Raytheon Company v. United States , 121 Fed. Cl. 135 ( 2015 )


Menu:
  •            In the United States Court of Federal Claims
    No. 15-77C
    (Filed Under Seal: May 11, 2015)
    (Reissued for Publication: June 2, 2015)*
    *************************************
    RAYTHEON COMPANY,                   *
    *
    Plaintiff,              *
    *              Bid Protest; Proposed Corrective Action
    v.                                 *              Based on GAO Attorney’s Statements
    *              During an Outcome Prediction Conference;
    THE UNITED STATES,                  *              Scope of the Court’s Review; Motion to
    *              Supplement the Administrative Record;
    Defendant,              *              Motion to Strike Document From the
    *              Administrative Record; Cross-Motions for
    and                                 *              Judgment on the Administrative Record;
    *              Noncompliance With Solicitation’s
    LOCKHEED MARTIN CORPORATION *                      Evaluation Scheme; Misleading and
    and NORTHROP GRUMMAN SYSTEMS *                     Unequal Discussions
    CORPORATION,                        *
    *
    Defendant-Intervenors.  *
    *************************************
    Mark D. Colley, Washington, DC, for plaintiff.
    Steven M. Mager, United States Department of Justice, Washington, DC, for defendant.
    Marcia G. Madsen, Washington, DC, for Lockheed Martin Corporation, and Deneen J. Melander,
    Washington, DC, for Northrop Grumman Systems Corporation, for defendant-intervenors.
    OPINION AND ORDER
    SWEENEY, Judge
    In this bid protest, plaintiff Raytheon Company (“Raytheon”), the contract awardee,
    challenges both the statements made by a Government Accountability Office (“GAO”) attorney
    during an outcome prediction conference held in conjunction with protests lodged by defendant-
    intervenors Lockheed Martin Corporation (“Lockheed”) and Northrop Grumman Systems
    *
    This reissued Opinion and Order incorporates the agreed-to redactions proposed by the
    parties on May 29, 2015. The redactions are indicated with bracketed ellipses (“[. . .]”).
    Corporation (“Northrop”), and the decision of the awarding agency to take corrective action after
    hearing those statements. Presently before the court are Northrop’s motion to supplement the
    administrative record, Raytheon’s motion to strike a document from the administrative record,
    and the parties’ cross-motions for judgment on the administrative record. As explained more
    fully below, the court denies Northrop’s motion to supplement the administrative record, grants
    Raytheon’s motion to strike, denies Raytheon’s motion for judgment on the administrative
    record, and grants the remaining cross-motions for judgment on the administrative record.
    I. BACKGROUND
    A. Earlier Phases of the Procurement
    Several years ago, the United States Air Force (“Air Force”) initiated the Three-
    Dimensional Expeditionary Long-Range Radar (“3DELRR”) acquisition program to replace its
    existing AN/TPS-75 radar system.1 AR 38928-29. The first phase of the program–the
    Technology Development phase–included two risk reduction periods. Id. at 38929-30. During
    the first risk reduction period, two contractors built and demonstrated radar system prototypes.
    Id. For the second risk reduction period, also referred to as the pre-Engineering and
    Manufacturing Development (“pre-EMD”) period, the Air Force awarded contracts to Raytheon,
    Northrop, and Lockheed to complete preliminary design reviews of their radar systems and
    demonstrate their prototypes. Id. at 38929, 38931.
    During both risk reduction periods in the Technology Development phase, a team of
    independent subject-matter experts (“independent review team”) with expertise in radar system
    design, hardware, software, testing, and signal processing performed a Technology Readiness
    Assessment of each radar system. Id. at 2377-79, 38930-31, 40614, 40625. The assessment
    began with the identification of the radar system’s critical technology elements (“CTEs”). Id. at
    2377-78, 40614. The independent review team used the following definition to guide its
    identification of CTEs:
    “A technology element is ‘critical’ if the system being acquired depends on this
    technology element to meet operational requirements (within acceptable cost and
    schedule limits) and if the technology element or its application is either new or
    novel or in an area that poses major technological risk during detailed design or
    demonstration.”
    1
    The facts in the background section are derived solely from the administrative record
    (“AR”), with one minor exception: the date and time that a specific document included in the
    administrative record was transmitted to the GAO was taken from an electronic-mail message to
    which the document was attached. That message, which is not in the administrative record but is
    attached as an exhibit to Raytheon’s motion to strike (“Mot. Strike Ex.”), is relevant only to the
    resolution of the motion to strike, and not to the merits of Raytheon’s protest.
    -2-
    Id. at 40625 (quoting Department of Defense, Technology Readiness Assessment (TRA)
    Deskbook (“TRA Deskbook”) 1-1 (July 2009)2); see also id. at 2382 (“[T]he technologies of
    interest here are not routine engineering or integration risk elements. They are items that require
    more than the normal engineering development that would occur in design for production as
    opposed to technology maturity programs.” (Department of Defense, Technology Readiness
    Assessment (TRA) Guidance (“TRA Guidance”) 2-11 (Apr. 2011))). Once the CTEs were
    identified, the independent review team evaluated the technological maturity of each CTE and
    then assigned each CTE a Technology Readiness Level (“TRL”). Id. at 2378-79, 38930-31,
    40614. As set forth in Interim Department of Defense Instruction (“DoDI”) 5000.02 (Nov. 26,
    2013), TRLs are meant to “be used to benchmark technology risk,” but are “rough benchmarks,
    and not conclusive about the degree of risk mitigation needed prior to development.” Id. at
    40398 (Interim DoDI 5000.02, § 5.d(4)(b)(3)). Indeed, TRLs “can serve as helpful knowledge-
    based standard and shorthand for evaluating technology maturity, but they must be supplemented
    with expert professional judgment.” Id. at 2371 (TRA Guidance 1-1); accord id. at 2377 (“TRLs
    will be used as a knowledge-based standard or benchmark but should not substitute for
    professional judgment tailored to the specific circumstances of the program.” (TRA Guidance 2-
    5)). With respect to the 3DELRR procurement, the contractors were required during the
    Technology Development phase to produce and demonstrate a functioning radar system
    prototype in which all CTEs were assigned a TRL of at least six. Id. at 40626. A CTE would be
    considered to be TRL 6 if the “[s]ystem/subsystem model or prototype” was “demonstrat[ed] in a
    relevant environment.” Id. at 2385 (TRA Guidance 2-13).
    At the conclusion of the pre-EMD period, after the demonstrations of the radar system
    prototypes, the independent review team prepared a Technology Readiness Assessment report for
    each contractor. Id. at 40614. In its report for Raytheon, the team described Raytheon’s
    proposed radar system as being composed of [. . .] subsystems. Id. at 40617. One of those
    subsystems, the [. . .] subsystem, included the antenna assembly, which consisted of [. . .]
    Transmit/Receive Line Replaceable Units (“TRLRUs”) [. . .]. Id. at 40619, 40631. Each
    TRLRU contained [. . .]. Id. at 40631. And, each T/R module consisted of [. . .], a circulator,
    [. . .], a gallium nitride high power amplifier (“GaN HPA”), [. . .].3 Id. at 40631. Some of the
    components of each T/R module [. . .], while the circulators [. . .]. Id. at 40631. The following
    figure depicts Raytheon’s TRLRU:
    2
    The July 2009 version of the Technology Readiness Assessment (TRA) Deskbook is
    not included in the administrative record.
    3
    Broadly speaking, when a transmit signal is generated by the radar system, it travels
    through the GaN HPA, which boosts the signal, then through the circulator, and finally through
    the radiator into open space. AR 76562.27. When the energy sent into open space is reflected
    back to the radar system, it passes through the radiator, the circulator, and then the rest of the
    “receive path.” Id. at 76562.28. The circulator protects the transmit and receive sides of the T/R
    module from interfering with each other. Id. at 76562.43-.44, .104.
    -3-
    [. . .]
    Id.
    The independent review team identified six CTEs for Raytheon’s radar system; of
    relevance here is Raytheon’s CTE 1, the Gallium Nitride High Power Amplifier [. . .] (“GaN
    HPA [. . .]”). Id. at 40614. The team described this CTE as a “[. . .].”4 Id. at 40630-31. It
    provided the following rationale for identifying the GaN HPA [. . .] as a CTE:
    [. . .]
    Id. at 40632; see also id. at 40632-36 (describing test results for the TRLRU, [. . .], [. . .], and
    [. . .]). In other words, notwithstanding its initial description of CTE 1 as the GaN HPA [. . .],
    the independent review team considered the GaN HPA and [. . .] as the new and novel critical
    technologies that required TRL assessment. Id. at 40632.
    The independent review team ultimately determined that Raytheon had demonstrated all
    of its CTEs in a relevant environment and therefore assessed each CTE as TRL 6. Id. at 40626,
    40630-54, 40658.
    B. The Solicitation for the Current Phase of the Procurement
    Indeed, the Air Force concluded that all three contractors–Raytheon, Northrop, and
    Lockheed–successfully “demonstrated mature, low risk radar designs ready for transition” into
    the next phase of the procurement, Engineering and Manufacturing Development (“EMD”). Id.
    at 38931. The purpose of the EMD phase was “to develop, build, and test” a radar system “to
    verify that all operational and derived requirements [were] met and to support production or
    deployment decisions.” Id. at 40403 (Interim DoDI 5000.02, § 5.d(9)(a)). Design changes were
    anticipated during the EMD phase, id. (Interim DoDI 5000.02, § 5.d(9)(b)(1)(a)), and the phase
    would conclude after the design had stabilized, id. at 40404 (Interim DoDI 5000.02, § 5.d(9)(d)).
    Accordingly, on November 15, 2013, the Air Force issued solicitation FA8730-13-R-
    0001 to the three contractors with the intent to award one of them a contract to proceed in the
    EMD phase. Id. at 40186-87, 41237. Of the fifteen contract line item numbers (“CLINs”)
    included in the solicitation, only one was not an option CLIN: CLIN 0001. Id. at 40187-96.
    This Fixed-Price-Incentive-Firm CLIN required the successful contractor to develop three
    3DELRR systems.5 Id. at 40187, 41237.
    4
    Lockheed describes Raytheon’s GaN HPA [. . .]. Lockheed Cross-Mot. for J. on the
    Administrative R. 10, 35.
    5
    The option CLINs were a combination of Fixed-Price-Incentive-Firm, Firm-Fixed-
    Price, and Cost-Plus-Fixed-Fee CLINs. AR 40188-96.
    -4-
    In section L of the solicitation, the Air Force described the proposal requirements. Id. at
    41234-79, 53772-73. Two of those requirements are relevant to this protest. First, in the
    technical volumes of their proposals, the contractors were to identify all CTEs that had changed
    since the pre-EMD period, provide the TRLs of those CTEs, and substantiate the TRLs with
    supporting data. Id. at 41250. Second, in the cost/price volumes of their proposals, the
    contractors were to identify and support their proposed cost reductions. Id. at 41261. With
    respect to this latter requirement, the solicitation provided:
    6.3.5.2 Cost Reductions
    6.3.5.2.1 Management Reduction
    If estimated costs to perform the proposed effort have been decreased due to a
    management decision, the Offeror shall provide a summary of the reduction by
    major cost element summary and complete rationale for the reduction.
    6.3.5.2.2 Commonality with Other Programs
    Any cost reductions made in the Offeror’s proposal that are attributed to
    commonality with other programs, company-funded efforts, or capitalization of
    equipment shall be supported with the following information:
    (a) Commonality     The Offeror shall identify the specific program(s) and why
    it is applicable.
    The Offeror shall address the cost allowability and
    allocatability of this action per [the Federal Acquisition
    Regulation (“FAR”)] and their [Cost Accounting Standards
    (“CAS”)] Disclosure Statement.
    (b) Company-        The Offeror shall identify the specific efforts, the planned
    Funded Efforts      start and end dates, the applicability to the current
    solicitation, the source of company funding and how they
    plan to account for or allocate these costs in accordance
    with generally accepted accounting principles, and your
    CAS Disclosure Statement, if applicable.
    (c) Capital         The Offeror shall identify the specific item(s) capitalized
    Equipment           and what other applications exist for the equipment, provide
    corporate approvals for each action, address the cost
    allowability and allocability of the action per the FAR and
    their CAS Disclosure Statement.
    Id. at 41261-62.
    -5-
    Then, in section M of the solicitation, the Air Force described how it would evaluate the
    contractors’ proposals. Id. at 40364-77. Of particular relevance in this bid protest, the Air Force
    indicated that it would evaluate the contractors’ proposals for technical compliance and technical
    risk under three technical subfactors. Id. at 40368, 40371-73. For each subfactor, the Air Force
    would assign technical compliance and technical risk ratings of Acceptable or Unacceptable. Id.
    at 40368, 40371-72. And, in evaluating the contractors’ proposals under Technical Subfactor 1,
    System Design and Performance, the Air Force would “determine if the subfactor [was] met
    based on”:
    2.4.1.1 Whether the proposal substantiates the ability to design, develop, and test
    a radar that . . . meets the system performance requirements [described elsewhere
    in the solicitation].
    ....
    2.4.1.3 Substantiation of at least a Technology Readiness Level 6 (TRL 6) for all
    Critical Technology Elements (CTEs) of the design solution that have changed
    since the Pre-EMD Preliminary Design Review (PDR). One CTE must be a
    Gallium Nitride (GaN) High Power Amplifier (HPA)-based Transmit/Receive
    (T/R) module.
    Id. at 40372.
    Also relevant to this bid protest are the Air Force’s criteria for evaluating the contractors’
    proposed costs and prices. Id. at 40374-76. The Air Force indicated that it would first assess
    whether the contractors’ cost/price proposals were reasonable and realistic. Id. at 40374-75.
    Next, for each proposal, it would calculate a total evaluated price. Id. at 40375-76. Then, it
    would apply a decrement factor to the contractors’ total evaluated prices; if a contractor’s radar
    system prototype exceeded the threshold range capability set forth in the solicitation’s
    requirements, the contractor’s total evaluated price could be reduced by as much as $155 million.
    Id. at 40368-69, 40372, 40376. This reduction would result in a Best Value Assessment. Id.
    The Air Force indicated that it intended to award a contract “to the Offeror with acceptable
    technical compliance, acceptable technical risk, . . . and the lowest [Best Value Assessment]
    (utilized for evaluation purposes only).” Id. at 40369.
    C. The Contractors’ Proposals
    All three contractors with pre-EMD contracts–Raytheon, Northrop, and Lockheed–
    submitted proposals pursuant to the EMD solicitation. Id. at 73324. Two aspects of the
    proposals are pertinent to the issues in this bid protest: the portions of Raytheon’s technical
    volume related to its CTE 1 and the portions of the contractors’ cost/price volumes related to
    proposed cost reductions.
    -6-
    In its technical volume, Raytheon described the [. . .] subsystems of its proposed radar
    system. Id. at 48392-404. The description of its [. . .] subsystem was consistent with the
    description contained in the Technology Readiness Assessment report prepared by the
    independent review team during the pre-EMD period; Raytheon did not indicate any significant
    changes. Id. at 48393-97. Indeed, in another portion of its technical volume, Raytheon expressly
    represented that since the pre-EMD period, it had not introduced any “new technologies” to its
    “design solution.” Id. at 48096. Raytheon further represented that its CTEs had not changed and
    that its prototype “successfully demonstrated all Pre-EMD phase CTEs at TRL 6 and the overall
    design maturity in a relevant environment.” Id. at 48096-97. However, as reflected in the
    following figure depicting the TRLRU that Raytheon included in its proposal, Raytheon did
    change the design of its TRLRU. Compare id. at 40631 (pre-EMD design), with id. at 48382
    (EMD proposal design). Specifically, Raytheon [. . .]. See id. at 48382 (containing Figure II-
    1.0.1-6, which includes a depiction of Raytheon’s redesigned TRLRU), 52911 (containing
    Raytheon’s rationale for the design change).
    [. . .]
    Id. at 48382.
    Turning to the cost/price volumes, the three contractors proposed vastly different
    approaches to reducing the costs of contract performance. In its proposal, Raytheon identified
    [. . .] in cost reductions: [. . .] for independent research and development (“IR&D”), and [. . .].
    Id. at 48688-98. In contrast, Lockheed proposed [. . .]. Id. at 42067. And, Northrop identified
    [. . .] cost reductions totaling [. . .]. Id. at 47078-81. Northrop explained that although its cost
    proposal provided the “Air Force with cost savings directly attributable to [. . .],” its proposal
    was [. . .]. Id. at 47085. It bears noting that the [. . .] described by Northrop included [. . .]. Id. at
    47086-87.
    After accounting for their cost reductions, Raytheon offered the lowest total price of
    $134,546,302, id. at 51001; Northrop offered [. . .], id. at 51456; and Lockheed offered [. . .], id.
    at 50533. All three contractors proposed prices that [. . .]. Id. at 73572.
    D. Discussions
    Upon receiving the proposals, the Air Force determined that all were in the competitive
    range. Id. at 52239-42, 73324. It therefore initiated discussions with all three contractors. Id. at
    73324. One of the technical discussion items is relevant to this protest. In Evaluation Notice
    (“EN”) RAY-TECH1-025, the Air Force requested information from Raytheon regarding its
    proposed production cost savings. Id. at 52909-10. In its response to the EN, Raytheon included
    the following information:
    [. . .]
    -7-
    Id. at 52911. The Air Force reviewed this response and ultimately deemed the discussion issue
    resolved. Id. at 52913.
    In addition, a number of discussion items pertaining to the contractors’ cost/price
    proposals bear on the issues raised in this protest. For example, in EN NG-CP-003, the Air Force
    requested that Northrop provide information, such as “[. . .]/IR&D planning statements,” to
    substantiate how it planned to fund contract performance during three specified fiscal years. Id.
    at 52482. Northrop responded: “The execution of this contract does not require [. . .] IR&D
    funding, and [Northrop] has the resources to implement this financial offer . . . .” Id. at 52483.
    The Air Force considered the discussion issue resolved. Id. at 52484.
    The Air Force also sent similar ENs to Raytheon and Northrop regarding the
    reasonableness and realism of their proposed cost reductions. Id. at 52558-60, 52813-15. Both
    EN RAY-K-016 and EN NG-K-011 provided:
    The Government is concerned with the reasonableness and realism of any
    affordability initiative offered. It is imperative the Offeror substantiate and the
    Government fully understand any claimed initiative which the Offeror desires to
    incorporate into its proposed cost/price.
    ....
    In accordance with (IAW) FAR 31.205-18 and [
    10 U.S.C. § 2320
    ], any
    cost claimed or considered to be IR&D or a capital investment shall not be
    allowable as indirect charges for work implicitly required for performance
    (necessary to perform the contract) or explicitly required to be done by the terms
    of the contract. Any such costs should be considered as direct charges to the
    3DELRR contract. Further, unless properly segregated and agreed to as
    unallowable costs IAW FAR Part 31, any such costs may be deemed unrealistic.
    Any cost reduction efforts specifically expended for or anticipation of the
    3DELRR requirements should be considered to be generated in performance of
    Government funded contract requirements . . . .
    In addition, any methodology proposing savings, which could be
    considered contingent on future events may be considered speculative and
    unrealistic as regards savings on the efforts proposed for purposes of the
    cost/price used in the Best Value Assessment.
    
