Huff v. FirstEnergy Corp. , 130 Ohio St. 3d 196 ( 2011 )


Menu:
  • [Cite as Huff v. FirstEnergy Corp., 
    130 Ohio St.3d 196
    , 
    2011-Ohio-5083
    .]
    HUFF ET AL., APPELLEES, v. FIRSTENERGY CORP. ET AL.;
    OHIO EDISON COMPANY ET AL., APPELLANTS.
    [Cite as Huff v. FirstEnergy Corp., 
    130 Ohio St.3d 196
    , 
    2011-Ohio-5083
    .]
    Contracts—Third-party beneficiaries—For an injured third party to qualify as an
    intended third-party beneficiary under a written contract, the contract
    must indicate an intention to benefit that third party.
    (No. 2010-0857—Submitted May 24, 2011—Decided October 5, 2011.)
    APPEAL from the Court of Appeals for Trumbull County,
    No. 2009-TR-00080, 
    2010-Ohio-1456
    .
    __________________
    SYLLABUS OF THE COURT
    For an injured third party to qualify as an intended third-party beneficiary under a
    written contract, the contract must indicate an intention to benefit that
    third party.
    __________________
    LANZINGER, J.
    {¶ 1} This discretionary appeal was accepted in a personal-injury case
    involving a summary judgment that was reversed by the Eleventh District Court
    of Appeals. We are asked to determine whether a person injured by a falling tree
    located near, but outside, the utility’s easement is an intended third-party
    beneficiary of a contract between a utility and its service contractor. We hold that
    under the facts of this case, a contract between a utility and a contractor that
    provides that “[t]he Contractor shall plan and conduct the work to adequately
    safeguard all persons and property from injury” does not create a duty on the part
    SUPREME COURT OF OHIO
    of the contractor, once the work has been completed, to protect a third party from
    injury.
    I. Case Background
    {¶ 2} In June 2004, appellee Lisa G. Huff was injured during a walk
    along Kings Grave Road in Hartford Township. She alleges that during a heavy
    thunderstorm, a large sugar maple tree split in two approximately 25 feet above
    the ground, and a large limb from the tree struck her, causing serious and
    permanent injuries. The tree was located on property owned by Gerald and
    Michelina Braho and stood about 30 feet from the center of Kings Grave Road
    and 20 feet from utility lines owned and maintained by appellant Ohio Edison
    Company, a subsidiary of FirstEnergy Corp.
    {¶ 3} Ohio Edison maintained an easement near the tree, but the tree was
    outside the easement. The tree did not present a hazard or threat to the power
    lines. Ohio Edison had hired appellant Asplundh Tree Expert Company to inspect
    trees and vegetation along its power lines in this area and to remedy any situation
    in which trees or vegetation might affect the lines.                   Ohio Edison and its
    contractors carry out this work to ensure that adequate clearance is maintained
    around electric lines. Generally, Ohio Edison deferred to Asplundh’s decisions
    regarding tree and vegetation maintenance and would perform an overview
    inspection of the electrical circuit only to determine whether any vegetation was
    growing into the electrical wires or equipment. Asplundh had last been in the
    area where Huff’s injury occurred in May 2001.
    {¶ 4} Huff, along with her husband, Reggie D. Huff, and children filed
    suit against Ohio Edison and Asplundh, as well as FirstEnergy1 and the Brahos.2
    1. The court of appeals concluded that FirstEnergy is merely a holding company that owns Ohio
    Edison and that it did not exercise any control or supervision over Ohio Edison’s day-to-day
    practices for clearing vegetation. The court of appeals accordingly concluded that the trial court
    properly granted summary judgment in FirstEnergy’s favor. The Huffs did not appeal the
    judgment in favor of FirstEnergy.
    2
    January Term, 2011
    The Huffs alleged that Ohio Edison and Asplundh were liable for Huff’s injuries
    based upon their failure to inspect, maintain, and remove the tree or to warn the
    landowner and the public of the danger raised by the tree.3
    {¶ 5} Ohio Edison and Asplundh filed motions for summary judgment.
    Ohio Edison argued that it had no prior knowledge that the tree was dangerous,
