Farrow Group Inc v. Ethan D Dunn ( 2023 )


Menu:
  •             If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
    revision until final publication in the Michigan Appeals Reports.
    STATE OF MICHIGAN
    COURT OF APPEALS
    FARROW GROUP, INC.,                                                  UNPUBLISHED
    August 17, 2023
    Plaintiff-Appellant,
    v                                                                    No. 361465
    Wayne Circuit Court
    ETHAN D. DUNN, JOSHUA C. CASTMORE, and                               LC No. 20-010870-NM
    MAXWELL DUNN, PLC,
    Defendants-Appellees.
    Before: REDFORD, P.J., and K. F. KELLY and RICK, JJ.
    PER CURIAM.
    Plaintiff, Farrow Group, Inc., appeals by right the trial court’s order granting defendants,
    attorneys Ethan D. Dunn, Joshua C. Castmore, and law firm Maxwell Dunn, PLC, summary
    disposition of plaintiff’s legal malpractice claim brought after plaintiff accepted the case
    evaluation award in its underlying lawsuit against North Corktown Venture, LLC (NCV), because
    defendants recommended plaintiff accept it and incorrectly advised plaintiff that its equitable
    claims in that action would remain for adjudication but were dismissed with prejudice upon
    acceptance. Defendants admitted in this action that they provided incorrect advice in the
    underlying action and breached the applicable standard of care, but defended on the ground that
    plaintiff could not prove that defendants’ malpractice proximately caused it damages. Because we
    conclude there are numerous questions of fact, the trial court erred when it granted defendants’
    motion for summary disposition. We therefore reverse.
    I. BACKGROUND FACTS
    Plaintiff contracted with NCV to demolish buildings located at 3300 Trumbull, Detroit,
    Michigan, remove debris, and clean the site. The contract identified Odell Jones, III, of DH
    Construction Management, LLC, as the dispute resolution “Initial Decision Maker” and as the
    owner’s representative, and Michael Farrow as plaintiff’s representative. Section 14 of the
    contract permitted NCV to terminate for cause or for convenience. Section 14.1.3 provided the
    consequence of termination for convenience:
    -1-
    If the Owner terminates the Contract for convenience in accordance with Article 14
    of AIA Document A201-2017, then the Owner shall pay the Contractor a
    termination fee as follows:
    * * *
    Contractor shall be entitled to fifteen percent (15%) of the costs to complete the
    Work, in accordance with the same requirements imposed prior to termination, as
    estimated by the Owner’s Representative or an agreed upon third-party.
    Article 16 of the contract enumerated the contract documents and § 16.1 specified that the
    agreement had multiple documents including under § 16.1.3 that AIA Document A201-2017,
    General Conditions of the Contract for Construction applied. The AIA Document A201-2017,
    General Conditions of the Contract for Construction document provided in Article 10, that the
    contractor shall take reasonable precautions for safety and shall protect against damage, injury, or
    loss to persons who may be affected and other adjacent properties such as walks, pavements,
    roadways, structures, and utilities. § 10.2.1.1-.3. Further, the contractor had an ongoing obligation
    to comply with all “applicable laws, statutes, ordinances, codes, rules and regulations, and lawful
    orders of public authorities bearing on the safety of persons or property or their protection from
    damage, injury or loss. § 10.2.2. Under § 14.3 of the AIA Document A201-2017, General
    Conditions of the Contract for Construction document, the owner could give notice in writing and
    “suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may
    determine.” Section 14.4 provided that the owner could terminate the contract for convenience
    and stated as follows:
    § 14.4.1 The Owner may, at any time, terminate the Contract for the Owner’s
    convenience and without cause.
    § 14.4.2 Upon receipt of written notice from the Owner of such termination for the
    Owner’s convenience, the Contractor shall
    .1 cease operations as directed by the Owner in the notice;
    .2 take actions necessary, or that the Owner may direct, for the protection
    and preservation of the Work; and
    .3 Except for Work directed to be performed prior to the effective date of
    termination stated in the notice, terminate all existing subcontracts and purchase
    orders and enter into no further subcontracts and purchase orders.
    § 14.4.3 In case of such termination for the Owner’s convenience, the Contractor
    shall be entitled to receive payment for Work executed, and costs incurred by
    reason of such termination, along with reasonable overhead and profit on the Work
    not executed.
