Musselshell Ranch Co. v. Seidel-Joukova , 366 Mont. 337 ( 2012 )


Menu:
  •                                                                                                October 9 2012
    DA 12-0151
    IN THE SUPREME COURT OF THE STATE OF MONTANA
    
    2012 MT 222
    MUSSELSHELL RANCH COMPANY, a
    Montana Corporation; MARY T. COOLEY,
    DANIEL COOLEY, BRIAN COOLEY,
    DARREN COOLEY, CALLIE RECH,
    d/b/a/ COOLEY RANCH,
    Plaintiffs and Appellants,
    v.
    NATALIYA SEIDEL-JOUKOVA, a/k/a
    NATALIYA SEIDEL JOUKOVA, and
    JOHN DOES 1-5,
    Defendants and Appellees.
    APPEAL FROM:            District Court of the Fourteenth Judicial District,
    In and For the County of Musselshell, Cause No. DV-09-43
    Honorable Randal I. Spaulding, Presiding Judge
    COUNSEL OF RECORD:
    For Appellants:
    John R. Christensen, Ben T. Sather, Christensen Fulton & Filz, PLLC,
    Billings, Montana
    For Appellee:
    Daniel G. Gillispie, Gillispie Law Office, Billings, Montana
    Submitted on Briefs: August 15, 2012
    Decided: October 9, 2012
    Filed:
    __________________________________________
    Clerk
    Justice Patricia O. Cotter delivered the Opinion of the Court.
    ¶1     This is the second appeal by these parties to this Court. A full factual recitation,
    procedural background and legal analysis is set forth in Musselshell Ranch Co. v.
    Seidel-Joukova, 
    2011 MT 217
    , 
    362 Mont. 1
    , 
    261 P.3d 570
     (Musselshell Ranch I). In this
    appeal, Musselshell Ranch and various individuals appeal the Fourteenth Judicial District
    Court’s denial of their request for attorney fees. We affirm.
    ISSUE
    ¶2     The dispositive issue on appeal is:
    ¶3     Did the District Court err in denying attorney fees to the Ranch?
    FACTUAL AND PROCEDURAL BACKGROUND
    ¶4     As noted above, an extensive factual background for this case is available in
    Musselshell Ranch I; however, for purposes of this Opinion, we provide a brief overview
    of pertinent facts. Plaintiffs/Appellants, i.e., Musselshell Ranch, the Cooleys and Rech
    (collectively the Ranch), own the right to appropriate water from the Musselshell River.
    The Ranch is the successor-in-interest to these rights which have been in place for more
    than 100 years with John Cooley being one of the original owners in 1891. The Ranch’s
    water rights are utilized through an irrigation ditch generally known as the
    Cooley-Goffena Ditch (Cooley ditch). With minor alterations, the Cooley ditch has been
    in its current location consistently and continuously for more than 100 years.
    ¶5     The Cooley ditch is currently accessible by Ranch personnel via two routes—a
    northern route through Joukova’s property entering a west end access gate, and a
    southern route created by the Montana Department of Transportation (MDOT) as part of
    2
    MDOT’s widening of Highway 12 in 2002. MDOT contoured the sides of the Cooley
    ditch and installed a lining and an underground pipeline as well as an east end access gate
    requested by the ditch users.
    ¶6     In 2006, defendant/appellee Nataliya Joukova purchased property through which a
    portion of the Cooley ditch flows. Shortly after taking possession of the property,
    Joukova graveled the two-lane road running along the north bank of the Cooley ditch that
    the Ranch had historically used to access the ditch. She also created an approach from
    the southern end across the pipeline installed by MDOT. She placed a permanent culvert
    in the Ranch’s ditch and then covered it with a “sturdy rock bridge” that allowed her to
    drive over the Cooley ditch to access another section of her property. These, and other
    actions by Joukova, sparked serious disagreements with Ranch personnel and in August
    2009, the Ranch brought suit against Joukova claiming she was interfering with the
    Ranch’s easement rights in violation of §§ 70-17-101(11) and 70-17-112, MCA.
