Wildearth Guardians v. Sally Jewell , 738 F.3d 298 ( 2013 )


Menu:
  •     United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 18, 2013            Decided December 24, 2013
    No. 12-5300
    WILDEARTH GUARDIANS, ET AL.,
    APPELLANTS
    POWDER RIVER BASIN RESOURCE COUNCIL, CA-11-037,
    APPELLANT
    v.
    SALLY JEWELL, SECRETARY, U.S. DEPARTMENT OF INTERIOR,
    ET AL.,
    APPELLEES
    Consolidated with 12-5312
    Appeals from the United States District Court
    for the District of Columbia
    (No. 1:10-cv-01174)
    Samantha Ruscavage-Barz argued the cause for the
    appellants. Scott Gollwitzer and Matt Kenna were on brief.
    Michael P. Senatore entered an appearance.
    J. David Gunter II, Attorney, United States Department of
    Justice, argued the cause for the appellees.
    2
    James Kaste, Senior Assistant Attorney General, Office of
    the Attorney General for the State of Wyoming, Creighton R.
    Magid, Andrew C. Emrich and John A. Bryson were on brief
    for intervenors Antelope Coal, LLC, et al. in support of the
    appellees. Michael J. McGrady, Senior Assistant Attorney
    General, Office of the Attorney General for the State of
    Wyoming, and Jay C. Johnson entered appearances.
    Before: HENDERSON and BROWN, Circuit Judges, and
    GINSBURG, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge HENDERSON.
    KAREN LECRAFT HENDERSON, Circuit Judge: In April
    2005, Antelope Coal LLC (Antelope Coal) filed an application
    with the Bureau of Land Management (BLM), an agency
    within the U.S. Department of the Interior (Interior),
    requesting that a tract of federal land adjacent to Antelope
    Coal’s existing mine in the Wyoming Powder River Basin be
    offered for competitive lease sale to interested parties. In
    March 2010 the BLM issued a Record of Decision (ROD),
    dividing the land into two tracts (the West Antelope II tracts)
    and offering them for lease through separate competitive
    bidding processes. WildEarth Guardians, Defenders of
    Wildlife, the Sierra Club (collectively, WildEarth) and the
    Powder River Basin Resource Council (PRBRC and,
    collectively with WildEarth, Appellants) challenge the BLM’s
    decision to approve the West Antelope II tracts for lease.
    They argue that the Final Environmental Impact Statement
    (FEIS) supporting the ROD is deficient in several respects.
    The district court granted summary judgment to the
    defendants,1 finding that the plaintiffs lacked standing to raise
    1
    The defendants include Interior Secretary Sally Jewell, the
    BLM and the United States Fish and Wildlife Service. The district
    court permitted Antelope Coal, the State of Wyoming and the
    3
    one of their arguments and that their remaining arguments
    failed on the merits. We conclude that, while they do have
    standing, their merits arguments fall short. Accordingly, we
    affirm the judgment of the district court.
    I
    A
    Under the Mineral Leasing Act (MLA), 30 U.S.C. §§ 181
    et seq., the Interior Secretary is authorized to offer leases on
    tracts of federal land suitable for coal mining and to award such
    leases based on a competitive bidding process.                 
    Id. § 201(a)(1).
    Pursuant to its authority under the MLA, see 
    id. § 189,
    the BLM has promulgated regulations governing the
    competitive leasing of rights to extract federal coal. See 43
    C.F.R. pt. 3420.
    The National Environmental Policy Act of 1969 (NEPA),
    42 U.S.C. §§ 4321 et seq., requires federal agencies, including
    the BLM, to consider and report on the environmental effect of
    their proposed actions. See Theodore Roosevelt Conservation
    P’ship v. Salazar (Theodore Roosevelt I), 
    616 F.3d 497
    , 503
    (D.C. Cir. 2010). “NEPA is an ‘essentially procedural’ statute
    intended to ensure ‘fully informed and well-considered’
    decisionmaking . . . .” New York v. NRC, 
    681 F.3d 471
    , 476
    (D.C. Cir. 2012) (quoting Vt. Yankee Nuclear Power Corp. v.
    Natural Res. Def. Council, Inc., 
    435 U.S. 519
    , 558 (1978)).
    “NEPA has twin aims. First, it places upon an agency the
    obligation to consider every significant aspect of the
    environmental impact of a proposed action. Second, it
    National Mining Association to intervene as defendants. See
    WildEarth Guardians v. Salazar, 
    272 F.R.D. 4
    (D.D.C. 2010). The
    district court also dismissed one of WildEarth’s claims on the
    pleadings, which claim is not appealed. See WildEarth Guardians
    v. Salazar, 
    783 F. Supp. 2d 61
    (D.D.C. 2011).
    4
    ensures that the agency will inform the public that it has indeed
    considered environmental concerns in its decisionmaking
    process.” Balt. Gas & Elec. Co. v. Natural Res. Def. Council,
    Inc., 
    462 U.S. 87
    , 97 (1983) (citation and quotation marks
    omitted); accord Dep’t of Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 768 (2004). To meet these aims, NEPA requires an
    agency to prepare, and solicit public comment on, an
    environmental impact statement (EIS) whenever it proposes a
    “major Federal action[] significantly affecting the quality of
    the human environment.” 42 U.S.C. § 4332(2)(C). The EIS
    must consider, inter alia, “the environmental impact of the
    proposed action,” 
    id. § 4332(2)(C)(i);
    “any adverse
    environmental effects which cannot be avoided,” 
    id. § 4332(2)(C)(ii);
    see Robertson v. Methow Valley Citizens
    Council, 
    490 U.S. 332
    , 351–52 (1989); and any “alternatives to
    the proposed action,” 42 U.S.C. § 4332(2)(C)(iii); see Citizens
    Against Burlington, Inc. v. Busey, 
    938 F.2d 190
    , 194–95 (D.C.
    Cir. 1991) (noting that “alternatives” is not self-defining and
    “must be moored to ‘some notion of feasibility’ ” (quoting Vt.
    
