Piketon v. Boone Coleman Constr., Inc. (Slip Opinion) , 145 Ohio St. 3d 450 ( 2016 )


Menu:
  • [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as
    Piketon v. Boone Coleman Constr., Inc., Slip Opinion No. 2016-Ohio-628.]
    NOTICE
    This slip opinion is subject to formal revision before it is published in an
    advance sheet of the Ohio Official Reports. Readers are requested to
    promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65
    South Front Street, Columbus, Ohio 43215, of any typographical or other
    formal errors in the opinion, in order that corrections may be made before
    the opinion is published.
    SLIP OPINION NO. 2016-OHIO-628
    BOONE COLEMAN CONSTRUCTION, INC., APPELLEE, v. THE VILLAGE OF
    PIKETON, APPELLANT.
    [Until this opinion appears in the Ohio Official Reports advance sheets, it
    may be cited as Piketon v. Boone Coleman Constr., Inc., Slip Opinion No.
    2016-Ohio-628.]
    Contracts―Public works―Enforceable liquidated-damages clause distinguished
    from     unenforceable        penalty―Samson          Sales     tripartite     test
    applied―Provision for liquidated damages of $700 per day for delay of
    completion upheld―Reasonableness of provision determined by per diem
    amount rather than aggregate amount of damages assessed―If provision
    was reasonable at the time of formation and bears reasonable relation to
    actual damages, provision will be enforced.
    (No. 2014-0978—Submitted June 9, 2015—Decided February 24, 2016.)
    APPEAL from the Court of Appeals for Pike County,
    No. 13CA836, 2014-Ohio-2377.
    _____________________
    SUPREME COURT OF OHIO
    O’CONNOR, C.J.
    {¶ 1} In this appeal arising from a public-road-construction contract, we
    consider our precedent on contractual liquidated-damages provisions.                             We
    expressly extend that precedent to public-works contracts, vacate the judgment of
    the court of appeals, and remand this cause to that court for reconsideration in light
    of our opinion.
    RELEVANT BACKGROUND
    {¶ 2} In 2007, appellant, the village of Piketon, solicited bids for the “Pike
    Hill Roadway and Related Improvements” project. The project included the
    installation of a traffic light at the intersection of U.S. Route 23 and Market Street
    in Piketon and improvements to the roadway.
    {¶ 3} Appellee, Boone Coleman Construction, Inc., submitted the lowest
    bid and was hired for the project. The parties entered into a contract in which
    Piketon agreed to pay Boone Coleman $683,300 to complete the work. The contract
    expressly provided that the time for completing the project was “of the essence”1
    1
    The relevant provisions of the contract stated:
    ARTICLE 4—CONTRACT TIMES
    4.01. Time of the Essence
    A. All time limits for Milestones, if any, Substantial Completion, and
    completion and readiness for final payment as stated in the Contract Documents
    are of the essence of the Contract.
    4.02 Days to Achieve Substantial Completion and Final Payment
    A. The Work will be substantially completed within 120 days after the
    date when the Contract Times commence to run as provided in paragraph 2.03 of
    the General Conditions, and completed and ready for final payment in accordance
    with paragraph 14.07 of the General Conditions within 120 days after the date
    when the Contract Times commence to run.
    4.03 Liquidated Damages
    A. CONTRACTOR and OWNER recognize that time is of the essence
    of this Agreement and that OWNER will suffer financial loss if the Work is not
    completed within the time(s) specified in paragraph 4.02 above, plus any
    extensions thereof allowed in accordance with Article 12 of the General
    Conditions. The parties also recognize the delays, expense, and difficulties
    involved in proving in a legal or arbitration [proceeding] the actual loss suffered
    2
    January Term, 2016
    and that the project had to be substantially completed within 120 days of the date
    of commencement of the project. A liquidated-damages provision made clear that
    Boone Coleman would pay $700 to Piketon for each day after the specified
    completion date that the contract was not substantially completed.
    {¶ 4} The date of commencement of the project was set for July 30, 2007.
    Thus, the contract required that the project be substantially completed 120 days
    later on November 27, 2007. Piketon granted Boone Coleman’s first request for an
    extension, which moved the completion date to May 30, 2008. But when Boone
    Coleman sought another extension, Piketon refused to grant it and notified Boone
    Coleman that it would assess the contractually specified liquidated damages of
    $700 per day if the project was not completed by May 30, 2008. Boone Coleman
    did not do so, and on July 7, 2008, Piketon informed Boone Coleman that it was
    assessing damages of $700 per day, as of May 31, 2008, until the completion of the
    project.
    {¶ 5} Boone Coleman did not complete the project until July 2, 2009―well
    over a year (397 days) after the parties’ extended completion date of May 30, 2008.
    {¶ 6} Boone Coleman brought suit against Piketon in the Pike County
    Common Pleas Court. Among other things, it alleged that Piketon had improperly
    by OWNER if the Work is not completed on time. Accordingly, instead of
    requiring any such proof, OWNER and CONTRACTOR agree that as liquidated
    damages for delay (but not as a penalty), CONTRACTOR shall pay OWNER
    $700.00 for each day that expires after the time specified in paragraph 4.02 for
    Substantial Completion until the Work is substantially complete.
    (Boldface, underlining, and capitalization sic.)
    3
    SUPREME COURT OF OHIO
    failed to pay $147,477 of the contract price for the construction.2                         Piketon
    counterclaimed for liquidated damages.
    {¶ 7} Piketon moved for summary judgment. The trial court granted
    Piketon’s motion and entered judgment in its favor, awarding Piketon $277,900 in
    liquidated damages.
    {¶ 8} Boone Coleman appealed, asserting that the trial court erred in
    awarding Piketon liquidated damages. The appellate court agreed. Citing our
    decision in Samson Sales, Inc. v. Honeywell, Inc., 
    12 Ohio St. 3d 27
    , 
    465 N.E.2d 392
    (1984), it held, “[W]hen we view the contract as a whole in its application, we
    conclude the amount of damages is so manifestly unreasonable and
    disproportionate that it is plainly unrealistic and inequitable.” (Emphasis added.)
    2014-Ohio-2377, 
    13 N.E.3d 1190
    , at ¶ 40. It concluded that because the “resulting
    amount [of liquidated damages] is manifestly inequitable and unrealistic, courts are
    justified in determining the provision to be an unenforceable penalty.” 
    Id. at ¶
    43,
    citing Samson Sales at 28. It reversed that portion of the trial court’s judgment and
    remanded for further proceedings.
    {¶ 9} We granted Piketon’s request for discretionary review and agreed to
    address two related propositions of law:
    2
    In its complaint, Boone Coleman asserted that the liquidated-damages provision was a penalty and
    also argued that it should have been awarded additional compensation based on work it performed
    to correct subsurface road problems and to perform revisions on the retaining wall and traffic signal.
    The trial court denied that relief and the appellate court affirmed, holding that “Boone Coleman did
    not follow the parties’ unambiguous notice provisions to claim additional compensation. And the
    contract explicitly precluded recovery for additional costs related to subsurface conditions
    encountered by Boone Coleman.” 2014-Ohio-2377, ¶ 4. Nevertheless, the dissenting opinion
    asserts, “Boone Coleman already suffered a loss from performing additional work for which it was
    not paid” and seemingly gives credence to Boone Coleman’s claim that Piketon provided inaccurate
    site information. It seems, then, that the dissent’s insistence on adhering to its own conclusion,
    without regard to the facts of this case or the law controlling it, is where “frontier justice” comes
    into play. In any event, Boone Coleman did not seek this court’s review of the holdings that it had
    been paid properly, and it is therefore not discussed further in this opinion.
    4
    January Term, 2016
    When evaluating the enforceability of a liquidated damages
    provision in a construction contract, the court must conduct its
    analysis prospectively, based on the per diem amount of the
    liquidated damages at the time the contract is executed, and not
    retrospectively, based on the total liquidated damages that
    ultimately accrue.
    Liquidated damages are not deemed a penalty simply
    because a project consists of new construction of an improvement
    that did not exist previously and no proof of actual damages is
    required to enforce liquidated damages pursuant to such a contract.
    