    that it owed and assumed no duty to Huff regarding the tree, and that it was not
    negligent and did not proximately cause or contribute to Huff’s injuries.
    Asplundh argued that it owed no duty to Huff and that its activities did not
    proximately cause the injury to Huff. The Huffs responded that Ohio Edison had
    contracted with Asplundh to inspect and maintain trees within the easement and
    that Asplundh failed to recognize that the tree in question was diseased and a
    hazard and failed to remove the tree when it was on site in May 2001. The Huffs
    also argued that Ohio Edison was responsible for maintaining trees within and
    around its easement, that Ohio Edison was aware of the tree based upon its
    location within an inspection zone, and that Ohio Edison had a duty to remove the
    diseased tree.
    {¶ 6} The trial court found that while the tree leaned approximately ten
    degrees away from the power lines, “there is absolutely no credible evidence
    about when the tree began to lean or if it was leaning because of the way it grew.”
    It also noted that one of the Huffs’ experts admitted that he could not testify to a
    reasonable degree of probability as to when the tree became a hazard. Finding no
    evidence that Ohio Edison or Asplundh actually inspected the tree or removed any
    branches, the court concluded that the Huffs failed to show that appellants ever
    had actual or constructive notice of any decay of the tree. The court found that
    2. The Huffs subsequently dismissed the Brahos from the case.
    3. While the Huffs did not explicitly aver their status as third-party beneficiaries in the complaint,
    they generally referred to contractual duties owed by Ohio Edison to the public to inspect, prune,
    and maintain trees along its power lines.
    3
    SUPREME COURT OF OHIO
    due to the tree’s location—leaning away from the power lines with no limbs near
    the power lines—Ohio Edison and Asplundh owed no duty to the Huffs. With
    respect to Ohio Edison, the court also found that “Ohio Edison * * * did not have
    actual or constructive notice of any defects in this tree located on someone else’s
    property” and that there was a “complete lack of any evidence that * * * Ohio
    Edison had any notice whatsoever that the interior of one tree on a rural township
    road was decaying.” After examining the contract between Ohio Edison and
    Asplundh, it concluded that the Huffs were not third-party beneficiaries under the
    contract. It accordingly granted appellants’ motions for summary judgment.
    {¶ 7} On appeal, the Huffs argued that the trial court erred when it found
    that Ohio Edison and Asplundh had no duty to Lisa Huff. Before considering
    whether appellants had a duty under the contract, the court of appeals first
    determined that no duty under traditional tort law existed: “The duty analysis in
    this case * * * does not turn on the foreseeability of the danger which caused
    [Huff’s] injury. Rather, it turns on the language of the contract into which Ohio
    Edison and Asplundh entered.” Trumbull App. No. 2009-T-0080, 2010-Ohio-
    1456, at ¶ 52. As a result, it examined the contract between Ohio Edison and
    Asplundh and held that there was a genuine issue of material fact regarding
    whether Huff had enforceable rights under the contract as an intended third-party
    beneficiary. Id. at ¶ 62. In reaching this conclusion, the court stated that a portion
    of the contract providing that “[Asplundh] shall plan and conduct the work to
    adequately safeguard all persons and property from injury” could be read in two
    ways: (1) a narrow reading that provides Asplundh must protect all persons from
    injury while Asplundh works on the site or (2) a broad reading that requires
    Asplundh to protect all persons from injury at all times, regardless of when the
    work is done. Id. at ¶ 60-61. The court accordingly held that the contract was
    ambiguous and reversed the trial court’s grant of summary judgment to Ohio
    Edison and Asplundh. Id. at ¶ 61-64.
    4
    January Term, 2011
    {¶ 8} We first denied jurisdiction in this case. 
    126 Ohio St.3d 1546
    ,
    