    ¶7     The District Court ruled in favor of Joukova on some issues and in favor of the
    Ranch on others. Specifically, the District Court concluded that the culvert and bridge
    could remain in place despite the Ranch’s demand that it be removed. In response to the
    Ranch’s claim that access to their ditch was blocked by a locked gate put in place by
    Joukova and that Joukova had removed a separate gate at the west end of the property,
    the court ruled that Joukova had to provide the Ranch with access through the locked gate
    and reinstall the removed gate. As a result of these and other rulings, the court concluded
    neither party had “prevailed” as required by § 70-17-112(5), MCA, and declined to award
    attorney fees and costs. Section 70-17-112, MCA, is the Montana statute expressly
    3
    prohibiting interference with canal and ditch easements. Section 70-17-112(5), MCA,
    provides: “If a legal action is brought to enforce the provisions of this section, the
    prevailing party is entitled to costs and reasonable attorney’s fees.”
    ¶8     The Ranch appealed the District Court’s ruling in favor of Joukova as to the
    culvert and bridge but it did not appeal the court’s ruling pertaining to attorney fees. On
    appeal, this Court reversed the District Court and remanded the matter with instruction
    that Joukova remove the culvert and bridge. We concluded that the installation of the
    culvert and rock bridge interfered with the Ranch’s secondary easement rights vis-à-vis
    the Cooley ditch.
    ¶9     On remand, the District Court ordered Joukova to remove the culvert and bridge.
    The Ranch then moved the District Court for its attorney fees and costs pursuant to
    § 70-17-112(5), MCA. Following oral argument on December 8, 2011, the District Court
    denied the Ranch’s request on two grounds: (1) the Ranch could have, and should have,
    appealed the issue of attorney fees and costs on the first appeal; and (2) the Ranch had
    not prevailed on all issues raised under § 70-17-112, MCA, and therefore was not entitled
    to attorney fees and costs. The Ranch appeals this ruling.
    STANDARD OF REVIEW
    ¶10    We review for correctness a district court’s decision as to whether legal authority
    exists to award attorney fees. Benintendi v. Hein, 
    2011 MT 298
    , ¶ 16, 
    363 Mont. 32
    , 
    265 P.3d 1239
    .
    DISCUSSION
    ¶11    Did the District Court err in denying attorney fees to the Ranch?
    4
    ¶12    The Ranch argues on appeal that it could not have appealed the court’s original
    ruling denying fees and costs because, given the District Court’s ruling allowing Joukova
    to retain the culvert and bridge over the Cooley ditch, it had not then prevailed on all
    issues pertaining to § 70-17-112, MCA; therefore, it was not entitled to fees and costs at
    that time. It maintains, however, that upon our favorable ruling issued in Musselshell
    Ranch I, it had prevailed on all issues pertaining to § 70-17-112, MCA, and was then
    entitled to fees and costs.
    ¶13    Joukova counters that the Ranch raised numerous claims under § 70-17-112,
    MCA, in the original law suit and that it did not prevail on all of them but chose not to
    appeal the loss of those claims, seeking to appeal only the retention of the culvert and
    bridge. We examine the issues raised by the Ranch at trial to determine whether those
    issues were raised pursuant to § 70-17-112, MCA, and whether the Ranch prevailed on
    those claims.
    ¶14    In the Complaint filed in August 2009, the Ranch asserted:
    In violation of [the Ranch’s] ditch easement and rights granted
    pursuant to Montana statutes, [Joukova] has interfered with [the Ranch’s]
    ditch easement, flow of water and the right to access up to 25 feet on either
    side of the canal for maintenance, cleaning and bank preservation purposes.
    Specifically [Joukova has] removed two 16 foot panels and by removing
    those panels, [the Ranch] cannot access the ditch bank when there is water
    in the ditch. [Joukova] further installed a culvert within the ditch, without
    consulting with or permission by the owners of the ditch easement
    impeding water flow. [Joukova] or her agents (John Does 1-5) have built a
    roadway on the bank of the irrigation ditch and have utilized heavy
    equipment including a dozer on the bank causing concern over deteriorating
    the banks infrastructure. [Joukova has] threatened physical harm to [the
    individual Ranch plaintiffs] and [the Ranch’s] agents.
    5
    ¶15    In its Complaint, the Ranch demanded that the District Court, pursuant to
    “§ 70-17-101(11), § 70-17-112(1) and (2), MCA, establish and declare that the [Ranch
    has] a permanent and perpetual right-of-way and easement over [Joukova’s] lands for the
    Cooley-Goffena ditch and further [has] a permanent right of ingress and egress of
    [Joukova’s] land . . . for up to 25 feet on both sides of the canal for maintenance
    purposes.”    The Ranch further demanded that Joukova be “ordered to remove all
    obstructions and not to place any additional obstructions in the Cooley-Goffena ditch
    which may impede the flow of water” and that she be permanently enjoined “from
    interfering with [the Ranch’s] access gates and other historical access for use and
    maintenance of the Cooley-Goffena ditch.”
