P & N Investments, LLC, d/b/a Dickey's Barbecue Pit v. Frontier Mall Associates, LP , 395 P.3d 1101 ( 2017 )


Menu:
  •                 IN THE SUPREME COURT, STATE OF WYOMING
    
    2017 WY 62
    APRIL TERM, A.D. 2017
    May 31, 2017
    P & N INVESTMENTS, LLC, d/b/a
    DICKEY’S BARBECUE PIT,
    Appellant
    (Plaintiff),
    S-16-0244
    v.
    FRONTIER MALL ASSOCIATES, LP,
    Appellee
    (Defendant).
    Appeal from the District Court of Laramie County
    The Honorable Steven K. Sharpe, Judge
    Representing Appellant:
    Tara B. Nethercott, Woodhouse Roden Nethercott, LLC, Cheyenne, Wyoming.
    Representing Appellee:
    Rick A. Thompson and Lucas E. Buckley, Hathaway & Kunz, LLP, Cheyenne,
    Wyoming. Argument by Mr. Buckley.
    Before BURKE, C.J., and HILL, DAVIS, FOX, and KAUTZ, JJ.
    FOX, J., delivers the opinion of the Court; Hill, J., files a dissenting opinion, in which
    DAVIS, J., joins.
    NOTICE: This opinion is subject to formal revision before publication in Pacific Reporter Third.
    Readers are requested to notify the Clerk of the Supreme Court, Supreme Court Building,
    Cheyenne, Wyoming 82002, of any typographical or other formal errors so that correction may be
    made before final publication in the permanent volume.
    FOX, Justice.
    [¶1] Appellant P & N Investments, LLC (P & N) obtained a franchise for a Dickey’s
    Barbeque Pit restaurant to be operated in Frontier Mall in Cheyenne, Wyoming. P & N
    entered into a lease with Frontier Mall Associates, LP (the Mall), which required the Mall
    to pay P & N a finish allowance when certain provisions had been satisfied. P & N then
    entered into a contract with a general contractor, which P & N eventually paid in full for
    the work done. The general contractor, however, did not pay all the subcontractors.
    P & N and the Mall now dispute whether the lease provision requiring that liens be
    released and work be paid for was satisfied. The district court ruled that the lease
    language is unambiguous, and, because it is undisputed that subcontractors have not been
    paid and have not provided evidence regarding satisfaction or waiver of any liens,
    granted summary judgment in favor of the Mall. We affirm.
    ISSUE
    [¶2] We rephrase the issue: Do the unambiguous terms of the lease require evidence
    that subcontractors and the general contractor have been paid in full before the Mall is
    obligated to pay the finish allowance?
    FACTS
    [¶3] P & N entered into a ten-year Shopping Center Lease (Lease) with the Mall for
    approximately 2500 square feet in Frontier Mall in which to operate a Dickey’s Barbeque
    Pit franchise. The Lease allowed P & N to renovate the space to suit its use as a
    restaurant. P & N retained East Rochester, New York contractor, CCI Builders and
    Developers, Inc. (CCI), to act as the general contractor on the project. CCI, in turn, hired
    a number of local subcontractors to provide materials and perform work on the project.
    [¶4] The Lease provided that upon satisfaction of ten express conditions, the Mall
    would pay P & N a tenant finish allowance of $150,180. The condition that lies at the
    heart of this dispute requires P & N to provide the Mall satisfactory evidence from P &
    N’s general contractor and subcontractors that any liens have been satisfied or waived
    and an affidavit that “all work has been paid for” before the finish allowance becomes
    due.
    [¶5] Work was completed on the project in September 2014 and the restaurant opened
    on schedule. For the purposes of this appeal, it is undisputed that the total cost of
    construction was $308,929.55 and that P & N paid CCI $308,929.55. P & N submitted
    an affidavit to the Mall stating:
    1
    6. The total cost of construction was three hundred
    eight thousand nine hundred twenty nine and 55/100 dollars
    ($308,929.55). The cost was paid in full by me [Nathaniel
    Schott, owner of P & N] to CCI.
    7. The construction was completed in September
    2014.
    7. [sic] No liens have been filed on the property or
    may be filed as a result of construction on the leased
    premises.
    It is also undisputed that CCI did not pay numerous subcontractors a total of
    approximately $90,000 for work they performed on or materials they provided to the
    project.1
    [¶6] Under Wyoming law, contractors have one hundred fifty days from the date of the
    completion of their work to assert a lien.2 Thus, CCI and the subcontractors had until
    February 27, 2015, at the latest, to assert a lien against the property. It is undisputed that
    no liens have been filed against the property.
    [¶7] Because the Mall has not paid the finish allowance, P & N sued the Mall, asserting
    claims of breach of contract and unjust enrichment, and seeking declaratory judgment