    140 Ohio St. 3d 1451
    , 2014-Ohio-4414, 
    17 N.E.3d 598
    .
    ANALYSIS
    Standard of Review for Contractual Liquidated-Damages Provisions
    {¶ 10} We review the interpretation of a contract, a question of law, de
    novo. Arnott v. Arnott, 
    132 Ohio St. 3d 401
    , 2012-Ohio-3208, 
    972 N.E.2d 586
    ,
    ¶ 14. Similarly, the question of whether a contract clause provides for liquidated
    damages or an unenforceable penalty is a question of law that we also review de
    novo. Lake Ridge Academy v. Carney, 
    66 Ohio St. 3d 376
    , 380, 
    613 N.E.2d 183
    (1993).
    Substantive Law on Liquidated Damages
    {¶ 11} Simply stated, liquidated damages are damages that the parties to a
    contract agree upon, or stipulate to, as the actual damages that will result from a
    future breach of the contract. Sheffield-King Milling Co. v. Domestic Science
    Baking Co., 
    95 Ohio St. 180
    , 183, 
    115 N.E. 1014
    (1917).
    {¶ 12} “ ‘The effect of a clause for stipulated damages in a contract is to
    substitute the amount agreed upon as liquidated damages for the actual damages
    resulting from breach of the contract, and thereby prevents [sic] a controversy
    5
    SUPREME COURT OF OHIO
    between the parties as to the amount of damages.’ ” Dave Gustafson & Co., Inc. v.
    South Dakota, 
    83 S.D. 160
    , 164, 
    156 N.W.2d 185
    (1968), quoting 22 American
    Jurisprudence 2d, Damages, Section 235, at 321 (1965). “ ‘If a provision is
    construed to be one for liquidated damages, the sum stipulated forms, in general,
    the measure of damages in case of a breach, and the recovery must be for that
    amount. No larger or smaller sum can be awarded even though the actual loss may
    be greater or less.’ ” 
    Id., quoting Section
    235 at 321. Put another way, “a liquidated
    damages clause in a contract is an advance settlement of the anticipated actual
    damages arising from a future breach.”        Carrothers Constr. Co., L.L.C. v. S.
    Hutchinson, 
    288 Kan. 743
    , 754, 
    207 P.3d 231
    (2009).
    {¶ 13} The common law viewed liquidated-damages provisions “with a
    gimlet eye,” Dist. Cablevision Ltd. Partnership v. Bassin, 
    828 A.2d 714
    , 723
    (D.C.App.2003), but that historical antipathy dissipated as parties to contracts,
    attorneys, and the courts recognized that such provisions serve valuable purposes.
    {¶ 14} “Today the law does not look with disfavor upon ‘liquidated
    damages’ provisions in contracts. When they are fair and reasonable attempts to
    fix just compensation for anticipated loss caused by breach of contract, they are
    enforced.” Priebe & Sons, Inc. v. United States, 
    332 U.S. 407
    , 411, 
    68 S. Ct. 123
    ,
    
