John R. Sand & Gravel Company v. United States , 457 F.3d 1345 ( 2006 )


Menu:
  •   United States Court of Appeals for the Federal Circuit
    05-5033
    JOHN R. SAND & GRAVEL COMPANY,
    Plaintiff-Appellant,
    v.
    UNITED STATES,
    Defendant-Appellee.
    Jeffrey K. Haynes, Beier Howlett, P.C., of Bloomfield Hills, Michigan, argued for
    plaintiff-appellant. With him on the brief was L. Rider Brice, III.
    Aaron P. Avila, Attorney, Environment & Natural Resources Division, United States
    Department of Justice, of Washington, DC, argued for defendant-appellee. With him on
    the brief were Kelly A. Johnson, Acting Assistant Attorney General; and Susan V. Cook,
    John S. Most, Steven D. Bryant, and Kathryn E. Kovacs, Attorneys.
    Steven C. Nadeau, Honigman Miller Schwartz and Cohn LLP, of Detroit, Michigan,
    for amici curiae Brunswick Corporation, et al. With him on the brief were Robert M.
    Jackson; and Robert K. Huffman, Miller & Chevalier Chartered, of Washington, DC.
    Appealed from: United States Court of Federal Claims
    Judge Emily C. Hewitt
    United States Court of Appeals for the Federal Circuit
    05-5033
    JOHN R. SAND & GRAVEL COMPANY,
    Plaintiff-Appellant,
    v.
    UNITED STATES,
    Defendant-Appellee.
    _______________________
    DECIDED: August 9, 2006
    _______________________
    Before NEWMAN, LOURIE, and SCHALL, Circuit Judges.
    Opinion for the court filed by Circuit Judge SCHALL. Dissenting opinion filed by Circuit
    Judge NEWMAN.
    SCHALL, Circuit Judge.
    John R. Sand and Gravel Company (“JRS&G”) appeals the final decision of the
    United States Court of Federal Claims, following a trial, that the United States was not
    liable to JRS&G under the Fifth Amendment to the Constitution for the alleged taking of
    JRS&G’s leasehold interest in a 158-acre tract of land in Lapeer County, Michigan.
    John R. Sand & Gravel Co. v. United States, 
    62 Fed. Cl. 556
     (2004) (“Sand & Gravel
    III”). Because we conclude that JRS&G did not file its complaint within the six-year
    limitations period of 
    28 U.S.C. § 2501
    , we hold that the Court of Federal Claims lacked
    jurisdiction. We therefore vacate the Court of Federal Claims’s decision and remand
    the case to the court with the instruction that it dismiss JRS&G’s complaint.
    BACKGROUND
    I.
    The pertinent facts, which are not in dispute, are set forth in John R. Sand &
    Gravel Co. v. United States, 
    57 Fed. Cl. 182
     (2003) (“Sand & Gravel I”), and Sand &
    Gravel III, 
    62 Fed. Cl. 556
    .
    In 1969, JRS&G leased a 158-acre tract of land in Metamora Township, Lapeer
    County, Michigan, from Russell and Mildred Parrish (“Parrish property”) for a term of
    fifty years. Sand & Gravel III, 62 Fed. Cl. at 558. Pursuant to the lease, JRS&G is
    entitled to the exclusive use of the property for the purpose of mining sand and gravel.
    Id. at 564.1
    The Parrish property consists of a rectangular area. Sand & Gravel I, 57 Fed. Cl.
    at 183 n.3. JRS&G’s operations are principally located in its plant area in the east-
    central portion of the property. JRS&G’s plant area contains several buildings, a supply
    pond, and customer access roads. Id. JRS&G’s main sand and gravel pit (“main pit”) is
    1
    According to the terms of the lease, JRS&G received “exclusive use” of
    the property
    for the purpose of stripping the land, taking out and removing
    therefrom the marketable stone and sand, which is, [or]
    which may hereafter be found on, in or under said land,
    together with the right to construct or build, and to make all
    excavations, pits openings, ditches, roadways and other
    improvements upon the said premises, which are or may
    become necessary or suitable for removing sand and stone
    from the said premises.
    Sand & Gravel III, 62 Fed. Cl. at 564.
    05-5033                                      2
    just southeast of the plant area. Id. A landfill is located to the north of JRS&G’s plant
    area. Id. The landfill is known as the Metamora Landfill. The features just described,
    as well as others, are shown on the map of the Parrish property that is titled “February
    1994 Fence Alignment Metamora Landfill Site.” The map is included with this opinion
    as Appendix A.
    The Area of Institutional Controls (“AIC”) comprises a 42-acre portion of the
    property to the north of JRS&G’s plant area. It encompasses the entirety of the landfill
    and some of the property surrounding the landfill wherein the landfill cap system is
    located.2 Id. at 185. The northern and eastern boundaries of the AIC run along the
    Parrish property lines. To the west, the AIC boundary runs just outside the edge of a
    gravel road. To the south, the AIC is located to the north of JRS&G’s siltation pond.
    The southern border of the AIC then cuts to the south to encompass the Stormwater
    Retention Pond.
    At the time JRS&G signed the lease in 1969, the landfill was already operating
    on the northern portion of the Parrish property. Sand & Gravel III, 62 Fed. Cl. at 560.
    The Parrishes continued to operate the landfill during the first eleven years of JRS&G’s
    leasehold until it closed in 1980. Id. at 559-60. During its years of operation, the landfill
    illegally accepted solid and liquid industrial waste in 55-gallon drums.            Tens of
    thousands of such drums are currently buried on the site. Id. at 570.
    2
    The landfill cap system involves a cap of impermeable material over the
    landfill. The cap is sloped to cause water to run off into a system of ditches. The
    ditches feed into a designated retention area away from the landfill. Id. at 560. The
    retention area is shown on the map at Appendix A under the heading “Storm Water
    Retention Pond.” The cap system prevents water from percolating through the
    hazardous waste in the landfill and into the aquifer below, thereby contaminating the
    groundwater.
    05-5033                                      3
    In 1984, the landfill was placed on the National Priorities List pursuant to the
    Comprehensive Environmental Response Compensation and Liability Act of 1980
    (“CERCLA”), 
    42 U.S.C. §§ 9601-9675
     (2000), due to the large number of drums
    containing hazardous waste that had been buried there. See Sand & Gravel III, 62 Fed.
    Cl. at 559. Pursuant to CERCLA, the Environmental Protection Agency (“EPA”) issued
    its first Record of Decision (“ROD”) in 1986.3 Sand & Gravel I, 57 Fed. Cl. at 183. In
    the 1986 ROD, the EPA stated that remedial action for the Metamora Landfill would
    consist of excavating the buried drums of hazardous waste for incineration off-site. The
    ROD estimated that the excavation would take six to eight months to complete.
    Pursuant to the 1986 ROD, the EPA not only excavated drums, but also took soil
    samples, installed groundwater monitoring wells, and constructed a storage pad4 east of
    JRS&G’s plant area. Id.
    In 1990, the EPA issued a second ROD. Sand & Gravel III, 62 Fed. Cl. at 559.
    In the 1990 ROD, the EPA stipulated additional remedies selected for the containment
    of the Metamora Landfill and for treatment of the groundwater at the site. Id. at 559-60.
    These remedies included installing a landfill cap system to prevent further
    contamination of aquifers by the wastes dumped in the Metamora Landfill and a fence
    around the landfill to restrict access to the site.   Id. at 560.   The 1990 ROD also
    contemplated the continued incineration of excavated drums off-site under the 1986
    3
    A ROD is a public record of an EPA decision that describes actions the
    EPA intends to take. See 40 C.F.R. 6.105(g) (2006). This includes the actions the EPA
    intends to take with respect to a site containing hazardous waste.
    4
    The EPA installed the storage pad on the property in 1989 to store the
    drums excavated on the site. The pad was later abandoned by the EPA. JRS&G does
    not allege a taking of the storage pad in this appeal. On the map at Appendix A the
    storage pad is labeled “Asphalt Pad.”
    05-5033                                    4
    ROD. The 1990 ROD did not provide a metes and bounds description of the landfill cap
    and fence or indicate when construction would begin. Sand & Gravel I, 
    57 Fed. Cl. 183
    .
    Pursuant to the the 1990 ROD, the EPA erected a chain link fence on JRS&G’s
    leasehold during the winter of 1992-1993.          Id. at 184.    The fence enclosed
    approximately 60% of the Parrish property, including the entirety of the present AIC,
    JRS&G’s plant area, and JRS&G’s main pit. Id. at 184 & n.5. The fence was six feet
    tall and anchored by posts set 48 inches into the ground.        Concrete secured the
    terminal, corner, and gate posts. The fence was topped with three strands of barbed
    wire and accompanied by EPA warning and no trespassing signs.
    The fence prevented JRS&G from accessing its operations, prompting protests
    from the company. Id. Following these protests, the EPA allowed JRS&G to access its
    plant area and relocated the fence. Id. The record reveals that the relocated fence still
    encompassed the AIC.
    In February of 1994, the EPA constructed a new internal security fence that cut
    off JRS&G’s access to parts of its plant area. Id. at 184. The area that was fenced off
    as of February of 1994 is designated on the map at Appendix A as February 1994
    Fence Alignment. As can be seen, as of February of 1994, fencing encompassed the
    overwhelming portion of JRS&G’s leasehold interest.5 The internal security fence that
    concerned JRS&G in 1994 is contained within the larger fenced area and cut through
    JRS&G’s plant area in the east-central portion of the property. This fence was relocated
    later in 1994 to allow JRS&G access to its plant area under the condition that JRS&G
    not intrude into the area enclosed by the internal security fence.     Id.   The internal
    5
    The map shows that in 1994 the fence constructed in 1992 still encircled
    the entirety of JRS&G’s plant area and its main pit.
    05-5033                                    5
    security fence was moved again in 1996 and in May of 1998. The AIC remained fenced
    off each time the internal security fence was moved. However, JRS&G continued to
    mine sand and gravel in parts of the AIC as late as 1996. Sand & Gravel I, 57 Fed. Cl.
    at 189.
    During the 1990s, JRS&G and the EPA disagreed on numerous issues. Counsel
    for JRS&G wrote a series of letters from 1992-1994 asserting JRS&G’s property rights
    and entitlement to just compensation. Id. at 184. In addition to the letters, JRS&G