    that the Mall must pay the tenant finish allowance because P & N has met the conditions
    for that payment set forth in the Lease. The Mall counterclaimed, seeking a
    determination that the Lease terms have not been satisfied and that the requirement to pay
    the finish allowance has not been triggered. The parties filed cross-motions for summary
    judgment. The district court concluded that the disputed contract language is
    unambiguous and requires the submission of evidence of lien release satisfactory to the
    Mall from the general contractor and the subcontractors and an affidavit that all
    1
    CCI is not a party to this action, perhaps because of the arbitration clause in its contract with P & N requiring that
    “[a]ny controversy or claim arising out of or relating to this contract, or the breach thereof, shall be settled by
    arbitration administered by the American Arbitration Association . . . .”
    2
    Wyo. Stat. Ann. § 29-2-106(a) (LexisNexis 2015) provides:
    (a) Except as provided in subsection (c) of this section, any contractor
    asserting a lien under this chapter shall file his lien statement within one
    hundred fifty (150) days and every other person asserting a lien under this
    chapter shall file within one hundred twenty (120) days:
    (i) Of the earlier of:
    (A) After the last day when work was performed or materials
    furnished under contract;
    (B) From the date of substantial completion of the project on
    which work was performed or materials were furnished under contract;
    or
    (ii) With respect to a subcontractor, after the last day he
    performed work at the direction of the contractor or other person
    authorized to provide direction.
    2
    outstanding amounts owed for the construction, including amounts owed to
    subcontractors, have been paid. Because there is no dispute that neither of these
    requirements has been met, the district court granted summary judgment in favor of the
    Mall. P & N appeals.
    STANDARD OF REVIEW
    [¶8] We review a grant of summary judgment deciding a question of law de novo.
    Anadarko Land Corp. v. Family Tree Corp., 
    2017 WY 24
    , ¶ 15, 
    389 P.3d 1218
    , 1223
    (Wyo. 2017); Williams v. Sundstrom, 
    2016 WY 122
    , ¶ 17, 
    385 P.3d 789
    , 793 (Wyo.
    2016). We use the same materials and follow the same standards as the district court.
    Leeks Canyon Ranch, LLC v. Callahan River Ranch, LLC, 
    2014 WY 62
    , ¶ 12, 
    327 P.3d 732
    , 737 (Wyo. 2014). Summary judgment can be granted when there are no genuine
    issues of material fact and the moving party is entitled to judgment as a matter of law.
    W.R.C.P. 56(c).
    [¶9]   When summary judgment is based on interpretation of a contract:
    The initial question of whether the contract is
    capable of being understood in only one way is a
    question of law for the court. If the court determines
    that the contract is capable of being understood in only
    one way, then the language used in the contract
    expresses and controls the intent of the parties. In such
    case, the next question, what is that understanding or
    meaning, is also a question of law. When we review
    the district court’s summary judgment decisions that a
    contract is capable of being understood in only one
    way and what that understanding is, we accord no
    deference to those decisions.
    Claman v. Popp, 
    2012 WY 92
    , ¶ 23, 
    279 P.3d 1003
    , 1012
    (Wyo. 2012) (quoting Union Pacific Railroad Co. v. Caballo
    Coal Co., 
    2011 WY 24
    , ¶ 13, 
    246 P.3d 867
    , 871 (Wyo.
    2011)).
    Leeks Canyon Ranch, LLC, 
    2014 WY 62
    , ¶ 
    12, 327 P.3d at 737
    .
    DISCUSSION
    [¶10] Our “ultimate goal when interpreting a contract ‘is to discern the intention of the
    parties to the document.’” Comet Energy Servs., LLC v. Powder River Oil & Gas
    Ventures, LLC, 
    2008 WY 69
    , ¶ 6, 
    185 P.3d 1259
    , 1261 (Wyo. 2008) (Comet I) (quoting
    Mullinnix, LLC v. HKB Royalty Trust, 
    2006 WY 14
    , ¶ 22, 
    126 P.3d 909
    , 919 (Wyo.
    2006)). In so doing, we first consider the “specific terms of the contract and give them
    their plain and ordinary meaning.” 
    Id. 3 [¶11]
    Section 1.5(b) of exhibit B to the Lease provides:
    Tenant shall have furnished evidence satisfactory to Landlord
    from its general contractor and any subcontractors that any
    and all liens that have been, or may be, filed have been
    satisfied of record or waived and an affidavit that all work has
    been paid for[.]
    Both parties contend that these terms are unambiguous, but they disagree as to the
    meaning. A disagreement between the parties as to the meaning of the terms of a
    contract does not give rise to an ambiguity. Omohundro v. Sullivan, 
    2009 WY 38
    , ¶ 9,
    