    The City of Detroit Buildings, Safety Engineering and Environmental Department issued
    a wrecking permit for plaintiff’s demolition, debris removal, and backfilling to grade level of the
    3300 Trumbull property, on August 16, 2017, with an expiration date of February 16, 2018.
    -2-
    Plaintiff commenced work and proceeded with the project. On January 24, 2018, Jones told
    Farrow that NCV issued a stop work order to plaintiff because of budget issues. Barry Ellentuck,
    who owned ADR Consultants, Inc., a company retained by plaintiff to assist with project
    management, corresponded with Jones via e-mail advising him that, because of the demolition
    permit, plaintiff had the obligation to complete the work to Detroit’s specifications. Ellentuck
    stated that work on the site had to resume on Monday February 19, 2018. Plaintiff resumed
    working on-site and NCV terminated the contract for convenience. Jones e-mailed Farrow to
    advise him of the contract’s termination. Ellentuck corresponded with Jones regarding issues
    related to unpaid invoices, the condition of the site, and that plaintiff could not simply abandon the
    site without consequences to itself and NCV. Plaintiff worked until it considered the site safe for
    its demobilization and departure from the site. Plaintiff invoiced NCV for work performed at the
    property but NCV did not pay. Plaintiff and NCV disputed whether plaintiff should have continued
    under the circumstances and what NCV owed plaintiff. On April 16, 2018, plaintiff asserted a
    claim of lien against the 3300 Trumbull property and recorded a construction lien in the amount
    of $536,778.65.
    In May 2018, plaintiff sued NCV to foreclose its construction lien against the 3300
    Trumbull property related to NCV’s failure to pay the balance due for the labor and materials to
    perform demolition services on the property. In addition to its lien foreclosure claim, plaintiff also
    asserted a claim for unjust enrichment and a breach of contract claim. Plaintiff alleged that NCV
    owed it $536,778.65, plus 15% of the costs to complete the work required under the contract,
    pursuant to § 14.1.3 of the contract.
    The court required the case be submitted to case evaluation. Just before the case evaluation
    hearing, defendants substituted into the case as plaintiff’s counsel in the underlying action.
    Castmore represented plaintiff at the case evaluation hearing. The case evaluators issued their case
    evaluation decision and awarded plaintiff $175,000. Defendants advised plaintiff to accept the
    case evaluation award. Plaintiff did so, believing defendants’ advice that its equitable claims
    would remain for adjudication after acceptance of the case evaluation award. NCV also accepted
    the case evaluation decision. The court in the underlying action dismissed plaintiff’s case in its
    entirety with prejudice.
    On August 24, 2020, plaintiff filed this legal malpractice action against defendants alleging
    that, based upon defendants’ professionally negligent advice that it could accept the case
    evaluation award in the underlying action and pursue its equitable claims against NCV, plaintiff
    accepted the case evaluation award. Plaintiff alleged that the court ruled that the mutual acceptance
    of the award ended the underlying litigation. Plaintiff alleged that defendants’ malpractice directly
    and proximately caused it to lose its claims under § 14.1.3 of the contract resulting in the loss of
    its damages claim for the contractual termination fee and that plaintiff lost its claim for unpaid
    work performed at the property. Plaintiff alleged that defendants’ acts and omissions constituted
    professional negligence and the violation of duties owed to plaintiff that caused it the loss of claims
    and monetary damages.
    Defendants moved for summary disposition under MCR 2.116(C)(10) and argued that, had
    plaintiff not accepted the case evaluation award in the underlying action, it would not have
    recovered more than the $175,000 case evaluation award because it would not have prevailed on
    its claims. Defendants asserted that plaintiff breached the terms of the NCV contract by continuing
    -3-
    to work after NCV terminated for convenience because plaintiff had the obligation to cease work
    and do no more than necessary to preserve and protect the site but it kept working. Defendants
    contended that plaintiff’s breach meant that plaintiff could not receive the contractual termination
    fee and at most at trial could have recovered $71,379.41, for two pre-termination invoices, an
    amount far less than the case evaluation award. Defendants contended that plaintiff, therefore,
    could not establish the proximate cause element of its legal malpractice claim entitling defendants
    to summary disposition. Plaintiff opposed the motion by arguing that defendants’ witnesses’
    testimonies establish that NCV did not expect plaintiff to just walk off the site after the stop work
    order. Plaintiff relied on Farrow’s and Ellentuck’s expertise in the demolition industry and their
    knowledge of the requirements to make the site safe and contended that plaintiff did what was
    reasonable and appropriate to protect the public. Plaintiff argued that its underlying case had not
    been lost because of the issues raised in defendants’ motion but occurred because of defendants’
    legal malpractice. Plaintiff asserted that genuine issues of material fact remained for trial regarding
    how much of plaintiff’s work after the stop work order was appropriate to make the site safe for
    demobilization. Plaintiff contended that it had a legal obligation to do the work it performed on-
    site and deserved to be paid for it, and would have succeeded on its claims and recovered in excess
    of the case evaluation award.
