Metro Renovations 12, L.L.C. v. Sabir , 2023 Ohio 1867 ( 2023 )


Menu:
  • [Cite as Metro Renovations 12, L.L.C. v. Sabir, 
    2023-Ohio-1867
    .]
    COURT OF APPEALS
    FAIRFIELD COUNTY, OHIO
    FIFTH APPELLATE DISTRICT
    METRO RENOVATIONS 12, LLC,                         :           JUDGES:
    :           Hon. William B. Hoffman, P.J.
    Plaintiff - Appellee                       :           Hon. John W. Wise, J.
    :           Hon. Craig R. Baldwin, J.
    -vs-                                               :
    :
    BILAL SABIR, ET AL.,                               :           Case No. 2022 CA 00022
    :
    Defendants - Appellants                    :           OPINION
    CHARACTER OF PROCEEDING:                                       Appeal from the Fairfield County
    Court of Common Pleas, Case No.
    20 CV 243
    JUDGMENT:                                                      Reversed in Part and Affirmed in
    Part
    DATE OF JUDGMENT:                                              June 6, 2023
    APPEARANCES:
    For Plaintiff-Appellee                                         For Defendants-Appellants
    MICHELLEA TENNIS                                               FELICE HARRIS
    DANIEL FRUTH                                                   Harris Law Firm, LLC
    Stebelton Snider LPA                                           Reynoldsburg, Ohio 43068
    109 N. Broad Street, Suite 200
    P.O. Box 130
    Lancaster, Ohio 43130
    Fairfield County, Case No. 2022 CA 00022                                               2
    Baldwin, J.
    {¶1}   Bilal and Faatimah Sabir appeal the Fairfield County Court of Common
    Pleas judgment in favor of appellee, Metro Renovations 12, LLC. The Sabirs also appeal
    the trial court’s decisions finding that Bilal Sabir acted in bad faith and that Faatimah Sabir
    was liable for attorney’s fees and court costs. The Sabirs also assign as error the trial
    court’s decision barring Sabirs’ expert from tendering an opinion regarding the percentage
    of completion of the project and they contend the trial court improperly took judicial notice
    of evidence outside the record.
    STATEMENT OF THE FACTS AND THE CASE
    {¶2}   Appellant, Bilal Sabir, is a veteran of the Vietnam war who suffered a
    disabling injury during his service. Faatimah Sabir is his spouse and also serves as his
    veteran’s affairs fiduciary. Together they determined that Bilal’s quality of life could be
    improved by modifications to his home that would increase his mobility and preserve his
    independence. They sought and were granted a sum of money from the Department of
    Veteran’s Affairs (VA) to complete renovations to Sabir Bilal’s home to enable him to “‘live
    more independently in a barrier-free environment.’ VA Manual 26-12, Chapter 1-3.”
    (Judgment Entry, March 23, 2022, p. 1; Exhibit 18, p. 1-4). The total amount allotted for
    this Special Adaptive Housing Grant (SAH) was $81,080.00.
    {¶3}   Metro Renovations 12, LLC (Metro) is a contractor with experience in
    renovation and construction of residential properties, but with no experience in completing
    renovations financed through a Specially Adapted Housing Grant financed by the VA.
    Bilal contacted Metro about completing the renovations to his home, and Metro, interested
    Fairfield County, Case No. 2022 CA 00022                                            3
    in expanding their business into completion of SAH projects, agreed to meet with the
    Sabirs to discuss the project.
    {¶4}   After discussion the parties entered into an agreement for the completion of
    renovations to the home. The Agreement was comprised of a three-page contract, plans
    and a material list all of which were either signed or initialed by Bilal. This document was
    then approved by SAH Agent, Rand Barnes, as meeting the VA's minimum property
    requirements. (Exhibit 18, p. 5-8; Exhibits 21, 25).
    {¶5}   During the hearing Faatimah repeated that she was Bilal’s VA fiduciary,
    implying that her presence or her approval was necessary for a valid contract. Neither
    Faatimah nor Bilal provided further insight regarding the purpose or breadth of her
    fiduciary authority and it is evident that she had no concern regarding his entering the
    Agreement at the time it was signed. During the trial, she acknowledged that she was
    aware that Bilal was executing the documents and that she was at work and was unable
    to attend the signing. There is no evidence that she took advantage of the opportunity to
    review the documents before or after they were approved by Bilal.
    {¶6}   The contract provided no initial payment, then five separate disbursements
    at specific stages of the project. The first disbursement was $10,000; the second
    disbursement was $28,800; the third disbursement was to be $14,000 the fourth
    disbursement was $12,000; and the final disbursement would represent 20.08 % of the
    contract or $16,280 for a total contract amount of $81,080.00. (Exhibit 40). Under the
    terms of the contract, the first four disbursements would occur after inspection and
    approval by the SAH agent with no requirement that Bilal be consulted for his input or
    Fairfield County, Case No. 2022 CA 00022                                              4
    approval. Disbursement of the final amount required the written approval of the SAH
    agent and Bilal Sabir.
    {¶7}   The contract expressly states that only Bilal and Metro are parties to the
    contract but the VA retained the authority to inspect and confirm that Metro’s work
    “conforms to the contract, plans and/or specifications submitted to and approved by the
    VA” prior to the disbursement of any funds. (Exhibit 1, ⁋ I, VI, VIII; Exhibit 40). The fact
    that disbursements were made by the VA to Metro confirms that the SAH agent approved
    Metro’s work. While the Sabirs expressed frustration with the SAH agent and the VA,
    disagreed with their assessment of Metro’s work, and at one point insisted that a new
    SAH agent be assigned to their case, they did not include the SAH agent or the VA in this
    matter, so the approval of the SAH agent and the disbursement of funds subject to that
    approval are not at issue.
    {¶8}   The contract was to be completed within approximately ninety days of the
    deposit of the funds into escrow, but the contract contained no express date upon which
    work was to be completed, nor did it state that time was of the essence. While the record
    contains a reference to delay in the start of work due to the completion of unidentified
    documentation, it is not possible to determine with certainty who was responsible for that
    delay. Metro did begin work on the renovations in October. (Trial Transcript, p. 302, lines
    9-14).