    202 P.3d 1077
    , 1081 (Wyo. 2009). We agree with the district court that the language of
    this provision is unambiguous. It is not “obscure in its meaning, because of
    indefiniteness of expression, or because a double meaning is present.” Amoco Prod. Co.
    v. Stauffer Chem. Co. of Wyo., 
    612 P.2d 463
    , 465 (Wyo. 1980) (citation omitted); see
    also Comet I, 
    2008 WY 69
    , ¶ 
    11, 185 P.3d at 1263
    .
    [¶12] Our settled rules of contract interpretation require that once we determine a
    contract is unambiguous, we determine the intention of the parties from the words of the
    contract and the context in which it was written. Hunter v. Reece, 
    2011 WY 97
    , ¶ 17,
    
    253 P.3d 497
    , 502 (Wyo. 2011); Comet Energy Servs., LLC v. Powder River Oil & Gas
    Ventures, LLC, 
    2010 WY 82
    , ¶ 13, 
    239 P.3d 382
    , 386 (Wyo. 2010) (Comet II); Amoco
    Prod. 
    Co., 612 P.2d at 465
    . We consider the contract as a whole and interpretation is a
    matter of law. 
    Id. [¶13] Section
    1.5, read in its entirety, indicates that the parties’ overarching intent was to
    ensure that all those who worked on the P & N job were paid in full, and evidence of that
    was to be obtained from several sources, including directly from the contractor and
    subcontractors, and by affidavit from P & N. “Our rules of interpretation require that we
    interpret a contract as a whole, reading each provision in light of all the others to find
    their plain meaning.” Pope v. Rosenberg, 
    2015 WY 142
    , ¶ 20, 
    361 P.3d 824
    , 830 (Wyo.
    2015) (citation omitted). The disputed language sets forth two requirements that must be
    met before the Mall is obligated to pay the finish allowance.
    [¶14] The first portion of section 1.5(b) requires that P & N furnish “evidence
    satisfactory to [the Mall] from its general contractor and any subcontractors that any and
    all liens that have been, or may be, filed have been satisfied of record or waived” before
    it is entitled to payment of the finish allowance. P & N argues that since the statutory
    time limit for filing a lien has passed, liens can no longer be filed and thus the terms of
    this provision have, in essence, been met.
    [¶15] We begin by looking at the plain language of the provision. It requires that (1)
    P & N provide to the Mall evidence from the general and subcontractors that any liens
    4
    filed by the general and subcontractors have been satisfied and that all other liens that
    may be filed have been either satisfied or waived, and (2) the Mall must be satisfied with
    the evidence provided. P & N claims the intent of this provision was to make sure there
    were no liens on the property, and that the Mall engaged in bad faith when it refused to
    accept P & N’s statement that no liens have been filed and any other liens have been
    waived, and instead insisted P & N satisfy it with written lien waivers from CCI and the
    subcontractors. Every contract imposes on the parties a duty of good faith and fair
    dealing in its performance and enforcement. Scherer Constr., LLC v. Hedquist Constr.,
    Inc., 
    2001 WY 23
    , ¶ 18, 
    18 P.3d 645
    , 652 (Wyo. 2001). While “[s]ubterfuges and
    evasions” can violate the obligation of good faith, 
    id. (quoting Restatement
    (Second) of
    Contracts § 205, comment d (1981)), courts have held that the insistence on compliance
    with the terms of a contract will not rise to the level of bad faith. See Thalle Constr. Co.
    v. City of New York, 
    256 A.D.2d 157
    (NY App. Div. 1998). That is particularly true here,
    where one of the terms of the contract gives the Mall discretion to determine whether the
    evidence of lien release or waiver is satisfactory.
    [¶16] While we cannot conclude that the Mall acted in bad faith, we would be hard
    pressed to conclude that, as a practical matter, the release or waiver requirement has not
    been satisfied by the passage of time. However, the second part of section 1.5(b) requires
    that “all work” be paid for before P & N is entitled to the finish allowance. The Mall
    argues that this provision is unambiguous and that “all work” includes work performed
    by not just the general contractor, but the subcontractors as well. Because it is
    undisputed that numerous subcontractors have not been paid, the Mall claims that this
    provision has not been satisfied. P & N also contends that the Lease provision is
    unambiguous, but claims it requires only that P & N pay the full cost of construction to
    CCI and provide an affidavit to that effect to the Mall.
    [¶17] We afford words in a contract the plain meaning that a reasonable person would
    give to them. Hunter, 
    2011 WY 97
    , ¶ 17, 253, P.3d at 502. “All” means everything. In
    Caballo Coal Company v. Fidelity Exploration & Production Company, 
    2004 WY 6
    , ¶ 4,
    
    84 P.3d 311
    , 313 (Wyo. 2004), we considered the meaning of deed language granting
    coal “[t]ogether with all of Grantor’s undivided interest in and to all other minerals,
    metallic or nonmetallic contained in or associated with” coal deposits conveyed coalbed
    methane gas to the grantee. (Emphasis added.) We concluded that the “clear language”
    of the deeds “expressly convey[ed] ownership of all metallic and nonmetallic minerals,”
    