    At the hearing on defendants’ motion, defendants argued that plaintiff did not have valid
    causes of action in the underlying action, and even if defendants committed malpractice, plaintiff
    did not suffer harm, so it could not establish the proximate cause element of its legal malpractice
    claim. Defendants admitted that Castmore committed malpractice by incorrectly advising plaintiff
    but argued that the malpractice did not cause plaintiff damages. Plaintiff argued that genuine
    issues of fact existed regarding the necessity of work it performed after the stop work order to take
    the debris piles down below the site’s barrier height and to remediate asbestos and do other things
    to protect and preserve the worksite to enable it to demobilize and leave the site. The trial court
    stated that it had heard enough and advised the parties that it would grant defendants’ motion. The
    court opined that the legal professional negligence did not rise to the level where the court “should
    come in and, and grant or allow this case to go any, any further. So for the reasons that the Court
    has stated and what counsel has stated in terms of what should have been done, done, the Court
    doesn’t—is, is granting the motion for summary disposition.” The trial court entered an order
    granting defendants summary disposition and dismissed the case with prejudice for the reasons
    stated on the record. Plaintiff now appeals.
    II. STANDARD OF REVIEW
    We review de novo a circuit court’s summary disposition decision. Dalley v Dykema
    Gossett PLLC, 
    287 Mich App 296
    , 304; 
    788 NW2d 679
     (2010). A motion for summary disposition
    under MCR 2.116(C)(10) tests the factual sufficiency of the complaint. Joseph v Auto Club Ins
    Ass’n, 
    491 Mich 200
    , 205-206; 
    815 NW2d 412
     (2012). This Court reviews a motion brought under
    MCR 2.116(C)(10) “by considering the pleadings, admissions, and other evidence submitted by
    the parties in the light most favorable to the nonmoving party.” Patrick v Turkelson, 
    322 Mich App 595
    , 605; 
    913 NW2d 369
     (2018). Summary disposition “is appropriate if there is no genuine
    issue regarding any material fact and the moving party is entitled to judgment as a matter of law.”
    
    Id.
     The movant must specifically identify the matters which have no disputable issue of fact and
    then support its position with documentary evidence. Patterson v Kleiman, 
    447 Mich 429
    , 432;
    
    526 NW2d 879
     (1994). The party opposing the motion must then establish with evidence that a
    -4-
    genuine issue of material fact exists. Skinner v Square D Co, 
    445 Mich 153
    , 160; 
    516 NW2d 475
    (1994) “There is a genuine issue of material fact when reasonable minds could differ on an issue
    after viewing the record in the light most favorable to the nonmoving party.” Allison v AEW
    Capital Mgt, LLP, 
    481 Mich 419
    , 425; 
    751 NW2d 8
     (2008). “Circumstantial evidence can be
    sufficient to establish a genuine issue of material fact, but mere conjecture or speculation is
    insufficient.” McNeill-Marks v Midmichigan Med Ctr-Gratiot, 
    316 Mich App 1
    , 16; 
    891 NW2d 528
     (2016). Reasonable inferences from the record evidence should be considered in addition to
    the record evidence. Baker v Arbor Drugs, Inc, 
    215 Mich App 198
    , 202; 
    544 NW2d 727
     (1996).
    “For purposes of MCR 2.116(C)(10), a trial court is not allowed to weigh the evidence, assess
    credibility, or resolve factual disputes.” Highfield Beach at Lake Michigan v Sanderson, 
    331 Mich App 636
    , 653; 
    954 NW2d 231
     (2020) (citation omitted).
    III. ANALYSIS
    Plaintiff argues that the trial court erred by granting defendants summary disposition
    because genuine issues of material fact remained in dispute precluding summary disposition. We
    agree.
    In Bowden v Gannaway, 
    310 Mich App 499
    ; 
    871 NW2d 893
     (2015), this Court explained
    the elements of a legal malpractice claim. A plaintiff must prove:
    (1) the existence of an attorney-client relationship;
    (2) negligence in the legal representation of the plaintiff;
    (3) that the negligence was a proximate cause of an injury; and
    (4) the fact and extent of the injury alleged.