    Id. at 52559, 52814
    . In the same ENs, the Air Force proposed the use of a special contract clause
    (“section H clause”) “[t]o ensure the proposed savings, incorporated into [the contractors’]
    proposed price, are determined reasonable and realistic.” 
    Id.
    -8-
    The contractors’ responses to this EN were quite different. Raytheon, after discussing its
    cost reduction efforts with the Air Force during a March 5, 2014 conference call, explained in its
    response to the EN that it received:
    2. Raytheon’s proposal is compliant with the FAR and government
    accounting rules governing the appropriate charging of IR&D, [. . .]. The
    Government states that [any] ‘cost claimed to be IR&D or capital investment shall
    not be allowable as indirect charges for work “implicitly” required for
    performance (necessary to perform a
    contract)’. This Government interpretation of rules on allowability of IR&D costs
    was specifically rejected by the United States Court of Appeals for the Federal
    Circuit [(“Federal Circuit”)] in ATK Thiokol Inc. v. United States, 
    598 F.3d 1329
    (Fed. Cir. 2010). The Federal Circuit held that research and development costs
    are allowable as IR&D costs unless specifically required by the contract. 
    598 F.3d at 1334-35
    . [. . .]
    Raytheon carefully reviewed the scope of the IR&D [. . .] to ensure they
    are compliant with the above current rules. [. . .] Raytheon assumes that the
    government will evaluate Raytheon’s proposal consistent with the rules as
    interpreted by the Federal Circuit.
    ....
    6. In accordance with Raytheon’s [. . .], IR&D [. . .].
    Id. at 52817-18. In addition, Raytheon proposed the use of a modified version of the section H
    clause suggested by the Air Force in which it agreed to expend [. . .] for IR&D, [. . .] in
    performing the contract. Id. at 52818-21. The Air Force’s only comment on Raytheon’s
    response was: “A follow-up EN has been generated to address the H Clause for Raytheon . . . .”
    Id. at 52821.
    In contrast to Raytheon, Northrop did not take issue with the Air Force’s stated
    interpretation of FAR 31.205-18 and 
    10 U.S.C. § 2320
     in its response to the EN that it received.
    
    Id. at 52560-61
    . Rather, its focus was on the Air Force’s proposed section H clause:
    [. . .]
    
    Id.
     Upon reviewing this response, the Air Force commented: “The offeror has substantiated
    their initiatives to reduce the proposed cost/price. . . . A Section H Clause will be proposed to
    NG in a follow-up EN to capture how their [. . .] will affect the contract.” 
    Id. at 52562
    .
    After the Air Force received the responses to ENs RAY-K-016 and NG-K-011, it
    contacted the Defense Contract Management Agency (“DCMA”) with questions regarding the
    -9-
    contractors’ concerns with its proposed section H clause, and its General Counsel with questions
    regarding IR&D. 
    Id. at 53852, 58971
    . On March 19, 2014, Air Force representatives received
    input from Steve Trautwein of the DCMA.6 
    Id. at 58691
    . Mr. Trautwein subsequently agreed to
    assist the Air Force with its evaluation of the cost/price proposals. 
    Id. at 38970, 58691, 58966, 73139
    .
    After conferring with Mr. Trautwein, the Air Force sent follow-up ENs to Raytheon and
    Northrop. In the follow-up EN that it sent to Raytheon (RAY-K-016a), the Air Force did not
    address Raytheon’s statements regarding IR&D, but did propose another version of the section H
    clause, [. . .]. 
    Id. at 59412-13
    ; see also 
    id. at 58696
     ([. . .]). After a conference call with the Air
    Force, Raytheon responded with another modified version of the section H clause that [. . .]. 
    Id. at 59415-16
    . The Air Force was satisfied with Raytheon’s response and deemed the EN
    resolved. 
    Id. at 59416
    .
    In the follow-up EN that it sent to Northrop (NG-K-011a), the Air Force did not mention
    IR&D. 
    Id. at 59389-90
    . Instead, as it did with Raytheon, the Air Force proposed another version
    of the section H clause. 
    Id.
     In response, after reiterating its position that such a clause was
    unnecessary, Northrop proposed [. . .]. 
    Id. at 59390-92
    . The Air Force commented that another
    follow-up EN would be sent to Northrop with a final version of a section H clause, and that no
    response from Northrop aside from an acknowledgment of receipt would be required. 
    Id. at 59392
    ; see also 
    id. at 60825-26
     (EN NG-K-011b).
    The Air Force did not send Lockheed an EN similar to ENs RAY-K-016 and NG-K-011.
    Rather, during the second round of discussions, the Air Force advised Lockheed in EN LM-K-
    014 that its “[. . .].” 
    Id. at 59958
    . In response, Lockheed [. . .]. 
    Id. at 59960-69
    . Altogether,
    these [. . .]. 
    Id. at 59969
    .
    E. Final Proposal Revisions, the Source Selection Decision, and Contract Award
    At the close of discussions, the Air Force requested a final proposal revision from each
    contractor. 
    Id. at 73324
    . In making its request, the Air Force advised all three contractors that
    their proposed costs and prices were, at that time, considered to be reasonable and realistic, and
    that the final proposal revision would be the contractors’ last opportunity to update their
    cost/price proposals. 
    Id. at 65227, 65231, 65238
    . The Air Force further advised [. . .]. 
    Id. at 65231
    .
    In its final proposal revision, Raytheon reduced its total proposed price to [. . .]. 
    Id. at 73603
    . One factor contributing to the lower price was [. . .]. 
    Id. at 73605-07
    . Of note, Raytheon
    [. . .] IR&D [. . .]. 
    Id. at 73606
    . Northrop proposed a price of [. . .] in its final proposal revision.
    
    Id. at 73615
    . Although Northrop [. . .], it did not [. . .]. 
    Id. at 73617-18
    . Lockheed, in its final
    6
    The documents from this time period contained in the administrative record do not
    describe the substance of Mr. Trautwein’s input.
    -10-
    proposal revision, [. . .] its total proposed price to [. . .]. 
    Id. at 73592
    . Its [. . .] price reflected,
    among other things, [. . .]. 
    Id. at 73594-95
    .
    As part of its evaluation of the contractors’ final proposal revisions, the Air Force’s
    technical evaluators reviewed Raytheon’s proposal for compliance with the solicitation’s
    technical requirements. 
    Id. at 72461-527
    . These technical evaluators were advised by four
    members of the original independent review team. Compare 
    id. at 38945
     (source selection plan),
    with 
    id. at 40625
     (Technology Readiness Assessment report). With respect to the requirement
    that contractors substantiate TRL 6 ratings for each of the CTEs that had changed since the pre-
    EMD period, 
    id. at 40372
    , Kevin Ray, the chief evaluator for Technical Subfactor 1, System
    Design and Performance, remarked:
    Raytheon substantiated all criteria listed in Section M 2.4.1.3.
    The Technology Readiness Assessment (TRA) Independent Review Team
    (IRT) assessed all Raytheon’s Critical Technology Elements (CTEs) at
    Technology Readiness Level 6 (TRL 6) during the Pre-Engineering and
    Manufacturing Development (Pre-EMD) Period of the Technology Development
    (TD) Phase. Raytheon listed the same CTEs in the EMD proposal as those
    identified in the Pre-EMD Period. In addition, Raytheon identified one CTE as a
    Gallium Nitride (GaN) High Power Amplifier (HPA)-based Transmit/Receive
    (T/R) module which met the Government’s requirement.
    TRA IRT members reviewed and analyzed Volume II, Paragraph 1.3,
    Pages II-86 to II-88. The IRT members confirmed the CTEs listed were the
    original CTEs approved by the team in 2013 and there were no changes to the
    CTEs since the Pre-EMD Period Preliminary Design Review (PDR) where
    Raytheon was assessed at TRL 6. Raytheon described each CTE in the following
    Volume II pages.
    1. Pages II-19 to II-21 and the classified Volume IIA, Figure IIA-1.0.1-6
    System Architecture for the T/R Line Replaceable Unit (LRU) and the
    receive LRU.7
    
    Id. at 72478-49
     (footnote added).
    In its Source Selection Decision Document, the Air Force noted that all three contractors
    had received technical compliance and technical risk ratings of Acceptable for all three technical
    7
    Raytheon represents, and the other parties do not dispute, that “classified Volume IIA,
    Figure IIA-1.0.1-6” is the same as Figure II-1.0.1-6 that appears in the unclassified technical
    volume of its proposal. Raytheon Mot. for J. on the Administrative R., Ex. 1. Both figures
    contain the same depiction of Raytheon’s redesigned TRLRU. 
    Id.
    -11-
    subfactors. 
    Id. at 73326
    . It also indicated that all of the proposed costs and prices were
    reasonable and realistic, and that each contractor received the full $155 million decrement for
    exceeding the specified threshold range capability. 
    Id. at 73326-27
    . Subtracting $155 million
    from each contractors’ total evaluated price, the Air Force arrived at the following Best Value
    Assessments: ($80,537,981) for Raytheon, [. . .] for Northrop, and [. . .] for Lockheed. 
    Id. at 73326
    . Based on all of this information, the Air Force concluded:
    In accordance with the [solicitation], award is to be made to the Acceptable
    Offeror with the lowest [Best Value Assessment], who is deemed responsible in
    accordance with the FAR. Raytheon is evaluated as Acceptable with the lowest
    [Best Value Assessment] and is deemed to possess the requisite technical,
    management and financial capability to perform the effort and is otherwise
    qualified within the meaning of FAR 9.104.
    
    Id. at 73327
    . It therefore awarded the contract to Raytheon. 
    Id. at 73327, 74952-53
    .
    F. Proceedings Before the GAO
    On the same date that it awarded the contract to Raytheon, October 6, 2014, the Air Force
    notified Northrop and Lockheed of its award decision. 
    Id. at 74957-60
    . In its award notices, the
    Air Force disclosed to Northrop and Lockheed that the total value (including options) of the
    contract awarded to Raytheon was $71,821,520. 
    Id. at 74957, 74959
    . It also advised both
    contractors of their technical ratings, total evaluated prices, and Best Value Assessments. 
    Id. at 74958, 74960
    . Lockheed received a debriefing on October 15, 2014, 
    id. at 75062
    , and Northrop
    received a debriefing the following day, 
    id. at 75088
    .
    Dissatisfied with the award decision, Northrop lodged a protest with the GAO on October
    21, 2014. 
    Id. at 75385
    . It asserted several errors with the Air Force’s evaluation of proposals,
    none of which are at issue in this bid protest. See 
    id. at 75388-89
    . However, in support of one of
    its initial protest grounds, Northrop stated: “While the [solicitation] contemplates cost
    reductions from commonality with other programs, it clearly anticipates that these reductions will
    take the form of company funded efforts, management challenges, IR&D, shared equipment,
    shared supplies, economies of scale, etc.” 
    Id. at 75420
    .
    The following day, Lockheed also protested the Air Force’s award decision at the GAO.
    
