Columbia Gas v. Bailey , 2023 Ohio 1245 ( 2023 )


Menu:
  • [Cite as Columbia Gas v. Bailey, 
    2023-Ohio-1245
    .]
    IN THE COURT OF APPEALS OF OHIO
    THIRD APPELLATE DISTRICT
    UNION COUNTY
    COLUMBIA GAS OF OHIO, INC.,
    PETITIONER-APPELLANT/                           CASE NO. 14-22-13
    CROSS-APPELLEE,
    v.
    PATRICK E. BAILEY, ET AL.,                              OPINION
    RESPONDENTS-APPELLEES/
    CROSS-APPELLANTS.
    COLUMBIA GAS OF OHIO, INC.,
    PETITIONER-APPELLANT/                           CASE NO. 14-22-14
    CROSS-APPELLEE,
    v.
    DON BAILEY, JR., SUCCESSOR
    TRUSTEE OF THE ARNO RENNER
    TRUST DATED APRIL 24, 1997, ET AL.,                     OPINION
    RESPONDENTS-APPELLEES/
    CROSS-APPELLANTS.
    Appeals from Union County Common Pleas Court
    Trial Court Nos. 21-CV-0112 and 21-CV-0113
    Judgments Affirmed in Part, Reversed in Part and Cause Remanded
    Date of Decision: April 17, 2023
    Case No. 14-22-13 and 14-22-14
    APPEARANCES:
    Adam C. Smith for Appellant/Petitioner Columbia Gas of Ohio, Inc.
    David Watkins for Appellees/Cross-Appellants/Respondents
    Ryan P. Sherman for Amici Curiae, Ohio Power Company and AEP
    Ohio Transmission Co., Inc.
    ZIMMERMAN, J.
    {¶1} Petitioner-appellant/cross-appellee, Columbia Gas of Ohio, Inc.
    (“Columbia Gas”), appeals the April 26, 2022 judgment of the Union County Court
    of Common Pleas denying its petitions for the appropriation of easement rights.
    Respondents-appellees/cross-appellants, Don Bailey, Jr., Successor Trustee of the
    Arno Renner Trust dated April 24, 1997 (“Don”), Charles Peter Renner (“Renner”),
    Patrick E. Bailey (“Patrick”), and Whitney Bailey (“Whitney”) (collectively,
    “respondents”), appeal the trial court’s determination that an agricultural easement
    does not prevent Columbia Gas’s petitions. For the reasons that follow, affirm in
    part and reverse in part.
    {¶2} Much like our previous and similar case, this case involves a dispute
    involving Columbia Gas over the necessity of easement rights it sought through
    eminent domain for the construction, operation, and maintenance of a natural-gas
    pipeline. See Columbia Gas of Ohio, Inc. v. Phelps Preferred Investments, LLC, 3d
    -2-
    Case No. 14-22-13 and 14-22-14
    Dist. Union No. 14-22-07, 
    2022-Ohio-2540
    . However, the main issues in this case
    is whether Columbia Gas is entitled to a necessity presumption under R.C.
    163.09(B)(1) and whether respondents’ agricultural easement precludes an
    appropriation of easement rights.
    Background
    {¶3} The Arno Renner farm originally comprised 231.25 acres of farmland
    in Marysville, Ohio (the “protected property”). However, the protected property is
    encumbered by an agricultural easement (as defined under R.C. 5301.67(C)) granted
    in favor of the Ohio Department of Agriculture (“ODA”). The easement was filed
    on August 21, 2003, recorded in Volume 509 of the Official Records at Page 369,
    in the Union County, Ohio Recorder’s Office. Later, the protected property was
    devised and divided. As a result, Don and Renner became the successive owners of
    121 acres of the protected property, while and Patrick and Whitney became the
    successive owners of 110.25 acres of the protected property.
    {¶4} Before filing its verified petitions in the trial court, Columbia Gas—a
    public utility—filed a letter-of-notification application under R.C. 4906.06 with the
    Ohio Power Siting Board (“OPSB”) on December 20, 2019. Importantly, Columbia
    Gas sought approval from the OPSB under R.C. 4906.03(F)(3) since it intended to
    construct a new natural-gas pipeline which would be greater than one-mile length
    but not greater than five miles in length. Specifically, Columbia Gas sought the
    -3-
    Case No. 14-22-13 and 14-22-14
    OPSB’s approval to construct a natural-gas pipeline that is approximately 4.78 miles
    in length, consisting of a 12-inch diameter “coated steel pipe with a wall thickness
    of 0.375 inches,” and “a Maximum Allowable Operating Pressure (“MAOP”) of
    190 pounds per square inch gauge * * * .” (Petitioner’s Ex. 1).
    {¶5} In its application, Columbia Gas generally represented to the OPSB that
    it had “not obtained any easements along the right-of-way” under the section of its
    application discussing the “list of properties for which the applicant ha[d] obtained
    easements * * * necessary to construct and operate the facility and a list of the
    additional properties for which such agreements have not been obtained.” (Id.).
    Nevertheless, Columbia Gas indicated that it was “working to obtain easements
    from the individuals and entities” identified in the appendix and that it would “not
    begin construction until all easements [were] secured.”        (Id.).   Significantly,
    Columbia Gas’s application did not include any further information regarding the
    specific easements it sought from the landowners in that section or in the
    corresponding appendix.
    {¶6} However, in the general information portion of the application,
    Columbia Gas informed the OPSB that “[t]he majority of the 12-inch natural gas
    main will be constructed within permanent private pipeline easements * * * as
    depicted in the construction plans in Appendix B.” (Id.). Further, Columbia Gas
    indicated to the OPSB that “the proposed pipeline route will only include a 75-foot
    -4-
    Case No. 14-22-13 and 14-22-14
    wide (50-foot permanent easement and 25-foot temporary easement) construction
    footprint” in the section of its application discussing the impact to wetlands. (Id.).
    {¶7} In its July 9, 2020 staff report of investigation, the OPSB documented
    that the pipeline project “crosses a parcel protected by an agricultural easement with
    the [ODA].” (Doc. No. 1, Ex. 3). However, the report reflects the findings that
    “[t]he easement held by ODA states that it does not preclude installation over or
    under the protected property for the purpose of providing gas” and that “[f]arming
    activities would be able to resume within the pipeline easement following
    completion of construction.” (Id.).
    {¶8} Ultimately, on August 27, 2020, the OPSB concluded that Columbia
    Gas’s letter-of-notification application satisfied the requirements enumerated under
    R.C. 4906.10.      Notably, the OPSB concluded that “Columbia [Gas] has
    demonstrated the basis of need for the Project” since “the Marysville area requires
    additional demand for natural gas and that the proposed Project, especially when
    connected to Columbia’s Columbus Northern Loop system, will provide an
    additional supply of natural gas.” (Case No. 21CV0112, Doc. No. 1, Ex. 17); (Case
    No. 21CV0113, Doc. No. 1, Ex. 17).
    {¶9} Furthermore, the OPSB concluded (based on the findings contained
    within its staff report of investigation) that “[l]and use throughout the Project area
    consists primarily of agricultural uses” and that “[t]he Project also crosses an
    -5-
    Case No. 14-22-13 and 14-22-14
    agricultural easement held by the [ODA]; however, the easement does not preclude
    installation over or under the property for purposes of providing gas. Farming
    activities can resume within the Project easement following completion of
    construction.” (Id.); (Id.).
    {¶10} As a result, the OPSB (conditionally) issued a certificate under R.C.
    Chapter 4906 to Columbia Gas.           Following the conditional approval of its
    certificate, Columbia Gas sought to appropriate the necessary easement rights from
    the respondents.
    {¶11} However, when negotiations with the respondents failed, Columbia
    Gas, filed a verified petition for the appropriation of easement rights in real property
    on July 22, 2021 in the Union County Court of Common Pleas against Patrick,
    Whitney, and the ODA (in case number 21CV0112) and a petition against Don,
    Renner, and the ODA (in case number 21CV0113).
    {¶12} In its petitions, Columbia Gas attached the specific easements rights
    that it sought from the respondents in relation to its pipeline project. In particular,
    the easements granted Columbia Gas a “permanent-easement area” “located within
    the limits of a fifty foot (50’) wide easement * * * as shown on Exhibit B attached
    * * * and made part” of the easement. (Case No. 21CV0112, Doc. No. 1, Ex. 18);
    (Case No. 21CV0113, Doc. No. 1, Ex. 18).            Similarly, the easements granted
    Columbia Gas a “temporary-easement area”
    -6-
    Case No. 14-22-13 and 14-22-14
    to temporarily use an additional twenty-five feet (25’) of space
    adjoining said Permanent Easement Area * * * , as shown on Exhibit
    B, only for the purpose of enabling [Columbia Gas] to initially
    construct the pipeline and to later alter, replace, and repair said
    pipeline and to conduct all activities incident [to], including
    restoration or clean-up activities.
    (Id.); (Id.). Significantly, Exhibit B depicts a “gas pipeline easement to [Columbia
    Gas]” and a “25’ perpetual temporary easement.” (Emphasis added.) (Id.); (Id.).
    {¶13} The ODA filed its answers to Columbia Gas’s petitions on September
    27, 2021. Patrick and Whitney filed their answer to Columbia Gas’s petition on
    October 1, 2021. Don and Renner filed their answer to Columbia Gas’s petition on
    October 5, 2021.
    {¶14} On October 22, 2021, the respondents filed motions for a hearing
    under R.C. 163.09. Because the ODA did “not interpret the proposed utility
    easement as violating the existing agricultural easement,” it filed a motion on
    November 10, 2021 requesting to be excused from the appropriation-necessity
    hearing. (Case No. 21CV0112, Doc. No. 31); (Case No. 21CV0113, Doc. No. 31).
    As evidence in support of its motion, the ODA submitted the affidavit of Sarah
    Huffman (“Huffman”), the executive director of the Office of Farmland
    Preservation for the ODA. In the affidavit, Huffman averred that “[a]ccording to
    Provision 7.1 of the Agricultural Easement,” the ODA “has the sole and exclusive
    discretion to enforce the terms of the Agricultural Easement.” (Id.); (Id.). Based on
    that determination, Huffman further averred that the
    -7-
    Case No. 14-22-13 and 14-22-14
    ODA has determined in its sole and exclusive discretion that the utility
    easement as proposed by Columbia Gas does not violate the terms of
    the Agricultural Easement. This is based on correspondence from
    Melissa Thompson [(“Thompson”)], Director of Regulatory Policy at
    Columbia Gas, dated February 24, 2020 * * * . Further, the proposed
    utility easements attached to the Petitions are consistent with this
    correspondence.
    (Id.); (Id.). Patrick and Whitney as well as Don and Renner filed memoranda in
    opposition to the ODA’s motion, respectively, on November 15, 2021. However,
    the trial court granted the ODA’s motion that same day.
    {¶15} On November 12, 2021, Columbia Gas filed a motion in both cases to
    strike “the affirmative defenses raised by” the respondents, arguing they are
    improper necessity challenges. The respondents filed memoranda in opposition to
    Columbia Gas’s motion to strike on November 16, 18, 23, and 24, 2021. On
    November 30, 2021, Columbia Gas filed its replies to the respondents’ memoranda
    in opposition to its motions to strike.
    {¶16} The trial court held necessity hearings on November 17, 2021 and
    February 22 and 25, 2022, at which Columbia Gas presented the testimony of four
    witnesses: Thompson; Matthew Opfer (“Opfer”), the manager of major projects for
    NiSource; Huffman; and Tiffany Fritchley (“Fritchley”), a natural resources
    permitting coordinator for Columbia Gas and NiSource.
    {¶17} In response, the respondents presented the testimony of five witnesses:
    Ryan Conklin (“Conklin”), an attorney retained to represent the respondents in
    -8-
    Case No. 14-22-13 and 14-22-14
    negotiations with Columbia Gas regarding the easement rights sought by Columbia
    Gas; Patrick; Fred Dailey (“Dailey”), Director of the ODA from 1991-2007; Patrick
    Hornschemeier (“Hornschemeier”), an expert in conservation easements; and Mark
    Wilson (“Wilson”), an expert agronomist.