    id. at ¶
    17, 84 P.3d at 318 
    (emphasis in original), and that a “reasonable interpretation of
    the intent of the grantors expressed within the deeds is that [they] simply intended to
    convey everything located within the coal seam.” 
    Id. at ¶
    19, 84 P.3d at 318
    . Likewise,
    “all work,” or the whole amount of work, on this project includes the work performed by
    the subcontractors. Thus, we find the language of section 1.5(b) requiring “all work” to
    be paid for is unambiguous and requires every individual component of work to be paid
    before the finish allowance becomes due.
    5
    [¶18] The affidavit P & N submitted to the Mall stated:
    The total cost of the construction was three hundred eight
    thousand nine hundred twenty nine and 55/100 dollars
    ($308,929.55). The cost was paid in full by me to CCI.
    P & N claims that the affidavit complies with the terms of section 1.5(b), but it does not
    say that “all work has been paid for,” as required by the Lease. Had the parties intended
    that only the general contractor needed to be paid in order for the finish allowance to
    come due, they could have used language to that effect, such as, “the general contractor
    has been paid in full.” Instead, they used the term “all work.” We will not “rewrite
    contracts under the guise of interpretation . . . .” Comet I, 
    2008 WY 69
    , ¶ 
    11, 185 P.3d at 1263
    . We interpret this provision according to its clear language, and conclude that the
    parties intended to include work by subcontractors on the project as work that must be
    paid for before the finish allowance became due. Because all work has not been paid for
    on this project, the Mall was entitled to summary judgment.
    [¶19] P & N asks us to examine the terms of its agreement with CCI to determine the
    intent of the disputed language in its contract with the Mall. “While unambiguous
    contract language is generally interpreted without resort to extrinsic evidence, it need not
    be interpreted in a vacuum.” 11 Samuel Williston, Treatise on the Law of Contracts
    § 30:6, at 108 (Richard A. Lord ed., 4th ed. 2012); see also Pokorny v. Salas, 
    2003 WY 159
    , ¶ 23, 
    81 P.3d 171
    , 177-78 (Wyo. 2003). “We consider the language in the context in
    which it was written, looking to the surrounding circumstances, the subject matter, and
    the purpose of the agreement to ascertain the intent of the parties at the time the
    agreement was made.” Comet II, 
    2010 WY 82
    , ¶ 
    13, 239 P.3d at 386
    .3 However, we
    have rejected the use of extrinsic evidence to determine whether a contract is ambiguous:
    The ambiguity which justifies examining extrinsic evidence
    must exist . . . in the language of the document itself. It
    cannot be found in the subsequent events or conduct of the
    parties, matters which are extrinsic evidence. The suggestion
    3
    The identity of the party drafting the contract is one of those surrounding circumstances that we may
    consider. See Williston, supra, § 30:5, at 84 (“Extrinsic evidence properly considered in deciding
    whether the contract is ambiguous may include . . . whether one of the parties prepared the instrument, so
    that the language should be construed most strongly against it.”); see Nuhome Invs., LLC v. Weller, 
    2003 WY 171
    , ¶ 17, 
    81 P.3d 940
    , 947 (Wyo. 2003) (considering identity of drafter to determine whether
    unequal bargaining power existed); Collins v. Finnell, 
    2001 WY 74
    , ¶ 19, 
    29 P.3d 93
    , 100 (Wyo. 2001)
    (ambiguity is construed against the drafter); Emulsified Asphalt, Inc. of Wyo. v. Transp. Comm’n of Wyo.,
    