    Id. at 75480
    . It then submitted a supplemental protest on October 27, 2014. 
    Id.
     None of
    Lockheed’s initial or supplemental protest grounds is at issue in this protest. See 
    id. at 75515
    .
    After reviewing a copy of the Source Selection Decision Document that it had received
    from the Air Force, Northrop filed a supplemental protest with the GAO on November 14, 2014.
    
    Id. at 75456
    . As with its initial protest, none of the supplemental protest grounds are at issue in
    this bid protest. See 
    id. at 75463-70
    . However, in support of one of those grounds, Northrop
    argued that had it known that the Air Force interpreted the cost reduction provisions of the
    -12-
    solicitation to include IR&D cost reductions, “it would have submitted a very different proposal
    with different types of and larger cost reductions, resulting in a [total evaluated price] that would
    likely be lower than those proposed by Raytheon and Lockheed Martin.” 
    Id. at 75470
    .
    In response to the initial and supplemental protests lodged by Northrop and Lockheed, the
    Air Force submitted a statement of facts, a memorandum of law, and an agency record
    (collectively, “the agency report”) to the GAO on November 25, 2014. 
    Id. at 75477-663
    . It
    requested that the protests be denied on their merits, contending that it “properly evaluated
    proposals and selected the best value Offeror in a thorough, fair, and reasonable manner” and that
    it “conducted this procurement in full accord with the selection criteria contained in the
    solicitation and in compliance with applicable procedures and regulations.” 
    Id. at 75539
    .
    Lockheed filed a second supplemental protest on December 4, 2014, raising grounds not
    applicable in this protest. See 
    id. at 75673-93
    . Then, on December 8, 2014, with its response to
    the agency report, Lockheed submitted a third supplemental protest. 
    Id. at 75694
    ; see also 
    id. at 75697
     (indicating that Lockheed received the agency report on November 26, 2014). One of the
    protest grounds in Lockheed’s third supplemental protest concerned Raytheon’s CTE 1;
    Lockheed argued that because Raytheon proposed using a TRLRU that was different from the
    one it demonstrated during the pre-EMD period, the Air Force improperly considered Raytheon’s
    CTE 1 to be mature, such that it could be assessed as TRL 6. 
    Id. at 75716-22
    .
    Northrop also submitted a supplemental protest on December 8, 2014, in response to the
    agency report. 
    Id. at 75741
    ; see also 
    id. at 75744
     (indicating that Northrop received the agency
    report on November 26, 2014). In this second supplemental protest, Northrop asserted that the
    Air Force conducted misleading discussions. 
    Id. at 75787-94
    . In particular, Northrop noted that
    the Air Force accepted Raytheon’s understanding of the allowability of IR&D costs as an indirect
    charge, but never advised Northrop of its changed understanding. 
    Id.
     Northrop argued that the
    Air Force’s failure to make such a disclosure prevented it from proposing IR&D cost reductions
    in line with the IR&D cost reductions proposed by Raytheon [. . .]. 
    Id. at 75793
    . Specifically, it
    contended:
    If Northrop Grumman had known of the Air Force’s changed
    interpretation, it would have responded by protesting the interpretation’s illegality
    and/or submitting a radically changed proposal. Northrop Grumman is a very
    large corporation with billions in assets and revenue. [. . .] Had Northrop
    Grumman known of the Air Force’s expansive view of IR&D, which permitted
    offerors to propose IR&D that violated the FAR and the Air Force instruction
    provided to Northrop Grumman, Northrop Grumman could have proposed the
    types and quantities of IR&D [. . .].
    
    Id.
     (citations omitted) (citing AR 71934, 44789); see also 
    id. at 75753
     (reflecting Northrop’s
    understanding that “IR&D funds could not be proposed to perform any of the required
    development work”).
    -13-
    In response to the additional supplemental protests lodged by Northrop and Lockheed, the
    Air Force submitted a supplemental statement of facts, a supplemental memorandum of law, and
    a supplemental agency record (collectively, “the supplemental agency report”) to the GAO on
    December 15, 2014. 
    Id. at 76007-187
    . In its supplemental statement of facts, the Air Force
    stated that [. . .] IR&D investments during the initial phases of the 3DELRR procurement,
    specifically noting that Northrop [. . .]. 
    Id.
     at 76029-30 (citing AR 27566, 44794). Ultimately, it
    once again requested that the GAO deny the protests on their merits. 
    Id. at 76186
    . All three
    contractors submitted comments on the supplemental agency report on December 22, 2014. 
    Id. at 76191, 76238, 76417
    . Of particular note, Northrop remarked, with respect to its IR&D-related
    supplemental protest ground:
    [T]he Air Force appears to confuse IR&D, in general, with future IR&D to be
    used to perform development work required by a contract, a subset that is
    expressly excluded from the FAR definition of IR&D that may be charged to
    government contracts. Northrop Grumman has never contended that IR&D could
    not be used at all. It has only contended that offerors could not propose as
    FAR-compliant – and here, as [solicitation-] and EN-compliant – any future
    IR&D funding to be used to perform required development under the 3DELRR
    contract but charged to other contracts, which is what Raytheon [. . .] proposed.
    
    Id. at 76248
    ; accord 
    id. at 76274
     (“Northrop Grumman has not and does not challenge
    [. . .] use of already completed IR&D efforts. It has only challenged the proposed future
    use of IR&D to fulfill development work required by the 3DELRR contract.”).
    On January 6, 2015, the GAO conducted a hearing concerning the protests filed by
    Northrop and Lockheed. 
    Id. at 76656
    . During the hearing, Mr. Ray testified regarding, among
    other things, Raytheon’s change to the design of its TRLRU. He emphasized that the Air Force
    considered the GaN HPA and [. . .] as the new and novel critical technologies that required TRL
    assessment. 
    Id. at 76562
    .38-.41, .44, .59, .68, .76, .91, .114-.115, .135. In contrast, the Air Force
    did not consider the circulator to be a critical technology, 
    id. at 76562
    .60-.62, .128-.129, even
    though the circulator was required for the T/R module to function properly, 
    id. at 76562
    .79-.80.
    Based on all of these understandings, the Air Force determined that although [. . .] the circulator
    [. . .] would require [. . .] to be redesigned, neither of the critical technologies in CTE 1 (the GaN
    HPA and [. . .]) were affected by the design change. 
    Id. at 76562
    .44-.47, .68-.69, .116, .128-.129,
    .132, .134-.135. In fact, the Air Force did not believe that [. . .] the circulator would impact
    performance. 
    Id. at 76562
    .99. As a result, the Air Force did not request, and Raytheon did not
    provide, any information regarding the proposed redesigned [. . .], such as the new design or test
    data. 
    Id. at 76562
    .88, .93-.94, .97-.98, .99, .105, .109, .112.
    Also testifying during the hearing was Elizabeth D. Kent, the Air Force’s procuring
    contracting officer. Of relevance is Ms. Kent’s testimony concerning the temporal characteristics
    of the IR&D costs proposed [. . .] and the Air Force’s changed understanding of the allowability
    -14-
    of IR&D costs. With respect to the former topic, Ms. Kent testified that the Air Force always
    understood that neither the solicitation, nor the FAR, nor the CAS differentiated between past,
    present, and future IR&D costs, and that such a distinction would be irrelevant to its price
    realism analyses. 
    Id. at 76507, 76517-18
    . With respect to the latter topic, Ms. Kent stated that
    Raytheon’s response to EN RAY-K-016 and the Air Force’s initial conversation with Mr.
    Trautwein from the DCMA informed the Air Force’s understanding of the difference between
    explicit and implicit contract requirements as they related to the rules concerning the allowability
    of IR&D costs as an indirect charge. 
    Id. at 76504, 76506, 76536
    . Indeed, the Air Force’s
    understanding changed to conform to Raytheon’s interpretation; the ENs that the Air Force had
    sent to Raytheon and Northrop no longer reflected its position on the allowability of IR&D costs
    related to implicit contract requirements. 
    Id. at 76538-39
    . Moreover, Mr. Trautwein, after
    reviewing the contractors’ price/cost proposals, advised the Air Force in late March 2014 that
    Raytheon’s reduction for IR&D was a permissible cost reduction method. 
    Id. at 76499-501
    .
    After the hearing, the participants filed posthearing briefs. See, e.g., 
    id. at 76656-710, 76738-50
    . In its briefs, the Air Force argued that the hearing testimony supported its position
    that the protests should be denied on their merits. 
    Id. at 76669, 76750
    . Notably, in regard to
    Northrop’s IR&D-related supplemental protest ground, the Air Force argued:
    Once Northrop notified the Air Force it would not be using IR&D (after EN
    NG-K-011 and NG-CP-003), . . . the Air Force was under no continuing
    obligation to pressure Northrop to include IR&D in its proposal. In fact,
    additional inquiries in this area may have inadvertently disclosed Raytheon [. . .].
    Based on Northrop’s responses, the Agency determined it must tailor further
    discussions to focus on Northrop’s proposed cost reduction methodology [. . .] as
    identified in Northrop’s EN response . . . .
    
    Id. at 76741
     (footnote omitted).
    Shortly after receiving the posthearing briefs, the GAO attorney assigned to the protests
    invited counsel for the parties to participate in an alternative dispute resolution outcome
    prediction conference. 
    Id. at 76751
    . She advised:
    I have reached my resolution concerning the merits of the protest and have
    discussed this matter with my supervisors. . . . [W]e are currently working on a
    draft of the decision.
    As an alternative to the issuance of a decision, we are inquiring at this time
    as to whether the parties would like to participate in an alternative dispute
    resolution (ADR) outcome prediction session, or prefer to proceed to a written
    decision.
    -15-
    Our Office may provide outcome prediction . . . where we believe that the
    record is appropriate for a discussion of the merits of the protest. Outcome
    prediction is a presentation by the GAO attorney assigned to the protest discussing
    his or her views as to the merits of the protest, and how he or she would draft a
    written decision. This presentation is not, however, a formal adjudication by
    GAO of the merits of the protest, as . . . such a[n] adjudication only occurs in a
    formal written decision issued by the Office in the name of the General Counsel.
    GAO does not and cannot impose binding arbitration in its outcome
    prediction; instead, the success of outcome prediction depends on voluntary action
    by the party who is advised that it is not likely to prevail. In order for outcome
    prediction to be a success, we ask that the agency commit to give serious
    consideration to taking corrective action in the event I advise that a sustain is
    likely, and [that the] protesters commit to give serious consideration to
    withdrawing the protest if I advise that a deny is likely.
    