    {¶9}   The details of the contract changed significantly when it was discovered that
    the municipality would not issue a permit for the changes to the Sabirs’ deck. The Sabir’s
    assumed responsibility for obtaining that permit, explained that they intended to pursue
    litigation over that issue but did not succeed in obtaining a permit. Metro had completed
    Fairfield County, Case No. 2022 CA 00022                                           5
    preparation of the porch and the deck, but halted all work when it became clear that no
    permit was to be issued to complete the deck. The modifications to the deck and the porch
    were removed from the scope of the contract and the price reduced by $14,000.00.
    {¶10} The Sabirs requested additions to the contract including a generator, ceiling
    fan, smart thermostat, fireplace tile and sump pump repair, but these items were not part
    of the SAH grant. Metro completed work regarding some of those items and issued a
    separate invoice, but the Sabirs made no payment.
    {¶11} Metro began work on the home in October 2018 while the Sabirs were out
    of the home. When the Sabirs decided to move back into the home in November 2018
    the work was not yet completed and progress was slowed due to their presence. With the
    Sabir’s in the home, Metro felt restrained to work only normal business hours and no
    earlier or later.
    {¶12} The Sabir’s were originally pleased with the work performed by Metro, at
    one point concluding a text message with a comment that “* * * overall I am quite pleased
    with your work and you.” Exhibit 39, p. 5. The relationship soured later and the comments
    were not complementary. One of the last texts offered in Exhibit 39 reflects a comment
    from the Sabirs: “Curse you, and your lying mother, may you go out of business very, very
    soon! I hope you get nothing but Curse after Curse on you, your lying mother and your
    worthless bullshit business!” These comments were in response to a request from Metro:
    “VA has proved their unwillingness to help you or us. The court system hasn't been
    favorable for you either. You ready to talk and figure this out without our lawyer and VA?
    Or should we continue to let this money sit and escrow where neither of us can touch it?
    IM(sic) sick of all this red tape with having them involved. Let me know if you'd like to
    Fairfield County, Case No. 2022 CA 00022                                             6
    come to a decision together so we can move forward in life.” (Exhibit 30, p. 45). The
    dispute between the parties was not resolved and the current litigation is the result.
    {¶13} The point at which the relationship broke down is not clear from the record.
    The Sabirs were frustrated that the project was not completed in the time frame they
    anticipated. When they discovered that Metro installed a laminate flooring instead of the
    wood that they expected, the relationship between the parties became more adversarial.
    Metro considered the project ninety-five to ninety-seven percent complete but they stated
    they were unable to complete the project because the Sabirs would not let them enter the
    home. Metro claimed that it made several attempts to enter the home or agree to a plan
    to finish the work, but they were not permitted access beginning in December 2018. The
    Sabirs claim they never prevented Metro from entering the home, but a comment of
    Faatimah Sabir regarding access suggests that permission was limited: “They were
    welcome to come back during the time that was allotted for them for the contract.” (Trial
    Transcript, Volume II, page 315, lines 18-20).
    {¶14} The VA attempted to assist with mediation, but that effort was unsuccessful
    and Metro claimed that the Sabirs continued to keep them from entering the home and
    completing the work.
    {¶15} On April 2, 2019, the Sabirs filed a small claims complaint in Franklin
    County, seeking to recover hotel expenses and boarding expenses for their pets they
    attributed to Metro. (Trial Transcript, page 282, line 20 to page 283, line 3; page 288, line
    8; page 314, lines 1-2, 11-12). Once the lawsuit was filed, the VA no longer attempted to
    engage in any mediation between the parties. On April 8, 2019 the Sabirs delivered an
    email to the VA and Metro explaining that they had lost all confidence in Metro and the
    Fairfield County, Case No. 2022 CA 00022                                              7
    lack of confidence is why Bilal “has not decided to proceed with choosing any options
    presented.” (Exhibit 31).
    {¶16} The small claims complaint was dismissed and the dispute between the
    parties remained unresolved. Metro contends it offered to discuss a resolution of the
    matter with the Sabirs, but claims that their attempts were rejected. Bilal expressed his
    anger and frustration in expletive riddled texts he delivered to Metro toward the end of
    2019.
    {¶17} On July 17, 2020, Metro filed a complaint in the Fairfield County Court of
    Common Pleas alleging that Bilal had breached the contract and that the Sabirs had been
    unjustly enriched as a result of the labor and materials provided by Metro. The Sabirs
    responded by filing an answer and counterclaim alleging Metro breached the contract,
    that Metro was negligent and damaged the home and that Metro had been unjustly
    enriched as a result of the payment of services that were of no value to the Sabirs. The
    Sabirs also filed a third-party action against Esteban Ceron, a member of Metro,
    individually, claiming that his negligence was a direct and proximate cause of damages
    to the Sabirs. This third-party complaint was withdrawn prior to the trial court deciding the
    matter.
    {¶18} Prior to trial there was a dispute regarding the Sabirs’ identification of their
    expert witnesses and compliance with Civ.R. 26. After submission of motions, the trial
    court ordered that the Sabirs provide Metro the curriculum vitae and compensation
    schedule of the experts that they intend qualify as an expert witness on or before March
    7, 2022 and warned that “failure to do so will result in the court precluding defendants
    from soliciting expert testimony from these witnesses.” (Magistrate Order, March 4, 2022).
    Fairfield County, Case No. 2022 CA 00022                                             8
    On March 7, 2022 the Sabir’s filed a document stating that they were “unable to comply
    with the magistrate’s order * * * will proceed with only the expert testimony of Richard
    Acree.”