    {¶18} On November 17, 2021, Thompson identified Columbia Gas’s letter-
    of-notification application (filed with the OPSB) and testified that it reflects that
    the proposed need of the project is to increase economic development
    and service reliability near Marysville in Union County and the
    project will, also, provide natural gas service to new industry and
    residential development near the project alignment and provide
    existing customers an increased capacity for reliable natural gas
    service.
    (Nov. 17, 2021 Tr. at 34).
    {¶19} Thompson explained Columbia Gas’s approach to acquiring the
    easement rights needed for the project from the respondents.             According to
    Thompson, Columbia Gas is generally “seeking the right to construct, operate and
    maintain the pipeline.” (Id. at 55-56). She also testified that the specific easement
    terms include “the right to lay a pipeline subservice on the premise” and “[t]he right
    to operate and maintain without restriction limitation, repair and replace a pipeline
    without interruption to service together with necessary valves and other necessary
    appurtenances.” (Id. at 56). Furthermore, Thompson testified that Exhibit B to
    Columbia Gas’s letter-of-notification application depicts the permanent and
    temporary easements.
    -9-
    Case No. 14-22-13 and 14-22-14
    {¶20} Moreover, Thompson testified that the specific easement rights that
    Columbia Gas sought from the respondents in relation to its pipeline project
    “provide for a permanent 50 foot wide easement and a 25 foot temporary easement
    * * * .” (Id. at 58). Thompson acknowledged the categorization of the “temporary
    perpetual easement” and described such easement as “necessary when Columbia
    [Gas] is doing its initial construction of the pipeline, as well as any future repairs or
    maintenance on the pipeline that require that kind of extra space for its equipment.”
    (Id.).   She further described that Columbia Gas “does not plan to utilize or
    permanently encumber that 25 foot easement, * * * every day[, u]nlike a permanent
    easement where Columbia [Gas] is laying a pipeline it will be permanently
    encumbering that easement area.” (Id.). In sum, she clarified that the temporary
    easement is “characterized as perpetual” because it grants Columbia Gas “the ability
    * * * to utilize it when it needs it for various specific activities” as described in the
    easement. (Id. at 59).
    {¶21} On cross-examination, Thompson acknowledged that the easements
    do not place restrictions on the size of the pipeline that may be installed or as to the
    type of material that may be transmitted through the pipeline. Moreover, Thompson
    agreed that the temporary easements do not include any temporal limitation.
    Further, Thompson testified that the purpose of the temporary easement is the initial
    -10-
    Case No. 14-22-13 and 14-22-14
    construction and the maintenance of the pipeline, which is also the basis of the
    permanent easement.
    {¶22} Opfer testified that, in his role for NiSource, he is responsible for
    ensuring the execution of the pipeline project at issue in this case. As relevant here,
    he testified that the permanent and temporary easements are necessary because that
    is the area required “to safely and efficiently construct the pipeline and then properly
    maintain and operate it moving forward.” (Id. at 81). He further described (using
    technical detail) why such easements are necessary for the construction and
    maintenance of the pipeline.
    {¶23} On February 22, 2022, Dailey testified regarding the importance of
    preserving farmland in Ohio for the public benefit and highlighted that “agriculture
    is the largest industry in Ohio.” (Feb. 22, 2022, Vol. I, Tr. at 106). Importantly,
    Dailey identified Union, County as situated in “the most productive ground on this
    earth.” (Id.). Further, he provided the trial court with an overview of his work as
    the former director of the ODA in establishing the ODA’s Office of Farmland
    Preservation from which Ohio’s agricultural-easement program evolved.
    {¶24} Critically, Dailey identified Respondents’ Exhibit N as the ODA’s
    Office of Farmland Preservation, Ohio Agricultural Easement Donation Program
    Guidelines that he helped codify in 2006. Dailey testified that the guidelines restrict
    that
    -11-
    Case No. 14-22-13 and 14-22-14
    [t]here cannot be any third party interest in the land that are not
    conducive to agriculture as determined by the Director of ODA.
    Examples of such interest would be surface mining leases, water,
    sewer, utility lines or roads and highways outside of existing right-of-
    ways or other development activities that would damage the topsoil
    or subsoil of the farm.
    (Id. at 112). Dailey testified that the current version of the guidelines contains the
    same restriction. (See Respondents’ Ex. O). According to Dailey, the installation
    of Columbia Gas’s pipeline project does not comply with the ODA’s guidelines.
    {¶25} Regarding the agricultural easement at issue in this case, Dailey
    testified that he acknowledged the agricultural deed as the grantee in his capacity as
    the director of the ODA. Relevantly, the agricultural easement provides that the
    “protected property” “consists of land devoted exclusively to agricultural use as
    defined by [R.C. 5713.30] and that it is valued for real property taxation at its current
    value for agricultural uses under [R.C. 5713.31] or that it constitutes a homestead”
    and that the grantor “has an interest in preserving the property for agricultural use.”
    (Respondents’ Ex. H). Further, the agricultural easement critically imparts that the
    grantee—the ODA—“is authorized [under R.C. 901.21] to hold agricultural
    easements * * * for the public purpose of retaining the Protected Property
    predominantly in agriculture.” (Emphasis added.) (Id.).
    {¶26} Moreover, paragraph E of the agricultural easement describes Ohio’s
    agricultural-conservation policy (which is consistent with the Federal Farmland
    Protection Act) and provides that “Ohio has a clearly delineated conservation policy
    -12-
    Case No. 14-22-13 and 14-22-14
    to preserve and promote agriculture and agricultural land for a significant public
    benefit” and that the ODA “is charged with the responsibility of protecting and
    promoting agriculture, including the preservation of Ohio’s farmland by accepting
    agricultural easements [under R.C. 901.21(B)].” (Id.).
    {¶27} Importantly, the agricultural easement’s statement of purpose reflects
    that “[i]t is the purpose of this Easement to assure that the Protected Property will
    be retained predominantly in agricultural use by preserving and protecting its
    agricultural soils and viability through a perpetual restriction on the use of the
    Protected Property.”    (Id.).   The agricultural easement also lists “prohibited
    uses/restrictions” as including “any activity on or use of the Protected Property
    inconsistent with the purposes of this easement is prohibited” and that
    [t]he following activities are expressly prohibited, except as provided
    in Paragraph 4 below:
    3.1 Industrial or Commercial Activity – There shall be no industrial
    or commercial activity undertaken or allowed on the Protected
    Property, except as provided in Paragraph 4 below. No right of
    passage shall be granted or retained across or upon the Protected
    Property if that right of passage is used in conjunction with such
    prohibited activities.
    3.2 Structures – There shall be no new structures or placing of any *
    * * fence or sign (other than those signs permitted, required or allowed
    by the Grantee for appropriate management, prevention of hunting or
    trespass, etc.), asphalt, concrete pavement, * * * utility pole, * * *
    conduit line, or any other temporary or permanent structure or facility
    on the Protected Property, except as provided in Paragraph 4 below.
    ***
    -13-
    Case No. 14-22-13 and 14-22-14
    3.5 Topography – There shall be no ditching; draining; diking; filling;
    excavating; removal of topsoil, sand, gravel, rock, or other materials;
    or any change in the topography of the land in any manner, unless in
    accordance with the farm conservation plan referenced in Paragraph
    C above.
    ***
    3.8 Roads – There shall be no building of new roads, parking lots, or
    other paved surfaces, or the widening of existing such surfaces, except
    on the Farmstead Area, state or local highway rights-of-way * * * ,
    and those improvements permitted under Paragraph 4.11 below.
    (Emphasis sic.) (Id.).
    {¶28} Paragraph 4 addresses the rights reserved for the grantor. As relevant
    here, Paragraph 4.10 highlights “utility services” and provides that the
    “[i]nstallation, maintenance, repair, replacement, removal and
    relocation of electric, gas, geothermal, water facilities, sewer lines
    and/or other public or private utilities * * * over or under the Protected
    Property for the purpose of providing electrical, gas, water, sewer, or
    other utilities to serve improvements permitted herein, and the right
    to grant easements over and under the Protected Property for such
    purposes, is permitted without permission of the Grantee.
    (Emphasis added.) (Id.). Further, Paragraph 4.11 discusses “paving and road
    construction” and provides, in its relevant part, that “[c]onstruction of new roads,
    parking lots, or other paved surfaces, or the widening of such surfaces, are permitted
    outside the Farmstead Area consistent with the agricultural purposes of this
    Easement with the advance written permission of the Grantee” but that “[t]he
    Grantee shall not give such permission, unless the Grantee determines that the
    -14-
    Case No. 14-22-13 and 14-22-14
    proposed paving or covering of the soil, or the location of any such road, will not
    substantially diminish the agricultural values of the Protected Property.” (Id.).
    {¶29} Paragraph 7 of the agricultural easement discusses the grantee’s
    enforcement rights and remedies. It provides, in its relevant part, that “the Grantee
    shall have the following rights and remedies” “[i]n order to enforce the terms of this
    Easement.” (Id.).
    7.1 Remedies – The Grantee shall have the right to enforce by
    proceedings at law or in equity the provisions of this Easement
    including, but not limited to, the right to require the restoration of the
    Protected Property to its condition at the date of the grant of this
    Easement, subject to the reserved rights of the Grantor set forth herein.
    (Emphasis sic.) (Id.). Importantly, that paragraph also commands that “[t]he
    Grantee, or its successors or assigns, shall not waive or forfeit the right to take action
    as may be necessary to ensure compliance with the terms and conditions of this
    Easement by any prior failures to act.” (Emphasis added.) (Id.). It continues by
    requiring “the Grantor [to] notify Grantee of any occurrence which would adversely
    affect or interfere with the agricultural purposes of the Easement, whether caused
    by the acts or omissions of the Grantor or third parties, or by natural occurrences.”
    (Emphasis added.) (Id.).
    {¶30} To extinguish the agricultural easement, paragraph 13 provides, in its
    relevant part, that,
    [s]hould the Director of the [ODA], at the request of the Grantor,
    determine that conditions surrounding the Protected Property have
    -15-
    Case No. 14-22-13 and 14-22-14
    changed so much that it becomes impossible or impractical to fulfill
    the agricultural purpose of this Easement, then the Grantee may
    extinguish or modify this Easement, or, extinguishment of the
    easement may occur in whole or in party by judicial proceeding under
    applicable local, state, or federal laws.
    (Emphasis added.) (Id.). Similarly, Paragraph 16 requires that the grantee obtain
    the “written consent of the Grantor” to amend the easement. (Emphasis added.)
    (Id.). That paragraph further requires any “such amendment [to be] consistent with
    the ‘Statement of Purpose’ of this Easement”; “with the Grantee’s Easement
    amendment policies,” “with Section 170(h) of the U.S. Internal Revenue Code or
    any regulations promulgated in accordance with that section”; and to “be consistent
    with Section 5301.67 et. seq., of the Ohio Revised Code or any regulations
    promulgated pursuant to those laws.”            (Id.).   Finally, paragraph 22 of the
    agricultural easement provides that it “may not be changed, modified or discharged
    except by a writing signed by the duly authorized representatives of both the
    Grantor and the Grantee.” (Emphasis added.) (Id.).
    {¶31} Based on the language contained in the agricultural easement, Dailey
    testified that the installation of the pipeline would not be consistent with preserving
    and protecting the viability of the protected property’s soils. Dailey also testified
    that the installation of the pipeline would be inconsistent with Paragraphs 3.1
    (restricting industrial or commercial activity); 3.2 (restricting the construction of
    new structures); and 3.5 (restricting disturbing the topography) of the agricultural
    -16-
    Case No. 14-22-13 and 14-22-14
    easement. By way of historical example, Dailey testified that the City of Marysville
    approached the ODA in 2005 (when he was the director of the agency) regarding
    installing a sanitary-sewer line on the protected property and that the project was
    denied as being “inconsistent with the easement.” (Feb. 22, 2022 Tr., Vol. I, at 120).
    (See also Respondents’ Ex. I).