    To prove proximate cause, a plaintiff must show that but for the attorney’s alleged
    malpractice, he would have been successful in the underlying suit. [Id. at 503-504
    (quotation marks and citations omitted).]
    The second element requires proof that the defendant breached a professional standard of care.
    Broz v Plante & Moran, PLLC, 
    331 Mich App 39
    , 52-53; 
    951 NW2d 64
     (2020). Professional
    malpractice claims ordinarily require expert testimony to establish the applicable standard of care
    and that the defendant breached that standard. Id. at 53. An attorney “must only act as would an
    attorney of ordinary learning, judgment, or skill under the same or similar circumstances.” Simko
    v Blake, 
    448 Mich 648
    , 650; 
    532 NW2d 842
     (1995). An attorney has a duty to exercise reasonable
    skill, care, discretion, and judgment in the conduct of the cause and representation of his or her
    client. 
    Id. at 656
    .
    Just like negligence actions, the third element requires the plaintiff to prove “that the
    defendant’s action was a cause in fact of the claimed injury.” Charles Reinhart Co v Winiemko,
    
    444 Mich 579
    , 586; 
    513 NW2d 773
     (1994). The plaintiff in a legal malpractice action must
    establish that he or she would have been successful in the underlying matter but for the attorney’s
    malpractice. 
    Id.
     “In other words, the client seeking recovery from his attorney is faced with the
    difficult task of proving two cases within a single proceeding.” 
    Id.
     (quotation marks and citation
    -5-
    omitted). That is, “but for the attorney’s alleged malpractice, he would have been successful in
    the underlying suit.” 
    Id.
     (quotation marks and citation omitted). When alleged malpractice “is
    focused on malpractice occurring during litigation or settlement negotiations, then proximate cause
    often is an issue of fact.” 
    Id.
     at 590-591 n 22 (citations omitted). A claim of malpractice requires
    a showing of actual injury, not just the potential for injury. Colvert v Conybeare Law Office, 
    239 Mich App 608
    , 619-620; 
    609 NW2d 208
     (2000). Proximate causation is a required element of a
    negligence claim. Loweke v Ann Arbor Ceiling & Partition Co, LLC, 
    489 Mich 157
    , 162; 
    809 NW2d 553
     (2011). “To establish proximate cause, the plaintiff must prove the existence of both
    cause in fact and legal cause.” Weymers v Khera, 
    454 Mich 639
    , 647; 
    563 NW2d 647
     (1997).
    Cause in fact requires the plaintiff to “present substantial evidence from which a jury may conclude
    that more likely than not, but for the defendant’s conduct, the plaintiff’s injuries would not have
    occurred.” 
    Id. at 647-648
     (quotation marks and citation omitted). “To establish legal cause, the
    plaintiff must show that it was foreseeable that the defendant’s conduct may create a risk of harm
    to the victim, and . . . [that] the result of that conduct and intervening causes were foreseeable.”
    
    Id. at 648
     (quotation marks and citation omitted; alterations in original). Causation is an issue
    typically reserved for the trier of fact unless there is no dispute of material fact. Holton v A+ Ins
    Assoc, Inc, 
    255 Mich App 318
    , 326; 
    661 NW2d 248
     (2003).
    In this case, the parties do not dispute that an attorney-client relationship existed or the
    applicable standard of care, and defendants admitted that they breached the standard of care by
    negligently representing plaintiff in the underlying action by incorrectly advising plaintiff that its
    acceptance of the case evaluation award would not dispose of plaintiff’s equitable claims including
    its construction lien claim. Plaintiff, therefore, established the first two elements of its legal
    malpractice claim.
    Having conceded their commission of legal malpractice, defendants dispute that their
    negligence proximately caused plaintiff any injury. To prove proximate cause, plaintiff had to
    prove that, but for defendants’ malpractice, it would have been successful in the underlying suit.
    In that action, plaintiff sued NCV to foreclose on its construction lien asserted in relation to the
    labor and materials furnished to NCV for improving the property and sought entry of a lien
    judgment ordering the sale of the property under MCL 570.1121. Plaintiff also stated a claim for
    unjust enrichment alleging that it furnished labor and materials in connection with improvement
    of the property that provided NCV a benefit that it would be unjust to allow NCV to retain without
    paying plaintiff. Plaintiff also sued NCV for breach of contract to recover money it contended
    NCV owed but failed to pay in relation to providing labor and materials to the project under the
    parties’ contract, plus the contract termination fee of 15% of the cost of the project’s completion.