    {¶19} The case was presented to the trial court on March 15, 2022 and completed
    the following day. On March 23, 2022 the trial court issued a lengthy judgment entry
    awarding plaintiff the amount of $28,290.00 and dismissing plaintiff’s second cause of
    action regarding unjust enrichment for lack of evidence showing an increase in value of
    the Sabirs’ home. The Sabirs’ counterclaim was dismissed. The trial court also ruled that
    “[b]ecause the Defendant filed a small claims lawsuit against the sole owner of the Plaintiff
    during the execution of the contract, essentially preventing a workable solution being
    reached in good faith, this court will award attorney fees to the Plaintiff as well as assess
    court costs upon the Defendants.” (Judgment Entry, March 23, 2022, page 4).
    {¶20} The parties filed pleadings regarding the attorney fees and, on June 7, 2022
    the trial court awarded Metro attorney fees and costs in the amount of $20,548.41.
    {¶21} The Sabirs filed a notice of appeal and submitted six assignments of error:
    {¶22} “I. THE TRIAL COURT ERRED AS A MATTER OF LAW IN HOLDING
    FAATIMAH SABIR LIABLE FOR ATTORNEYS FEES AND COURT COSTS.”
    {¶23} “II. THE TRIAL COURT ERRED IN FINDING BILAL SABIR "BREACHED
    THE WRITTEN CONTRACT BY REFUSING TO ALLOW PLAINTIFF TO COMPLETE
    THE CONTRACT FOR CONSTRUCTION SERVICES RENDERED UNDER THE
    CONTRACT.”
    Fairfield County, Case No. 2022 CA 00022                                              9
    {¶24} “III. THE TRIAL COURT ERRED IN DISMISSING DEFENDANT-
    APPELLANTS(SIC) FIRST DEFENSE AND COUNTERCLAIM AGAINST METRO
    RENOVATIONS 12, LLC.”
    {¶25} “IV. THE TRIAL COURT ERRED IN PROHIBITING DEFENDANTS'
    EXPERT FROM TENDERING AN OPINION AS TO METRO'S PERCENTAGE OF
    COMPLETENESS.”
    {¶26} “V. THE TRIAL COURT ERRED IN FINDING DEFENDANT, BILAL SABIR,
    ACTED IN BAD FAITH.”
    {¶27} “VI. THE TRIAL COURT ERRED IN TAKING IMPROPER JUDICIAL
    NOTICE OF EVIDENCE OUTSIDE THE RECORD.”
    STANDARD OF REVIEW
    {¶28} The issues presented in this appeal implicate different standards of review.
    This court reviews de novo issues of law, including the sufficiency of the evidence, See
    N. Side Bank & Trust Co. v. Trinity Aviation LLC, 
    2020-Ohio-1470
    , 
    153 N.E.3d 889
    , ¶ 17
    (1st Dist.), but reviews fact finding under a deferential standard of review. In weighing the
    evidence, we must presume that the findings of the trier of fact are correct, and if the
    evidence is susceptible of more than one construction, as a reviewing court, we must give
    it that interpretation that is consistent with the verdict or finding and judgment. Eastley v.
    Volkman, 
    132 Ohio St.3d 328
    , 
    2012-Ohio-2179
    , 
    972 N.E.2d 517
    , ¶ 21.
    {¶29} While the standard of review in a breach of contract action is whether the
    trial court erred as a matter of law, the Sabirs’ assignments of error focus on factual
    issues. Unifund, CCR, L.L.C. v. Johnson, 8th Dist. Cuyahoga No. 100600, 2014–Ohio–
    Fairfield County, Case No. 2022 CA 00022                                            10
    4376 ¶ 7, citing Arrow Unif. Rental LP v. Wills, Inc., 6th Dist. Wood No. WD–12–057,
    2013–Ohio–1829. To the extent a legal issue is addressed, we must “determine whether
    the trial court's order is based on an erroneous standard or a misconstruction of the law.”
    
    Id.
     At the same time, due deference must be given to the trial court's findings of fact if
    supported by competent, credible evidence. State v. Clements, 5th Dist. No. 08 CA 31,
    2008–Ohio–5549 ¶ 11.
    THE CONTRACT
    {¶30} The contract between Bilal Sabir and Metro warrants examination prior to
    beginning our analysis as it differs significantly from the more common construction
    contract. The renovations to be completed under the contract were funded by a grant
    from the Department of Veteran’s Affairs. In exchange for the grant, Bilal empowered the
    VA to inspect and approve the work that was completed as well as certify that Metro’s
    work complied with the applicable Minimum Property Requirements (MPR), the Special
    Adaptive Housing Requirements and the plan that had been approved by the VA. While
    the contract explicitly states that the VA is not a party to the contract, it possessed
    authority to conclude that the work performed by Metro satisfied the requirements of the
    contract and to pay for that work. We find this significant because the Sabirs are
    contradicting the findings of the VA and claiming the work did not fulfill the terms of the
    contract and violated the MPR’s, raising the question of whether the VA should have been
    included as a party to this action.
    {¶31} The contract between Bilal Sabir and Metro was subject to the requirements
    established by the VA, the most relevant of which to this matter is that the funds be held
    in escrow subject to the completion of the process for the release of those funds to the
    Fairfield County, Case No. 2022 CA 00022                                              11
    contractor. VA Manual 26-12, captioned Specially Adapted Housing Grant Processing
    Procedures Loan Guaranty Operations for Regional Offices (Manual) (Exhibit 18)
    contains an explanation of the regulations controlling the use and application of SAH grant
    funds. The Manual provides a clear requirement that the grant monies be deposited by
    the veteran, in this case Bilal, into an escrow account where they are to be held pending
    authorization of their release. (Manual, p. 8-2). Paragraph VIII of the contract provides
    that “Payment will be in accordance with VA procedures and in accordance with the
    disbursement schedule agreed to by the contractor and VA. It is understood that no
    payment will be made "up-front", and that there will be a holdback of 20% after the job is
    complete subject to final approval by VA and the veteran.” (Exhibit 1, p. 3).
    {¶32} Funds held in escrow are to be disbursed only after fulfilling the
    requirements of the Manual. At appropriate stage of the project, a Compliance Inspector
    (CI) who has been assigned to the project completes an inspection to ensure that the
    work completed by the contractor fulfills the term of the contract.