    92 L. Ed. 32
    (1947). The modern rule is “to look with candor, if not with favor”
    upon liquidated-damages provisions in contracts when those provisions were
    “deliberately entered into between parties who have equality of opportunity for
    understanding and insisting upon their rights.” Wise v. United States, 
    249 U.S. 361
    ,
    365, 
    39 S. Ct. 303
    , 
    63 L. Ed. 647
    (1919). See also Bassin at 724, quoting Wilmington
    Trust Co. v. Aerovias de Mexico, S.A. de C.V., 
    893 F. Supp. 215
    , 218
    (S.D.N.Y.1995) (“ ‘Relevant to this inquiry is the sophistication of the parties and
    whether both sides were represented by able counsel who negotiated the contract at
    arms length without the ability to overreach the other side’ ”).
    6
    January Term, 2016
    {¶ 15} Part of the appeal of liquidated-damages provisions is that they allow
    the contracting parties to “protect themselves against the difficulty, uncertainty, and
    expenses that necessarily follow judicial proceedings when trying to ascertain
    damages.” Carrothers Constr. 
    Co., 288 Kan. at 754
    , 
    207 P.3d 231
    . This benefit is
    particularly valuable when “actual damages are likely to be difficult to quantify in
    the event that the contract is breached.” 
    Bassin, 828 A.2d at 723
    . Liquidated-
    damages provisions thereby “promot[e] prompt performance of contracts” and
    “adjust[] in advance, and amicably, matters the settlement of which through courts
    would often involve difficulty, uncertainty, delay and expense.” Wise at 366.
    {¶ 16} Ohio has long recognized liquidated-damages provisions as valid
    and enforceable, see Samson 
    Sales, 12 Ohio St. 3d at 28
    , 
    465 N.E.2d 392
    , citing
    Jones v. Stevens, 
    112 Ohio St. 43
    , 
    146 N.E. 894
    (1925); Lange v. Werke, 
    2 Ohio St. 519
    (1853), as long as the provisions are not ones for penalties, Samson Sales, 
    id. And therein
    lies the rub. “The difficult problem, in each case, is to determine
    whether or not the stipulated sum is an unenforceable penalty or an enforceable
    provision for liquidated damages.” Dave Gustafson & 
    Co., 83 S.D. at 165
    , 
    156 N.W.2d 185
    .
    {¶ 17} In addressing whether a contract includes a permissible liquidated-
    damages provision or an unenforceable penalty, one of our appellate courts has
    explained that a “penalty” is
    “a sum inserted in a contract, not as the measure of compensation
    for its breach, but rather as a punishment for default, or by way of
    security for actual damages which may be sustained by reason of
    nonperformance, and it involves the idea of punishment. A penalty
    is an agreement to pay a stipulated sum on breach of contract,
    irrespective of the damage sustained. Its essence is a payment of
    money stipulated as in terrorem of the offending party, while the
    7
    SUPREME COURT OF OHIO
    essence of liquidated damages is a genuine covenanted pre-estimate
    of damages. The amount is fixed and is not subject to change;
    however, if the stipulated sum is deemed to be a penalty, it is not
    enforceable and the nondefaulting party is left to the recovery of
    such actual damages as he can prove.”
    (Emphasis sic.) Piper v. Stewart & Inlow, 5th Dist. Licking No. CA-2530, 
    1978 WL 217430
    , *1 (June 14, 1978), quoting 22 American Jurisprudence 2d, Damages,
    Section 213, at 298 (1965).
    {¶ 18} In Samson Sales, we set forth Ohio’s tripartite test to determine
    whether a contractual provision should be considered a liquidated-damages
    provision or an unenforceable penalty. We held:
    Where the parties have agreed on the amount of damages,
    ascertained by estimation and adjustment, and have expressed this
    agreement in clear and unambiguous terms, the amount so fixed
    should be treated as liquidated damages and not as a penalty, if the
    damages would be (1) uncertain as to amount and difficult of proof,
    and if (2) the contract as a whole is not so manifestly
    unconscionable, unreasonable, and disproportionate in amount as to
    justify the conclusion that it does not express the true intention of
    the parties, and if (3) the contract is consistent with the conclusion
    that it was the intention of the parties that damages in the amount
    stated should follow the breach thereof.
    Samson Sales, 
    12 Ohio St. 3d 27
    , 
    465 N.E.2d 392
    , at syllabus.
    {¶ 19} Valid and enforceable liquidated-damages provisions are those
    intended by the parties to give reasonable compensation for damages, but
    8
    January Term, 2016
    provisions that impose amounts that are “manifestly inequitable and unrealistic”
    are deemed unenforceable penalties. 
    Id. at 28.
    Since Samson Sales, we have
    reiterated its holding once, in Lake Ridge Academy v. Carney, 
    66 Ohio St. 3d 376
    ,
    380, 
    613 N.E.2d 183
    (1993), and have not departed from its teachings. This case
    requires that we consider our precedent in a context we have not previously
    addressed: public-works-construction contracts.
    Liquidated Damages in Public-Works-Construction Contracts
    {¶ 20} The benefits of liquidated-damages provisions in building and
    construction contracts are well documented. R. Harper Heckman & Benjamin R.
    Edwards, Time is Money: Recovery of Liquidated Damages by the Owner, 24
    Constr.Lawyer 28, 29 (Fall 2004). The provisions create firm expectations and
    allow the parties to allocate damages caused by delays in completing construction.
    