    2010-Ohio-3855
    , 
    932 N.E.2d 340
    . On reconsideration, we granted jurisdiction on
    all propositions of law raised by Ohio Edison and Asplundh. 
    126 Ohio St.3d 1620
    , 
    2010-Ohio-5101
    , 
    935 N.E.2d 856
    .
    II. Analysis
    {¶ 9} Ohio Edison’s and Asplundh’s propositions of law raise a number
    of challenges to the court of appeals’ holding that they owed a duty to the Huffs
    as intended third-party beneficiaries of the contract between Ohio Edison and
    Asplundh. Because we hold that the contract between Ohio Edison and Asplundh
    did not create any duty to the Huffs as third-party beneficiaries, we reverse the
    judgment of the court of appeals.
    {¶ 10} In Hill v. Sonitrol of Southwestern Ohio, Inc. (1988), 
    36 Ohio St.3d 36
    , 40, 
    521 N.E.2d 780
    , we adopted the statement of law in Restatement of the
    Law 2d, Contracts (1981), Section 302.        Section 302(1)(b) provides that “a
    beneficiary of a promise is an intended beneficiary if recognition of a right to
    performance in the beneficiary is appropriate to effectuate the intention of the
    parties and * * * the circumstances indicate that the promisee intends to give the
    beneficiary the benefit of the promised performance.” Comment e to Section 302
    limits the creation of duties to third parties: “[U]nless the third person is an
    intended beneficiary as here defined, no duty to him is created.”
    {¶ 11} In applying this rule, we referred to Norfolk & W. Co. v. United
    States (C.A.6, 1980), 
    641 F.2d 1201
    . We adopted language from Norfolk & W.
    Co. explaining the “intent to benefit” test, which is used to determine whether a
    third party is an intended beneficiary of a contract: “ ‘Under this analysis, if the
    promisee * * * intends that a third party should benefit from the contract, then that
    third party is an “intended beneficiary” who has enforceable rights under the
    contract. If the promisee has no intent to benefit a third party, then any third-
    party beneficiary to the contract is merely an “incidental beneficiary,” who has no
    5
    SUPREME COURT OF OHIO
    enforceable rights under the contract.’ ” Hill at 40, quoting Norfolk & W. Co. at
    1208.
    {¶ 12} Courts generally presume that a contract’s intent resides in the
    language the parties chose to use in the agreement. Shifrin v. Forest City Ents.,
    Inc. (1992), 
    64 Ohio St.3d 635
    , 638, 
    597 N.E.2d 499
    . “Only when the language
    of a contract is unclear or ambiguous, or when the circumstances surrounding the
    agreement invest the language of the contract with a special meaning will
    extrinsic evidence be considered in an effort to give effect to the parties’
    intentions.” 
    Id.
     at syllabus. Ohio law thus requires that for a third party to be an
    intended beneficiary under a contract, there must be evidence that the contract
    was intended to directly benefit that third party. Generally, the parties’ intention
    to benefit a third party will be found in the language of the agreement.
    {¶ 13} The facts in this case do not show that the agreement between Ohio
    Edison and Asplundh was intended to benefit the Huffs. The court of appeals and
    the Huffs point to one specific portion of the contract that they argue creates a
    genuine issue of material fact regarding whether Lisa Huff has an enforceable
    right under the contract. This statement, which is found in an attachment entitled
    “FirstEnergy Vegetation Management Specifications” and incorporated into the
    Ohio Edison-Asplundh contract, provides that “[t]he Contractor shall plan and
    conduct the work to adequately safeguard all persons and property from injury.”
    The Huffs contend that this statement distinguishes their case from Hill and
    Norfolk & W. because it assigns to both Ohio Edison and Asplundh clearly
    defined duties—to safeguard the public—for the Huffs’ benefit.
    {¶ 14} When this statement is placed in context, however, it is clear that
    neither Ohio Edison nor Asplundh intended to make the Huffs third-party
    beneficiaries under the contract. The contract was not entered into for the general
    benefit of the public walking on public roads. It was designed to support the
    electrical service offered by Ohio Edison. The contract states that it applies to
    6
    January Term, 2011
    work, consisting of “tree trimming, tree removal, clearance of rights-of-way using
    either manual or chemical methods, and disposal of trees and brush,” completed
    by Asplundh on behalf of Ohio Edison. The purpose of the contract, then, is to
    ensure that Ohio Edison’s equipment and lines are kept free of interference from
    trees and vegetation. The remainder of the contract sets forth how this work is to
    be carried out, such as the standards by which Asplundh is to perform its work,
    the limits on liability for the performance of the work, and the necessary
    qualifications for the Asplundh employees who were to perform the work. The
    contract contains no language establishing an ongoing duty to the general public
    on behalf of either Ohio Edison or Asplundh.
    {¶ 15} The document on vegetation management incorporated into the
    contract provides that “[t]he objective of all work covered by these documents is
    to maintain reliable and economical electric service, through effective line
    clearance and satisfactory public relations.” A portion of that document sets forth
    safety standards for Asplundh to follow while it is on site:
    {¶ 16} “SAFETY         PRECAUTIONS           AND        PROTECTION       TO
    PROPERTY
    {¶ 17} “The Contractor shall plan and conduct the work to adequately
