Electrical Contractors v. Westwater Farms , 370 P.3d 949 ( 2016 )


Menu:
  •                         
    2016 UT App 60
    THE UTAH COURT OF APPEALS
    ELECTRICAL CONTRACTORS, INC.,
    Appellee,
    v.
    WESTWATER FARMS, LLC,
    Appellant.
    Opinion
    No. 20141166-CA
    Filed March 31, 2016
    Seventh District Court, Moab Department
    The Honorable Lyle R. Anderson
    No. 120700003
    Craig C. Halls, Attorney for Appellant
    Douglas E. Griffith and Adam L. Grundvig,
    Attorneys for Appellee
    SENIOR JUDGE RUSSELL W. BENCH authored this Opinion, in which
    JUDGES J. FREDERIC VOROS JR. and MICHELE M. CHRISTIANSEN
    concurred.1
    BENCH, Senior Judge:
    ¶1     Westwater Farms, LLC (Westwater) appeals the district
    court’s grant of summary judgment in favor of Electrical
    Contractors, Inc. (ECI) and its denial of Westwater’s motion to
    submit supplemental affidavits and documents in opposition to
    summary judgment. We affirm.
    1. Senior Judge Russell W. Bench sat by special assignment as
    authorized by law. See generally Utah R. Jud. Admin. 11-201(6).
    Electrical Contractors v. Westwater Farms
    BACKGROUND
    ¶2     In September 2010, Westwater, through its managing
    members, Thomas Warnes and Carl Borgstrom, allegedly
    entered into an oral contract with ECI pursuant to which ECI
    would provide general and electrical contracting services on a
    cost-plus2 basis in connection with a water disposal system to be
    constructed on Westwater’s property in Grand County, Utah
    (the Project). Stewart Environmental Services, Inc. (Stewart
    Environmental) joined the Project as Westwater’s engineering
    representative in late 2010 or early 2011. Between late 2010 and
    July 2011, ECI provided approximately $1,028,849 in
    construction services on the Project and sent invoices to
    Westwater for this work. Stewart Environmental made
    payments to ECI in May and July 2011 totaling $152,061.24. On
    August 8, 2011, ER&PWD Joint Venture—an LLC created by
    Warnes and Dave Stewart, a principal of Stewart
    Environmental—entered into a written agreement with ECI
    regarding documentation of charges and a schedule for paying
    ECI. However, other than the aforementioned payments made
    by Stewart Environmental, no additional payments were made
    to ECI by any party.
    ¶3     On January 19, 2012, ECI filed a complaint alleging
    various causes of action against Westwater, Stewart
    Environmental, ER&PWD Joint Venture, and several other
    parties. On May 28, 2014, ECI moved for summary judgment on
    its breach of contract claim against Westwater. In support of its
    motion, ECI submitted an affidavit from Doyle Jensen, job
    supervisor for ECI, describing the oral contract he entered into
    with Borgstrom and Warnes. Westwater filed a response in
    opposition to the motion for summary judgment on June 23,
    2. A cost-plus contract is one ‚in which payment is based on a
    fixed fee or a percentage added to the actual cost incurred.‛
    Contract, Black’s Law Dictionary (9th ed. 2009).
    20141166-CA                     2                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    2014 (the Opposition Memo). The Opposition Memo was
    supported by an affidavit from Warnes, but rather than denying
    the allegations in Jensen’s affidavit, Warnes merely averred,
    ‚Neither I nor any other person on behalf of Westwater . . .
    authorized Mr. Stewart or any entity under his control, to
    engage Electrical Contractors, Inc. as the general contractor . . . .‛
    ¶4      Subsequently, on August 1, 2014, Westwater moved the
    court, pursuant to rule 15(d) of the Utah Rules of Civil
    Procedure, ‚to allow amendment and supplementation of
    [additional] documents and affidavits to be considered by the
    Court before consideration of summary . . . judgment.‛
    Westwater claimed that it was unable to provide the documents
    earlier because they were in the possession of Warnes, who had
    been hospitalized on June 27, 2014. The district court denied
    Westwater’s motion to supplement, concluding that Westwater
    had ‚provided no persuasive explanation for failing to include
    the documents or arguments in its original response.‛
    ¶5      The district court held a hearing on ECI’s motion for
    summary judgment on September 23, 2014. Following the
    hearing, the district court determined that Westwater’s
    Opposition Memo did not ‚contain a verbatim restatement of
    each of *ECI’s+ facts that is controverted‛ or ‚provide an
    explanation of the grounds for any dispute,‛ as required by rule
    7 of the Utah Rules of Civil Procedure. See Utah R. Civ. P.