    repeatedly physically interfered with the EPA’s operations.6 As a result of the disputes
    between JRS&G and the EPA, on December 18, 1996, the EPA issued an
    Administrative Order requiring JRS&G to cooperate with the EPA.                    Id.   The
    Administrative Order defined the metes and bounds of the AIC and forbade JRS&G
    from mining within the AIC. Id. at 185. The order also forbade JRS&G from further
    interference with the EPA and threatened a fine of $25,000 per day of noncompliance
    with the order.      Id.   Disputes arose regarding JRS&G’s compliance with the
    Administrative Order, and on March 23, 1998, the United States District Court for the
    Eastern District of Michigan entered an order enjoining JRS&G from further interference
    with the EPA’s remedial efforts. Id. Shortly after the issuance of the district court’s
    order, the fence was realigned. This fence realignment was complete in May of 1998.
    Id.
    6
    JRS&G’s interference included cutting the locks and entering fenced-off
    portions of the property, blocking the EPA’s access to the site by obstructing the access
    road either by piling dirt on it or by flooding it through overfilling its siltation pond, and
    threatening to drive its loaders through the gates in the fence unless it was given access
    to fenced-off portions of the property.
    05-5033                                       6
    II.
    On May 20, 2002, JRS&G filed suit in the Court of Federal Claims.             In its
    complaint, JRS&G alleged that the EPA’s construction of the landfill cap, occupation of
    the AIC, construction of fences and access roads, and installation of groundwater
    monitoring wells amounted to a permanent physical taking.           Compl. at 4-5, 9-11.
    JRS&G also alleged that the court orders created an easement appurtenant for access
    by the EPA and were thus a physical taking by the EPA. Id. at 11-13.
    In due course, the government moved for dismissal of the complaint for lack of
    jurisdiction on the ground that JRS&G’s suit was untimely.7 The government argued
    that JRS&G’s suit was time-barred because it was filed after the running of the six-year
    limitations period of 
    28 U.S.C. § 2501
    . Sand & Gravel I, 57 Fed. Cl. at 186. According
    to the government, JRS&G’s claim accrued in December of 1992, when the government
    physically occupied the property, installed monitoring wells, and fenced off parts of the
    Parrish property.   Id.   On July 27, 2003, the Court of Federal Claims denied the
    government’s motion with respect to most of the Parrish property that was allegedly
    taken because it concluded that the government had not met its burden of showing that
    there was no genuine issue of material fact as to whether the government had “clearly
    and permanently” taken the property in 1992. Id. at 189. The alleged taking in 1992
    was not permanent, the court found, because (i) JRS&G was allowed access to the
    property after protesting the construction of the fence, (ii) it continued to mine sand and
    gravel on the property, including the AIC, between 1991 and 1996, and (iii) it was
    7
    The government moved for judgment on the pleadings, or in the in the
    alternative, summary judgment. Sand & Gravel I, 57 Fed. Cl. at 182-83. The court
    treated the motion as one for summary judgment because the parties included materials
    outside the pleadings in their briefing. Id. at 185.
    05-5033                                     7
    allowed to tour the landfill, which was within the AIC. Id. The court acknowledged that
    JRS&G had been deprived of the right to exclude others from the Parrish property in
    1992. However, it determined that the government presence on the property was not
    sufficiently permanent and exclusive to comprise a physical taking until at least late
    1996, when the Administrative Order was issued. Id. The Court of Federal Claims also
    rejected the government’s argument that because JRS&G knew it had a potential
    takings claim as early as 1992-1994, the claim had accrued. Id. at 190-93. Instead,
    the court found that JRS&G did not know or have reason to know of the accrual of its
    claim under United States v. Dickinson, 
    331 U.S. 745
     (1947), because the situation on
    the Parrish property did not stabilize until 1996 when the EPA issued the Administrative
    Order, defining the metes and bounds of the AIC and barring JRS&G from entry. Sand
    & Gravel I, 57 Fed. Cl. at 192-93.     The court declined to pinpoint when the claim
    accrued, but found that the government had failed to meet its burden on summary
    judgment of demonstrating that there was no genuine issue of material fact as to
    whether the claim accrued more than six years prior to May 20, 2002, when JRS&G
    filed its complaint. Id. at 193. Accordingly, the court denied the government’s motion to
    dismiss with respect to most of the property that allegedly had been taken. Id.
    The Court of Federal Claims, however, did grant the government’s motion to
    dismiss insofar as it related to JRS&G’s claim with respect to the monitoring wells
    placed on the property in March of 1989. Id. at 183, 189. Under Hendler v. United
    States, 
    952 F.2d 1364
    , 1376 (Fed. Cir. 1991), the court found that the wells were
    sufficiently permanent to comprise a physical taking upon their installation. Sand &
    Gravel I, 57 Fed. Cl. at 189. Because the wells were installed over six years before
    05-5033                                    8
    JRS&G filed its complaint, the court granted summary judgment based on the statute of
    limitations with regard to the wells.8 Id. at 193.
    Subsequently, the parties cross-moved for summary judgment on liability. On
    April 2, 2004, the Court of Federal Claims granted in part the government’s motion for
    summary judgment and denied JRS&G’s motion for partial summary judgment. John R.
    Sand & Gravel v. United States, 
    60 Fed. Cl. 230
     (2004) (“Sand & Gravel II”). The court
    agreed with the government’s contention that background principles of Michigan
    nuisance and property law limit the scope of compensable property interests in a
    physical takings case such as JRS&G’s. Id. at 239. The court then set forth three steps
    for determining whether background principles of Michigan nuisance and property law
    limited the use of JRS&G’s leasehold: (i) JRS&G had to demonstrate possession of a
    property interest; (ii) the government had to identify background principles of Michigan
    law prohibiting certain uses of the property; and (iii) the government had to connect
    those background principles to the facts to show that the use of the property intended
    by JRS&G was barred by applicable Michigan law. Id. at 240. The court found that
    JRS&G had demonstrated its possession of a property interest and that the government
    had identified applicable principles of Michigan nuisance and property law. Id. at 242-
    51. However, the court denied the government’s motion for summary judgment without
    prejudice because it found that the government had not sufficiently demonstrated the
    existence of each of the alleged nuisances at the site. Id. at 243, 245, 247-51.
    8
    On appeal, JRS&G has not challenged the Court of Federal Claims’s
    holding that its takings claim for the groundwater monitoring wells is barred by the
    statute of limitations.
    05-5033                                       9
    After a bench trial, the Court of Federal Claims issued an opinion on October 29,
    2004, finding that the government’s actions had not taken JRS&G’s property. Sand &
    Gravel III, 62 Fed. Cl. at 589. The Court of Federal Claims revisited the question of
    when JRS&G’s takings claim accrued. Id. at 562-63. The court found that JRS&G’s
    claim accrued when the government first permanently and exclusively occupied
    JRS&G’s property. Id. at 563. The court determined that this occurred in May of 1998,
    when the government completed its relocation of the perimeter fence around the AIC.
    Id. The court found that the claim had not accrued prior to May of 1998 because
    ongoing access disputes between the government and JRS&G precluded the
    government from permanently and exclusively occupying the property. Id.
    After setting the date of accrual as May of 1998, the Court of Federal Claims
    addressed the merits of JRS&G’s takings claim. The court noted that JRS&G, as the
    plaintiff, bore the burden of demonstrating a legally-cognizable property interest under
    the framework set out in Sand & Gravel II. Id. at 562. The court found that JRS&G had
    not met this burden because JRS&G had taken its lease to the Parrish property subject
    to the landfill. Id. at 568, 570. The court noted that JRS&G knew about the landfill
    when it signed the lease and had allowed the landfill to operate despite its right to
    prohibit the landfill’s operations under the terms of the lease. Id. The court charged
    JRS&G with “knowledge of, acquiescence in, and cooperation with” the Parrishes’
    landfill operation. Id. at 570. “[F]airness and justice,” the court concluded, required
    JRS&G, as a party participating in the illegal landfill operation, to bear the burden of the
    cleanup in the form of the EPA’s presence on the property.            Id. at 572 (quoting
    05-5033                                     10
    Armstrong v. United States, 
    364 U.S. 40
    , 49 (1960)).         Therefore, the court denied
    JRS&G’s takings claims on the merits.
    The court continued that it was, “in the interest of judicial economy and
    efficiency” to elucidate a second reason why JRS&G could not recover for a physical
    taking.     
    Id.
       The court found that continued mining in the AIC would contravene
    remediation efforts, pollute groundwater, and risk fires from methane. Id. at 579-88.
    Under Michigan law, the court found that activities resulting in these risks are prohibited.
    Id. at 589. Thus, under the framework set forth in Sand & Gravel II, the court found that
    background principles of Michigan law, including both Michigan’s Natural Resources
    and Environmental Protection Act, 
    Mich. Comp. Laws §§ 324.20101
    -.20142 (2006), and
    Michigan general nuisance law, allowed the EPA to enter the property to prevent
    JRS&G from using the property in a way that would result in these nuisances. Sand &
    Gravel III, 62 Fed. Cl. at 589.
    JRS&G appeals from the decision of the Court of Federal Claims granting
    judgment in favor of the government. We have jurisdiction over this appeal pursuant to
    
