all of the elements of the
    cause of action have occurred and can be alleged in a proper complaint”). 2 While the
    plaintiffs refer to the alleged “minor flooding” that occurred in 2015 in the factual section
    of their complaint, in the section labeled “COUNT I. CLAIM PURSUANT TO MCL
    2
    That distinguishes this cause of action from one in which an isolated incident caused
    successive injuries that do not give rise to a new cause of action. Connelly, 
    388 Mich at 151
     (“Later damages may result [from an isolated negligent act], but they give rise to no
    new cause of action, nor does the statute of limitations begin to run anew as each item of
    damage is incurred.”).
    9
    691.1417(3),” they only argue that the “overflow and backup referenced previously in this
    complaint” constituted an “event” under § 1416(k) of the SDSE exception that would allow
    them to steer around governmental immunity and recover compensation. And the overflow
    and backup previously referred to in the complaint was clearly the 2018 flooding, not the
    2015 flooding. Because we must “look to plaintiff’s complaint to determine when the
    wrong upon which the claim is based was done,” here, the “wrong” was the event that
    occurred in 2018.    Therefore, the complaint was timely filed within the three-year
    limitations period. Fraser Twp v Haney, 
    509 Mich 18
    , 24; 
    983 NW2d 309
     (2022).
    We also agree with the Court of Appeals that, contrary to the defendant’s assertion,
    the plaintiffs are not attempting to rely on the now-abrogated continuing-wrongs doctrine.
    Sunrise Resort, 339 Mich App at 452; see also Garg v Macomb Co Community Mental
    Health Servs, 
    472 Mich 263
    , 266; 
    696 NW2d 646
     (2005). That doctrine provided that
    “[w]here a defendant’s wrongful acts are of a continuing nature, the period of limitations
    will not run until the wrong is abated . . . .” Horvath v Delida, 
    213 Mich App 620
    , 626-
    627; 
    540 NW2d 760
     (1995). As we recently explained, the continuing-wrongs doctrine
    provided plaintiffs a method to “reach back to recover for wrongs that occurred outside the
    statutory period of limitations” when there were distinctive wrongs within a continuing
    series. Haney, 509 Mich at 27.
    We agree with the Court of Appeals that the “abrogation of the continuing-wrongs
    doctrine means that plaintiffs are prohibited from relying on the harm caused by the 2018
    event to argue any claim based on the 2015 incident is timely” because they are a series of
    continuing harms. Sunrise Resort, 339 Mich App at 452-453. But the discontinuation of
    10
    the continuing-wrongs doctrine does not prevent the plaintiffs from recovering damages
    associated with the 2018 flooding.
    Haney is instructive here. In Haney, the defendants kept pigs on property zoned for
    commercial use. Haney, 509 Mich at 20-21. The plaintiffs sued, alleging that the piggery
    constituted a zoning violation and a nuisance, only resolvable through an injunction. Id. at
    21. As the defendant does here, the Haney defendants argued that the action was time-
    barred because the pig problems began outside the applicable six-year statute of limitations.
    Id. We disagreed. We noted that the “wrong alleged in plaintiff’s complaint [wa]s
    defendants’ keeping of hogs on their property,” which was a continuing problem and a
    violation of the zoning ordinance every day that the pigs remained. Id. at 25. While the
    wrong had begun long before the six-year limitations period passed, the plaintiffs did not
    seek a remedy for those long-past pig problems—rather, by seeking an injunction, the
    plaintiffs sought relief for “only present violations.” Id. at 21. This Court explained that
    when we abrogated the continuing-wrongs doctrine, we “simply held that a plaintiff may
    not recover for injuries that fall outside the statutory period of limitations.” Id. at 29,
    discussing Garg, 
    472 Mich at 282
    . We did not “immunize future wrongful conduct.”
    Haney, 509 Mich at 28, discussing Garg, 
    472 Mich 263
    . “[A] plaintiff’s failure to timely
    sue on the first violation in a series does not grant a defendant immunity to keep committing
    wrongful acts of the same nature.” Haney, 509 Mich at 28. Rather, “[a] plaintiff is free to
    bring a new action each time a defendant commits a new violation.” Id. at 28-29.