    {¶33} The purpose of a compliance inspection is to verify compliance of individual
    construction phases, or turn-key construction, for all Specially Adapted Housing (SAH)
    and Special Housing Adaptation (SHA) grant projects in which grant funds are being
    disbursed to a builder. The compliance inspection is used to certify that the property has
    been constructed in accordance with Department of Veterans Affairs (VA) approved plans
    and specifications, including SAH minimum property requirements (MPs) and
    recommended adaptations (RAs).
    {¶34} VA can authorize the release of grant funds to the builder only after:
    Fairfield County, Case No. 2022 CA 00022                                             12
    •   A compliance inspection has been completed by a VA-assigned
    compliance inspector (CI).
    •   A VA Form 26-1839, Compliance Inspection Report (CIR), indicating
    "no evidence of noncompliance observed" is received.
    •   The CIR has been reviewed and approved by the SAH Agent.
    Manual, page 7-2.
    {¶35} The parties acknowledge the authority of the VA to conduct the compliance
    inspections: “We, the undersigned, do hereby acknowledge and agree to periodic
    inspections and final approval by a VA compliance inspector and/or SAH agent of the
    above reference construction to assure that the construction conforms to the contract,
    plans and/or specifications submitted to and approved by the VA” and that payment will
    be made in accordance with VA procedures.” (Exhibit 18, page 3).
    {¶36} Upon the CI’s report of compliance, the escrow agent is authorized to issue
    payment to the contractor. As noted in the Escrow Agreement signed by Bilal, “The
    Veteran agrees that for the purpose of this Agreement the VA Representative is
    authorized to consent on his/her behalf to disbursements of escrowed funds by the
    Escrowee to such payees, in such amounts and at such times as the VA Representative
    considers proper to fulfill the purposes and conditions of this Agreement.” The Manual
    does provide that a signed letter of satisfaction from the Veteran is needed prior to the
    release of the final 20% of the contract amount, but this contract stalled prior to the final
    compliance inspection, and no Final Field Review was completed, so those provisions
    are not applicable. (Manual, p. 5-26, 7-10, 8-9, 8-11, 10-2).
    Fairfield County, Case No. 2022 CA 00022                                            13
    {¶37} The record in this case contains evidence demonstrating that two
    disbursements were made by the VA to Metro, consequently the trial court had before it
    evidence to support a conclusion that the VA completed at least two compliance
    inspections and found that Metro had completed construction “in accordance with
    Department of Veterans Affairs (VA) approved plans and specifications, including SAH
    minimum property requirements (MPRs) and recommended adaptations (RAs).”
    {¶38} We review the Sabirs assignments of error in the context of this unique
    contractual arrangement.
    ANALYSIS
    {¶39} As a preliminary matter, we will address the first assignment of error
    regarding the award of attorney fees and costs against Faatimah Sabir with the fifth
    assignment of error addressing the finding of bad faith on the part of Bilal Sabir as it is
    the more logical place for that assignment.
    II.
    {¶40} In their second assignment of error, the Sabirs argue that the trial court
    erred in finding that Bilal breached the written contract by refusing to allow Metro to
    complete the contract. The Sabirs offer citations to parts of the record reflecting
    correspondence regarding their request to have Metro complete parts of the project or
    make corrections, but it is evident that most of these exchanges occurred in the early part
    of December 2018. Metro offered testimony that supports a conclusion that it was
    excluded from the home “somewhere between December and January” or after much of
    the correspondence the Sabirs describe in their brief. (Trial Transcript, Vol. I, p. 129).
    Metro claims that it did send working crews to the home and that the Sabirs did not permit
    Fairfield County, Case No. 2022 CA 00022                                                 14
    them to enter. This rejection is confirmed in the email, delivered January 24, 2019 and
    admitted as Exhibit 27 where a representative from the VA states:
    * * I believe it will take some cooperation. It will also take your cooperation
    for Metro to be able to correct any defects that may exist in the work already
    completed.
    It seems that Metro is willing to attempt to address your concerns,
    but you must be willing to let them. In addressing any issues, Metro only
    must comply with the signed contract. No party of that contract is bound to
    any new terms, conditions, and/or materials that have not been agreed to
    by all parties and then formally adopted as a part of the contract.
    We all want resolution and we all want your satisfaction with the
    completed work. The work and materials are clearly defined in your
    husband's contract with Metro. The builder needs to be able to resume work
    to finish the project in accordance with the contract.
    {¶41} Both witnesses who testified on behalf of Metro confirmed that they
    attempted to return to the site to complete the work and correct errors, but were not
    permitted access. (Trial Transcript, p. 59, lines 8-15; p. 131, line 7 to p. 132, p. 2). In
    response to a question regarding Metro being locked out of the premises, Faatimah
    responded in a manner that suggests that Metro’s access was limited by Faatimah’s belief
    that the contract was subject to a fixed date of completion:
    You're insisting that you did not lock Plaintiff off your property; that
    they were always welcome to come back. Right? Was that your testimony?
    Fairfield County, Case No. 2022 CA 00022                                            15
    They were welcome to come back during the time that was allotted
    for them for the contract.
    Trial Transcript, p. 315, lines 14-10.
    {¶42} This court relies on the trial court to resolve disputed issues of fact and
    weigh the testimony and credibility of the witnesses. Bechtol v. Bechtol, 
    49 Ohio St.3d 21
    ,
    23, 
    550 N.E.2d 178
     (1990). We defer to the trial court's discretion because the trial court
    had the opportunity to observe the witnesses and parties in weighing the credibility of the
    proffered testimony in a way a reviewing court cannot. The Sabirs sole issue in this
    assignment of error questions the factual finding of the trial court regarding whether the
    Sabirs prevented Metro from completing the contract. The parties provided contradicting
    evidence regarding whether Metro was permitted to enter the home to complete the
    contract and the resolution of that issue required the trial court to resolve the dispute
    based upon the weight of the testimony and the credibility of the witnesses. We find that
    the trial court’s decision is supported by competent, credible evidence and that the trial
    court did not abuse its discretion in finding that the Sabir’s prevented Metro from entering
    the home and completing the contract.