    28 U.S.C. § 1295
    (a)(3).
    DISCUSSION
    I.
    On appeal, JRS&G argues that the Court of Federal Claims erred when it found
    that JRS&G’s takings claim failed because JRS&G had taken its lease subject to a pre-
    existing landfill. JRS&G also argues that the principles of “fairness and justice” relied
    upon by the Court of Federal Claims in its resolution of this issue apply only in
    regulatory takings cases—not in physical takings cases like JRS&G’s.              Likewise,
    05-5033                                     11
    JRS&G argues that the Court of Federal Claims’s alternative rationale was incorrect
    because background principles of nuisance and property law only limit property
    interests for the purpose of regulatory takings.
    The government responds that the Court of Federal Claims did not err in
    concluding that JRS&G’s takings claim failed because JRS&G took the lease for the
    Parrish property subject to the landfill. Based on principles of “fairness and justice,” the
    government contends that the court properly found that the cooperation between the
    Parrishes’ landfill operation and JRS&G barred JRS&G from recovering for a taking.
    With regard to the court’s alternative rationale based on nuisance law, the government
    argues that background principles of nuisance and property law, as articulated in Lucas
    v. South Carolina Coastal Council, 
    505 U.S. 1003
    , 1029 (1992), properly apply in
    physical takings cases.     The government urges that the Court of Federal Claims
    properly applied Michigan’s background principles of nuisance and property law and
    thus correctly found that JRS&G’s takings claim was barred under this theory. On
    appeal, the government does not challenge the decision of the Court of Federal Claims
    in Sand & Gravel I rejecting its argument that the court lacked jurisdiction because
    JRS&G’s claim was time-barred.
    Although the government does not raise a jurisdictional challenge on appeal, an
    amicus, the Metamora Group, does.9 The Metamora Group argues that the Court of
    9
    The Metamora Group consists of twelve corporations that contributed
    waste to the Metamora Landfill. With one exception, these twelve corporations signed a
    consent decree with the EPA in 1993 in which they agreed to fund the remediation of
    the Metamora Landfill. Under the consent degree, the corporations agreed to provide
    “any compensation that the United States may be required to pay to the property
    owner.”
    05-5033                                     12
    Federal Claims erred in exercising jurisdiction over JRS&G’s claim because the claim
    was barred by the six-year statute of limitations set forth in 
    28 U.S.C. § 2501
    . In order
    for a takings claim to accrue and therefore begin the running of the statute of limitations,
    the Metamora Group contends, the government’s occupation need not have been
    exclusive. Instead, the amicus argues that a property owner’s right to exclude others is
    the focus of determining when a takings claim accrues. Thus, the amicus argues that
    the claim accrued over six years prior to the filing of JRS&G’s complaint in 1989, when
    the EPA constructed the storage pad on the Parrish property and began removing
    drums. Alternatively, the Metamora Group argues that the claim accrued in 1992, when
    the government constructed a fence barring others from the site, or in 1994, when the
    government constructed the internal security fence that interfered with JRS&G’s
    operations. By 1994, the amicus argues, the government had declared itself a co-
    tenant of the property and thus JRS&G’s claim had accrued. The amicus argues that to
    the extent that JRS&G mined within the AIC in 1996 or entered the area enclosed by
    the fence, it was without the government’s permission and did not alter the date of
    accrual. The Metamora Group contends that by 1994 the government’s construction of
    fences was sufficiently permanent in nature to cause a physical takings claim to accrue.
    Finally, the Metamora Group states that the court erred in relying on Dickinson v. United
    (Cont’d. . . . )
    The Metamora Group filed a motion to intervene on October 24, 2003, which was
    denied by the Court of Federal Claims. John R. Sand & Gravel Co. v. United States, 
    59 Fed. Cl. 645
     (2004). We affirmed the denial “without prejudice to the application of the
    Metamora Group to participate as amicus curiae in any appeal to this court of the
    decision on the merits.” John R. Sand & Gravel v. United States, 
    143 Fed. Appx. 317
    ,
    319 (Fed. Cir. July 22, 2005). Accordingly, the Metamora Group has filed an amicus
    brief urging us to find that JRS&G’s claim is barred by the statute of limitations.
    Alternatively, the Metamora Group argues that the decision of the Court of Federal
    Claims should be affirmed on the merits.
    05-5033                                     13
    States in its ruling in Sand & Gravel I that JRS&G’s claim did not stabilize until within six
    years of the filing of JRS&G’s complaint because Dickinson is only applicable in cases
    where slow natural processes, such as flooding, are involved.
    JRS&G responds in its reply brief that its takings claim accrued when the
    government realigned the fence encompassing the AIC in May of 1998.                  JRS&G
    contends that the Court of Federal Claims properly found that the fences constructed in
    1992-1993 and 1994 did not permanently interfere with JRS&G’s leasehold and that
    therefore no takings claim accrued at those times. JRS&G argues that the March 1998
    district court order granted the government the undisputed authority to control JRS&G’s
    leasehold property for the first time.        Prior to this time, JRS&G asserts, the
    government’s actions were unauthorized and therefore no takings claim accrued.
    JRS&G attacks the amicus’s argument that the 1992-1993 and 1994 fences were
    sufficiently permanent to form the basis for a takings claim by noting that these fences
    were removed and therefore cannot form the basis for a permanent takings claim. At
    oral argument, counsel for the government agreed with JRS&G that its takings claim
    accrued in May of 1998 and that therefore the statute of limitations, 
    28 U.S.C. § 2501
    ,
    did not bar JRS&G’s claim.
    For the reasons set forth below, we agree with the amicus that JRS&G’s suit in
    the Court of Federal Claims was time-barred and that, therefore, the court lacked
    jurisdiction. Accordingly, we vacate the court’s decision and remand the case to the
    court with the instruction that it dismiss JRS&G’s complaint.
    05-5033                                      14
    II.
    A.
    As an appellate court, we must be satisfied that the court whose opinion is the
    subject of our review properly exercised jurisdiction, regardless of whether the parties
    challenge the lower court’s jurisdiction. Mitchell v. Maurer, 
    293 U.S. 237
    , 244 (1934)
    (“An appellate federal court must satisfy itself not only of its own jurisdiction, but also of
    that of the lower courts in a cause under review.”); Consolidation Coal Co. v. United
    States, 
    351 F.3d 1374
    , 1378 (Fed. Cir. 2003) (“[U]nder federal rules any court at any
    stage in the proceedings may address jurisdictional issues. Thus, even if the issue is
    not properly raised, this court sua sponte may consider all bases for the trial court's
    jurisdiction.”). We review the Court of Federal Claims findings of fact for clear error and
    its legal rulings without deference. Banks v. United States, 
    314 F.3d 1304
    , 1307 (Fed.
    Cir. 2003).    Accordingly, we review the trial court’s findings of fact relating to
    jurisdictional issues for clear error.   
    Id. at 1308
     (stating that the Court of Federal
    Claims’s “jurisdictional findings of fact are reviewed for clear error”). In this case, the
    pertinent jurisdictional facts are not in dispute.        The Court of Federal Claims’s
    jurisdiction is a question of law which we review de novo. Cyprus Amax Coal Co. v.
    United States, 
    205 F.3d 1369
    , 1373 (Fed. Cir. 2000) (“A determination of the Court of
    Federal Claims’ jurisdiction presents a question of law that we review de novo.”).
    The Tucker Act, 
    28 U.S.C. § 1491
    (a)(1), provides the Court of Federal Claims
    with jurisdiction over takings claims brought against the United States. Morris v. United
    States, 
    392 F.3d 1372
    , 1375 (Fed. Cir. 2004). Pursuant to 
    28 U.S.C. § 2501
    , claims
    brought in the Court of Federal Claims under the Tucker Act are “barred unless the
    05-5033                                      15
    petition thereon is filed within six years after such claim first accrues.” The six-year
    statute of limitations set forth in section 2501 is a jurisdictional requirement for a suit in