    safeguard all persons and property from injury.
    {¶ 18} “The Contractor shall take the necessary precautions to render the
    Work secure in order to decrease the probability of accident from any cause and
    to avoid delay in completion of Work. The Contractor shall use proper safety
    appliances and provide first aid treatment and ambulance for emergency treatment
    of injuries and shall comply with all applicable Federal, State and Local Laws,
    rules and regulations with regard to the safe performance of the work.”
    {¶ 19} Working near electrical lines has its inherent hazards. It is clear
    that this portion of the agreement establishes safety guidelines designed to protect
    persons and property from injury while the contractor performs its work. This
    7
    SUPREME COURT OF OHIO
    period is finite: until the work has been completed. Contrary to the assertion of
    the court of appeals, the agreement cannot be plausibly read to require Ohio
    Edison or Asplundh to safeguard all persons from injury at all times, regardless of
    when the work is completed.
    {¶ 20} Even if the Huffs were able to show that at some point in time,
    members of the public using the road near the power lines might receive
    incidental or indirect benefits from the agreement, this would not satisfy the
    burden of proof established in Hill. See Terry v. Hancock-Wood Elec. Coop.,
    Inc., Erie App. No. E-08-060, 
    2009-Ohio-4925
    , at ¶ 29. The agreement does not
    indicate that either Ohio Edison or Asplundh intended to give the general public
    the benefit of a promise to perform. The Huffs thus fail to qualify as intended
    third-party beneficiaries, and the court of appeals improperly reversed the
    summary judgment granted to Ohio Edison and Asplundh.
    {¶ 21} It should be noted that while there is no contractual duty on behalf
    of Ohio Edison or Asplundh toward the Huffs, this fact did not preclude the Huffs
    from showing that appellants owed them a duty under traditional principles of tort
    law. Indeed, during oral argument, the Huffs’ counsel proposed that either Ohio
    Edison or Asplundh had caused damage, at some unspecified time, to the tree that
    struck Lisa Huff, and thus that appellants had a duty to make the tree safe for the
    general public. Counsel admitted, however, that the Huffs had no direct evidence
    to support this theory. In fact, the trial court found that the Huffs failed to show
    that either Ohio Edison or Asplundh was on notice of any decay in the tree when
    Asplundh was on the site in 2001. Furthermore, the Huffs failed to preserve this
    issue on appeal.4
    4. We decline to address the specific issues contained within Ohio Edison’s third proposition of
    law and Asplundh’s fourth proposition of law, both of which propose general rules for contract
    interpretation that are rendered irrelevant to this case, given our holding that the Huffs are not
    intended third-party beneficiaries as defined by Ohio law. Furthermore, because the court of
    appeals limited its analysis to whether the Huffs are intended third-party beneficiaries under the
    8
    January Term, 2011
    III. Conclusion
    {¶ 22} We hold that for an injured third party to qualify as an intended
    third-party beneficiary under a written contract, the contract must indicate an
    intention to benefit that third party. Because the contract between Ohio Edison
    and Asplundh does not indicate an intent to benefit the Huffs, the trial court
    properly granted summary judgment to Ohio Edison and Asplundh. We therefore
    reverse the judgment of the court of appeals.
    Judgment reversed.
    O’CONNOR, C.J., and LUNDBERG STRATTON, CUPP, and MCGEE BROWN,
    JJ., concur.
    PFEIFER and O’DONNELL, JJ., concur in judgment only.
    __________________
    O’DONNELL, J., concurring in judgment only.
    {¶ 23} The issue in this case is whether Ohio Edison and Asplundh Tree
    Expert Company intended to make Huff and other members of the public third-
    party beneficiaries of a contract that required Asplundh to conduct its work in a
    manner that adequately safeguarded “all persons” from injury. I agree with the
    majority that the parties did not intend to make Huff a third-party beneficiary of
    the contract and that she may not bring a claim against Ohio Edison or Asplundh
    for breach of that contract. However, I concur in judgment only because, in my
    view, the majority creates a new requirement that the intention to benefit a third
    party must be indicated in the terms of the contract. This is not the law in Ohio.
    {¶ 24} In Hill v. Sonitrol of Southwestern Ohio, Inc. (1988), 
    36 Ohio St.3d 36
    , 
    521 N.E.2d 780
    , we adopted the test found in the Restatement of the Law 2d,
    contract, we also decline to address Asplundh’s first proposition of law, which addresses whether
    a utility or its contractor has a general duty to protect the public from trees that are not located on
    utility property or within a utility easement and do not pose a threat to utility equipment.
    9
    SUPREME COURT OF OHIO
    Contracts (1981), to define the duty that the parties to a contract owe to a third-
    party beneficiary. Quoting Section 302 of the Restatement, we stated:
    {¶ 25} “ ‘(1) Unless otherwise agreed between promisor and promisee, a
    beneficiary of a promise is an intended beneficiary if recognition of a right to
    performance in the beneficiary is appropriate to effectuate the intention of the
    parties and either
    {¶ 26} “ ‘(a) the performance of the promise will satisfy an obligation of
    the promisee to pay money to the beneficiary; or
    {¶ 27} “ ‘(b) the circumstances indicate that the promisee intends to give