    Yankee, 435 U.S. at 551
    )). The EIS is to be prepared in
    consultation with any federal agency with special expertise
    relating to the environmental impact involved, 42 U.S.C.
    § 4332(2)(C) (flush language), and the Environmental
    Protection Agency (EPA) must review it and submit written
    comments, see 
    id. § 7609(a).
    The EIS also must include a
    “cumulative impact” analysis addressing “the incremental
    impact of the action when added to other past, present, and
    reasonably foreseeable future actions” of any agency or
    individual. 40 C.F.R. § 1508.7; see 40 C.F.R. § 1508.25;
    TOMAC, Taxpayers of Mich. Against Casinos v. Norton, 
    433 F.3d 852
    , 864 (D.C. Cir. 2006). NEPA does not, however,
    “require agencies to elevate environmental concerns over other
    appropriate considerations. . . . [I]t require[s] only that the
    agency take a ‘hard look’ at the environmental consequences
    before taking a major action.” Balt. Gas & Elec., 462 U.S. at
    5
    97 (citation omitted) (quoting Kleppe v. Sierra Club, 
    427 U.S. 390
    , 410 n.21 (1976)). It requires informed decisionmaking
    “but not necessarily the best decision.” New 
    York, 681 F.3d at 476
    ; see also Winter v. Natural Res. Def. Council, Inc., 
    555 U.S. 7
    , 23 (2008) (“NEPA itself does not mandate particular
    results.” (quoting 
    Robertson, 490 U.S. at 350
    )).
    The BLM is also constrained by the Federal Land Policy
    and Management Act of 1976 (FLPMA), 43 U.S.C. §§ 1701 et
    seq., which requires it to “manage the public lands under
    principles of multiple use and sustained yield,” 
    id. § 1732(a).
    Multiple use requires balancing the competing uses of land, 
    id. § 1702(c);
    sustained yield requires the BLM to control
    depleting uses over time, 
    id. § 1702(h).
    See also Norton v. S.
    Utah Wilderness Alliance, 
    542 U.S. 55
    , 58 (2004). The BLM
    does so by using a “multi-step planning and decisionmaking
    process” that begins with the formation of a land use plan for a
    geographic region called a resource management plan.
    Theodore Roosevelt 
    I, 616 F.3d at 504
    ; see 43 C.F.R.
    § 1601.0-5(n) (describing contents of resource management
    plan). The resource management plan “does not, however,
    include a decision whether to undertake or approve any
    specific action. Specific projects are reviewed and approved
    separately, but must conform to the relevant [plan].”
    Theodore Roosevelt 
    I, 616 F.3d at 504
    (citing 43 C.F.R.
    §§ 1601.0-5(n), 1610.5-3(a)); see also 
    Norton, 542 U.S. at 59
    –
    60.
    B
    The Wyoming Powder River Basin is the largest source of
    coal in the United States. It accounted for more than 33 per
    cent of all coal mined in the United States in 2003. An
    increasing percentage of the coal mined in the United States in
    recent years comes from the Powder River Basin because its
    coal is lower in sulfur than most coal, contains less fly ash
    6
    when burned and can be mined using surface mining methods
    that are generally safer and less labor intensive than
    underground mining.
    Antelope Coal operates a coal mine (Antelope Mine) in
    the Wyoming Powder River Basin. The Antelope Mine
    produced 33.9 million tons of coal in 2006, representing 7.9
    per cent of the coal produced in the Wyoming Powder River
    Basin and 1.1 per cent of the estimated carbon dioxide (CO2)
    emissions in the United States. If production continues at
    average historical rates, the Antelope Mine’s coal reserves will
    be depleted within the decade. In order to extend the life of
    the mine, Antelope Coal sought to lease the West Antelope II
    tracts, encompassing 4,100 acres of federal coal reserves on
    two separate tracts adjacent to the mine.
    On April 6, 2005, Antelope Coal applied to the BLM,
    requesting that the West Antelope II tracts be offered for
    competitive lease sale. On October 17, 2006, the BLM
    published a notice of its intent to prepare an EIS for leasing the
    West Antelope II tracts and announced that it planned to hold a
    public “scoping” hearing to solicit comments on the issues to
    be considered in the EIS. On February 8, 2008, the EPA
    published a notice of the availability of the draft EIS and
    solicited public comment on it. The BLM received comments
    on the draft EIS at a public hearing and in writing. On
    December 19, 2008, the EPA published a notice of the
    availability of the FEIS. The FEIS spans nearly five hundred
    pages and includes the BLM’s responses to public comments
    on the draft EIS. The BLM solicited further public comment
    on the FEIS and issued written responses to the comments it
    received. On March 25, 2010, the BLM issued the ROD,
    approving Antelope Coal’s application and dividing the land
    into two tracts, each to be offered for lease by competitive
    bidding. Antelope Coal won the bidding for both leases and
    the leases became effective in 2011.
    7
    After the BLM approved the leases, WildEarth and the
    PRBRC each filed a notice of administrative appeal with the
    Interior Board of Land Appeals (IBLA). WildEarth sought a
    stay of the ROD pending appeal but the IBLA did not act on
    WildEarth’s motion within 45 days, thus making the ROD the
    BLM’s final agency action in WildEarth’s appeal. 43 C.F.R.
    § 4.21(a)(3), (c). The PRBRC pursued its administrative
    appeal and the IBLA affirmed the ROD in full. See Powder
    River Basin Res. Council, 180 IBLA 119 (2010); see also 43
    C.F.R. § 4.21(d) (IBLA decision is final agency action).
    WildEarth and the PRBRC filed separate complaints in the
    district court raising similar challenges to the adequacy of the
    FEIS. 2 The district court consolidated the two cases and,
    upon the parties’ cross-motions, granted summary judgment to
    the defendants on all claims. WildEarth Guardians v.
    Salazar, 
    880 F. Supp. 2d 77
    (D.D.C. 2012). Both WildEarth
    and the PRBRC timely appealed.
    II
    A. Standing
    We begin with standing. See Steel Co. v. Citizens for a
    Better Env’t, 
    523 U.S. 83
    , 94–95 (1998). The party invoking
    federal jurisdiction bears the burden of establishing the
    elements of Article III standing:
    First, the plaintiff must have suffered an injury in
    fact—an invasion of a legally protected interest which
    is (a) concrete and particularized, and (b) actual or
    2
    We note that, although the Appellants’ claim may not have
    been ripe when first pursued in district court, it has since ripened
    because leases have been issued to Antelope Coal for the tracts.
    Recording of Oral Argument at 9:40 (Nov. 18, 2013); see Ctr. for
    Biological Diversity v. U.S. Dep’t of Interior, 
    563 F.3d 466
    , 480–82
    (D.C. Cir. 2009).
    8
    imminent, not conjectural or hypothetical. Second,
    there must be a causal connection between the injury
    and the conduct complained of—the injury has to be
    fairly traceable to the challenged action of the
    defendant, and not the result of the independent action
    of some third party not before the court. Third, it
    must be likely, as opposed to merely speculative, that
    the injury will be redressed by a favorable decision.
    Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 560–61 (1992)
    (citations, quotation marks and alterations omitted); accord
    Texas v. EPA, 
    726 F.3d 180
    , 198 (D.C. Cir. 2013). “[A]n
    association has standing to bring suit on behalf of its members
    when: (a) its members would otherwise have standing to sue in
    their own right; (b) the interests it seeks to protect are germane
    to the organization’s purpose; and (c) neither the claim asserted
    nor the relief requested requires the participation of individual
    members in the lawsuit.” Hunt v. Wash. State Apple Adver.
    Comm’n, 
    432 U.S. 333
    , 343 (1977); accord Am. Trucking
    Ass’ns, Inc. v. Fed. Motor Carrier Safety Admin., 
    724 F.3d 243
    , 247 (D.C. Cir. 2013), petition for cert. filed, 
    82 U.S.L.W. 3259
    (U.S. Oct. 17, 2013) (13-509). We have little difficulty
    concluding that the latter two elements of associational
    standing are met here and focus on whether the members of
    WildEarth or the PRBRC would otherwise have standing to
    sue in their own right.
    As we discuss in Section II.B, infra, the Appellants claim
    that the BLM failed to adequately consider several
    environmental concerns, including the increase in local
    pollution and global climate change caused by future mining,
    before authorizing the leasing of the West Antelope II tracts.
    Their claim describes the “archetypal procedural injury”—an
    agency’s failure to prepare (or adequately prepare) an EIS
    before taking action with adverse environmental
    consequences. Nat’l Parks Conservation Ass’n v. Manson,
    9
    
