In re Application of Columbus S. Power Co. , 138 Ohio St. 3d 448 ( 2014 )


Menu:
  • [Cite as In re Application of Columbus S. Power Co., 
    138 Ohio St. 3d 448
    , 2014-Ohio-462.]
    IN RE APPLICATION OF COLUMBUS SOUTHERN POWER COMPANY ET AL.;
    INDUSTRIAL ENERGY USERS-OHIO ET AL., APPELLANTS;
    PUBLIC UTILITIES COMMISSION, APPELLEE;
    OHIO POWER COMPANY, INTERVENING APPELLEE.
    [Cite as In re Application of Columbus S. Power Co., 
    138 Ohio St. 3d 448
    ,
    2014-Ohio-462.]
    Public utilities—Electric security plan—R.C. 4928.143—Commission’s decision
    to permit recovery of carrying charges under R.C. 4928.143(B)(2)(d) was
    lawful and reasonable—Utility not required to prove charges are
    “necessary” in order to recover costs under R.C. 4928.143(B)(2)(d)—
    Commission did not err in denying recovery of previously collected
    “provider of last resort” charges—Refund of POLR revenues already
    collected from customers by utility would violate prohibition against
    retroactive ratemaking—Orders affirmed.
    (No. 2012-0187—Submitted October 8, 2013—Decided February 13, 2014.)
    APPEAL from the Public Utilities Commission of Ohio,
    Nos. 08-917-EL-SSO and 08-918-EL-SSO.
    ____________________
    LANZINGER, J.
    I. SUMMARY
    {¶ 1} This second appeal stems from the approval by the Public Utilities
    Commission (“commission” or “PUCO”) of the first electric security plan of the
    American Electric Power operating companies, Columbus Southern Power
    Company and Ohio Power Company (collectively, “AEP”). We first reviewed
    the commission’s approval of the electric security plan in 2011. In re Application
    of Columbus S. Power Co., 
    128 Ohio St. 3d 512
    , 2011-Ohio-1788, 947 N.E.2d
    SUPREME COURT OF OHIO
    655. There, we held that the commission committed reversible error on three
    issues: (1) granting AEP a retroactive rate increase (but finding that no refund was
    available), (2) approving the recovery of carrying costs associated with
    environmental investments without proper statutory authority, and (3) authorizing
    the provider-of-last-resort (“POLR”) charge without sufficient evidence.        We
    remanded the POLR-charge and carrying-costs issues for further consideration.
    
    Id. at ¶
    8-21, 31-35, 22-30.
    {¶ 2} On remand, the commission determined that the environmental-
    investment carrying costs were lawful under R.C. 4928.143(B)(2)(d).           In re
    Application of Columbus S. Power Co., Pub. Util. Comm. Nos. 08-917-EL-SSO
    and 08-918-EL-SSO, at 14-15 (Oct. 3, 2011) (the “Remand Order”). But the
    commission found that AEP had not presented evidence of its actual POLR costs
    and directed the company to deduct that charge from its tariff schedules. 
    Id. at 22-24.
    The commission also rejected a request to recover the amounts of the
    POLR charge and carrying costs that AEP had collected from April 2009 through
    May 2011. 
    Id. at 34-36.
           {¶ 3} Following rehearing, the Office of Consumers’ Counsel (“OCC”)
    and Industrial Energy Users-Ohio (“IEU”) filed this appeal, raising numerous
    challenges to the commission’s remand orders. None has merit. Therefore, we
    affirm the orders of the commission.
    II. FACTS AND PROCEDURAL BACKGROUND
    {¶ 4} R.C. 4928.141(A) requires electric-distribution utilities to provide
    to consumers a “standard service offer of all competitive retail electric services
    necessary to maintain essential electric service to consumers, including a firm
    supply of electric generation service.” The utility may provide the offer in one of
    two ways: through a “market rate offer” under R.C. 4928.142 or through an
    “electric security plan” under R.C. 4928.143.
    2
    January Term, 2014
    {¶ 5} AEP chose the second option and filed an application for approval
    of an electric security plan (“ESP”). The ESP statute permits numerous rate
    components, R.C. 4928.143(B)(2), but says very little about rate calculation. The
    only substantive requirement is that the plan must be “more favorable in the
    aggregate as compared to the expected results” of a market-rate offer. R.C.
    4928.143(C)(1).
    A. ESP approval and court remand
    {¶ 6} On March 18, 2009, the commission issued an opinion and order
    approving AEP’s first ESP, to be in effect from 2009 to 2011. In re Application
    of Columbus S. Power Co., Pub. Util. Comm. Nos. 08-917-EL-SSO and 08-918-
    EL-SSO (Mar. 18, 2009) (the “ESP Order”). Following two rounds of rehearings,
    OCC and IEU appealed. We eventually held that the commission had granted
    AEP a retroactive rate increase of $63 million in violation of R.C. 4928.141(A),
    as well as the rule established in Keco Industries, Inc. v. Cincinnati & Suburban
    Bell Tel. Co., 
    166 Ohio St. 254
    , 
    141 N.E.2d 465
    (1957). Nevertheless, OCC had
    not established that it was entitled to its requested remedy of a refund, and that
    ruling was conclusive of the issue. In re Application of Columbus S. Power Co.,
    
    128 Ohio St. 3d 512
    , 2011-Ohio-1788, 
    947 N.E.2d 655
    , ¶ 8.
    {¶ 7} We also held that the commission erred when it found that AEP
    could      recover   environmental-investment    carrying    costs   under    R.C.
    4928.143(B)(2). We remanded the matter to allow the commission to specifically
    determine whether any of the nine categories of cost recovery under R.C.
    4928.143(B)(2)(a) through (i) authorized the recovery of carrying costs. 
    Id. at ¶
    31-35.
    {¶ 8} Finally, we determined that the commission approved more than
    $500 million in POLR charges over the three years of the plan. 
    Id. at ¶
    22. POLR
    costs are intended to compensate for the utility’s risks in standing ready to serve
    customers who purchase generation service from a competitive supplier and then
    3
    SUPREME COURT OF OHIO
    return to the utility for generation service. See Constellation NewEnergy, Inc. v.