    7(c)(3)(B) (2014).3 In light of these shortcomings, the district court
    deemed ECI’s statement of material facts admitted for purposes
    3. Rule 7 of the Utah Rules of Civil Procedure was repealed and
    reenacted in 2015, and ‚the special requirements for a motion for
    summary judgment‛ were moved to rule 56. See Utah R. Civ. P. 7
    advisory committee notes; 
    id.
     R. 56. Thus, we cite the 2014
    version of both rules.
    20141166-CA                      3                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    of the summary judgment motion.4 The district court further
    determined, based on the undisputed facts, that ECI had
    established its breach of contract claim as a matter of law, and
    the court therefore awarded damages in the amount of
    $876,788.10, plus interest, for a total award of $1,165,084.09. The
    district court certified the judgment as final under rule 54(b) of
    the Utah Rules of Civil Procedure, and Westwater now appeals.
    ISSUES AND STANDARDS OF REVIEW
    ¶6      Westwater first argues that the district court erred in
    granting ECI’s motion for summary judgment. ‚Because a
    district court’s ruling on summary judgment is a question of law,
    we review it for correctness.‛ Rupp v. Moffo, 
    2015 UT 71
    , ¶ 5, 
    358 P.3d 1060
    .
    ¶7     Westwater further asserts that the district court erred by
    declining to accept Westwater’s proffered supplemental
    affidavits and documents. We review the district court’s ruling
    for an abuse of discretion. See United Park City Mines Co. v.
    Greater Park City Co., 
    870 P.2d 880
    , 893 (Utah 1993).
    4. The district court also observed that even if it had not deemed
    ECI’s facts admitted, Westwater’s Opposition Memo and
    Warnes’s affidavit did not establish the existence of a genuine
    issue of material fact because they asserted only that Stewart did
    not have the power to contract on behalf of Westwater, not that
    Westwater had not itself entered into a contract. Since ECI
    alleged that it had contracted with Westwater through Warnes
    and Borgstrom, the district court concluded that ‚it’s a red
    herring whether Mr. Stewart was acting on behalf of
    Westwater.‛
    20141166-CA                     4                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    ANALYSIS
    I. Summary Judgment
    ¶8      Westwater raises several arguments in support of its
    assertion that the district court erred in granting ECI’s summary
    judgment motion. First, Westwater argues that the allegations in
    ECI’s complaint failed to establish the elements of its breach of
    contract claim as a matter of law. Second, Westwater asserts that
    documents attached to ECI’s amended complaint established a
    genuine issue of material fact. Third, Westwater argues that the
    district court should not have considered evidence relating to the
    oral contract because such evidence violated the parol evidence
    rule. Summary judgment is appropriate when ‚there is no
    genuine issue as to any material fact and . . . the moving party is
    entitled to a judgment as a matter of law.‛ Utah R. Civ. P. 56(c)
    (2014).
    A.     Breach of Contract Claim
    ¶9     Westwater first argues that ECI did not adequately allege
    a breach of contract claim, because it did not establish the
    existence of an enforceable contract. See Orvis v. Johnson, 
    2008 UT 2
    , ¶ 19, 
    177 P.3d 600
     (‚If the moving party would bear the
    burden of proof on the relevant issue, . . . then the movant has an
    affirmative duty to provide the court with facts that demonstrate
    both that the party is entitled to judgment as a matter of law and
    that there are no material issues of fact that would require
    resolution at trial.‛); Bair v. Axiom Design, LLC, 
    2001 UT 20
    , ¶ 14,
    
    20 P.3d 388
     (indicating that the first element of a breach of
    contract claim is the existence of a contract). Westwater asserts
    that the terms of the alleged oral contract were too indefinite to
    be enforced, see Nielsen v. Gold’s Gym, 
    2003 UT 37
    , ¶ 11, 
    78 P.3d 600
    , because they did not include ‚the price to be paid and work
    to be done.‛
    ¶10 First, Westwater does not appear to have preserved this
    argument. In its Opposition Memo, Westwater alleged only that
    20141166-CA                     5                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    there were genuine issues of fact precluding summary judgment,
    not that there was no contract as a matter of law. See generally
    Brookside Mobile Home Park, Ltd. v. Peebles, 
    2002 UT 48
    , ¶ 14, 
    48 P.3d 968
     (‚*I+n order to preserve an issue for appeal the issue
    must be presented to the trial court in such a way that the trial
    court has an opportunity to rule on that issue.‛). But even if this
    argument was preserved, we agree with ECI that Jensen’s
    affidavit adequately alleged the existence of an enforceable oral
    contract.
    ¶11 ‚‘A contract may be enforced even though some contract
    terms may be missing or left to be agreed upon’‛ so long as ‚‘the
    essential terms are [not] so uncertain that there is no basis for
    deciding whether the agreement has been kept or broken.’‛
    Nielsen, 
    2003 UT 37
    , ¶ 12 (quoting Academy Chicago Publishers v.