    414 F.3d 1
    , 5 (D.C. Cir. 2005); see Defenders of 
    Wildlife, 504 U.S. at 572
    & n.7. Although we relax the redressability and
    imminence requirements for a plaintiff claiming a procedural
    injury, “the requirement of injury in fact is a hard floor of
    Article III jurisdiction that cannot be removed by statute.”
    Summers v. Earth Island Inst., 
    555 U.S. 488
    , 497 (2009);
    accord Nat’l Ass’n of Home Builders v. EPA, 
    667 F.3d 6
    , 15
    (D.C. Cir. 2011). A procedural injury claim therefore must be
    tethered to some concrete interest adversely affected by the
    procedural deprivation: “[A] procedural right in vacuo . . . is
    insufficient to create Article III standing.” 
    Summers, 555 U.S. at 496
    .
    The procedural injury the Appellants claim—the allegedly
    deficient FEIS—is tied to their respective members’ concrete
    aesthetic and recreational interests.           “[E]nvironmental
    plaintiffs adequately allege injury in fact when they aver that
    they use the affected area and are persons ‘for whom the
    aesthetic and recreational values of the area will be lessened’
    by the challenged activity.” Friends of the Earth, Inc. v.
    Laidlaw Envtl. Servs. (TOC), Inc., 
    528 U.S. 167
    , 183 (2000)
    (quoting Sierra Club v. Morton, 
    405 U.S. 727
    , 735 (1972)). In
    support of their summary judgment motion, the Appellants
    submitted affidavits from several of their members attesting to
    those members’ aesthetic interests in the land surrounding the
    West Antelope II tracts and specific plans to visit the area
    regularly for recreational purposes. We agree that, as the
    district court found and the parties do not dispute, the affidavits
    suffice to show that some of the Appellants’ members will be
    injured by the increase in local air, water and land pollution
    that will result from mining on the West Antelope II tracts.
    See Friends of the 
    Earth, 528 U.S. at 181
    –83; Defenders of
    