    the Court of Federal Claims. Martinez v. United States, 
    333 F.3d 1295
    , 1316 (Fed. Cir.
    2003) (en banc) (“It is well established that statutes of limitations for causes of action
    against the United States, being conditions of the waiver of sovereign immunity, are
    jurisdictional in nature.”); Frazer v. United States, 
    288 F.3d 1347
    , 1351 (Fed. Cir. 2002)
    (“Section 2501 constitutes a jurisdictional limit on the authority of the Court of Federal
    Claims.”); Caguas Cent. Fed. Sav. Bank v. United States, 
    215 F.3d 1304
    , 1310 (Fed.
    Cir. 2000) (“In the Court of Federal Claims, the statute of limitations is jurisdictional,
    because filing within the six-year period was a condition of the waiver of sovereign
    immunity in the Tucker Act, 
    28 U.S.C. § 1491
    (a)(1).”); Seldovia Native Ass’n v. United
    States, 
    144 F.3d 769
    , 774 (Fed. Cir. 1998); Hopland Band of Pomo Indians v. United
    States, 
    855 F.2d 1573
    , 1576-77 (Fed. Cir. 1988). Due to the jurisdictional nature of
    section 2501 it may not be waived. Hopland Band of Pomo Indians, 
    855 F.2d at 1577
    (“[S]ince the 6-year limitations period of section 2501, serves as a jurisdictional
    limitation rather than simply as an affirmative defense, such statutes of limitations have
    been held as not capable of waiver or subject to an estoppel, whether pled or not.”)
    (internal quotation marks omitted).
    The dissenting opinion cites several recent Supreme Court decisions in support
    of the proposition that the statute of limitations set forth at section 2501 is not
    jurisdictional, including Day v. McDonough, 
    126 S. Ct. 1675
     (2006); Arbaugh v. Y&H
    Corp., 
    126 S. Ct. 1235
     (2006), Eberhart v. United States, 
    126 S. Ct. 403
     (2005) (per
    curiam), Scarborough v. Principi, 
    541 U.S. 401
     (2004), and Kontrick v. Ryan, 
    540 U.S. 05
    -5033                                      16
    443 (2004). None of the foregoing decisions address section 2501. Day, 
    126 S. Ct. at 1681
     (holding that that the one-year statute of limitations for filing a habeas petition
    under the Antiterrorism and Effective Death Penalty Act of 1996 is not jurisdictional);
    Arbaugh, 
    126 S. Ct. at 1245
     (addressing whether the numerosity requirement of 42
    U.S.C. § 2000e(b) is jurisdictional); Eberhart, 
    126 S. Ct. at 405
     (finding that the seven-
    day time limit for filing a motion for a new trial under Federal Rules of Criminal
    Procedure 33(b)(2) and 45(b)(2) is not jurisdictional); Scarborough, 
    541 U.S. at 414
    (finding that the thirty-day time limit for filing a claim for fees under 
    28 U.S.C. § 2412
    (d)(1)(B) is not jurisdictional); Kontrick, 540 U.S. at 456 (holding that a time limit
    for filing a complaint as a creditor in bankruptcy proceedings is not jurisdictional).
    Instead, the statutes at issue involved minor procedural requirements and time limits
    that the Court characterized as non-jurisdictional “claim-processing rules.” E.g.,
    Kontrick, 540 U.S. at 456.     Day is the only case involving a statute of limitations.
    However, that case did not involve a suit against the United States for money damages.
    In contrast to a non-jurisdictional claim-processing rule or the statute of limitations in
    Day, section 2501 sets forth a condition that must be met for a waiver of sovereign
    immunity in a suit for money damages against the United States.
    We have continued to hold that section 2501 creates a jurisdictional prerequisite
    even after the Supreme Court decided Kontrick and its progeny. See, e.g., MacLean v.
    United States, __ F.3d __, No. 05-5149, 
    2006 WL 1897047
    , at *3 (Fed. Cir. July 12,
    2006) (“In the Court of Federal Claims, the statute of limitations ‘is a jurisdictional
    requirement attached by Congress as a condition of the government’s waiver of
    sovereign immunity and, as such, must be strictly construed.’” (quoting Hopland, 855
    05-5033                                     17
    F.2d at 1576-77)); Goodrich v. United States, 
    434 F.3d 1329
    , 1331, 1336 (Fed. Cir.
    2006) (affirming the Court of Federal Claims’s decision dismissing Goodrich’s takings
    claim for lack of jurisdiction under section 2501 (citing Goodrich v. United States, 
    63 Fed. Cl. 477
    , 481 (2005))); Ind. Mich. Power Co. v. United States, 
    422 F.3d 1369
    , 1378
    (Fed. Cir. 2005) (“The statute of limitations is jurisdictional in nature and, as an express
    limitation on the waiver of sovereign immunity, may not be waived.”) (citation omitted).
    Further, the six-year statute of limitations of section 2501 enjoys a longstanding
    pedigree as a jurisdictional requirement. Since 1883 when the Court first held that the
    statute of limitations was jurisdictional in Kendall v. United States, 
    107 U.S. 123
    , 125
    (1883), the Court has consistently maintained that the time limit is jurisdictional and
    therefore cannot be waived.       United States v. Wardwell, 
    172 U.S. 48
    , 52 (1898)
    (“[Section 2501’s predecessor] is not merely a statute of limitations but also
    jurisdictional in its nature, and limiting the cases of which the Court of Claims can take
    cognizance.”); see also United States v. New York, 
    160 U.S. 598
    , 619 (1896); Austin v.
    United States, 
    155 U.S. 417
    , 427 (1894); De Arnaud v. United States, 
    151 U.S. 483
    ,
    495-96 (1894); Finn v. United States, 
    123 U.S. 227
    , 232, 233 (1894); Rice v. United
    States, 
    122 U.S. 611
    , 618-19 (1887).        We recognize the Supreme Court’s recent
    jurisprudence concerning claim-processing rules, but do not think that section 2501 falls
    in that category. Therefore, we are unwilling to disturb the well-settled law that section
    2501 creates a jurisdictional condition precedent for suit in the Court of Federal Claims,
    which may not be waived by the parties. See, e.g., De Arnaud, 
    151 U.S. at 495-96
    (“‘The general rule that limitation does not operate by its own force as a bar, but is a
    defen[s]e, and that the party making such a defen[s]e must plead the statute if he
    05-5033                                     18
    wishes the benefit of its provisions, has no application to suits in the Court of Claims
    against the United States. An individual may waive such a defen[s]e, either expressly
    or by failing to plead the statute, but the government has not expressly or by implication
    conferred authority upon any of its officers to waive the limitation imposed by the statute
    upon suits against the United States in the Court of Claims.’” (quoting Finn, 123 U.S. at
    232, 233)).
    A takings claim accrues “‘when all the events have occurred which fix the liability
    of the Government and entitle the claimant to institute an action.’” Goodrich, 
    434 F.3d at 1333
     (quoting Hopland, 
    855 F.2d at 1577
    ); see also Bowen v. United States, 
    292 F.3d 1383
    , 1385 (Fed. Cir. 2002). In addition, the claim only accrues if the plaintiff knew
    or should have known of the existence of the events fixing the government’s liability.
    Goodrich, 
    434 F.3d at 1333
    ; Hopland, 
    855 F.2d at 1577
    ; Kinsey v. United States, 
    852 F.2d 556
    , 557 n.* (Fed. Cir. 1988).
    B.
    The question we must decide then is when JRS&G’s takings claim accrued. The
    Court of Federal Claims held that the claim accrued in May of 1998 when the
    government relocated the fence around the AIC. We conclude, however, that the claim
    accrued not later than February of 1994 when the government constructed the fence
    that cut off JRS&G’s access to its plant area. That date was more than six years before
    JRS&G filed its complaint on May 20, 2002.
    The Fifth Amendment provides, “[N]or shall private property be taken for public
    use without just compensation.” U.S. Const. amend. V. Property rights in a physical
    thing consist of a bundle of rights, including the rights to possess, to use, and to dispose
    05-5033                                     19
    of the physical thing. Loretto v. Teleprompter Manhattan CATV Corp., 
    458 U.S. 419
    ,
    435 (1982); United States v. Gen. Motors Corp., 
    323 U.S. 373
    , 377-78 (1945) (finding
    that property rights “denote the group of rights inhering in the citizen’s relation to the
    physical thing, as the right to possess, use and dispose of it”).
    The right to exclude others is “one of the most treasured strands in an owner’s
    bundle of property rights.” Loretto, 
    458 U.S. at 435
    ; see also Nollan v. Cal. Coastal
    Comm’n, 
    483 U.S. 825
    , 831 (1987) (noting that the right to exclude others is one of the
    most essential sticks in the bundle of property rights); Kaiser Aetna v. United States,
    