    970 P.2d 858
    , 864 (Wyo. 1998) (same). It is unclear from the record which party drafted the Lease,
    however, the Lease itself contains many deletions and additions, indicating that a significant number of
    changes had been made from its original version.
    6
    that one should examine extrinsic evidence to determine
    whether extrinsic evidence may be examined is circuitous.
    Wolter v. Equitable Res. Energy Co., Western Region, 
    979 P.2d 948
    , 952 (Wyo. 1999)
    (citation omitted and emphasis in original); see also Thornock v PacifiCorp., 
    2016 WY 93
    , ¶ 20, 
    379 P.3d 175
    , 181 (Wyo. 2016).
    [¶20] P & N emphasizes the terms of its agreement with CCI prohibiting P & N from
    communicating with subcontractors. It argues that this prohibition is further evidence of
    P & N’s intent that only CCI must be paid before the finish allowance is due because
    P & N had no contracts with or invoices from the subcontractors. “A party’s subjective
    intent is not relevant in contract interpretation cases because we use an objective
    approach to interpret contracts.” Omohundro, 
    2009 WY 38
    , ¶¶ 
    24-25, 202 P.3d at 1085
    (declining to consider affidavit regarding parties’ subjective intent regarding covenants).
    Moreover, we note that P & N entered into the Lease with the Mall on February 11, 2014,
    while its contract with CCI is dated May 5, 2014. Thus, even if we were to consider the
    terms of the CCI contract, we are not persuaded that those terms impacted P & N’s intent
    as it entered into its contract with the Mall.
    [¶21] P & N also points to the standard and custom in the construction industry that the
    general contractor is responsible for paying the subcontractors in support of its argument
    that the intent was only to require P & N to pay CCI, citing Black’s Law Dictionary’s
    definition of general contractor:
    One who contracts for the construction of an entire building
    or project, rather than for a portion of the work. The general
    contractor hires subcontractors, coordinates all work, and is
    responsible for payment to the subcontractors.
    Black’s Law Dictionary 683 (6th ed. 1990). P & N argues that because it paid CCI, the
    general contractor, it paid for all work and it was CCI’s responsibility to pay the
    subcontractors. P & N claims that because it has clean hands, it should not be punished
    by not receiving the finish allowance or by having to pay the subcontractors directly
    (when it has already paid CCI) in order to receive the finish allowance.4
    [¶22] We cannot rewrite the terms of the Lease. Brashear v. Richardson Constr., Inc.,
    