    Id. The ability
    to agree about damages is particularly important in public-works-
    construction contracts because “[i]t is uniquely difficult to calculate damages to the
    general public interest caused by a contractor’s breach of its agreement to provide
    public improvements.” Carrothers Constr. 
    Co., 288 Kan. at 756
    , 
    207 P.3d 231
    .
    {¶ 21} In a public-roadway-construction contract, each delay in completing
    the project adds to inconvenience, increased costs, and loss of use of the roadway.
    Dave Gustafson & 
    Co., 83 S.D. at 167
    , 
    156 N.W.2d 185
    . But “ ‘each day’s delay,
    while unquestionably injurious, is injurious frequently in ways that are difficult to
    estimate.’ ” 
    Id., quoting 5
    Williston on Contracts, Section 785, 733 (3d Ed.1961).
    {¶ 22} We recognize that liquidated-damages provisions in public-
    construction projects play an important civic purpose in that they help foster timely
    completion of the project, thereby avoiding the loss of billions of taxpayers’ dollars
    caused by contractors’ delays. See, e.g., Scott M. Tyler, No (Easy) Way Out:
    “Liquidating” Stipulated Damages for Contractor Delay in Public Construction
    Contracts, 44 Duke L.J. 357, 358-359 (1994); Christian, Public Entities in Nevada
    Beware, 12-OCT Nevada Lawyer 16. We are not alone in that recognition. The
    9
    SUPREME COURT OF OHIO
    Supreme Court and many state and federal appellate courts also recognize that
    liquidated-damages provisions in public contracts are particularly valuable given
    the unique difficulty in calculating the damages associated with a public
    contractor’s breach of its promise to timely complete a public-improvement project.
    See, e.g., Priebe & 
    Sons, 332 U.S. at 411
    , 
    68 S. Ct. 123
    , 
    92 L. Ed. 32
    (recognizing
    that liquidated-damages provisions “serve a particularly useful function when
    damages are uncertain in nature or amount or are unmeasurable, as is the case in
    many government contracts”); Hovas Constr., Inc. v. W. Line Consol. School Dist.
    Bd. of Trustees, 
    111 So. 3d 663
    , 666-667 (Miss.App.2013); Carrothers Constr. 
    Co., 288 Kan. at 756
    , 
    207 P.3d 231
    (the unique difficulty of calculating damages when
    a contractor breaches a public-works contract “should be an important
    consideration in such cases and weigh favorably in finding a liquidated damages
    provision to be reasonable”); Fortune Bridge Co. v. Dept. of Transp., 
    242 Ga. 531
    ,
    533-534, 
    250 S.E.2d 401
    (1978) (noting that “damages flowing from the
    contractor’s failure to complete [public] roadway and bridges in a timely fashion
    are, as a practical matter, incapable of proof”); Brooks v. Wichita, 
    114 F. 297
    , 299
    (8th Cir.1902) (recognizing that liquidated-damages provisions are the only way
    for a city to obtain adequate compensation for breach of a public contract; the
    damages sustained by the public in such cases are not capable of “judicial
    ascertainment” because they are “too remote, conjectural, and speculative” to
    prove); Dade Cty. Pub. Health Trust v. Romart Constr., Inc., 
    577 So. 2d 636
    , 638,
    669 (Fla.App.1991) (fact that public entity may have suffered no monetary loss
    from breach does not render liquidated-damages provision unconscionable,
    because public project was intended for public use, not for profit).
    {¶ 23} We agree with those courts that find that “the protection of the public
    interest is a proper consideration in determining [the] validity of a liquidated
    damages provision.” Carrothers Constr. 
    Co., 288 Kan. at 756
    , 
    207 P.3d 231
    . The
    Ohio General Assembly requires that every state-funded public-improvement-
    10
    January Term, 2016
    construction contract include a liquidated-damages provision. R.C. 153.19. Many
    states have similar requirements. Dave Gustafson & 
    Co., 83 S.D. at 166
    , 
    156 N.W.2d 185
    ; Fortune Bridge 
    Co., 242 Ga. at 534
    , 
    250 S.E.2d 401
    ; see also Bale
    Contracting, Inc. v. Westerville, 
    7 Ohio App. 3d 271
    , 272, 
    455 N.E.2d 517
    (10th
    Dist.1982) (recognizing the materiality of a completion date in a public-works-
    construction project and that a bid for such a project is incomplete when it fails to
    specify the time for performance, citing R.C. 153.19).
    {¶ 24} With these principles in mind, we turn to the appellate court’s
    opinion in this case.
    The Appellate Court’s Analysis of the Liquidated-Damages Provision
    {¶ 25} In considering whether the liquidated-damages provision in this case
    constituted an unenforceable penalty, the court of appeals properly applied the first
    and third parts of the test in Samson Sales, 
    12 Ohio St. 3d 27
    , 
    465 N.E.2d 392
    . The
    appellate court recognized that “the damages incurred as a result of a delay [by
    Boone Coleman in completing the project] were uncertain as to amount and
    difficult to prove” and that “the plain and unambiguous language of the liquidated
    damages clause is consistent with the conclusion that the parties intended that
    damages in the amount of $700 per day would follow the contractor’s breach of the
    project completion deadline.” 2014-Ohio-2377, 
    13 N.E.3d 1190
    , ¶ 38 and 39,
    citing Samson Sales. But the appellate court concluded that the provision did not
    pass the second prong of the Samson Sales test. The second prong requires a court
    reviewing a liquidated-damages provision to consider whether “the contract as a
    whole is not so manifestly unconscionable, unreasonable, and disproportionate in
    amount as to justify the conclusion that it does not express the true intention of the
    parties.” Samson Sales, at syllabus.
    {¶ 26} Even though the appellate court had already determined that the
    provision reflected the parties’ intentions, the appellate court focused solely on the
    aggregate amount of the penalty, $277,900, in relation to the total value of the
    11
    SUPREME COURT OF OHIO
    contract, $683,300.     See 2014-Ohio-2377, ¶ 42.      Only after finding that the
    liquidated-damages aggregate award constituted a third of the total contract price
    did the court determine that the application of the provision rendered it an
    unenforceable penalty. 2014-Ohio-2377, ¶ 40. For several reasons, it was error to
    do so.
    {¶ 27} First, the appellate court relied heavily on a decision of one of its
    sister courts, Harmon v. Haehn, 7th Dist. Mahoning No. 10 MA 177, 2011-Ohio-
    6449. But Harmon is wholly distinguishable here.
    {¶ 28} Given “the wide range and variety of contracts, and of their subject-
    matter, it is sometimes difficult to determine whether the terms thus agreed upon in
    advance actually provide for damages or for a penalty.” Sheffield-King Milling 
    Co., 95 Ohio St. at 183
    , 
    115 N.E. 1014
    . See also 
    Lange, 2 Ohio St. at 533
    (noting that
    in evaluating a liquidated-damages provision, “Arbitrary rules can not help us, and
    judicial decisions are of less value than upon most other questions, as each case
    depends so peculiarly on its own circumstances”). Thus, when courts review
    liquidated-damages provisions, they often look to similar provisions in contracts
    that govern similar subject matter. See, e.g., Kurtz v. W. Property, L.L.C., 10th
    Dist. Franklin No. 10AP-1099, 2011-Ohio-6726, ¶ 33 (in case involving delay in
    sale of real estate, cases involving breaches in other contexts are “readily
    distinguishable”).
    {¶ 29} Here, Harmon is of limited value because it arose from a private
    commercial real estate lease rather than a public-works-construction contract.
    2011-Ohio-6449, ¶ 1. That distinction is particularly relevant because the actual
    damages at issue in Harmon were far easier to quantify than those at issue here.
    {¶ 30} Moreover, the Harmon decision involved a liquidated-damages
    provision that contemplated a lump sum. Piketon and Boone Coleman did not
    contract for a lump sum. Rather, the parties contracted for a per diem measure of
    damages which, as Chief Justice Marshall recognized, is more likely to be an
    12
    January Term, 2016
    enforceable liquidated-damages provision than an unenforceable penalty: “[T]he
    agreement to pay a specified sum weekly during the failure of the party to perform
    the work, partakes much more of the character of liquidated damages than the
    reservation of a sum in gross.” Tayloe v. T. & S. Sandiford, 
    20 U.S. 13
    , 18, 
    5 L. Ed. 384
    (1822). In failing to recognize this distinction, the appellate court committed
    its second error.
    {¶ 31} More importantly, the appellate court’s myopic focus on the
    reasonableness of the total amount of liquidated damages in application, rather than
    on the reasonableness of the per diem amount in the contract terms, was not proper.
    The correct analysis looks at whether it was conscionable to assess $700 per day in
    liquidated damages for each day that the contract was not completed rather than
    looking at the aggregate amount of the damages awarded. Accord Carrothers
    Constr. 
    Co., 288 Kan. at 759
    , 
    207 P.3d 231
    .
    {¶ 32} Although per diem amounts vary greatly in the case law, courts have
    upheld liquidated-damages provisions in public-construction contracts with per
    diem amounts similar to those at issue here. See, e.g., Sec. Fence Group, Inc. v.
    Cincinnati, 1st Dist. Hamilton No. C-020827, 2003-Ohio-5263 (enforcing a per
    diem liquidated-damages provision in a public-bridge-replacement project that
    imposed $600 per day); see also Carter Steel & Fabricating Co. v. Ohio Dept. of
    Transp., 102 Ohio Misc.2d 1, 
    721 N.E.2d 1115
    (Ct. of Cl.1999) (impliedly
    recognizing the validity of a liquidated-damages per diem provision in bridge-
    construction project that imposed $600 in liquidated damages per day, but refusing
    to enforce it against subcontractor who had no control over delay); Hovas 
    Constr., 111 So. 3d at 667
    (upholding as reasonable a $500 per diem assessment of liquidated
    damages in public-construction contract); Carrothers Constr. 
    Co., 288 Kan. at 759
    ,
    