    {¶43} The second assignment of error is denied.
    III.
    {¶44} In their third assignment of error, the Sabirs contend that the “trial court
    erred in dismissing Defendant-Appellants first defense and counterclaim against Metro
    Renovations 12, LLC.” The Sabirs argue that Metro failed to meet the contractual
    Fairfield County, Case No. 2022 CA 00022                                             16
    completion date, failed to complete the work in a workmanlike manner and fulfill the
    minimum property requirements and erred in addressing damages.
    COMPLETION DATE
    {¶45} The contract contains a section captioned VII. COMMENCEMENT AND
    COMPLETION SCHEDULE that includes the following:
    The work specified above shall be started on or about: Within two
    weeks of the grant check being placed in the escrow account.
    Completed on or about: within ninety days of the start date.
    {¶46} The Sabirs contend “the contract includes a date of completion” (Appellant’s
    Brief, page 15) but no such date appears in the contract. As noted above there is a
    commencement and completion schedule which gives general instructions when the work
    is to begin and when it should be completed but no specific date for commencement or
    completion. The description of the commencement and completion as being “on or about”
    an unspecified date further undermines the Sabirs’ contention that the contract was
    subject to a specific completion date.
    {¶47} The contract provides work was to begin on or about “within two weeks of
    the grant check being placed in the escrow account.” The Escrow Agreement, Exhibit 40,
    was signed by Bilal on October 16, 2018, and the terms of that Agreement provide that
    Bilal was to deposit the check on the day it was executed. Metro was to begin work no
    later than October 30 and, though the first date of work is not recorded in an exhibit, Metro
    filed a Partial Unconditional Waiver of Lien dated October 29, 2018 for labor and materials
    Fairfield County, Case No. 2022 CA 00022                                             17
    provided prior to that date. (Exhibit 40, p. 5) Further, Sabir admitted in a response to a
    written interrogatory that the work began on October 17. (Trial Transcript, p. 302, lines 9-
    14). The record supports a conclusion that Metro began work in a timely manner.
    {¶48} We have concluded that the Sabir’s prevented Metro from entering the
    home and completing the work that remained unfinished in our resolution of the second
    assignment of error. That finding plays an important role in the resolution of this
    assignment of error as well. The delay caused by the Sabirs refusing access as well as
    any delay that may be attributable to the dispute over the permit for the deck, the vendor’s
    delay in delivering appliances and the need to work around the Sabirs when they returned
    to the home played a role in Metro’s inability to complete the project within ninety days of
    the start date. We cannot find that the trial court erred by not finding that Metro breached
    the contract by not completing the work in a timely manner.
    {¶49} If, arguendo, we disregard the delays outside the control of Metro, we must
    determine whether the date of completion was a material term of the contract. Ohio cases
    have held broadly that time of performance is not of the essence of a contract unless
    made so by its terms or by the acts of the parties. Hubbard v. Norton, (1875) 
    28 Ohio St. 116
    , para. 4 of the syllabus. Adams v. Walton, 5th Dist. Morrow No. 601, 
    1983 WL 5069
    ,
    *3; Accord Brown v. Brown, 
    90 Ohio App.3d 781
    , 784, 
    630 N.E.2d 763
    , 765 (11th
    Dist.1993), cause dismissed, 
    68 Ohio St.3d 1441
    , 
    626 N.E.2d 124
     (1994) We have
    searched the contract to determine whether “the contract expressly provided that the time
    for completing the project was ‘of the essence’ and that the project had to be substantially
    completed within [90] days of the date of the commencement of the project.” Boone
    Coleman Constr., Inc. v. Piketon, 
    145 Ohio St.3d 450
    , 
    2016-Ohio-628
    , 
    50 N.E.3d 502
    ,
    Fairfield County, Case No. 2022 CA 00022                                               18
    ¶ 3. The contract contains only the general description of the start date and completion
    date and no express completion date nor anything from which a reasonable person could
    imply that the parties had agreed that time was of the essence.
    {¶50} The parties did not make the time of completion an essential element of the
    contract and the trial court did not err in failing to find that Metro breached the contract by
    failing to complete the project in a timely manner.
    WORKMANLIKE MANNER AND MINIMUM PROPERTY REQUIREMENTS
    {¶51} Sabir urges us to find that Metro failed to complete the project in a
    workmanlike manner and did not satisfy the Minimum Property Requirements as required
    by the Manual. Minimum Property Requirements “are absolute conditions specified under
    governing law for the Specially Adapted Housing (SAH) grant.” (Manual, Appendix A, p.
    A-2). The parties agreed and the Manual requires that the VA Representative complete
    an inspection and find that the work complies with the plans and the MPR before funds
    are issued. The parties also agreed that payment would be issued upon the approval of
    the work by the VA. The VA issued two payments, one in the amount of $10,000.00 and
    one in the amount of $28,000.00 comprising the first two disbursements described in the
    Escrow Agreement. This information supports a conclusion that the VA found that Metro
    satisfied the terms of the contract and fulfilled the applicable MPRs.
    {¶52} The Sabirs did present the testimony of an expert who concluded that Metro
    failed to satisfy the MPRs, contradicting the implication to be drawn from the payment
    made by the VA. The trial court was required to weigh the evidence and testimony
    regarding compliance with the MPRs and the contract and we find that there was
    Fairfield County, Case No. 2022 CA 00022                                                 19
    sufficient, credible evidence to support a finding that Metro received approval of its work
    from the VA and, therefore, it satisfied the terms of the contract and the MPRs applicable
    to the stage of the project that had been completed.
    {¶53} The Sabirs’ expert, Richard Acree, completed a “limited accessibility
    survey” of the home and concluded that some elements were installed in error or omitted
    by Metro or exhibit poor workmanship. Acree submitted an extensive report containing a
    long list of criticisms and recommendations, but no comment regarding the approval
    received from the VA. Acree reviewed the projects as if the work had been completed,
    but Metro had been prevented from completing the project and the VA never had the
    opportunity to complete the final inspection, during which Bilal would have had the
    opportunity to reject Metro’s work and insist on changes or withhold distribution of the
    final 20% of the contract amount.