    {¶32} Moreover, Dailey testified that Huffman’s affidavit averring “that the
    utility easement * * * does not violate the terms of the Agricultural Easement”
    “looks incestuous” because Huffman’s determination—as opposed to consulting an
    outside, independent source—relies on Columbia Gas’s conclusion that its project
    is consistent with a predominantly agricultural purpose. (Feb. 22, 2022 Tr., Vol. I,
    at 118). Significantly, Dailey testified that Columbia Gas’s intended use of the
    property will not be predominately agricultural because there will be “changes to
    the topsoil and substrata” and because it will alter the agricultural “use of this
    ground.” (Id. at 119). Notably, Dailey testified that Columbia Gas’s proposed use
    for the protected property will destroy the current public benefit provided by the
    agricultural easement.
    {¶33} On cross-examination, Dailey testified that the ODA’s easement-
    donation-program guidelines permit extinguishment of an agricultural easement
    through eminent domain. However, Dailey clarified that the guidelines state that
    -17-
    Case No. 14-22-13 and 14-22-14
    “the procedure for extinguishment on account of changed conditions always begins
    with a request from the landowner to the Director of ODA.” (Id. at 134).
    {¶34} Wilson testified, based on his specific experience with the
    construction and installation of pipelines in the ground on agricultural land, that the
    protected property’s designation as prime farmland “would be forever lost” as a
    result of Columbia Gas’s pipeline project. (Feb. 22, 2022, Tr., Vol. II, at 179). He
    explained that prime farmland is defined by the Department of Agriculture as “the
    land that can provide the greatest crop return with the least amount of inputs” and
    “as the most productive land [because] it has unique properties that insure [sic] a
    stable food supply.” (Id. at 165). Furthermore, Wilson testified that “[p]rime
    farmland insures [sic] a public good” because “[i]t insures [sic] that we have a food
    supply that keeps up with the growing population * * * .” (Id. at 166).
    {¶35} Critically, Wilson testified that he studied the soil contained on the
    protected property—namely, in the area of the easement rights sought by Columbia
    Gas—and testified that it reflects the types of soils which qualify as “prime
    farmland” because “[t]hey are highly productive soils” and “are desirable to be
    farmed and they are valuable from that standpoint.” (Id. at 172). (See also
    Respondents’ Ex. W).       In other words, Wilson testified that the open-ditch
    excavation of Columbia Gas’s pipeline project will disturb the soil structure and
    composition of the protected property.
    -18-
    Case No. 14-22-13 and 14-22-14
    {¶36} Specifically, he testified that “[t]he process of excavating soil * * *
    would use a very large excavator and in doing so, you disturb and damage the entire
    soil profile by pulling it out and placing it in a pile” and “in that process, you would
    have mixing of * * * horizons.” (Feb. 22, 2022, Tr., Vol. II, at 174). Importantly,
    Wilson testified that, “even after every precaution is taken by Columbia Gas” there
    would be some mixing of the soil horizons” as a result of construction of the
    pipeline.
    {¶37} Wilson described a soil horizon as “a distinct arrangement of soil in
    layers,” which “are parallel to the soil surface and contain unique properties.” (Id.
    at 172). For illustration purposes, he analogized that
    a good way to think of soil horizons is like a cake. On the top of the
    cake, [is] the A horizon or the top horizon. That’s the best soil. The
    best stuff for producing crops.
    Following the next layer in the cake, you would have the B horizon.
    The B horizon is known as the subsoil. The subsoil does support crop
    growth and it is important. However, it’s not as vital to crop
    productivity as the topsoil. * * *
    Then the bottom of the cake is known as the C horizon. * * * The C
    horizon is referred to as the substratum [or] the parent material. * * *
    It’s the material that is breaking down, resulting in soil * * * .
    (Id. at 172-173).
    {¶38} Similarly, Wilson testified that the pipeline project will compress the
    soil through a process known as compaction.           He described that compaction
    “eliminate[s] an ability of the soil to exchange air and have water infiltrate and
    -19-
    Case No. 14-22-13 and 14-22-14
    percolate through the * * * soil profile” and that “compaction is detrimental.” (Id.
    at 175). Likewise, Wilson described the dynamic and inherent properties of soil.
    As relevant here, he testified that “[t]hose dynamic properties, once they are
    changed, it is possible over a long period of time to make adjustments and change
    those,” but that “[t]he inherent properties, once those are changed,” they “are
    irreversible.” (Id. at 178-179).
    {¶39} Moreover, Wilson testified that he reviewed Columbia Gas’s
    Agricultural Impact Mitigation Plan. (See Petitioner’s Ex. 33). Critically, Wilson
    testified that “[m]itigation means to make less severe,” “it does not mean to
    eliminate.” (Feb. 22, 2022, Tr., Vol. II, at 183). Based on his review of the plan,
    Wilson testified that “much of the language refers to, if it’s convenient, if it’s
    possible, [Columbia Gas] will do such a thing.” (Id. at 184). He further highlighted
    some of the troubling procedures. In sum, he testified that the document “falls far
    short of the specifics needed” and that “there’s a lot of room for improvement.” (Id.
    at 185).
    {¶40} On cross-examination, Wilson testified that, even if the protected
    property is no longer considered prime farmland, it still could be used for crop
    production after the installation of the pipeline.
    {¶41} Because      the   petitioners     objected   to   the   presentation   of
    Hornschemeier’s testimony under Evid.R. 702, the respondents proffered that
    -20-
    Case No. 14-22-13 and 14-22-14
    Hornschemeier would have testified to “the significance of” “Section D of the Ag
    Easement related to Section 170 of the IRS Code.” (Id. at 212). Specifically,
    Hornschemeier would have applied his knowledge and experience to offer the trial
    court his opinion on the significance of the intersection of the federal tax code and
    the requirement that the protected property remain “exclusively for the
    ‘conservation purpose’ as the term is described in Section 170(H)(4)(A)(III) of the
    Internal Revenue Code.” (Respondents’ Ex. H).
    {¶42} Likewise, the respondents proffered that Hornschemeier would have
    testified that the agricultural easement does not permit construction of the pipeline
    and would have testified that Huffman’s assessment is incorrect. Importantly, the
    respondents proffered that Hornschemeier would have testified that “the
    preservation of farmland is a public benefit” and that “the installation of the gas
    pipeline on the protected property would alter or destroy the public benefit provided
    by the Ag Easement.” (Feb. 22, 2022 Tr., Vol. II, at 214).
    {¶43} On February 25, 2022, Huffman testified that she is responsible for
    overseeing management of the ODA’s agricultural-easement program, including
    entering and enforcing such easements. Pertinently, Huffman testified that the
    Revised Code distinguishes between an agricultural easement and a conservation
    easement. She indicated that, under the statute, the ODA is permitted to hold only
    agricultural easements. Regarding her position with the ODA, Huffman testified
    -21-
    Case No. 14-22-13 and 14-22-14
    that the ODA has adopted a position of “non-interference” with utility installation
    through farmland, similar to the pipeline project at issue in this case. (Feb. 25, 2022
    Tr. at 17-18).
    {¶44} Huffman identified that the purpose of the agricultural easement at
    issue in this case is “to assure that the protected property shall be retained
    predominately in agricultural use by preserving and protecting its agricultural soils
    and viability.” (Id. at 10). According to Huffman, the term “predominately in
    agricultural” means that the protected property “has to be primarily an agricultural
    use. It can’t be converted acres and that can’t be converted alternative uses that
    aren’t agriculture” and that such provision applies to the entire property. (Id.).
    {¶45} Moreover, Huffman testified that the section of the agricultural
    easement describing prohibited uses of the property applies only to the landowner—
    that is, not the ODA—and prohibits only such uses that are “inconsistent with
    maintaining the property in predominantly agricultural use.” (Id. at 11). According
    to Huffman, the landowners do not have the power to enforce the agricultural
    easement at issue in this case.
    {¶46} Huffman further testified that she received correspondence from the
    respondents requesting that the ODA enforce the agricultural easement at issue in
    this case. In response, Huffman contacted Columbia Gas requesting an evaluation
    of its project. Huffman testified that she received a response from Thompson
    -22-
    Case No. 14-22-13 and 14-22-14
    indicating that Columbia Gas’s intended use of the protected property is consistent
    with the ODA’s purpose of preserving “Ohio land to remain predominately
    agricultural.” (Petitioner’s Ex. 28). As a result, Huffman testified that, after
    reviewing Columbia Gas’s proposal and Thompson’s correspondence, the ODA did
    “not believe the pipeline violates the purpose of the easement nor the terms.” (Feb.
    25, 2022 Tr. at 24). (See also Petitioner’s Ex. 30). Huffman further testified that
    she offered “experts from [ODA’s] soil and water * * * to review the easement * *
    * and insure [sic] that there were acceptable standards that would return the property
    to use” “if the [OPSB] were to approve the project.” (Feb. 25, 2022 Tr. at 25).
    {¶47} On cross-examination, Huffman testified that she did not review
    Columbia Gas’s proposed easements (as attached to its petitions) when she issued
    her opinion that its project does not violate the purpose of the agricultural easement
    at issue in this case. Further, Huffman testified that “[t]he protected property cannot
    be retained predominately in agriculture if its soils are not preserved and protected.”
    (Id. at 55).
    {¶48} Moreover, Huffman testified that the ODA’s role on the OPSB is “to
    represent agricultural interests and ag impact of projects” but that it recused itself
    from participating in the OPSB’s decision in this case.1 (Feb. 25, 2022 Tr. at 67).
    1
    The director of the ODA is a voting member of the OPSB. In this case, Dorothy Pelanda (“Pelanda”), the
    (former) director of the ODA designated Huffman to serve as her representative on the OPSB. However, the
    ODA recused itself from participating in matters relating to Columbia Gas’s pipeline project.
    -23-
    Case No. 14-22-13 and 14-22-14
    Nevertheless, Huffman testified that the OPSB incorrectly concluded in its
    certificate (and staff report of investigation) that the agricultural easement “does not
    preclude installation over or under the property to provide gas * * * .” (Id. at 61).
    {¶49} Furthermore, Huffman testified regarding the denial of the 2005
    sanitary-sewer project. She identified Petitioner’s Exhibit 22 as a June 10, 2005
    letter from the Union Soil and Water Conservation District expressing “conflicts”
    between the project and the agricultural easement. (Id. at 62). Huffman agreed that
    such concerns also apply to Columbia Gas’s project. Likewise, Huffman identified
    Petitioner’s Exhibit 23 as a September 28, 2005 letter from the Ohio Department of
    Natural Resources expressing concerns that the sanitary-soil project will destroy the
    soil structure, lead to compaction, and provoke surface and subsurface drainage
    issues on the protected property. Notably, the letter directs the reader to the
    Agricultural Mitigation Procedures promulgated by the Ohio Federation of Soil and
    Water Conservation Districts and suggests that such minimization techniques be
    followed. (See Respondents’ Ex. AE). Huffman testified that she is not aware if
    Columbia Gas is following such mitigation procedures in this case.
    {¶50} Fritchley testified that Columbia Gas’s pipeline will be installed
    through open-trench cutting. According to Fritchley, Columbia Gas is required to
    comply with a Storm Water Prevention Plan (“SWPP”) through the Ohio
    Environmental Protection Agency (“Ohio EPA”). A SWPP through the Ohio EPA
    -24-
    Case No. 14-22-13 and 14-22-14
    discusses   soil-segregation    techniques;      soil-compaction   and   decompaction
    techniques; soil-restoration techniques; soil-erosion prevention; and crop
    restoration. Fritchley testified that the Ohio EPA issued Columbia Gas a general
    permit for its pipeline project, including approval of its SWPP. Fritchley identified
    Columbia Gas’s Agricultural Impact Mitigation Plan for the pipeline project and
    discussed its contents. (See Petitioner’s Ex. 33).
    {¶51} On cross-examination, Fritchley testified that even though the
    mitigation plan states that it “it is intended to become a part of the * * * easement
    agreement,” it was not made part of either easement in this case. (Id.). Further,
    Fritchley testified that she is not an agronomist (or a soils expert).