    444 U.S. 164
    , 176 (1979) (characterizing the right to exclude as “one of the most
    essential sticks in the bundle of rights that are commonly characterized as property”);
    Hendler, 952 F.2d at 1374 (stating that “[i]n the bundle of rights we call property, one of
    the most valued is the right to sole and exclusive possession—the right to exclude
    strangers, or for that matter friends, but especially the Government”).         When the
    government permanently and physically occupies property, it effectively destroys the
    owner’s right to exclude, as well as the owner’s right to make non-possessory use of the
    property. Loretto, 
    458 U.S. at 435-36
    . Due to the importance of a property owner’s
    right to exclude, we have held that “[t]he Government does not have the right to declare
    itself a co-tenant-in-possession with a property owner.” Hendler, 952 F.2d at 1374; see
    also Kaiser Aetna, 
    444 U.S. at 179-80
     (holding that “the ‘right to exclude,’ so universally
    held to be a fundamental element of the property right, falls within this category of
    interests that the Government cannot take without compensation”). Thus, a permanent
    physical occupation by the government is a per se physical taking requiring
    compensation under the Fifth Amendment because it destroys, among other rights, a
    05-5033                                      20
    property owner’s right to exclude. Loretto, 
    458 U.S. at 441
    ; Boise Cascade Corp. v.
    United States, 
    296 F.3d 1339
    , 1353 (Fed. Cir. 2002) (“[A] permanent physical
    occupation of property, no matter how slight, is a per se taking.”); Hendler, 952 F.2d at
    1375 (“A physical occupation of private property by the government which is adjudged
    to be of a permanent nature is a taking, and that is true without regard to whether the
    action achieves an important public benefit or has only minimal economic impact on the
    owner.”).
    “A physical occupation . . . is a permanent and exclusive occupation by the
    government that destroys the owner’s right to possession, use, and disposal of . . .
    property.” Boise Cascade Corp., 
    296 F.3d at 1353
    . Thus, physical occupation by the
    government only comprises a taking when that occupation is “permanent.” Id.; Boling v.
    United States, 
    220 F.3d 1365
    , 1370 (Fed. Cir. 2000); Hendler, 952 F.2d at 1375.
    “Permanent” has a special meaning in the determination of whether a physical
    occupation has occurred. See Hendler, 952 F.2d at 1376. In the context of physical
    takings “‘permanent’ does not mean forever, or anything like it.” Id. A government
    occupation is “permanent” when the government’s “intrusion is a substantial physical
    occupancy of private property.” Id. at 1377. The government’s occupation may be
    permanent even if it is not “exclusive, or continuous and uninterrupted.” Id.; see also
    Skip Kirchdorfer, Inc. v. United States, 
    6 F.3d 1573
    , 1582 (Fed. Cir. 1993) (“[A]
    permanent physical occupation need not be continuous and uninterrupted.                 An
    intermittent intrusion still causes a taking.”) (citations omitted). The Supreme Court held
    in Loretto that the placement of cable and connection boxes on the plaintiff’s property
    was a physical taking. 
    458 U.S. at 441
    . In Hendler, we held that the placement of
    05-5033                                     21
    groundwater monitoring wells on the plaintiff’s property and the government’s periodic
    presence for installing and servicing the wells was “permanent” and therefore a physical
    taking.     952 F.2d at 1377.    In contrast, we noted that a transient and relatively
    inconsequential incursion by the government, such as a truckdriver parking on a vacant
    lot to eat lunch, is not sufficiently permanent to comprise a taking. Id. at 1376-77.
    Similarly, in Boise Cascade, we determined that government surveyors who briefly
    entered the plaintiff’s land over a period of five months to perform owl surveys did not
    “permanently” occupy the plaintiff’s property.            
    296 F.3d at 1356
    .   Thus, the
    determination of whether government occupancy is “permanent” is highly fact-specific.
    In any event, the installation of fixed physical structures, such as the cable and cable
    connections in Loretto or the groundwater monitoring wells in Hendler is typical of a
    “permanent” occupation, while the transient entry of persons via government authority
    on a plaintiff’s property is generally not “permanent.”
    C.
    We hold that JRS&G’s takings claim accrued not later than February of 1994
    upon the completion of the 1994 fence. The 1994 security fence ran across JRS&G’s
    plant area, cutting off JRS&G’s access to its pond and stockpile areas. Sand & Gravel
    I, 57 Fed. Cl. at 184. The six-foot fences, with posts that were anchored by concrete in
    some instances, comprised just the sort of permanent structure have been found to
    form the basis for a physical takings claim. See Loretto, 
    458 U.S. at 422
     (finding cables
    attached by screws and nails and a box attached by bolts to be sufficiently permanent to
    comprise a physical taking); see also Hendler, 952 F.2d at 1376 (finding that
    groundwater monitoring wells were permanent in nature given their structure). Thus,
    05-5033                                      22
    the EPA took possession of the property at least as of 1994 when it erected permanent
    structures to bar JRS&G from portions of the Parrish property.10
    The EPA’s presence destroyed JRS&G’s right to exclude others from its
    leasehold, one of the most treasured rights of property owners. See Kaiser Aetna, 
    444 U.S. at 176
    . Further, the EPA’s 1994 fence also inhibited JRS&G’s right to use its
    property free of interference. In fact, the firm conducting the remediation efforts stated
    that the removal of the offending portions of the 1994 fence “will be contingent upon
    John R’s agreement to stay out of the new security area.” Pl.’s Mem. In Opp’n to Def.’s
    Mot. for J. on the Pleadings, Exh. 10 (Jan. 23, 2003). Thus, the EPA and its agents
    placed conditions on the use of JRS&G’s property in exchange for relocating the
    fence—destroying the use strand in JRS&G’s bundle of property rights in addition to
    JRS&G’s right to exclude. Based on the foregoing, we find that, not later than 1994, the
    10
    We express no opinion as to whether the construction of the 1992-1993
    fence around the entirety of JRS&G’s operations was sufficiently permanent for a
    takings claim to accrue.
    Although not argued by the amicus, we note that the EPA’s issuance of
    RODs in 1986 and 1990 was not sufficient for a physical takings claim to accrue in this
    case. In Goodrich v. United States, 
    434 F.3d 1329
     (Fed. Cir. 2006), we found that a
    takings claim accrued upon the issuance of an ROD ordering that Goodrich allow
    another rancher’s animals to drink on his allotment of federal land. 
    Id. at 1332
    . The
    agency specified both the number of animals and the rancher to whom they belonged.
    