    During the underlying litigation, before plaintiff’s claims were adjudicated, defendants
    were retained and stepped in to provide plaintiff legal representation. They substituted into the
    case for plaintiff’s previous counsel shortly before the parties to that lawsuit participated in case
    evaluation on February 20, 2019. Neither plaintiff’s original counsel nor defendants moved nor
    -6-
    sought a stipulation before case evaluation to exempt plaintiff’s equitable claims from case
    evaluation as permitted under MCR 2.403(A)(3).1 The case evaluators awarded plaintiff $175,000.
    After case evaluation in the underlying case, defendants advised plaintiff that it could
    accept the case evaluation award and continue litigating its remaining claims. Defendants
    recommended that plaintiff accept the award. Plaintiff accepted the case evaluation award on the
    basis of that recommendation. NCV also accepted the case evaluation decision. The trial court in
    the underlying case, therefore, dismissed the entire action. Under MCR 2.403(M)(1), “the court
    shall dismiss the action with prejudice” and such “judgment or dismissal shall be deemed to
    dispose of all claims in the action . . . .”
    Defendants admit their professional negligence but argue that plaintiff materially breached
    its contract with NCV by continuing to work after NCV issued a stop work order and after its
    demolition permit expired. Defendants contend that plaintiff’s breaches precluded it from payment
    of its post-termination invoices or its contractual termination fee and that it recovered more from
    the case evaluation award than it would have gained from litigation of the underlying action.
    Defendants contend that, at most, plaintiff may have recovered payment of two pre-termination
    invoices totaling $71,379.41. Defendants argue that plaintiff’s legal malpractice claim failed
    because it could not prove proximate causation, i.e., that defendants’ negligence caused it any
    damages.
    The record reflects that defendants neglected to investigate and understand that under MCR
    2.403(A)(3), equitable claims could be exempted from case evaluation. Defendants also neglected
    to file a motion or seek a stipulation to exempt those claims. Then, after case evaluation,
    defendants neglected to understand and properly inform plaintiff of the consequences of accepting
    that case evaluation award. Plaintiff’s acceptance of the case evaluation award based upon
    defendants’ mistaken and professionally negligent advice resulted in its loss of its two equitable
    claims, the right to seek recovery on its construction lien and obtain a judgment ordering the sale
    of the property to satisfy the lien, and the right to seek recovery under the alternative unjust
    enrichment theory. Moreover, had plaintiff rejected case evaluation, its breach of contract claim
    would not have been resolved and plaintiff would have been able to litigate that claim as well for
    its determination on the merits. That claim included all unpaid invoices and the contractual
    termination fee.
    Defendants argued to the lower court in this case and argue to this Court that plaintiff’s
    equitable claims were essentially the same and derivative of its breach of contract claim, and they
    contend that plaintiff would not have prevailed even on the breach of contract claim in the
    1
    The provisions stated in MCR 2.403(A)(3) are now featured in MCR 2.403(A)(4). The rule
    provides:
    A court may exempt claims seeking equitable relief from case evaluation
    for good cause shown on motion or by stipulation of the parties if the court finds
    that case evaluation of such claims would be inappropriate.
    -7-
    underlying action. In Ronnisch Constr Group, Inc v Lofts on the Nine, LLC, 
    499 Mich 544
    , 561-
    562; 
    886 NW2d 113
     (2016), our Supreme Court explained:
    Under Michigan law, a lien foreclosure claim and a claim for breach of the
    underlying contract are integrally related. A contract is a necessary prerequisite to
    a construction lien. A construction lien stems from the underlying contract, and its
    amount is determined by the contract’s terms. These principles are reflected
    throughout the [Construction Lien Act, MCL 570.1101 et seq]. In essence, the lien
    is but a means for enforcing the payment of the debt arising from the performance
    of the contract. A party may proceed to enforce its lien through foreclosure while
    simultaneously seeking recovery based on the contract from which the lien arose.
    But there can only be one satisfaction. Thus, a lien foreclosure claim and a claim
    for breach of the underlying contract are integrally related, and allowing a party to
    pursue both merely gives it a better chance of recovering what it is owed.
    [Quotation marks, citations, and alteration omitted.]