    Pub. Util. Comm., 
    104 Ohio St. 3d 530
    , 2004-Ohio-6767, 
    820 N.E.2d 885
    , ¶ 39,
    fn. 5.    AEP had calculated its POLR costs for the commission using a
    mathematical formula (called the “Black-Scholes model”) that was created to
    price stock options. We held that contrary to the commission’s finding, the
    formula did not reflect the costs to AEP to be the POLR. 
    128 Ohio St. 3d 512
    ,
    2011-Ohio-1788, 
    947 N.E.2d 655
    , ¶ 25-30.
    {¶ 9} The case was remanded to allow the commission the option to
    consider whether (1) “a non-cost-based POLR charge is reasonable and lawful” or
    (2) “it is appropriate to allow AEP to present evidence of its actual POLR costs.”
    
    Id. at ¶
    30.
    B. Remand proceedings
    {¶ 10} On remand, the commission issued its May 25, 2011 order,
    directing that AEP file revised tariffs making the recovery of environmental-
    investment carrying costs and the POLR charge subject to refund as of the first
    billing cycle of June 2011. The order provided that if the commission ultimately
    determines that these charges are to be refunded to customers, interest may be
    imposed on the amounts collected by AEP in the interim.
    {¶ 11} Following a five-day hearing, the commission issued its opinion
    and order on October 3, 2011.            The commission determined that the
    environmental-investment      carrying   costs    were    lawful    under    R.C.
    4928.143(B)(2)(d). Remand Order at 14-15. Because the commission approved
    the recovery of carrying costs, no refund was ordered of those that were collected
    during the remand proceedings.
    {¶ 12} In addition, because the commission found that AEP had failed to
    submit any evidence of its actual POLR costs, it ordered AEP to remove the
    POLR charge from its tariffs. Remand Order at 22-24 and 33. And consistent
    with its May 25, 2011 order, it also directed AEP to refund to customers the
    4
    January Term, 2014
    amount of the POLR charges collected during the remand proceedings (i.e., from
    the first billing cycle in June 2011 until the October 3, 2011 remand order). 
    Id. at 33-34.
    The ESP was set to expire at the end of 2011, which was two months after
    the commission’s remand order and two weeks after the final rehearing entry. As
    a result, AEP was able to collect nearly all of its POLR costs during the term of
    the ESP, except from June 2011 to December 2011 (the end of the ESP).
    {¶ 13} During the remand proceedings, OCC and IEU had also requested
    that the commission allow customers to recover the POLR and environmental-
    investment carrying charges that AEP had collected from April 2009 through May
    2011 (when those charges became subject to refund by order of the commission
    on remand). In the initial ESP proceedings, the commission had allowed AEP to
    phase in its rate increase by deferring the recovery of a portion of annual fuel
    costs incurred during the ESP period. Under this part of the plan, the balance of
    the deferred fuel costs remaining at the end of the ESP would be recovered with
    carrying charges from 2012 to 2018. ESP Order at 20-23. On remand, OCC and
    IEU argued that the commission should reduce the balance of the deferred fuel
    costs to be collected from customers by the amount of POLR and environmental-
    investment carrying costs collected, on the theory that those charges were not
    lawfully collected based on this court’s rejection of them in the first ESP appeal.
    {¶ 14} The commission, however, refused, reasoning that any adjustment
    of the deferred fuel-cost balance to account for the collection of the past charges
    would violate this court’s prohibition against retroactive ratemaking. Remand
    Order at 35-36.
    {¶ 15} OCC’s and IEU’s applications for rehearing were denied, and this
    appeal followed.
    III. STANDARD OF REVIEW
    {¶ 16} “R.C. 4903.13 provides that a PUCO order shall be reversed,
    vacated, or modified by this court only when, upon consideration of the record,
    5
    SUPREME COURT OF OHIO
    the court finds the order to be unlawful or unreasonable.”           Constellation
    NewEnergy, Inc. v. Pub. Util. Comm., 
    104 Ohio St. 3d 530
    , 2004-Ohio-6767, 
    820 N.E.2d 885
    , ¶ 50. We will not reverse or modify a PUCO order on questions of
    fact when the record contains sufficient probative evidence to show that the
    commission’s decision was not manifestly against the weight of the evidence and
    was not so clearly unsupported by the record as to show misapprehension,
    mistake, or willful disregard of duty. Monongahela Power Co. v. Pub. Util.
    Comm., 
    104 Ohio St. 3d 571
    , 2004-Ohio-6896, 
    820 N.E.2d 921
    , ¶ 29.               The
    appellant bears the burden of demonstrating that the PUCO’s decision is against
    the manifest weight of the evidence or is clearly unsupported by the record. 
    Id. {¶ 17}
    Although the court has “complete and independent power of
    review as to all questions of law” in appeals from the PUCO, Ohio Edison Co. v.
    Pub. Util. Comm., 
    78 Ohio St. 3d 466
    , 469, 
    678 N.E.2d 922
    (1997), we may rely
    on a state agency’s expertise in interpreting a law where “highly specialized
    issues” are involved and “where agency expertise would, therefore, be of
    assistance in discerning the presumed intent of our General Assembly.”
    Consumers’ Counsel v. Pub. Util. Comm., 
    58 Ohio St. 2d 108
    , 110, 
    388 N.E.2d 1370
    (1979).
    IV. DISCUSSION
    {¶ 18} OCC and IEU challenge the commission’s orders on two primary
    grounds: (1) the orders improperly authorized the recovery of carrying costs
    associated with environmental investments under R.C. 4928.143(B)(2)(d) and (2)
    the orders improperly denied the recovery of the POLR charges and
    environmental-investment carrying costs collected by AEP from April 2009
    through May 2011. None of appellants’ supporting arguments justify reversal.
    6
    January Term, 2014
    A.     The commission’s decision to permit recovery of carrying charges
    under R.C. 4928.143(B)(2)(d) was lawful and reasonable
    {¶ 19} In its first three propositions of law, IEU argues that the
    commission erred when it found that AEP could recover certain carrying costs
    associated with environmental investments pursuant to R.C. 4928.143(B)(2)(d).