    the beneficiary the benefit of the promised performance.’ ” (Emphasis added.)
    Hill at 40.
    {¶ 28} Contrary to the holding of the majority as expressed in the syllabus
    in this case, the plain language of Section 302 of the Restatement does not require
    the parties to a contract to indicate their intention to benefit a third party in the
    terms of the contract. As Professor John E. Murray Jr. explains in Corbin on
    Contracts, “The critical right of a third party is the right to sue the promisor.
    [However], the promisor and promisee will almost never state that intention
    explicitly. Nonetheless, the critical test is whether the language of the contract,
    the extrinsic evidence interpreting that language and all of the surrounding
    circumstances manifest an intention by the promisee and promisor to confer that
    right on the third party. If so, it is ‘appropriate’ for a court to recognize that right
    in the third party.” (Footnotes omitted.) 9 Corbin on Contracts (2007) 65-66,
    Section 44.6.
    {¶ 29} Thus, courts applying the same Restatement test that we adopted in
    Hill recognize that “ ‘[a] court in determining the parties’ intention should
    consider the circumstances surrounding the transaction as well as the actual
    language of the contract.’ ” Subaru Distribs. Corp. v. Subaru of Am., Inc. (C.A.2,
    2005), 
    425 F.3d 119
    , 124, quoting Restatement Section 302, Reporter’s Note,
    10
    January Term, 2011
    comment a; see also Pub. Serv. Co. of New Hampshire v. Hudson Light & Power
    Dept. (C.A.1, 1991), 
    938 F.2d 338
    , 342; Beverly v. Macy (C.A. 11, 1983), 
    702 F.2d 931
    , 940; Hickman v. SAFECO Ins. Co. of Am. (Minn.2005), 
    695 N.W.2d 365
    , 370; 13 Lord, Williston on Contracts 67-68, Section 37:8 (noting that most
    jurisdictions follow this rule).     As the Eleventh Circuit Court of Appeals
    explained in Beverly, “when determining whether the parties to the contract
    intended to bestow a benefit on a third party, a court may look beyond the
    contract to the circumstances surrounding its formation.” 702 F.2d at 940.
    {¶ 30} We have never held that the intention to benefit a third party must
    be indicated in the contract. In fact, the court in Anderson v. Olmsted Util.
    Equip., Inc. (1991), 
    60 Ohio St.3d 124
    , 
    573 N.E.2d 626
    , looked both to the terms
    of the contract and to extrinsic evidence of the intent of the parties to determine
    whether third parties could enforce the contract. In that case, the city of Niles had
    contracted with Olmsted Utility Equipment to inspect and repair the hydraulic
    arm of the city’s “cherry picker” truck before remounting it on a new truck.
    Anderson and Carlson, electrical linemen employed by the city, were
    subsequently injured when the arm failed and they fell to the ground. They sued
    Olmsted Utility Equipment, asserting that it had breached the express warranty
    made to the city.
    {¶ 31} We rejected the argument that Anderson and Carlson were at most
    incidental beneficiaries of the contract, stating:
    {¶ 32} “[I]n this case, it is clear to us that the city, as promisee, intended
    that Anderson and Carlson benefit from the contract. The specific terms of the
    contract provided that ‘[t]he City of Niles is interested in having this equipment
    rebuilt to 100% Holan specifications and safety.’ (Emphasis added.) In addition,
    when questioned at trial concerning the inspection and rebuilding of the aerial
    device, Charles Burgess, the superintendent of the city's light department, testified
    11
    SUPREME COURT OF OHIO
    that the purpose of rebuilding the aerial device was for safety of linemen who
    were to use the truck.
    {¶ 33} “Indeed, Anderson and Carlson were not merely incidental
    beneficiaries but were, in all respects, intended beneficiaries under the contract.”
    Anderson, 60 Ohio St.3d at 130, 
    573 N.E.2d 626
    .
    {¶ 34} Accordingly, the rule is not that “the contract must indicate an
    intention to benefit [the] third party.” Majority opinion at the syllabus. Rather,
    the test is whether “ ‘recognition of a right to performance in the beneficiary is
    appropriate to effectuate the intention of the parties and * * * the circumstances
    indicate that the promisee intends to give the beneficiary the benefit of the
    promised performance.’ ” Hill, 36 Ohio St.3d at 40, 
    521 N.E.2d 780
    , quoting
    Restatement, Section 302.
    {¶ 35} Here, the language of the contract and the circumstances
    surrounding its formation do not show that either Ohio Edison or Asplundh
    intended to give Huff the benefit of the promised performance. Since Huff is not
    a third-party beneficiary of the contract, she had no right to enforce its
    performance.    I therefore agree with the majority that the court of appeals’
    judgment should be reversed because Huff is not a third-party beneficiary of the
    contract. However, because the majority modifies the third-party beneficiary rule
    in Ohio by requiring that the contract—rather than the surrounding
    circumstances—indicate an intention to benefit a third party, I concur in its
    judgment but not its statement of law.
    PFEIFER, J., concurs in the foregoing opinion.
    __________________
    Betras, Kopp & Harshman, L.L.C., and David Betras, for appellees.
    Harrington, Hoppe & Mitchell, Ltd., and John T. Dellick, for appellant
    Ohio Edison Company.
    12
    January Term, 2011
    Reminger Co., L.P.A., Clifford C. Masch, Brian D. Sullivan, and Martin
    T. Galvin, for appellant Asplundh Tree Expert Company.
    ______________________
    13
    