    Id.
     We affirmed the Court of Federal Claims’s characterization of the taking as
    regulatory rather than physical and its finding that the regulatory takings claim accrued
    upon the issuance of the ROD. 
    Id. at 1333-35
    . We find that the date of issuance of the
    1986 and 1990 RODs did not mark the accrual of JRS&G’s takings claim for two
    reasons. First, unlike Goodrich, JRS&G’s claim is for a physical taking, rather than a
    regulatory taking. Second, the two RODs issued with regard to the Metamora Landfill
    did not contain the level of detail about the government’s actions necessary for a claim
    to accrue. The 1986 ROD set forth remedies for removal of drums of waste, which the
    EPA predicted would take six to eight months. The 1986 ROD did not set forth the long-
    term plan for site remediation challenged by JRS&G. The 1990 ROD did propose a
    long-term remediation plan involving a landfill cap system. However, the ROD did not
    set forth the metes and bounds of the landfill cap or a specific timeframe for its
    completion. Sand & Gravel I, 57 Fed. Cl. at 184.
    05-5033                                    23
    EPA had effectively declared itself a co-tenant in possession of a portion of the property
    and that accordingly, JRS&G’s takings claim accrued at that time.
    Although we acknowledge that the EPA relocated portions of the fence in 1994 to
    accommodate JRS&G’s need for access to its plant area, we note that the fence
    remained on the property and that the EPA continued to carry on its remediation
    activities on the leasehold. The net effect of the restructuring of the fence in 1994 was
    to reduce the area around the landfill enclosed by fencing—the government did not
    remove the fence entirely. The EPA’s willingness to alter the parameters of the fence
    does not change the fact that the fence itself was permanent in nature. The fact that
    JRS&G interfered with the EPA’s efforts and ignored the fence until ordered in 1998 by
    the United States District Court for the Eastern District of Michigan to cooperate with the
    EPA, does not alter our conclusion. Likewise, we find that a physical occupation of the
    fenced area occurred despite JRS&G’s continued and permitted use of the area not
    enclosed by the 1994 fence. See Loretto, 
    458 U.S. at 430
     (finding that a permanent
    physical occupation is a taking even if the government “occup[ies] only relatively
    insubstantial amounts of space and do[es] not seriously interfere with the landowners
    use of the rest of his land”).
    We find unpersuasive the Court of Federal Claims’s reliance in Sand & Gravel I
    on 767 Third Avenue Associates v. United States, 
    48 F.3d 1575
     (Fed. Cir. 1995). In
    767 Third Avenue Associates, the plaintiff was a landlord who leased three properties to
    offices of the Socialist Federal Republic of Yugoslavia. Id. at 1576. In response to
    political unrest in Yugoslavia, the United States government ordered closure of the
    operations of the three tenants. Id. at 1577. After the three tenants left, agents of the
    05-5033                                     24
    Department of the Treasury inspected the plaintiff’s premises and posted a notice on
    the door of each office stating that it was “CLOSED BY ORDER OF THE UNITED
    STATES DEPARTMENT OF THE TREASURY” and that “NO ACCESS TO THESE
    PREMISES IS PERMITTED.”            We held that there was no per se physical taking
    because “the government did not physically occupy the premises at 767 Third Avenue.”
    Id. at 1583. We noted that the notices were up for less than three months, that the
    locks were not changed, that nothing physical was attached to the premises except for
    the notices, and that no guards were placed at the door. Id. Further, the landlord was
    allowed access on request.       Id.   The Court of Federal Claims drew a comparison
    between 767 Third Avenue Associates’s facts and those relating to the 1992 and 1994
    fences by noting that JRS&G was allowed access to its plant area shortly after it
    protested the fences.      Id.    However, unlike 767 Third Avenue Associates, the
    government physically entered JRS&G’s property for a prolonged period.           Further,
    remediation equipment was stored on the property for extended periods, and permanent
    physical structures, fences, were erected. The mere fact that JRS&G was allowed
    access to portions of the property on request does not alter the fact that the government
    had a presence of a “permanent nature” on JRS&G’s leasehold not later than 1994.
    See Skip Kirchdorfer, Inc., 
    6 F.3d at 1583
     (holding that “retention of some access rights
    . . . does not preclude a per se taking”).
    In addition to concluding that all the events fixing the government’s liability
    occurred not later than 1994, we think that the Court of Federal Claims erred in
    concluding that JRS&G neither knew nor should have known of those events as of
    1994. See Sand & Gravel I, 57 Fed. Cl. at 192-93. The Court of Federal Claims found
    05-5033                                      25
    that JRS&G’s claims did not stabilize under Dickinson, 
    331 U.S. 745
    , until at least 1996
    due to the changing boundaries of the fences and JRS&G’s ability to mine within the
    AIC during the 1992-1996 period.11 See Sand & Gravel I, 57 Fed. Cl. at 192. In
    Dickinson, property owners experienced intermittent flooding and could not determine at
    the outset the frequency or permanency of the flooding. Thus, only when the situation
    “stabilized” did a takings claim accrue. 
    331 U.S. at 749
    . In Northwest Louisiana Fish &
    Game Preserve Commission v. United States, 
    446 F.3d 1285
    , 1290-91 (Fed. Cir. 2006),
    we recently applied Dickinson to the overgrowth of aquatic weeds in a lake controlled by
    the United States Corps of Engineers. In contrast, the present case does not involve
    the type of gradual physical process that was involved in Dickinson or Northwest
    Louisiana Fish, but rather the entry of the EPA onto the plaintiff’s leasehold. Both the
    Supreme Court and our court have acknowledged that the Dickinson stabilization
    doctrine is only applicable in cases involving gradual physical processes. See, e.g.,
    United States v. Dow, 
    357 U.S. 17
    , 27 (1958) (“The expressly limited holding in
    Dickinson was that the statute of limitations did not bar an action under the Tucker Act
    for a taking by flooding when it was uncertain at what stage in the flooding operation the
    land had become appropriated to public use.”); Ariadne Fin. Servs. Pty. Ltd. v. United
    States, 
    133 F.3d 874
    , 879 (Fed. Cir. 1998) (“The Dickinson stabilization principle,
    however, does not apply outside its context. Later cases have essentially confined the
    stabilization doctrine to the class of flooding cases from which it originated.”).    We
    conclude that the Court of Federal Claims erred by extending the Dickinson stabilization
    11
    On appeal, JRS&G states that it mined within the AIC as late as 1997.
    For purposes of our decision, whether JRS&G last mined within the AIC in 1996 or 1997
    does not matter.
    05-5033                                    26
    doctrine outside the realm of gradual physical processes caused by government action,
    such as flooding or plant overgrowth, into the area of direct government entry onto
    property. Therefore, JRS&G’s takings claim accrued no later than February of 1994.
    That JRS&G knew or should have known that its claim had accrued at that time is
    evidenced by the letters written by JRS&G between 1992 and 1994 threatening suit
    against the EPA. See Sand & Gravel I, 57 Fed. Cl. at 184.
    Finally, we reject JRS&G’s argument that its claim did not accrue until 1998
    because the EPA’s actions were not authorized until the United States District Court for
    the Eastern District of Michigan issued its March 1998 order. This argument lacks merit
    because, when the EPA and its agents entered JRS&G’s leasehold, the government
    was acting in accordance with the authority granted to the EPA by Congress in
    CERCLA.12 See Armijo v. United States, 
    229 Ct. Cl. 34
    , 41 (1981) (finding a Tucker Act
    claim viable when Congress authorizes the government to take property).
    Because we decide the case on jurisdictional grounds, it is unnecessary to
    address whether background principles of nuisance and property law, as articulated in
    Lucas, apply in physical takings, or whether JRS&G took the lease subject to the
    landfill.
    CONCLUSION
    In sum, we hold that JRS&G’s takings claim accrued not later than February of
    1994, when the security fence was complete. JRS&G did not file its complaint until over
    six years later on May 20, 2002.     Therefore, the claim is barred by the statute of
    12
    Pursuant to CERCLA, the EPA is “authorized to enter at reasonable times
    any . . . facility, establishment, or other place or property where any hazardous
    substance or pollutant or contaminant may be or has been generated, stored, treated,
    disposed of, or transported from.” 
    42 U.S.C. § 9604
    (e)(1), (e)(3)(A).
    05-5033                                   27
    limitations and the Court of Federal Claims lacks jurisdiction to consider it. Accordingly,
    we vacate the Court of Federal Claims’s decision and remand the case to the court with
    the instruction that it dismiss JRS&G’s complaint.
    COSTS
    Each party shall bear its own costs.
    VACATED and REMANDED
    05-5033                                       28
    Appendix A
    05-5033       29
    United States Court of Appeals for the Federal Circuit
    05-5033
    JOHN R. SAND & GRAVEL COMPANY,
    Plaintiff-Appellant,
    v.
    UNITED STATES,
    Defendant-Appellee.
    NEWMAN, Circuit Judge, dissenting.
    The threshold question is whether, more than six years before this suit was filed, all
    of the events occurred whereby government action can be held to have permanently
    deprived JRS&G of its property rights. This is a question of fact, and its answer determines
    whether this lawsuit was timely brought. However, it is not a question of "jurisdiction," for
    the Court of Federal Claims, without dispute, had jurisdiction of the parties and the subject
    matter. See United States v. Causby, 
    328 U.S. 256
    , 267 (1946) ("If there is a taking, the
    claim is 'founded upon the Constitution' and within the jurisdiction of the Court of Claims to
    hear and determine"). The text of the statute confirms that the limitations period is applied
    to claims of which the Court of Federal Claims already "has jurisdiction":
    