    207 P.3d 231
    ($850 per diem assessment of liquidated damages held reasonable in
    public-construction contract). In fact, courts have upheld far greater amounts of
    per diem damages in construction contracts. See, e.g., Dade Cty. Pub. Health Trust,
    13
    SUPREME COURT OF 
    OHIO 577 So. 2d at 638
    (upholding as “perfectly reasonable” a liquidated-damages
    provision imposing $2,500 in damages per day in public-construction project for
    medical facility); Bethlehem Steel Corp. v. Chicago, 
    350 F.2d 649
    (7th Cir.1965)
    (upholding a liquidated-damages provision imposing $1,000 in damages per day in
    public-construction project for elevated highway, even though contractor’s delay
    did not prevent highway from opening to public on date scheduled). See also Unruh
    & Worden, 34 Santa Clara L.Rev. 1, at fn. 1 (in commercial construction contracts,
    “a typical per diem liquidated damages provision might provide that the general
    contractor pay the owner/developer $10,000 for each calendar day” of delay).
    {¶ 33} Moreover, the per diem liquidated damages imposed by the contract
    between Piketon and Boone Coleman reflect the Ohio Department of
    Transportation’s 2013 Construction and Material Specifications.                           Those
    specifications not only require liquidated damages be deducted from any sum owed
    the contractor for each day by which the contractor exceeds the completion date,
    but set out the specific amount of the per diem damages.3             The per diem damages
    are thus consistent with Ohio public policy.
    3
    The Ohio Department of Transportation’s 2013 document entitled “Construction and Material
    Specifications”   is    available at    http://www.dot.state.oh.us/Divisions/ConstructionMgt
    /Specification%20Files/2013%20CMS%2011142012%20FINAL.PDF. Section 108.07 provides:
    Failure to Complete on Time. If the Contractor fails to complete the Work
    by the Completion Date, then the Director, if satisfied that the Contractor is making
    reasonable progress, and deems it in the best interest of the public, may allow the
    Contractor to continue in control of the Work. The Department will pay the Contractor
    for Work performed on the Project less any liquidated damages incurred.
    (Boldface sic.)
    The 2013 schedule of liquidated damages, found in Table 108.07-1, provides that the
    amount of liquidated damages to be deducted for each calendar day of an “overrun in time” varies
    depending on the original amount of the contract. For contracts between 0 and $500,000, the
    amount of per diem liquidated damages is $500; for contracts between $500,000 and $2,000,0000,
    the amount of per diem liquidated damages is $1,000; for contracts between $2,000,0000 and
    $10,000,000, the amount of per diem liquidated damages is $1,500; for contracts between
    14
    January Term, 2016
    {¶ 34} Finally and most importantly, we note that the appellate court stated
    that its conclusion resulted from viewing “the contract as a whole in its
    application.” (Emphasis added.) 2014-Ohio-2377, ¶ 3. The use of the phrase “in
    its application” is not part of our test from Samson Sales. The appellate court’s use
    of this invented perspective resulted in a distorted analysis of our precedent.
    {¶ 35} We reaffirm that Ohio law requires a court, when considering a
    liquidated-damages provision, to “examine it in light of what the parties knew at
    the time the contract was formed.”          Jones, 
    112 Ohio St. 43
    , 
    146 N.E. 894
    , at
    paragraph one of the syllabus; Miller v. Blockberger, 
    111 Ohio St. 798
    , 
    146 N.E. 206
    (1924), paragraph one of the syllabus; Sec. Fence Group, 2003-Ohio-5263,
    ¶11. Accord Priebe & 
    Sons, 332 U.S. at 412
    , 
    68 S. Ct. 123
    , 
    92 L. Ed. 32
    . “If the
    provision was reasonable at the time of formation and it bears a reasonable (not
    necessarily exact) relation to actual damages, the provision will be enforced.”
    (Emphasis added.) Lake Ridge Academy at 382.
    {¶ 36} This prospective or “front end” analysis of a liquidated-damages
    provision focuses on the reasonableness of the clause at the time the contract was
    executed rather than looking at the provision retrospectively, i.e., ascertaining the
    reasonableness of the damages with the benefit of hindsight after a breach. See
    generally Heckman & Edwards, 24 Constr.Law. at 30-31; Hovas 
    Constr., 111 So. 3d at 668-669
    (Maxwell, J., concurring); Carrothers Constr. Co., 
    288 Kan. 743
    ,
    