    10 P.3d 1115
    , 1118 (Wyo. 2000). “[T]he question whether a bargain is smart or foolish,
    or economically efficient or disastrous, is not ordinarily a legitimate subject of judicial
    inquiry.” Williston, supra, § 31:5, at 455; see Sowerwine v. Keith, 
    997 P.2d 1018
    , 1020-
    21 (Wyo. 2000). “[C]ourts are not at liberty to rescue parties from the consequences of
    4
    In their briefs, the parties dispute whether the Mall could or could not be sued by unpaid subcontractors under a
    variety of legal theories. That question is not before the Court and is not relevant to the unambiguous terms of the
    Lease.
    7
    their unwisely made bargains and we cannot rewrite the contract under the guise of
    judicial construction.” Hunter, 
    2011 WY 97
    , ¶ 
    23, 253 P.3d at 503
    (internal quotation
    marks and citations omitted).
    [¶23] P & N was in a better position than the Mall to ensure subcontractors were paid.
    Accordingly, the Lease put the burden on P & N to ensure that all work was paid for, and
    it specifically required P & N to provide an affidavit to that effect. Read together, the
    terms of section 1.5(b) indicate that the intent of the parties was for the general and the
    subcontractors to be paid, and the affidavit stating that CCI had been paid did not satisfy
    that requirement.
    CONCLUSION
    [¶24] The Lease provision requiring P & N to furnish “evidence satisfactory to [the
    Mall] from its general contractor and any subcontractors that any and all liens that have
    been, or may be, filed have been satisfied of record or waived” and an “affidavit that all
    work has been paid for” before the finish allowance becomes due is unambiguous. Even
    if we were to conclude that the passage of time has fulfilled the lien satisfaction and
    waiver requirement, all work completed by the subcontractors has not been paid for.
    Accordingly, P & N is not entitled to the finish allowance from the Mall. The district
    court’s summary judgment in favor of the Mall is affirmed.
    8
    HILL, Justice, dissenting, with whom DAVIS, Justice, joins.
    [¶25] I agree that the lease between the Mall and P & N is unambiguous, but because I
    interpret the lease differently from the majority opinion, I respectfully dissent.
    The disputed lease provision reads:
    Section 1.5 Landlord’s Contribution to Construction
    of Leased Premises. Of the costs incurred by Tenant in
    constructing or improving qualified long-term real property
    for use in Tenant’s trade or business at the Leased Premises
    (the “Leasehold Improvements”), Landlord agrees to pay to
    Tenant the lesser of (a) the actual cost of said construction of
    or improvements to said real property made in accordance
    with this Exhibit, or (b) the sum of One Hundred Fifty
    Thousand One Hundred Eighty and 00/100 Dollars
    ($150,180.00), less any sums owed to Landlord by Tenant
    under this Lease or this Exhibit, and the excess, if any, shall
    be paid by Tenant. Landlord’s obligations under the
    preceding sentence shall not bind any Mortgagee Party of the
    Shopping Center nor any party acquiring title through or
    under any such Mortgage Party. The sum to be paid by
    Landlord hereunder shall be paid by check to Tenant after all
    of the following conditions shall have been satisfied:
    ***
    (b)    Tenant shall have furnished evidence
    satisfactory to Landlord from its general contractor and
    any subcontractors that any and all liens that have
    been, or may be, filed have been satisfied of record or
    waived and an affidavit that all work has been paid
    for[.]
    [¶26] I view this term as imposing two separate but related obligations on P & N, as
    Tenant. First, P & N is obligated to furnish evidence satisfactory to the Mall from its
    general contractor and any subcontractors that any and all liens that have been filed, or
    may be filed, have been satisfied of record or waived. Second, P & N is obligated to
    furnish an affidavit that all work has been paid for.
    [¶27] With respect to the first obligation, I view this as an obligation to perform that is
    subject to a condition precedent. A condition precedent is “an act or event, other than a
    lapse of time, which must exist or occur before a duty of immediate performance of a
    promise arises.” Mad River Boat Trips, Inc. v. Jackson Hole Whitewater, Inc., 
    803 P.2d 366
    , 368 (Wyo. 1990) (quoting Robert W. Anderson Housewrecking and Excavating, Inc.
    9
    v. Board of Trustees, School District No. 25, Fremont County, Wyoming, 