    {¶52} After the necessity hearings, the trial court permitted the parties to
    submit briefs and proposed findings of fact and conclusions of law, which the parties
    submitted. On April 26, 2022, the trial court denied Columbia Gas’s petitions for
    the appropriation of the respondents’ easement rights. (Case No. 21CV0112, Doc.
    No. 63); (Case No. 21CV0113, Doc. No. 58). Further, the trial court determined
    that the agricultural easement does not prevent Columbia Gas’s petitions.
    {¶53} Columbia Gas filed its notices of appeal on May 18, 2022 in both
    cases. The respondents filed notices of cross-appeal on May 20, 2022. This court
    consolidated the cases for purposes of appeal. Columbia Gas raises six assignments
    of error, and the respondents raise two assignments of for our review. For ease of
    -25-
    Case No. 14-22-13 and 14-22-14
    our discussion, we will begin by discussing Columbia Gas’s first, second, third,
    fourth, and sixth assignments of error, along with the respondents’ first assignment
    of error. Then, we will discuss Columbia Gas’s fifth assignment of error and
    respondents’ second assignment of error together.
    Columbia Gas’s Assignment of Error No. I
    The Trial Court erred in holding a hearing (the “Hearing”)
    pursuant to R.C. 163.09(B) because Appellees/Respondents Don
    Bailey, Jr., Successor Trustee of the Arno Renner Trust dated
    April 24, 1997 (“Bailey, Jr.”), Charles Peter Renner (“Renner”),
    Patrick Bailey (“P. Bailey”), and Whitney Bailey (“W. Bailey”)
    (collectively, “Appellees”) failed to assert specific denials under
    R.C. 163.08 and instead asserted Affirmative Defenses which
    cannot trigger a necessity challenge under R.C. 163.09(B)(1).
    Columbia Gas’s Assignment of Error No. II
    The Trial Court erred in finding in the Judgment Entry on
    Necessity    Hearing       (the   “Judgment     Entry”)     that
    Appellant/Petitioner Columbia Gas of Ohio, Inc. (“Columbia
    Gas”) is not entitled to an irrebuttable presumption of necessity
    pursuant to R.C. 163.09(B)(1)(c), despite the Ohio Power Sitting
    Board (“OPSB”) approving Columbia Gas’ Letter of Notification
    Application (“Application” or “OPSB Application”) for the
    Marysville Connector Pipeline Project (the “Project”), which
    contained the easement terms Columbia Gas seeks to appropriate.
    Columbia Gas’s Assignment of Error No. III
    The Trial Court erred in failing to find in the Judgment Entry
    that Columbia Gas is entitled to a rebuttable presumption of
    necessity pursuant to R.C. 163.09(B)(1)(b), despite Columbia Gas
    presenting evidence of necessity of the appropriation, despite
    considerable deference afforded to an appropriating public
    utility, and despite Appellees’ failure to overcome Columbia Gas’
    presumption of necessity of the appropriation.
    -26-
    Case No. 14-22-13 and 14-22-14
    Columbia Gas’s Assignment of Error No. IV
    The Trial Court erred in finding in favor of Appellees in the
    Judgment Entry on Appellees’ Affirmative Defense set forth in
    Paragraph 18 of Appellees’ Answers that the OPSB did not
    approve the particular easements that Columbia Gas seeks to
    acquire and that the OPSB did not find that the easements were
    necessary.
    Columbia Gas’s Assignment of Error No. VI
    The Trial Court erred by dismissing Columbia Gas’ Petition in
    the Judgment Entry and by failing to hold a compensation
    hearing pursuant to R.C. 163.09(B)(2), regardless of how the Trial
    Court ruled on Appellees’ Affirmative Defenses.
    Respondents’ Assignment of Error No. I
    The Trial Court erred by ruling that the Appellant/Cross
    Appellee/Petitioner had a right to appropriate the property of the
    Appellees/Cross Appellants/Respondents.
    {¶54} In its assignments of error, Columbia Gas argues that the trial court
    erred by denying its verified petitions for the appropriation of easement rights in
    real property. In particular, under its first assignment of error, Columbia Gas argues
    that the trial court erred by setting the matters for a necessity hearing because the
    respondents “failed to assert a single specific denial pursuant to R.C. 163.08.”
    (Appellant’s/Cross-Appellee’s Brief at 8).
    {¶55} Under its second and third assignments of error, Columbia Gas
    contends that it is entitled to the irrebuttable presumption under R.C.
    163.09(B)(1)(c) or the rebuttable presumption under 163.09(B)(1)(b). Similarly, it
    -27-
    Case No. 14-22-13 and 14-22-14
    argues under its fourth assignment of error that the trial court failed to review the
    specific easement rights that Columbia Gas sought from the respondents. Finally,
    under its sixth assignment of error, Columbia Gas argues that this court should the
    remand the cases to the trial court for compensation hearings under R.C.
    163.09(B)(2).
    {¶56} The respondents, in their first assignment of error, argue that the trial
    court should have applied Ohio’s prior public use doctrine to conclude that the
    specific easement rights sought by Columbia Gas in these cases are not authorized
    as a result of the agricultural easement.
    Standard of Review
    {¶57} “The scrutiny by the courts in appropriation cases is limited in scope,”
    but “requires vigilance in reviewing state actions for the necessary restraint,
    including review to ensure that the state takes no more than that necessary to
    promote the public use, and that the state proceeds fairly and effectuates takings
    without bad faith, pretext, discrimination, or improper purpose.” Norwood v.
    Horney, 
    110 Ohio St.3d 353
    , 
    2006-Ohio-3799
    , ¶ 69-70. See also State ex rel. Ohio
    History Connection v. Moundbuilders Country Club Co., 5th Dist. Licking No. 2019
    CA 00039, 
    2020-Ohio-276
    , ¶ 35 (“The question of necessity is subjected on appeal
    to a ‘limited standard of review.’”), quoting Willoughby Hills v. Andolsek, 11th Dist.
    Lake No. 2001-L-173, 
    2003-Ohio-323
    , ¶ 92.
    -28-
    Case No. 14-22-13 and 14-22-14
    {¶58} Because municipalities “enjoy broad discretion in determining
    whether a proposed taking serves the public,” a trial court’s review of a
    municipality’s appropriation decision consists of whether “the legislature’s exercise
    of power is not beyond the scope of its authority, and that the power is not abused
    by irregular or oppressive use, or use[d] in bad faith.” Norwood at ¶ 70. See also
    Ohio Power Co. v. Burns, ___ Ohio St.3d ___, 
    2022-Ohio-4713
    , ¶ 32; United States
    v. Carmack, 
    329 U.S. 230
    , 243, 
    67 S.Ct. 252 (1946)
     (applying an ultra-vires as well
    as an arbitrary, capricious, and bad-faith standard of review to takings challenges).
    Generally, an abuse of discretion suggests the trial court’s decision is unreasonable,
    arbitrary, or unconscionable. Blakemore v. Blakemore, 
    5 Ohio St.3d 217
    , 219
    (1983). See also Bd. of Commrs. Mill Creek Park Metro. Dist. v. Less, 7th Dist.
    Mahoning No. 20MA0074, 
    2022-Ohio-1289
    , ¶ 19 (applying the abuse-of-discretion
    standard to an R.C. Chapter 163 appropriation case).
    {¶59} “However, ‘when the authority is delegated to another,’” it is the duty
    of the trial court to “‘ensure that the grant of authority is construed strictly and that
    any doubt over the propriety of the taking is resolved in favor of the property
    owner.’” (Emphasis added.) Less at ¶ 16, quoting Norwood at ¶ 70.
    {¶60} When a trial court’s decision regarding a petition for appropriation
    rights brought under R.C. Chapter 163 is “‘supported by some competent, credible
    evidence going to all the essential elements of the case[, it] will not be reversed by
    -29-
    Case No. 14-22-13 and 14-22-14
    a reviewing court as being against the manifest weight of the evidence.’” Seasons
    Coal Co. v. Cleveland, 
    10 Ohio St.3d 77
    , 80 (1984), quoting C.E. Morris Co. v.
    Foley Constr. Co., 
    54 Ohio St.2d 279
     (1978), syllabus. See also Ohio Power at ¶
    35 (applying the civil-manifest-weight standard of review to a petition for
    appropriation rights brought under R.C. Chapter 163); Willoughby Hills, 2003-
    Ohio-323, at ¶ 91. In other words, “a trial court’s findings of fact will be upheld
    when they are supported by some competent and credible evidence.” Ohio Power
    at ¶ 35. See also Dublin v. Beatley, 5th Dist. Delaware No. 18 CAE 01 0007, 2018-
    Ohio-3354, ¶ 15 (reviewing a trial court’s appropriations-rights decision against the
    competent-credible-evidence standard in an appropriations rights case brought
    under R.C. Chapter 163).
    -30-
    Case No. 14-22-13 and 14-22-14
    Analysis
    {¶61} “The property rights of an individual are fundamental rights, and ‘the
    bundle of venerable rights associated with property is strongly protected in the Ohio
    Constitution and must be trod upon lightly, no matter how great the weight of other
    forces.’” Ohio Power at ¶ 22, quoting Norwood at ¶ 38. However, “[l]ike the
    individual’s right to property, the state’s great power to seize private property
    predates modern constitutional principles.” Norwood at ¶ 39. Indeed, “[a]t the time
    the Constitution was adopted, * * * [t]he founders recognized the necessity of the
    takings power and expressly incorporated it into the Fifth Amendment to the United
    States Constitution.” 
    Id.
     Nevertheless, even “though its existence is undeniable and
    its powers are sweepingly broad, the power is not unlimited.” (Emphasis added.)
    
    Id.
    {¶62} R.C. Chapter 163 governs the appropriation of private property for
    public use in Ohio. Importantly, the Revised Code directs that “[n]o agency shall
    appropriate real property except as necessary and for a public use” and that “[i]n
    any appropriation, the taking agency shall show by a preponderance of the evidence
    that the taking is necessary and for a public use.”2 R.C. 163.021(A). See also Ohio
    2
    Under R.C. Chapter 163, an agency “means any public agency or private agency.” R.C. 163.01(C). See
    also R.C. 163.01(G) (defining public utility as including “an agency holding a certificate of public
    convenience and necessity granted by the federal energy regulatory commission). A private agency is “any
    corporation, firm, partnership, voluntary association, joint-stock association, or company that is not a public
    agency and that is authorized by law to appropriate property in the courts of this state.” R.C. 163.01(B).
    -31-
    Case No. 14-22-13 and 14-22-14
    Power at ¶ 22 (noting that “[t]he state, however, may seize private property when it
    is necessary for public use.”), citing Norwood at ¶ 39, 41. “This provision enforces
    our state constitution’s requirement * * * .” State ex rel. Ohio History Connection
    v. Moundbuilders Country Club Co., ___ Ohio St.3d ___, 
    2022-Ohio-4345
    , ¶ 41.
    See Ohio Constitution, Article I, Section 19.
    {¶63} Importantly, the Supreme Court of Ohio stresses that “the term
    ‘appropriation’ means the appropriation of the specific property sought to be
    appropriated by the agency; it does not mean the project or the taking in general,
    given the restrictions on an agency’s right to appropriate.” (Emphasis added.) Ohio
    Power at ¶ 24. Consequently,
    R.C. 163.09(B)(1) comes into play only when (1) the agency has filed
    a petition under R.C. 163.05 against a landowner to appropriate a
    “parcel or contiguous parcels in a single common ownership, or
    interest or right therein,” and (2) the landowner has filed an answer in
    response to that petition denying the “necessity for the appropriation”
    under R.C. 163.08.
    
    Id.,
     citing R.C. 163.09(B)(1). If in play, R.C. 163.09(B)(1) requires the trial court
    to set a hearing to address the appropriation. See id. at ¶ 25 (noting that the trial
    “court must resolve the agency’s right to make the appropriation and the necessity
    of the appropriation”), citing R.C. 163.08.