    Id.
     Although Northrop’s counsel indicated a “strong preference” for a written decision, 
    id. at 76761
    , counsel for Lockheed and the Air Force were amenable to participating in an outcome
    prediction conference, 
    id. at 76759, 76764
    .8 Accordingly, the GAO attorney conducted the
    conference at noon on January 15, 2015, 
    id. at 76719-34
    , fourteen days before the GAO’s written
    decision was due, 
    id. at 76751
    .
    As reflected in handwritten notes taken by Air Force personnel during the outcome
    prediction conference, the GAO attorney advised the participants that she had reached a decision,
    that she had consulted with her supervisors, and that it was highly likely that her decision would
    be reflected in the GAO’s published decision if such a decision were necessary. 
    Id. at 76719, 76728, 76732
    . She then indicated that she would sustain the protests on only two grounds. 
    Id. at 76719-34
    .
    First, she stated that the record reflected that Raytheon’s CTE 1 was the [. . .] GaN HPA
    [. . .], not just the GaN HPA and [. . .], and that Raytheon’s [. . .], as redesigned with the
    circulator [. . .], was never tested. 
    Id. at 76720
     (“Record supports CTE is [. . .] and not just GaN
    HPA, which is un-tested as changed in [Raytheon’s] proposal. Untested & unevaluated as
    impact of change on performance.”), 76723 (“CTE #1 is [. . .], not just GaN HPA and [. . .].”),
    76726 (“Definition is to test in relevant enviro[nment] . . . . Names should be used consistently,
    clearly list CT vs CTE. TRA report – CT if sys[tem] depends on an element. . . . CTE in
    question is the [. . .], not just a portion . . . . [Raytheon] changed the [. . .] since last tested at
    TRL-6. GaN & [. . .] is not the only portion of the CTE as defined in the TRA Report; they may
    be novel elements, but excludes the [. . .] in the [. . .]. Did not assess how change would affect
    8
    Although the GAO attorney invited counsel for Raytheon to the outcome prediction
    conference, she indicated that the GAO would only consider the views of Northrop, Lockheed,
    and the Air Force in determining “whether to proceed with outcome prediction.” AR 76751.
    -16-
    overall performance.”), 76729 (“[Air Force] erred in [Raytheon] TR/LRU untested [change]
    ([. . .]). [Air Force] . . . did not test design [change is] unreasonable. . . . [. . .], not portion of
    [. . .].”), 76732 (“Untested design change that cannot be assessed @ TRL6. Design change was
    to CTE. . . . CTE in question is [. . .], not limited to a portion of [. . .]. . . . Remainder of [. . .]
    need to be part of the CTE.”). Accordingly, she opined that the Air Force erred in concluding
    that Raytheon’s CTE 1 was at TRL 6. 
    Id. at 76720, 76733
    .
    Second, the GAO attorney indicated that the record reflected that the Air Force changed
    its understanding regarding the allowability of future IR&D costs, but never advised Northrop of
    its changed understanding. 
    Id. at 76721
     (“Testimony shows understanding changed at time [final
    proposal revisions] were submitted. . . . Failing to inform [Northrop] of change in future IR&D
    use.”), 76725 (“Future [IR&D] was not allowable at the time of ENs. The Agency reversed its
    decision after discussions with [Raytheon] concerning the use of future [IR&D] and failed to
    inform [Northrop] of its reversal.”), 76727 (“[D]id not express Agenc[y’s] revised understanding
    of IR&D. . . . [Air Force] reversed stance on allowability of IR&D after [Raytheon] response.
    Failed to inform [Northrop.]”), 76730 (“[Air Force] failed to inform [Northrop] of change.”),
    76733 (“Never informed [Northrop] of reversal.”). She therefore opined that the Air Force’s
    discussions with Northrop were misleading and unequal. 
    Id. at 76721, 76723, 76727, 76733
    .
    In light of her anticipated resolution of the protests, the GAO attorney recommended that
    the Air Force re-evaluate the TRL of Raytheon’s CTE 1 (reopening technical discussions with all
    three contractors if necessary), reopen cost/price discussions with all three contractors to explain
    its current view of the allowability of IR&D costs, and permit the submission of new final
    proposal revisions. 
    Id. at 76722, 76724-25, 76727, 76731, 76734
    . She then requested that the
    Air Force respond to her recommendations by 3:00 p.m. on the following day. 
    Id. at 76722-23, 76725-26, 76728, 76732
    .
    The Air Force complied with the GAO attorney’s request. See 
    id. at 76735
     (containing
    the Air Force’s response); Mot. Strike Ex. 1 (reflecting that the Air Force responded to the GAO
    via electronic mail at 10:43 a.m. on January 16, 2015). In a January 16, 2015 letter that was also
    provided to counsel for Raytheon, Northrop, and Lockheed via electronic mail, the Air Force
    advised the GAO attorney that it had decided to take corrective action:
    In response to the Outcome Prediction session, and in accordance with guidance
    from your office, the Air Force has decided to take corrective action. The Air
    Force intends to reopen discussions concerning the technical evaluation of
    Raytheon’s Technology Readiness Level in accordance with Section M, Paragraph
    2.4.1.3 of the [solicitation]. In addition, the Air Force intends to reopen
    discussions with all offerors to clarify the allowability of Independent Research
    and Development (IR&D) as it relates to the cost/price evaluation. The Air Force
    reserves the right to take any other corrective action it deems appropriate.
    -17-
    AR 76735. Given this proposed corrective action, the Air Force requested that the GAO dismiss
    Northrop’s and Lockheed’s protests as moot. 
    Id.
     The GAO did so on January 21, 2015. 
    Id. at 76736-73
    .
    G. The Current Protest
    Two days later, Raytheon submitted to the court, pursuant to Appendix C of the Rules of
    the United States Court of Federal Claims (“RCFC”), a notice that it intended to file a protest
    challenging the need for, and scope of, the corrective action proposed by the Air Force.9 Mot.
    Strike Ex. 2 at 3. That same morning, Raytheon provided the identical prefiling notice to counsel
    for the United States, the Air Force, Northrop, and Lockheed. 
    Id. at 1-4
    . In its prefiling notice,
    Raytheon alleged that the Air Force proposed its corrective action “in response to a flawed
    Outcome Prediction announcement” by the GAO in connection with the protests lodged by
    Northrop and Lockheed. 
    Id. at 1
    . Raytheon also indicated that it intended to file its protest on
    January 26, 2015. 
    Id. at 2
    .
    As it represented in its prefiling notice, Raytheon filed a protest in this court on January
    26, 2015, challenging the Air Force’s decision to take corrective action in response to the
    outcome prediction statement made by the GAO attorney. Compl. ¶ 1. In its first claim for
    relief, Raytheon contends that the Air Force’s decision to take corrective action with respect to
    the TRL of its CTE 1 was arbitrary, capricious, and unreasonable because the GAO’s
    determination was unreasonable. 
    Id. ¶¶ 82-152
    . It therefore requests that the court (1) declare
    that “the outcome prediction findings and recommendations of GAO, and the Air Force’s
    decision to take corrective action in response, are irrational and contrary to law;” (2) declare that
    the contract it was awarded is valid; and (3) issue an injunction preventing the Air Force from
    taking the proposed corrective action or “otherwise interfering with Raytheon commencing
    performance” of the contract. 
    Id. at 40
    . In the alternative, Raytheon requests that if the court
    determines that the independent review team’s assessment of its CTE 1 was not sufficiently
    documented, that the court declare the Air Force’s proposed corrective action to be arbitrary and
    capricious for being overly broad. 
    Id.
    In its second claim for relief, Raytheon alleges that the Air Force’s decision to take
    corrective action with respect to the allowability of IR&D costs was arbitrary, capricious, and
    unreasonable because the GAO’s determination was unreasonable. 
    Id. ¶¶ 153-255
    . It therefore
    requests that the court (1) declare that “the outcome prediction recommendation of GAO and the
    Air Force’s decision to take corrective action in response to that recommendation are irrational
    and contrary to law;” (2) declare that the contract it was awarded is valid; and (3) issue an
    injunction preventing the Air Force from taking the proposed corrective action or “otherwise
    interfering with Raytheon commencing performance” of the contract. 
    Id. at 75
    .
    9
    The procedural history in this section is derived from the parties’ filings.
    -18-
    Shortly after Raytheon filed its complaint, the court allowed Northrop and Lockheed to
    intervene as defendants. After defendant filed the administrative record, Northrop moved to
    supplement the record with a declaration from one of its employees and Raytheon moved to
    strike a purportedly improper document from the record. As the parties were briefing those two
    motions, they began to address the merits of Raytheon’s bid protest in cross-motions for
    judgment on the administrative record. All motions have been fully briefed and the court heard
    argument on April 29, 2015.
    II. THE SCOPE OF THE COURT’S REVIEW
    Underlying all of the parties’ motions is a critical threshold issue: What, precisely, is the
    scope of the court’s review?
    In this bid protest, Raytheon challenges the Air Force’s decision to take corrective action.
    The United States Court of Federal Claims (“Court of Federal Claims”) possesses jurisdiction to
    entertain such a challenge. 
    28 U.S.C. § 1491
    (b)(1) (2012); Sys. Application & Techs., Inc. v.
    United States, 
    691 F.3d 1374
    , 1380-82 (Fed. Cir. 2012). As in all bid protests, the court reviews
    a decision to take corrective action pursuant to the standards set forth in the Administrative
    Procedure Act (“APA”), see 
    28 U.S.C. § 1491
    (b)(4), and will set aside the decision if it is
    “‘arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law,’”
    Banknote Corp. of Am. v. United States, 
    365 F.3d 1345
    , 1350 (Fed. Cir. 2004) (quoting 
    5 U.S.C. § 706
    (2)(A) (2012)). Under this standard, the court may set aside the Air Force’s decision to
    take corrective action if, as Raytheon alleges, the Air Force’s decision lacked a rational basis or
    involved a violation of regulation or procedure. See Centech Grp., Inc. v. United States, 
    554 F.3d 1029
    , 1037 (Fed. Cir. 2009).
    Procurement officials “are entitled to exercise discretion upon a broad range of issues
    confronting them in the procurement process.” Impresa Construzioni Geom. Domenico Garufi v.
    United States, 
    238 F.3d 1324
    , 1332 (Fed. Cir. 2001) (internal quotation marks omitted). Thus,
    when a protestor challenges the procuring agency’s decision as irrational, the court’s review is
    “highly deferential” to the agency’s decision, Advanced Data Concepts, Inc. v. United States, 
    216 F.3d 1054
    , 1058 (Fed. Cir. 2000), and “[t]he court is not empowered to substitute its judgment
    for that of the agency,” Citizens to Preserve Overton Park, Inc. v. Volpe, 
    401 U.S. 402
    , 416
    (1971). “Accordingly, the test for reviewing courts is to determine whether the contracting
    agency provided a coherent and reasonable explanation of its exercise of discretion, and the
    disappointed bidder bears a heavy burden of showing that the award decision had no rational
    basis.” Impresa, 
    238 F.3d at 1332-33
     (citation and internal quotation marks omitted); accord
    Advanced Data Concepts, 
    216 F.3d at 1058
     (“The arbitrary and capricious standard . . . requires a
    reviewing court to sustain an agency action evincing rational reasoning and consideration of
    relevant factors.”). When a protestor claims that the procuring agency’s decision violates a
    statute, regulation, or procedure, it must show that the violation was “clear and prejudicial.”
    Impresa, 
    238 F.3d at 1333
     (internal quotation marks omitted).
    -19-
    In determining “whether the contracting agency provided a coherent and reasonable
    explanation” of its decision, Impresa, 
    238 F.3d at 1332-33
     (internal quotation marks omitted), a
    court may only consider the grounds for the decision articulated by the agency, Burlington Truck
    Lines, Inc. v. United States, 
    371 U.S. 156
    , 168-69 (1962); SEC v. Chenery Corp., 
    332 U.S. 194
    ,
    196 (1947). The court cannot “supply a reasoned basis for the agency’s action that the agency
    itself has not given . . . .” Bowman Transp., Inc. v. Ark.-Best Freight Sys., Inc., 
    419 U.S. 281
    ,
    285-86 (1974). However, it can “uphold a decision of less than ideal clarity if the agency’s path
    may reasonably be discerned.” 
    Id. at 286
    .
    The Air Force, in its January 16, 2015 notice of corrective action, articulated the
    following rationale for taking corrective action: “In response to the Outcome Prediction session,
    and in accordance with guidance from [the GAO], the Air Force has decided to take corrective
    action.” AR 76735. In other words, the Air Force expressly represented that the GAO’s
    “guidance” during the outcome prediction conference was the basis for its decision to take
    corrective action.
    In general, when a court considers the propriety of a procuring agency’s decision to take
    corrective action recommended by the GAO, it reviews whether the GAO’s recommendation was
    itself rational. See Turner Constr. Co. v. United States, 
    645 F.3d 1377
    , 1383 (Fed. Cir. 2011)
    (stating that “an agency’s decision to follow a GAO recommendation . . . lacks a rational basis if
    it implements a GAO recommendation that is itself irrational”); Honeywell, Inc. v. United States,
    
    870 F.2d 644
    , 648 (Fed. Cir. 1989) (“[A] procurement agency’s decision to follow the
    Comptroller General’s recommendation, even though that recommendation differed from the
    contracting officer’s initial decision, was proper unless the Comptroller General’s decision itself
    was irrational.”); CBY Design Builders v. United States, 
    105 Fed. Cl. 303
    , 339 (2012) (“When
    the relevant procurement official . . . decides to adopt the views of the GAO after a protest has
    been heard by that body, this agency decision is not considered inherently unreasonable (for
    departing from the agency’s previous position) nor invulnerable (under the shield of GAO
    authority), but is instead measured by the rationality of the recommendation it follows.”). As the
    court explained in Systems Application & Technologies, Inc. v. United States, the GAO’s
    recommendation need not be final or formal:
    [T]he court has a broad mandate to entertain bid protests and review government
    procurement decisions. If a procuring agency takes an action that is challenged in
    this court, this court has the responsibility to examine the basis for the agency’s
    action, regardless of what that basis might be. In other words, when determining
    the propriety of a procuring agency’s decision to take corrective action, the court
    may review the rationality of, as appropriate, the underlying formal GAO decision
    containing a recommendation that the agency take such action or the underlying
    informal suggestion by the GAO, or any other entity or individual, that such action
    might be proper.
    -20-
    
    100 Fed. Cl. 687
    , 713 (2011), aff’d, 691 F.3d at 1374.10 In other words, it makes no difference
    whether the GAO’s recommendation was made in a written decision sustaining a protest, in an
    electronic-mail message addressing the merits of a protest, or during an outcome prediction
    conference.11 Indeed, the means by which the GAO recommends corrective action are irrelevant
    because the GAO’s recommendations, in any form, are never binding on a procuring agency. See
    