    681 P.2d 1326
    ,
    1331 (Wyo. 1984)). A condition precedent need not be labeled as such in a contract, and
    what is instead controlling is whether the contract language creates a contingency on
    which performance depends. 
    Id. at 367-68
    (finding Forest Service approval to be a
    condition precedent to defendant’s obligation to transfer special use permit to plaintiff
    even though Forest Service approval was not contained in section of contract labeled
    “Conditions Precedent”).
    [¶28] In my view, P & N’s obligation to furnish evidence satisfactory to the Mall was
    conditioned on the requirement that at least one of two events occurred: 1) a lien was
    filed against the Mall’s property; or 2) a lien may be filed against the Mall’s property. It
    is undisputed that neither event occurred. No lien was filed against the Mall’s property in
    relation to P & N’s project, and because the time for any lien to be filed has expired, no
    lien may be filed. The condition precedent to P & N’s obligation to perform did not
    come to pass, and P & N was therefore under no obligation to provide evidence of any
    type concerning lien satisfaction or lien waivers.
    [¶29] P & N’s second obligation is to furnish “an affidavit that all work has been paid
    for.” I do not agree that this provision should be read to refer back to both subcontractors
    and general contractors. The term requires that P & N furnish an affidavit. Because it is
    P & N that is to provide the affidavit, I believe a reasonable reading of the requirement is
    one that requires P & N to attest that it has performed its obligation to pay for all work. I
    do not agree the language may be extended to add a requirement that P & N attest that the
    general contractor has also performed all of its separate payment obligations.
    [¶30] This interpretation is borne out by the requirement this provision imposes with
    regard to liens against the Mall's property. With respect to liens that have been or may be
    filed, the provision requires that P & N furnish evidence that such liens have been either
    satisfied or waived. A lien waiver suggests that there are amounts owing to the party that
    has agreed to waive its lien, which is inconsistent with the meaning the Mall asks this
    Court to give the phrase “all work has been paid for.” If “all work has been paid for”
    means, as the Mall contends, that the general contractor and all subcontractors are
    satisfied, there would be no occasion to need or require a lien waiver. The Mall’s
    willingness to accept a lien waiver rather than satisfaction of that lien simply cannot be
    reconciled with its insistence that “all work has been paid for” means P & N must attest
    not only that it has paid the amounts it was obligated to pay but also that there are no
    outstanding claims against the general contractor.
    [¶31] The record of nonpayment to the subcontractors on this project is troubling. It is
    undisputed, however, that P & N paid CCI, the general contractor, for all the work done
    on the project. P & N did not breach its payment obligations under its contract with CCI,
    and P & N had no contracts with the subcontractors. Any breach resulting in
    underpayment of subcontractors was a breach of CCI’s separate contracts with the
    10
    subcontractors, contracts to which P & N was not a party. I am unwilling to read section
    1.5(b) of the lease to make P & N a guarantor under the separate contracts between CCI
    and the subcontractors. I believe the more reasonable interpretation to give section
    1.5(b), and the one that avoids inconsistencies between its terms, is to interpret the
    requirement that P & N furnish an affidavit “that all work has been paid for” to mean P &
    N must attest that it, the affiant, has paid for all work it was obligated to pay for.
    [¶32] My final observation relates to the opening paragraph of section 1.5. In that
    paragraph, the Mall promises to P & N a payment of $150,180.00, upon satisfaction of
    the enumerated conditions. That opening paragraph also put P & N on notice, however,
    that the Mall would decrease that amount by any outstanding sums owed to the Mall by P
    & N under the terms of the lease. It seems to me that the Mall could have added similar
    language regarding outstanding amounts owing to subcontractors, if its intent was to
    ensure not only that P & N met its payment obligations, but that all subcontractors were
    paid in full. This certainly would have been a more transparent imposition of that
    payment obligation.
    11
    