    The logic of Haney plainly applies here. While the plaintiffs seek monetary
    damages for the 2018 flooding, rather than an injunction, the distinction is irrelevant.
    Because the plaintiffs’ amended complaint alleges, under the SDSE exception, harm
    11
    caused by a discrete sewage disposal system event that occurred within the three-year
    limitations period, each event has the potential to be its own independent cause of action,
    and plaintiffs do not seek to reach back and recover for any potential harms that may have
    occurred before that date, the continuing-wrongs doctrine is inapplicable. A contrary
    holding would require plaintiffs to file SDSE claims at the first flooding or forever lose
    their leverage to urge the government to remedy defects in sewage disposal systems. This
    would be particularly puzzling considering that two required elements of an SDSE claim
    are that the governmental agency knew (or should have known) of the defect and it failed
    to take reasonable corrective actions within a reasonable period. MCL 691.1417(3)(c) and
    (d).
    For all these reasons, we affirm the Court of Appeals’ conclusion that the plaintiffs’
    SDSE claim was timely filed and reverse the trial court’s decision granting summary
    disposition to the defendant on statute-of-limitations grounds.
    IV. THE PLAINTIFFS’ REQUEST FOR INJUNCTIVE RELIEF
    A. ABROGATION OF THE COMMON LAW UNDER THE SDSE EXCEPTION
    We must now address the plaintiffs’ request for injunctive relief attached to their
    common-law trespass-nuisance claim. Before the enactment of the GTLA, there existed
    common-law immunity for government actors. In fact, there was a “long history in
    Michigan jurisprudence” of recognizing a trespass-nuisance exception to governmental
    immunity. Hadfield v Oakland Co Drain Comm’r, 
    430 Mich 139
    , 145; 
    422 NW2d 205
    (1988), overruled by Pohutski v Allen Park, 
    465 Mich 675
     (2002). Since the GTLA’s
    passage, courts have grappled with the intersection of the common-law rules of
    governmental immunity and the rules spelled out in the GTLA itself.
    12
    The SDSE exception to the GTLA contains an express provision concerning the
    abrogation of the common law that is integral to this case. It states:
    [The SDSE exception] abrogate[s] common law exceptions, if any, to
    immunity for the overflow or backup of a sewage disposal system and
    provide[s] the sole remedy for obtaining any form of relief for damages or
    physical injuries caused by a sewage disposal system event regardless of the
    legal theory. [MCL 691.1417(2).]
    The statutory language makes clear that the SDSE exception abrogates common-law
    exceptions to immunity that might apply under the facts of a particular case. It then goes
    on to clarify that when a plaintiff seeks “any form of relief for damages or physical
    injuries,” the SDSE exception provides the “sole remedy.” 
    Id.
    B. THE PLAINTIFFS CANNOT SEEK INJUNCTIVE RELIEF
    We hold that the trespass-nuisance exception to governmental immunity was
    abrogated by the plain language of § 1417(2) of the SDSE exception; therefore, defendant
    is immune from that claim, and it must be dismissed.
    “ ‘The Legislature may alter or abrogate common law through its legislative
    authority.’ ” McMaster v DTE Energy Co, 
    509 Mich 423
    , 433; 
    984 NW2d 91
     (2022),
    quoting Murphy v Inman, 
    509 Mich 132
    , 153; 
    983 NW2d 354
     (2022). But “[w]e will not
    lightly presume that the Legislature has abrogated the common law . . . .” McMaster, 509
    Mich at 434 (citations, quotation marks, and brackets omitted), quoting Murphy, 509 Mich
    at 153. “[T]he Legislature should speak in no uncertain terms when it exercises its
    authority to modify the common law.” McMaster, 509 Mich at 434 (quotation marks and
    citation omitted), quoting Murphy, 509 Mich at 153. Relevant here, § 1417(2) of the SDSE
    exception states clearly that the Legislature intended to “abrogate common law exceptions,
    13
    if any, to immunity for the overflow or backup of a sewage disposal system.” MCL
    691.1417(2). It is hard to imagine the Legislature speaking in more certain terms than it
    has in § 1417(2); the statutory language clearly abrogates any common-law exceptions to
    governmental immunity—including the trespass-nuisance exception—when a plaintiff
    alleges there has been an overflow or backup of a sewage disposal system.