    31 U.S.C. § 3554
    (b)(3) (2012) (indicating that a procuring agency must inform the GAO when it
    decides not to take the GAO’s recommended corrective action); AR 76751 (“GAO does not and
    cannot impose binding arbitration in its outcome prediction; instead, the success of outcome
    prediction depends on voluntary action by the party who is advised that it is not likely to
    prevail.”). Accordingly, so long as a procuring agency indicates that its decision to take
    10
    The Federal Circuit affirmed the court’s jurisdictional, standing, and ripeness rulings.
    Sys. Application & Techs., 691 F.3d at 1380-85. The court’s merits rulings were not appealed.
    Id. at 1380.
    11
    There appear to be three published decisions from this court that concern bid protests
    in which the protestor challenged corrective action proposed by the procuring agency in response
    to a GAO attorney’s statements during an outcome prediction conference. See Metro. Van &
    Storage, Inc. v. United States, 
    92 Fed. Cl. 232
     (2010); Carahsoft Tech. Corp. v. United States, 
    86 Fed. Cl. 325
     (2009); ManTech Telecomms. & Info. Sys. Corp. v. United States, 
    49 Fed. Cl. 57
    (2001), aff’d per curiam, 30 F. App’x 995 (Fed. Cir. 2002). In Metropolitan Van & Storage, the
    court concluded that contrary to the protestor’s contentions, some of the protestor’s allegations
    were mooted by the corrective action taken by the procuring agency in response to a GAO
    outcome prediction conference because the corrective action addressed the improprieties
    identified by the GAO. 92 Fed. Cl. at 241, 249-55. In Carahsoft Technology, the protestor
    challenged the breadth of the corrective action taken by the procuring agency in response to the
    GAO’s outcome prediction statement, requiring the court to analyze whether the corrective
    action was appropriately tailored to remedy the impropriety identified by the GAO. 86 Fed. Cl.
    at 344-46. And in ManTech Telecommunications, the GAO recommended certain corrective
    action during an outcome prediction conference, but the procuring agency opted to propose
    different corrective action; in considering the protestor’s challenge to the corrective action
    proposed by the agency, the court reviewed the purported improprieties to determine whether
    they would be remedied by the proposed corrective action. 86 Fed. Cl. at 62-63, 65-80. In none
    of these cases did the protestor challenge the need for, or decision to take, corrective action.
    Rather, the protestors’ focus was on whether the procuring agency’s corrective action remedied
    the improprieties identified by the GAO during the outcome prediction conference. Accord
    Consol. Eng’g Servs., Inc. v. United States, 
    64 Fed. Cl. 617
    , 627-28 (2005) (noting that one of
    the contentions raised by the protestor in arguing that the procuring agency did not conduct
    meaningful discussions was that the agency should have conducted broader discussions upon
    taking corrective action in response to a GAO outcome prediction conference). Thus, the
    reviewing courts in those bid protests had no need to review whether the GAO’s identification of
    improprieties was reasonable or rational.
    -21-
    corrective action was based on a recommendation by the GAO, the court may examine the
    rationality of the GAO’s decision.
    In short, to the extent that the Air Force’s January 16, 2015 notice of corrective action
    contains the sole justification for the Air Force’s decision to take corrective action, the court is
    entitled to review the rationality of the GAO’s recommendation that formed the basis of the Air
    Force’s decision. Of course, as addressed below, the Air Force contends that another document
    that it included in the administrative record–a January 26, 2015 “Memorandum for
    Record”–provides its independent rationale for taking corrective action. If the court concludes,
    over Raytheon’s objections, that the memorandum is properly before the court, then the court
    would revise the scope of its review of the Air Force’s decision to take corrective action
    accordingly.
    III. THE ADMINISTRATIVE RECORD
    In addition to determining which decision(s) should be the focus of its review, the court
    must determine what evidence it may examine to assess the propriety of those decisions. There
    can be no dispute that in a bid protest, the focal point of the court’s review of a procuring
    agency’s decision is the administrative record. Camp v. Pitts, 
    411 U.S. 138
    , 142 (1973) (per
    curiam); Axiom Res. Mgmt., Inc. v. United States, 
    564 F.3d 1374
    , 1381 (Fed. Cir. 2009). An
    administrative record typically contains the materials developed and considered by an agency in
    making its decision. See Camp, 
    411 U.S. at 142-43
     (remarking that an agency’s finding must be
    “sustainable on the administrative record made” by the agency at the time of its decision);
    Citizens to Preserve Overton Park, 
    401 U.S. at 420
     (noting that the trial court’s review of the
    decision of the head of the agency was “to be based on the full administrative record that was
    before the Secretary at the time he made his decision”); Smith v. United States, 
    114 Fed. Cl. 691
    ,
    694 (2014) (“The administrative record to be considered by a reviewing court shall include all
    the materials compiled by the agency before it made its decision.”); CRAssociates, Inc. v. United
    States, 
    95 Fed. Cl. 357
    , 377 (2010) (“[A]n essential premise of [APA] review presupposes that
    the agency will establish its rationale at, or prior to, the time of its decision–not after.”); Arch
    Chems., Inc. v. United States, 
    64 Fed. Cl. 380
    , 385 (2005) (“The administrative record is
    supposed to reflect the information available to the decision maker at the time the challenged
    decisions were made . . . .”); Cubic Applications, Inc. v. United States, 
    37 Fed. Cl. 345
    , 349-50
    (1997) (“[T]he primary focus of the court’s review should be the materials that were before the
    agency when it made its final decision.”). The typical practice in bid protests is for the procuring
    agency to compile the relevant materials and certify that those materials constitute the record
    relating to the decision being challenged by the protestor; defendant then files those materials
    with the court as the administrative record. See RCFC 52.1(a); RCFC App. C, ¶¶ 21-24; Fla.
    Power & Light Co. v. Lorion, 
    470 U.S. 729
    , 743-44 (1985) (explaining that a court reviews an
    agency’s decision “based on the record the agency presents to the reviewing court” and that
    “[t]he APA specifically contemplates judicial review on the basis of the agency record compiled
    in the course of informal agency action”); Arch Chems., Inc., 64 Fed. Cl. at 385 (noting that the
    administrative record in a bid protest “is prepared by an agency after the decision has been made
    -22-
    in response to questions about the validity of the decision making process”). Here, both
    Northrop and Raytheon contend that the administrative record compiled by the Air Force and
    filed by defendant is not a complete and accurate collection of the materials relevant to the Air
    Force’s decision to take corrective action.
    A. Northrop’s Motion to Supplement the Administrative Record
    Northrop asserts that it cannot fully respond to the allegations advanced by Raytheon in
    its complaint based on the existing administrative record. As Northrop explains, Raytheon
    alleges that the evidence in the record before the GAO reflected that Northrop was not prejudiced
    by the purportedly misleading discussions, and that the GAO attorney’s implicit acceptance of
    that evidence as sufficient to demonstrate prejudice was improper. Northrop contends that
    although it made an adequate showing of prejudice before the GAO, it could have supplied the
    GAO with additional information describing the prejudice it suffered. Thus, noting that the court
    might conclude that its review would be aided by this additional information, Northrop moves to
    supplement the administrative record with a declaration from one of its employees. Both
    Raytheon and defendant oppose Northrop’s motion.
    In assessing the propriety of an agency’s decision, a court may allow supplementation of
    the administrative record “only if the existing record is insufficient to permit meaningful review
    consistent with the APA.” Axiom Res. Mgmt., 
    564 F.3d at 1381
    ; accord 
    id. at 1380
    (“[S]upplementation of the record should be limited to cases in which the omission of extra-
    record evidence precludes effective judicial review.” (internal quotation marks omitted)).
    Northrop argues that the information contained in the proffered declaration is necessary for
    meaningful judicial review, asserting that the Court of Federal Claims has repeatedly held that
    supplementation of the administrative record may be warranted when there is a dispute
    concerning the prejudice suffered by an unsuccessful offeror resulting from misleading
    discussions. However, in every decision cited by Northrop, the party seeking to supplement the
    administrative record with evidence of prejudice was the party protesting the procuring agency’s
    decision. See Sims v. United States, 
    112 Fed. Cl. 808
    , 815 (2013) (permitting a protestor to
    supplement the administrative record with a declaration supporting her allegation of prejudice);
    State of N.C. Bus. Enters. Program v. United States, 
    110 Fed. Cl. 354
    , 365 (2013) (allowing a
    protestor to supplement the administrative record with the portion of an affidavit containing
    evidence of its competitive injury); East West, Inc. v. United States, 
    100 Fed. Cl. 53
    , 57-58
    (2011) (explaining that a declaration containing evidence of the prejudice suffered by the
    protestor may be considered by the court as part of the court’s record, not the administrative
    record); Hunt Bldg. Co. v. United States, 
    61 Fed. Cl. 243
    , 272 (2004) (permitting a protestor to
    supplement the administrative record with a declaration supporting its allegation of prejudice);
    Gentex Corp. v. United States, 
    58 Fed. Cl. 634
    , 649 (2003) (holding that supplementation of the
    administrative record with an affidavit containing a description of the prejudice suffered by the
    protestor was appropriate). Northrop is not the protestor in this bid protest. Consequently, the
    decisions relied upon by Northrop are inapposite.
    -23-
    In this bid protest, Raytheon challenges the decision of the Air Force to take corrective
    action, arguing that the decision was based on unreasonable findings and recommendations made
    by the GAO attorney during the outcome prediction conference. As previously explained, to the
    extent that the Air Force’s decision to take corrective action was based on the GAO attorney’s
    outcome prediction statement, the court’s task is to evaluate whether that statement was
    reasonable in light of the record submitted to the GAO. See Turner Constr., 
    645 F.3d at 1383
    ;
    Honeywell, 
    870 F.2d at 648
    ; Sys. Application & Techs., 100 Fed. Cl. at 712-13. Because the
    declaration proffered by Northrop was not in the record submitted to the GAO, it is irrelevant to
    the court’s examination of the reasonableness of the GAO’s attorney’s statement.
    Northrop seeks to avoid this result by arguing that it was impossible for it to provide the
    information contained in the proffered declaration to the GAO due to Raytheon’s proposed
    redaction of material pursuant to the GAO protective order and the timing of Raytheon’s
    prejudice arguments before the GAO. But even if Northrop’s representations are accurate and it
    was precluded from submitting additional information regarding prejudice to the GAO, it was not
    harmed by the omission of that information from the record before the GAO. Indeed, as
    Northrop acknowledges, given that the GAO attorney advised that she would likely sustain
    Northrop’s protest with respect to its allegation of misleading discussions, it appears that
    Northrop successfully established prejudice without the GAO considering the additional
    information.
    In sum, supplementation of the administrative record with the declaration proffered by
    Northrop is not necessary for meaningful judicial review. The court therefore denies Northrop’s
    motion.
    B. Raytheon’s Motion to Strike
    Unlike Northrop, Raytheon does not seek to supplement the administrative record with
    additional information. Rather, Raytheon seeks to remove a document from the administrative
    record filed by defendant. Specifically, Raytheon contends that a January 26, 2015
    “Memorandum for Record” that purports to address the Air Force’s decision to take corrective
    action does not belong in the administrative record because it was not prepared
    contemporaneously with the Air Force’s decision to take corrective action, and therefore
    constitutes a post-hoc rationalization of the Air Force’s decision. Defendant, Northrop, and
    Lockheed all oppose Raytheon’s motion.
    1. The Legal Basis for Raytheon’s Motion to Strike
    As a threshold matter, the court must address the contention of defendant, Northrop, and
    Lockheed that Raytheon did not identify an appropriate legal basis for its motion to strike. All
    three opposing parties assert that motions to strike are governed by RCFC 12(f), and that the
    motion filed by Raytheon does not fall within that rule’s parameters. The court disagrees that
    Raytheon is invoking RCFC 12(f) with its motion.
    -24-
    RCFC 12(f) provides that “[t]he court may strike from a pleading an insufficient defense
    or any redundant, immaterial, impertinent, or scandalous matter.” Only the following
    documents, whether filed by the original parties to the suit or by third parties, are considered to
    be pleadings: complaints, answers, replies to offsets or pleas of fraud contained in an answer,
    and replies to an answer. RCFC 7(a). An administrative record is not a pleading. Id.; see also
    Mathews v. Weber, 
    423 U.S. 261
    , 264 (1976) (noting that the court could “consider only the
    pleadings and administrative record”); Sherwin v. United States, 
    436 F.2d 992
    , 968 (Ct. Cl.
    1971) (indicating that it reviewed “the pleadings, administrative record, and briefs”); Three S
    Consulting v. United States, 
    104 Fed. Cl. 510
    , 514 (2012) (stating that the facts were derived
    “from the pleadings and administrative record”). In fact, the rule that governs administrative
    records in this court–RCFC 52.1–is not contained in the title of the RCFC devoted to pleadings
    and motions, but is instead located in the title of the RCFC regarding trials. Thus, there can be
    no doubt that an administrative record is not a pleading, and that therefore an administrative
    record is not an appropriate target of an RCFC 12(f) motion to strike.
    Raytheon, a sophisticated party represented by experienced counsel, must know that
    RCFC 12(f) cannot be invoked to strike a document from an administrative record.12 Indeed, at
    no point in its motion does it mention RCFC 12(f). Instead, Raytheon framed its motion as an
    attempt to ensure that the administrative record was an accurate representation of the Air Force’s
    decision-making process. As it explains in its reply brief, a motion to strike a document from the
    administrative record is the flip side of a motion to supplement the administrative record; the
    ultimate result sought by the proponents of both motions is an evidentiary record upon which a
    court can conduct an effective review of an agency’s action.
    Raytheon’s characterization of its motion is consistent with the decision of the Federal
    Circuit in Axiom Resource Management. In that case, the Court of Federal Claims allowed the
    parties to freely supplement the administrative record with the understanding that it would only
    rely on the relevant supplementary material. 
    564 F.3d at 1379
    . The Federal Circuit rejected this
    approach, holding that the administrative record should be “supplemented only if the existing
    record is insufficient to permit meaningful review consistent with the APA.” 
    Id. at 1381
    . If the
    Court of Federal Claims is charged with ensuring that an administrative record is not
    supplemented with improper material, then it follows that the court is also responsible for
    ensuring that an administrative record does not itself contain improper material. See also Arch
    Chems., 64 Fed. Cl. at 385 (“Thus, the Court must focus on the timing of the decisions at issue to
    determine if the administrative record assembled by an agency needs to be supplemented or
    12
    Defendant is also represented by experienced counsel–the United States Department of
    Justice. It therefore bears noting that notwithstanding the plain language of RCFC 12(f),
    defendant regularly moves to strike documents in bid protests that are not pleadings. See, e.g.,
    Kvichak Marine Indus., Inc. v. United States, 
    118 Fed. Cl. 385
    , 387 (2014); Command Mgmt.
    Servs., Inc. v. United States, 
    111 Fed. Cl. 279
    , 285 (2013); CW Gov’t Travel, Inc. v. United
    States, 
    110 Fed. Cl. 462
    , 478 (2013); State of N.C. Bus. Enters. Program, 110 Fed. Cl. at 361.
    -25-
    pared back.”); Cubic Applications, Inc. v. United States, 
    37 Fed. Cl. 339
    , 341, 343-44 (1997)
    (considering, and ultimately denying, the plaintiff’s motion to “limit” the administrative record).
    Raytheon’s characterization of its motion also comports with the manner in which the
    Court of Federal Claims resolves the merits of a bid protest. Typically, the parties’ substantive
    contentions regarding the merits of a bid protest are advanced in motions for judgment on the
    administrative record filed pursuant to RCFC 52.1(c). Because the court makes “factual findings
    . . . from the record evidence” in ruling on such motions, judgment on the administrative record
    “is properly understood as intending to provide for an expedited trial on the administrative
    record.” Bannum, Inc. v. United States, 
    404 F.3d 1346
    , 1356 (Fed. Cir. 2005). There can be no
    dispute that parties trying a case in the absence of an administrative record may move both for
    the admission of relevant evidence and for the exclusion of irrelevant or otherwise inappropriate
    evidence. See Fed. R. Evid. 402 (noting that relevant evidence is generally admissible and
    irrelevant evidence is not admissible); Fed. R. Evid. 403 (“The court may exclude relevant
    evidence if its probative value is substantially outweighed by a danger of one or more of the
    following: unfair prejudice, confusing the issues, misleading the jury, undue delay, wasting time,
    or needlessly presenting cumulative evidence.”). The court discerns no reason why the parties
    trying a case on an administrative record should not be afforded the same opportunities.
    Therefore, it concludes that there is an adequate legal basis for Raytheon’s motion to strike.
    2. The Proper Standard for Reviewing Raytheon’s Motion to Strike
    Implicitly recognizing that there might be a legal basis for Raytheon’s motion, defendant
    and Northrop contend that Raytheon did not recognize, or attempt to meet, its burden to establish
    that the document at issue should be stricken from the administrative record. Problematically,
    however, both defendant and Northrop rely on decisions addressing the standard for reviewing
    motions to strike under RCFC 12(f). See Cal. Indus. Facilities Res., Inc. v. United States, 
    104 Fed. Cl. 617
    , 618 (2012) (setting forth the standard for reviewing a motion to strike pursuant to
    RCFC 12(f) in a case where the defendant sought to strike an exhibit attached to a complaint);
    Waltner v. United States, 
    98 Fed. Cl. 737
    , 766-67 (2011) (setting forth the standard for reviewing
    a motion to strike pursuant to RCFC 12(f) in a case where the plaintiffs sought to strike
    information contained within, and exhibits attached to, the defendant’s motion to dismiss);
    Fisherman’s Harvest, Inc. v. United States, 
    74 Fed. Cl. 681
    , 689-90 (2006) (setting forth the
    standard for reviewing a motion to strike pursuant to RCFC 12(f) in a case where the plaintiffs
    sought to strike another party’s motion); Impresa Construzioni Geom. Domenico Garufi v.
    United States, 
    61 Fed. Cl. 175
    , 177 (2004) (noting that the plaintiff’s motion to strike a statement
    contained in one of the defendant’s briefs was untimely under RCFC 12(f)), appeal voluntarily
    dismissed, 125 F. App’x 310 (Fed. Cir. 2005). These decisions, and the standards described
    therein, are therefore inapplicable to Raytheon’s motion.
    The proper standard of review for a motion to strike a document from an administrative
    record is the mirror image of the one that applies to motions to supplement the administrative
    record–the court will strike a document from an administrative record if its inclusion in the
    -26-
    record would preclude effective, meaningful judicial review. See Axiom Res. Mgmt., 
    564 F.3d at 1380-81
    . Given the importance of having a properly constituted administrative record to
    permit meaningful judicial review, common sense demands that the court use the same standard
    for motions to supplement the administrative record and motions to remove documents from the
    administrative record. After all, merely because the government assembles the administrative
    record does not mean that the record is inviolate and not subject to the court’s scrutiny.
    In applying this standard to Raytheon’s motion, the court does not ignore the presumption
    of regularity that attaches to the actions of government agencies. See U.S. Postal Serv. v.
    Gregory, 
    534 U.S. 1
    , 10 (2001) (noting that “a presumption of regularity attaches to the actions
    of Government agencies”); Schism v. United States, 
    316 F.3d 1259
    , 1302 (Fed. Cir. 2002) (en
    banc) (“This presumption of regularity is the supposition that public officers perform their duties
    correctly, fairly, in good faith, and in accordance with law and governing regulations, and is valid
    and binding unless ‘well-nigh irrefragable proof rebuts or overcomes it.’” (citation omitted)
    (quoting Alaska Airlines, Inc. v. Johnson, 
    8 F.3d 791
    , 795 (Fed. Cir. 1993))); Am-Pro Protective
    Agency, Inc. v. United States, 
    281 F.3d 1234
    , 1239 (Fed. Cir. 2002) (noting “the strong
    presumption that government contract officials exercise their duties in good faith”). Indeed, the
    court presumes that the Air Force compiled the administrative record correctly and in good faith.
    This presumption, however, can be overcome if Raytheon can clearly demonstrate that the Air
    Force incorrectly included the document at issue in the administrative record.13
    3. The Merits of Raytheon’s Motion to Strike
    Raytheon contends that the January 26, 2015 memorandum concerning the Air Force’s
    decision to take corrective action should be removed from the administrative record because it
    was not prepared contemporaneously with the Air Force’s decision to take corrective action and
    therefore constitutes a post-hoc rationalization of the Air Force’s decision. As reflected in the
    administrative record, the GAO attorney conducted the outcome prediction conference at noon
    on January 15, 2015. The following day at 10:43 a.m., the Air Force sent a letter to the GAO
    indicating its intent to take corrective action. On January 23, 2015, Raytheon submitted a notice
    to the court and the other parties of its intent to file a bid protest three days later to challenge the
    Air Force’s decision to take corrective action. Raytheon filed its protest on January 26, 2015,
    and on the same date, the Air Force issued a memorandum regarding its decision to take
    corrective action.14 Thus, the memorandum purporting to explain the reasons for the Air Force’s
    decision to take corrective action was issued ten days after the Air Force indicated its intent to
    13