    Wildlife, 504 U.S. at 562
    –64.
    As for causation, in a case alleging a procedural
    deficiency, “an adequate causal chain must contain at least two
    10
    links: one connecting the omitted EIS to some substantive
    government decision that may have been wrongly decided
    because of the lack of an EIS and one connecting that
    substantive decision to the plaintiff’s particularized injury.”
    Fla. Audubon Soc’y v. Bentsen, 
    94 F.3d 658
    , 668 (D.C. Cir.
    1996) (en banc); see also Defenders of Wildlife v. Perciasepe,
    
    714 F.3d 1317
    , 1323 (D.C. Cir. 2013) (causation requirement
    not relaxed). The first link does not require the plaintiff to
    show that but for the alleged procedural deficiency the agency
    would have reached a different substantive result. See City of
    Dania Beach, Fla. v. FAA, 
    485 F.3d 1181
    , 1186 (D.C. Cir.
    2007); Ctr. for Law & Educ. v. Dep’t of Educ., 
    396 F.3d 1152
    ,
    1160 (D.C. Cir. 2005). “All that is necessary is to show that
    the procedural step was connected to the substantive result.”
    Massachusetts v. EPA, 
    549 U.S. 497
    , 518 (2007) (quoting
    Sugar Cane Growers Coop. of Fla. v. Veneman, 
    289 F.3d 89
    ,
    94–95 (D.C. Cir. 2002)); accord Defenders of 
    Wildlife, 504 U.S. at 572
    n.7. But a plaintiff “must still demonstrate a
    causal connection between the agency action and the alleged
    injury.” City of Dania Beach, 
    Fla., 485 F.3d at 1186
    ; accord
    Ctr. for Law & 
    Educ., 396 F.3d at 1160
    ; see also Fla. Audubon
    
    Soc’y, 94 F.3d at 664
    –65 (“[A] procedural-rights plaintiff must
    show not only that the defendant’s acts omitted some
    procedural requirement, but also that it is substantially
    probable that the procedural breach will cause the essential
    injury to the plaintiff’s own interest.”). We think the
    Appellants have done so here because the local pollution that
    causes their members’ aesthetic and recreational injuries
    follows inexorably from the decision to authorize leasing on
    the West Antelope II tracts.
    The relaxed redressability requirement is also satisfied.
    See Ctr. for Law & 
    Educ., 396 F.3d at 1160
    & n.2 (discussing
    relationship between causation and redressability); Fla.
    Audubon 
    Soc’y, 94 F.3d at 668
    (first causal link “foreshadows”
    11
    redressability). Vacatur of the BLM order would redress the
    Appellants’ members’ injuries because, if the BLM is required
    to adequately consider each environmental concern, it could
    change its mind about authorizing the lease offering. See
    Lemon v. Geren, 
    514 F.3d 1312
    , 1315 (D.C. Cir. 2008); City of
    Dania Beach, 
    Fla., 485 F.3d at 1186
    . We therefore conclude
    that the Appellants have standing to challenge the procedural
    inadequacy of the BLM’s decision—namely, the alleged
    deficiencies in the FEIS—based on their members’ aesthetic
    and recreational injuries caused by local pollution.
    The district court used this analysis insofar as it applied to
    the Appellants’ argument that the BLM failed to adequately
    address local pollution. WildEarth Guardians, 
    880 F. Supp. 2d
    at 86–87. The court went on, however, to address
    separately their standing to argue that the FEIS failed to
    adequately address the impact of the leasing decision on global
    climate change. 
    Id. at 83.
    It found they lacked standing to
    raise the argument because they could not demonstrate a link
    between their members’ recreational and aesthetic interests,
    “which are uniformly local, and the diffuse and unpredictable
    effects of [greenhouse gas] emissions.” 
    Id. at 84.
    The
    district court therefore seemed to require that the specific type
    of pollution causing the Appellants’ aesthetic injury—here,
    local pollution—be the same type that was inadequately
    considered in the FEIS. In this respect, we think it sliced the
    salami too thin. Cf. Duke Power Co. v. Carolina Envtl. Study
    Grp. Inc., 
    438 U.S. 59
    , 78–79 (1978) (rejecting contention that,
    excepting taxpayer suit, plaintiff who has otherwise
    established elements of Article III standing must also
    demonstrate nexus between right asserted and injury alleged).
    In Center for Biological Diversity v. U.S. Department of
    Interior, environmental groups challenged Interior’s decision
    to expand leasing areas for oil and gas development off the
    coast of Alaska. 
    563 F.3d 466
    (D.C. Cir. 2009). We
    12
    concluded that the petitioners had satisfied neither the injury in
    fact nor the causation requirements of standing based on their
    claim that expanded drilling would contribute to global climate
    change which in turn would threaten their members’
    enjoyment of the area and indigenous animal species. 
    Id. at 475–79;
    see also Wash. Envtl. Council v. Bellon, 
    732 F.3d 1131
    , 1141–46 (9th Cir. 2013) (finding no causal link between
    regulatory failure and assumed injury from climate change).
    We think (and the Appellants do not dispute) that the
    Appellants likewise cannot establish standing based on the
    effects of global climate change. But they have established a
    separate injury in fact not caused by climate change—the harm
    to their members’ recreational and aesthetic interests from
    local pollution. In Center for Biological Diversity, we noted
    that “Interior’s adoption of an irrationally based Leasing
    Program could cause a substantial increase in the risk to”
    petitioners’ similar aesthetic injury—“their enjoyment of the
    animals affected by the offshore drilling”—and held that this
    gave petitioners standing to challenge the decision to authorize
    the leasing even though the claimed deficiencies concerned
    Interior’s failure to consider greenhouse gas emissions and
    global climate 
    change. 563 F.3d at 479
    . The same reasoning
    applies here. The Appellants’ aesthetic injury follows from
    an inadequate FEIS whether or not the inadequacy concerns
    the same environmental issue that causes their injury. If we
    vacate the BLM order, their injury will be redressed regardless
    whether the FEIS’s specific flaw relates to local or global
    environmental impacts; either way, the remedy is “limited to
    the inadequacy”—here, a deficient FEIS—“that produced the
    injury in fact that the plaintiff has established.”
    DaimlerChrysler Corp. v. Cuno, 
    547 U.S. 332
    , 353 (2006)
    (quoting Lewis v. Casey, 
    518 U.S. 343
    , 357 (1996)).
    This Court once held that “having established standing to
    challenge the adequacy of the FEIS on at least one ground,
    13
    [plaintiffs] are entitled to raise other inadequacies in the FEIS.”
    Sierra Club v. Adams, 
    578 F.2d 389
    , 392 (D.C. Cir. 1978).
    We rested this statement on the premise that a plaintiff may
    invoke “the ‘public interest’ in requiring government officials
    to discharge faithfully their statutory duties under NEPA.” 
    Id. at 392;
    see also 
    Morton, 405 U.S. at 737
    . We express no
    opinion on whether the “public interest” rationale remains
    cognizable in light of subsequent Supreme Court precedent.
    See, e.g., 
    DaimlerChrysler, 547 U.S. at 351
    –53 (rejecting
    “commutative” theory of standing whereby standing as to one
    claim would suffice for all claims arising from same nucleus of
    operative fact); see also 
    id. at 353
    n.5 (distinguishing Adams
    from case at bar but expressing no opinion on its validity);
    