    Plaintiff’s first count in the underlying action sought foreclosure of the construction lien it
    recorded in the Wayne County Register of Deeds on April 16, 2018, in which it asserted that the
    contract amount was $2,498,747.15, that it received payment on the contract totaling
    $1,961,968.50, and that the lien on the 3300 Trumbull property equaled $536,778.65, the unpaid
    amount, plus interest. Such claim involves the Construction Lien Act, MCL 570.1101 et seq. “It
    has long been recognized that construction lien laws serve two purposes: to protect the right of lien
    claimants to payment for wages or materials and to protect owners from paying twice for such
    services.” M D Marinich, Inc v Mich Nat’l Bank, 
    193 Mich App 447
    , 453; 
    484 NW2d 738
     (1992)
    (citation omitted). MCL 570.1117 provides construction lien claimants the right to bring an action
    for enforcement of a construction lien through foreclosure. MCL 570.117(5) permits lien
    claimants to maintain an action on any contract from which the lien arose in the same action.
    MCL 570.1118(1) specifies that a construction lien foreclosure action must be brought in the
    circuit court for the county where the real property is located and that such foreclosure action is
    equitable in nature. Under MCL 570.118(2), in such action the circuit court must examine each
    claim and defense and determine the amount, if any, due the lien claimant. MCL 570.1120
    specifies the damages recoverable including “compensation for as much as was performed by the
    claimant under the contract, in proportion to the price stipulated for complete performance of the
    whole contract, less any payments made to the lien claimant and also to any additional damages
    which the lien claimant may be entitled to as a matter of law.” MCL 570.1121 provides in relevant
    part:
    (1) If the court finds that a lien claimant is entitled to a construction lien upon the
    real property to which he or she furnished an improvement, and the amount
    adjudged to be due has not been paid, the court may enter a judgment ordering the
    sale of any interest in the real property, or a part of the real property, to which the
    construction lien attaches. . . .
    Plaintiff’s second count in the underlying action sought recovery under a theory of unjust
    enrichment. To prove unjust enrichment, the plaintiff must show “(1) receipt of a benefit by the
    defendant from the plaintiff, and (2) an inequity resulting to plaintiff from defendant’s retention
    of the benefit.” Bellevue Ventures, Inc v Morang-Kelly Investment, Inc, 
    302 Mich App 59
    , 64;
    -8-
    
    836 NW2d 898
     (2013). An implied contract prevents unjust enrichment but only in the absence
    of an “express contract covering the same subject matter.” 
    Id.
    Equitable claims are determined by the court. New Products Corp v Harbor Shores BHBT
    Land Dev, LLC, 
    308 Mich App 638
    , 651-652; 
    866 NW 2d 850
     (2014); see also Madugula v Taub,
    
    496 Mich 685
    ; 
    853 NW2d 75
     (2014). A court of equity must state its specific findings of fact and
    conclusions of law on the record. Id. at 716-717.
    Plaintiff’s third count stated a claim for NCV’s breach of contract. To prevail on a claim
    for breach of contract, a plaintiff must establish by a preponderance of the evidence that (1) a
    contract existed between the parties, (2) the other party breached the contract, and (3) the breach
    caused damages to the party claiming breach. Bank of Am, NA v First Am Title Ins Co, 
    499 Mich 74
    , 100; 
    878 NW2d 816
     (2016). The plaintiff must establish a causal link between the breach of
    contract and the claimed damages. Gorman v Am Honda Motor Co, Inc, 
    302 Mich App 113
    , 118-
    19; 
    839 NW2d 223
     (2013). “The party asserting a breach of contract has the burden of proving its
    damages with reasonable certainty, and may recover only those damages that are the direct, natural,
    and proximate result of the breach.” Doe v Henry Ford Health Sys, 
    308 Mich App 592
    , 601-02;
    
    865 NW2d 915
     (2014) (citation omitted).
    In the underlying action, in relation to its construction lien foreclosure claim, plaintiff
    sought the court’s determination of the amount due plaintiff pursuant to its lien and asked the court
    to order the sale of the property under the Construction Lien Act and order payment from the
    proceeds of the sale. It sought a monetary judgment in the amount of $536,778.65 for its unjust
    enrichment claim. In relation to its breach of contract claim, plaintiff requested a monetary
    judgment against NCV in the amount of $536,778.65 for NCV’s default of payment for labor and
    materials plus an additional sum equal to 15% of the cost to complete the work.