    A finding of bad faith is not required to overcome the presumption of regularity if one
    or more of the other elements of regularity is implicated.
    14
    The memorandum is dated January 26, 2015. There is no evidence in the
    administrative record that the Air Force began to prepare the memorandum prior to January 26,
    2015. Moreover, defendant did not offer any evidence, such as a declaration from an Air Force
    official, indicating when the Air Force began to prepare the memorandum.
    -27-
    take corrective action. From Raytheon’s perspective, a ten-day delay is too long for the
    memorandum to be considered a contemporaneous justification for the Air Force’s decision to
    take corrective action.
    As noted above, the Court of Federal Claims reviews a decision of a procuring agency
    based on the record that was before the agency at the time that it made its decision. The court in
    Arch Chemicals explained this requirement in more detail:
    The administrative record is supposed to reflect the information available to the
    decision maker at the time the challenged decisions were made, as well as the
    rationale for why the agency acted as it did at the time that it did. Thus, the Court
    must focus on the timing of the decisions at issue to determine if the
    administrative record assembled by an agency needs to be supplemented or pared
    back. . . . Documents that pre-date or are contemporaneous with the relevant
    decisions may appropriately be a part of the Administrative Record. Those
    created after-the-fact are suspect, as courts reviewing an administrative record
    recognize that they must reject “post hoc rationalizations” as a basis for the
    agency action.
    64 Fed. Cl. at 385-86 (citations omitted). The Air Force did not issue its memorandum justifying
    its decision to take corrective action until ten days after it indicated its intent to take corrective
    action and three days after it learned that Raytheon would be protesting its proposed corrective
    action. Nevertheless, defendant, Northrop, and Lockheed contend that the memorandum was
    prepared contemporaneously with the Air Force’s decision and should therefore be included in
    the administrative record.
    The contentions of the parties opposing Raytheon’s motion can be summarized as
    follows:15 The Air Force prepared the January 26, 2015 memorandum to formally memorialize
    the information it acquired and considered in deciding to take corrective action. The
    memorandum accordingly does not contain a post-hoc rationalization of the Air Force’s decision.
    The mere ten-day delay between the decision to take corrective action and the memorandum
    containing the justification for the decision does not render the memorandum untimely or
    otherwise improper. In fact, there is no legal requirement that such a memorandum be completed
    prior to a procuring agency announcing its decision. Further, the information in the
    memorandum is consistent with the remainder of the administrative record. Moreover, because
    the Air Force did not prepare the memorandum while this litigation was pending, it could not
    have used the memorandum to invent a justification for its decision to take corrective action for
    the purposes of litigation. In sum, there is no reason to suspect that the memorandum does not
    accurately reflect the rationale for the Air Force’s decision. Nevertheless, any concerns regarding
    15
    Each party did not necessarily advance each contention. The court combined the
    parties’ arguments for convenience.
    -28-
    the memorandum should be addressed by giving it the necessary weight, rather than by striking it
    from the administrative record.
    The court does not find merit in these arguments. First, a ten-day gap between a decision
    and the issuance of a document justifying the decision is more than a de minimis delay. The Air
    Force presumably had a reason for deciding to take corrective action in advance of announcing
    its decision. It should have been able to memorialize that rationale at the time the decision was
    reached, or immediately thereafter.
    Second, by definition, a post-hoc rationale is any rationale that departs from the rationale
    provided at the time the procuring agency made its decision. See CRAssociates, 95 Fed. Cl. at
    377 (remarking that a post-hoc rationale can take the form of a new explanation for a decision or
    a previously undocumented rationale); see also id. at 376 n.15 (distinguishing between post-hoc
    rationalizations and “further explanations”); D & S Consultants, Inc. v. United States, 
    101 Fed. Cl. 23
    , 35-36 (2011) (same). When the Air Force, in its January 16, 2015 letter, notified the
    GAO and the contractors that it intended to take corrective action, it provided: “In response to
    the Outcome Prediction session, and in accordance with guidance from your office, the Air Force
    has decided to take corrective action.”16 AR 76735. In contrast, the Air Force provided the
    following justifications for taking corrective action in its January 26, 2015 memorandum: (1) it
    “concede[d] that its documentation included references to the [TRLRU], which could create
    ambiguity as to the TRL assessment team’s conclusions”; (2) it “concede[d] that after receiving
    Raytheon’s response to the subject EN, it did not reply to Northrop Grumman reiterating the
    present legal treatment of IR&D”; (3) it wanted “to ensure [that] all offerors [had] a complete
    understanding of [its] actions”; and (4) it wanted “to provide more robust documentation
    supporting [its] decision” to award the contract to Raytheon. 
    Id. at 76714-16
    . The justifications
    contained in the memorandum go beyond the rationale that the Air Force described in its earlier
    letter. The most reasonable reading of the Air Force’s January 16, 2015 letter is that the Air
    Force recognized that the GAO would sustain the protests lodged by Northrop and Lockheed and
    that, to avoid that result, it decided to take corrective action to address the GAO’s concerns
    (regardless of whether it agreed with the GAO that the relevant protest grounds were valid17).
    16
    Although this justification lacks detail, it is sufficient to convey the basis of the Air
    Force’s decision. See Camp, 
    411 U.S. at 143
     (“[I]n the present case there was contemporaneous
    explanation of the agency decision. The explanation may have been curt, but it surely indicated
    the determinative reason for the final action taken[.] . . . The validity of the [agency’s] action
    must, therefore, stand or fall on the propriety of that finding, judged, of course, by the appropriate
    standard of review.”).
    17
    The Air Force was entitled to take corrective action upon hearing the GAO attorney’s
    outcome prediction statement, even after vigorously defending its position before the GAO. See
    John Reiner & Co. v. United States, 
    325 F.2d 438
    , 442 (Ct. Cl. 1963) (“It would be entirely
    justifiable for the contracting officer to follow the general policy of acceding to the views of the
    [GAO] . . . even though he had another position on the particular issue of legality or propriety.”).
    -29-
    However, in its January 26, 2015 memorandum, the Air Force expressly conceded the validity of
    the relevant protest grounds, posited that the contractors did not completely understand its
    actions, and asserted that the documentation of its award decision was not sufficiently robust.
    None of these reasons was contained in its original letter.18 Even if they were not new rationales
    from the Air Force’s point of view, they certainly constituted previously undocumented
    rationales.
    Third, while there may be no statute or regulation requiring an agency to document its
    reasons for taking corrective action at the time it makes its decision, both binding and nonbinding
    precedent indicate that a court should limit its review of an agency’s decision to the materials
    that were before the agency when it made its decision. See Camp, 
    411 U.S. at 142-43
    ; Citizens
    to Preserve Overton Park, 
    401 U.S. at 420
    ; Smith, 114 Fed. Cl. at 694; CRAssociates, 95 Fed. Cl.
    at 377; Arch Chems., 64 Fed. Cl. at 385; Cubic Applications, 37 Fed. Cl. at 349-50. It therefore
    follows that a procuring agency should document the reasons for its decision to take corrective
    action at the time that it makes the decision.
    Finally, the fact that the Air Force issued its memorandum before Raytheon filed this bid
    protest does not preclude an inference that the Air Force prepared the memorandum for the
    purposes of this litigation. The Air Force had more than enough time to finalize the
    memorandum before it received notice that Raytheon intended to file a bid protest in the Court of
    Federal Claims, but it did not do so until three days after it received that notice. Raytheon’s
    prefiling notice clearly indicated that Raytheon intended to protest the Air Force’s proposed
    corrective action, and based on the extensive proceedings before the GAO and the GAO
    attorney’s statement during the outcome prediction conference, the Air Force, Northrop, and
    Lockheed would have known the precise nature of Raytheon’s protest. Thus, it is not
    unreasonable to suspect that the memorandum was prepared in anticipation of litigation.
    In sum, the court concludes that consideration of the Air Force’s January 26, 2015
    memorandum would not be conducive to meaningful, effective judicial review. Accordingly,
    two courses of action are available to the court. First, the court can strike the memorandum from
    the administrative record pursuant to its inherent authority to ensure that the administrative
    record is properly constituted. Cf. Axiom Res. Mgmt., 
    564 F.3d at 1379-81
     (rejecting the trial
    court’s process of allowing a generous supplementation of the administrative record and then
    deciding after supplementation what materials were actually relevant to the bid protest). Second,
    the court can leave the memorandum in the administrative record and assign it no weight. See
    Citizens to Preserve Overton Park, 
    401 U.S. at 420
     (allowing an agency to add newly prepared
    formal findings to a pre-existing administrative record, but noting that “[s]uch an explanation
    [would], to some extent, be a ‘post hoc rationalization’ and thus must be viewed critically”);
    18
    Indeed, given how succinctly the Air Force’s after-the-fact justifications for its
    decision to take corrective action can be summarized, it is baffling that the Air Force could not
    have included those justifications in its January 16, 2015 letter or in a separate document
    prepared that same day.
    -30-
    CRAssociates, 95 Fed. Cl. at 377 (remarking that there is no legal authority that “requires the
    court to give” a contracting officer’s statement of facts submitted during a GAO protest “any
    independent, let alone dispositive, weight”); Al Ghanim Combined Grp. Co. Gen. Trad. & Cont.
    W.L.L. v. United States, 
    56 Fed. Cl. 502
    , 508 (2003) (“The Supreme Court has made clear that
    post hoc rationalizations offered by the agency should be afforded limited importance in the
    court’s analysis.”); Cubic Applications, 37 Fed. Cl. at 343-44 (noting that the court had “a choice
    about the degree of relevance to assign to” postdecisional documents included in an
    administrative record). Based on the circumstances in this case, where the Air Force documented
    a justification for its decision to take corrective action ten days after it had made the decision and
    three days after learning that Raytheon intended to file this bid protest, the court will strike the
    memorandum from the administrative record. Raytheon’s motion is therefore granted.
    IV. THE PARTIES’ CROSS-MOTIONS FOR JUDGMENT ON THE
    ADMINISTRATIVE RECORD
    Having disposed of the parties’ procedural motions, the court shifts its attention to the
    parties’ cross-motions for judgment on the administrative record, which address the merits of
    Raytheon’s bid protest. As discussed above, because Raytheon challenges the Air Force’s
    decision to take corrective action in response to the outcome prediction statement made by the
    GAO attorney, the court is tasked with reviewing whether the recommendations encompassed
    within the GAO attorney’s statement were themselves rational. When reviewing the rationality
    of GAO recommendations that form the basis of the procuring agency’s decision to take
    corrective action, the court examines the original actions of the procuring agency that were
    challenged at the GAO. See Turner Constr., 
    645 F.3d at 1383
     (“Our task is to evaluate the
    rationality of the GAO decision. . . . When [the contracting officer’s evaluation of bids] is
    reasonable, neither a court nor the GAO may substitute its judgment for that of the agency.”).
    The court’s examination is highly deferential to the procuring agency due to the broad discretion
    that government officials have in procurement matters. 
    Id.
     If the court concludes that the
    challenged action was irrational for the reasons stated by the GAO, then it must find that the
    GAO’s recommendation to take corrective action was rational. 
    Id.
     Conversely, if the court
    concludes, contra the GAO, that the challenged action was rational, then it must find that the
    GAO’s recommendation to take corrective action was irrational. 
    Id.
     With this standard in mind,
    the court addresses Raytheon’s allegations.
    A. The Technical Evaluation of Raytheon’s Proposal
    Raytheon first challenges the Air Force’s decision to take corrective action with respect to
    the TRL of its CTE 1. The GAO attorney concluded that Raytheon’s CTE 1 was the [. . .] GaN
    HPA [. . .], and not just the GaN HPA and [. . .], and that Raytheon’s [. . .], as redesigned with
    the circulator [. . .], was never tested. She therefore opined that the Air Force erred in concluding
    that Raytheon’s CTE 1 was at TRL 6. Raytheon contends that the GAO attorney’s findings and
    conclusion were irrational, and that the Air Force properly assessed its CTE 1 as TRL 6.
    -31-
    1. Raytheon’s Pre-EMD CTE 1
    The administrative record reflects that during the pre-EMD period of the 3DELRR
    acquisition program, the independent review team identified Raytheon’s GaN HPA [. . .] as a
    CTE. In its Technology Readiness Assessment report, the team described the GaN HPA [. . .] as
    a “[. . .].” On its face, this description is confusing because it purports to define the GaN HPA
    [. . .] as including a single T/R module and as constituting an entire TRLRU, which is [. . .].
    However, for the purposes of this bid protest, whether it is more accurate to consider the GaN
    HPA [. . .] as a single T/R module or the entire TRLRU is unimportant, because the independent
    review team specified that its focus was not on the GaN HPA [. . .], but on what it considered to
    be the new and novel elements of the GaN HPA [. . .]: the GaN HPA and [. . .]. It concluded,
    upon reviewing the relevant test results, that both of the new and novel technologies included in
    the GaN HPA [. . .], as well as the GaN HPA [. . .] itself, were sufficiently mature to be assessed
    as TRL 6. In other words, they had been demonstrated in a relevant environment.
    2. Raytheon’s EMD Proposal
    Raytheon did not rest on its laurels after the pre-EMD period concluded. Because the
    EMD solicitation reflected that price would play a key role in the Air Force’s source selection
    decision, the contractors had a considerable incentive to propose the lowest price possible.
    Raytheon determined that it could propose a lower price by decreasing its cost to produce its
    radar system. To lower its production costs, Raytheon changed the design of its TRLRU, [. . .]
    with COTS circulators, and [. . .]. The only evidence of this design change in Raytheon’s
    proposal for the EMD contract was in a figure depicting its TRLRU in which the [. . .] did not
    appear. Raytheon did not describe the change in the text of its proposal, nor did Raytheon submit
    any information concerning the effect that the change would have on the TRL of its CTE 1.
    Raytheon first addressed the design change during discussions with the Air Force. In
    response to an EN related to its proposed production cost savings, Raytheon characterized the
    design change to the TRLRU as a “producibility improvement,” and did not indicate any concern
    that the [. . .] COTS circulators or redesigned [. . .] would affect the TRL of its CTE 1. Upon
    reviewing Raytheon’s response, the Air Force similarly did not express any concerns that the
    design change would affect the TRL 6 assessment for Raytheon’s CTE 1, likely because its focus
    was on the two new and novel technologies previously identified by the independent review
    team–the GaN HPA and [. . .].
    This lack of concern carried over into the Air Force’s technical evaluation of Raytheon’s
    final proposal revision. Although the independent review team and the Air Force’s technical
    evaluators reviewed the figure depicting the [. . .] TRLRU,19 they did not seek any information
    19
    Contrary to Raytheon’s contention, there is no evidence in the administrative record
    that the GAO attorney stated that the Air Force was unaware that Raytheon changed the design of
    its TRLRU. Indeed, such a statement is not reflected in the handwritten notes taken by the Air
    -32-
    from Raytheon concerning the effects that the design change might have on the performance of
    the TRLRU or the maturity of Raytheon’s CTE 1. Instead, the Air Force determined that there
    were no changes to Raytheon’s CTE 1 and that Raytheon had met the requirement set forth in
    section M of the solicitation that one of the CTEs be a GaN HPA-based T/R module.
    3. The Air Force Did Not Comply With the Evaluation Scheme Set Forth in the Solicitation
    Based on the contemporaneous evidence contained in the administrative record, it is
    readily apparent that despite the various labels used to denote Raytheon’s CTE 1, the
    independent review team and the Air Force’s technical evaluators focused their evaluation of the
    maturity of Raytheon’s CTE 1 on the new and novel aspects of the GaN HPA [. . .]–the GaN
    HPA and [. . .]. Indeed, neither the members of the independent review team nor the Air Force’s
    technical evaluators–the individuals with the relevant knowledge and expertise–expressed any
    concern that the introduction of COTS circulators or the [. . .] would affect the TRL of
    Raytheon’s CTE 1.
    Normally, a procuring agency’s technical assessments, such as the ones made by the Air
    Force with respect to Raytheon’s CTE 1, must be afforded the greatest possible deference. E.W.
    Bliss Co. v. United States, 
    77 F.3d 445
    , 449 (Fed. Cir. 1996); Beta Analytics Int’l, Inc. v. United
    States, 
    67 Fed. Cl. 384
    , 395 (2005) (“The evaluation of proposals for their technical excellence
    or quality is a process that often involves the special expertise of procurement officials, and thus
    reviewing courts give the greatest deference possible to these determinations.”). Such deference
    would be especially appropriate in this case because the relevant guidance instructs that (1) CTEs
    are new or novel technologies, (2) technologies requiring nothing more than routine engineering
    development are not CTEs, (3) the evaluation of technical maturity must involve expert
    professional judgment, and (4) the design of a product may still be evolving through the end of
    the EMD phase. See TRA Deskbook 1-1; TRA Guidance 1-1, 2-5, 2-1; Interim DoDI 5000.02,
    § 5.d(9)(b)(1)(a), (9)(d). In light of the highly deferential standard applicable in these
    circumstances, the court has no difficulty concluding, based on the evidence in the administrative
    record, that the independent review team and the Air Force’s technical evaluators reasonably
    assessed that the design change proposed by Raytheon would not affect the TRL of Raytheon’s
    CTE 1. The members of the independent review team in particular possessed expertise in radar
    system design, hardware, software, testing, and signal processing, and it is eminently reasonable
    to conclude that they applied that expertise in determining that the use of COTS circulators and
    the redesign of the [. . .] would not affect the technical maturity of Raytheon’s GaN HPA [. . .].
    Problematically, however, the Air Force did not comply with the solicitation when it
    evaluated Raytheon’s GaN HPA [. . .]. Pursuant to the solicitation, the contractors were required
    to substantiate a TRL 6 assessment for any CTEs that had changed since the conclusion of the
    pre-EMD period. Raytheon’s CTE 1 was its GaN HPA [. . .], and not just portions of its GaN
    Force personnel participating in the outcome prediction conference–the only contemporaneous
    evidence of what the GAO attorney advised the parties.
    -33-
    HPA [. . .], such as the GaN HPA or [. . .]. Accordingly, Raytheon was required to substantiate
    that the changes it made to the design of its GaN HPA [. . .]–using COTS circulators and
    [. . .]–did not affect the TRL of the GaN HPA [. . .]. Raytheon did not do so. Thus, the Air
    Force’s conclusion that Raytheon substantiated TRL 6 ratings for each of the CTEs that had
    changed since the pre-EMD period was erroneous. The Air Force should have required Raytheon
    to substantiate the TRL 6 rating of its changed CTE 1, and its failure to do so caused its
    assessment of Raytheon’s CTE 1 to be in violation of the evaluation scheme set forth in the
    solicitation. The Air Force’s evaluation of the technical maturity of Raytheon’s CTE 1 was
    therefore arbitrary and capricious. See, e.g., CRAssociates, Inc. v. United States, 
    102 Fed. Cl. 698
    , 713 (2011) (noting that a procuring agency’s departure from the evaluation scheme set forth
    in a solicitation can “lead to the award . . . being set aside as arbitrary, capricious or otherwise
    contrary to law”). Consequently, the GAO attorney’s findings on this issue were rational, and the
    Air Force’s reliance on her findings in deciding to take corrective action was also rational.
    4. Raytheon’s Arguments Lack Merit
    In arguing against this result, Raytheon fails to distinguish between the substantive merits
    of the Air Force’s technical evaluation and the need for the Air Force to comply with the
    evaluation scheme set forth in the solicitation. For example, Raytheon contends that the GAO
    attorney, in making her outcome prediction statement, confused two distinct evaluation criteria:
    the projected performance of its proposed radar system and the maturity of the critical
    technologies included in its proposed radar system. The distinction between performance and
    maturity is irrelevant, however. Even if the GAO attorney conflated the two concepts, she was
    still correct in noting that (1) Raytheon’s CTE 1 was its GaN HPA [. . .], not just some [. . .] of
    its GaN HPA [. . .]; (2) Raytheon changed its GaN HPA [. . .] by introducing [. . .] circulators and
    [. . .]; (3) the Air Force directed the contractors to substantiate a TRL 6 assessment for any
    changed CTEs; (4) Raytheon did not submit any information substantiating that its changed GaN
    HPA [. . .] remained at TRL 6; and (5) the Air Force incorrectly determined that Raytheon did
    not change any of its CTEs and therefore satisfied the requirement that it substantiate TRL 6
    ratings for each of the CTEs that had changed since the pre-EMD period.
    Raytheon further argues that the GAO attorney substituted her judgment for that of the
    Air Force’s technical evaluators. But again, the merits of the conclusions reached by the Air
    Force regarding the technical maturity of Raytheon’s CTE 1 do not excuse the fact that the Air
    Force did not comply with the express terms of the solicitation in reaching those conclusions.
    The Air Force was required to evaluate proposals in accordance with the evaluation scheme it
    described in the solicitation. Thus, the GAO attorney’s outcome prediction statement was
    rational.