    {¶54} Also, Acree offers no information regarding whether the recommendations
    in his report could be completed with the grant money available.
    {¶55} We find that the record supports the trial court’s decision to give little weight
    to the report and that the trial court did not err by failing to find that Metro violated Minimum
    Property Requirements or that the work was not completed in a workmanlike manner.
    DAMAGES
    {¶56} The Sabirs contend that the trial court miscalculated damages, relying on a
    comment in an email from a VA Representative: “In reviewing the disbursement schedule,
    it seems that the builder is reasonably owed $12,000 to $15,000 based on stage 4 and
    taking into consideration a portion of the 20% holdback.” (Exhibit 34, page 3). This
    Fairfield County, Case No. 2022 CA 00022                                             20
    comment was made in the context of attempting to come to a compromise and does not
    appear to be offered as a firm figure. Further, that same email mentions that “[t]here is
    also some off contract work between the Sabirs and Metro Renovation that we have been
    made aware of for ceiling fans, the thermostat, the fireplace, and the sump pump. VA will
    not enforce any payment or agreement for that work that wasn't in the signed contract.
    The two parties can negotiate that separately without VA involvement. The builder could
    also use that additional work in lien proceedings.”
    {¶57} The amount that the “builder is reasonably owed” as described in this email
    was a factor that the trial court could consider, but was not a binding amount, does not
    appear to be calculated with accuracy and can interpreted as part of an effort to get the
    builder “out from under this” as quickly as possible. (Exhibit 34, page 1).
    {¶58} The Sabirs also complain that the trial court did not permit Faatimah to
    testify regarding damages and that it required expert testimony to establish damages. As
    we have concluded that the trial court did not err is dismissing the counterclaim, this issue
    is moot. However, even if we would consider the merits, our conclusion would not change.
    {¶59} Expert testimony is not always required to establish the necessity of repairs
    or the reasonableness of the costs incurred to repair such” McCoy v. Good, 2d Dist.
    No. 06–CA–34, 
    2007-Ohio-327
    , 
    2007 WL 196551
    , ¶ 21 as quoted in Evans Landscaping,
    Inc. v. Stenger, 1st Dist. No. C-110104, 
    2011-Ohio-6033
    , 
    969 N.E.2d 1264
    , ¶ 24, and lay
    persons can, in proper circumstances, testify regarding damages to property. In this case,
    Faatimah did not offer her own estimate of the damages, but only a comment regarding
    the conclusion of an expert who would not testify, so the trial court properly excluded it
    from the record. (Trial Transcript, p. 346). No other testimony from Faatimah or Bilal
    Fairfield County, Case No. 2022 CA 00022                                               21
    regarding damages was proffered, so we find that the trial court did not err in its handling
    of damages.
    {¶60} The third assignment of error is denied.
    IV.
    {¶61} In their fourth assignment of error, the Sabirs claim the trial court erred in
    prohibiting their expert from tendering an opinion as to Metro’s percentage of
    completeness.
    {¶62} Richard Acree, the Sabirs’ expert, was asked whether he felt he was
    competent to discuss the degree of completion and he stated “In most cases, yes” but he
    conceded that he had never been asked “to do this type of thing before.” (Trial Transcript,
    p. 607, lines 1-12). Thereafter the parties engaged in a lengthy discussion regarding the
    propriety of the testimony, initiated by the trial court’s comment that “This is too – it’s too
    dangerous of a ground to pursue.” (Trial Transcript, p. 609, lines 2-3). Metro’s counsel
    objected:
    MR. FRUTH: Your Honor, the problem here is that we're trying to stretch
    the witness beyond what he was disclosed to do.
    THE COURT: I agree.
    MR. FRUTH: And the reason we're trying to stretch the witness beyond what
    he was disclosed to do is because the other experts that would have
    competently addressed this issue were barred. So we're trying to make him
    do too much.
    Fairfield County, Case No. 2022 CA 00022                                                 22
    (Trial Transcript, p. 615, lines 7-17).
    {¶63} Ultimately the trial court decided the testimony would not be allowed. (Trial
    Transcript, p. 615, lines 18-19). Sabirs counsel responded “Okay” continued the
    questioning of Acree and did not proffer the excluded testimony nor any evidence that
    would establish Acree’s qualifications to provide an opinion regarding the percentage of
    completion.
    {¶64} “When the court's ruling is one excluding evidence, a party must proffer the
    evidence at trial to preserve the issue for appeal.” State v. Smith, 9th Dist. Wayne
    No. 15AP0001, 
    2017-Ohio-359
    , ¶ 19 as quoted in State v. Freed, 5th Dist. Fairfield
    No. 2019 CA 00018, 
    2020-Ohio-655
    , ¶ 28. The record in this case shows that the Sabirs
    were asking Acree to offer an opinion that he had not offered in any other case and which
    violated the court’s requirements regarding disclosure of witnesses. Without a proffer
    explaining the qualifications of the witness and the evidence to be offered, we cannot
    consider this assignment of error.
    {¶65} The fourth assignment of error is denied.
    I., V.
    {¶66} We will consider the first and the fifth assignment of error collectively as
    they are closely related. In the first assignment of error, the Sabirs claim that the trial court
    erred as a matter of law in holding Faatimah Sabir liable for attorney fees and court costs
    and in the fifth assignment of error they claim the trial court erred in finding Defendant,
    Bilal Sabir, acted in bad faith, presumably in an attempt to undermine the basis for an
    award of attorney fees against him.
    Fairfield County, Case No. 2022 CA 00022                                               23
    I.