    207 P.3d 231
    , at paragraph nine of the syllabus. The prospective approach properly
    focuses on whether (1) the parties evaluated, at the time of contract formation, the
    probable loss resulting from delay in completing the construction, (2) the parties
    clearly intended to use liquidated damages in case of a delay because actual
    $10,00,000 and $50,000,000, the per diem amount is $2,600; and for contracts over $50,000,000,
    the per diem amount is $3,200.
    15
    SUPREME COURT OF OHIO
    damages would be difficult to ascertain, and (3) the parties reached an agreement
    as to a per diem amount for delays. Carrothers Constr. Co. at 757. See also Hutton
    Contracting Co., Inc. v. Coffeyville, 
    487 F.3d 772
    , 781 (10th Cir.2007), quoting
    Kelly v. Marx, 
    428 Mass. 877
    , 881, 
    705 N.E.2d 1114
    (1999) (recognizing that
    prospective analysis “ ‘resolve[s] disputes efficiently by making it unnecessary to
    wait until actual damages from a breach are proved’ ” and “ ‘eliminates uncertainty
    and tends to prevent costly future litigation’ ”); William Schwartzkopf & John J.
    McNamara, Calculating Construction Damages, Section 13.02, at 257-258 (2d
    Ed.2015) (“The reasonableness of the forecast or estimate [in a liquidated-damages
    provision] is usually determined in view of the facts known at the time of
    contracting, and not at the time of the breach or delayed completion” [emphasis
    sic]).
    {¶ 37} Here, the appellate court improperly engaged in retrospective
    analysis, i.e., it looked, with hindsight, to the aggregate application of the per diem
    liquidated damages to conclude that the provision was unconscionable. But it did
    not determine that the per diem amount was unconscionable at the time the parties
    entered into the contract. The question whether the liquidated-damages provision
    is conscionable “must be viewed by the court from the standpoint of the parties at
    the time of the contract, and not ex post facto when the litigation is up for trial.
    Contracts are always so construed and a stipulation for liquidated damages is no
    exception.” Jacobs v. Shannon Furniture Co., 
    22 Ohio Cir. Dec. 51
    , 53, 
    1910 WL 1170
    (1910), citing Sun Printing & Pub. Assn. v. Moore, 
    183 U.S. 642
    , 672, 
    22 S. Ct. 240
    ,
    