    Raytheon raises one additional issue regarding the Air Force’s technical evaluation of its
    CTE 1 that is worth addressing: whether the Air Force’s proposed corrective action is properly
    tailored to remedy the impropriety identified by the GAO. See Chapman Law Firm Co. v.
    Greenleaf Constr. Co., 
    490 F.3d 934
    , 938 (2007) (holding that it was proper for the Court of
    -34-
    Federal Claims to inquire into the reasonableness of the government’s proposed corrective action
    and then determine that the proposed corrective action was reasonable); Sheridan Corp. v. United
    States, 
    95 Fed. Cl. 141
    , 151 (2010) (“[C]ontracting officers are provided ‘broad discretion to take
    corrective action where the agency determines that such action is necessary to ensure fair and
    impartial competition.’ Nevertheless, the chosen corrective action must be ‘reasonable under the
    circumstances.’ To be reasonable, the agency’s corrective action must be rationally related to the
    defect to be corrected.” (citations omitted)). In its complaint, Raytheon contends that if the court
    determines that the Air Force did not properly document the rationale underlying its conclusion
    that Raytheon’s CTE 1 did not change after the pre-EMD period, then the Air Force’s proposed
    corrective action–“reopen[ing] discussions concerning the technical evaluation of Raytheon’s
    Technology Readiness Level in accordance with Section M, Paragraph 2.4.1.3 of the
    [solicitation]”–is overly broad, and therefore arbitrary and capricious.20 However, as explained
    above, the problem with the Air Force’s evaluation was not a lack of documentation. Rather, in
    limiting its technological maturity assessment of Raytheon’s CTE 1 to just its new and novel
    elements, the Air Force did not evaluate Raytheon’s proposal in accordance with the plain
    language of the solicitation, which required substantiation of a TRL 6 assessment for any
    changed CTEs. Raytheon changed its CTE 1, but did not provide the necessary substantiation.
    Therefore, the Air Force erred in concluding that Raytheon met the substantiation requirement.
    As such, the Air Force’s proposed corrective action, which will allow Raytheon to provide the
    required substantiation, is a reasonable means by which to remedy the impropriety identified by
    the GAO attorney.
    In sum, the Air Force did not evaluate Raytheon’s technical proposal in accordance with
    the solicitation. The recommendation of the GAO attorney therefore had a rational basis, and it
    was rational for the Air Force to rely on the GAO attorney’s recommendation in deciding to take
    corrective action. The court therefore denies Raytheon’s protest on this ground.
    B. The Cost/Price Discussions
    Raytheon next challenges the Air Force’s decision to take corrective action with respect
    to the allowability of IR&D costs. The GAO attorney concluded that the Air Force changed its
    understanding regarding the allowability of future IR&D costs, but never advised Northrop of its
    changed understanding. She therefore opined that the Air Force’s discussions with Northrop
    were misleading and unequal. Raytheon contends that the GAO attorney’s findings and
    conclusion were irrational, and that the Air Force properly conducted discussions with respect to
    IR&D cost reductions.
    20
    Raytheon does not pursue this contention in its motion for judgment on the
    administrative record.
    -35-
    1. Discussions Concerning IR&D Cost Reductions
    The administrative record reflects that pursuant to the terms of the solicitation, the
    contractors were to identify and substantiate all reductions to their estimated costs to perform the
    EMD contract. Permissible cost reductions included those attributed to management decisions
    and those attributed to commonality with other programs. The latter category included cost
    reductions attributable to commonality with other programs, company-funded efforts, and capital
    equipment. With respect to common programs, the contractors were required to explain how the
    associated costs were allowable and allocated pursuant to the FAR and their CAS Disclosure
    Statements. With respect to company-funded efforts, the contractors were required to identify
    the efforts, the efforts’ start and end dates, the applicability of the efforts to the EMD contract,
    the source of funding for the efforts, and their plans for allocating those costs in accordance with
    generally accepted accounting principles and their CAS Disclosure Statements.
    In its initial proposal, Raytheon proposed [. . .] IR&D effort, and [. . .]. Lockheed [. . .]
    proposed [. . .]. And, Northrop initially proposed [. . .]. During the first round of discussions, the
    Air Force sent the contractors a number of ENs to obtain more information regarding their
    cost/price proposals. For example, to assist in its cost realism analysis, the Air Force sent
    Raytheon and Northrop similar ENs that explained the Air Force’s position with respect to the
    allowability of IR&D costs. These ENs reflected the Air Force’s understanding that pursuant to
    FAR 31.205-18 and 
    10 U.S.C. § 2320
    , IR&D costs were not “allowable as indirect charges for
    work implicitly required for performance (necessary to perform the contract) or explicitly
    required to be done by the terms of the contract.” In other words, the contractors would not be
    permitted to use IR&D costs to reduce their costs of performing the EMD contract if those costs
    were implicitly or explicitly required for contract performance. At the same time that the Air
    Force sent these similar ENs to Raytheon and Northrop, it sent a separate EN to Northrop
    requesting information, such as “[. . .]/IR&D planning statements,” to substantiate Northrop’s
    plan to fund contract performance during three specified fiscal years.
    In its response to the latter EN, Northrop stated that its performance of the EMD contract
    would not require the allocation of IR&D funding. Consistent with this representation,
    Northrop’s response to the former EN–the EN that was similar to the one sent to Raytheon–did
    not mention IR&D at all. Raytheon, however, did mention IR&D in its EN response.
    Specifically, it stated its disagreement with the Air Force’s position on the allowability of IR&D
    costs, asserting that the Federal Circuit had held in ATK Thiokol, Inc. that all IR&D costs were
    allowable unless they were for work explicitly required by the contract. It further asserted that it
    was in full compliance with the applicable rules regarding the allowability of IR&D costs.
    After this first round of discussions, the Air Force investigated the rules pertaining to the
    allowability of IR&D costs and determined that Raytheon’s statement was accurate. It therefore
    changed its position and concluded that IR&D costs for work implicitly required for contract
    performance were allowable as indirect charges. Although it did not expressly advise Raytheon
    of its agreement with Raytheon’s response, the Air Force conducted no further discussions with
    -36-
    Raytheon concerning the allowability of IR&D costs, implicitly signaling its change of position.
    [. . .] Northrop, however, received no such signals from the Air Force. Indeed, the Air Force
    never advised Northrop that the statement it made in its EN regarding the allowability of IR&D
    costs for work implicitly required for contract performance was no longer an accurate
    representation of its position. Thus, as far as Northrop was aware, the Air Force would not
    accept IR&D cost reductions for work implicitly required for contract performance.
    Ultimately, only Raytheon [. . .] proposed IR&D cost reductions [. . .].
    2. Standards for Conducting Discussions
    Northrop contends that the Air Force engaged in misleading and unequal discussions
    when it failed to advise Northrop that it had changed its position with respect to the allowability
    of IR&D costs. As set forth in the FAR, discussions “are undertaken with the intent of allowing
    the offeror to revise its proposal,” FAR 15.306(d), with the “primary objective of . . .
    maximiz[ing] the Government’s ability to obtain best value,” FAR 15.306(d)(2). To meet this
    objective, procuring agencies are “encouraged to discuss . . . aspects of the offeror’s proposal that
    could . . . be altered or explained to enhance materially the proposal’s potential for award,” but
    are “not required to discuss every area where the proposal could be improved.” FAR
    15.306(d)(3). Indeed, “[t]he scope and extent of discussions” are matters within the procuring
    agency’s discretion. 
    Id.
    Such discretion, however, does not permit a procuring agency to conduct misleading or
    unequal discussions. Discussions are misleading when a procuring agency issues “incorrect,
    confusing or ambiguous” communications that misdirect an offeror attempting to revise its
    proposal. DMS All-Star Joint Venture v. United States, 
    90 Fed. Cl. 653
    , 670 (2010); accord
    Analytical & Research Tech. v. United States, 
    39 Fed. Cl. 34
    , 48 (1997) (“‘An agency may not
    inadvertently mislead an offeror, through the framing of a discussion question, into responding in
    a manner that does not address . . . the government’s requirements.’” (quoting SRS Techs., B-
    254425 et al., 94-2 CPD ¶ 125 (Comp. Gen. Sept. 14, 1994)). A procuring agency also misleads
    an offeror when the agency “knows that an offeror’s interpretation of the [solicitation] is
    contrary, in a material way, to its own interpretation and that of a successful offeror,” but fails to
    advise the offeror of that fact. Gentex Corp., 58 Fed. Cl. at 653. Discussions are unequal when a
    procuring agency favors “one offeror over another.” FAR 15.306(e)(1). Consequently, although
    contracting officers should tailor discussions to each offeror’s proposal, FAR 15.306(d)(1), they
    should not “inform some offerors of a concern . . . while staying silent with respect to identical
    issues in other offerors’ proposals,” Ashbritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 372 (2009).
    3. The Air Force’s Discussions With Northrop Regarding the Allowability of IR&D Costs
    Were Misleading and Unequal
    Raytheon contends that discussions regarding the allowability of IR&D costs were neither
    misleading nor unequal, and there is support in the administrative record for its position. During
    -37-
    the first round of discussions, Northrop unambiguously disclaimed any reliance on IR&D cost
    reductions in response to one EN, and at the same time raised no objections to the Air Force’s
    statements regarding the allowability of IR&D costs in response to a separate EN. As a result,
    when the Air Force decided not to pursue further discussions with Northrop regarding IR&D
    costs, there is a nonfrivolous argument to be made that the Air Force was merely tailoring its
    discussions to Northrop’s proposal pursuant to FAR 15.306(d)(1).
    Nevertheless, the evidence in the administrative record weighs more heavily in favor of
    Northrop’s contention that the discussions were misleading and unequal. After the Air Force
    received the contractors’ responses to the initial set of ENs, it determined that a statement it had
    communicated to Raytheon and Northrop regarding the allowability of IR&D costs no longer
    accurately represented its position. By not lodging any further objections to Raytheon’s [. . .]
    proposed IR&D cost reductions, the Air Force signaled [. . .] that it was permissible to propose
    such reductions. However, the Air Force never advised Northrop of its changed understanding of
    the allowability of IR&D costs. Through its silence, the Air Force misled Northrop into
    believing that it would not accept IR&D cost reductions. Moreover, by advising only Raytheon
    [. . .] that it would accept IR&D cost reductions notwithstanding the language of its ENs, the Air
    Force engaged in unequal discussions with the contractors. At bottom, it was the Air Force’s
    duty to ensure that all three contractors were competing on a level playing field. See, e.g., Joseph
    L. DeClerk & Assocs., Inc. v. United States, 
    26 Cl. Ct. 35
    , 46 (1992), cited in Sys. Application &
    Techs., 691 F.3d at 1383; see also FAR 1.102-2(c)(3) (requiring procuring agencies to treat all
    prospective contractors “fairly and impartially”). By misleading Northrop regarding its position
    on the allowability of IR&D costs and advising only Raytheon [. . .] that it had changed its
    position, the Air Force violated that duty. Consequently, the GAO attorney’s conclusion that the
    Air Force engaged in misleading and unequal discussions concerning the allowability of IR&D
    costs was rational, and the Air Force’s reliance on her conclusion in deciding to take corrective
    action was also rational.
    4. Raytheon’s Arguments Are Not Persuasive
    None of Raytheon’s arguments to the contrary persuade the court to alter its conclusion.
    Raytheon first contends that the Air Force did not change the underlying rules of the procurement
    during discussions; IR&D costs were equally allowable under the solicitation and the FAR before
    discussions as they were under the solicitation and the FAR after discussions. Raytheon’s
    contention, while accurate, is irrelevant. Although the rules regarding the allowability of IR&D
    costs remained unchanged throughout the procurement, the Air Force provided the contractors
    with different information regarding its understanding of those rules. In doing so, the Air Force
    engaged in misleading and unequal discussions.
    Raytheon further argues that Northrop advanced inconsistent and shifting arguments
    before the GAO regarding its views on the allowability of IR&D costs in general, and the
    allowability of past, present, and future IR&D costs more specifically. Once again, these
    contentions are irrelevant. As noted above, in assessing whether the Air Force’s decision to take
    -38-
    corrective action by reopening cost/price discussions was proper, the court must determine
    whether the Air Force’s discussions pertaining to IR&D costs were misleading and unequal in the
    first instance. Northrop’s representations to the GAO have no bearing on the court’s inquiry in
    these circumstances.
    Next, Raytheon asserts that ENs RAY-K-016 and NG-K-011 contained a misstatement of
    law regarding the allowability of IR&D costs, and that such a misstatement cannot constitute
    misleading or unequal discussions. In support of its argument, it cites several decisions in which
    the court ruled that a misrepresentation of law could not, absent unusual circumstances, form the
    basis for rescinding or reforming a contract. See Mills v. United States, 
    410 F.2d 1255
    , 1257
    (Ct. Cl. 1969); Edwards v. United States, 
    19 Cl. Ct. 663
    , 671-73 (1990); C & L Constr. Co. v.
    United States, 
    6 Cl. Ct. 791
    , 798 (1984). None of these decisions arises from a bid protest, and
    therefore have little relevance here. The court is instead guided by the FAR, and the FAR lacks
    any misstatement-of-law exception to the requirement that procuring agencies conduct fair and
    equal discussions with offerors.
    Relatedly, Raytheon contends that as an experienced government contractor, Northrop
    should have known what the law permitted with respect to the allowability of IR&D costs and
    therefore should not benefit from its own misunderstanding of the law. However, Northrop’s
    understanding of the relevant law is of no moment when analyzing whether the Air Force
    conducted misleading or unequal discussions. The Air Force sent Northrop an EN containing its
    understanding of the allowability of IR&D costs but then changed its understanding without
    advising Northrop that it had done so. The fact that Northrop agreed with the Air Force’s
    original understanding of the allowability of IR&D costs does not change the misleading and
    unequal nature of the discussions.
    Raytheon’s final two arguments concern the findings of the GAO attorney. Specifically,
    Raytheon contends that the GAO attorney’s conclusion that the Air Force conducted misleading
    and unequal discussions was irrational because she should have dismissed Northrop’s
    contentions as untimely and because she should have found that Northrop did not establish that it
    was prejudiced by the purportedly improper discussions. Neither argument has merit.
    As Raytheon correctly notes, “except under limited circumstances, the GAO may not
    entertain untimely protests because they are not filed in accordance with the governing statutes”
    and regulations. Sys. Application & Techs., 100 Fed. Cl. at 713 (referring to 
    31 U.S.C. § 3552
    (a), 
    31 U.S.C. § 3555
    (a), 
    4 C.F.R. § 21.5
    (e), and 
    4 C.F.R. § 21.2
    (c)). And, “[w]hen the
    GAO acts in violation of the law, the act lacks a rational basis.” 
    Id. at 714
    . However, the
    evidence in the administrative record is unequivocal that Northrop had no basis for a claim of
    misleading and unequal discussions until after it received the agency report on November 26,
    2014, reflecting that the Air Force had changed its position with respect to the allowability of
    IR&D costs during discussions, and that Northrop raised that claim in a supplemental protest on
    December 8, 2014, within the ten-day time limit set forth in the GAO’s bid protest regulations.
    See 
    4 C.F.R. § 21.2
    (a)(2) (2014). Nevertheless, Raytheon asserts that Northrop should have
    -39-
    lodged its protest before the deadline for submitting final proposal revisions because two of the
    ENs that Northrop received from the Air Force during the initial round of discussions–EN NG-
    CP-003 and EN NG-K-011–were, when read together, patently ambiguous. Raytheon contends
    that had Northrop challenged the purported patent ambiguity when it received the ENs, then the
    Air Force would have been forced to examine its position on the allowability of IR&D costs,
    foreclosing the possibility of a later claim for misleading and unequal discussions. However, as
    counsel for Northrop explained during oral argument, the two ENs can be read harmoniously.
    See Oral Arg. Tr. 141:23-144:18, Apr. 29, 2015. Specifically, in EN NG-CP-003, the Air Force
    merely requested that Northrop support its funding decisions; it did not indicate that it would
    have accepted IR&D costs as a means of funding contract performance had Northrop proposed to
    do so. Indeed, the Air Force explained in EN NG-K-011 that certain types of IR&D costs were
    unallowable. Thus, the two ENs are not, when read together, patently ambiguous. Accordingly,
    when the GAO attorney implicitly concluded that Northrop timely raised the issue of misleading
    and unequal discussions by reaching the merits of its protest, she had a rational basis for that
    conclusion.
    By reaching the merits of Northrop’s protest, the GAO attorney also implicitly concluded
    that Northrop had established that it was prejudiced by the Air Force’s misleading and unequal
    discussions. It is well settled that before a protestor can prevail on a claim that there was “a
    significant error in the procurement process,” it must show “that the error prejudiced it.” Data
    Gen. Corp. v. Johnson, 
    78 F.3d 1556
    , 1562 (Fed. Cir. 1996); see also Bannum, Inc., 
    404 F.3d at 1351
     (holding that if the procuring agency’s decision lacked a rational basis or was made in
    violation of the applicable statutes, regulations, or procedures, the court must then “determine, as
    a factual matter, if the bid protester was prejudiced by that conduct”). “To establish prejudice
    . . . , a protester must show that there was a ‘substantial chance’ it would have received the
    contract award absent the alleged error.” Banknote Corp. of Am., 
    365 F.3d at 1350
     (quoting
    Emery Worldwide Airlines, Inc. v. United States, 
    264 F.3d 1071
    , 1086 (Fed. Cir. 2001)); see also
    Data Gen. Corp., 
    78 F.3d at 1562
     (“[T]o establish prejudice, a protester must show that, had it
    not been for the alleged error in the procurement process, there was a reasonable likelihood that
    the protester would have been awarded the contract.”). The protestor is not required to
    demonstrate that but for the alleged error, it would have received the contract. Bannum, Inc., 
    404 F.3d at 1358
    .
    The evidence in the record before the GAO reflected the following facts: (1) all three
    contractors received Acceptable technical compliance and technical risk ratings; (2) the
    difference between Northrop’s final proposed price of [. . .] and Raytheon’s final proposed price
    of [. . .] was [. . .]; (3) Raytheon proposed IR&D cost reductions of [. . .]; and (4) Northrop is a
    large government contractor with extensive financial resources. Based on these facts, it was
    entirely reasonable for the GAO attorney to surmise that Northrop possessed the financial means
    to propose IR&D cost reductions [. . .], making it possible for Northrop to overcome the [. . .]
    differential in proposed prices. Thus, the GAO’s implicit conclusion that Northrop had a
    substantial chance of receiving the contract in the absence of the Air Force’s misleading and
    unequal discussions was rational.
    -40-
    In sum, the Air Force conducted misleading and unequal discussions with respect to the
    allowability of IR&D costs. The recommendation of the GAO attorney therefore had a rational
    basis, and it was rational for the Air Force to rely on the GAO attorney’s recommendation in
    deciding to take corrective action. The court therefore denies Raytheon’s protest on this ground.
    V. CONCLUSION
    Although the court is ruling against Raytheon, Raytheon’s bid protest is far from
    frivolous. The evidence in the administrative record supports the Air Force’s original
    conclusion, based on the expertise of the independent review team and its technical evaluators,
    that the design changes proposed by Raytheon would not have affected the TRL 6 assessment of
    Raytheon’s CTE 1 because the new and novel aspects of Raytheon’s CTE 1 were unchanged.
    However, pursuant to the plain language of the solicitation, the Air Force should have ensured
    that Raytheon’s CTE 1 as a whole remained at TRL 6 by requiring Raytheon to substantiate the
    TRL 6 assessment. And, the evidence in the administrative record also reflects that Northrop
    made a strategic decision, based on its understanding of the relevant statutes, regulations, and
    guidance, not to rely on IR&D cost reductions to lower its proposed price. However, the Air
    Force rendered that strategic decision irrelevant when it failed to advise Northrop of its changed
    position regarding the allowability of IR&D costs. The Air Force’s errors prevented a fair and
    equal competition, and the Air Force was therefore entitled, based on the GAO attorney’s
    outcome prediction statement, to propose corrective action to remedy those errors.
    Accordingly, for the reasons set forth above, the court DENIES Northrop’s motion to
    supplement the administrative record, GRANTS Raytheon’s motion to strike, DENIES
    Raytheon’s motion for judgment on the administrative record, and GRANTS the remaining
    cross-motions for judgment on the administrative record. No costs. The clerk shall enter
    judgment accordingly.
    The court has filed this ruling under seal. The parties shall confer to determine agreed-to
    proposed redactions. Then, by no later than Friday, May 29, 2015, the parties shall file a joint
    status report indicating their agreement with the proposed redactions, attaching a copy of those
    pages of the court’s ruling containing proposed redactions, with all proposed redactions
    clearly indicated.
    Also, as the parties are aware, they are required to file redacted versions of all documents
    that they filed under seal under paragraph 12 of the January 29, 2015 protective order. The
    -41-
    parties shall continue to comply with this requirement until they have filed redacted versions of
    all sealed documents.
    IT IS SO ORDERED.
    s/ Margaret M. Sweeney
    MARGARET M. SWEENEY
    Judge
    -42-
    