    Columbia Gas’s Appeal
    {¶64} In this case, Columbia Gas filed its petitions under R.C. 163.05 against
    the respondents and the respondents filed their answers in response to those petitions
    -32-
    Case No. 14-22-13 and 14-22-14
    denying the necessity for the appropriations under R.C. 163.08. Nevertheless,
    Columbia Gas argues under its first assignment of error that the trial court erred by
    setting the matter for a hearing because the respondents “failed to assert a single
    specific denial pursuant to R.C. 163.08.” (Appellant’s/Cross-Appellee’s Brief at 8).
    Instead, Columbia Gas contends that the respondents asserted affirmative defenses
    under Civ.R. 8(C), which “are not specific denials under R.C. 163.08, * * * and
    cannot trigger a R.C. 163.09(B) hearing.” (Emphasis sic.). (Id.). Therefore,
    Columbia Gas asserts that the trial court should have resolved “any issue that could
    have been raised through a specific denial by [the respondents] in favor of Columbia
    Gas.” (Id.).
    {¶65} Columbia Gas’s argument is without merit. R.C. 163.08 provides, in
    its relevant part that
    [s]uch answer * * * shall contain a general denial or specific denial of
    each material allegation not admitted. The agency’s right to make the
    appropriation, the inability of the parties to agree, and the necessity
    for the appropriation shall be resolved by the court in favor of the
    agency unless such matters are specifically denied in the answer and
    the facts relied upon in support of such denial are set forth therein * *
    *.
    {¶66} Here, the respondents’ answers reflect general and specific denials of
    each material allegation not admitted. Even though the respondents included a
    section of specific denials titled “affirmative defenses,” under which they listed the
    specific reasons Columbia Gas’s appropriations are not necessary, such
    -33-
    Case No. 14-22-13 and 14-22-14
    characterization is not fatal to their answers. Indeed, a review of the respondents’
    denials reflects that they are “sufficiently specific and factually supported to have
    required a necessity hearing.” Ohio River Pipe Line, LLC v. Gutheil, 
    144 Ohio App.3d 694
    , 698 (4th Dist.2001). Thus, Columbia Gas’s first assignment of error
    is overruled.
    {¶67} Pivoting to the underlying considerations of R.C. Chapter 163, even
    though “economic factors may be considered in determining whether private
    property may be appropriated, the fact that the appropriation would provide an
    economic benefit to the government and community, standing alone, does not
    satisfy the public-use requirement of Section 19, Article I of the Ohio Constitution.”
    Norwood, 
    110 Ohio St.3d 353
    , 
    2006-Ohio-3799
    , at paragraph one of the syllabus.
    Nevertheless, the Revised Code defines “public use.” “R.C. 163.01(H)(1) first
    defines ‘public use’ by negation”—that is, the Revised Code defines that “a
    ‘[p]ublic use’ does not include any taking that is for conveyance to a private
    commercial enterprise, for economic development, or solely for the purpose of
    increasing public revenue, unless the property is conveyed or leased to” “[a] public
    utility, municipal power agency, or common carrier.” Ohio History Connection,
    ___ Ohio St.3d ___, 
    2022-Ohio-4345
    , at ¶ 43; R.C. 163.01(H)(1)(a). The parties
    do not dispute that Columbia Gas is a public utility. Consequently, there is some
    competent, credible evidence in the record that the appropriations in this case satisfy
    -34-
    Case No. 14-22-13 and 14-22-14
    the public-use element. See, e.g., Sunoco Pipeline L.P. v. Teter, 7th Dist. Harrison
    No. 16 HA 0002, 
    2016-Ohio-7073
    , ¶ 81.
    {¶68} Turning to the necessity element, an agency “must show by a
    preponderance of the evidence that the taking of the property is necessary, unless
    one of three circumstances in division (a), (b), or (c) [of R.C. 163.09(B)(1)] has
    occurred.” Ohio Power, ___ Ohio St.3d ___, 
    2022-Ohio-4713
    , at ¶ 20. “‘The
    “necessity” required in the exercise of the power of eminent domain does not require
    a showing of absolute necessity, but includes “that which is reasonably convenient
    or useful to the public.”’” Ohio Power Co. v. Duff, 12th Dist. Madison No. CA2020-
    01-004, 
    2020-Ohio-4628
    , ¶ 32, quoting Ferencz v. Toledo, 6th Dist. Lucas No. L-
    87-379, 
    1988 WL 139615
    , *3 (Dec. 30, 1988), quoting Giesy v. Cincinnati,
    Wilmington, and Zanesville RR. Co., 
    4 Ohio St. 308
    , 327 (1854). “Necessity
    includes present needs as well as future needs.” Erie-Ottawa-Sandusky Regional
    Airport Auth. v. Orris, 6th Dist. Ottawa No. 90-OT-039, 
    1991 WL 254227
    , *4 (Sept.
    13, 1991).
    {¶69} Under R.C. 163.09(B)(1)(a), an agency “is entitled to a rebuttable
    presumption of necessity if the [governing board of the agency] declared by
    resolution ‘the necessity for the appropriation.’” 
    Id.,
     quoting R.C. 163.09(B)(1)(a).
    “Under division (b), [an agency] is entitled to a rebuttable presumption of necessity
    if it presented ‘evidence of the necessity for the appropriation.’” 
    Id.,
     quoting R.C.
    -35-
    Case No. 14-22-13 and 14-22-14
    163.09(B)(1)(b).    Finally, “under division (c), [an agency] is entitled to an
    irrebuttable presumption of necessity if a state or federal regulatory authority, such
    as the [OPSB], approved ‘of [the] appropriation.’”                 
    Id.,
     quoting R.C.
    163.09(B)(1)(c). “Thus, to be entitled to any of the presumptions, the relevant
    entities must determine the necessity of the appropriation.” 
    Id.
    {¶70} Finally, if the trial court determines that the appropriation is not
    necessary or not for a public use, the court shall award the respondent the full
    amount of attorney’s fees, costs, and expenses. Id. at ¶ 26, citing R.C. 163.041.
    {¶71} In its second assignment of error, Columbia Gas contends that it is
    entitled to the irrebuttable presumption of necessity under R.C. 163.09(B)(1)(c)
    because the OPSB approved its pipeline project. Columbia Gas’s argument is
    unfounded. Indeed, the Supreme Court of Ohio recently determined that an agency
    is entitled to the irrebutable presumption of necessity under R.C. 163.09(B)(1)(c) if
    a state or federal regulatory authority, such as the OPSB, approves “appropriation
    of the individual property, or the interest or right therein, that is sought to be taken
    by the agency, not the project in its entirety.” (Emphasis added.) Id. at ¶ 28 (holding
    “that the term ‘appropriation’ as used in R.C. 163.09(B)(1) means the appropriation
    of the individual property, or the interest or right therein, that is sought to be taken
    by the agency, not the project in its entirety”).
    -36-
    Case No. 14-22-13 and 14-22-14
    {¶72} In this case, the trial court concluded that the OPSB “failed to
    determine if the appropriation was taking only that which was necessary” because
    it did not “examine the applicable easement documents itself [sic] * * * .” (Case
    No. 21CV0112, Doc. No. 63); (Case No. 21CV0113, Doc. No. 58). Specifically,
    the trial court found that “[t]he OPSB approved the project and a 75 foot wide
    easement over Respondents’ properties, but failed to examine the proposed
    easement.” (Id.); (Id.).
    {¶73} We conclude that some competent, credible evidence supports the trial
    court’s determination that Columbia Gas is not entitled to the irrebuttable
    presumption of necessity under R.C. 163.09(B)(1)(c). That is, the record reflects
    that the OPSB approved Columbia Gas’s project as it is generally described in its
    letter-of-notification application.     Specifically, under the project-description
    section, the OPSB illustrated that Columbia Gas sought “certification to build a
    4.78-mile long, 12-inch diameter natural gas pipeline, with a maximum allowable
    operating pressure of 190 pounds per square inch gauge, in Union County.” (Case
    No. 21CV0112, Doc. No. 1, Ex. 17); (Case No. 21CV0113, Doc. No. 1, Ex. 17).
    The OPSB further illustrated that “[p]ipeline construction will occur within a 75-
    foot easement, 25-foot of which is temporary, with the remainder being permanent.”
    (Id.); (Id.).   In other words, the record reflects that the OPSB did not approve “the
    -37-
    Case No. 14-22-13 and 14-22-14
    specific property being appropriated by the agency.” (Emphasis added.) Ohio
    Power at ¶ 23. See also id. at ¶ 29.
    {¶74} Nonetheless, Columbia Gas argues that “[e]ven if approval of the
    Project, alone, does not trigger the irrebuttable presumption under R.C.
    163.09(B)(1)(c) * * * , the OPSB approved the terms of the easement that Columbia
    Gas seeks to acquire when it approved the rights contained in the easements.”
    (Emphasis sic.) (Appellant’s/Cross-Appellee’s Brief at 14-15). Stated another way,
    Columbia Gas contends that the documentation concerning the easements that it
    sought from the landowners contained in its letter-of-notification application (and
    as reviewed by the OPSB) is sufficient to trigger the irrebuttable presumption under
    R.C. 163.09(B)(1)(c). We disagree. The Supreme Court of Ohio unequivocally
    determined that a state or federal regulatory authority, such as the OPSB, must
    approve the individual appropriations to trigger the irrebuttable presumption under
    R.C. 163.09(B)(1)(c). Ohio Power at ¶ 31.
    {¶75} Importantly, the Supreme Court stressed that “because it may be
    inconvenient or tedious for [an agency] to obtain the required resolutions or
    approvals for each appropriation to be entitled to a presumption under R.C.
    163.09(B)(1)(a) or (c) does not mean that such an interpretation is unreasonable or
    absurd.” (Emphasis added.) Id. Consequently, we conclude that, since the OPSB
    did not review and approve the individual appropriations at issue in this case—i.e.,
    -38-
    Case No. 14-22-13 and 14-22-14
    the specific proposed easement terms—Columbia Gas is not entitled to the
    irrebuttable presumption under R.C. 163.09(B)(1)(c). Id. at ¶ 2, 31. Accordingly,
    Columbia Gas’s second assignment of error is overruled.
    {¶76} Alternatively, Columbia Gas argues under its third assignment of error
    that it is entitled to the rebuttable presumption under R.C. 163.09(B)(1)(b) since it
    provided evidence of the necessity for the appropriations. Accord id. at ¶ 2, 32.
    That is, Columbia Gas argues that the trial court should have resolved this case in
    its favor after determining that “‘[t]his project would benefit the community of
    Marysville and surrounding areas with an increase in available natural gas.’”
    (Appellant’s/Cross-Appellee’s Brief at 17, quoting Case No. 21CV0112, Doc. No.
    63 and Case No. 21CV0113, Doc. No. 58).
    {¶77} In particular, Columbia Gas posits that it presented evidence of the
    necessity for the appropriations through the OPSB’s issuance of the certificate in
    which the OPSB “found that ‘the public interest, convenience, and necessity are
    served’ through construction, operation, and maintenance of the pipeline.”
    (Appellant’s/Cross-Appellee’s Brief at 17, quoting Petitioner’s Ex. 9). Columbia
    Gas further contends that it presented evidence of the necessity for the
    appropriations through Opfer’s testimony “that a 75’corridor—a 50’ permanent
    easement and a 25’ temporary construction easement—is reasonably convenient
    and useful to the public.” (Id. at 17-18, citing Nov. 17, 2021 Tr. at 80). Therefore,
    -39-
    Case No. 14-22-13 and 14-22-14
    Columbia Gas argues that there is some competent, credible evidence in the record
    supporting that it satisfied its burden to prove that the easement terms were
    necessary under R.C. 163.09(B)(1)(b). And, to bolster its argument, Columbia Gas
    advocates that the respondents did not produce any evidence to balance or counter
    balance that presumption of necessity.
    {¶78} “The General Assembly requires an agency to set forth in its verified
    petition the ‘parcel or contiguous parcels in a single common ownership, or interest
    or right therein,’ that it seeks to appropriate.” Ohio Power at ¶ 34, quoting R.C.