    28 U.S.C. §2501
    . Every claim of which the United States Court of Federal
    Claims has jurisdiction shall be barred unless the petition thereon is filed
    within six years after such claim first accrues.
    Contrary to the position of the panel majority, the limitations period is not itself a matter of
    jurisdiction. See Ariadne Fin. Servs. Pty. Ltd. v. United States, 
    133 F.3d 874
    , 878 (Fed.
    Cir. 1998) (the "statutory language confirms that the question of a time bar on [plaintiff's]
    claim does not affect the subject matter jurisdiction of the Court of Federal Claims"); Grass
    Valley Terrace v. United States, 
    69 Fed. Cl. 341
    , 347 (2005) ("This plain English
    interpretation of the statute is supported by the Federal Circuit cases that have closely
    examined this issue") (emphasis in original).          My colleagues read the phrase "has
    jurisdiction" out of the statute and thereby violate the "cardinal principle of statutory
    construction that a statute ought, upon the whole, to be so construed that, if it can be
    prevented, no clause, sentence, or word shall be superfluous, void, or insignificant." TRW
    Inc. v. Andrews, 
    534 U.S. 19
    , 31 (2001). Their interpretation is also inconsistent with the
    trial court's own rules, which state that the "statute of limitations" is an "affirmative defense."
    Rule of the Court of Federal Claims 8(c).
    The panel majority reasons that §2501 is "jurisdictional" because it is a "condition
    that must be met for a waiver of sovereign immunity in a suit for money damages against
    the United States." Maj. op. at 17. That is incorrect. Section 2501 is an unexceptional
    statute of limitations that is interpreted like any other statute of limitations. See Irwin v.
    Department of Veterans Affairs, 
    498 U.S. 89
    , 94 (1990) (statutes of limitations on suits
    against the government should be treated "in the same way" as statutes of limitations in
    private suits); Franconia Associates v. United States, 
    536 U.S. 129
    , 145 (1986) ("limitations
    principles should generally apply to the Government in the same way that they apply to
    private parties"). In Franconia Associates the Court rejected the government's attempt to
    ascribe a "special" interpretation to §2501 on a theory of sovereign immunity:
    05-5033                                         2
    We do not agree that § 2501 creates a special accrual rule for suits against
    the United States. Contrary to the Government's contention, the text of §
    2501 is unexceptional: A number of contemporaneous state statutes of
    limitations applicable to suits between private parties also tie the
    commencement of the limitations period to the date a claim "first accrues." . .
    . In line with our recognition that limitations principles should generally apply
    to the Government "in the same way that" they apply to private parties, we
    reject the Government's proposed construction of § 2501. That position, we
    conclude, presents an "unduly restrictive" reading of the congressional waiver
    of sovereign immunity, rather than "a realistic assessment of legislative
    intent."
    536 U.S. at 145 (internal citations omitted). My colleagues make the same mistake; they
    fail to see §2501 for what it is: an "unexceptional" statute of limitations that is interpreted
    like any other. Instead, they impose an "unduly restrictive" interpretation on §2501,
    transforming it into a "jurisdictional" statute, contrary to the statutory text, and contrary to
    precedent.
    The panel majority relies on Supreme Court cases interpreting a superceded statute,
    and Federal Circuit panel decisions applying overruled precedent. For example, Hopland
    Band of Pomo Indians v. United States, 
    855 F.2d 1573
    , 1576-77 (Fed. Cir. 1988) relies on
    Soriano v. United States, 
    352 U.S. 270
    , 276 (1957), which interprets              §2501 as a
    jurisdictional bar not subject to tolling. The Court in Irwin overruled Soriano, and clarified
    that limitations principles apply to the government "in the same way" as they are applied to
    private parties, e.g., they may be tolled or waived in appropriate circumstances. Irwin, 498
    U.S. at 94-96. My colleagues cite Goodrich v. United States, 
    434 F.3d 1329
    , 1336 (Fed.
    Cir. 2006), and Caguas Cent. Fed. Savings Bank v. United States, 
    215 F.3d 1304
    , 1310
    (Fed. Cir. 2000), which rely solely on Hopland. They also cite Frazer v. United States, 
    288 F.3d 1347
    , 1351 (Fed. Cir. 2002), which cites Caguas, and Indiana Michigan Power Co. v.
    United States, 
    422 F.3d 1369
    , 1378 (Fed. Cir. 2005), which cites Hart v. United States, 910
    05-5033 
    3 F.2d 815
    , 818-19 (Fed. Cir. 1990), a case also citing Hopland. None of these cases
    grounded on Hopland accounts for the Court's recent jurisprudence, under which it is clear
    that it is incorrect to accord unique status to §2501 and hold that it is a limit on "jurisdiction."
    My colleagues also cite Martinez v. United States, 
    333 F.3d 1295
     (Fed. Cir. 2003) (en
    banc), which left the matter unresolved.
    In contrast, other panel decisions have correctly interpreted §2501 as a statute of
    limitations, not a jurisdictional limit on the Court of Federal Claims. See Venture Coal Sales
    Co. v. United States, 
    370 F.3d 1102
    , 1105 n.2 (Fed. Cir. 2004) ("The most precise ground
    for the trial court's decision here therefore would seem to be that Venture Coal failed to
    make its claim within the required limitations period -- that is not a question of subject
    matter jurisdiction of the" Court of Federal Claims); Ariadne Fin. Servs. Pty. Ltd. v. United
    States, 
    133 F.3d 874
    , 878 (Fed. Cir. 1998) ("the question of a time bar on [plaintiff's] claim
    does not affect the subject matter jurisdiction of the Court of Federal Claims"); Henke v.
    United States, 
    60 F.3d 795
    , 798 n.3 (Fed. Cir. 1995) ("The raising of the statutory bar to a
    remedy does not, as such, deprive the court of jurisdiction to hear the cause in the first
    instance. Indeed, the court could not adjudicate the question of the proper application of
    the statute if it did not have subject matter jurisdiction over the claim"); Borough of Alpine v.
    United States, 
    923 F.2d 170
    , 171 n.1 (Fed. Cir. 1991) (despite an untimely filing the
    "Claims Court has and will continue to have jurisdiction over the subject matter of Contract
    Disputes Act cases").
    The Supreme Court has, in several recent statements, emphasized that statutes of
    limitations and time prescriptions are not "jurisdictional." See Arbaugh v. Y & H Corp., 
    126 S. Ct. 1235
    , 1242 (2006) (stating that the Court has established that time prescriptions are
    05-5033                                          4
    not jurisdictional); Day v. McDonough, 
    126 S. Ct. 1675
    , 1681 (2006) ("A statute of
    limitations defense, the State acknowledges, is not 'jurisdictional,' hence courts are under
    no obligation to raise the time bar sua sponte") (emphasis in original); Eberhart v. United
    States, 
    126 S. Ct. 403
    , 405 (2005) ("They are not 'jurisdiction[al],' but are instead 'claim-
    processing rules,' that may be 'unalterable on a party's application' but 'can nonetheless be
    forfeited if the party asserting the rule waits too long to raise the point'"); Scarborough v.
    Principi, 
    541 U.S. 401
    , 414 (2004) (time prescriptions are "not properly typed
    'jurisdictional'"); Kontrick v. Ryan, 
    540 U.S. 443
    , 456 (2004) ("Clarity would be facilitated if
    courts and litigants used the label 'jurisdictional' not for claim-processing rules, but only for
    prescriptions delineating the classes of cases (subject-matter jurisdiction) and the persons
    (personal jurisdiction) falling within a court's adjudicatory authority").
    Thus, the question is whether the statute that sets a six-year limit on claims against
    the United States has been met on the facts affecting JRS&G. Both the government and
    JRS&G agree that the statute of limitations has not run. Since it is not "jurisdictional," it
    need not be considered sua sponte by this court.
    Despite this clear waiver and concession by the government, my colleagues overrule
    the Court of Federal Claims, reject the position of the government, and hold that the six-
    year limitations period started to accrue by February 1994 when the EPA erected its first
    transient security fence. The Court of Federal Claims found that JRS&G had access to and
    mining use of much of that property until at least the December 1996 Administrative Order,
    for the EPA soon moved the fence to enclose a smaller area, and also permitted access by
    JRS&G to mine sand and gravel in parts of the smaller area. The government recognized
    and testified that JRS&G was not permanently excluded from the property until May 1998.
    05-5033                                        5
    See Defendant's Response to the Court's Order of July 7, 2004 ("it appears that it was not
    until May 1998 . . . that plaintiff was clearly and permanently excluded from the AIC [Area of
    Institutional Controls]"). Nonetheless, my colleagues now rule that since the fence was not
    entirely removed, the February 1994 exclusion was a permanent taking of the entire area
    including the area that was used by JRS&G until judicial intervention in 1998.
    The Court of Federal Claims applied the Court's three-part test of Loretto v.
    Telepromter Manhattan CATV Corp., 
    458 U.S. 419
    , 435 (1982), viz. that a taking occurs
    only when the property owner has lost the rights to possess, use, and dispose of the
    property. See, e.g., Boise Cascase Corp. v. United States, 
    296 F.3d 1339
    , 1353 (Fed. Cir.
    2002) (applying the Loretto test). In this case, the Court of Federal Claims found that the
    three-part test had not been met, except for the permanent wells, because JRS&G retained
    beneficial use of the property at least until December 1996. No error has been shown in
    that analysis. On that finding, which must be sustained, the statute of limitations cannot
    have run.
    I am concerned that the court's position today brings serious imprecision to takings
    law. My colleagues hold that the entire claim is now barred and that irrevocable limitations
    accrued as to property that JRS&G continued to use during a period for which a Fifth
    Amendment claim was conspicuously unavailable. The panel majority cites various actions
    such as "lawyers' letters" to support its theory that JRS&G had knowledge that a taking had
    already occurred in February 1994, maj. op. at 24, although the effect of the letters was the
    removal of the fence. The question before the Court of Federal Claims was whether a
    compensable taking occurred in February 1994 as to the property that was restored to use
    by JRS&G until at least December 1996. When that court's findings as to the extent of this
    05-5033                                       6
    access and use are reviewed on the appropriate standard of appellate review, the findings
    must be sustained.
    Thus I would affirm the holding of the Court of Federal Claims that the limitations
    period had not accrued in 1994, and would reach the merits of the takings claim. On the
    merits, I would affirm that JRS&G is not entitled to compensation for a larger land area than
    measured by the permit wells, for JRS&G was aware of the landfill when it took the
    leasehold. I would affirm the Court of Federal Claims on this ground.
    05-5033                                      7
    