    Cheever, 
    578 N.E.2d 981
    , 984 (Ill. 1991)). Jensen’s affidavit
    indicated that ECI and Westwater agreed that ECI would ‚serve
    as the Project’s general contractor and electrical contractor.‛
    Thus, any services that would normally be performed by a
    general contractor or an electrical contractor on a project such as
    the one at issue would be included in the contracted services;
    these services did not need to be explicitly enumerated in order
    for the parties to determine whether ECI had provided them.
    Further, Jensen indicated that the parties agreed to a cost-plus
    payment structure ‚such that ECI would charge Westwater the
    actual costs that ECI incurred in providing the requested
    services, plus a 1% administrative fee markup on certain items, a
    3% bonding fee markup on certain items, and a 12% profit
    markup on other items.‛ The fact that the parties did not know
    what the ultimate cost would be does not demonstrate, as
    Westwater asserts, that there was no meeting of the minds.
    While the cost-plus terms did not establish a precise price to be
    paid, they did provide a clear method for calculating the price
    once the work was completed. Thus, the essential terms of the
    oral contract were established and the district court did not err
    in determining that ECI established its claim as a matter of law.
    20141166-CA                     6                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    B.     Genuine Issue of Material Fact
    ¶12 Westwater next asserts that Exhibits A, B, and C of ECI’s
    amended complaint contained documents that established
    genuine issues of material fact that would preclude summary
    judgment. But even assuming that these exhibits contained
    evidence sufficient to create a factual dispute, it was ultimately
    Westwater’s burden, under rule 7 of the Utah Rules of Civil
    Procedure, to dispute the facts asserted in ECI’s summary
    judgment motion with ‚an explanation of the grounds for any
    dispute, supported by citation to relevant materials.‛ Utah R.
    Civ. P. 7(c)(3)(B) (2014); see also Orvis, 
    2008 UT 2
    , ¶ 10 (explaining
    that where the moving party would bear the burden of proof at
    trial, once the moving party has ‚present*ed+ evidence sufficient
    to establish . . . that no material issues of fact remain,‛ the
    burden ‚shifts to the nonmoving party to identify contested
    material facts‛). Westwater did not refer to any of these exhibits
    in its Opposition Memo. Indeed, the Opposition Memo was so
    incomplete that the district court ultimately deemed ECI’s
    statement of undisputed material facts admitted for purposes of
    the summary judgment motion. See Utah R. Civ. P. 7(c)(3)(A)
    (2014); see also Bluffdale City v. Smith, 
    2007 UT App 25
    , ¶¶ 8–11,
    
    156 P.3d 175
    . Westwater has not challenged the district court’s
    rule 7 ruling, yet it asks us to hold that the district court, having
    deemed ECI’s facts admitted, should have nevertheless reviewed
    the record sua sponte in an effort to find evidence supporting a
    dispute of fact.5 But ‚*a+ district court is not obliged to comb the
    record to determine whether a genuine issue as to any material
    5. Much of Westwater’s discussion focuses on the question of
    whether it could rely on the exhibits in disputing ECI’s
    statement of facts when the exhibits were submitted as part of
    ECI’s pleadings rather than Westwater’s. This argument is
    beside the point, as Westwater made no attempt to rely on those
    exhibits in its Opposition Memo.
    20141166-CA                      7                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    fact exists to prevent summary judgment.‛6 Jennings Inv., LC v.
    Dixie Riding Club, Inc., 
    2009 UT App 119
    , ¶ 26, 
    208 P.3d 1077
    .
    Given that ECI’s statement of facts was deemed admitted, the
    district court needed only to examine whether those facts
    established ECI’s breach of contract claim as a matter of law, not
    whether those facts could be disputed by other evidence in the
    record.7
    C.    Parol Evidence Rule
    ¶13 Westwater next argues that the district court violated the
    parol evidence rule by considering ECI’s evidence regarding the
    oral agreement. As with Westwater’s other arguments,
    Westwater failed to preserve its parol evidence argument in the
    district court. But in any event, the parol evidence rule does not
    apply in this case. ‚The parol evidence rule operates to exclude
    6. Indeed, the current version of the Utah Rules of Civil
    Procedure provides that although the district court ‚may
    consider other materials in the record,‛ it ‚need consider only
    the cited materials‛ in ruling on a motion for summary
    judgment. Utah R. Civ. P. 56(c)(3) (emphasis added).
    7. We also observe that it is by no means clear that any of the
    exhibits actually establish a dispute of fact. Exhibit A shows that
    ECI had a written agreement with ER&PWD Joint Venture
    regarding a payment schedule for services ECI had provided.