Document Info

Docket Number: 15-77

Citation Numbers: 121 Fed. Cl. 135

Judges: Margaret M. Sweeney

Filed Date: 6/2/2015

Precedential Status: Precedential

Modified Date: 1/13/2023

Authorities (26)

E.W. Bliss Company v. United States , 77 F.3d 445 ( 1996 )

Honeywell, Inc. v. The United States v. Haz-Tad, Inc. , 870 F.2d 644 ( 1989 )

banknote-corporation-of-america-inc-and-guilford-gravure-inc-v-united , 365 F.3d 1345 ( 2004 )

Centech Group, Inc. v. United States , 554 F.3d 1029 ( 2009 )

Bannum, Inc. v. United States , 404 F.3d 1346 ( 2005 )

ATK Thiokol, Inc. v. United States , 598 F.3d 1329 ( 2010 )

Chapman Law Firm Co. v. Greenleaf Construction Co. v. ... , 490 F.3d 934 ( 2007 )

William O. Schism and Robert Reinlie v. United States , 316 F.3d 1259 ( 2002 )

Am-Pro Protective Agency, Inc. v. United States , 281 F.3d 1234 ( 2002 )

Emery Worldwide Airlines, Inc. v. United States and Federal ... , 264 F.3d 1071 ( 2001 )

Axiom Resource Management, Inc. v. United States , 564 F.3d 1374 ( 2009 )

data-general-corporation-v-roger-w-johnson-administrator-general , 78 F.3d 1556 ( 1996 )

alaska-airlines-inc-american-airlines-inc-continental-airlines , 8 F.3d 791 ( 1993 )

Impresa Construzioni Geom. Domenico Garufi v. United States , 238 F.3d 1324 ( 2001 )

Mathews v. Weber , 96 S. Ct. 549 ( 1976 )

William R. Sherwin, D/B/A Sherwin Electric Service v. The ... , 436 F.2d 992 ( 1971 )

Irene E. Mills and Florence E. Mahoney v. The United States , 410 F.2d 1255 ( 1969 )

Advanced Data Concepts, Incorporated v. United States , 216 F.3d 1054 ( 2000 )

Turner Const. Co., Inc. v. United States , 645 F.3d 1377 ( 2011 )

John Reiner & Company, Individually and to the Use of Kurz &... , 325 F.2d 438 ( 1963 )

View All Authorities »