    Lewis, 518 U.S. at 358
    n.6 (where injunction requiring
    provision of certain services to inmates concerned
    inadequacies other than those that harmed plaintiffs, noting
    that “standing is not dispensed in gross. If the right to
    complain of one administrative deficiency automatically
    conferred the right to complain of all administrative
    deficiencies, any citizen aggrieved in one respect could bring
    the whole structure of state administration before the courts for
    review.”). We rest our holding on a different rationale. The
    Appellants may challenge each of the alleged inadequacies in
    the FEIS because each constitutes a procedural injury
    connected to their members’ recreational and aesthetic
    injuries: Their members’ injuries are caused by the allegedly
    unlawful ROD and would be redressed by vacatur of the ROD
    on the basis of any of the procedural defects identified in the
    FEIS. 3 Contrary to the BLM’s assertion, the Appellants
    3
    The familiar principle that a plaintiff must demonstrate
    standing for each form of relief sought, see 
    Summers, 555 U.S. at 493
    ; 
    DaimlerChrysler, 547 U.S. at 352
    , is not to the contrary. The
    Appellants seek only one type of relief relevant here—the vacatur of
    the BLM’s leasing decision. They simply advance several
    14
    adequately raised their theory of procedural injury below and
    we therefore conclude that they have standing to challenge
    each of the alleged deficiencies in the FEIS.
    B. The Merits
    We apply the arbitrary and capricious standard of the
    Administrative Procedure Act, 5 U.S.C. §§ 551 et seq., to the
    merits of the Appellants’ NEPA and FLPMA challenges and
    review de novo the district court’s grant of summary judgment.
    Theodore Roosevelt 
    I, 616 F.3d at 507
    ; Nevada v. Dep’t of
    Energy, 
    457 F.3d 78
    , 87 (D.C. Cir. 2006); see 5 U.S.C.
    § 706(2)(A). In doing so, we are mindful that our role is not to
    “ ‘flyspeck’ an agency’s environmental analysis, looking for
    any deficiency no matter how minor.” 
    Nevada, 457 F.3d at 93
    . Rather, it is “simply to ensure that the agency has
    adequately considered and disclosed the environmental impact
    of its actions and that its decision is not arbitrary or
    capricious.” City of Olmsted Falls, Ohio v. FAA, 
    292 F.3d 261
    , 269 (D.C. Cir. 2002) (quoting Balt. Gas & 
    Elec., 462 U.S. at 97
    –98). In short, “an agency must take a ‘hard look’ at the
    environmental effects of its proposed action.” Theodore
    Roosevelt Conservation P’ship v. Salazar (Theodore Roosevelt
    II), 
    661 F.3d 66
    , 75 (D.C. Cir. 2011); accord Balt. Gas & 
    Elec., 462 U.S. at 97
    . While the Appellants raise numerous
    challenges to the sufficiency of the FEIS, we find none has
    merit and consider only two worthy of discussion.
    1. Global Climate Change
    We turn first to the Appellants’ argument that the BLM
    did not take a hard look at the effect of its leasing decision on
    arguments in support of that claim. Cf. Am. Petroleum Inst. v. EPA,
    