    The following background is pertinent to resolving these claims.
    {¶ 20} In the initial ESP proceedings, the commission permitted AEP to
    recover the incremental capital carrying costs on past environmental investments
    after January 1, 2009 (the beginning of the ESP period). AEP itself had made the
    environmental investments between 2001 and 2008, but they were not included in
    rates before the ESP Order. See ESP Order at 28. The commission, however,
    found that the carrying costs were recoverable during the ESP period under the
    broad language of R.C. 4928.143(B)(2), which states, “The [electric security] plan
    may provide for or include, without limitation, any of the following,” and then
    lists nine categories of cost recovery. See R.C. 4928.143(B)(2)(a) through (i). On
    appeal, we reversed the commission’s order on that point and remanded the
    matter for the commission’s specific determination whether any of the nine
    categories listed in R.C. 4928.143(B)(2)(a) through (i) authorized the recovery.
    In re Application of Columbus S. Power Co., 
    128 Ohio St. 3d 512
    , 2011-Ohio-
    1788, 
    947 N.E.2d 655
    , ¶ 31-35.
    {¶ 21} On      remand,    the    commission      determined     that    R.C.
    4928.143(B)(2)(d) permits AEP’s recovery of carrying costs. Remand Order at
    13-15. Subsection (d) provides that an ESP may include “[t]erms, conditions, or
    charges relating to * * * carrying costs * * * as would have the effect of
    stabilizing or providing certainty regarding retail electric service.” In turn, R.C.
    4928.01(A)(27) defines “retail electric service” as “any service involved in
    supplying or arranging for the supply of electricity to ultimate consumers in this
    state, from the point of generation to the point of consumption.” According to the
    7
    SUPREME COURT OF OHIO
    commission, the record evidence demonstrated that the environmental-investment
    carrying costs “have the effect of providing certainty to both the Companies and
    their customers regarding retail electric service, specifically generation service.”
    Remand Order at 14. The commission confirmed this finding on rehearing and
    further found that the carrying costs contribute to “stabilizing prices,” which
    benefits AEP’s customers. Nos. 08-917-EL-SSO and 08-918-EL-SSO, at 5-6
    (Dec. 14, 2011) (the “Remand Rehearing Entry”).
    {¶ 22} On appeal, IEU devotes its first three propositions of law to
    arguing that the commission misstated the applicable law and the facts. We will
    address each claim in turn.
    1.      The utility is not required to prove that charges are
    “necessary” in order to recover costs under R.C.
    4928.143(B)(2)(d)
    {¶ 23} In proposition of law No. I, IEU contends that the commission
    misconstrued R.C. 4928.143(B)(2)(d)’s requirement that carrying costs “have the
    effect of stabilizing or providing certainty regarding retail electric service.” IEU
    raises two challenges here: one legal (statutory interpretation) and one factual.
    We reject IEU’s arguments for the reasons that follow.
    a.      IEU has not demonstrated that R.C. 4928.143(B)(2)(d) imposes
    a “necessary” requirement
    {¶ 24} IEU offers a single challenge to the commission’s interpretation of
    R.C. 4928.143(B)(2)(d), which allows an ESP to include “charges relating to
    * * * carrying costs * * * as would have the effect of stabilizing or providing
    certainty regarding retail electric service.” IEU argues that for carrying costs to
    fit under the statute, AEP must demonstrate that the costs were necessary. IEU
    premises its argument entirely on the dictionary definition of “certainty,” citing
    Webster’s Ninth New Collegiate Dictionary 222-223 (1983).           Relying on its
    preferred definition, IEU asserts that “certainty,” as used in the statute, “denotes
    8
    January Term, 2014
    that the retail electric service is made probable of occurrence, dependable, or
    reliable.” Based on this definition, IEU asserts that AEP had the burden of
    showing that the carrying costs were “necessary to make it probable that
    customers would receive retail electric service.” (Emphasis added.) Although it
    is not entirely clear, IEU appears to argue that AEP bears the burden of justifying
    the carrying charges, which required it to demonstrate that the provision of retail
    electric service would become less probable if the carrying costs were excluded
    from the ESP, i.e., that carrying costs are necessary. IEU has not demonstrated,
    however, that R.C. 4928.143(B)(2)(d) contains a necessity requirement.
    {¶ 25} First, contrary to IEU’s representations, the Webster’s definition
    used by IEU does not define “certainty” in terms of “probability of occurrence.”
    {¶ 26} Second, and most importantly, the statute does not expressly
    require a showing of necessity. When interpreting a statute, a court must first
    examine the plain language of the statute to determine legislative intent.
    Cleveland Mobile Radio Sales, Inc. v. Verizon Wireless, 
    113 Ohio St. 3d 394
    ,
    2007-Ohio-2203, 
    865 N.E.2d 1275
    , ¶ 12. The court must give effect to the words
    used, making neither additions nor deletions from words chosen by the General
    Assembly. 
    Id. See also
    Columbia Gas Transm. Corp. v. Levin, 
    117 Ohio St. 3d 122
    , 2008-Ohio-511, 
    882 N.E.2d 400
    , ¶ 19. Certainly, had the General Assembly
    intended to require that electric-distribution utilities prove that carrying costs were
    “necessary” before they could be recovered, it would have chosen words to that
    effect.
    {¶ 27} Third, IEU’s argument otherwise finds no support in the statutory
    language. Although R.C. 4928.143(B)(2)(d) does not expressly require a showing
    of necessity, it does expressly impose a standard for recovery.           The statute
    authorizes cost recovery through such “[t]erms, conditions, or charges * * * as
    would have the effect of stabilizing or providing certainty regarding retail electric
    service.” (Emphasis added.) The critical problem for IEU is that it attempts to
    9
    SUPREME COURT OF OHIO
    prove its theory solely through the meaning of a single word in the statute—the
    word “certainty”—to the exclusion of all others. But the question is what R.C.
    4928.143(B)(2)(d) means when read as a whole, and IEU never explains how the
    statute as a whole supports its position.