Document Info

Docket Number: 2005-5033

Citation Numbers: 457 F.3d 1345

Judges: Lourie, Newman, Schall

Filed Date: 8/9/2006

Precedential Status: Precedential

Modified Date: 8/3/2023

Authorities (43)

Donald A. Henke v. United States , 60 F.3d 795 ( 1995 )

I.K. Frazer, Margie P. Berger, Peggy Cothren Jasso, Michael ... , 288 F.3d 1347 ( 2002 )

Morris Kinsey D/B/A Kinsey Farms, Inc. v. The United States , 852 F.2d 556 ( 1988 )

Boise Cascade Corporation v. United States , 296 F.3d 1339 ( 2002 )

John B. Goodrich (Doing Business as Checkerboard Cattle Co.)... , 434 F.3d 1329 ( 2006 )

Venture Coal Sales Company, Sanner Energies, Inc., and ... , 370 F.3d 1102 ( 2004 )

Skip Kirchdorfer, Inc. v. United States , 6 F.3d 1573 ( 1993 )

Gabriel J. Martinez v. United States , 333 F.3d 1295 ( 2003 )

Robert E. Morris and Carol L. Morris v. United States , 392 F.3d 1372 ( 2004 )

cyprus-amax-coal-company-cyprus-western-coal-company-mountain-coal , 205 F.3d 1369 ( 2000 )

john-h-banks-mary-e-banks-robert-cunat-june-m-cunat-ehret-michigan , 314 F.3d 1304 ( 2003 )

w-frank-boling-we-gore-jr-george-rayford-vereen-hope-willard-in , 220 F.3d 1365 ( 2000 )

caguas-central-federal-savings-bank-and-maria-victoria-vazquez-severiano , 215 F.3d 1304 ( 2000 )

consolidation-coal-company-consol-of-pennsylvania-coal-company-consol-of , 351 F.3d 1374 ( 2003 )

Indiana Michigan Power Company v. United States , 422 F.3d 1369 ( 2005 )

Seldovia Native Association, Inc. v. United States , 144 F.3d 769 ( 1998 )

Gary W. Bowen v. United States , 292 F.3d 1383 ( 2002 )

The Borough of Alpine v. The United States , 923 F.2d 170 ( 1991 )

Hopland Band of Pomo Indians v. The United States , 855 F.2d 1573 ( 1988 )

Ariadne Financial Services Pty. Ltd. And Memvale Pty. Ltd. ... , 133 F.3d 874 ( 1998 )

View All Authorities »