    {¶67} When considering an award of attorney fees, Ohio follows the “American
    Rule,” under which a prevailing party in a civil action may not generally recover attorney
    fees. Wilborn v. Bank One Corp., 
    121 Ohio St.3d 546
    , 
    2009-Ohio-306
    , 
    906 N.E.2d 396
    ,
    ¶ 7. However, attorney fees may be awarded when a statute or an enforceable contract
    specifically provides for an award of attorney fees, or when the prevailing party
    demonstrates the losing party acted in bad faith. 
    Id.
     McHenry v. McHenry, 5th Dist.
    No. 2016CA00158, 
    2017-Ohio-1534
    , 
    88 N.E.3d 1222
    , ¶ 54. The Sabirs contend that
    Metro is not the prevailing party in relation to Faatimah as its only claim against her, unjust
    enrichment, was dismissed by the trial court “because there is no evidence in the record
    any(sic) appraisal that would indicate how much value the Defendants' home has
    increased because of the renovation work.” (Judgment Entry, March 23, 2022, p. 4).
    Metro implicitly concedes this point, but argues that the trial court reinstated Plaintiff’s
    claim for unjust enrichment against Faatimah Sabir or, in the alternative, that the trial court
    held she was a third-party beneficiary.
    {¶68} A prevailing party is generally the party “ ‘in whose favor the decision or
    verdict is rendered and judgment entered.’ ” Hagemeyer v. Sadowski (1993), 
    86 Ohio App.3d 563
    , 566, 
    621 N.E.2d 707
    , quoting Yetzer v. Henderson, 5th Dist. No. CA–1967,
    
    1981 WL 6293
     *2 (June 4, 1981). See also Falther v. Toney, 5th Dist. No. 05 CA 32,
    
    2005-Ohio-5954
    , 
    2005 WL 2995161
    . We find that with regard to the claim of unjust
    enrichment against Faatimah, Metro was not the prevailing party.
    {¶69} The trial court dismissed Metro’s unjust enrichment claim against Faatimah
    and we decline Metro’s invitation to interpret the trial court’s June 7, 2022 Judgment Entry
    Fairfield County, Case No. 2022 CA 00022                                             24
    Regarding Fees and Costs as a reinstatement of that claim. The Entry contains no
    reference to the unjust enrichment claim and contains no information that can be
    interpreted as reversing trial court’s March finding that Metro provided no evidence “that
    would indicate how much value the Defendants' home has increased because of the
    renovation work.”
    {¶70} Alternatively, Metro contends that Faatimah was found to be a third-party
    beneficiary when the trial court stated: “Despite the fact that Defendant Faatimah Sabir
    would sometimes act as her husband's veteran representative during the creation and,
    execution of the contract, both Faatimah Sabir and her husband would personally benefit
    from the improvements of the residence under the renovation contract.” (Judgment Entry,
    June 7, 2022, p. 3).
    {¶71} The trial court does not state that it is finding that Faatimah is a third-party
    beneficiary and we will not construe the entry to support such a conclusion. “Ohio law * *
    * requires that for a third party to be an intended beneficiary under a contract, there must
    be evidence that the contract was intended to directly benefit that third party.” Huff v.
    FirstEnergy Corp., 
    130 Ohio St.3d 196
    , 
    2011-Ohio-5083
    , 
    957 N.E.2d 3
    , ¶ 12. The
    Supreme Court of Ohio adopted the “intent to benefit” test to measure the rights and
    responsibilities of a third-party beneficiary and found that if Metro had intended that
    Faatimah should benefit from the contract she could be an intended beneficiary with rights
    under the contract but if Metro had no intent to benefit her, then she was an incidental
    beneficiary who has no enforceable rights under the contract. The court also noted that
    “the mere conferring of some benefit on the supposed beneficiary by the performance of
    a particular promise in a contract [is] insufficient; rather, the performance of that promise
    Fairfield County, Case No. 2022 CA 00022                                              25
    must also satisfy a duty owed by the promisee to the beneficiary.” Hill v. Sonitrol of
    Southwestern Ohio, Inc., 
    36 Ohio St.3d 36
    , 40, 
    521 N.E.2d 780
    , 784–85 (1988) quoting
    Norfolk & Western Co. v. United States (C.A.6, 1980), 
    641 F.2d 1201
    , 1208.
    {¶72} The trial court’s finding that Faatimah would personally benefit from the
    improvements is, at most, a finding that she is an incidental beneficiary and not a third-
    party beneficiary to the contract against whom Metro was the prevailing party.
    {¶73} Because Metro is not a prevailing party with regard to Faatimah, the trial
    court was not authorized to order her to pay attorney fees. The Sabirs’ first assignment
    of error is sustained.
    V.
    {¶74} In their fifth assignment of error, the Sabirs contend that the trial court erred
    in finding that Bilal acted in bad faith.
    {¶75} In the March 2022 Entry, the trial court stated: “Because the Defendant filed
    a small claims lawsuit against the sole owner of the Plaintiff during the execution of the
    contract, essentially preventing a workable solution being reached in good faith, this Court
    will award attorney fees to the Plaintiff as well as assess court costs upon the Defendants.
    The Plaintiff shall submit an attorney fee affidavit no later than April 7, 2022. A non-oral
    hearing shall take place on April 27, 2022 at 11 a.m.” (Judgment Entry, March 23, 2022,
    p. 4). After the parties filed pleadings regarding their respective positions, the trial court
    awarded attorney fees to Metro after considering “all of the actions taken by Defendants
    during the execution of the contract” the trial court found “that the Defendants acted in
    bad faith, wantonly and/or obdurately.” (Judgment Entry Regarding Attorney Fees And
    Costs, June 7, 2022, p. 1).
    Fairfield County, Case No. 2022 CA 00022                                            26
    {¶76} Attorney fees are not ordinarily recoverable but may be awarded where it is
    demonstrated that an action is defended in bad faith, namely, continuing litigation that is
    obdurate, vexatious, wanton, or engaged in for oppressive reasons. Sorin v. Bd. of Edn.
    (1976), 
    46 Ohio St.2d 177
     as quoted in State ex rel. Esselburne v. Maurer, 10th Dist.