    46 L. Ed. 366
    (1902), and Knox Rock-Blasting Co. v. Grafton Stone Co., 64 Ohio
    St. 361, 266, 
    60 N.E. 563
    (1901). Moreover, when the appellate court determined
    that the award was an unenforceable penalty because the amount was “so
    unreasonably high and so disproportionate to the consideration paid,” 2014-Ohio-
    2377, ¶ 40, the court failed to fully consider that the amount was large only because
    16
    January Term, 2016
    Boone Coleman failed to complete the project for more than a year after the agreed-
    upon completion date, with full awareness of the consequences.
    {¶ 38} By the appellate court’s reasoning, the same provision might have
    been enforceable if Boone Coleman’s delay had been briefer, e.g., two days, two
    weeks, or even two months, but not so long as to accrue the significant damages
    that arose here. It is a perverse rule of law to hold that a court can relieve a
    breaching party of the consequences it agreed to by refusing to enforce a per diem
    liquidated-damages provision solely because the breach was an egregious one. We
    decline to adopt that rationale and vacate the judgment of the appellate court in this
    cause.
    {¶ 39} We remind our appellate courts that in engaging in prospective
    analysis, the appellate court’s role is not to determine what the parties should have
    contracted for based on the court’s understanding of the damages after the breach.
    Lake Ridge 
    Academy, 66 Ohio St. 3d at 382
    , 
    613 N.E.2d 183
    . This court has made
    clear for over 150 years that judges have no more power to disregard a valid
    liquidated-damages provision than they do to disregard any other contractual
    provision. 
    Lange, 2 Ohio St. at 533
    ; see also Knox Rock-Blasting Co. at 367-368.
    The proper course is to enforce contracts according to their plain meaning and “not
    to undertake to be wiser than the parties.” 
    Jones, 112 Ohio St. at 56
    , 
    146 N.E. 894
    .
    “It is certainly not incumbent on the appellate courts * * * to change the contracts
    of people, after the fact, in the name of public policy.” Court Rooms of Am., Inc.
    v. Diefenbach, 
    425 N.E.2d 122
    , 124 (Ind.1981).
    “The parties themselves best know what their expectations
    are in regard to the advantages of their undertaking and the damages
    attendant on its failure, and when they have mutually agreed on the
    amount of such damages in good faith and without illegality, it is as
    17
    SUPREME COURT OF OHIO
    much the duty of the court to enforce that agreement as it is the other
    provisions of the contract.”
    Sheffield-King Milling 
    Co., 95 Ohio St. at 185
    , 
    115 N.E. 1014
    , quoting Knox Rock-
    Blasting Co. at 368.
    CONCLUSION
    {¶ 40} Benjamin Franklin advised us to remember that “time is money.”
    United States v. One 1971 Corvette Stingray, E.D.Pa. No. 89-5398, 
    1990 WL 4374
    ,
    *1 (Jan. 18, 1990), citing Benjamin Franklin, Advice to a Young Tradesman (1748).
    Boone Coleman would have done well to follow that advice.
    {¶ 41} Boone Coleman entered a contract that required it to perform the
    project within 120 days. It took four times that long to do so. It may not avoid the
    result of the valid liquidated-damages provision it negotiated through able counsel.
    “There is no sound reason why persons competent and free to contract may not
    agree upon this subject [of liquidated damages] as fully as upon any other, or why
    their agreement, when fairly and understandingly entered into with a view to just
    compensation for the anticipated loss, should not be enforced.” 
    Wise, 249 U.S. at 365
    , 
    39 S. Ct. 303
    , 
    63 L. Ed. 647
    .
    {¶ 42} The appellate court erred in its use of a retrospective analysis to find
    that the total amount of damages awarded to Piketon was so unreasonable as to
    constitute a penalty, and in failing to focus on the per diem nature of the liquidated
    damages. Accordingly, we vacate the judgment of the Fourth District Court of
    Appeals and remand the cause to that court to reconsider the enforceability of the
    liquidated-damages provision in light of this opinion.
    Judgment vacated
    and cause remanded.
    O’NEILL, J., concurs.
    18
    January Term, 2016
    O’DONNELL, LANZINGER, KENNEDY, and FRENCH, JJ., concur in judgment
    only.
    PFEIFER, J., dissents.
    _________________
    KENNEDY, J., concurring.
    {¶ 43} I agree with the majority opinion. However, I would exclude the
    first paragraph of the majority’s conclusion.
    {¶ 44} Therefore, I respectfully concur.
    O’DONNELL, J., concurs in the foregoing opinion.
    _________________
    PFEIFER, J., dissenting.
    {¶ 45} We should dismiss this case as having been improvidently accepted
    and allow the court of appeals decision to stand. That court reached a sound and
    proper conclusion that is fair to both parties. Furthermore, no new legal issue is at
    stake.
    {¶ 46} Instead this court has taken a bad situation and made it worse. Boone
    Coleman already suffered a loss from performing additional work for which it was
    not paid. On top of that, this court now determines that Boone Coleman must pay
    a penalty because it didn’t complete the contract on time, never mind that Boone
    Coleman claims that part of the problem was that Piketon provided inaccurate site
    information. This is akin to frontier justice: we do it because we can, not because
    it makes sense.
    {¶ 47} Barring a dismissal, the sensible approach to this case, the approach
    taken by the court of appeals, is to declare the liquidated-damages clause to be
    unreasonable and disproportionate. Equities do matter―even in a contract case.
    Given the circumstances of this case, which include Piketon allegedly providing
    inaccurate site plans to Boone Coleman, the court of appeals got it right. It
    disallowed Boone Coleman’s requests for additional payment because they were
    19
    SUPREME COURT OF OHIO
    not properly submitted and refused to enforce the liquidated-damages clause
    because it was so unreasonable and disproportionate as to amount to a penalty.
    {¶ 48} Because the court is neither dismissing the case nor affirming the
    court of appeals, I dissent.
    _________________
    Stephen C. Rodeheffer and John A. Gambill, for appellee.
    Kegler Brown Hill & Ritter, L.P.A., Eric B. Travers, and Timothy A.
    Kelley, for appellant.
    Bricker & Eckler, L.L.P., Jack R. Rosati Jr., and Adam F. Florey, urging
    reversal for amici curiae, County Commissioners Association of Ohio, Ohio
    Municipal League, Ohio School Boards Association, and Ohio Township
    Association.
    _________________
    20
    