    Exhibit B is a document titled ‚Scope of Work‛ that is not
    addressed to anyone in particular. And Exhibit C shows that ECI
    asserted a claim of lien against Stewart Environmental relating
    to work done on the Project. To even begin to construe these
    documents as contradicting ECI’s assertion that it had an oral
    contract with Westwater, a number of inferences must be made.
    Without the benefit of Westwater’s argument on the subject, the
    district court could not have been expected to construe the
    documents the way Westwater does on appeal.
    20141166-CA                     8                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    [extrinsic] evidence of contemporaneous conversations,
    representations, or statements offered for the purpose of varying
    or adding to the terms of an integrated contract.‛ DCH Holdings,
    LLC v. Nielsen, 
    2009 UT App 269
    , ¶ 8, 
    220 P.3d 178
     (alteration in
    original) (citation and internal quotation marks omitted). The
    only written contract related to this case is the agreement
    between ECI and ER&PWD Joint Venture.8 There is no
    integrated written contract between Westwater and ECI, and the
    evidence of an oral agreement between Westwater and ECI was
    not offered to vary or add to the terms of ECI’s written
    agreement with ER&PWD Joint Venture. Thus, we are at a loss
    to see how the parol evidence rule could apply to exclude ECI’s
    evidence of an oral contract with Westwater.
    II. Motion to File Supplemental Documents
    ¶14 Finally, Westwater challenges the district court’s denial of
    its motion to file supplemental affidavits and documents in
    support of its Opposition Memo. Westwater claims that its
    motion was made pursuant to rule 56(f) of the Utah Rules of
    Civil Procedure. ‚Rule 56(f) motions opposing a summary
    judgment motion on the ground that discovery has not been
    completed should be granted liberally unless they are deemed
    dilatory or lacking in merit.‛ Energy Mgmt. Servs., LLC v. Shaw,
    
    2005 UT App 90
    , ¶ 10, 
    110 P.3d 158
     (citation and internal
    quotation marks omitted). Westwater asserts that the district
    8. Although Westwater attempts to characterize this agreement
    as an integrated contract relating to the same subject matter as
    the alleged oral agreement, it cannot really be characterized as
    such. The agreement was entered into after ECI had completed
    its work on the Project, says nothing about the work ECI agreed
    to perform, and mentions the cost-plus terms only in a note
    explaining ECI’s invoice. Indeed, this document is more
    properly characterized as an agreement regarding a payment
    schedule than a contract for services.
    20141166-CA                     9                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    court exceeded its discretion by denying Westwater’s motion on
    the ground that Westwater had ‚provided no persuasive
    explanation for failing to include the documents or arguments in
    its original response,‛ because the district court made no
    determination that its motion was meritless or dilatory. We
    disagree.
    ¶15 First, Westwater did not indicate to the district court that
    it was making its motion to supplement pursuant to rule 56(f).
    To the contrary, Westwater explicitly stated that its motion
    relied on rule 15(d) of the Utah Rules of Civil Procedure,
    governing supplemental pleadings. Thus, Westwater’s rule 56(f)
    argument was not preserved. See Brookside Mobile Home Park, Ltd.
    v. Peebles, 
    2002 UT 48
    , ¶ 14, 
    48 P.3d 968
    .
    ¶16 Furthermore, we agree with ECI that Westwater’s motion,
    even if had been a rule 56(f) motion, was dilatory and/or lacking
    in merit on its face. Westwater submitted its Opposition Memo
    on June 23, 2014, which included an affidavit by Warnes.
    Westwater did not indicate to the court at that time that it was
    unable to ‚present by affidavit facts essential to justify *its+
    opposition‛ to the summary judgment motion. Utah R. Civ. P.
    56(f) (2014). Rather, it asserted, both in its Opposition Memo and
    in a later response to ECI’s reply memorandum, that the facts
    alleged in Warnes’s affidavit evidenced a factual dispute
    sufficient to preclude summary judgment. Further, Westwater’s
    proffered reason for its failure to provide the court with the
    supplemental documents sooner was that Warnes had been
    hospitalized, but Warnes was not hospitalized until after
    Westwater had filed its Opposition Memo, and he actually
    provided an affidavit that was submitted with the memo. Thus,
    it is unclear why Warnes’s hospitalization prevented Westwater
    from submitting the supplemental documents with its
    Opposition Memo. For these reasons, it does not appear that
    Westwater was precluded from adequately opposing ECI’s
    motion for summary judgment in its Opposition Memo.
    20141166-CA                    10                 
    2016 UT App 60
    Electrical Contractors v. Westwater Farms
    CONCLUSION
    ¶17 For the foregoing reasons, we conclude that the district
    court did not err in granting ECI’s motion for summary
    judgment and denying Westwater’s motion to submit
    supplemental affidavits and documents. Accordingly, we affirm.
    20141166-CA                   11                 
    2016 UT App 60