    Franklin No. 89AP-953, 
    1991 WL 94443
    , *2. See also State ex rel. Butterbaugh v. Ross
    Cty. Bd. of Commrs., 
    79 Ohio App.3d 826
    , 837, 
    608 N.E.2d 778
    , 785 (4th Dist.1992)
    Though not specifically labeled as such, we find the trial court essentially found and the
    evidence supported, that the Sabirs acted obdurately; therefore, attorney fees incurred to
    enforce Metro’s contractual rights were recoverable for Sabirs’ breach of the contract.
    {¶77} Webster's dictionary defines “obdurately” as stubbornly persistent in
    wrongdoing; hardened in feeling; resistant to persuasion. Stambaugh v. T.C. Wood
    Realty, Inc., 5th Dist. Morrow No. 09 CA 00008, 
    2010-Ohio-3763
    , fn. 3 and the trial court
    cites to instances of such obdurate behavior. Both Sabirs insisted they were entitled to
    wood flooring despite the contract clearly reflecting that they had chosen a laminate
    flooring. They argued that the contract had been altered to allow Metro to install
    appliances they had not chosen, but the evidence reflected that the correct appliances
    where installed. The trial court found, and we have found that the record supports the
    conclusion that the Sabirs prevented Metro from finishing the contract and filed a small
    claims suit that was unsuccessful on its merits, but did serve to prevent resolution of the
    dispute.
    {¶78} Both Bilal and Faatimah complained that Metro’s work failed to fulfill
    applicable MPR’s and SAH standards and provided expert testimony to support that
    contention. Neither the Sabirs nor their expert addressed the fact that the VA was the
    Fairfield County, Case No. 2022 CA 00022                                              27
    sole arbiter of the quality of the work prior to the last disbursement and that the record
    shows that the VA had concluded that the work satisfied the SAH standards and MPR’s.
    The same expert criticized Metro’s exterior work when the parties had agreed that it was
    no longer part of the contract and Metro would receive no payment for any work involved
    in the demolition they had completed on that part of the project. Metro fulfilled its duties
    under the contract and the Sabirs expert’s opinion “truly didn’t matter” and only served to
    increase Metro’s litigation expenses. (Judgment Entry March 23, 2022, p. 3).
    {¶79} After a review of the record we find that the trial court did not abuse its
    discretion when it concluded that Bilal “acted in bad faith, wantonly and/or obdurately.”
    {¶80} The fifth assignment of error is denied.
    VI.
    {¶81} In their sixth assignment of error, the Sabirs assert that the trial court erred
    in taking improper judicial notice of evidence outside the record. The Sabirs contend that
    because the second filing date is included within the trial court’s June 7, 2022 entry, “it
    appears the trial court may have independently obtained information regarding the
    second filing and incorporated such information into its Judgment.” (Appellants’ Brief, p.
    27).
    {¶82} The record contains information regarding the small claims lawsuit filed by
    the Sabirs on April 2 that was dismissed and refiled in Fairfield County to recover money
    for the Sabirs’ hotel stay and boarding their dog. (Trial Transcript, p. 283, line 10 to p.
    284, line 2; p. 313, line 19, to p. 314, line 15). The Sabirs threatened to file a lawsuit and
    did file against the owner, Gloria Urrea. Both claims were dismissed. One case was
    dismissed for “the wrong court,” and one for suing the owner instead of the Metro. (Trial
    Fairfield County, Case No. 2022 CA 00022                                              28
    Transcript, p. 144, lines 22-24). The Sabirs notified the VA of the lawsuit and knew that
    the VA would “shut down” not “help anybody” and “everything is held up in escrow.” (Trial
    Transcript, p. 315, lines 1-12).
    {¶83} The trial court’s findings regarding the lawsuit are supported by the record.
    In the March Entry, the trial court found that “defendant had filed a small claims lawsuit
    against the owner of the plaintiff’s business on April 2, 2019 in the wrong jurisdiction and
    refiled days later in the proper jurisdiction.” The trial court concluded “because the
    defendant filed a small claims lawsuit against the sole owner of the plaintiff during the
    execution of the contract, essentially preventing a workable solution being reached in
    good faith, this court will award attorney fees to the plaintiff as well as assess court costs
    upon the defendants.” The June entry provides little additional information as the court
    found “that during the execution of the contract the defendants veteran representative
    (the defendant’s wife) filed a small claims lawsuit against the owner of plaintiff
    reimbursement of hotel expenses and dog boarding. This lawsuit was first filed in the
    wrong jurisdiction (Franklin County) on April 2, 2019. The small claims action was then
    refiled by the veteran representative in Fairfield County on June 11, 2019, before it was
    dismissed.”
    {¶84} The only fact contained within the judgment entries that is not found within
    the record is the date of June 11, 2019. The Sabirs attach unwarranted significance to
    this date and claimed that it is evidence that the trial court “may have independently
    obtained information regarding the second filing and incorporated such information into
    its judgment.” (Appellant’s Brief, p. 27). After reviewing the record, we find that the trial
    court’s findings are supported by the evidence in the record and that the date of June 11,
    Fairfield County, Case No. 2022 CA 00022                                               29
    2019 is inconsequential. Even if the trial court had committed an error by including this
    date, the error is not materially prejudicial to the Sabirs as we find that the absence of this
    error would not have changed the outcome of the proceedings. Fada v. Information Sys.
    & Networks Corp. (1994), 
    98 Ohio App.3d 785
    , 
    649 N.E.2d 904
     as quoted in Nilavar v.
    Osborn, 
    137 Ohio App.3d 469
    , 500, 
    738 N.E.2d 1271
    , 1293 (2nd Dist.2000).
    {¶85} The sixth assignment of error is overruled.
    Fairfield County, Case No. 2022 CA 00022                                      30
    {¶86} The decision of the Fairfield County Court of Common Pleas is reversed to
    the extent that it ordered Faatimah Sabir to pay attorney fees. The balance of the
    judgment is affirmed.
    By: Baldwin, J.
    Hoffman, P.J. and
    Wise, John, J. concur.