Document Info

Docket Number: 2014-0978

Citation Numbers: 2016 Ohio 628, 145 Ohio St. 3d 450

Judges: O'Connor, C.J.

Filed Date: 2/24/2016

Precedential Status: Precedential

Modified Date: 1/13/2023

Authorities (15)

Hutton Contracting Co. v. City of Coffeyville , 487 F.3d 772 ( 2007 )

Bethlehem Steel Corporation v. City of Chicago , 350 F.2d 649 ( 1965 )

PUBLIC HEALTH TRUST OF DADE CTY. v. Romart Const., Inc. , 577 So. 2d 636 ( 1991 )

Fortune Bridge Co. v. Department of Transportation , 242 Ga. 531 ( 1978 )

District Cablevision Limited Partnership v. Bassin , 828 A.2d 714 ( 2003 )

Court Rooms of America, Inc. v. Diefenbach , 425 N.E.2d 122 ( 1981 )

Carrothers Construction Co. v. City of South Hutchinson , 288 Kan. 743 ( 2009 )

Wise v. United States , 39 S. Ct. 303 ( 1919 )

Bale Contracting, Inc. v. Westerville , 7 Ohio App. 3d 271 ( 1982 )

Miller v. Blockberger , 111 Ohio St. 798 ( 1924 )

Jones v. Stevens , 112 Ohio St. 43 ( 1925 )

Sun Printing and Publishing Assn. v. Moore , 22 S. Ct. 240 ( 1902 )

Tayloe v. T. & S. Sandiford , 5 L. Ed. 384 ( 1822 )

Priebe & Sons, Inc. v. United States , 68 S. Ct. 123 ( 1947 )

Dave Gustafson & Co. v. State , 83 S.D. 160 ( 1968 )

View All Authorities »