    ¶16    As the case developed, the Ranch challenged Joukova’s right to drive and operate
    heavy equipment on the road along the northern bank of the ditch and to drive vehicles
    and heavy equipment over the highway approach built over the pipeline installed by the
    MDOT, claiming that such use could damage or weaken the ditch bank or underlying
    infrastructure.
    ¶17    In April 2010, the District Court issued a Pretrial Order setting forth the
    contentions of both parties. The Pretrial Order noted that the Ranch presented five 1
    alleged actions by Joukova that constituted interference with the Ranch’s easement: (a)
    removal of two 16-foot portable panels making access difficult or impossible; (b)
    removal of an access gate specifically installed by MDOT for the benefit of the ditch
    1
    We acknowledge that six specific actions were listed in the Pretrial Order, including a
    challenge to Joukova’s creation and use of an access approach from the south. This particular
    challenge was dismissed by the District Court prior to trial.
    6
    users and replaced with a continuously locked gate; (c) creation of a roadway on the
    north bank of the ditch which was constructed for the ditch users by the MDOT and was
    not designed to be used for vehicle and heavy equipment traffic; (d) placement of a
    culvert in the ditch which encroaches on the ditch and impedes the flow of water and
    hinders maintenance; and (e) threatened physical harm to individual Ranch plaintiffs and
    their agents when Ranch personnel entered Joukova’s property for ditch maintenance
    purposes.
    ¶18    In the court’s June 2010 Findings of Fact, Conclusions of Law and Order issued
    following trial, it determined that the placement of the culvert and bridge and Joukova’s
    upgrade and utilization of the road adjacent to the Cooley ditch did not interfere with the
    Ranch’s easement rights. The court concluded, however, that Joukova must replace the
    removed 16-foot panels and the removed gate at the west end of the property, and that
    she must allow access for Ranch personnel through both gates. The Ranch appealed the
    District Court’s ruling on the culvert and bridge alone. This Court, as noted above,
    reversed the District Court on this issue and remanded with instruction that Joukova
    remove the culvert and bridge.
    ¶19    In summary, the Ranch ultimately prevailed on its claims pertaining to the 16-foot
    panels, the culvert and bridge, a replacement gate on the west end and unlimited access
    through both gates. It did not prevail on its claim that Joukova could not travel the gravel
    road along the north bank of the Cooley ditch.
    ¶20    On appeal, the Ranch avers:
    7
    The allegation that Joukova constructed a roadway over the north
    bank of the Cooley-Goffena Ditch was not made under § 70-17-112(1)-(2),
    MCA. Although [the Ranch] sought relief on this point, the allegations
    against Joukova did not pertain to interference with [the Ranch’s]
    secondary easement rights. Thus, the fact Joukova prevailed on this issue is
    not relevant to the recoverability of attorneys’ fees and costs under
    § 70-17-112(5), MCA.
    ¶21    The record, however, reveals that the Ranch provided no independent legal basis
    for this claim; rather, this allegation was embedded within the Ranch’s arguments under
    § 70-17-112, MCA, without distinction from the remaining easement arguments. There
    is no support, therefore, for a conclusion that this argument was posited under a separate
    and distinct legal theory.
    ¶22    We now turn to whether the Ranch may still be considered a “prevailing party”
    having prevailed on the majority but not all of the issues raised pertaining to Joukova’s
    interference with its easement rights. We conclude under our precedent that it cannot.
    ¶23    We first addressed this issue in Knudsen v. Taylor, 
    211 Mont. 459
    , 
    685 P.2d 354
    (1984). In Knudsen, Taylor sued Knudsen alleging Knudsen failed to maintain his
    ditches properly, causing them to back up and seep onto Taylor’s land. Taylor also
    accused Knudsen of removing a culvert that Taylor had installed to allow Taylor access
    to another section of his land. Knudsen filed a separate complaint arguing that Taylor
    was interfering with his ditch easement rights under § 70-17-112, MCA. Knudsen, 211
    Mont. at 460-61, 
    685 P.2d at 355
    . The cases were consolidated and a jury trial was
    conducted. The jury ruled in favor of both parties on different issues but Knudsen was
    awarded $10,000 to Taylor’s $666.48. Claiming to be the prevailing party based upon
    the net judgment, Knudsen sought attorney fees and costs under § 70-17-112(5), MCA.