Document Info

Docket Number: 2010-0857

Citation Numbers: 2011 Ohio 5083, 130 Ohio St. 3d 196

Judges: Brown, Cupp, Lanzinger, Lundberg, McGee, O'Connor, O'Donnell, Pfeifer, Stratton

Filed Date: 10/5/2011

Precedential Status: Precedential

Modified Date: 8/31/2023

Cited By (17)

United Gulf Marine, L.L.C. v. Continental Refining Co., L.L.... , 2019 Ohio 666 ( 2019 )

Calypso Asset Mgt., L.L.C. v. 180 Indus., L.L.C. , 2021 Ohio 1171 ( 2021 )

Starr v. Ohio Dept. Commerce, Div. of Real Estate & ... , 2021 Ohio 2243 ( 2021 )

Asia-Pacific Futures Research Symposium Planning Commt. v. ... , 2016 Ohio 2691 ( 2016 )

Boatwright v. Penn-Ohio Logistics , 2012 Ohio 6238 ( 2012 )

Dynamics Research Corp. v. Ohio Dept. of Job & Family Servs. , 2014 Ohio 516 ( 2014 )

Bierl v. BGZ Assoc. II, L.L.C. , 2013 Ohio 648 ( 2013 )

Savoy Hospitality, L.L.C. v. 5839 Monore St. Assocs., L.L.C. , 2015 Ohio 4879 ( 2015 )

Coman v. Coman , 2016 Ohio 464 ( 2016 )

Zipkin v. FirstMerit Bank, N.A. , 2021 Ohio 2583 ( 2021 )

Taylor v. Honda Motorcars, Inc. , 2019 Ohio 1891 ( 2019 )

Torrance v. Rom , 2020 Ohio 3971 ( 2020 )

Metro Renovations 12, L.L.C. v. Sabir , 2023 Ohio 1867 ( 2023 )

APCO Industries, Inc. v. Braun Constr. Group, Inc. , 2020 Ohio 4762 ( 2020 )

Johnson v. U.S. Title Agency, Inc. , 91 N.E.3d 76 ( 2017 )

Image Group of Toledo, Inc. v. Holland-Springfield Twp. ... , 93 N.E.3d 343 ( 2017 )

Meinert Plumbing v. Warner Industries, Inc. , 90 N.E.3d 966 ( 2017 )

View All Citing Opinions »