    {¶ 28} In the context of IEU’s argument, the word “necessary” denotes
    something that is essential, indispensable, or absolutely required. See Webster’s
    Third New International Dictionary 1510-1511 (1986). Yet IEU never explains
    how the phrase “as would have the effect of stabilizing or providing certainty
    regarding retail electric service” imposes a necessity requirement. Indeed, it is
    anything but self-evident that this phrase requires the utility to show that carrying
    costs are necessary (absolutely required or indispensable) before they may be
    recovered. That is, nothing supports IEU’s assertion that the utility must prove
    that the provision of retail electric service would be less probable (or certain) in
    order to recover costs under the statute.
    {¶ 29} In the end, the commission’s finding that R.C. 4928.143(B)(2)(d)
    does not require a showing of necessity is entitled to deference as an
    interpretation of a rate-related statutory provision if it is reasonable. See In re
    Application of Columbus S. Power Co., 
    134 Ohio St. 3d 392
    , 2012-Ohio-5690,
    
    983 N.E.2d 276
    , ¶ 36-38. We find that it was. Therefore, we reject IEU’s
    argument.
    b.     The record supported authorization of the carrying charges
    under the requirements of R.C. 4928.143(B)(2)(d)
    {¶ 30} IEU also contends in proposition of law No. I that the evidence
    before the commission did not support the legitimacy of the carrying costs under
    R.C. 4928.143(B)(2)(d). After review, we hold that IEU’s evidentiary claim lacks
    merit.
    {¶ 31} The commission found that the record supported the authorization
    of the carrying costs under R.C. 4928.143(B)(2)(d) as having the effect of
    10
    January Term, 2014
    providing certainty to both AEP and its customers regarding retail electric service,
    specifically generation service. Citing the testimony of AEP witness Nelson, the
    commission found that the environmental-investment carrying costs allowed AEP
    to continue to provide low-cost generation power, which had the effect of
    lowering the price of retail electric service. Nelson did indeed testify to this. He
    testified that the environmental-investment carrying costs were necessary to allow
    AEP to keep its coal-fired generation plants running. Nelson explained that AEP
    had made significant capital investments in environmental improvements to its
    generating plants and that capital expenditures are typically long-lived assets that
    are recovered over the life of the asset. According to Nelson, the inclusion of
    carrying costs in the ESP compensated the company for the investment in its
    generating plants. He also testified that retail customers benefitted from the low-
    cost power generated from these plants because AEP passed those lower costs
    through to its customers.
    {¶ 32} IEU, however, faults the commission for relying on Nelson’s
    testimony, asserting that Nelson did not address the relevant question of whether
    the carrying charges would have the effect of making retail electric service more
    certain. According to IEU, “the availability of lower cost power does not support
    the finding” that the environmental investments (which gave rise to the carrying
    costs) “made the availability of the power more ‘certain.’ ”              But R.C.
    4928.143(B)(2)(d) does not require a showing that the investment underlying the
    carrying costs makes “the availability of the power more certain.” As already
    discussed, the statute requires only a showing that “[t]erms, conditions, or charges
    * * * have the effect of stabilizing or providing certainty regarding retail electric
    service.” Nelson testified that the environmental-investment carrying charges
    were important to AEP’s ability to provide generation power at a cost that was
    below the market rate for purchased power at that time, which in turn had the
    effect of lowering or stabilizing the price of retail electric service. Generation
    11
    SUPREME COURT OF OHIO
    falls within the definition of “retail electric service.” See R.C. 4928.01(A)(27)
    (defining “retail electric service” as “any service involved in supplying or
    arranging for the supply of electricity to ultimate consumers in this state, from the
    point of generation to the point of consumption”). Thus, Nelson’s testimony
    explicitly confirms what the commission found: that the carrying charges had the
    effect of providing certainty regarding retail electric service, specifically by
    providing reasonably priced electric-generation service.
    {¶ 33} As a final matter, IEU contends that the commission ignored
    evidence that contradicted its finding that customers benefitted from the lower-
    cost power generated from AEP’s coal-fired plants. IEU refers here to testimony
    from its executive director, Kevin M. Murray, describing how regional
    transmission organization PJM Interconnection1 dispatches power to meet
    demand. IEU states that PJM—rather than AEP—is charged with dispatching
    generation power to meet the load of AEP’s customers in AEP’s service territory.
    IEU’s point seems to be that AEP’s customers do not benefit from the lower-cost
    power because AEP does not provide power generated from its own plants
    directly to its own customers.
    {¶ 34} The commission, however, did not ignore Murray’s testimony; it
    deemed his testimony irrelevant. According to the commission, the manner in
    which PJM dispatches power is not relevant, because AEP generally uses its own
    generating units to serve its customers and passes the benefit of the lower costs of
    power to AEP customers through reductions in the fuel-adjustment clause. IEU’s
    claim that Murray’s testimony on this subject was “unrefuted” is unfounded. The
    commission did cite other testimony as a basis to reject Murray’s testimony.
    1. PJM is a multiutility regional transmission organization designated by the Federal Energy
    Regulatory Commission to coordinate the movement of wholesale electricity in all or part of 13
    states—including Ohio—and the District of Columbia. See generally Ohio Consumers’ Counsel
    v. Pub. Util. Comm., 
    111 Ohio St. 3d 384
    , 2006-Ohio-5853, 
    856 N.E.2d 940
    , ¶ 5-6.
    12
    January Term, 2014
    {¶ 35} In the end, IEU asks the court to reweigh the evidence. But that is
    not our function on appeal. See, e.g., Elyria Foundry Co. v. Pub. Util. Comm.,
    
    114 Ohio St. 3d 305
    , 2007-Ohio-4164, 
    871 N.E.2d 1176
    , ¶ 39.                              As the
    commission’s orders were amply supported by the record, we reject IEU’s
    evidentiary claims.
    2.       R.C. 4928.143(B)(2)(d) does not require an economic basis for
    recovery
    {¶ 36} In proposition of law No. II, IEU asserts that to recover
    environmental-investment carrying costs under R.C. 4928.143(B)(2)(d), AEP
    must first show that its other revenues were insufficient to compensate it for
    providing generation service. Conceding that R.C. 4928.143(B)(2)(d) does not
    expressly require an economic justification as a prerequisite for authorizing cost
    recovery, IEU nevertheless avers that when the commission authorized the
    recovery of carrying costs on remand, it failed to abide by its “economic need”
    policy established in the ESP Order.