    72 F.3d 907
    , 911–12 (D.C. Cir. 1996).
    15
    global climate change.4 In the FEIS, the BLM discussed at
    length the prevailing scientific consensus on global climate
    change and coal mining’s contribution to it. The BLM
    estimated the greenhouse gas (GHG) emissions that occurred
    at the Antelope Mine in 2007 and projected emissions for a
    typical year of operations if the West Antelope II tracts are also
    leased. It projected that, with the addition of the West
    Antelope II tracts, Antelope Mine would account for only .63
    per cent of state-wide emissions of carbon dioxide equivalent
    (CO2e). At the same time, the BLM noted that several factors
    made any projection about future emissions speculative.
    First, the BLM does not authorize mining through the issuance
    of a coal lease; rather, a mining permit must be obtained from
    the Wyoming Department of Environmental Quality with
    oversight from an independent federal agency, the Office of
    Surface Mining, and therefore mitigation measures can be
    imposed at a later stage. Joint Appendix (JA) 422–23; see 30
    U.S.C. §§ 1253, 1273(c). The BLM further assumed that
    mining would continue at existing production rates and the
    coal would continue to be used to generate electricity by
    coal-fired power plants.         Finally, the BLM identified
    considerable uncertainty about regulatory and technological
    developments that could affect future emissions.
    4
    The district court did not reach this issue and the Appellants
    therefore ask us to remand. The parties have briefed the issue,
    however, and at argument the Appellants indicated they have little
    more to add. The agency record is before us, our review of the
    district court’s decision post-remand would be de novo and we think
    the merits of the issue are clear. Indeed, the only purpose served by
    remand would be to satisfy the Appellants’ evident desire to delay
    mining on the West Antelope II tracts. We think it appropriate to
    resolve the issue now. See Friends of Blackwater v. Salazar, 
    691 F.3d 428
    , 434 n.* (D.C. Cir. 2012).
    16
    The Appellants allege several inadequacies in the BLM
    analysis but they are of the flyspecking variety. First, they
    contend that the BLM’s estimate of Antelope Mine’s
    contribution to state-wide emissions failed to incorporate an
    analysis of the impact of these emissions, particularly their
    cumulative impact together with emissions from eleven other
    pending lease applications in the Powder River Basin. We
    think the BLM satisfied its obligation to consider “the
    incremental impact of the action when added to other past,
    present, and reasonably foreseeable future actions.” 40
    C.F.R. § 1508.7; see 
    TOMAC, 433 F.3d at 864
    . The BLM
    quantified average CO2 or CO2e emissions for the Antelope
    Mine, for Wyoming and for the United States. From these
    figures it quantified the Antelope Mine’s contribution to
    state-wide CO2e and nation-wide CO2 emissions and the
    Wyoming Powder River Basin’s contribution to nation-wide
    CO2 emissions.         It also projected Antelope Mine’s
    contribution to state-wide emissions going forward. Although
    it did not discuss specific global impacts that would result from
    additional emissions, the BLM explained that “[g]iven the state
    of the science, it is not possible to associate specific actions
    with the specific global impacts such as potential climate
    effects.” JA 891. This conclusion is supported by draft
    guidance from the Council on Environmental Quality (CEQ).5
    See JA 1281 (“[I]t is not currently useful for the NEPA analysis
    to attempt to link specific climatological changes, or the
    environmental impacts thereof, to the particular project or
    emissions, as such direct linkage is difficult to isolate and to
    understand. The estimated level of GHG emissions can serve
    5
    The CEQ promulgates regulations that implement NEPA.
    See 40 C.F.R. § 1500.1; see also 
    Robertson, 490 U.S. at 355
    (CEQ
    regulations “are entitled to substantial deference”). As the BLM
    concedes, the draft guidance is not an authoritative interpretation of
    NEPA’s requirements entitled to deference but nevertheless we find
    it useful.
    17
    as a reasonable proxy for assessing potential climate change
    impacts, and provide decision makers and the public with
    useful information for a reasoned choice among alternatives.”).
    Because current science does not allow for the specificity
    demanded by the Appellants, the BLM was not required to
    identify specific effects on the climate in order to prepare an
    adequate EIS.
    As for consideration of the eleven other pending lease
    applications, the Appellants have not shown that approval of
    the applications was “reasonably foreseeable.” Granted,
    when WildEarth filed its brief in the district court in 2011, it
    asserted that the eleven lease applications “certainly qualify as
    ‘reasonably foreseeable future actions,’ given that BLM has
    already prepared EISs for all of these leases, recently held a
    sale for one lease, recently issued RODs for three leases, and
    has four RODs currently pending.” JA 57 (WildEarth brief in
    district court); see also JA 989 (listing eleven applications).
    But hindsight is 20-20. In December 2008, when the BLM
    issued the FEIS, it had issued drafts EISs for only four of the
    eleven leases; seven had not passed the “scoping” stage. See
    http://www.blm.gov/wy/st/en/programs/energy/Coal_Resourc
    es/PRB_Coal/lba_title.html (last visited December 15, 2013).
    Because “projects in their infancy have uncertain futures,” it
    was neither arbitrary nor capricious for the BLM to omit the
    eleven proposed leases from its analysis of reasonably
    foreseeable future actions. Theodore Roosevelt 
    I, 616 F.3d at 513
    . (Hindsight bears this out: Although five of the leases
    have now been sold, one was rejected and five are either
    pending or have been suspended. See http://www.blm.gov/
    wy/st/en/programs/energy/Coal_Resources/PRB_Coal/lba_titl
    e.html (last visited December 15, 2013)).            Instead of
    assuming, as the Appellants do, that every pending lease
    application will be approved, the BLM evaluated GHG
    emissions as a percentage of state- and nation-wide emissions.
    18
    We think this approach suffices. See Mayo Found. v. Surface
    Transp. Bd., 
    472 F.3d 545
    , 555–56 (8th Cir. 2006) (modeling
    of emissions on both regional and national levels sufficient if
    local modeling infeasible and requirements of 40 C.F.R.
    § 1502.22(b) satisfied); see also Morris v. NRC, 
    598 F.3d 677
    ,
    693 (10th Cir. 2010) (FEIS need not quantify amount of
    radiation emitted from other sources if it considered effect of
    radiation from past mining and proposed operation and
    determined that issuance of new license would have only
    negligible effect on amount of radiation emitted).
    The Appellants also argue that the BLM failed to analyze a
    reasonable range of alternatives to address GHG emissions and
    climate change.        The BLM discussed five separate
    alternatives in the FEIS at length, however, and analyzed the
    environmental impact of each. The Appellants nevertheless
    protest that the FEIS did not adequately consider a list of
    alternative ideas that WildEarth submitted in a single
    paragraph in response to the FEIS. We sense a bit of
    sandbagging here. The PRBRC participated in the scoping
    hearing that preceded the draft EIS and submitted written
    comments on the draft EIS and WildEarth submitted written
    comments on the draft EIS that specifically addressed the
    draft’s discussion of reasonable alternatives. At no point did
    either WildEarth or the PRBRC mention the list of alternatives
    WildEarth raised at the last minute. To be sure, the BLM
    invited written comments on the FEIS, see 40 C.F.R.
    § 1503.1(b), and it had the opportunity to respond before it
    issued the ROD. But WildEarth’s final comments did not
    really respond to the FEIS; instead, they raised new issues.
    We generally apply a deferential “rule of reason” to govern
    “both which alternatives the agency must discuss, and the
    extent to which it must discuss them,” Citizens Against
    