    8
    Knudsen, 211 Mont. at 461, 
    685 P.2d at 356
    . The district court denied the request and
    Knudsen appealed. We held on appeal that “the District Court was correct in finding in
    effect there was no prevailing party in the cause in the contemplation of Section
    70-17-112(5), MCA, and properly denied attorney fees.” Knudsen, 211 Mont. at 464,
    
    685 P.2d at 357
    .
    ¶24       Subsequently, in Sharon v. Hayden, 
    246 Mont. 186
    , 
    803 P.2d 1083
     (1990), Sharon
    sued Hayden, the holder of a ditch easement on Sharon’s property, claiming Hayden
    “unreasonably burdened his land by using heavy equipment to clear the irrigation ditch,
    constructing a roadway along the ditch and constructing gates at locations along Sharon’s
    fence line to allow access to the roadway.” Sharon, 246 Mont. at 187, 803 P.2d at 1084.
    Hayden answered seeking adjudication of his secondary easement rights and requested
    attorney fees under § 70-17-112(5), MCA.         The district court granted Hayden all
    easement rights but ordered that each party bear their own fees and costs. Sharon, 246
    Mont. at 188, 803 P.2d at 1085. On appeal, we reversed the district court holding that
    Hayden had successfully enforced both § 70-17-112(1) and (2), MCA; therefore he was
    “entitled, as the prevailing party, to costs and reasonable attorney fees.” Sharon, 246
    Mont. at 190, 803 P.2d at 1086. See also Boylan v. Van Dyke, 
    247 Mont. 259
    , 266, 
    806 P.2d 1024
    , 1029 (1991) (“Here, Mr Boylan failed to prevail in any of his claims. . . .
    [D]efendants prevailed and are therefore entitled to costs and attorney fees as a matter of
    law.”).
    ¶25       In Rieman v. Anderson, 
    282 Mont. 139
    , 
    935 P.2d 1122
     (1997), we acknowledged
    that the district court had determined that Anderson was the prevailing party on “all
    9
    issues” pertaining to § 70-17-112, MCA, and was entitled to attorney fees. Rieman, 282
    Mont. at 148, 
    935 P.2d at 1127
    .
    ¶26     Notably, in Engel v. Gampp, 
    2000 MT 17
    , 
    298 Mont, 116
    , 
    993 P.2d 701
    , we
    categorically stated “In order to be deemed a ‘prevailing party’ for the purposes of
    § 70-17-112(5), MCA, we have strictly held that a party must successfully prevail on all
    claims raised pursuant to this statute.” Engel, ¶ 40. (Emphasis in original.) We have
    since reaffirmed this holding in Espy v. Quinlan, 
    2000 MT 193
    , ¶ 28, 
    300 Mont. 441
    , 
    4 P.3d 1212
    , Graveley Simmental Ranch, Co. v. Quigley, 
    2003 MT 34
    , ¶ 49, 
    314 Mont. 226
    , 
    65 P.3d 225
    , and Byrum v. Andren, 
    2007 MT 107
    , ¶ 67, 
    337 Mont. 167
    , 
    159 P.3d 1062
    .
    ¶27     This line of cases unequivocally establishes that a “prevailing party” under
    § 70-17-112(5), MCA, must prevail on all claims raised pursuant to § 70-17-112, MCA.
    In the case before us, the Ranch, while prevailing on the majority of claims, did not
    prevail on all claims. As such it is not entitled to fees and costs under § 70-17-112(5),
    MCA.
    ¶28     Having determined the Ranch is not entitled to attorney fees and costs as a matter
    of law, we need not address the District Court’s ruling that the Ranch should have
    appealed the fee issue during Musselshell Ranch I.
    CONCLUSION
    ¶29     For the foregoing reasons, we affirm the District Court’s denial of Musselshell
    Ranch’s request for attorney fees.
    10
    /S/ PATRICIA COTTER
    We concur:
    /S/ MIKE McGRATH
    /S/ BETH BAKER
    /S/ JAMES C. NELSON
    Justice Jim Rice, concurring.