    163.05. See also Ayersville Water & Sewer Dist. v. Geiger, 3d Dist. Defiance No.
    4-11-19, 
    2012-Ohio-2689
    , ¶ 69 (discussing that “R.C. 163.05 provides the
    requirements an agency must meet to commence an appropriation action”). “Thus,
    the agency must demonstrate the necessity of that appropriation—the need to take
    the property, or interest or right therein, set forth in its verified petition.” Ohio
    Power at ¶ 34. Consequently, in a case in which “the easement terms include
    various rights that” an agency seeks to take from landowners, “each easement term
    that is challenged must be reviewed by the trial court.” 
    Id.
    {¶79} Here, even though the trial court determined that the “project would
    benefit the community of Marysville and surrounding areas with an increase in
    available natural gas,” the trial court nevertheless concluded that “it was ‘bad faith’
    to represent one thing to the [OPSB] and then ask [the trial] Court to approve
    -40-
    Case No. 14-22-13 and 14-22-14
    something greater” since “the 25foot easement was labeled ‘temporary’ before the
    [OPSB] and transformed itself to ‘perpetual’ before [the trial] Court * * * .” (Case
    No. 21CV0112, Doc. No. 63); (Case No. 21CV0113, Doc. No. 58). Importantly,
    the “rebuttable presumption [under R.C. 163.09(B)(1)(b)] gives rise only to a prima
    facie showing of necessity,” it does not shift the ultimate burden of proof from the
    agency “to the landowners but, rather, it impose[s] on the landowners ‘“the burden
    of going forward with evidence to rebut or meet the presumption.’” Ohio Power at
    ¶ 32, quoting Hoyle v. DTJ Ents., Inc., 
    143 Ohio St.3d 197
    , 
    2015-Ohio-843
    , ¶ 24,
    quoting Evid.R. 301. The presumption disappears if the landowners produce
    “evidence that balances or counterbalances the presumption,” “and the case must be
    resolved on the evidence presented under the original burden of proof.” 
    Id.
    {¶80} Nevertheless, this case may be resolved on evidence that Columbia
    Gas acted in bad faith, abused its discretion, or acted with improper purpose to
    satisfy its burden of proof. See 
    id.
     See also Springfield v. Gross, 
    164 Ohio App.3d 1
    , 
    2005-Ohio-5527
    , ¶ 12 (2d Dist.) (“‘[W]here the appropriating agency has passed
    a resolution of necessity for the appropriation, the resolution is prima facie evidence
    of such necessity in the absence of proof showing fraud, bad faith, or abuse of
    discretion by the agency.’”), quoting Mentor v. Osborne, 
    143 Ohio App.3d 439
    , 446
    (11th Dist.2001). Here, there is some competent, credible evidence supporting the
    trial court’s determination that Columbia Gas acted in bad faith to satisfy its burden
    -41-
    Case No. 14-22-13 and 14-22-14
    of proving that the taking is necessary. That is, there is some competent, credible
    evidence in the record supporting the trial court’s assessment that since “the 25foot
    easement was labeled ‘temporary’ before the [OPSB] and transformed itself to
    ‘perpetual’ before this Court,” amounted to “bad faith.” (Case No. 21CV0112, Doc.
    No. 63); (Case No. 21CV0113, Doc. No. 58).
    {¶81} In the context of appropriations, the Ohio Supreme Court recently
    defined “bad faith” to mean “‘[d]ishonesty of belief, purpose, or motive.’” Ohio
    History Connection, ___ Ohio St.3d ___, 
    2022-Ohio-4345
    , at ¶ 31, quoting Black’s
    Law Dictionary 171 (11th Ed.2019). When considering whether a party acted in
    bad faith, the court suggested that we consider whether that party “acted reasonably
    under the circumstances in addition to considering whether it acted honestly.” Id.
    at ¶ 32.
    {¶82} Here, our review of the record reflects that Columbia Gas did not act
    with full honesty. Specifically, the record reflects that the OPSB (conditionally)
    issued a certificate under R.C. Chapter 4906 to Columbia Gas after reviewing
    Columbia Gas’s letter-of-notification application. The certificate (conditionally)
    authorized Columbia Gas to construct, operate, and maintain a 4.78-mile long, 12-
    inch diameter natural gas pipeline, with a maximum allowable operating pressure
    of 190 pounds per square inch gauge.
    -42-
    Case No. 14-22-13 and 14-22-14
    {¶83} Under the project description, the OPSB unequivocally stated that the
    “[p]ipeline construction will occur within a 75-foot easement, 25-feet of which is
    temporary, with the remainder being permanent.” (Emphasis added.) (Petitioner’s
    Ex. 9). Compare Phelps Preferred Invests., 
    2022-Ohio-2540
    , at ¶ 36 (taking note
    of the “the project description portion of the [OPSB’s] certificate of approval” for
    the pipeline project in which Columbia Gas represented that “‘Pipeline construction
    will occur within a 75-foot easement, 25-feet of which is temporary, with the
    remainder being permanent’” before the OPSB).
    {¶84} As evidence for issuance of the certificate, the OPSB relied on
    Columbia Gas’s letter-of-notification application in which it included obtuse
    information regarding the easements in the relevant sections.          Significantly,
    Columbia Gas did not include any information regarding the specific easements that
    it sought from the landowners under the section of its application (or corresponding
    appendix) discussing the “list of properties for which [it] ha[d] obtained easements
    * * * necessary to construct and operate the facility and [the] list of the additional
    properties for which such agreements have not been obtained.” (Petitioner’s Ex. 1).
    {¶85} Furthermore, the record reflects that the general-information section
    of Columbia Gas’s application informed the OPSB that “[t]he majority of the 12-
    inch natural gas main will be constructed within permanent private pipeline
    easements * * * as depicted in the construction plans in Appendix B.” (Id.). In
    -43-
    Case No. 14-22-13 and 14-22-14
    other words, Columbia Gas did not mention the necessity of a temporary easement
    in the general-information section of its application. However, the reader must look
    to Appendix B of the application to learn of Columbia Gas’s full intention to
    construct the pipeline using a permanent and temporary easement. Yet, a review of
    Appendix B reflects that Columbia Gas characterized the temporary easement as
    just that and not a perpetual-temporary easement.
    {¶86} Nevertheless, Columbia Gas inconspicuously declared that “the
    proposed pipeline route will only include a 75-foot wide (50-foot permanent
    easement and 25-foot temporary easement) construction footprint” in the section of
    its application discussing the impact to wetlands. (Id.).
    {¶87} Notwithstanding the evidence before the OPSB, Columbia Gas
    attached the specific easement rights that it sought from the respondents in relation
    to its pipeline project to its petitions filed with the trial court. Importantly, the
    easements granted Columbia Gas a “temporary-easement area” “to temporarily use
    an additional twenty-five feet (25’) of space adjoining [the] Permanent Easement
    Area * * * , as shown on Exhibit B, only for the purpose of enabling [Columbia
    Gas] to initially construct the pipeline and to later alter, replace, and repair said
    pipeline and to conduct all activities incident [to], including restoration or clean-up
    activities.” (Case No. 21CV0112, Doc. No. 1, Ex. 18); (Case No. 21CV0113, Doc.
    No. 1, Ex. 18). Exhibit B depicts a “gas pipeline easement to [Columbia Gas]” and
    -44-
    Case No. 14-22-13 and 14-22-14
    a “25’ perpetual temporary easement.” (Emphasis added.) (Id.); (Id.). Compare
    Phelps Preferred Invests., 
    2022-Ohio-2540
    , at ¶ 36 (acknowledging the
    transformation of the temporary easement from its application before the OPSB to
    “a ‘perpetual temporary easement’ at the necessity hearing,” and finding
    significance that “the proposed easement * * * had no expiration date”).
    {¶88} During the necessity hearing, Columbia Gas presented the testimony
    of Thompson, who acknowledged the categorization of the “temporary perpetual
    easement” and described such easement as “necessary when Columbia [Gas] is
    doing its initial construction of the pipeline, as well as any future repairs or
    maintenance on the pipeline that require that kind of extra space for its equipment.”
    (Nov. 17, 2021 Tr. at 58). She further described that Columbia Gas “does not plan
    to utilize or permanently encumber that 25 foot easement, * * * every day [u]nlike
    a permanent easement where Columbia [Gas] is laying a pipeline it will be
    permanently encumbering that easement area.” (Id.). Rather, she testified that the
    (temporary) easement is “characterized as perpetual” because it grants Columbia
    Gas “the ability * * * to utilize it when it needs it for various specific activities” as
    described in the easements. (Id. at 59). On cross-examination, Thompson testified
    that the temporary easement does not include any temporal limitation. She further
    testified that the purpose of the temporary easement is the initial construction and
    the maintenance of the pipeline, which is also the basis of the permanent easement.
    -45-
    Case No. 14-22-13 and 14-22-14
    {¶89} Consequently, contrary to Columbia Gas’s argument under its fourth
    assignment of error, it is evident that the trial court not only reviewed the specific
    easement rights that Columbia Gas sought from the respondents but concluded that
    Columbia Gas acted in bad faith to satisfy its burden of proving that the taking is
    necessary. Therefore, the trial court’s determination that Columbia Gas is not
    entitled to the rebuttable presumption under R.C. 163.09(B)(1)(b) is supported by
    some competent, credible evidence.        See Phelps Preferred Invests. at ¶ 36
    (concluding that Columbia Gas’s “reliance upon testimony to indicate that the 75-
    foot corridor—a 50-foot permanent easement area and 25-foot temporary perpetual
    construction easement area * * * is factually inconsistent”). See also id. at ¶ 37.
    For these reasons, Columbia Gas’s third and fourth assignments of error are
    overruled.
    {¶90} Finally, Columbia Gas’s argument under its sixth assignment of error
    advocating for this court to remand the cases to the trial court for compensation
    hearings under R.C. 163.09(B)(2) is without merit. Accord Phelps Preferred
    Invests. at ¶ 43. Indeed, under R.C. 163.09(B)(2), “if the landowner appeals from a
    necessity determination, the trial court’s ability to hold a compensation trial is
    extinguished until the appeal is decided.” State ex rel. Bohlen v. Halliday, 
    164 Ohio St.3d 121
    , 
    2021-Ohio-194
    , ¶ 17. Therefore, Columbia Gas’s sixth assignment of
    error is overruled.
    -46-
    Case No. 14-22-13 and 14-22-14
    Respondents’ Cross-Appeal
    {¶91} Regardless of any presumption applied to Columbia Gas’s petitions,
    the respondents contend under their first assignment of error that they are entitled
    to judgment in their favor as a matter of law because Columbia Gas’s appropriation
    of the specific easement rights in these cases is not authorized as a result of the
    agricultural easement. Specifically, the respondents argue that “the express terms
    of the Ag Easement prohibit the installation of the Columbia Gas pipeline on the
    [protected] Property.” (Appellee’s/Cross-Appellant’s Brief at 25).
    {¶92} “An easement is a non-possessory property interest in the land of
    another.” Pomante v. Marathon Ashland Pipe Line, LLC, 
    187 Ohio App.3d 731
    ,
    
    2010-Ohio-1823
    , ¶ 7 (10th Dist.).       “An easement ‘entitles the owner of the
    easement, the dominant estate, to a limited use of the land in which the interest
    exists, the servient estate.’” Tower 10, LLC v. 10 W Broad Owner, LLC, 10th Dist.
    Franklin No. 18AP-998, 
    2020-Ohio-3554
    , ¶ 27, quoting Crane Hollow, Inc. v.
    Marathon Ashland Pipe Line, L.L.C., 
    138 Ohio App.3d 57
    , 66 (4th Dist.2000).
    Easements are either appurtenant or in gross. 
    Id.
     “An easement appurtenant runs
    with the land and is transferable to future buyers,” while an “easement in gross is
    personal only to the grantee and, therefore does not run with the land.” 
    Id.,
     quoting
    Walbridge v. Carroll, 
    172 Ohio App.3d 429
    , 
    2007-Ohio-3586
    , ¶ 17 (6th Dist.).