    {¶ 37} IEU’s position is premised on the part of the ESP Order that
    addressed two plans proposed by AEP to improve its distribution system. AEP
    had sought approval and cost recovery for a series of plans designed to modernize
    and improve its vegetation management, underground-cable maintenance,
    distribution automation,2 and overhead-equipment inspection under R.C.
    4928.143(B)(2)(h), which allows an ESP to include provisions regarding the
    utility’s distribution service. See ESP Order at 30-34.
    {¶ 38} The commission found, consistent with its prior decisions, that a
    distribution rider established pursuant to R.C. 4928.143(B)(2)(h) should be based
    on the electric utility’s prudently incurred costs. ESP Order at 34. But contrary
    2. Distribution automation is an advanced technology that improves service reliability by quickly
    identifying and isolating faulty distribution-line sections and remotely restoring service
    interruptions. See generally http://www.eeweb.com/blog/nicholas_abisamra/distribution-systems-
    automation-optimization-part-1 (accessed Feb. 7, 2014).
    13
    SUPREME COURT OF OHIO
    to IEU’s claim, nothing suggests that the commission intended this policy to also
    apply to R.C. 4928.143(B)(2)(d). IEU points to no language in the ESP Order
    that this policy extends beyond the provisions for distribution-cost recovery in
    R.C.   4928.143(B)(2)(h).         The    commission     did    not   mention     R.C.
    4928.143(B)(2)(d), and we decline IEU’s invitation to read an economic-need
    policy into the language of that statute. Therefore, IEU’s second proposition of
    law is denied.
    3.        IEU’s claim regarding R.C. 4928.143(B)(1) is moot
    {¶ 39} In proposition of law No. III, IEU maintains that the commission
    exceeded the scope of this court’s remand instructions when it relied on R.C.
    4928.143(B)(1) as “an alternative theory” to justify recovery of the carrying costs.
    We find it unnecessary to determine whether the commission erroneously relied
    on R.C. 4928.143(B)(1), because the commission was clearly authorized under
    R.C. 4928.143(B)(2)(d) to approve the carrying costs. Accordingly, we dismiss
    IEU’s third proposition of law as moot. See Armco, Inc. v. Pub. Util. Comm., 
    69 Ohio St. 2d 401
    , 406, 
    433 N.E.2d 923
    (1982) (this court does not indulge itself in
    advisory opinions).
    B.     IEU has waived its challenge to the collection of carrying costs during
    the remand proceedings
    {¶ 40} In proposition of law No. IV, IEU challenges the commission’s
    decision to allow AEP to recover carrying costs during the remand proceedings.
    The commission had issued an order on May 25, 2011, allowing AEP to continue
    to collect these charges during the remand proceedings. The order made the
    collection of the charges subject to refund in the event that the commission found
    that they were not authorized by one of the categories of R.C. 4928.143(B)(2).
    This meant, according to IEU, that the commission allowed recovery of carrying
    costs during the remand period, i.e., after this court struck down the basis for their
    14
    January Term, 2014
    recovery and before the commission authorized recovery on an alternate basis.
    Thus, recovery of those costs during the remand period was unauthorized by law.
    {¶ 41} IEU failed to preserve this issue by not challenging the
    commission’s May 25, 2011 order until November 2011, after the charges subject
    to refund had already been collected. By waiting six months to challenge the
    order, IEU deprived the commission of an opportunity to cure any error when it
    reasonably could have. The issue is therefore waived and will not be considered.
    See, e.g., Parma v. Pub. Util. Comm., 
    86 Ohio St. 3d 144
    , 148, 
    712 N.E.2d 724
    (1999) (“By failing to raise an objection until the filing of an application for
    rehearing, Parma deprived the commission of an opportunity to redress any injury
    or prejudice that may have occurred”).
    C.      The appellants have failed to show error in the orders denying the
    recovery of previously collected POLR charges
    {¶ 42} In its first and only proposition of law, OCC argues that the
    commission erred when it allowed AEP to retain the “unlawful” POLR charges
    that AEP collected from customers during the term of the ESP. In the ESP Order,
    the commission authorized a phase-in of AEP’s rates during the ESP period by
    allowing AEP to defer a portion of its annual incremental fuel costs for recovery
    after the ESP expired. OCC argues that the commission erred when it refused to
    reduce the deferred-fuel-costs balance by an amount equal to the “unjustified”
    POLR charge. Likewise, IEU argues in proposition of law Nos. V through VII
    that the commission was required to reduce the deferred-fuel-costs balance in an
    amount equal to the unauthorized POLR charge.3
    3. IEU also sought to reduce the deferred fuel costs by the amount of the environmental-
    investment carrying charges collected by AEP through May 2011, on the theory that those charges
    were unlawfully collected. See In re Application of Columbus S. Power Co., 
    128 Ohio St. 3d 512
    ,
    2011-Ohio-1788, 
    947 N.E.2d 655
    , ¶ 31-35. We have already held that AEP’s recovery of carrying
    charges was authorized under R.C. 4928.143(B)(2)(d), rendering this claim moot.
    15
    SUPREME COURT OF OHIO
    {¶ 43} To understand appellants’ arguments requires a review of the
    commission’s approval of AEP’s incurred fuel costs and deferred fuel costs in the
    ESP Order. Therefore, the following background is provided to place this issue
    in proper context.
    1.      The commission’s approval of the Fuel Adjustment Clause and
    deferral of fuel costs
    {¶ 44} ESPs may provide for “[a]utomatic recovery” of “the cost of fuel
    used to generate the electricity supplied under the [standard service] offer,”
    “provided the cost is prudently incurred.” R.C. 4928.143(B)(2)(a). The Fuel
    Adjustment Clause (“FAC”) is a mechanism that provides for a separate charge
    from the base rate that will automatically adjust as the cost of fuel fluctuates. If
    fuel costs rise, the base rate will stay the same, but the FAC will rise
    automatically without a new rate case. ESP Order at 14-15, 18-19.