Document Info

Docket Number: S-16-0244

Citation Numbers: 2017 WY 62, 395 P.3d 1101

Filed Date: 5/31/2017

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (20)

Pokorny v. Salas , 81 P.3d 171 ( 2003 )

Emulsified Asphalt, Inc. v. Transportation Commission of ... , 970 P.2d 858 ( 1998 )

MULLINNIX LLC v. HKB Royalty Trust , 126 P.3d 909 ( 2006 )

Caballo Coal Company v. Fidelity Exploration & Production ... , 84 P.3d 311 ( 2004 )

Scherer Construction, LLC v. Hedquist Construction, Inc. , 18 P.3d 645 ( 2001 )

Amoco Production Co. v. Stauffer Chemical Co. , 612 P.2d 463 ( 1980 )

Hunter v. Reece , 253 P.3d 497 ( 2011 )

Omohundro v. Sullivan , 202 P.3d 1077 ( 2009 )

Sowerwine v. Keith , 997 P.2d 1018 ( 2000 )

leeks-canyon-ranch-llc-a-wyoming-limited-liability-company-leeks-canyon , 2014 WY 62 ( 2014 )

David A. Pope, CPA LLC and David A. Pope, Individually v. ... , 361 P.3d 824 ( 2015 )

Jason Thornock v. Pacificorp, an Oregon Company , 379 P.3d 175 ( 2016 )

Bruce B. Williams v. Laura L. Sundstrom, as Campbell County ... , 385 P.3d 789 ( 2016 )

Anadarko Land Corporation F/K/A Union Pacific Land ... , 389 P.3d 1218 ( 2017 )

Comet Energy Services, LLC v. Powder River Oil & Gas ... , 185 P.3d 1259 ( 2008 )

Wolter v. Equitable Resources Energy Co. , 979 P.2d 948 ( 1999 )

Robert W. Anderson House-Wrecking & Excavating, Inc. v. ... , 681 P.2d 1326 ( 1984 )

Brashear v. Richardson Constr., Inc. , 10 P.3d 1115 ( 2000 )

Comet Energy Services, LLC v. Powder River Oil & Gas ... , 239 P.3d 382 ( 2010 )

Collins v. Finnell , 29 P.3d 93 ( 2001 )

View All Authorities »