    -47-
    Case No. 14-22-13 and 14-22-14
    {¶93} “Easements may be created by grant, implication, prescription, or
    estoppel.” Id. at ¶ 28. “‘When an easement is created by express grant, the extent
    and limitations of the easement depend upon the language of the grant.’” Id.,
    quoting Pomante at ¶ 7. “‘There are no particular words required to create an
    easement by express grant, provided that the intent of the parties is clear from the
    document.’” Id., quoting Cincinnati Entertainment Assocs., Ltd. v. Bd. of Commrs.,
    
    141 Ohio App.3d 803
    , 813 (1st Dist.2001).
    {¶94} “When an easement is set forth in a written agreement, it is subject to
    the rules of contract law.” Zagrans v. Elek, 9th Dist. Lorain No. 08CA009472,
    
    2009-Ohio-2942
    , ¶ 9. “When the terms of an easement ‘are clear and unambiguous,
    the construction of an express easement presents an issue of law.’” Tower 10 at ¶
    29, quoting Pomante at ¶ 7. In that case, we apply a de novo standard of review.
    St. Marys v. Auglaize Cty. Bd. of Commrs., 
    115 Ohio St.3d 387
    , 
    2007-Ohio-5026
    , ¶
    38, citing Nationwide Mut. Fire Ins. Co. v. Guman Bros. Farm, 
    73 Ohio St.3d 107
    ,
    108 (1995). “De novo review is independent and without deference to the trial
    court’s determination.” ISHA, Inc. v. Risser, 3d Dist. Allen No. 1-12-47, 2013-
    Ohio-2149, ¶ 25.
    {¶95} “‘If there is no specific delineation of the easement, or if the document
    is ambiguous, the court must then look to the circumstances surrounding the
    transaction in order to determine the intent of the parties.’” Tower 10 at ¶ 29,
    -48-
    Case No. 14-22-13 and 14-22-14
    quoting Delaware Golf Club, LLC v. Dornoch Estates Homeowners Assn., 5th Dist.
    Delaware No. 19 CAE 04 0027, 
    2020-Ohio-880
    , ¶ 43, citing Hemmelgarn v.
    Huelskamp & Sons, Inc., 3d Dist. Shelby No. 17-19-07, 
    2019-Ohio-5298
    , ¶ 13
    (addressing that “if there is no specific delineation of the easement, or if the
    document is ambiguous, then the court must look to the surrounding circumstances
    in order to determine the intent of the parties”). An easement “is ambiguous if it is
    ‘susceptible to more than one reasonable interpretation.’” Westlake v. VWS, Inc.,
    8th Dist. Cuyahoga No. 100180, 
    2014-Ohio-1833
    , ¶ 34, quoting Michael A. Gerard,
    Inc. v. Haffke, 8th Dist. Cuyahoga No. 98488, 
    2013-Ohio-168
    , ¶ 11. Because the
    intent of the parties becomes a question of fact when a court finds an ambiguity in
    the easement language, the trier of fact may rely on extrinsic evidence to ascertain
    such intent. See Mulchin v. ZZZ Anesthesia, Inc., 6th Dist. Erie No. E-05-045, 2006-
    Ohio-5773, ¶ 36.
    {¶96} A conservation or agricultural easement must be liberally construed in
    favor of the underlying intention for the easement as well as the policy and purpose
    of Sections 5301.67 through 5301.70 of the Revised Code. Taylor v. Taylor, 12th
    Dist. Butler No. CA2017-05-061, 
    2018-Ohio-1571
    , ¶ 27. See also Beaumont v.
    FirstEnergy Corp., 11th Dist. Geauga No. 2004-G-2573, 
    2004-Ohio-5295
    , ¶ 18
    (“Since an easement is set forth in a written agreement, it must be interpreted in the
    -49-
    Case No. 14-22-13 and 14-22-14
    identical manner as any other legal contract; i.e., the primary goal in construing the
    terms of an easement is to ascertain and enforce the intent of the parties.”).
    {¶97} Decisively, the respondents argue that the agricultural easement
    restricts the construction of the pipeline project by means of the “[t]he prior public
    use doctrine.” (Appellee’s/Cross-Appellant’s Brief at 26). That is, the respondents
    advocate that the “doctrine prohibits the taking [of the respondents’ property]
    because of the prior public use in place under the Ag Easement to perpetually
    preserve agricultural lands through the preservation and protection of soils for the
    full range of agricultural activities available under law, as defined by R.C. §5713.30
    * * * .” (Id.).
    {¶98} Ohio’s prior public use doctrine provides
    that when a condemner, to which the power of eminent domain is
    given by law, seeks to exercise its power with respect to property
    already devoted to public use, its action may be enjoined if the
    proposed use will either destroy the existing use or interfere with it to
    such an extent as is tantamount to destruction, unless the law has
    authorized the acquisition either expressly or by necessary
    implication.
    Blue Ash v. Cincinnati, 
    173 Ohio St. 345
    , 351 (1962). See also Worthington v.
    Columbus, 
    100 Ohio St.3d 103
    , 
    2003-Ohio-5099
    , ¶ 19 (addressing “that the prior
    public use doctrine arose as the result of interpretation of statutes vesting
    municipalities and other public entities with the power of eminent domain”).
    Moreover, “[t]he manner in which the property was originally acquired has no
    -50-
    Case No. 14-22-13 and 14-22-14
    bearing upon the operation of the general rule.” Blue Ash at 351. “[D]efining the
    parameters of the power of eminent domain is a judicial function.” Worthington at
    ¶ 21.
    {¶99} The respondents argue that “[t]he preservation of farmland and
    agricultural soils is a public use” and that “the agricultural easement is a statement
    of a public use that existed prior to the attempt to appropriate the” protected property
    in this case. (Appellee’s/Cross-Appellant’s Brief at 26). By way of historical
    timeline, the respondents illustrate that the State of Ohio codified “the ‘Clean Ohio’
    amendment to the Ohio Constitution” in 2000 for the “‘conservation and
    preservation of * * * farmlands and other lands devoted to agriculture, including by
    acquiring land or interests therein * * * .” (Id. at 26-27, quoting Ohio Constitution,
    Article VIII, Section 2o(A)(1)).      Therefore, the respondents contend that the
    protected property is already devoted to public use under the agricultural easement.
    {¶100} In Ohio, “R.C. 5301.67 through R.C. 5301.70 govern the creation,
    ownership and enforcement of conservation” and agricultural easements. Lightle v.
    Washington Court House, 12th Dist. Fayette No. CA2006-08-033, 2007-Ohio-
    2069, ¶ 12. An
    “agricultural easement” means an incorporeal right or interest in land
    that is held for the public purpose of retaining the use of land
    predominantly in agriculture; that imposes any limitations on the use
    or development of the land that are appropriate at the time of creation
    of the easement to achieve that purpose; that is in the form of articles
    of dedication, easement, covenant, restriction, or condition; and that
    -51-
    Case No. 14-22-13 and 14-22-14
    includes appropriate provisions for the holder to enter the property
    subject to the easement at reasonable times to ensure compliance with
    its provisions.
    (Emphasis added.)      R.C. 5301.67(C).        R.C. 5713.30 defines land devoted
    exclusively to agricultural use. Generally, “land devoted exclusively to agricultural
    use” means devoting a minimum of ten acres of land for at least one of the purposes
    described in the statute for the three years prior to an application filed under R.C.
    5713.31. R.C. 5713.30(A)(1). An application filed under R.C. 5713.31 generally
    requests “the auditor to value the land for real property tax purposes at the current
    value such land has for agricultural use.” R.C. 5713.31(A).
    {¶101} R.C. 5301.68 permits “[a]n owner of land [to] grant an agricultural
    easement to the director of agriculture * * * .” Importantly, that landowner “may
    grant an agricultural easement only on land that is valued for purposes of real
    property taxation at its current value for agricultural use under section 5713.31 of
    the Revised Code or that constitutes a homestead when the easement is granted.”
    R.C. 5301.68. R.C. 901.21(B) authorizes the ODA to accept such agricultural
    easements. That statute provides, in its relevant part that
    [t]he director of agriculture may acquire real property used
    predominantly in agriculture and agricultural easements by gift,
    devise, or bequest if, at the time an easement is granted, such an
    easement is on land that is valued for purposes of real property
    taxation at its current value for agricultural use under section 5713.31
    of the Revised Code or that constitutes a homestead. Any terms may
    be included in an agricultural easement so acquired that are necessary
    or appropriate to preserve on behalf of the grantor of the easement the
    -52-
    Case No. 14-22-13 and 14-22-14
    favorable tax consequences of the gift, devise, or bequest under the
    “Internal Revenue Act of 1986,” 
    100 Stat. 2085
    , 26 U.S.C.A. 1, as
    amended.
    R.C. 901.21(B).
    {¶102} R.C. 5301.70 advises that “[c]onservation easements are not
    unenforceable for lack of privity of contract or estate or lack of benefit to a particular
    dominant estate.” Likewise, the statute directs that “[t]he terms of a conservation
    easement may be enforced by injunction or in any other civil action by the holder
    of the easement.” R.C. 5301.70. See Zagrans, 
    2009-Ohio-2942
    , at ¶ 9. Even
    though “conservation easement” and “agricultural easement” are independently
    defined under the Revised Code, such definitional distinction does not change the
    enforceability of the agricultural easement in this case.
    {¶103} Here, the respondents assert that the statutory definition of an
    agricultural easement necessitates judicial review of the prior public use doctrine in
    this case. That is, because the General Assembly defined an agricultural easement
    under R.C. 5301.67(C) to mean a right in land that is held for “the public purpose,”
    the respondents insist that they have invoked the prior public use doctrine since there
    is an agricultural easement encumbering the protected property. Columbia Gas
    opposes the respondents’ argument by advocating that “[a] ‘public use’ and a
    ‘public purpose’ are different things.” (Appellant’s/Cross-Appellee’s Reply Brief
    at 15). Columbia Gas’s argument is a distinction without a difference. Indeed, the
    -53-
    Case No. 14-22-13 and 14-22-14
    Supreme Court of Ohio uses the phrases synonymously when discussing the prior
    public use doctrine. See, e.g., Worthington, 
    100 Ohio St.3d 103
    , 
    2003-Ohio-5099
    ,
    at ¶ 23.
    {¶104} Our review of the record reflects that the respondents’ presented
    some competent, credible evidence that the protected property is encumbered by a
    prior public use. That is, the respondents presented evidence that the protected
    property is encumbered by an agricultural easement (as defined under R.C.
    5301.67(C)) granted in favor of the ODA. Specifically, Respondents’ Exhibit H
    reflects that the agricultural easement was filed on August 21, 2003, recorded in
    Volume 509 of the Official Records at Page 369, in the Union County, Ohio
    Recorder’s Office.
    {¶105} Nevertheless, Columbia Gas seeks to exercise its power as a public
    utility to appropriate the protected property.      The Supreme Court of Ohio
    unequivocally held that such “taking may be enjoined if it will result in the
    destruction of an existing public use.” Northwood v. Wood Cty. Regional Water &
    Sewer Dist., 
    86 Ohio St.3d 92
    , 95 (1999). That is, “[t]he Ohio Constitution does not
    expressly or by necessary implication authorize a city [or agency] to take property
    already used for public purposes in order to further a proprietary function * * * .”
    Worthington, 
    100 Ohio St.3d 103
    , 
    2003-Ohio-5009
    , at ¶ 23. Importantly, the
    Supreme Court of Ohio has not refined the prior public use doctrine to permit the
    -54-
    Case No. 14-22-13 and 14-22-14
    courts to balance the competing public uses to determine which necessity best serves
    the public interest. See id. at ¶ 27 (Pfeifer, J., dissenting). Accordingly, to overcome
    application of the prior public use doctrine, Columbia Gas must present evidence to
    contradict (evidence presented by the respondents) that the proposed pipeline
    project will destroy the existing public use of the protected property. Accord id.
    (holding that “Worthington did not contradict evidence proffered by Columbus that
    its proposed use of the subject property as a cemetery would destroy the existing
    public use of the land as an open-space park”).