    {¶ 45} It is important to remember that no matter how the baseline was
    calculated, only actual fuel costs will be recovered. See In re Application of
    Columbus S. Power Co., 
    128 Ohio St. 3d 512
    , 2011-Ohio-1788, 
    947 N.E.2d 655
    ,
    ¶ 66. The FAC mechanism includes quarterly adjustments to reconcile actual fuel
    costs incurred, which establishes the new charge for the following quarter. The
    FAC mechanism also requires an annual prudency and accounting review. These
    are designed to control for any over- or underrecoveries that may occur within a
    particular quarter. ESP Order at 14-15.
    {¶ 46} In the ESP Order, the commission established caps on how much
    AEP could increase its rates each plan-year to ensure rate stability and to mitigate
    the impact on customers. ESP Order at 22. R.C. 4928.144 authorizes “any just
    and reasonable phase-in of any electric distribution utility rate * * * as the
    commission considers necessary to ensure rate or price stability for consumers.”
    Under the rate caps, AEP could increase its bills only by a set percentage each
    year. During the term of the ESP, AEP deferred for future collection a portion of
    16
    January Term, 2014
    the annual incremental FAC costs (i.e., fuel costs) that exceeded the rate caps. In
    short, amounts earned during each year of the ESP but not collected would be
    placed into a “deferral” account and, as required by statute, accrue “carrying
    charges,” a type of financing charge added to them. See R.C. 4928.144; ESP
    Order at 22.
    2.      The appellants’ proposed remedy violates the rule against
    retroactive ratemaking
    {¶ 47} On appeal, OCC and IEU challenge the commission’s decision to
    refuse to adjust the FAC deferral balance. OCC and IEU seek a reduction in the
    FAC deferral in the amount of $368 million, the amount of POLR costs collected
    by AEP from April 2009 through May 2011. OCC and IEU both characterize
    their proposed adjustment of the FAC deferral balance as a prospective offset of
    revenues deferred for future collection.4
    {¶ 48} OCC and IEU effectively ask the court to direct the commission to
    order a refund of the POLR revenues that AEP had already collected from
    customers during the ESP term—specifically from April 2009 through May 2011.
    Their theory is that the charges were not lawfully collected because this court
    rejected the POLR charge in the first ESP appeal, as did the commission on
    remand. We hold, however, that the law does not require recovery of the POLR
    charges. Granting appellants’ request would constitute retroactive ratemaking.
    a.      R.C. Title 49 forbids retroactive ratemaking
    {¶ 49} Seeking to recover excessive rates charged during the appeal of a
    commission order is exactly the action this court found contrary to law in Keco
    Industries, 
    166 Ohio St. 254
    , 
    141 N.E.2d 465
    , paragraph two of the syllabus (R.C.
    Title 49 “affords no right of action for restitution of the increase in charges
    4. The commission has approved a mechanism for AEP to collect the deferred fuel costs (the
    deferred FAC balance) with carrying charges, so the revenues at issue are currently being
    collected. See In re Application of Columbus S. Power Co. for Approval of Mechanism to
    Recover Deferred Fuel Costs, Pub. Util. Comm. No. 11-4920-EL-RDR (Aug. 1, 2012).
    17
    SUPREME COURT OF OHIO
    collected during the pendency of the appeal”). Likewise, in Lucas Cty. Commrs.
    v. Pub. Util. Comm., 
    80 Ohio St. 3d 344
    , 348, 
    686 N.E.2d 501
    (1997), the court
    ruled that “utility ratemaking * * * is prospective only” and that R.C. Title 49
    “prohibit[s] customers from obtaining refunds of excessive rates that may be
    reversed on appeal.” Moreover, the court has consistently applied Keco and
    refused to grant refunds in appeals from commission orders. Ohio Consumers'
    Counsel v. Pub. Util. Comm., 
    121 Ohio St. 3d 362
    , 2009-Ohio-604, 
    904 N.E.2d 853
    , ¶ 21, citing Keco (“any refund order would be contrary to our precedent
    declining to engage in retroactive ratemaking”); Green Cove Resort I Owners’
    Assn. v. Pub. Util. Comm., 
    103 Ohio St. 3d 125
    , 2004-Ohio-4774, 
    814 N.E.2d 829
    ,
    ¶ 27 (“Neither the commission nor this court can order a refund of previously
    approved rates, * * * based on the doctrine set forth in Keco * * *”). These cases
    teach that present rates may not make up for excessive rate charges due to
    regulatory delay, which is exactly what OCC and IEU are seeking here.
    b.      Appellants’ theory that the POLR charge was unlawfully
    collected is wrong
    {¶ 50} As noted, appellants seek to recover charges that were already
    collected in rates on the theory that the charges were not lawful based on this
    court’s rejection of the POLR charge in the first ESP appeal and on the
    commission’s similar rejection of the POLR charge on remand.                  More
    specifically, OCC and IEU argue that the phase-in of rates in the ESP was not
    “just and reasonable,” as required by R.C. 4928.144, because the deferred FAC
    balance was calculated in part on the unlawful POLR revenues collected by AEP.
    See R.C. 4928.144 (authorizing the commission to order “any just and reasonable
    phase-in of any electric distribution utility rate * * * as the commission considers
    necessary to ensure rate or price stability for consumers”). And the remedy,
    according to appellants, is to deduct the unlawful POLR revenues from the
    deferred FAC balance that would otherwise be charged to customers.
    18
    January Term, 2014
    {¶ 51} There is no basis, however, for appellants to claim that the POLR
    charges that were collected from April 2009 to May 2011 were “unlawful.” Keco
    holds that rates set by the commission are lawful until such time as this court later
    finds that the commission erred in setting that particular rate. 
    Keco, 166 Ohio St. at 259
    , 
    141 N.E.2d 465
    . See also Lucas Cty. Commrs. v. Pub. Util. 