    Examination of the record in this case establishes that plaintiff presented evidence that a
    cost-plus contract existed between it and NCV respecting demolition of the 3300 Trumbull
    property requiring NCV to pay for the labor and materials expended by plaintiff in performance
    of its contractual obligations. Plaintiff presented evidence that NCV failed to pay plaintiff the full
    amount plaintiff billed. The proceedings in the underlying action did not result in the
    determination of contested specific facts regarding damages, legal or equitable, the validity and
    amount of plaintiff’s construction lien, or whether plaintiff could assert a viable unjust enrichment
    claim. Further, the underlying action left undetermined whether plaintiff was entitled to the
    claimed contractual damages and the contractual 15% termination fee, and if so, in what amount.
    In this case, plaintiff presented evidence that NCV failed to pay invoices for work performed by it
    before NCV terminated the contract for convenience. Plaintiff also presented evidence that, after
    the stop work order issued, it had to continue performing work because of the dangerous conditions
    on the property and the presence of hazardous materials that required work to prevent airborne
    dissemination to the surrounding neighborhood. Plaintiff presented evidence that work had to be
    performed to prevent damage to adjacent sidewalks and roads. Farrow’s, Ellentuck’s, and Jones’s
    testimonies supported plaintiff’s contention that it performed work for which it was entitled to
    payment and that NCV refused to pay it. Documentary evidence also supported plaintiff’s claim
    for monetary damages in excess of the case evaluation award.
    -9-
    The bone of contention respecting whether plaintiff would have prevailed in the underlying
    action and done better than the amount awarded from the case evaluation, but for defendants’ legal
    malpractice, requires determination whether and to what extent plaintiff had to perform the work
    it undertook after the stop work order and termination of the contract. Farrow’s and Ellentuck’s
    testimonies, and even Jones’s testimony, established that plaintiff had to perform certain work to
    prepare and protect the site before plaintiff demobilized and left. Farrow’s and Ellentuck’s
    testimonies, support plaintiff’s position that the circumstances required performance of all of the
    work for which plaintiff billed NCV. Jones’s testimony agreed in part with their testimonies but
    he questioned the necessity of the extent of the work plaintiff performed. However, he did not
    specify what plaintiff did that exceeded what was required. His testimony does not set forth how
    plaintiff should have limited its work under the circumstances presented by the site at the time he
    issued the stop work order or thereafter. To the extent he contradicted Farrow’s and Ellentuck’s
    testimonies, a question of fact obviously remained for adjudication. Even defendants’ expert’s
    testimony supported plaintiff’s position that the dangerous conditions on the site necessitated
    continued work for which plaintiff should have been compensated. He opined that plaintiff could
    perform all necessary work in one week at a cost of only around $50,000. The expert’s opinion
    testimony sharply contrasts with Farrow’s and Ellentuck’s testimonies and establishes that a
    question of fact remained for trial on the type and amount of work necessary to prepare and protect
    the work before demobilizing and leaving the site, and the amount for which plaintiff should have
    been compensated for it. The record in this case does not demonstrate that no dispute existed
    regarding these facts. Further, plaintiff established that genuine issues of material fact remained
    regarding what aspects of the site were safe and what were not necessitating work, what the city
    required before plaintiff could leave the site, how long the necessary work would and should take,
    and how much plaintiff should be compensated for such necessary work. The evidence presented
    by plaintiff established that, in the underlying action, plaintiff would have prevailed on its breach
    of contract claim and its construction lien claim, but genuine issues of fact remained regarding the
    extent of the work necessary to fulfill its obligations and the amount of damages to which plaintiff
    was entitled for such work it performed. The existence of such issues precluded granting
    defendants summary disposition in this case.
    The issue whether plaintiff’s acceptance of the case evaluation award provided plaintiff
    more than what it could or would have been able to recover, had it been able to proceed with its
    entire suit to a final adjudication on the merits, was not conclusively established. Plaintiff
    presented evidence from which a jury could conclude that NCV breached the contract and owed
    plaintiff monetary damages in excess of the case evaluation award. The record in this case
    establishes that the trial court did not view the evidence in a light most favorable to plaintiff, the
    nonmoving party. Rather, the trial court accepted defendants’ expert’s opinions and discounted
    Farrow’s and Ellentuck’s testimonies, and even Jones’s testimony favorable to plaintiff.