    ¶30    I concur with the Court’s opinion because it accurately applies the law regarding
    attorney fees under § 70-17-112(5), MCA, including the principle stated in ¶ 26 of the
    Opinion that “we have strictly held that a party must successfully prevail on all claims
    raised pursuant to this statute” in order to qualify for fees. Engel, ¶ 40. (Emphasis in
    original.)
    ¶31    That said, I harbor doubts about Engel’s holding in this regard. I fail to see why a
    party who prevails in an action “to enforce the provisions” of § 70-17-112(5), MCA, as
    Musselshell Ranch did here, should not be entitled to a statutory fee award.          At a
    minimum, the trial court should be able to determine, under the usual standards, whether
    the party seeking enforcement is the “prevailing party” of the entire litigation and thus
    entitled to fees. See Avanta Fed. Credit Union v. Shupak, 
    2009 MT 458
    , ¶¶ 45-50, 
    354 Mont. 372
    , 
    223 P.3d 863
    . However, Engel’s holding has been affirmed in subsequent
    cases by this Court, and until the Legislature addresses the issue or a persuasive argument
    is made for this Court to overturn precedent, I believe stare decisis requires that
    Musselshell Ranch’s claim for fees be denied.
    11
    /S/ JIM RICE
    Justice James C. Nelson joins in the concurring opinion of Justice Rice.
    /S/ JAMES C. NELSON
    Justice James C. Nelson, concurring.
    ¶32    Based on Engel v. Gampp, 
    2000 MT 17
    , ¶ 40, 
    298 Mont. 116
    , 
    993 P.2d 701
    , and
    the line of authority discussed at ¶¶ 23-26 of today’s Opinion, I concur in the Court’s
    conclusion that since the Ranch did not prevail on all of the claims it brought under
    § 70-17-112, MCA, it was not entitled to attorney’s fees as the “prevailing party” in this
    litigation pursuant to § 70-17-112(5), MCA. That is the current state of the law.
    ¶33    That said, if the Ranch views our decision here as adding insult to its injury, I can
    certainly commiserate with that sentiment. The Ranch did prevail on its main claim
    under the statute—forcing Joukova to remove her culvert and rock bridge which she had
    unlawfully constructed in the Ranch’s irrigation ditch.
    ¶34    In Musselshell Ranch I, I strongly criticized and dissented from this Court’s
    determination to judicially rewrite § 70-17-112(2), MCA, so as to add, among other
    things, this Court’s own “public policy” determinations to the otherwise plain and
    unambiguous text of the statute.       Musselshell Ranch I, ¶¶ 75-77, 81 (Nelson, J.,
    concurring in the result but dissenting from the reasoning). I pointed out that this Court’s
    decision placed irrigators in an untenable position. I observed that “[t]here is no reason,
    12
    much less any legal basis, why owners of canal or ditch easements should have to defend,
    as they henceforth must, their statutory easement rights from the ‘interference’
    (reasonable or otherwise) of every hobby rancher with 20 acres and a horse.”
    Musselshell Ranch I, ¶ 82 (Nelson, J., dissenting).
    ¶35    If irrigators expect to retain the full measure of the ditch and canal rights they once
    enjoyed, it will be up to the next session of the Legislature to amend § 70-17-112, MCA,
    so as to correct the damage to the statute done by this Court’s judicial rewriting of it. See
    Musselshell Ranch I, ¶ 85 (Nelson, J., dissenting). And, lest the importance of amending
    the statute be lost on irrigators, they should keep in mind that this Court also took the
    position in Musselshell Ranch I that if the Legislature does nothing this next session to
    fix § 70-17-112, MCA, then this Court will “presume” that the Legislature agrees with
    our decision to rewrite the statute. See Musselshell Ranch I, ¶ 14 (Court’s opinion),
    ¶¶ 53-59 (Nelson, J., dissenting).
    ¶36    Finally, in amending § 70-17-112, MCA, the Legislature may also wish to include
    a revised attorney’s fees provision in the statute. In future cases, where the irrigator
    successfully litigates an unlawful encroachment upon or impairment to its ditch or canal
    rights, the irrigator should be awarded its costs and reasonable attorney’s fees for
    prevailing on its main claim under the statute.
    ¶37    With these caveats, I concur.
    /S/ JAMES C. NELSON