    Comm., 80 Ohio St. 3d at 347
    , 
    686 N.E.2d 501
    (“while a rate is in effect, a public utility must
    charge its consumers in accordance with the commission-approved rate
    schedule”). Moreover, a remand order of this court does not automatically render
    the existing rates unlawful, as “the rate schedule filed with the commission
    remains in effect until the commission executes this court’s mandate by an
    appropriate order.” Cleveland Elec. Illum. Co. v. Pub. Util. Comm., 46 Ohio
    St.2d 105, 
    346 N.E.2d 778
    (1976), paragraph two of the syllabus (holding that a
    decision of this court to reverse and remand an order of the commission “does not
    reinstate the rates in effect before the commission’s order or replace that rate
    schedule as a matter of law, but is a mandate to the commission to issue a new
    order”).
    {¶ 52} We reversed the POLR charge on April 19, 2011.                  In re
    Application of Columbus S. Power, 
    128 Ohio St. 3d 512
    , 2011-Ohio-1788, 
    947 N.E.2d 655
    . On remand, the commission ordered that POLR charges not yet
    collected would be subject to refund as of the first billing cycle of June 2011.
    Remand Order at 39. When the commission issued its remand order, it directed
    AEP to refund the POLR charges collected during the remand proceedings. 
    Id. at 34.
    Thus, the deferred FAC balance—which was calculated during the ESP term
    (2009-2011)—was not derived from “unlawful” POLR charges, as the appellants
    contend.
    19
    SUPREME COURT OF OHIO
    c.     The existence of the FAC deferral balance is of no avail to
    appellants in this case
    {¶ 53} Appellants contend that the existence of the deferred FAC balance
    creates a mechanism that allows for prospective rate adjustments to fully remedy
    the POLR overcharges, without running afoul of the prohibition against
    retroactive ratemaking. We disagree.
    {¶ 54} The fact that the deferred fuel costs may provide a mechanism to
    adjust rates prospectively does not alter the nature of appellants’ requested
    remedy. The appellants are seeking to recover—through an adjustment to current
    rates—POLR charges that already have been collected from customers and later
    were found to be unjustified. The rule against retroactive ratemaking, however, is
    clear: present rates may not make up for revenues lost due to regulatory delay. In
    re Application of Columbus S. Power Co. at ¶ 10-11.
    d.     The court lacks jurisdiction over the appellants’ ratemaking
    and accounting arguments
    {¶ 55} OCC claims that any adjustment to the deferred fuel costs does not
    result in retroactive ratemaking because the commission was not engaged in
    ratemaking when it established the FAC mechanism and FAC deferral balance. In
    a similar vein, OCC and IEU maintain that the commission was not engaged in
    ratemaking because the FAC deferral component was only an accounting
    mechanism. The appellants have forfeited these claims by failing to present them
    to the commission on rehearing. That failure jurisdictionally bars the court from
    considering them. See R.C. 4903.10; Consumers’ Counsel v. Pub. Util. Comm.,
    
    70 Ohio St. 3d 244
    , 247, 
    638 N.E.2d 550
    (1994) (citing cases). See also Discount
    Cellular, Inc. v. Pub. Util. Comm., 
    112 Ohio St. 3d 360
    , 2007-Ohio-53, 
    859 N.E.2d 957
    , ¶ 59 (“when an appellant's grounds for rehearing fail to specifically
    allege in what respect the PUCO's order was unreasonable or unlawful, the
    requirements of R.C. 4903.10 have not been met”).
    20
    January Term, 2014
    e.       The appellants failed to avail themselves of the only remedy
    available to them: a stay under R.C. 4903.16
    {¶ 56} AEP collected $368 million in POLR charges during the ESP,
    without any evidence that would justify the cost recovery. But under Keco’s no-
    refund rule, AEP is permitted to keep it, resulting in a windfall for AEP. While
    we recognize that this particular outcome is unfair, as we noted in Columbus S.
    Power, any unfairness must be viewed in the context of the larger legislative
    scheme:
    As Keco and other cases have noted, the statutes protect
    against unlawfully high rates by allowing stays. R.C. 4903.16
    authorizes the court to stay execution of commission orders. * * *
    This section makes “clear that the General Assembly intended that
    a public utility shall collect the rates set by the commission’s order,
    giving, however, to any person who feels aggrieved by such order
    a right to secure a stay of the collection of the new rates after
    posting a bond.” 
    Keco, 166 Ohio St. at 257
    , 2 O.O.2d 85, 
    141 N.E.2d 465
    . The stay remedy “completely abrogated” the form of
    refund (a restitution order) sought in that case. 
    Id. at 259.
    Columbus S. Power, 
    128 Ohio St. 3d 512
    , 2011-Ohio-1788, 
    947 N.E.2d 655
    , ¶ 17.
    {¶ 57} Critical for both OCC and IEU is that they failed to obtain such a
    stay from this court in the first ESP appeal, at a time when the POLR charges
    were being collected.5 OCC and IEU do not address R.C. 4903.16, let alone offer
    an argument against its application.
    5. Before filing the instant appeal, OCC attempted to stay the collection of the ESP rates, filing an
    action in prohibition, an action in procedendo, a premature appeal, and a motion to suspend the
    ESP order. The difficulty for OCC is that it failed to seek a bond, as required by R.C. 4903.16.
    21
    SUPREME COURT OF OHIO
    D.       The rule against retroactive ratemaking bars adjustments in this case
    to delta revenues, the Universal Service Fund rates, and the
    significantly-excessive-earnings test
    {¶ 58} In proposition of law No. VIII, IEU claims that in addition to
    reducing the deferred-fuel-costs balance by the POLR, the commission was
    required to make downward adjustments in other areas due to AEP’s unlawful
    recovery of POLR revenues. IEU identifies delta revenues, Universal Service
    Fund (“USF”) amounts, and the significantly-excessive-earnings test (“SEET”),
    as areas that it believes warrant additional adjustments.6
    {¶ 59} IEU’s theory is that the unlawful POLR charges are “embedded” in
    AEP’s collection of delta revenues, USF charges, and annual ESP earnings,
    causing these revenues to be overstated. We have already rejected IEU’s theory
    that the POLR charges were unlawful. Therefore, we dismiss IEU’s proposition
    of law No. VIII.
    See In re Application of Columbus S. Power Co., 
    128 Ohio St. 3d 512
    , 2011-Ohio-1788, 
    947 N.E.2d 655
    , ¶ 18-19.