    Burlington, 938 F.2d at 195
    (emphasis in original) (quotation
    marks omitted); see also 
    Nevada, 457 F.3d at 93
    , and we think
    19
    the last-ditch, kitchen-sink nature of WildEarth’s suggestions
    bears on the extent to which the BLM was required to address
    them. See Vt. 
    Yankee, 435 U.S. at 553
    –54 (“[A]dministrative
    proceedings should not be a game or a forum to engage in
    unjustified obstructionism by making cryptic and obscure
    reference to matters that ‘ought to be’ considered and then,
    after failing to do more to bring the matter to the agency’s
    attention, seeking to have that agency determination vacated
    on the ground that the agency failed to consider matters
    ‘forcefully presented.’ ”).        The BLM responded to
    WildEarth’s comments by referring WildEarth to the portion of
    the FEIS that does address a full range of alternatives and
    reminding WildEarth that the BLM does not issue mining
    permits and therefore further alternatives could also be
    addressed at the permitting stage. We think the BLM acted
    reasonably by responding in this manner. We therefore agree
    with the IBLA that the BLM satisfied its obligations under
    NEPA to consider climate change. See Powder River Basin
    Resource Council, 180 IBLA at 134.
    2. Local Pollution
    Next we consider the Appellants’ argument that the BLM
    failed to take a hard look at the effect the lease developments
    would have on local ozone levels. Ground level ozone is a
    pollutant that forms when emissions of nitrogen oxides (NOx)
    and volatile organic compounds react to sunlight. There are
    several types of NOx, the most toxic being nitrogen dioxide
    (NO2). Inhalation of ground level ozone is associated with
    several health risks, which the FEIS discussed. While the
    EPA has established National Ambient Air Quality Standards
    (NAAQS) for ozone and NO2, see Coal. for Responsible
    Regulation, Inc. v. EPA, 
    684 F.3d 102
    , 132 (D.C. Cir. 2012),
    cert. granted in part 
    134 S. Ct. 418
    (2013), there is no
    corresponding NAAQS for NOx.
    20
    In the FEIS, the BLM noted that the area around the West
    Antelope II tracts is in attainment—i.e., in compliance with
    NAAQS—for all pollutants. JA 496, 789; see 42 U.S.C.
    § 7407(d)(1)(A)(ii); see also JA 932 (responding to comment
    regarding compliance with ozone NAAQS). The BLM
    projected that by 2010 emissions of NO2 would remain well
    below NAAQS; further, the FEIS included an extensive
    discussion of the current and projected emissions of NOx and
    NO2. See JA 510–17; JA 680–81.6 The projection of NO2
    emissions was based on modeling done for the Powder River
    Basin Coal Review, “a regional technical study . . . to help
    evaluate the cumulative impacts of coal and other mineral
    development in the PRB.” JA 648; see JA 678. No separate
    projection, however, was made for ozone. As the BLM
    explained, it addressed ozone in its discussion of NOx
    emissions because NOx is one of the main ingredients in the
    formation of ground level ozone and NO2, in turn, is a type of
    NOx. The BLM also noted that further modeling would be
    done at the permitting stage to ensure compliance with state
    and federal air quality standards.
    The Appellants’ objections to the BLM’s analysis boil
    down to a dispute about the adequacy of using projected
    emissions of ozone precursors—like NOx and NO2—as
    proxies by which to analyze the impact of future ozone levels.
    They point to one report in the record observing that there is
    not a one-to-one correlation between NOx and ozone levels
    6
    We agree with the Appellants that the BLM’s interchangeable
    use of the terms NOx and NO2 can be confusing, especially where it
    erroneously refers to a NAAQS for NOx. JA 514; see also BLM Br.
    31–32 (making same error). But we do not think one typo in a
    five-hundred page FEIS renders it insufficient where, as here,
    context makes the point clear. Cf. US Magnesium, LLC v. EPA, 
    630 F.3d 188
    , 193 & n.3 (D.C. Cir. 2011) (typo irrelevant where meaning
    could be readily ascertained).
    21
    because ozone produced per molecule of NOx emissions varies
    considerably depending on local conditions. See JA 995.
    But the same report observed that “[o]zone can be reduced by
    controlling . . . NOx” and “[r]ural ozone is more sensitive to
    NOx controls,” JA 994, which observation tends to confirm the
    appropriateness of the BLM’s use of NOx as a proxy for ozone.
    The Appellants also rely on an email from a BLM air
    quality specialist opining on the adequacy of the FEIS. We
    are dubious of the email’s value, particularly because the BLM
    specialist began the email by noting that she had conducted “a
    very cursory review of the ROD” and was “not very familiar
    with the project and ha[d] not read the FEIS.” JA 1348; see
    WildEarth Guardians v. Nat’l Park Serv., 
    703 F.3d 1178
    ,
    1186–87 (10th Cir. 2013) (emails from local or lower-level
    agency representatives expressing diversity of opinion “will
    not preclude the agency from reaching a contrary decision, so
    long as the decision is not arbitrary and capricious and is
    otherwise supported by the record”); cf. Nat’l Ass’n of Home
    Builders v. Defenders of Wildlife, 
    551 U.S. 644
    , 658–59 (2007)
    (inconsistent statements by agencies’ regional offices during
    early stages of review do not render decisionmaking process
    arbitrary and capricious where proper procedures are
    followed). In any event, the email did not suggest that it was
    inappropriate to rely on NOx models instead of modeling ozone
    separately. It merely stated that the reasons for the lack of
    ozone modeling should have been articulated better. JA 1348
    (“[T]he response should include a concise explanation of
    ozone modeling and its limitations . . . and why this pollutant
    was not modeled.”). The Appellants do not question the
    adequacy of the explanation for the absence of ozone
    modeling, however, only the use of NOx as a proxy.
    We conclude that the BLM satisfied its obligations under
    NEPA. “ ‘The NEPA process involves an almost endless
    series of judgment calls,’ and ‘the line-drawing decisions
    22
    necessitated by the NEPA process are vested in the agencies,
    not the courts.’ ” Duncan’s Point Lot Owners Ass’n, Inc. v.
    FERC, 
    522 F.3d 371
    , 376 (D.C. Cir. 2008) (quoting Coal. on
    Sensible Transp., Inc. v. Dole, 
    826 F.2d 60
    , 66 (D.C. Cir.
    1987)) (alterations omitted). It may have been possible or
    even prudent for the BLM to separately model future ozone
    levels but we think that, given the limitations on such modeling
    and the critical role NOx plays in ozone formation, the BLM’s
    projections and extensive discussion of NOx and NO2
    emissions suffice.
    We have considered—and rejected—the Appellants’ other
    arguments challenging the sufficiency of the FEIS and
    conclude that the FEIS complies with NEPA, the FLPMA and
    the MLA. We therefore affirm the district court’s grant of
    summary judgment to the defendants.
    So ordered.
    