    Defendants’ argument that plaintiff materially breached the contract by continuing to work
    negating any right it had to recover in the underlying action lacks merit. Under Michigan law, a
    contracting party may repudiate its contractual obligations if the other party “has committed a
    material breach.” Walker & Co v Harrison, 
    347 Mich 630
    , 635; 
    81 NW2d 352
     (1957). Claiming
    that there has been a material breach justifying repudiation “is fraught with peril, for should such
    determination, as viewed by a later court in the calm of its contemplation, be unwarranted, the
    repudiator [] will have been guilty of material breach and [] have become the aggressor, not an
    innocent victim.” 
    Id.
     In Walker, our Supreme Court explained how to determine whether a breach
    -10-
    constituted a material breach and applied the factors stated in Restatement of the Law of Contracts
    § 275, which provides:
    In determining the materiality of a failure fully to perform a promise the following
    circumstances are influential:
    (a) The extent to which the injured party will obtain the substantial benefit which
    he could have reasonably anticipated;
    (b) The extent to which the injured party may be adequately compensated in
    damages for lack of complete performance;
    (c) The extent to which the party failing to perform has already partly performed
    or made preparations for performance;
    (d) The greater or less hardship on the party failing to perform in terminating the
    contract;
    (e) The wilful, negligent or innocent behavior of the party failing to perform;
    (f) The greater or less uncertainty that the party failing to perform will perform the
    remainder of the contract. [Id. (quotation marks and citation omitted).]
    “[T]he court should consider whether the nonbreaching party obtained the benefit it
    reasonably expected to receive.” Omnicom of Mich v Giannetti Inv Co, 
    221 Mich App 341
    , 348;
    
    561 NW2d 138
     (1997). In Omnicom, this Court reviewed the record and applied the factors
    articulated in Walker and held that they favored finding that no material breach had occurred. Id.
    at 348-349.
    In this case, defendants invoked § 14.4.2 of the AIA Document A201-2017, General
    Conditions of the Contract for Construction to argue that once NCV issued the stop work order
    plaintiff had to cease operations and only take minimum actions necessary for the protection and
    preservation of the work. The contract, however, does not specify what actions are necessary for
    the protection and preservation of the work. The parties in this case dispute what plaintiff had to
    do before demobilizing and leaving the site and what actions were necessary for the protection and
    preservation of the work. Review of AIA Document A201-2017, General Conditions of the
    Contract for Construction reveals that in Article 10, the contract specifies that the contractor shall
    take reasonable precautions for safety and shall protect against damage, injury, or loss to persons
    who may be affected and other adjacent properties such as walks, pavements, roadways, structures,
    and utilities. § 10.2.1.1-.3. Further, the contractor had an ongoing obligation to comply with all
    “applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public
    authorities bearing on the safety of persons or property or their protection from damage, injury or
    loss.” § 10.2.2.
    Under the contract, plaintiff had the obligations to take reasonable precautions prevent
    damage, injury, or loss to any persons and to adjacent properties. Farrow and Ellentuck testified
    that the actions plaintiff took after the stop work order were undertaken for precisely those reasons
    -11-
    and they recognized that the site’s condition at that time posed unreasonable risks of harm to
    persons and adjacent properties.
    The record demonstrates that plaintiff presented evidence sufficient to establish a question
    of fact whether it would have received a higher recovery had it rejected the case evaluation award
    and proceeded to trial on all three claims in its complaint. Whether a jury in this case would accept
    the proofs of damages in the suit within the suit portion of the claim is, of course, unknown at this
    time. However, the record establishes that there were proofs of damages to present in the
    underlying case that, if accepted, could have resulted in a much larger judgment. Thus, plaintiff
    has established a question of fact as to the “fact and extent” of its damages, sufficient to survive
    summary disposition on its claim of legal malpractice.
    Plaintiff also argues that the trial court applied a degree of malpractice standard that does
    not comport with Michigan law. The trial court stated that the malpractice did not rise to a level
    where the court believed the case should go any further. The trial court failed to articulate what
    that meant. We decline to speculate as to the court’s rationale for granting summary disposition.
    Nevertheless, it is apparent that the trial court failed to consider all of the evidence in a light most
    favorable to the nonmoving party and made credibility determinations regarding the witnesses’
    testimonies. In so doing, the trial court failed to discern the genuine issues of material fact and
    committed reversible error.
    Reversed and remanded for further proceedings consistent with this opinion. We do not
    retain jurisdiction.
    /s/ James Robert Redford
    /s/ Kirsten Frank Kelly
    /s/ Michelle M. Rick
    -12-