    6. Delta revenues are derived from discounted rate arrangements under R.C. 4905.31. Delta
    revenue refers to the amount of the discount: it is the difference between what the utility would
    have collected under its tariffs and what it actually collected under the discounted rate. See Ohio
    Adm.Code 4901:1-38-01(C). Delta revenue may be recovered (in whole or in part) from all other
    customers. See R.C. 4905.31(E) (allowing utility to recover costs, including “revenue foregone,”
    as a result of a discounted rate arrangement). Somewhat similarly, the USF provides bill-payment
    assistance to low-income residential consumers, and other consumers pay USF charges to make
    the utility whole. R.C. 4928.51; Constellation NewEnergy, Inc. v. Pub. Util. Comm., 104 Ohio
    St.3d 530, 2004-Ohio-6767, 
    820 N.E.2d 885
    , ¶ 28, fn. 4.
    As to the SEET, under R.C. 4928.143(F), electric distribution utilities are required to
    undergo an annual earnings review. If their ESP resulted in “significantly excessive earnings”
    compared to similar companies, the utility must return the excess to customers. See, e.g., In re
    Application of Columbus S. Power Co., 
    134 Ohio St. 3d 392
    , 2012-Ohio-5690, 
    983 N.E.2d 276
    (the court’s review of AEP’s SEET for 2009).
    22
    January Term, 2014
    V. CONCLUSION
    {¶ 60} In summary, we hold that OCC and IEU have not carried their
    burden of showing reversible error in the commission’s remand orders. Ohio
    Consumers’ Counsel v. Pub. Util. Comm., 
    125 Ohio St. 3d 57
    , 2010-Ohio-134,
    
    926 N.E.2d 261
    , ¶ 42 and ¶ 73. Therefore, we affirm the commission’s orders.
    Orders affirmed.
    O’CONNOR, C.J., and O’DONNELL, KENNEDY, and FRENCH, JJ., concur.
    PFEIFER and O’NEILL, JJ., dissent.
    ____________________
    PFEIFER, J., dissenting.
    {¶ 61} On remand, the PUCO has determined that AEP did not present
    evidence of its Provider of Last Resort (“POLR”) costs. The PUCO stated that
    the $368 million in POLR revenues that AEP had collected from customers was
    “unjustified.”   Nevertheless, the PUCO asserted that a refund under the
    circumstances would be tantamount to retroactive ratemaking, something it is not
    authorized to engage in. See Lucas Cty. Commrs. v. Pub. Util. Comm., 80 Ohio
    St.3d 344, 348, 
    686 N.E.2d 501
    (1997).
    {¶ 62} It is unconscionable that a public utility should be able to retain
    $368 million that it collected from consumers based on assumptions that are
    unjustified. The problem stems from this court’s 1957 decision that determined
    that “[w]here the charges collected by a public utility are based upon rates which
    have been established by an order of the Public Utilities Commission of Ohio, the
    fact that such order is subsequently found to be unreasonable or unlawful on
    appeal to the Supreme Court of Ohio, in the absence of a statute providing
    therefor, affords no right of action for restitution of the increase in charges
    collected during the pendency of the appeal.” Keco Industries, Inc. v. Cincinnati
    & Suburban Bell Tel. Co., 
    166 Ohio St. 254
    , 
    141 N.E.2d 465
    (1957), paragraph
    two of the syllabus. Clearly the time has come to overturn this case.
    23
    SUPREME COURT OF OHIO
    {¶ 63} R.C. 4905.32, the statute on which the Keco decision is based, does
    not state that there is “no right of action for restitution of the increase in charges
    collected during the pendency of the appeal.” In my view, that part of the opinion
    is mere dicta, foolhardy, erroneous, and not binding on this court. Indeed, it
    boggles the mind that this court would ever countenance such a proposition: that
    a public utility should be allowed to fatten itself on the backs of Ohio residents by
    collecting unjustified charges.
    {¶ 64} In this case, we are talking about $368 million in unjustified
    charges that, instead of redounding to the people who paid them, reside in the
    coffers of a public utility without the justification of actual costs. This illusory
    charge will become pure unwarranted profit based on this court’s decision today.
    And it does not have to be this way.
    {¶ 65} Keco should be overturned. Charges that are approved by the
    PUCO but that do not withstand challenge in this court ought to be subject to
    restitution.
    {¶ 66} A public utility ought not to receive unjust enrichment based on
    charges that in the context of this case as determined by the PUCO, clearly should
    not have been approved. R.C. 4905.32 states that utilities cannot refund a rate
    that has been charged pursuant to the rate schedule filed with the PUCO. It does
    not say that this court cannot compel a utility to provide restitution for charges
    that it has unjustifiably collected. A practical way to unwind this case so that it
    does not shock the utility and its investors is to set off the unjustifiable collections
    against future charges. The Ohio Consumers’ Counsel has suggested that a direct
    setoff against the deferred fuel-cost rider is an appropriate way for Columbus
    Southern to provide restitution.
    {¶ 67} Allowing AEP to retain the $368 million that it collected based on
    charges that were not justified is unconscionable. Doing so because of a 50-year-
    24
    January Term, 2014
    old case that is not supported by the statute on which it is based is ridiculous. The
    ratepayers of Ohio deserve better. I dissent.
    O’NEILL, J., concurs in the foregoing opinion.
    ____________________
    Bruce J. Weston, Consumers’ Counsel, and Maureen R. Grady and Terry
    L. Etter, Assistant Consumers’ Counsel, for appellant Ohio Consumers’ Counsel.
    McNees, Wallace & Nurick, L.L.C., Samuel C. Randazzo, Frank P. Darr,
    and Joseph E. Oliker, for appellant Industrial Energy Users-Ohio.
    Michael DeWine, Attorney General, and William L. Wright, Werner L.
    Margard III, and John H. Jones, Assistant Attorneys General, for appellee Public
    Utilities Commission of Ohio.
    Steven T. Nourse and Matthew J. Satterwhite; and Porter, Wright, Morris
    & Arthur, Kathleen M. Trafford, and Daniel R. Conway, for intervening appellee,
    Ohio Power Company.
    _________________________
    25