    {¶106} Even though “there is abundant evidence in the record, we are loath
    to make a factual determination, especially in the first instance” since the trial court
    did not resolve this issue. Northwood at 95. Accordingly, we reverse the trial
    court’s determination that the agricultural “easement prevents eminent domain in
    this action” and remand the matters to the trial court to determine whether Columbia
    Gas’s proposed easement will destroy the existing public use of the protected
    property. (Case No. 21CV0112, Doc. No. 63); (Case No. 21CV0113, Doc. No. 58).;
    Northwood at 95 (“Accordingly, we reverse the judgment of the court of appeals
    and remand to the trial court to review the current record to determine whether the
    proposed taking will result in the destruction of the district.”). That is, we remand
    these cases to the trial court to determine whether Columbia Gas presented evidence
    contradicting the evidence presented by the respondents that Columbia Gas’s
    -55-
    Case No. 14-22-13 and 14-22-14
    proposed use will destroy the existing public use of the protected property. Based
    on the foregoing, the respondents’ first assignment of error is sustained.
    Columbia Gas’s Assignment of Error No. V
    The Trial Court erred by admitting into evidence at the Haring
    settlement discussions regarding the terms of the easements
    before the underlying appropriation cases were filed because such
    settlement discussions constitute compromise negotiations and
    are inadmissible under Rule 408 of the Ohio Rules of Evidence.
    Respondents’ Assignment of Error No. II
    The Trial Court erred by not allowing the testimony of
    Appellees/Cross Appellants/Respondents’’ expert witness,
    Patrick Hornschemeier.
    {¶107} Under its fifth assignment of error, Columbia Gas contends that the
    trial court abused its discretion by admitting Conklin’s testimony because it
    constituted compromise negotiations. Similarly, under their second assignment of
    error, the respondents argue that the trial court abused its discretion by excluding
    Hornschemeier’s testimony.
    Standard of Review
    {¶108} An appellate court reviews decisions involving the admissibility of
    evidence for an abuse of discretion. Estate of Johnson v. Randall Smith, Inc., 
    135 Ohio St.3d 440
    , 
    2013-Ohio-1507
    , ¶ 22. See also Akron Bar Assn. v. Shenise, 
    143 Ohio St.3d 134
    , 
    2015-Ohio-1548
    , ¶ 13 (“We review a decision on the admission or
    exclusion of expert witness testimony under an abuse-of-discretion standard.”). As
    -56-
    Case No. 14-22-13 and 14-22-14
    we previously stated, an abuse of discretion suggests the trial court’s decision is
    unreasonable, arbitrary, or unconscionable. Blakemore, 5 Ohio St.3d at 219.
    Analysis
    {¶109} We will begin by addressing Columbia Gas’s argument that the trial
    court abused its discretion by admitting Conklin’s testimony.          Specifically,
    Columbia Gas contends that Conklin’s testimony should have been excluded
    because “[c]ompromise negotiations between an appropriating entity and a
    landowner concerning land rights before an appropriation action is filed * * * are
    inadmissible as a matter of law pursuant to Evid.R. 408.” (Appellant’s/Cross-
    Appellee’s Brief at 22). Therefore, Columbia Gas asserts that the trial court abused
    its discretion by admitting Conklin’s testimony “regarding his pre-suit negotiations
    with Columbia Gas for the land rights sought by Columbia gas and Appellees’
    proposed revisions to the easements.” (Id.).
    Evid.R. 408 provides:
    Evidence of (1) furnishing or offering or promising to furnish, or (2)
    accepting or offering or promising to accept, a valuable consideration
    in compromising or attempting to compromise a claim which was
    disputed as to either validity or amount, is not admissible to prove
    liability for or invalidity of the claim or its amount. Evidence of
    conduct or statements made in compromise negotiations is likewise
    not admissible. This rule does not require the exclusion of any
    evidence otherwise discoverable merely because it is presented in the
    course of compromise negotiations. This rule also does not require
    exclusion when the evidence is offered for another purpose, such as
    proving bias or prejudice of a witness, negating a contention of undue
    -57-
    Case No. 14-22-13 and 14-22-14
    delay, or proving an effort to obstruct a criminal investigation or
    prosecution.
    See also Toledo v. Bernard Ross Family Ltd. Partnership, 
    165 Ohio App.3d 557
    ,
    
    2006-Ohio-117
    , ¶ 64 (6th Dist.) (“Evid.R. 408 prohibits introduction of evidence
    regarding settlement or compromise that is offered ‘to prove liability for or
    invalidity of the claim or its amount.’”), quoting Evid.R. 408.
    {¶110} “Evid.R. 408 does not prohibit all evidence concerning settlement
    negotiations, as such evidence may be admissible under the relevancy test of Evid.R.
    401, to show a witness is biased or to impeach a witness.” M.M. v. V.S., 6th Dist.
    Lucas No. L-21-1176, 
    2022-Ohio-1531
    , ¶ 28, citing Kane v. Inpatient Med.
    Services, Inc., 9th Dist. Summit No. 29087, 
    2019-Ohio-1975
    , ¶ 18. “Where a
    statement is not made in the context of an offer of compromise, however, it is not
    granted the protection of the exclusionary rule contained in Evid.R. 408.”
    USCA/USA, Inc. v. High Tech Packaging, Inc., 6th Dist. Wood No. WD-05-088,
    
    2006-Ohio-6195
    , ¶ 34. “In addition, Evid.R. 408 is applicable only to bar the
    admission of evidence which is offered to show ‘that because a settlement offer was
    made, the offeror must be liable, because people [do not] offer to pay for things for
    which they are not liable.’” 
    Id.,
     quoting Boyle v. Daimler Chrysler Corp., 2d Dist.
    Clark No. 2001-CA-81, 
    2002-Ohio-4199
    , ¶ 95. “In other words, Evid.R. 408 does
    not bar information from settlement negotiations when it is offered for another
    purpose and not to prove liability against one of the parties to the negotiations.” 
    Id.
    -58-
    Case No. 14-22-13 and 14-22-14
    {¶111} Here, the trial court did not abuse its discretion by admitting
    Conklin’s testimony regarding his pre-suit negotiations with Columbia Gas in this
    case. That is, the evidence was not offered for the purpose of establishing liability
    or the value of any claim. Rather, the respondents offered Conklin’s testimony to
    prove that the specific easement rights sought by Columbia Gas are not necessary.
    Consequently, Conklin’s testimony is outside the scope of Evid.R. 408. See High
    Tech Packaging at ¶ 35. Therefore, Columbia Gas’s fifth assignment of error is
    overruled.
    {¶112} Turning to the respondents’ second assignment of error, based on our
    conclusion as to the applicability of the prior public use doctrine, we conclude that
    the trial court abused its discretion by excluding Hornschemeier’s testimony.
    Indeed, under their second assignment of error, the respondents argue
    Hornschemeier’s testimony was admissible because he is “an expert in conservation
    easements, including agricultural easements” and he “would have testified and
    provided expert opinion on the significance of Federal tax law with regard to the
    agricultural easement.” (Appellee’s/Cross-Appellant’s Brief at 33). In other words,
    Hornschemeier would have testified to the intersection of ODA’s argument that the
    protected property will remain “predominately” for agricultural use against the
    federal tax code’s preservation requirements.
    -59-
    Case No. 14-22-13 and 14-22-14
    {¶113} For a witness to testify as an expert witness under Evid.R. 702, three
    conditions must be satisfied: (1) his or her testimony must “‘relate to matters
    beyond the knowledge or experience possessed by laypersons; (2) [the witness]
    must be qualified as an expert by specialized knowledge regarding the subject
    matter of the testimony; and, (3) [the] testimony must be based on reliable scientific,
    technical, or other specialized information.’” Levine v. Kellogg, 10th Dist. Franklin
    No. 18AP-694, 
    2020-Ohio-1246
    , ¶ 63, quoting Laketran Bd. of Trustees v. Mentor,
    11th Dist. Lake No. 2001-L-027, 
    2002-Ohio-3496
    , ¶ 54, citing Evid.R. 702.
    Typically, “[e]xpert testimony under Evid.R. 702 ‘is admissible in the form of an
    opinion to aid the court in arriving at a correct determination.’” 
    Id.,
     quoting Copper
    & Brass Sales, Inc. v. Plating Resources, Inc., 9th Dist. Summit No. 15563, 
    1992 WL 368497
    , *5 (Dec. 9, 1992). However, “[t]here is no requirement that an expert
    possess complete knowledge of the field in question but must possess enough
    knowledge that he or she will aid the trier of fact in performing its fact-finding
    function.” Id. at ¶ 52.
    {¶114} In response to the respondents’ argument, Columbia Gas asserts that
    the trial court did not abuse its discretion by excluding Hornschemeier’s testimony
    because his “proffered testimony * * * is irrelevant and would have constituted
    nothing more than an improper legal opinion and conclusion.” (Appellant’s/Cross-
    Appellee’s Reply Brief at 19). Generally, “‘[a]n expert witness is not permitted to
    -60-
    Case No. 14-22-13 and 14-22-14
    give an opinion relating to the law, and a trial court that allows such an opinion
    abuses its discretion.’” Hubbard v. Defiance, 3d Dist. Defiance No. 4-12-22, 2013-
    Ohio-2144, ¶ 27, quoting Witzmann v. Adam, 2d Dist. Montgomery No. 05-CV-
    4086, 
    2011-Ohio-379
    , ¶ 62. However, that rule applies to jury trials. See Wizmann
    at ¶ 62, citing Kraynak v. Youngstown City School Dist. Bd. of Edn., 
    118 Ohio St.3d 400
    , 
    2008-Ohio-2618
    , at ¶ 21 (providing that a trial court abuses its discretion when
    it allows an expert witness to interpret for the jury what a statute requires).
    {¶115} “[I]n the context of a bench trial, reviewing courts ‘afford broad
    leeway to the trial court in deciding the reliability of particular expert testimony’
    under Evid.R. 702.” Levine at ¶ 67, quoting Knott v. Revolution Software, Inc., 
    181 Ohio App.3d 519
    , 
    2009-Ohio-1191
    , ¶ 46 (5th Dist.). “Further, ‘“[w]hen a matter is
    tried before the court in a bench trial, there is a presumption that the trial judge
    ‘considered only the relevant, material, and competent evidence in arriving at its
    judgment unless it affirmatively appears to the contrary.’”’” 
    Id.,
     quoting In re Fair,
    11th Dist. Lake No. 2007-L-166, 
    2009-Ohio-683
    , ¶ 66, quoting Jackson v. Herron,
    11th Dist. Lake No. 2003-L-145, 
    2005-Ohio-4046
    , ¶ 28, quoting State v. White, 
    15 Ohio St.2d 146
    , 151 (1968).
    {¶116} Based on our conclusion that the prior public use doctrine applies to
    the facts and circumstances of this case (and our decision to remand the matter to
    the trial court to determine whether Columbia Gas’s proposed easement will destroy
    -61-
    Case No. 14-22-13 and 14-22-14
    the existing public use of the protected property), Hornschemeier’s testimony is
    relevant to whether Columbia Gas’s proposed easement will destroy the existing
    public use of the protected property. Specifically, Hornschemeier’s testimony is
    relevant to ensuring that the parties to the agricultural easement comply with the
    federal-tax requirements pertaining to the donation of an agricultural easement. His
    testimony is further relevant to the trial court’s consideration of whether Columbia
    Gas’s proposed easement will destroy the existing public use of the protected
    property.     Therefore, the trial court abused its discretion by excluding
    Hornschemeier’s testimony. Consequently, the respondents’ second assignment of
    error is sustained.
    {¶117} Having found no error prejudicial to the appellant/cross-appellee
    herein in the particulars assigned and argued in appellant/cross-appellee’s
    assignments of error, but having found error prejudicial to the appellees/cross-
    appellants herein in the particular assigned and argued in appellees/cross-appellants’
    assignments of error, we reverse the judgment of the trial court and remand for
    further proceedings consistent with this opinion.
    Judgment Affirmed in Part,
    Reversed in Part and
    Cause Remanded
    MILLER, P.J. and WILLAMOWSKI, J., concur.
    /jlr
    -62-