    Because the plaintiffs’ amended complaint alleges that there was an overflow or
    backup of a sewage disposal system onto their property, they cannot maintain their
    trespass-nuisance claim. Stated differently, because § 1417(2) of the SDSE exception
    abrogated the trespass-nuisance exception to governmental immunity, the defendant is
    immune from this claim, and it must be dismissed. Accordingly, we also vacate as
    unnecessary the Court of Appeals’ holding that the plaintiffs’ trespass-nuisance claim was
    timely.
    In their prayer for relief, the plaintiffs sought injunctive relief only in connection
    with this now-abrogated common-law claim for trespass-nuisance. Because the request for
    injunctive relief is tied expressly to a claim that the plaintiffs cannot maintain, we hold that
    they cannot seek injunctive relief in this case. Therefore, we reverse the Court of Appeals
    contrary conclusion that the plaintiffs’ “claim for injunctive relief is permitted by MCL
    691.1417(2) and not prohibited by the elimination of the trespass-nuisance exception to
    governmental immunity . . . .” Sunrise Resort, 339 Mich at 454.
    The Court of Appeals focused on whether the SDSE exception barred the general
    ability to request an injunction to remedy an overflow or backup of a sewage disposal
    system. Id. at 457. We leave open the question of whether a plaintiff can seek injunctive
    relief in connection with an SDSE claim properly pled under § 1417(3) for a later date.
    14
    Our holding today is narrower. As applied to the plaintiffs’ amended complaint in this
    case, we hold that injunctive relief was unavailable because it was sought only in
    connection with a clearly abrogated common-law claim. For these reasons, we reverse the
    Court of Appeals’ conclusion that the plaintiffs could seek an injunction.
    V. CONCLUSION
    We hold that the plaintiffs’ SDSE claim is timely under the applicable three-year
    statute of limitations. Because their amended complaint argues that the flooding only in
    2018 constituted an “overflow or backup” under the SDSE exception, and they clearly seek
    relief in connection only with that flooding, the SDSE claim was timely. The now-
    abrogated continuing-wrongs doctrine does not apply to this case because the plaintiffs do
    not seek to grandfather any prior flooding into the action.
    However, we hold that the defendant is immune from the plaintiffs’ common-law
    trespass-nuisance claim. Section 1417(2) of the SDSE exception evinces clear legislative
    intent to abrogate all common-law exceptions to governmental immunity, including the
    trespass-nuisance exception.    Because the plaintiffs only sought injunctive relief in
    connection with their common-law trespass-nuisance claim, we reverse the Court of
    Appeals’ conclusion that they could seek an injunction in this instance. We reserve any
    broader conclusions about the availability of injunctive relief in connection with a properly
    pled SDSE claim under § 1417(3) for the future.
    Because we conclude the SDSE claim is timely, we reverse the trial court’s grant of
    summary disposition to the defendant with respect to the plaintiffs’ claim brought under
    the SDSE exception. However, we affirm the trial court’s grant of summary disposition
    15
    with respect to the common-law trespass-nuisance claim because the defendant is immune
    from it. We also vacate the Court of Appeals holding that the trespass-nuisance claim was
    timely. Finally, we remand this case to the trial court for further proceedings consistent
    with this opinion. We do not retain jurisdiction.
    Elizabeth T. Clement
    Brian K. Zahra
    David F. Viviano
    Richard H. Bernstein
    Megan K. Cavanagh
    Elizabeth M. Welch
    Kyra H. Bolden
    16