Document Info

Docket Number: 12-5300

Citation Numbers: 407 U.S. App. D.C. 309, 738 F.3d 298

Filed Date: 12/24/2013

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (37)

Morris v. United States Nuclear Regulatory Commission , 598 F.3d 677 ( 2010 )

TOMAC v. Norton, Gale A. , 433 F.3d 852 ( 2006 )

Lemon v. Geren , 514 F.3d 1312 ( 2008 )

Center for Biological Diversity v. US Dept. of Interior , 563 F.3d 466 ( 2009 )

THEODORE ROOSEVELT CONSERVATION v. Salazar , 616 F.3d 497 ( 2010 )

Theodore Roosevelt Conservation Partnership v. Salazar , 661 F.3d 66 ( 2011 )

City Dania Beach FL v. FAA , 485 F.3d 1181 ( 2007 )

National Parks Conservation Ass'n v. Manson , 414 F.3d 1 ( 2005 )

citizens-against-burlington-inc-v-james-b-busey-iv-administrator , 938 F.2d 190 ( 1991 )

US Magnesium, LLC v. Environmental Protection Agency , 630 F.3d 188 ( 2011 )

Sugar Cane Growers Cooperative of Florida v. Veneman , 289 F.3d 89 ( 2002 )

american-petroleum-institute-and-national-petroleum-refiners-association-v , 72 F.3d 907 ( 1996 )

Duncan's Point Lot Owners Ass'n v. Federal Energy ... , 522 F.3d 371 ( 2008 )

The Center for Law and Education v. Department of Education , 396 F.3d 1152 ( 2005 )

City of Olmsted Falls, Ohio v. Federal Aviation ... , 292 F.3d 261 ( 2002 )

Coalition on Sensible Transportation, Inc. v. Elizabeth Dole , 826 F.2d 60 ( 1987 )

Sierra Club v. Brock Adams, Jr., Secretary of ... , 578 F.2d 389 ( 1978 )

National Ass'n of Home Builders v. Environmental Protection ... , 667 F.3d 6 ( 2011 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

WILDEARTH GUARDIANS v. Salazar , 783 F. Supp. 2d 61 ( 2011 )

View All Authorities »